experience sharing workshop on research and development … · experience sharing workshop on...
TRANSCRIPT
Experience Sharing Workshop on
Research and Development 2015
(Group 5)(Group 5)(Group 5)(Group 5)
Mr. LAU Koon-ming
Chief Quantity Surveyor / 2
18 June 2015
Accomplishments with Stakeholders in Quantity Surveying Works
1. Benchmarking HA Construction Cost against Residential Buildings in Private Sector
2. Compilation of Housing Authority's Standard Conditions of Contract in Capital Works New Works Contract (HAGCC)
3. Electronic Dissemination of Tender Documents4. 5D BIM 5. BIM as a Value Management Tool for Collaborative
Design Decisions
Group 52
Benchmarking HA Construction Cost against Residential Buildings in Private Sector
� Objectives -
� To benchmark superstructure construction cost for HA domestic blocks against that for residential buildings of average standard in Private Sector.
� To identify areas of major differences in costs and outline specifications.
� To identify building elements in HA projects with cost significance for improving cost effectiveness.
Group 53
Stakeholder: Langdon & Seah Hong Kong Limited
� Findings of Study in 2012Findings of Study in 2012Findings of Study in 2012Findings of Study in 2012� Superstructure construction cost of HA Public Rental Housing (PRH) blocks was on average 57% *57% *57% *57% * lower than that of residential buildings of average standard in private sector.
� About 77% of total cost variance attributed to architectural and finishes elements reflecting the difference in choice of finishes materials and provisions of fittings, etc.
� Remaining 23% of the total cost variance was mainly attributed to the differences of BS provisions such as non-provision of decorative and luxurious light fittings and luxurious interior finishes in lift cars, and less adoption of transfer plates in HA projects.
Benchmarking HA Construction Cost against Residential Buildings in Private Sector (Cont’d)
Group 54
Benchmarking HA Construction Cost against Residential Buildings in Private Sector (Cont’d)
� Consultant’s Consultant’s Consultant’s Consultant’s conclusionsconclusionsconclusionsconclusions
� HA’s PRH projects have achieved better cost effectiveness.� Some provisions such as partitions, timber flooring, air-conditioning units and domestic electrical appliances are usually provided in private sector projects but not in HA domestic blocks. If discounting these provisions, the superstructure construction cost of HA site specific rental blocks would be on average 51%51%51%51%
lower than that of private sector projects.
� Structure is a more significant element in HA projects as its cost contributes a higher proportion of the superstructure costs (about 47%47%47%47%) than that in private sector projects.
Group 55
Compilation of HAGCC
� Before May 2014, the Housing Authority (HA) adopted the Government of Hong Kong General Conditions of Contract 1993 Edition (Government GCC) which had been used for 20 years
� A significant number of Special Conditions of Contract (SCC) clauses were made to modify the Government GCC for implementation of HA’s quality housing initiatives and to suit HA’s operation
� The contract documents had become bulky and not user-friendly
BackgroundBackgroundBackgroundBackground
Group 56
Stakeholder: Langdon & Seah Hong Kong Limited
� To cater for HA’s circumstances and requirements
� To embody HA’s policies in respect of –
� fair risk allocation and equitable risk-sharing
� risk management and dispute avoidance
� prompt settlement of claims and final account
� To enhance user friendliness and operational efficiency
� To preserve users’ long established experience with the previous conditions of contract
� To foster collaboration between the HA and Contractors
Objectives of the HA’s Standard Conditions of ContractObjectives of the HA’s Standard Conditions of ContractObjectives of the HA’s Standard Conditions of ContractObjectives of the HA’s Standard Conditions of Contract
Compilation of HAGCC
Group 57
� The HA’s standard Conditions of Contract has been implemented in HA’s capital works new works contracts with tenders issued from May 2014 onwards
� General Conditions of Contract (GCC)
� HKHA GCC for Building Works 2013 Edition
� HKHA GCC for Foundation Works 2013 Edition
� HKHA GCC for Civil Engineering Works 2013 Edition
� HKHA GCC for Miscellaneous Works 2013 Edition
� HKHA Articles of Agreement and General Conditions of Nominated Sub-contract to Building Contracts 2013 Edition
� Special Conditions of Contract (SCC)
� HKHA Standard Consolidated Libraries of SCC for Building, Foundation, Civil Engineering and Miscellaneous Works 2013 Edition
� HKHA Standard Library of Special Conditions of Nominated Sub-contract to Building Works Contracts 2013 Edition
� Appendices to the Conditions of Contract and to the Conditions of Nominated Sub-contract
The Suite of HA’s Standard Conditions of ContractThe Suite of HA’s Standard Conditions of ContractThe Suite of HA’s Standard Conditions of ContractThe Suite of HA’s Standard Conditions of ContractCompilation of HAGCC
Group 58
� Electronic dissemination of tender document (by L10/L10Pro) had been implemented in many building tenders since April 2010
� It was technically feasible
Group 59
Stakeholder: ARCADIS Asia Limited
BackgroundBackgroundBackgroundBackground
Electronic Dissemination of Tender Documents
Tender Distribution (L10/L10Pro System)
Electronic Tender DisseminationElectronic Tender DisseminationElectronic Tender DisseminationElectronic Tender Dissemination
Disc A
Disc B
Disc C
- Front Part, etc.
including Form of
Tender
- BQ in L10 format
- L10 Software Installation Programme
Traditional Tender
�2 sets Tender Documents
+
Additional
Form of Tender
Disc D - Drawings, ref.
document
+Additional
Form of Tender
Group 510
- Addendum for
Front Part, etc.
�
Tender Addendum (L10/L10Pro System)
Traditional Tender
- Addendum to be
inserted to the original
Tender Documents by
hand- Addendum for BQ to
be merged with the
original BQ by L10/L10Pro
Disc
A#
Disc
B#
Electronic Dissemination of tender
Group 511
L10/L10Pro
generated
discWith Priced BQ
information
�+
+
Tender
Documents
Additional
Form of Tender
Technical
Submission
(if any)
Tender Submission (L10/L10Pro System)
Traditional Tender
Form of Tender
(2 copies)
+
+
Technical
Submission
(if any)
+Priced BQ
generated by L10
Hardcopy
Electronic Dissemination of tender
Group 512
� an average of 153 man-hours per building tender or 19 man-hours per foundation tender could be saved after the use of L10Pro;
� the average paper saving per building tender was 68,543 pages, while in the foundation tender, the reduction in the use of paper was 13,147 pages per tender;
� Tenderers have no adverse comments on the use of L10Pro;
� New development on L10Excel that can convert BQ in Excel format into L10Pro environment will soon be launched, RD219 to follow up.
FINDINGS: TIME, RESOURCES AND WAY FORWARD
Group 513
5D BIM
Integrated 5D =
3D 4thD 5thD
Group 514
Stakeholder: China State Construction Engineering (Hong Kong) Ltd.
isBIM limited
BIM
5D BIM
3D Model
Time (4th D)Construction Programme
Cost (5th D)
BQ Rates 5D Database
An integrated 5th Dimensions Approach
Group 515
5D BIM
Application of 5D BIM and Way Forward
� The quantities generated from BIM model benefit both payment application by contractor and payment assessment by project QS
� Upon linking of construction programme with the model quantity and BQ rates, the construction cash flow simulation can be generated for budget planning and cash flow forecast
� Contractor could further benefit in managing subletting, sub-contactor management and procurement of material
� HA has been exploring the Standard Approach of Modelling (SAM), and the measurement practice for BIM quantity take-off
Group 517
BIM as a BIM as a BIM as a BIM as a Value Management ToolValue Management ToolValue Management ToolValue Management Toolfor for for for Collaborative Design DecisionsCollaborative Design DecisionsCollaborative Design DecisionsCollaborative Design Decisions
� Incorporation of material costcostcostcost and construction timetimetimetime parameters into the design models;
� Comparison between different design design design design optionsoptionsoptionsoptions can be easily and readily obtained in real time;
� 4D-simulation of plant layoutplant layoutplant layoutplant layout and construction sequenceconstruction sequenceconstruction sequenceconstruction sequence for site level operations;
� BuildabilityBuildabilityBuildabilityBuildability of different design options can be accurately reflected and validated in advance.
� This is a retrospective study
Group 518
Stakeholder: isBIM limited
To identify the To identify the To identify the To identify the Best ValueBest ValueBest ValueBest Value solutionsolutionsolutionsolution
To identify the best value solution through studies and evaluation of-
� ArchitecturalArchitecturalArchitecturalArchitectural
� GeotechnicalGeotechnicalGeotechnicalGeotechnical &&&&
� StructuralStructuralStructuralStructural DesignDesignDesignDesign OptionsOptionsOptionsOptions
The process involves multimultimultimulti----disciplinarydisciplinarydisciplinarydisciplinary interactions, maximizing the creative potential of all concerned project team members to achieve the optimum balanceoptimum balanceoptimum balanceoptimum balance....
Quality
TimeCost
Group 519
(3) Options for transfer slab and transfer beam
Option A
selected
Group 522
Based on the quantities extracted from BIM models and after analysing the data. Design Option A has been selected revealing the option requires the least Construction Time in spite of the higher cost as time is the major concern of the project team in this project.