field validation of cementing solutions for wells … no. 06.pdf · design slurry with adequate...
TRANSCRIPT
FIELD VALIDATION OF CEMENTING SOLUTIONS FOR WELLS
WITH LOW BOTTOM HOLE TEMPERATURES S. Banerjee, K.M. Suyan, R.K. Meher and D. Dasgupta
Institute of Drilling Technology, ONGC, Dehradun – 248195 Email : [email protected]
ABSTRACT Cement slurry designing using conventional cement additives for primary casing cementation of
wells with low / moderately low BHCT (40 – 70 Deg. C) is an industry challenge. Cement slurries
for field implementation needs to possess adequate placement time, minimum fluid loss, good
rheological behaviour, minimum free water separation, short transition time, good stability and
early strength development capability under operational conditions. However, even with all the
recent advancements in cementing technology, till today simultaneously meeting all of above
requirements is extremely difficult for slurries designed with conventional cement additives.
In this study extensive investigations have been carried out to formulate suitable cement slurry
systems for low BHCT wells where all cement slurry parameters could be controlled
simultaneously. Studies have culminated in the development of novel slurry systems by
incorporating pozzolan spheres giving total control over all crucial slurry parameters which could
not be done earlier. The performance of developed designs have been elucidated and validated by
successful field implementation in an onshore field of ONGC. Case studies along with conclusions
and recommendations derived from this endeavor are presented in this paper.
KEYWORDS Low BHCT, Control Slurry Parameters, Pozzolan, Fluid loss control
INTRODUCTION
Bottom hole circulating temperature (BHCT) in the range 40 – 70 Deg C is encountered by almost
all operators across the globe quite frequently while drilling of oil and gas wells. Temperature in
this range is experienced mostly in shallow wells or in wells located in mature / depleted
reservoirs. However even today, cement slurry designing for casing cementation of wells with low
/ moderately low (40 – 70 Deg C) bottom hole circulating temperature is a challenging issue. The
situation becomes critical when the bottom hole temperature is lower than 50 Deg C.
Ideally designed cement slurries needs to be of desired density and should possess adequate
thickening time under field temperature and pressure conditions to provide sufficient operational
time to carry out cementation job. In addition the slurries used for production casing cementation
should have minimum free water separation, should be stable (no settling tendency) under
operational conditions, should possess minimum fluid loss and short transition time with right
angle set characteristics. For operational requirement they should also exhibit good rheological
1
behaviour. The good rheological properties facilitate efficient placement and effective mud
removal during cementation. The designed cement slurries should also have early strength
development characteristics and sufficient compressive strength development to meet mandatory
requirements within least waiting time. Additionally the designed cement slurry should be gas tight
for inhibiting gas migration / inter zonal communication and very low set cement permeability when
used against gas zone and should be financially attractive, eco-friendly and non-hazardous.
However, even with all the recent advancements in cementing technology, till today meeting all of
above requirements simultaneously is extremely difficult and a practical approach, with the least
acceptable variance from ideality, is adopted without compromising on crucial parameters.
In many onshore fields of ONGC, wells are being drilled where the BHCT is in the range of 40 – 70
Deg C. With the existing facilities and with available conventional cement additives, problems are
being experienced in these fields for designing suitable cement slurries for casing cementation
without compromising in one or more of crucial parameters (eg. fluid loss / rheology / thickening
time / compressive strength).
While cement compositions have been developed and are in use for casing cementation of wells
with low BHCT, the intricacies on satisfactory slurry designing for such wells is limited.
Thus, there is a pressing requirement for finding a feasible solution to this perennial problem and
have been consequently been investigated at the Institute of Drilling Technology (IDT) in ONGC.
This paper presents the laboratory data showing unique feature of the developed formulations
along with several recent field case histories demonstrating the effectiveness and advantages.
PROBLEMS THAT LEADS TO THE DEVELOPMENT
Many wells with low / moderate BHCT are presently being drilled in several onshore fields of
ONGC. However in many of such wells poor cementation have been observed possibly due to
job execution with cement slurries unsuitable for the purpose. The reason for implementation of
such cement slurries is the limitations in available technology.
A review of casing cementation details of some typical low BHCT wells in the onshore fields of
ONGC it is observed that the field implemented slurries are not adequately designed (Table– 1).
At least one parameter among thickening time / fluid loss / rheology is substantially above the
desired level. This is possibly one of the major factors which is responsible for poor casing
cementation and associated problems. The problem deserves immediate attention
In the effort to resolve the issue, the first attempt in designing such a cement slurry system for low
BHCT wells is naturally oriented towards a recipe containing a blend of conventional dispersant /
fluid loss control additive / accelerator.
2
Thickening time of cement slurry should be sufficient to enable an operator to safely place the
slurry to the predetermined depth. However, unnecessarily long thickening time should be avoided
as excessive thickening time resulted in annular rings against permeable zones to cause gas
migration, causes water pockets and severely affect the quality of cementation. In the results
presented in Table–1 it is observed that at moderately low BHCT of 60 Deg C, conventional
formulation with only fluid loss control additive & dispersant does not set upto 350 minutes. Hence
there is requirement of addition of a set accelerating additive. Calcium Chloride is mostly used in
the industry as set accelerator and has been used for this study. From the Table-2, it is observed
that addition of CaCl2 for cement slurry formulation had profound undesirable effects (increase in
fluid loss and poor rheology). The minimum dosage requirement of CaCl2 is 1.5% BWOC in
combination with additional fluid loss control agent & dispersants to attain the desired thickening
time of around 200 mins at this temperature. At these dosage the rheology of the cement slurry is
very poor (Vc = 12.2ft / sec in 3“ equivalent annular diameter) and it is very difficult to attain
turbulent flow regime with such poor rheology. With higher dosage of CaCl2 (eg. 2.0 % BWOC)
though the thickening time achieved near the desired value but both the rheology and the fluid loss
increases beyond control / acceptable limits. Therefore, while designing cement slurries at low /
moderately low BHCT by addition of set accelerator, it was essential to add high dosage of fluid
loss control additive to counter the effects of increase in fluid loss of the cement formulation.
However addition of high dosage of fluid loss control additive also again resulted in increase of
both the thickening time and rheology. Since the effect of set accelerator and fluid loss control
additive on thickening time and fluid loss control is diagonally opposite, it was nearly impossible to
design slurry with adequate parameters for production casing cementation at low / moderately low
BHCT using both the additives simultaneously.
Poor rheology results in poor cementation, as rheology of cement slurry governs mud
displacement in the annulus. Similarly, if fluid loss is not controlled it can cause premature
dehydration of slurry which can lead to annulus plugging resulting in incomplete displacement or to
a lesser extent change in slurry rheology and consequent decrease in mud removal efficiency. All
this thing have serious consequences and may ultimately lead to cement job failure or poor
cementation job. Therefore, to bring all these parameters under control simultaneously, a simple
but different approach is obviously required.
TURNAROUND INVESTIGATIONS
On the basis of experiments detailed above it is well realized that by following conventional
methodologies it may not be possible to design a cement slurry system where there will be total
control over all the crucial slurry parameters.
It is also realized that to meet the technical requirements, it is necessary to incorporate a suitable
material in the slurry design which will have profound influence on the control of all these crucial
3
parameters. Furthermore the selected material should have high pozzolanic reactivity so as to
able to participate in the chemical reactions towards reduction of thickening time at low bottom
hole temperature. The selected material also should be compatible with other conventional cement
additives, be low cost, non-hazardous and eco-friendly.
From previous experience of this laboratory in designing high performance slurries1, it is
understood that if a sub micron size particle is chosen it can fill up the void space between the
solid cement particles and thereby enhance mixability at reduced water and in the process lead to
reduction in fluid loss of the designed slurry.
Amorphous silicon based artificial pozzolanic material though have been used in slurry design for
cementation of wells for various purposes but its use for slurry designing for low BHCT wells is not
a established practice2. But considering the advantages of high reactivity of amorphous silicon
based artificial pozzolanic material and its fine particle size3, it was realized that incorporating this
material in slurry designing for low BHCT wells may provide a simple but effective solutions for this
problem.
Inspired by this concept, cement slurry designing for low BHCT wells incorporating artificial
pozzolanic silicon based material is viewed as an alternate for the total control of crucial parameter
of the cement slurry required for obtaining good zonal isolation.
Under the present study slurries have been developed using class G oil well cement and
conventional cement additives in conjunction with amorphous silica based pozzolanic material
where all crucial slurry parameters could be brought under control simultaneously (Table 3).
UNIQUE FEATURES OF SMART CEMENTING SOLUTIONS The developed slurries inspite of being designed with conventional additives had desired
thickening time (which can be adjusted to any predetermined time), low fluid loss, excellent
rheology, early compressive strength characteristics, zero free water and high stability (Table- 3)
as compared to conventional presently field implemented slurries (Table -1). These slurries were
also gas tight and exhibited very short transition time with near right-angle setting (Figure -1).
Obtaining all of the above mentioned parameter in the same manner was not possible through
earlier industry practices.
FIELD IMPLEMENTATION - CASE HISTORIES In early 2006 production casing cementation had been successfully performed as field trial of the
developed cement slurries in two development wells having low BHCT in onshore Cauvery basin
of ONGC. Later two other production casing cementations have also been successfully performed
in the same basin using the slurry formulation developed at IDT.
4
CASE HISTORY - 1
The initial field trials were executed in Well # KPDK and Well # VJDA for 5-1/2” casing
cementation. The details are given in Tables 4 & 5.
In both the wells KPDK and VJDA the actual cementing operations were performed as per industry
best practices. Wells were conditioned prior to cementation, IDT designed slurry was batch mixed
and casing reciprocated. Preflush (SAPP / Water) and spacer (Ultraflush-II) were used on
requirement. During operations turbulent flow could also be attained as the slurry had good
rheology and mud removal was efficient. Enhanced slurry properties coupled with concerted
efforts resulted in perfect cementation as evident from excellent CBL / VDL for both the wells
(Figure 2 & 3)
In the Well # VJDA, object-1 has produced gas 210000 M³ / day & condensate 50 M³ / day through
12 mm bean during production testing. In the Well # KPDK, Object- 1 during testing has produced
15000 cu.m gas /day and 50 cu.m oil with no water cut through 6mm bean at FTHP 950 psi and
CHP 1600 psi.
CASE HISTORY - 2
After successful initial field trials, the next field trial was carried out in an exploratory Well TVAT
(Tables 4 & 5) for 5-1/2 inch production casing cementation. The well details are given below.
Well name : TVAT, Depth : 3088m, Float collar : 3075m
Casing size : 5.5”, Bit size : 8.5”, Cement rise : 3088m-2500m
Zone of interest Obj-1: 3065-61m, 3037-34m, 3029-26m, 3022-20m, 3018-16m, 2991-89m, 2973-
70m, 2944-40m, and 2896-2894m; Obj-2: 2759-55m and 2735-32m
Max recoded temperature 241º F aT 3088 M; The average hole size was 9.5inch in this well.
Slurry was designed at 65º C BHCT using 10 % Pozzolan , 0.4% FLA and 0. 6% Dispersant. TT
was 190min and API Fluid loss was 180ml.
Execution
The job was carried out by pumping 8M³ water as pre-flush followed by 17 M ³ smart solutions
slurry of 1.90 gm/cc and displaced with 37.2 M ³ mud of 1.30gm/cc . Bumped plug at 1200psi and
raised to 1700psi. Job was normal and the CBL-VDL recorded at 700psi is found excellent
throughout the cemented interval (Figure 5).
CASE HISTORY- 3
The fourth successful field trial was carried out in exploratory Well # UGAB in the same onshore
basin (Tables 4 & 5). The well was having drilled depth of 3005m but the 7inch casing was short
landed at 2075m by placing a cement plug at 2200m. Here cement rise was planned 1700m from
surface. A SAPP solution was pumped as preflush and which was followed by cement slurry of
1.88 sg. The cement bond log shows excellent cement bondage.
5
VALIDATION THROUGH FIELD IMPLEMENTATIONS In the year 2005-06, remedial jobs had to be performed in at least 6 Nos. of low BHCT wells in this
onshore field alone. Implementations of the smart cementing solutions presented in this paper
have solved the field problems of poor cementation in such wells. To establish the effectiveness of
smart cementing solutions, the results of cement job evaluation for four representative wells drilled
in the same area (Well # KMP # 36, KMP # 37, KMP # 40 and KP# 42) are compared (Table – 6 &
Figure 4). It can be seen from the CBL/VDL of these wells that much improved bondage has been
achieved in well KP#42 where cementation was performed adopting the smart cementing solutions
in comparison to the other wells cemented with conventional slurry. The cementation problems
faced in earlier wells have been completely eliminated by the implementation of smart cementing
solutions in Well KP # 42 resulting in no need for any remedial cementation job. The
implementation of this innovation has resulted in saving on OPEX, as expensive rigdays were not
required for any unproductive downtime. Thus this innovation has served dual punch of technology
upgradation as well as cost savings.
CONCLUSIONS
¬ Conventional cement slurry is not ideal for production casing cementation of wells with low /
moderately low BHCT (40 – 70 Deg C). In such formulations, Calcium Chloride is often used
as set accelerator. It adversely affects cement slurry properties. The present practice is to
compromise on any one parameter due to technical reasons.
¬ Cement slurry design for low / moderately low BHCT wells may be done with an alternate
approach of incorporating a suitable material in the slurry design which should have high
pozzolanic reactivity and small particle size to fill up the void space between the solid cement
particles for exhibiting easy mixability at reduced water.
¬ Amorphous silica based pozzolon material has been successfully used for cement slurry
design for low / moderately low BHCT wells. It has shown excellent results with simultaneous
total control of all crucial parameters such that cement slurry can now be designed for any
specific requirement within this range which was earlier nor possible.
¬ Use of amorphous silica based pozzolan material in cement slurry design helps in early
compressive strength development and results in reduction of WOC period leading to cost
savings.
¬ Comparison of properties of presently used cement slurry designs being implemented in fields
with formulated cement slurries under this study clearly show that the formulated cement
slurries are superior than presently used cement slurry on all crucial parameters.
ACKNOWLEDGMENTS
6
Authors are highly thankful to Sri V. K. Jain, GGM (D), Head-IDT for his inspiration & valuable
guidance during this study and the management of Oil & Natural Gas Corporation Limited for the
permission to present this paper. Thanks are also given to all associated with the Cementation
and Cementing Material Laboratory of IDT, ONGC for their help and co-operation rendeded for this
Project.
REFERENCES 1. Dasgupta, D, et all,: “Lightweight slurries - A success story of application in low fracture
gradient and depleted fields for improved cementation”, SPE paper 101810 presented at the
2006 SPE/IADC Indian Drilling Technology Conference and Exhibition held in Mumbai, India,
16–18 October 2006.
2. Nelson, Erik B,: “Well Cementing”, Edited by., Elsevier Science Publisher B.V., The
Netherlands.
3. Ghosh, S.N.: Cement and Concrete Science & Technology”, Volume I, Part I, ABI Books
Private Limited, New Delhi - 110019 (1991) 361.
7
TABLES: Table 1: Table 2: Typical field conditions and slurry Parameters with Calcium Chloride Acclerator Parameters of field implemented Slurry (Sg. 1.90, BHCT 60 Deg C)
conventional slurries
*Critical Velocity Vc, through 3” equiv. annular dia
Composition
C W FLA Disp-ersant CaCl2
TT (mins)
Fluid Loss (ml/30 min)
Vc * (ft/sec)
100 44 0.7 0.4 - Not Set
upto 350 min
- -
100 44 1.0 0.2 1.0 285 190 10.50
100 44 1.0 0.4 1.0 295 175 9.83
100 44 1.0 0.4 1.5 260 234 12.20
100 44 1.0 0.5 1.5 332 - -
100 44 1.0 0.4 2.0 230 290 14.3
WELL KKDB KADH KPDI VJDB
Slurry Density 1.90 1.90 1.90 1.90
BHCT, Deg. C 55 63 60 67
BHP, PSI 3500 4500 3400 4500
FLA % BWOC 0.2 0.3 0.3 0.4
Dispersant % BWOC 0.1 0.3 0.2 0.3
Thickening Time (mins) )
at BHCT
205
215
215
250
Fluid Loss (ml/30 mins)
at BHCT
1379
1583
1050
1279
Rheology at BHCT
Vc (ft/sec)*
10.55
9.48
8.78
8.33
*Critical Velocity Vc, through 3” equiv. annular dia
Table 3 : Performance of smart cementing solutions slurries
Table 4 : Wells Parameters for Development Wells # KPDK, # VJDA
and Exploratory Well # TVAT and # UGAB
KPDK (KP # 42)
VJDA (VJ # 27)
TVAT UGAB
BHCT, Deg. C
60 63 65 60
BHST, Deg. C
90 101 107 90
BHP, psi
3500
4100 4000 3500
Depth (m)
1950
2690 3088 3005
Mud Sp.Gr.
1.22
1.23 1.30 1.24
Slurry Sp. Gr. (planned)
1.90 1.90 1.90 1.90
Sl. No Particulars Bottom hole conditions
1 BHCT (Deg. C) 55 60 63 67
2 BHST (Deg. C) 90 94 101 107
COMPOSITION
3 Cement 100 100 100 100
4 Water % BWOC
46 46 46 46
5 Pozzolan% BWOC
10 10 10 8
6 FLA % BWOC
0.4 0.4 0.4 0.5
7 Dispersant % BWOC
0.6 0.6 0.6 0.6
SLURRY PARAMETERS
8 Thickening Time (mins)
237 215 207 191
9
Fluid Loss (ml/30 mins) at BHCT
221 223 225 123
10 Free Water (ml) at BHCT
Nil Nil Nil Nil
11 Rheology at BHCT, PV
56 54 60 73
Rheology at BHCT, Yp
10 10 10 7
Rheology at BHCT, Vc (ft/sec) *
4.98 4.14 4.84 5.48
12 Stability Stable Stable Stable Stable 13 Comp. Strength (psi) at BHST / 3000 psi 8 Hrs 1250 - - - 24 hrs 3640 3710 4300 3850 96 hrs 5300 - 4900 4000
*Critical Velocity Vc, through 3” equiv. annular dia
9
Table 5: Slurry Composition & Parameters for Wells # KPDK, # VJDA, # TVAT and # UGAB Table 6: Comparison of Casing Cementation
results between Well KP # 42 (smart solutions) and KMP # 40
Targeted Values KPDK VJDA TVAT UGAB
COMPOSITION Cement - 100 100 100 100 Water % BWOC - 46 46 46 46
Pozzalan % BWOC - 8 8 10 10
FLA % BWOC - 0.5 0.4 0.4 0.4
Dispersant % BWOC - 0.6 0.6 0.6 0.6
SLURRY PARAMETERS Thickening Time (mins)
200 239 227 190 210
Fluid Loss (ml/30 mins) at BHCT
200 158 223 180 238
Rheology at BHCT, Vc ft/sec
6.0 6.9 6.4 6.7 6.5
Free Water (ml) at BHCT
Nil Nil Nil Nil Nil
Stability Stable Stable Stable Stable Stable Comp. Strength (psi) at BHST / 3000 psi
2000 Plus 3140 3230 3340 3175
Well Parameters
Well No. KP # 42 (KPDK) KMP # 40
Category Development Development
Depth (m) 1950 2500
Slurry Sp. Gr. 1.90 1.90 BHCT, Deg. C 60 67
Thickening Time (min) 228 242
Fluid Loss (ml/30 mins) 144 808
Remedial Jobs Nil Remedial operations (squeeze)
carried out against two
zones of interest
CBL / VDL Excellent (under 2 mV)
Moderate to Good
(Average near 20 mV all through)
FIGURES: Figure 1 : Consistency Plot Composition : C100 + Water - 46 + FLA – 0.4% + Dispersant – 0.6% + Pozzalan – 10% + TBP – 0.1%
10
Figure 2: Figure 3: Excellent CBL-VDL at well # KPDK (KP#42) CBL-VDL at well # VJDA excellent against throughout the entire cemented interval all the three objects
Figure 4: Comparison of CBL-VDL of well KP#42 completed with smart cementing solutions with that of completed wells with conventional Figure 5: slurry in the same field Excellent CBL-VDL at well # TVAT
11
KMP#36 KMP#37 KMP#40 KP#42
12