fault clearance for zhoushan hvdc system · 2018-07-12 · introduction 6 sgri -h-bridge cascaded...
TRANSCRIPT
FAULT CLEARANCE FOR ZHOUSHAN HVDC SYSTEM
Ting An (PhD CEng FIET)
国网智能电网研究院Smart Grid Research Institute, SGCC
2
FAULT CLEARANCE OPTIONS2
3 CASE STUDY
4 CONCLUSIONS
TABLE OF CONTENTS
INTRODUCTION1
INTRODUCTION
3
A DC network with a plurality of converters
Partially meshed Partially radial an overlaid network 5
6
DC Grid Definition
CIGRE B4.52 WG – HVDC Grid Feasibility StudyCIGRE B4.52 WG – HVDC Grid Feasibility Study
INTRODUCTION
4
INTRODUCTION
5
ABB - Hybrid DC Breaker *ABB - Hybrid DC Breaker *
* ABB published paper BOLOGNA 2011
INTRODUCTION
6
SGRI - H-bridge Cascaded DC CB *SGRI - H-bridge Cascaded DC CB *
Transfer Branch
Arrester Banks
Main Branch
UFD
Voltage 200kV Nominal current 1.2kAProspective fault rise 3.6kA/ms Nominal loss <0.01%Limited current 18kA Time to interrupt 3ms
Three branches - UFD, H-bridge modular & SAsBidirectional fault current limitation and interruption
UFD opens at current zero (2ms)Low stress and loss
Breaker reclose function
* Presented by SGRI during CIGRE 2014in Paris
FAULT CLEARANCE OPTIONS
7
Three possible solutions to clear DC faultsSolution 1 - DC Circuit Breakers (DC CBs) FC time < 5ms Minimal disturbance Half bridge converters (HBCs) STATCOM functionalitySolution 2 - Blocking Converters (BC)+DC Disconnector (DCD) FC time > 30ms Disturbance to the whole grid STATCOM functionalitySolution 3 - Half Bridge (HBCs) + ACCBs+ DCD FC time > 70ms Disturbance to the whole grid No STATCOM functionality
FAULT CLEARANCE OPTIONS
8
Option DC CBs BC + DC SWHBC + AC
CBs + DC SW
Fault clearance
time< 5ms >30ms >70ms
STATCOM functionality Yes Yes No
Losses Medium High Low
Cost Medium High* Low
Technical & Economic Comparison
CASE STUDY
9
Zhoushan400MW
Daishan300MW
Sijiao100MW
Yangshan100MW
Qushan100MW
Zhoushan400MW
Daishan300MW
Qushan100MW
Yangshan100MW
Sijiao100MW
46km
17km
39km
32.3km
46km 17km39km
32.3km
In service 4th July 2014Rated capacity 400/300/100/100/100 MW
Rated DC voltage ±200 kV
• Power supply to islands• 5-terminal radial network• No redundancy• AC CBs to clear DC side faults
Current status
• Transform to HVDC grid• Reduce line losses• Provide redundancy for Zhoushan• DC side fault clearance
Upgrade plan
CASE STUDY
10
• 3 protection zones
• 4 DC CBs in tie-lines required
• Option 4: BC
• Option 5: HBC
Zhoushan
Daishan
SijiaoYangshan
QushanDC
breaker
• Op 1: HBCs, no DC CBs
• Op 2: BCs, no DC CBs
• Op 3: HBCs, two DC CBs for each DC
Options 1, 2 & 3 Options 4 & 5
Zhoushan
Daishan
SijiaoYangshan
QushanDC
breaker
CASE STUDY
11
Option Protection zones
No. of DC CBs Converters Cost ratio STATCOM
functionality
1 1 0 HBC: 5 1.0 No
2 1 0 BC: 5 1.40 Yes
3 1 10 (x2) HBC: 5 1.45 Yes
4 3 4 (x2) BC: 5 1.54 Yes
5 3 4 (x2) HBC: 5 1.18 No
Technical & Economic Comparison
CONCLUSIONS
12
• Both technologies of DC circuit breakers and the blocking converters can be used to clear DC side faults
• Using DC circuit breakers is the best option technically but may not be the preferred option economically
• Using blocking converters needs DC switchgear to isolate faulted section which increase the fault clearance time
• Dividing DC grid into multiple zones can reduce the need of number of DC circuit breakers and affected area of the grid
• Dividing DC grid into multiple zones may be the preferred option technically and economically
Paris Palais des Congrès
7