file: adv-pe-landmc 02 national energy board land...
TRANSCRIPT
![Page 1: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/1.jpg)
File: ADV-PE-LandMC 02
NATIONAL ENERGY BOARD
LAND MATTERS CONSULTATION INITIATIVE - STREAM 3
ENBRIDGE PIPELINES INC.
ABANDONMENT PHYSICAL PLANS
MAY 25, 2011
![Page 2: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/2.jpg)
INTRODUCTION
National Energy Board File: ADV-PE-LandMC 02
Enbridge Pipelines Inc. Abandonment Physical Plans
Page 2
1. In its RH-2-2008 Reasons for Decision dated May 26, 2009, the National Energy Board
("Board" or "NEB") set out a time line for the Land Matters Consultation Initiative ("LMCI")
Stream 3 process. An Action Plan was presented, which included deadlines for various
submissions. On March 7,2011, the NEB issued a letter stating that in order to allow additional
time for consultation, the deadline for Group 1 physical plans (not for approval) remains at May
31, 2011, but the deadline for the cost estimates and updates to physical plans has been changed
to November 30, 2011. This submission provides the physical plans for abandonment of
Enbridge Pipelines Inc. ("Enbridge").
2. The physical plans for abandonment that are discussed in this submission have been developed
for the purpose of creating preliminary estimates of abandonment costs. The methods of
abandonment that will ultimately be undertaken for any specific facilities or pipelines will be
determined at the time of the application to abandon. Enbridge is committed to basing any
decision that it will make regarding the actual method of abandonment - including with respect
to removal versus abandonment in place - on the most current sound scientific studies and
accepted industry practice.
ENBRIDGE PIPELINES
3. The Enbridge pipeline system and the Lakehead System in the United States ("U.S.") together
transport liquid petroleum eastbound for delivery primarily to markets in the U.S. Midwest and
in Ontario. Appendix A to this submission is a map illustrating the routes of the Enbridge
pipeline system and the Lakehead System.
4. The Enbridge pipeline system includes:
• Lines 1, 2, 3 and 4 (all originating in Edmonton, Alberta), Line 67 (Alberta Clipper,
originating in Hardisty, Alberta), and Line 65 (LSr Pipeline - Light Sour Capacity
Replacement, originating in Cromer, Manitoba). All of these lines extend to the
CanadalU.S. border near Gretna, Manitoba where they connect with the Lakehead
System.
![Page 3: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/3.jpg)
National Energy Board File: ADV-PE-LandMC 02
Enbridge Pipelines Inc. Page 3
• The Canadian sections of Line 5 and Line 6B extend from connections with the
Lakehead System on the CanadalU.S. border under the St. Clair River to Samia,
Ontario.
• Line 7 extends from Samia to Westover (Hamilton), Ontario where it connects with
Line 10 and Line 11. These two pipelines in tum extend from Westover to,
respectively, the CanadalU.S. border under the Niagara River near Chippawa, Ontario
and to Nanticoke, Ontario on the north shore of Lake Erie.
• Line 8 extends from Samia to Millgrove Junction in Hamilton, Ontario.
• Line 9 extends from Montreal, Quebec to Westover, Samia and Corunna, Ontario.
• The Shell lateral and Suncor lateral extend from takeoff points on Enbridge Lines 5,
6B and 9 to the associated refineries in Samia, Ontario.
5. In addition to its active pipelines, Enbridge has a number of deactivated lines, pipeline segments
and terminals, all of which are included in the overall scope of the physical plans for
abandonment that are reflected in this submission. These include the following:
• Line 7 - Westover Junction, Hamilton, Ontario to Bronte Junction, Oakville, Ontario
as per Board Order MO-II-2006;
• Line 8 - Millgrove Junction, Hamilton, Ontario to Bronte Junction, Oakville, Ontario
as per Board Order MO-Jl-24-95;
• Line 12 and Bronte Lateral- Bronte Terminal, Oakville, Ontario to Clarkson Terminal,
Oakville, Ontario as per Board Order MO-II-2006;
• Line 22 - Ninth Line Junction, Mississauga, Ontario to Clarkson Terminal, Oakville,
Ontario as per Board Order MO-II-2006; and
• 508 mm (20") mainline pipe lying between Clarkson Terminal, Oakville, Ontario and
Port Credit, Oakville, Ontario as per Board approval DI793-Jl-20.
A map which includes the locations of these deactivated facilities is attached as Appendix B to
this submission.
![Page 4: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/4.jpg)
PHYSICAL ABANDONMENT PLANS
National Energy Board File: ADV-PE-LandMC 02
Enbridge Pipelines Inc. Page 4
6. For the purposes of this submission, Enbridge has adopted the definition of "abandonment" that
appears in the Glossary of the NEB Discussion Paper for LMCI - Stream 3: "to permanently
cease operation such that the cessation results in the discontinuance of service".
Framework for Land Use Analysis
7. For purposes of its land use analysis, Enbridge utilized the three broad categories as reflected in
Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the recommended ten
sub-categories.
8. Enbridge retained Stantec Consulting Ltd. ("Stantec") to define the Board's categories and
classify the lands along the Enbridge pipelines according to these categories. These definitions
are provided below. A copy of the Stantec report entitled "Land Matters Consultation Initiative"
and dated April 29, 2011 ("Stantec Report") is included as Appendix C to this submission.
Agricultural
a. Cultivated - Canada Land Inventory ("CLI") 1-4 class soils (Agricultural
Interpretation).
b. Cultivated with Special Features Arable lands (CLI - 1-4 class soils) where the
depth of cover is less than 2 feet (0.6m).1
c. Non-cultivated - topsoil/sod production, native prairie, pastures and crops that
inhibit cultivation.
Non Agricultural
a. Existing Developed Lands urban and rural settlement areas within
municipalities (cities, towns, villages and hamlets) that are built up areas where
development is concentrated with a mix of land uses.
1 Enbridge has a Pipeline Depth Monitoring Program ("PDMP") in place for Lines 65 and 67 and is evaluating the potential for extending this program to others of its pipelines. The PDMP is a process designed to routinely test, evaluate, and where required, take appropriate action to ensure a standard minimum depth of cover is achieved. As a result, Enbridge does not anticipate any difficulties concerning pipeline depth of cover at the end of service life.
![Page 5: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/5.jpg)
National Energy Board File: ADV-PE-LandMC 02
Enbridge Pipelines Inc. Page 5
b. Prospective Future Development - undeveloped areas located in urban areas and
rural settlement areas within municipal boundaries.
c. No Future Development Anticipated - areas where potential for future
development is low (e.g. forest, landfills, mine sites, National and Provincial
Parks, conservation areas, areas with land use protection, as well as Crown lands,
etc.)
Other
a. Environmentally Sensitive Areas - areas that contain a natural feature which is
protected by government (federal or provincial) regulations. This land use can
include, but is not limited to: sandy soils (Alberta), wetlands, valley/coulee
breaks, significant woodlands, endangered wildlife habitat, and areas with
permafrost.
b. Roads and Railway Crossings - a system consisting of corridors and rights of way
for the movement of people and goods, and associated transportation facilities
including transit stops and stations, cycle lanes, bus lanes, high occupancy vehicle
lanes, rail facilities, park 'n' ride lots, service centers, rest stops, vehicle
inspection stations, inter-modal terminals, harbours, and associated facilities such
as storage and maintenance.
c. Water Crossings - watercourses, rivers, streams, and small inland lakes or water
bodies that have a measurable or predictable response to a single runoff event.
d. Other Crossings (Utilities) - sewage and water systems, septic treatment systems,
waste management systems, electric power generation and transmission,
communications/telecommunications, transit and transportation corridors and
facilities, oil and gas pipeline and associated facilities.
9. To locate the applicable land use areas, Stantec used a Geographic Information System model
populated with numerous data sources from each of the provinces. The Enbridge right of way
![Page 6: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/6.jpg)
National Energy Board File: ADV-PE-LandMC 02
Enbridge Pipelines Inc. Page 6
was then overlaid on the resulting output to categorize the Enbridge pipeline facilities according
to land use.
10. As quality varied among the data sources, an eight level hierarchy was developed to utilize the
data in order of accuracy. Higher accuracy data was utilized first and lower accuracy data was
relied upon only after the higher accuracy data was exhausted. Details are provided in Section
2.2 of the Stantec Report.
11. In instances where the data provided was a line or a point feature without any defined spatial
boundaries (e.g. roads, bridges, minor stream, etc.), Stantec developed standard widths to convert
the point and line data to areas with defined boundaries ..
12. For purposes of this submission, Enbridge has also adopted the pipeline abandonment methods
outlined in the Canadian Energy Pipeline Association ("CEP A") document entitled "Technical
and Environmental Considerations for Development of Pipeline Abandonment Strategies,
September 2006 - April 2007" ("CEP A 2006 Report"). A copy of the CEP A 2006 Report is
included as Appendix D to this submission. Table 1 below outlines the abandonment methods -
categorized according to facility size, type (i.e. pipeline versus above grade) and land use - that
Enbridge has assumed for purposes of determining the method of abandonment for the purposes
of cost estimation.
13. Table 1 reflects the adoption by Enbridge of the Pipeline Abandonment Matrix that appears as
Table 1 (at page 10) in the CEPA 2006 Report as well as the view that, in general, and absent
reasons to suggest otherwise, abandonment in place is the preferable method.
14. The assumptions reflected in Table 1 differ from those in Table A-2 of Appendix A to the
Board's March 4, 2010 letter in that no removal of pipeline facilities is contemplated in respect of
the Cultivated, Non Cultivated and No Future Development Anticipated land use categories.
Determinations regarding removal versus abandonment in place of each pipeline facility will be
made by Enbridge before it seeks abandonment approval from the Board, and on the basis of
sound scientific study and accepted industry practice.
![Page 7: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/7.jpg)
National Energy Board File: ADV-PE-LandMC 02
Enhridge Pipelines Inc. Page 7
Table 1: Physical Assumptions by Land Use and Facility For the Purpose of Estimating Preliminary Cost Estimates
Land Use Agricultural Cultivated
Cultivated with Special Features (depth of cover issues)
Non Cultivated Non Existing Developed Lands
Agricultural Prospective Future Development No Future Development Anticipated
Other Environmentally Sensitive Areas
Roads and Railways Water Crossings Other Crossings (Utilities)
Legend: A = Abandon in Place A + = Abandon in Place with Special Treatment R = Removal
Physical Assumptions by Land Use and Facility
Pi )eline Diameter 2" to 12" 14" to 24" >26" Above 60.3 to 355.6 to 610 >660 Grade
323.9 mm mm mm Facilities A A A R
R R R R A A A R A A A R R R R R A A A R A A A R
A+ A+ A+ R A A A R A A+ A+ R
15. Table 2a below categorizes the Enbridge pipeline facilities that are subject to NEB jurisdiction
according to the diameter categories specified in Table A-I of Appendix A to the Board's March
4,2010 letter.
Table 2a: Pipe Diameter Categorization
2" to 12" (Small) 14" to 24" (Medium) >26" (Large) 60.3 to 323.9 mm 355.6 to 610 mm >660mm
Line 10* Lines 1,2, 7, 8, 9**, 10*, 11, Lines 3, 4, 5, 6B, 9**, 67, 12,22,65, Suncor Lateral, Shell Lateral
Clarkson to Port Credit deactivated pipeline
.. *Note: Lme 10 IS dIvIded between the "small" and "medmm" categones as follows: (34 km of 12" and 73 km of 20") **Note: Line 9 is divided between the "medium" and "large" categories as follows: (9 km of20" and 832 km of30")
![Page 8: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/8.jpg)
National Energy Board File: ADV-PE-LandMC 02
Enbridge Pipelines Inc. Page 8
16. Table 2b below categorizes the Enbridge pipeline facilities (expressed in kilometres of pipeline)
that are subject to NEB jurisdiction according to the land use categories specified in Table A-I of
Appendix A to the Board's March 4,2010 letter.
Table 2b: Physical Assumptions by Land Use and Facility For the Purpose of Estimating Preliminary Cost Estimates (Expressed in Kilometres of Pipeline)2
Pipeline Diameter
2" to 12" 14" to 24" >26" Land Use 60.3 to 323.9 mm 355.6 to 610 mm >660mm
Line 10* Lines 1,2,7,8,9**, 10*, 11, Lines 3, 4, 5, 12,22,65, Suncor Lateral, 6B, 9**, 67,
Clarkson to Port Credit Shell Lateral deactivated pipeline Total
Agricultural Cultivated 3 2246.4 2805.4 5054.8 Cultivated with Special Features (depth of cover issues) 0 0 0 0
Non Cultivated 0 142.7 236.1 378.8 Non Existing Developed Lands 0 53.2 44.5 97.7
Agricultural Prospective Future Development 0 14.5 31.7 46.2 No Future Development Anticipated 0 4.4 5.4 9.8
Other Environmentally Sensitive Areas 29.8 603 794.3 1427.1
Roads and Railways 0.3 144.3 167.6 312.2
Water Crossings 0.4 69.7 101.8 171.9
Other Crossings (Utilities) 0 153.7 225 378.7
Total 7877.2
2 As at April 29, 2011.
![Page 9: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/9.jpg)
National Energy Board File: ADV-PE-LandMC 02
Enbridge Pipelines Inc. Page 9
17. Table 2c below categorizes the Enbridge pipeline facilities (expressed in kilometres of pipeline)
that are subject to NEB jurisdiction according to the abandonment method specified in the CEP A
2006 Report. The results of this analysis, expressed as percentages of total pipeline length, are
as follows:
• 90.6% - abandonment in place;
• 8.8% - abandonment in place with special treatment; and
• 0.6% - removaL
Table 2c: Physical Assumptions by Land Use and Facility For the Purpose of Estimating Preliminary Cost Estimates (Expressed in Kilometres ofPipeline)3
Pipeline Diameter
2" to 12" 60.3 to 323.9 14" to 24" >26"
. Land Use mm 355.6 to 610 mm > 660 mm
Line 10* Lines 1,2, 7, 8, Lines 3, 4, 9**,10*, 11, 12, 5,6B, 22,65, Suncor 9**,67,
Lateral, Clarkson to Shell Port Credit Lateral deactivated
pipeline Total
A Abandon in Place 33.2 3119.4 3987.5 7140.1
A+ Abandon in Place with Special Treatment 0.3 298 392.6 690.9
R Removal 0 14.5 31.7 46.2
Total 7877.2
18. Finally, regarding above grade facilities, Enbridge has assumed that the facilities described in
Table 3 below will be removed.
3 As at April 29, 2011.
![Page 10: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/10.jpg)
Table 3: Facility Removal Categorization4
Above Grade Facility Basis for Sco~e Terminals Meter Manifold Typical meter manifold used
as basis: 3 - 10" (254 mm) meter complete skid, 40m piping, prover, 50m delivery recycle line, instrument building, 4 way valve, static mIxer
Terminals Valve Manifold Typical valve manifold used as basis: 2 - 36" (914 mm) tank lines, 4 - 24" (610 mm) connection valve headers
Terminals Electrical Building The count represents the electrical buildings at Terminal locations as one electrical building is already included as part of each pump station.
Terminals Maintenance Physical count of each Building building
Terminals Above Grade Total volume of installed Storage Tank tankage
Terminals Booster Pump Total horsepower of installed Station pumps
Terminals Below Grade Sump The count represents the Tank sump tanks at Terminal
locations as one sump tank is already included as part of each pump station.
Pipeline Mainline Valve Physical count of each valve
(Remote Control) Pipeline Mainline Valve Physical count of each valve
(Manual Control) Pipeline Mainline Physical count of each
Instrumentation building Building
Pipeline Pig Trap Assembly Physical count of each trag Station Pump Station Total horsepower of installed
pumps
4 As at April 29, 2011.
National Energy Board File: ADV-PE-LandMC 02
Enbridge Pipelines Inc. Abandonment Physical Plans
Page 10
QuantliY/ Measure 63
100
58
102
15.418 million bbl
53,560 hp
29
129
255
42
119 1.164 million hp
![Page 11: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/11.jpg)
CONCLUSION
National Energy Board File: ADV-PE-LandMC 02
Enbridge Pipelines Inc. Page 11
19. Enbridge will file the required cost estimates on or before November 30, 2011. Should updates
of physical abandonment plans be required, they will be included in that filing.
![Page 12: File: ADV-PE-LandMC 02 NATIONAL ENERGY BOARD LAND …ceaa-acee.gc.ca/050/documents_staticpost/cearref...Table A-2 of Appendix A to the Board's March 4, 2010 letter, as well as the](https://reader034.vdocuments.mx/reader034/viewer/2022043008/5f9966abaa42c65ef4187ca9/html5/thumbnails/12.jpg)