FAB CE Feasibility Study Technical Activities. FAB CE Internal Stakeholders’ Workshop March 5 th 2008, Prague. Content. Introduction. TEC WG Approach to FAB CE. Mission and Scope. Deliverables. Roadmap. Technical Enablers. Initial Scenario. Static Scenario. Dynamic Scenario. - PowerPoint PPT PresentationTRANSCRIPT
1
FAB CE Feasibility Study Technical Activities
FAB CE Internal Stakeholders’ Workshop
March 5th 2008, Prague
Click to edit Master title style
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
04/20/23 2
2
FAB CE
Introduction
Content
Conclusions
Initial Scenario Static Scenario Dynamic Scenario Contingency
Technical Enablers
Technical Opportunities
TEC WG Approach to FAB CE Mission and Scope Deliverables Roadmap
Click to edit Master title style
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
04/20/23 3
3
FAB CE
Mission and scope for the FAB Technical Developments:
SCOPE
DataProcessing
Systems(DPS)
“Define options for pragmatic and feasible technical solutions to support the establishment of the FAB CE”
TEC Approach for FAB CE
Technical Services (support, maintenance)
CommunicationsNavigationsSurveillance
(CNS)
Technical Services (support, maintenance)
Click to edit Master title style
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
04/20/23 4
4
FAB CE
WP 2.1Analyze the Technical
Environment
What is required by the new airspace and concepts
What are the required technical changes and opportunities
Provide a high level timescale for implementation activities
Development Process of the TEC WG
WP 2.2Analyze OPS Concept
WP 2.3Define Technical Solutions
WP 2.4Develop Technical Roadmap
What is currently available and planned by 2010
TEC Approach for FAB CE
Click to edit Master title style
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
04/20/23 5
5
FAB CETEC Approach for FAB CE
Key Elements of the Technical Roadmap
TEC ENABLERS: changes required by FAB operations (airspace/concept)
TEC OPPORTUNITIES in the use and planning of the CNS/ATM
2009 201520132011
• FAB CE Technical Planning Board• Technical Cooperation and Harmonisation Activities
Main driver for TEC environment evolution
Contribute to improve TEC coordination, achieve cost and risk reduction
STATIC ScenarioAirspace and OPS Concept
DYNAMIC ScenarioAirspace and OPS Concept
INITIAL ScenarioFAB CE Establishment
Click to edit Master title style
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
04/20/23 6
6
FAB CE
Establishment of Regional Technical Planning Board
Existing and planned by 2010 DPS systems and CNS infrastructure
Airspace and Concept
TEC Enablers/ Initial Scenario
CONFLICT TOOLS
Data Processing Systems [DPS]
SUPERVISION
MONITORINGTOOLS
SAF-NETSVOICE COMS
SYSTEM
FLIGHT DATA [Management and
Processing]
SURVEILLANCE[SDPDS]
INTERFACES
ENVIRONMENTALData Processing
CONTROLLER WORKINGPOSITIONS
NETWORK Ground-Ground
Communications Infrastructure
Communications/Navigations/Surveillance [CNS]
Radios Sensors
NETWORK Ground-Ground
Communications Infrastructure
Radios Sensors
Click to edit Master title style
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
04/20/23 7
7
FAB CE
ENV - Modification of existing systems / data according to the new airspace design
FDP - Modification of existing systems addressing:
New Area Of Responsibility, Modifications of interfaces
SUR - Data Distribution based on Coverage requirements
COM - Communication Support
A/G coverage, G/G – voice and data
Airspace Modifications
TEC Enablers/ Static Scenario
CONFLICT TOOLS
Data Processing Systems [DPS]
SUPERVISION
MONITORING TOOLS
SAF-NETSVOICE COMS
SYSTEM
FLIGHT DATA [Management and
Processing]
SURVEILLANCE[SDPDS]
INTERFACES
ENVIRONMENTALData Processing
CONTROLLER WORKINGPOSITIONS
Communications/Navigations/Surveillance [CNS]
Radios Sensors
ENVIRONMENTALData Processing
FLIGHT DATA [Management and
Processing]INTERFACES
SURVEILLANCE[SDPDS]
SensorsRadios
VOICE COMSSYSTEM
NETWORK Ground-Ground
Communications Infrastructure
NETWORK Ground-Ground Communications
Infrastructure
Click to edit Master title style
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
04/20/23 8
8
FAB CE
Operational Concept
TEC Enablers/ Static Scenario
ATC Tools - Change of Area of Interest of the ATM Systems
SNETS - Change of Area of Interest of the ATM Systems
CWP/HMI Convergence –This OPS Concept Element will be based on a common ORD for the FAB CE
ASM/ATFCM Integration – for Level 2 (pre-tactical phase) as identified by the CIV/MIL concept of operations
New technical support tool to be developed for the agreed implementation solution
CONFLICT TOOLS
Data Processing Systems [DPS]
SUPERVISION
MONITORINGTOOLS
SAF-NETSVOICE COMS
SYSTEM
FLIGHT DATA [Management and
Processing]
SURVEILLANCE[SDPDS]
INTERFACES
ENVIRONMENTALData Processing
CONTROLLER WORKING
POSITIONS
Communications/Navigations/Surveillance [CNS]
Radios Sensors
Interoperability –Harmonisation of SYSCO implementation
SAF-NETS
SURVEILLANCE[SDPDS]
MONITORINGTOOLS
CONFLICT TOOLS
FLIGHT DATA [Management and
Processing]
CONTROLLER WORKINGPOSITIONS
INTERFACES
NETWORK Ground-Ground Communications
Infrastructure
ENVIRONMENTALData Processing
ASM/ATFCM Integration – for Level 2 (pre-tactical phase) as identified by the CIV/MIL concept of operations
New technical support tool to be developed for the agreed implementation solution
Click to edit Master title style
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
04/20/23 9
9
FAB CE
ENV - Ensure data consistency for the area of dynamicity
FDP
TEC Enablers/ Dynamic Scenario
Airspace and Concept
Adaptation of systems to the Dynamic change of AoR
SNETS
ATC Tools
SSCM – Single Sector Configuration Management for a
Sector Group Supported by more than one ATSU/system
CONFLICT TOOLS
Data Processing Systems [DPS]
SUPERVISION
MONITORINGTOOLS
SAF-NETSVOICE COMS
SYSTEM
FLIGHT DATA [Management and
Processing]
SURVEILLANCE[SDPDS]
INTERFACES
ENVIRONMENTALData Processing
CONTROLLER WORKING
POSITIONS
Communications/Navigations/Surveillance [CNS]
Radios Sensors
CONFLICT TOOLS
MONITORINGTOOLS
SAF-NETS
FLIGHT DATA [Management and
Processing]
SURVEILLANCE[SDPDS]
INTERFACES
ENVIRONMENTALData Processing
CONTROLLER WORKINGPOSITIONS
Radios Sensors
In addition to Static Scenario, new functionalities are required
ENVIRONMENTALData Processing
FLIGHT DATA [Management and
Processing]
SAF-NETS
SURVEILLANCE[SDPDS]
CONFLICT TOOLS
MONITORINGTOOLS
SUPERVISION
SSCM
INTERFACES
New Functionality in FDP(s) where required, orNew regional distributed architectureCoordination and Transfer Interfaces
Extension of Area of Interest of the ATM SystemsSame situation awareness in area of dynamicity within the systems
Extension of Area of Interest of the ATM Systems Common Application of Controller Decision Support Tools
VCS Interfaces
NETWORK Ground-Ground
Communications Infrastructure
NETWORK Ground-Ground Communications
Infrastructure
VOICE COMSSYSTEM
VOICE COMSSYSTEM
Click to edit Master title style
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
04/20/23 10
10
FAB CE
• Definition of aiding units for each ATSU• Definition of level of contingency service provision, etc
TEC Enablers/ Contingency
The current Contingency Plan provides high level operational principles.
Its impact on TEC environment will be analyzed in detail at a later stage of the project when particular decisions will be made on contingency solutions:
Dynamicity Function can be an enabler
Click to edit Master title style
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
04/20/23 11
11
FAB CE
Future developments and services
TEC Opportunities
Common Definition and Synchronised Procurement of :
20112010 2012 2013 2014 2015
Flight Message Transfer Protocol (FMTP) Implementation
Common Approach to New Surveillance Technologies
HMI Convergence
Down-Linked Airborne Parameters
Air Ground Data Link Services (AGDL)
TEC Services Optimisation
Migration to SESAR compliant regional system
Voice Communications Protocol (Migration to VoIP)
Harmonised Approach to AMAN
Click to edit Master title style
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
04/20/23 12
12
FAB CEConclusions
No TEC blocking factors identified for FAB CE establishment
Multiple parallel implementation activities may represent risks for meeting the timescales
Implementation of TEC enablers supporting dynamic AoR cross border operations suggested to align with the introduction of SESAR compliant systems (beyond 2015)
Details to be clarified during the definition phase
Regional Technical Planning Board will mitigate the risk developing detailed implementation plans