fhwa ndor phase v case study june 2, 2015 prepared by: michael hughes & debra drecksel
TRANSCRIPT
FHWA NDOR Phase V Case Study
JUNE 2, 2015
Prepared by:
Michael Hughes & Debra Drecksel
The case study will include:
• Project background & history
• Strategies that were applied during the Environmental Conflict Resolution (ECR) process
• Challenges encountered during the ECR process
• What worked well and what did not work well during the ECR process
• Recommendations and best practices that resulted from the ECR process
Phase V - Overview
• Between 2008 and 2014 – concerns in Nebraska regarding environmental analysis and documentation requirements to satisfy federal NEPA requirements for federally aided state or local projects
• FHWA’s Office of Planning, Environment, and Realty (HEP) and the FHWA Resource Center’s technical services team (RC) investigate the concerns
• As part of the resolution process, HEP asked the Udall Foundation’s US Institute for Environmental Conflict Resolution to provide neutral third-party services for a Joint Project Delivery Action Plan
Background and History
- Strengthen the partnership and improve the relationship between FHWA Division and NDOR
- Develop a sustainable approach to project delivery in Nebraska that:- Ensures Federal-aid projects in Nebraska are delivered
in compliance with all applicable Federal laws and regulations;
- Reduces the duration of the NEPA decision-making set of activities within the project delivery work flow, and
- Reduces the project delivery time for projects requiring Categorical Exclusions (CEs) and Environmental Assessments (EAs)
The Objective of the Action Plan
FHWA DIVISION
FHWA DIVISIONDIVISION ADMINISTRATORASSISTANT DIVISION ADMINISTRATORPROGRAM DELIVERY TEAM LEADENGINEERING/OPS TEAM LEADENVIRONMENTAL SPECIALISTPLANNING, ROW & CIVIL RIGHTS SPECIALIST
STATE DOT ADVISORSOHIOMARYLAND
RESOURCE CENTER
NDOR
DIRECTORDEPUTY DIRECTORPROJECT DEVELOPMENT MANAGERENVIRONMENTAL SECTION MANAGERENVIRONMENTAL PROGRAM MANAGERPROGRAM MANAGEMENT ENGINEERLOCAL PROJECTS ENGINEERROADWAY DESIGN ENGINEER
FHWA HEADQUARTERS
The Udall Foundation’s US Institute for Environmental Conflict Resolution and its contractor, Hughes Collaboration, served as the facilitation team that provided neutral third party support to this effort
Joint Project Delivery Efficiency Team
I. Situation Assessment Individual Interviews Assessment Report
II. Partnering Six Meetings Survey to Guide Phase III
III. Problem Solving Seven Meetings
IV. Lessons Learned Survey
V. Case Study Final Report
Five Phases
SITUATION ASSESSMENT
Substantive challenges• Complexity of project delivery• Development of a project delivery process
that is efficient, predictable, and accommodates the State’s letting schedule
• Number of projects• Complexity of laws, rules, and regulations• Retaining knowledge, skills, and experience of
staff (in both agencies and consultants)• Differences in policy, interpretation, and
implementation
SITUATION ASSESSMENT
Procedural challenges
• Timing and sequence• Documentation (format and content)• Staff turnover and tenure• Procedures that are adequately and
completely applied to each project
SITUATION ASSESSMENT
Relationship challenges
• Focusing on the past• Taking it personally• Questioning intent• Focusing on authority, power, and control• Spillover – to politicians, to higher agency
authority, etc. – in ways that deepen the divide• Thinking of this in epic terms – villain, victim,
hero – and talking about it that way inside your own team
• Maximize the value of the federal funds to the benefit of Nebraska• Efficiency and timeliness• Improve project delivery• Legal compliance• Consider impacts on the environment• Apply avoidance, impact minimization, or mitigation• Project delivery• Professional work products• No more paperwork or time than necessary to meet requirements• Respect, honesty and fairness• Follow-through and accountability• Consistency and predictability• True partnership
Common Interests
Substance• CE programmatic agreement progress• Three levels of CEs• Goal – NDOR making CE determinations for Levels 1 and 2 on
FHWA’s behalf• New guiding documents• CE form and instructions
Process and Relationship• Open dialogue• Working to produce products of mutual interest• Starting to see results• Positive outlook• Sense of teamwork
Phase II – Partnering – What Worked
Substance• CE programmatic agreement• Three levels/thresholds• Level 1 and 2 CE determinations made by NDOR on FHWA’s behalf• Smart form and instructions• Public involvement and EJ procedures• Section 4(f)• Section 106 guidance• Project efficiency improvements
Process and Relationship• Communication, • Confidence in the prospects for the future working relationship
between NDOR and FHWA• Potential to translate partnership to other agencies
Phase III - Problem Solving – What Worked
What Contributed To Success
• CE Agreement
• Between-Meeting Work
• State and Resources Center Advisors
• Agreement-Building Process
• Meeting Management
Lessons Learned Survey
What Inhibited Success
• Outside Workload
• Differing Interpretation of Law and
Regulation
• Resources
• Time
Lessons Learned Survey
What I Had to Do Differently
• Get past the history
• Don’t look back
• Move forward
• Allow the opportunity for people to change
• Listen
• Respect
• Appreciate all points of view
• Trust that we all will do what we say we will do
Lessons Learned Survey
Structure
Individual situation assessment interviews
Summary report and face-to-face meeting to confirm the assessment and launch the second phase
Divide the partnering phase and problem-solving phase
Evaluation at the end of each phase
Recommendations and Best Practices
Reflection and Evaluation
At the end of each phase the group had to assess their progress, evaluate the prior phase, and commit to embarking on the next phase
Regular leadership team calls
Individual check-in to evaluate
Continuous reflection and evaluation throughout the year-long process
Recommendations and Best Practices
Breaking with the Past• Look forward• Imagine that others can and will change• Create a future that is different from the past• Build a new way to do things
• New CE agreement• New way to process level-1 and level-2 projects• New tools for project review
• Use the opportunity to create a new, productive working relationship
Recommendations and Best Practices
Moving to Mutual Gain
Moving away from right or wrong
Meeting environmental compliance requirements and having NDOR make CE determination on FHWA’s behalf are complementary and simultaneous
Eliminating backward-looking discussion about who had been right and who had been wrong
Recommendations and Best Practices
Eliminating the Discord
Take an affirmative approach
Search for what will work in the future
Discord persists because we refuse to hear anything else
Listen only for the harmony
Recommendations and Best Practices
Outside Catalysts
State DOT advisors
FHWA resource center staff
Outside meeting management
Provided Reality checks Advice to try, test and rely on continuous improvement Simplified views of legal and regulatory requirements Freedom to focus on the project delivery improvements
instead of the partnering and problem-solving process
Recommendations and Best Practices
Move Quickly to Capture the Momentum
Set realistic timelines
Set measurable goals
Commit sufficient time, talent, and experience
Move quickly
Do things differently right now
Recommendations and Best Practices
Set measureable goals
Commit the necessary resources
Get outside assistance
Work to change fundamentally both project
delivery and the working relationship
Recommendation to Other States
True partnership requires looking forward, communicating carefully, and working to respect all points of view
True partners move away from who’s right and who’s wrong and focus on building something new that serves the needs of both
The NDOR-FHWA partnership produced mutual gain –making CE review simultaneously more compliant and more efficient
Agreements have to lock in – institutionalize the agreement through a set of implementing processes and procedures, forms, and instructions
It is possible to redraw responsibilities and change the way NEPA processes and project delivery are conducted in Nebraska
Conclusion