1 FCU Checklist Fan Coil Unit System Checklist This checklist should be used and completed throughout the project, and its different stages, delivery, storage, installation & pre-commissioning, before the functional testing occurs. Project Name: Date: Equipment ID. Contents Contents ..................................................................................................... 1 Delivery Inspection ...................................................................................... 3 Storage Inspection ....................................................................................... 5 Storage Area ............................................................................................ 5 Storage of Fan Coil Unit ............................................................................ 6 Pre-Installation Inspection ............................................................................ 7 Maintenance/Access .................................................................................... 9 Pre-Commissioning Inspection .................................................................... 10 General .................................................................................................. 10 Electrical General ................................................................................... 10 Controls System/Motorized Dampers & Interlocks ....................................... 11 Fresh Air Supply [Direct] .......................................................................... 12 Fresh Air Supply [AHU] ............................................................................ 13 System Fire Dampers .............................................................................. 14 Filters .................................................................................................... 14 Supply Air Fan ........................................................................................ 15

Upload: others

Post on 04-May-2022

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Fan Coil Unit System Checklist

1 FCU Ch eck l is t

Fan Coil Unit System Checklist This checklist should be used and completed throughout the project, and its

dif ferent stages, delivery, storage, installat ion & pre-commissioning, before the

functional test ing occurs.

Project Name:

Date:

Equipment ID.

Contents Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

Delivery Inspection .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

Storage Inspection .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

Storage Area .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

Storage of Fan Coil Unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

Pre-Installat ion Inspection .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

Maintenance/Access .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

Pre-Commissioning Inspection .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

Electrical General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

Controls System/Motorized Dampers & Interlocks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

Fresh Air Supply [Direct] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

Fresh Air Supply [AHU] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

System Fire Dampers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

Filters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

Supply Air Fan .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Page 2: Fan Coil Unit System Checklist

2 FCU Ch eck l is t

Cooling Coil . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

Heating Coil . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

Refrigerant Dx Coil System .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

Condensate drain/siphon .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

Electric Heater . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

Supply Air Ductwork . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

Return Air Ductwork . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

Controls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

Page 3: Fan Coil Unit System Checklist

3 FCU Ch eck l is t

Delivery Inspection Once the Fan Coil Unit arrives at the site, usually delivered by a transport

company, the following should be checked with the driver b efore being accepted

into storage.

Any noted damage should be reported to the manufacturer/supplier within 3 days

in writ ing, supported with photographs.

Ref Inspection/Task Yes/No

/[n/a]

Notes

1 Supplier's consolidated delivery

t icket is available, showing all

equipment and ancil laries for

inspection and being used to

check.

2 Copy of the order issued to the

supplier is available for reference

and is being used to check .

3 Equipment is packaged and crated

in separate boxes for maximum

protect ion

4 The unit nameplate and details

match the purchase order

5 Delivery protect ion is dry

6 Unit /s are dry internally

7 The external casing of the unit /s

are undamaged

8 All pipework connections are the

correct size

9 Pipework connections are

undamaged

Page 4: Fan Coil Unit System Checklist

4 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

10 All pipework handing 's are correct

11 All ducting connections are the

correct size

12 All ancil laries [valves, actuators,

dampers, f i l ters] included in

delivery as per the order and

delivery note

13 Spin the fan blades to ensure not

damaged and out of l ine

14 Check all coils for damage

externally and internally

15 Check drip pan/condensate pan

for damage, including insulat ion.

16 If purchased, check plenums for

damage and ensure they are the

correct sizes & spigots.

17 Replace any protect ion that has

been removed

Page 5: Fan Coil Unit System Checklist

5 FCU Ch eck l is t

Storage Inspection

Storage Area I f the equipment is to be placed into storage on -site before installat ion, there wil l

be an inspection completed checking the following.

Ref Inspection/Task Yes/No/[n/a]

Notes

1 The area is internal and wil l not

be affected by the weather.

[ i f t h e u ni t is n o t r a t e d fo r ex t er na l us e]

2 The surface where the equipment

is to be placed is f lat .

3 The equipment wil l be raised from

the f loor to allow airf low and stop

the risk of water ingress.

4 The area is well covered and

protected.

5 The area is well venti lated and

has no risk of high humidity .

6 The area is clean & dust-free.

Page 6: Fan Coil Unit System Checklist

6 FCU Ch eck l is t

Storage of Fan Coil Unit Prior to the units being placed into storage , the following should be checked.

Ref Inspection/Task Yes/No/[n/a]

Notes

1 Units wil l not be stacked .

2 Units wil l not have materials

stacked on them.

3 All ancil laries wi l l be placed in a

safe and secure location , so items

do not go missing or get

damaged.

4 All original packaging is intact and

not removed.

5 Pipework caps are not removed .

6 Ductwork connections a re covered

to stop the ingress of dirt and

foreign objects

7 Unit and all components placed on

a f lat surface.

Page 7: Fan Coil Unit System Checklist

7 FCU Ch eck l is t

Pre-Installation Inspection Prior to the units being installed, the following should be checked.

Ref Inspection/Task Yes/No

/[n/a]

Notes

1 The slab/wall/base is ready, f lat ,

and level & can bear the weight of

the installat ion and bracketry.

2 I f being installed above an

exist ing ceil ing, ensure that there

is enough space through the

ceil ing grid to install the unit and

ancil laries.

3 The room/area is dry and

watert ight.

4 The area being installed is not

prone to f looding or ponding of

water.

[ f or w a l l mo u nt e d/ f l oo r mou n te d u ni ts ]

5 The room/area the unit wil l be

installed into is clean and dust -

free.

I f there is dust/construct ion work,

then the unit should be protected.

6 I f the unit has a venti lat ion

supply, ensure it is installed ready

for connecting, or the louver has

been installed , if direct fresh a ir.

7 The installat ion of the unit wil l not

impede the installat ion of the

condensate trap/pipework , and the

pipework run vs. fall required wil l

be achievable.

Page 8: Fan Coil Unit System Checklist

8 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

8 All connections,

pipework/ductwork, etc. , can be

independently supported and not

supported by the unit .

The best pract ice is to install self -

support ing brackets prior to the

connection of the unit

9 Ensure that all access doors are

clear and not blocked from

brackets or other services , where

required.

10 Check to ensure that all

connections kits containing -

gaskets, bolts, cleats, screws are

available to allow bolt ing up of the

equipment and ancil lary

equipment.

11 Remove all transport feet and

bolts.

12 Check that all required cabling is

available for

connection[power/controls] .

Page 9: Fan Coil Unit System Checklist

9 FCU Ch eck l is t

Maintenance/Access Ref Inspection/Task Yes/No

/[n/a] Notes

1 There is enough space allowed

around and above/below the unit

once installed to perform

maintenance and remove

components.

[ch eck t h e man uf ac t ur er 's mai nt e n anc e

ins t ruc t i o ns f or r eq u i r e me nts ]

2 All doors can be fully opened , and

panels are removed to gain

access to the unit .

3 Check that there is enough space

for coils, fans, and f i l ters to be

removed and replaced.

4 I f the unit is mounted at high

level, confirm that there is a safe

manner to remove the parts and

components and that there is

enough space at high level and at

the f loor level to allow this.

Page 10: Fan Coil Unit System Checklist

10 FCU Ch eck l is t

Pre-Commissioning Inspection Once the equipment has been installed and prior to the functional test ing and

commissioning phase taking place, the following wil l be checked.

General Ref Inspection/Task Yes/No

/[n/a] Notes

1 Document the information of the

unit from its nameplates and

cross-reference with the specif ied

information to ensure correct.

2 Ensure the unit is level.

3 All-access doors/panels can be

open and closed with no gaps or

leakage.

4 Check that all transport bolts and

feet are removed.

5 External supply/extract louver, if

being used, is installed and f ixed

with no air gaps.

6 All vibrat ion mounts installed

7 Seismic restraints, where

required, installed.

8 Unit and all components , including

valves and controls , are labeled in

l ine with the project naming

convention.

9 Operation and startup manual for

the Fan Coil Unit available.

Electrical General

Page 11: Fan Coil Unit System Checklist

11 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a] Notes

1 Unit and components are

fully earthed in l ine with

the manufacturer 's

instruct ions.

2 Earthing has been tested

3 Emergency disconnect

installed for each

component in l ine with

NFPA/local code

requirements

4 Electrical voltage from the

site matches the unit

required voltages.

5 All cabling is installed and

connected on the correct

containment/raceways and

not damaged.

6 All cabling has been

tested/torque tested.

7 A local motor control panel

[LMCP] has been installed

8 The local motor control

panel has been electrically

tested

9 All electrical cabling is

labeled in l ine with the

project naming convention.

Controls System/Motorized Dampers & Interlocks

Page 12: Fan Coil Unit System Checklist

12 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a] Notes

1 Motorized dampers

installed as per the

drawings and open/close

freely.

2 All controls and panels

have been installed to

operate the motorized

dampers

3 Fire trip has been installed

and operating/interlocked

with the venti lat ion system.

Fresh Air Supply [Direct] This wil l cover Fan Coil Units that are installed connected direct ly to the outside

to draw in the fresh air.

Ref Inspection/Task Yes/No

/[n/a]

Notes

1 The posit ion of the intake louver

is in l ine with the design

requirements and posit ioned so

as it wil l not be affected by any

exhaust air .

2 Weather louver/roof cowl

installed and weather t ight with

relevant mesh and is

unobstructed.

3 Weather louver installed with

correct mesh.

4 Weather louver mesh-free area

meets the design requirements

5 Plenum installed connecting the

louver to the ducting.

Page 13: Fan Coil Unit System Checklist

13 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

6 Plenum has drain installed with

trap to remove any unwanted

ingress of water

7 Plenum has access hatch/s

installed to allow future

maintenance and inspections

8 All fresh air ductwork is

installed, correct size, and

connected to the unit with

correct f ixings

9 All attenuators are installed as

shown on the drawings.

10 All non-return dampers are

installed as per construct ion

drawings.

11 All volume control dampers are

installed as per construct ion

drawings.

12 Ductwork insulated and vapor

seal in l ine with the

specif icat ion.

13 Test holes available in the duct

to allow air readings

Fresh Air Supply [AHU] This wil l cover Fan Coil Units that are installed connected to an AHU system that

supplies its fresh air.

Ref Inspection/Task Yes/No

/[n/a]

Notes

1 The posit ion of ducting is in l ine

with the design requirements .

2 Plenum installed , allowing the

connection of the supply ducting

to the ducting.

Page 14: Fan Coil Unit System Checklist

14 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

3 All fresh air ductwork is

installed, correct size, and

connected to the unit with

correct f ixings

4 All fresh air has been balanced

and provid ing the correct amount

of airf low at the required

temperature as per design.

5 All attenuators are installed as

shown on the drawings.

6 All non-return dampers are

installed as per construct ion

drawings.

7 All volume control dampers are

installed as per construct ion

drawings.

8 Ductwork insulated and vapor

seal in l ine with the

specif icat ion.

System Fire Dampers Ref Inspection/Task Yes/No

/[n/a] Notes

1 Check that the f ire dampers are

installed, as per the drawings,

and have been tested in l ine with

the project requirements.

Filters

Page 15: Fan Coil Unit System Checklist

15 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

1 Filter mounting frames are clean

and dust free.

2 Panel f i l ters are installed, clean,

and are of the correct grade.

3 Filters have the correct sealing

gaskets installed.

4 The f i l ters are not jammed in the

rails

5 All components upstream of the

f i l ter are clean and dust -free

6 Panel f i l ters are locked in place

7 Differential pressure sensors are

installed and calibrated.

Supply Air Fan Ref Inspection/Task Yes/No

/[n/a] Notes

1 Electrical connections and

cables are complete, fully tested,

and torqued in l ine with

project /manufacturer

requirements

2 Motor protect ion installed and

operating [Overload]

3 Motor protect ions calibrated

4 Voltage from electrical systems

is correct for the unit

requirements [within +/ -10%]

Page 16: Fan Coil Unit System Checklist

16 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

5 The fan housing is clean and

dust-free

6 Fan, blades, and motors are

clean and dust -free.

7 Fan belt tension is correct

8 Fan belt condit ion is good

9 Check the t ightness of f ixings

[torque]

10 Impeller is balanced

11 Fan/motor rotates in the correct

direct ion with no obstruct ions [by

hand]

12 Fan/motor rotates in the correct

direct ion with no obstruct ions

[electrically bump unit on ]

Cooling Coil Ref Inspection/Task Yes/No

/[n/a] Notes

1 The cooling coil is clean, in good

condit ion, and the f ins

undamaged.

2 Ensure that the pipework is the

connected and correct size

3 Ensure that the f low and return

pipework handings are correct.

[W at er I n l e t – do wns t r ea m o f th e a i r f l ow

d i rec t i on

Wa te r O ut l e t – u ps t re a m of t h e a i r f lo w

d i rec t i on ]

Page 17: Fan Coil Unit System Checklist

17 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

4 The installat ion of the pipework

wil l not put stress on the

equipment connections or create

vibrat ions.

5 The materials used between the

equipment and the chil led water

system wil l not cause

Electrolysis.

6 Pipework that is to connect to

the unit has been weld tested.

7 Pipework that is to connect to

the unit has been pressure

tested.

8 Pipework that is to connect to

the unit has been cleaned and

f lushed.

9 Equipment has been

backflushed.

10 The system has been bled and

air removed.

11 The chil led water system has

been hydraulically balanced.

12 Pipework is insulated and vapor

sealed

13 Insulat ion is labe led

14 All pressure gauges installed

and display scale as per design

requirements.

Page 18: Fan Coil Unit System Checklist

18 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

15 All valves/control valves are

installed, and the correct

direct ion

16 All commissioning devices are

installed

17 All strainers are installed and

clean.

Heating Coil Ref Inspection/Task Yes/No

/[n/a]

Notes

1 The heating coil is clean, in good

condit ion, and the f ins are

undamaged

2 Ensure that the pipework is the

connected and correct size

3 Ensure that the f low and return

pipework handings are correct .

[W at er I n l e t – do wns t r ea m o f th e a i r f l ow

d i rec t i on

Wa te r O ut l e t – u ps t re a m of t h e a i r f lo w

d i rec t i on ]

4 The installat ion of the pipework

wil l not put stress on the

equipment connections or create

vibrat ions.

5 The materials used between the

equipment and the heating water

system wil l not cause

Electrolysis.

Page 19: Fan Coil Unit System Checklist

19 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

6 Pipework that is to connect to

the unit has been weld tested.

7 Pipework that is to connect to

the unit has been pressure

tested.

8 Pipework that is to connect to

the unit has been cleaned and

f lushed.

9 Equipment has been

backflushed.

10 The system has been bled and

air removed.

11 The heating water system has

been hydraulically balanced.

12 Pipework is insulated and vapor

sealed

13 Insulat ion is labe led

14 All pressure gauges installed

and display scale as per design

requirements.

15 All valves/control valves are

installed and, the correct

direct ion

16 All commissioning devices are

installed

17 All strainers are installed and

clean.

Page 20: Fan Coil Unit System Checklist

20 FCU Ch eck l is t

Refrigerant Dx Coil System Ref Inspection/Task Yes/No

/[n/a] Notes

1 The refrigerant coil is clean, in

good condit ion , and f ins are

undamaged

2 External condenser installed

3 Ensure that the gas and suction

pipework is connected and the

correct size

4 Ensure that the gas and suction

pipework handing 's are correct.

5 The installat ion of the pipework

wil l not put stress on the

equipment connections or create

vibrat ions.

6 The materials used between the

equipment and the refrigerat ion

pipework system wil l not cause

Electrolysis.

7 Pipework that is to connect to

the unit has been

pressure/vacuum tested.

8 The system is charged with the

correct amount of refrigerant.

9 Pipework is insulated and vapor

sealed

10 Insulat ion is labe led

11 All solenoids installed and

operating

Page 21: Fan Coil Unit System Checklist

21 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

12 All sight glasses installed

13 All valves/control valves are

installed and, the correct

direct ion

Condensate drain/siphon Ref Inspection/Task Yes/No/[n/a] Notes

1 The condensate is installed

to the correct fall.

2 Ensure it is protected from

any frost with insulat ion

and/or heating cable.

3 There is a trap installed

and is installed in l ine with

manufacturers '

requirements.

[Ch eck man u fac tu rer 's i ns t r uc t io ns

for ca lcu l at io n / r eq ui re me nts ]

4 I f there are mult iple coils

installed on a unit , ensure

the condensate pipework

configurat ion is insta lled in

l ine with the

manufacturer 's

requirements.

5 Check that the size of the

condensate is correct.

6 Ensure the trap is f i l led to

the correct level.

Page 22: Fan Coil Unit System Checklist

22 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a] Notes

7 Ensure the drain pan is

clean and free of debris

Electric Heater Ref Inspection/Task Yes/No

/[n/a] Notes

1 Operation of the heating coil is

fan controlled/ interlocked

2 Fan delay incorporated into the

control 's logic, allowing the fan

to run [15 mins] after the heater

has deactivated/switched off.

3 Heater elements are clean and

not obstructed by debris

4 All electrical test ing was

completed, including torque tests

of connections.

5 All safety components are

connected and operational ,

including all thermostats to cut

power to the heater if needed.

6 All controls cabling is connected

and installed in l ine with the

manufacturers/design drawings.

7 Power is available to the electric

heater/control panel for

operation.

Supply Air Ductwork This covers ductwork f rom the fan coil unit to gri l les.

Page 23: Fan Coil Unit System Checklist

23 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

1 All supply air ductwork is

installed, correct size , and

connected to the unit with

correct f ixings

2 All attenuators are installed as

shown on the drawings.

3 All volume control dampers are

installed as per construct ion

drawings.

4 Ductwork insulated and vapor

seal in l ine with the

specif icat ion.

5 Test holes available in the duct

to allow air readings

Return Air Ductwork Ref Inspection/Task Yes/No

/[n/a]

Notes

1 The posit ion of recirculat ion

gri l les is in l ine with the design

requirements and posit ioned so

as wil l not be affected by the

fresh air intake.

[B e mi n df u l o f sh or t cyc l in g]

2 Plenum installed connecting the

gri l les to the ducting/fan coil

unit .

3 Plenum has access hatch/s

installed to allow future

maintenance and inspections

4 All extract air ductwork is

installed, correct size , and

connected to the unit with

correct f ixings

Page 24: Fan Coil Unit System Checklist

24 FCU Ch eck l is t

Ref Inspection/Task Yes/No/[n/a]

Notes

5 All attenuators are installed as

shown on the drawings.

6 All non-return dampers are

installed as per construct ion

drawings.

7 All volume control dampers are

installed as per construct ion

drawings.

8 Ductwork insulated and vapor

seal in l ine with the

specif icat ion.

9 Test holes available in the duct

to allow air readings

Controls Ref Inspection/Task Yes/No/[n/a] Notes

1 Ensure all sensors and

instruments are installed

as per the control

logic/manufacturers wiring

drawings

2 All sensors are calibrated