executive summary initial environmental examination … activities... · initial environmental...
TRANSCRIPT
Executive Summary
Initial Environmental Examination
Marine Seismic Studies AD-5
Myanmar
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-1
INTRODUCTION
Woodside (Myanmar) Pte Ltd (Woodside) intends to acquire a two dimensional (2D) marine seismic survey
and a three dimensional (3D) marine seismic survey, as well as gravity and magnetic data and seabed
samples (the Project), in Block AD-5 (AD-5), which is located offshore Myanmar in the Rakhine Basin in
the Bay of Bengal (Figure 0-1). Woodside is the Operator of the block with equity interests of 55% together
with BG Exploration & Production (Myanmar) Pte Ltd (BGEPM) with non-operating interests of 45%.
The proposed Project activities are planned to be undertaken between November 2015 and April 2016, due
to favourable weather and sea conditions for offshore surveys during the North-east Monsoon.
In accordance with the draft Environmental Impact Assessment Procedure (EIAP) of the Republic of the
Union of Myanmar, this Initial Environmental Examination (IEE) is a report comprising a systematic
assessment of the proposed activities. Woodside prepared this IEE for these activities for submission to
the Myanmar Oil and Gas Enterprise (MOGE) and the Ministry of Environment, Conservation and Forestry
(MOECAF). Woodside undertook a screening assessment whereby a Project Proposal was submitted to
MOECAF in February 2015, and MOECAF then confirmed that the level of assessment for the proposed
survey activities would be set at an IEE level. Subsequently, a series of stakeholder engagements were
conducted at various levels.
The purpose of the proposed surveys is to commence investigation the possible presence of hydrocarbons
within AD-5. An initial geophysical investigation (Stage 1) is proposed to include 2D and 3D marine seismic
acquisition, gravity and magnetic data acquisition, and seabed coring. Additional seismic surveying (Stage
2) may be undertaken if the results of Stage 1 deliver a business case to pursue additional seismic data
acquisition. The activities would most likely include additional 3D marine seismic acquisition. The scope
and timing of these activities relies on the evaluation of the Stage 1 results. The scope of this IEE report
includes both the Stage 1 and Stage 2 activities. Possible future activities exploration drilling and
development activities are not included in this IEE. Should the Stage 2 activities introduce any new
significant environmental impact risk or significant increase in an existing environmental impact/risk not
provided for in this document, Woodside will update and resubmit the document for re-assessment.
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-2
Figure 0-1: Location of AD-5, Offshore Myanmar
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-3
PROJECT DESCRIPTION
The Project will be undertaken within AD-5, which is located immediately off the coast of the Ayeyarwady
Region, to the west of the townships of Labutta and Ngapudaw in the Village-tract of SinMa to the south of
Pathein Township.
Seismic acquisition and associated activities within AD-5 will take place from approximately 247kilometres
(km) to approximately 94km off the west coast of the Ayeyarwady Region and about 100km to the west-
north-west of Thameehla Kyun (Diamond Island). The surveys will comprise an acquisition area of
approximately 10,645 square kilometres (km2), in water depths ranging from approximately 2,300m to
2,800m.
The Project will comprise 2D marine seismic and 3D marine seismic data acquisition as well as gravity and
magnetic data acquisition and seabed coring, and is expected to be conducted as multiple activities across
both AD-5 and A-7 which is immediately to the east (Figure 0-1). Survey activities in A-7 are subject to a
separate IEE process and are not included in this IEE.
Due to the length of the towed streamers, the seismic vessels will require an additional turnaround zone
approximately 8km wide outside of the blocks as shown in Figure 0-2, which depicts the extent of the
Project operational area. The turning area allows for survey line run-outs, survey line turns and survey line
run-ins and minimises the likelihood of streamer entanglement; however, no acquisition of data will be
conducted in this zone.
Project Schedule
The 2D and 3D marine seismic survey (MSS) activities are expected to commence between mid-November and early December 2015, with approximately 35 days and 180 days of acquisition across A-7 and AD-5, respectively.
The 3D MSS in AD-5 and A-7 will be followed by 2-D in A-7.
Gravity and magnetic data will be acquired concurrently with seismic acquisition, utilising the same survey vessels. The seabed sampling is likely to commence in March 2016 after the majority of the 3D MSS has been completed.
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-4
Figure 0-2: The Project Operational Area including Buffer Zone
Marine Seismic Surveys
Marine seismic surveys enable the mapping of subsurface geological formations and the identification of
potential hydrocarbon deposits. The seismic surveys involve directing acoustic (sound) energy into the
geology (rocks) under the seabed and measuring their reflection using specialised equipment towed by a
purpose-built survey vessel as shown in Figure 0-3. The survey vessel tows long cables called ‘streamers’
behind it at a set depth below the water surface. Sound receiving devices called ‘hydrophones’ are attached
to the streamers at specific intervals to measure the reflected sound. The sound source and streamers are
usually towed at a depth of 5 – 20m below the water surface, and are towed at a speed of approximately 5
knots (8 – 9km/h), thus the vessel is constantly moving.
The sound source generates intermittent acoustic pulses that are directed downwards to the seabed. These
sound waves are reflected back upwards from the various layers of sediment and rock below the seabed,
and are received by the hydrophones contained in the streamers being towed behind the survey vessel.
Hydrophones convert the reflected pressure signals into electrical energy that is digitised and transmitted
along the streamer to the recording system on board the survey vessel. A computerised analysis of these
reflected sound waves generates images of the geology below the seabed, which enables an accurate
identification of the location, extent and depth of possible hydrocarbon reserves below the seabed.
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-5
Figure 0-3: Diagrammatic Overview of Seismic Survey Operations
Source: Base image sourced from www.seismicsurvey.com.au and reproduced courtesy of IPIECA
Proposed 2D and 3D MSS
The proposed 2D and 3D MSS are transient activities that do not require the construction of any facilities,
structures or permanent features.
The 2D MSS will use one streamer, approximately 10,000 to 12,000m in length, towed at 10m below the
sea surface behind the seismic vessel (see Plate 0-1). The seismic source array will be located
approximately 7m below the surface with single array configuration and a typical volume of 4,000 cubic
inches (cui). Typical source outputs (sound pressure levels – SPL) during the 2D MSS will be 245 – 260
dB re 1 μPa@ 1m (when measured relative to a reference pressure of one micropascal). In the 3D MSS,
10 to 12 streamers are towed behind the seismic vessel, together with dual acoustic sources. The
streamers, each approximately 7,000m long, will be towed at 10m below the sea surface and 100m apart
at their widest point at the end of the streamers. The 3D MSS is expected to use a dual acoustic array
configuration with a typical volume of 4,000cui. A 3D survey gives a detailed 3D image of the subsurface
geology.
To complete each survey, the vessel with its towed streamer (2D) or streamers (3D) will complete a series
of parallel survey lines. The survey lines are typically 4km apart in the case of the 2D MSS and typically
500m apart for the 3D MSS.
Acoustic pulses are generated by the sound source
Acoustic pulses reflect off the various rock layers below the seabed
Reflected sound waves are received by hydrophones contained in the streamers
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-6
Plate 0-1: 3D Survey Vessel and Towed Array
Figure 0-4: Generic 3D MSS Equipment Configuration
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-7
Gravity and Magnetic Data Acquisition
Gravity and magnetic data is utilised in the oil and gas industry to assess the depth and nature of the
seabed sediments. Acquisition equipment measures changes in density and magnetic intensity, and this
allows maps to be created showing the lateral distribution of the various sediments. Gravity and magnetic
data acquisition is proposed to be conducted as part of the 2D and 3D MSS in AD-5, with equipment and
personnel working in conjunction with seismic operations to acquire the data simultaneously.
Seabed Sampling
In addition to the proposed seismic acquisition, Woodside will also undertake seabed sampling to
characterise the seabed sediments. A separate vessel fitted with sampling equipment will be utilised to
undertake the seabed sampling via non-drilling techniques. These cores will be analysed to provide
additional information on the seabed. The seabed sampling survey will utilise a single dedicated survey
vessel. Once retrieved, the cores will be removed from the core barrel and a preliminary analysis will take
place on board the vessel, the cores will then be retained for more detailed laboratory analysis. The seabed
sampling will take place at locations to be determined after the 3D seismic data has been analysed. All
samples will be retained on the vessel and not discharged back to the ocean.
Plate 0-2: Core Sampler equipment
being deployed from the
vessel
Plate 0-3: Sample of the seabed sediments after
recovery of the core sampler equipment
to the vessel
Project Vessels
For the AD-5 2D and 3D MSS, the expected survey fleet will comprise of approximately six (6) to eight (8)
vessels in total, including:
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-8
Seismic vessel: a purpose-built vessel with accommodation for the survey crew and operating
equipment. The vessel will tow the streamers and seismic source. The same vessel or separate seismic
vessels will be utilised for the 2D and 3D MSS.
Support vessel: the support vessel provides assistance to the seismic vessel during each of the survey
activities. This includes maintaining a safe work area around the towed equipment (the safety zone),
providing supplies when required for the seismic vessel, at sea refuelling, and assisting in emergency
situations.
Chase vessels: one or more chase boats will be used to clear acquisition lines of any debris, liaise
with fishermen and ward off other vessels entering the safety zone around the survey vessel to maintain
safe operating distances.
A dedicated vessel is likely to be utilised for the seabed sampling. The vessels will operate 24 hours per
day, 7 days a week throughout the survey periods.
Project Logistics
The seismic survey vessel is expected to remain offshore for the entire survey. Bunkering and resupply of
the vessel will be conducted at sea by a support vessel. The survey contractor will utilise an existing onshore
supply base, A specific port is yet to be determined; however, it is likely to be located outside of Myanmar.
Crew changes for the seismic vessels utilised for the 2D and 3D MSS will be conducted offshore within the
operational area or in the waters surrounding AD-5 and A-7, using the support vessels. In some instances,
helicopters may be used to transfer personnel and equipment to and from the seismic vessels. Any
helicopter flights during the 2D and 3D MSS will be operated from an airport in Myanmar, which has not
been identified at this stage.
Vessel Discharges and Waste Management
Wastewater generated by the seismic and support/ chase vessels includes domestic and sanitary
wastewater, deck and bilge water that will be treated and monitored aboard before discharge into the
surrounding environment. These wastewater releases will strictly comply with MARPOL 73/78 Annex I
requirements.
A variety of non-hazardous solid wastes will be generated during the seismic survey such as glass, paper,
plastic and wood. No solid wastes will be disposed of intentionally into the marine environment. All solid
wastes will be collected and shipped to a shore. Vessels shall be operated in compliance with MARPOL
regulations whereby the discharge of comminuted and disinfected sewage and food waste ground to
particle size <25 millimetres (mm) is permitted >3 nautical miles (nm) from the nearest land. Hazardous
wastes such as lubricants, filters, chemical containers and used equipment, will be stored and consolidated
for disposal onshore.
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-9
BASELINE ENVIRONMENTAL CONDITIONS
Physical Environment
Weather and oceanographic conditions in the Bay of Bengal are dominated by the North-east Monsoon in
the months from November through to April, and the South-west Monsoon from April through to September,
the former being the period of calmest seas. The Block AD-5 operational area is located within the Rakhine
Basin, on the eastern fringe of the Bay of Bengal and offshore from the western coast of Ayeyarwady
Province, Myanmar. Adjacent offshore features to the basin include the Bay of Bengal and the associated
Bengal Fan deposits to the west, the Ayeyarwady Delta and associated Moattama Offshore Basin to the
south and the Andaman-Nicobar Trench and associated island arc to the south. The Rakhine Basin is
approximately 850km in length and 200km in width. Water depths range from approximately 2,300m to
2,800m.
Biological Environment
The operational area for AD-5 is located at approximately 100km west-north-west of Diamond Island and
about 95km from the nearest mainland of Myanmar. It is within a deep water zone where there are no coral
reefs, mangroves, seagrass, estuarine or shoreline transition-zone habitats within the area of influence
(AOl). This zone is relatively unproductive as compared with the coastal area due to lack of nutrients. The
major habitat types include a low-productivity pelagic zone and deep water benthic ecosystems. It is
believed that major taxa found in the pelagic zone are expected to be mobile or transient like oceanic shark,
tuna and whale while the demersal communities are dominated by crab, prawn, shrimp, rays, skates and
flatfish.
There are 20 species of ocean seabirds currently identified as occurring in Myanmar waters. An additional
61 species of birds live in the coastal zone, although there is limited data on their use of the marine
environment. The Project is not expected to have any impact on marine or coastal birdlife.
There are two broad groups of marine mammals present in Myanmar waters—cetaceans (whales and
dolphins) and sirenians (dugongs and manatees). It is highly unlikely that any dugongs will be present in
the operational area, given that their preferred habitat is seagrass meadows in shallow waters and the
survey activities will take place in waters greater than 50m deep. There is limited detailed research into the
presence and activities of cetaceans in the eastern Bay of Bengal, and data has been compiled based on
information that is available from primary literature and historical records. There is evidence of the possible
presence of approximately 32 species of cetaceans in Myanmar waters. These species are comprised of
seven (7) baleen whales, five (5) beaked whales, three (3) large delphinds, 14 smaller delphinds and three
(3) species of sperm whale. Cetacean range data is considered to be approximate due to limited information
sources.
Socio-economic Environment
Fisheries
Myanmar's marine fishing industry consists of three distinct fishing zones namely, onshore, inshore and
offshore. The inshore area starts from the Low Water Mark to 10NM from shore in the Ayeyarwady Region.
For offshore fisheries management, the Department of Fisheries has divided the Myanmar coastline into
140 fishing grounds of 30 by 30 nautical mile blocks by using latitude and longitude lines and has designated
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-10
four fishing areas—Rakhine, Ayeyarwady, Mon and Tanintharyi. The AD-5 MSS will not interact with any
coastal zone artisanal fishing activities.
The operational area is located in the offshore fishery zone and encompasses fishing block B17 and part
of blocks B11, B12, B13, B16 and B18. The operational area also includes known offshore tuna fishing
grounds, with the western part of AD-5 overlapping one of these areas. Given that the survey vessels will
operate in water depths deeper than 2,000, it is possible that fishing vessels targeting large pelagic fish
species such as tuna and swordfish may be encountered.
Marine Traffic
Marine traffic off the coast of the Ayeyarwady Region is limited to regional traffic, mostly inshore, away from
AD-5. A moderately busy shipping lane connects Chittagong port in Bangladesh to the Malacca Straits in
Malaysia. AD-5 is coincident with this shipping lane in the east of the block and encounters with vessels
during the proposed 2D and 3D MSS and associated activities in the operational area can be expected.
The AD-5 area may also be utilised by coastal trading vessels travelling from Yangon and Kyaukpyhu.
POTENTIAL IMPACTS AND MITIGATION
Methodology
The environmental and social risk management methodology used in this IEE is based on Woodside’s Risk
Management Operating Standard. These standards are consistent with the AS/ISO 31000-2009 Risk
Management Principles. The risk management methodology provides a framework to demonstrate that the
identified risks and impacts are reduced to as low as reasonably practicable (ALARP), and the acceptability
of risks and impacts.
Identification of Impacts
Based on the project description, the potential impacts resulting from the proposed 2D and 3D MSS and
associated activities in the AD-5 operational area can be categorised as.
1. Potential impacts related to the activities of the vessels:
Physical presence:
o interference with shipping activities; and/or with commercial fisheries;
o collision with marine mammals and other protected marine species (such as turtles and whale
sharks);
o loss of towed seismic equipment resulting in physical damage to seabed substrates and
habitats; and
o introduction of invasive marine species.
Atmospheric emissions: emissions primarily from fuel combustion on the seismic and
support/chase vessels.
Discharge to sea and solid wastes: sewage, grey water and food waste discharge, impact to the
marine environment from incorrect handling and disposal of chemicals, solid and hazardous
wastes.
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-11
Generation of light: generation of artificial light aboard the vessels is necessary for safety reasons;
however it can attract marine fauna close to the vessels.
Accidental releases: spills of marine fuel oil (MFO) during at sea bunkering (refuelling), or resulting
from vessel collisions, accidental releases of hazardous materials.
2. Potential impacts related to the 2D and 3D seismic acquisition activities:
Underwater noise generated by the seismic sources (discharge of airguns throughout the
operational area).
3. Impacts related to seabed sampling activities:
Physical disturbance/damage to seabed sediments and benthic communities resulting from gravity
coring.
Summary of Environmental/Social Risk Assessment
An environmental and social risk assessment of the 2D and 3D MSS and associated activities has been
undertaken to understand and manage the environmental and social risks associated with the activities to
a level that minimises impacts on the environment and meets the objectives of the proposed surveys.
The risk assessment indicates that the potential impacts arising from the Project in AD-5 can be categorised
as having Low residual risk levels. No residual risks were assessed as Medium, High or Severe. Table 0-
1 below presents a summary of the assessed level of residual (post-mitigation) environmental and social
risk associated with the Project.
Mitigation Measures
Table 0-2 summarises the key mitigation strategies and measures that Woodside and the geophysical
contractor(s) will implement during the Project to ensure that potential impacts are either eliminated or
reduced to levels that are ALARP and environmentally and socially acceptable.
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-12
Table 0-1: Summary of Environmental/Social Risk Assessment for the Project, AD-5, Offshore Myanmar
Aspect Source of Risk Key Potential Environmental / Social Impacts
Residual Risk Rating
Co
ns
eq
uen
c
e
Lik
eli
ho
od
Res
idu
al
Ris
k
Planned (Routine) Activities
Physical presence of
project vessels
Proximity of project vessels causing
interference with or displacement of other
vessels (commercial shipping, fishing)
Short-term, isolated interference with/exclusion of
commercial shipping and fishing vessels F 1 Low
Routine noise
emissions
Generation of noise from project vessels
and mechanical equipment during normal
operations (excluding seismic survey
equipment)
Temporary and minor behavioural and physiological
disturbance (e.g. avoidance or attraction) to marine
fauna
F 2 Low
Generation of noise from seismic survey
equipment
Temporary and minor behavioural and physiological
disturbance (e.g. avoidance of local area) to fauna
Temporary and minor changes to the location of target
species for fishing activities
E 1 Low
Routine atmospheric
emissions
Internal combustion engines on survey
vessel, supply vessel(s) and machinery
engines
Reduced local air quality from atmospheric emissions
Minor contribution to greenhouse gas emissions F 1 Low
Routine discharges
Discharge of bilge water, grey water,
sewage and putrescible wastes from the
survey and support vessels to the marine
environment
Localised and temporary reduction in water quality due
to nutrient enrichment
Localised and temporary adverse effect to marine biota
in offshore waters
F 0 Low
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-13
Aspect Source of Risk Key Potential Environmental / Social Impacts
Residual Risk Rating
Co
ns
eq
uen
c
e
Lik
eli
ho
od
Res
idu
al
Ris
k
Routine light generation Light spill from seismic, support and chase
vessel
Temporary and minor behavioural effect to fauna
attracted to light (seabirds, turtles) F 0 Low
Seabed sampling Gravity coring of seabed sediments
Localised physical disturbance and impact to substrates
and benthic communities
Potential physical damage to submarine cables
F 0 Low
Unplanned Activities (Accidents/ Incidents)
Unplanned discharges
to the marine
environment
Hydrocarbon release to the marine
environment during at sea refuelling, or from
vessel collision
Accidental discharge of
hydrocarbons/chemicals from seismic or
support vessel deck activities and
equipment (e.g. cranes and winches)
Localised and minor temporary disruption to fauna such
as oiling of marine mammals, reptiles and seabirds
Localised and temporary contamination of water which
may lead to toxic effects on marine biota in offshore
waters
F 2 Low
Accidental loss of solid hazardous or non-
hazardous wastes to the marine
environment
Pollution and contamination of the environment and
secondary impacts on marine fauna (e.g. ingestion or
entanglement)
F 1 Low
Unplanned events
associated with physical
presence of project
vessels
Accidental collision between project vessels
and migratory marine fauna
Potential injury or fatality of an individual or a number of
marine fauna with no threat to overall population viability E 1 Low
Loss of seismic streamers and/or acoustic
source
Localised short-term damage of substrates and benthic
communities in the immediate location of the dropped
seismic streamers and/or acoustic source
F 1 Low
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-14
Aspect Source of Risk Key Potential Environmental / Social Impacts
Residual Risk Rating
Co
ns
eq
uen
c
e
Lik
eli
ho
od
Res
idu
al
Ris
k
Introduction of invasive marine species
associated with ballast water transfer
Disturbance, damage, or alteration of the receiving
natural ecosystem E 0 Low
Transportation of invasive marine species
via vessel hull, internal niches or in-water
equipment
Disturbance, damage, or alteration of the receiving
natural ecosystem E 0 Low
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-15
Table 0-2: Summary of Mitigation Measures for the Project, AD-5, Offshore Myanmar
Aspect Management Objectives/
Commitments
Mitigation Strategies / Measures
Planned (Routine) Activities
Physical presence of
project vessels
Minimise potential disruption to
commercial fishing and to local and
international shipping activities
Timely advice to local fishermen concerning the survey activities
Notifications to all known relevant fishery stakeholders including the Department of
Fisheries and the various fishing associations,
Fisheries Liaison Officer to participate in the survey and interact with local fishermen
when necessary (Burmese Speaker);
Issuance of Notice to Mariners;
Maintenance of a Safety Zone around project vessel and all towed equipment;
Establishment of a Communications Protocol
Use of chase vessel(s) to liaise with approaching vessels and maintain the Safety
Zone (MSS only)
Crew to include at least one bilingual English/Burmese speaking member
Implementation of a Community Grievance Mechanism to deal with any claims /
complaints
Adherence to the international convention concerning the interaction of vessels at sea
(COLREGS)
Maximizing efficiency of seismic surveys to reduce operation times, where possible;
Standard maritime safety procedures will be followed including the appropriate
navigational lighting and maintenance of radio contact with nearby vessel
Routine noise
emissions from
acoustic source
Minimise disruption to marine fauna,
particularly mammals, fishes and turtles
Appropriate maintenance of vessels and associated equipment.
Maximizing efficiency of seismic surveys to reduce operation times, where possible;
Pre-start search (30mins shallow water, 60mins deep water) (MSS only)
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-16
Aspect Management Objectives/
Commitments
Mitigation Strategies / Measures
Marine Mammal Observer present (MSS only)
All sightings recorded (MSS only))
Soft start (20mins) (MSS only)
Prestart delay zones (500m of source) (MSS only)
Routine atmospheric
emissions
Minimise impacts on air quality in
operational area
Comply with MARPOL73/78 Annex VI requirements specifically:
Adequate maintenance of mechanical/motor systems (vessel operator to maintain
maintenance and inspection log)
Vessel to hold an International Air Pollution Prevention (IAPP) Certificate as appropriate
to class
Use of low sulphur fuel (sulphur content not to exceed 3.5% m/m) when it is available
Practice segregation of waste - only appropriate non-hazardous wastes to be disposed
in incinerator (wastes which cannot be safely incinerated are to be disposed of at a
shore base)
Routine discharges Minimise reduction of water quality in
vicinity of vessels from discharge of
sewage, grey water, putrescible and
other wastes
Comply with MARPOL requirements for waste management, e.g. sewage treatment
unit, oil/water separator, macerator for biodegradable waste
Vessel to obtain International Sewage Pollution Prevention (ISPP) certificate and
International Oil Pollution Prevention (IOPP) certificate, as appropriate to vessel class
The vessel will carry waste management plan providing procedure for minimizing,
collecting, storing, processing and disposing of garbage waste inventories will be
maintained
Maintain waste log including waste type, quantity and disposal method
Routine light
generation
Minimise light disturbance to marine
fauna
Lighting will be minimised to sources required for navigational and operational safety
reasons.
On-board operational lighting will be located and oriented in such a way to direct
working light where it is needed, and minimise light spill to the marine environment.
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-17
Aspect Management Objectives/
Commitments
Mitigation Strategies / Measures
Seabed sampling No damage to undersea utilities, for
example submarine cables or pipelines
Confirm locations of undersea utilities prior to any seabed sampling
Aspect Management Objectives/
Commitments
Mitigation Strategies / Measures
Unplanned Activities (Accidents/ Incidents)
Unplanned
discharges to the
marine environment
Avoid fuel and oil spills
Minimise the potential impacts of fuel
and oil spills on the marine environment
Surveys will take place in the period of calmest weather and seas in the Project
operational area.
Seismic vessels will be relatively slow moving approximately 4.5 knots.
Notice to Mariners will be issued with the Myanmar ports authority to advise as many
vessels as possible of the survey activities and timing.
Survey vessels and chase boats with utilise radar and visual observation to track
vessels in the area and where necessary advise of the activity by radio or hailed.
Refuelling to commence during daylight and when sea conditions are appropriate as
determined by the vessel master;
Job hazard analysis (or equivalent) is undertaken in place and reviewed before each
fuel transfer;
Transfer hoses are fitted with ‘dry-break’ couplings (or similar and checked for integrity);
Spill response kits are maintained and located in close proximity to hydrocarbon
bunkering areas to use to contain and recover deck spills;
Bunkering operations will be manned with constant visual monitoring of gauges, hoses
and fittings and sea surface; and
Radio communications will be maintained between seismic and support vessel
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-18
Aspect Management Objectives/
Commitments
Mitigation Strategies / Measures
In the event of any incidents which resulted in the release of hydrocarbon fuels to the
marine environment, vessel Masters will enact a Shipboard Marine Pollution
Emergency Plans (SOPEP)
Any significant fuel losses to the marine environment will be immediately reported to the
relevant third-party authorities.
Crew induction to include spill prevention, reporting and use of spill response
equipment.
Unplanned events
associated with
physical presence of
project vessels
Minimise likelihood of interactions with
marine fauna
Apply the procedures for vessel/marine fauna interactions as per IAGC/JNCC
guidelines, these measures include:
o Appropriate searches prior to start-up; soft start procedures; use of the Marine
Mammal Observer (MMO) (MSS only)
o Use of tail buoys designed to minimise turtle interaction (MSS only)
o Any vessel or towed equipment interactions with marine fauna recorded and
reported (MSS only)
o Where possible, reduction in vessel speed if mammals sighted within 500m
o Where possible, survey vessels will not approach closer than 100m for a cetacean
(unless animals bow riding)
o Training of personnel
Minimise risk of bringing exotic and pest
marine species into Bay of Bengal via
ballast water exchange
All Woodside-contracted vessels will comply with IMO Ballast Water requirements
Vessels which have obtained their ballast water from an area outside of Bay of Bengal /
Andaman Sea are not to discharge it within 50 nautical miles from land, or in water
depths less than 200m
Vessels to maintain record of ballast water uptake and discharge locations
Note that freshwater ballast can be discharged
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-19
Aspect Management Objectives/
Commitments
Mitigation Strategies / Measures
Minimise risk of bringing exotic and pest
marine species into coastal waters via
biofouling of hull and other niches
Woodside’s invasive marine species risk assessment process will be applied
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-20
Acoustic Disturbance to Marine Fauna
The response of marine fauna to seismic airgun noise will range from no effect to some behavioural
changes. Immediate physical effects are likely only to occur at very short ranges and high sound
intensities and will largely be unlikely to occur for the majority of species, as most free-swimming
animals will practice avoidance manoeuvres well before they get within the ranges at which physical
effects may occur. Animals that do not move away from the path of a seismic vessel because of
behavioural or physical constraints, or which are caught unaware within a few hundred metres of an
array when it starts up, will be most at risk of pathological effects. A behavioural response could occur
within 2.0km in deep water and 6.1km in shallow water of the airgun source using the 160dB re 1µPa
NMFS criteria..
Noise associated with airguns used during seismic surveys can cause behavioural changes in whales,
including swimming away from the source, rapid swimming on the surface and breaching. The level of
noise at which a response is elicited varies between species and even between individuals within a
species. With regards to avoidance behaviour by baleen whales; it is known that baleen whales will
avoid operating seismic vessels and the distance over which the avoidance occurs seems to be highly
variable between species and even within species. It is considered that this avoidance behaviour
represents only a minor effect on either the individual or the species population unless avoidance results
in displacement of whales from nursery, resting or feeding areas, at an important period for the species.
The AD-5 operational area and surrounding waters is not a known critical habitat for any cetacean
species.
For cetaceans, whale sharks and turtles that may be present in the operational area and surrounding
waters during the survey periods, the implementation of the procedures based on the International
Association of Geophysical Contractors (IAGC) Recommended Mitigation Measures For Cetaceans
during Geophysical Operations and the United Kingdom Joint Nature Conservation Committee (UK
JNCC) Guidelines for minimising the risk of injury and disturbance to marine mammals from seismic
surveys, plus the implementation of specific vessel-marine fauna interaction procedures to minimise
the risk of collision with the support and chase vessels, and the use of streamer tail buoys designed to
minimise turtle interaction, will minimise the likelihood of negative impacts upon these individuals from
survey activities.
PUBLIC CONSULTATION AND INFORMATION DISCLOSURE
Approach
The public consultation for the Project in AD-5 offshore Myanmar aimed to achieve a consistent,
comprehensive, coordinated and culturally appropriate approach. Principles employed for consultation
included:
Stakeholder identification, analysis and mapping;
Information disclosure;
Consultation and participation, and
Feedback system.
Stakeholders were identified at three levels – Union (Country/National level), Regional (Ayeyarwady
Region) and ‘Local’ (Township and Village-tract levels). Stakeholder groups included Government, civil
society and institutions and potentially affected people in local communities.
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-21
The consultation process was designed to align to the stages of an IEE, and involved three key phases:
1. Consultation for the IEE;
2. Baseline Data Gathering: conducted from 28th March 2015 to 24th June 2015, and
3. Disclosure of the IEE (to be completed within ten days after submission of the report to MOECAF).
Outcomes of Consultation
Some Union level Government departments highlighted the importance of following national
regulations, verifying baseline data and community development needs. MOECAF provided details on
the regulatory submission and approvals process. The Department of Fisheries (DoF) representatives
highlighted that they do not want local fishers to be affected by the seismic surveys and that, if there
were not any impacts, they would have no objections to the activities. They also advised that Woodside
should gain the consent of local authorities before undertaking the surveys and to inform the DoF once
the survey has been completed.
Stakeholders from the Ayeyarwady Regional Government encouraged Woodside to continue to engage
with the Regional Government and requested more details on project activities (e.g. vessel
specifications). ‘Environmental Conservation’ was highlighted as an important issue, and specifically
water and air pollution issues were raised. It was also emphasised that Woodside should engage
transparently and sensitively with local communities, particularly as there were existing sensitivities in
local communities about previous development projects, resulting in local controversy due to non-
transparent engagement.
As per Myanmar regulations, this draft IEE will be made available for public comment.. The full report
will be made available to the public in English and a non-technical summary will be made available in
Burmese. The report will be disclosed to stakeholders by means of local media, at public meeting
places and at Woodside’s office in Yangon.
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-22
Plate 0-4: Disclosure of Project Activities, Ywar Thit Village-tract (29/03/2015)
Plate 0-5: Disclosure of Project Activities, Thae Phyu Village-tract (31/03/2015)
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-23
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Overview
A Project-specific Environmental and Social Management Plan (ESMP) has been prepared for the
proposed marine seismic surveys and associated activities in AD-5. The ESMP aims to provide an
environmental and social management framework by outlining the compliance requirements, mitigation
measures and monitoring programmes to be undertaken throughout the marine seismic surveys and
associated activities.
The ESMP has been prepared based on the findings of this IEE and describes management measures
designed to mitigate potential environmental and social impacts of the proposed marine seismic surveys
and associated to levels that are considered to be ALARP and acceptable. The overarching purpose of
the ESMP is to:
Integrate management and mitigation measures into the Project activities in order to reduce or
mitigate any potential adverse impacts on natural and socio-economic environments.
Consider and address the concerns and interests of stakeholders who will potentially be engaged
or impacted during execution of the marine seismic surveys.
Establish systems and processes for delivery and implementation of the Project environmental and
social requirements in order to meet statutory and compliance standards.
Stakeholder Engagement and Communications Plan
The Stakeholder Engagement and Communications Plan details plans for the continued engagement
and notification of the proposed activities with local coastal communities, fishers and key stakeholders
prior to, during and after the surveys are completed.
The Plan contains actions and protocols that satisfy management requirements of both the Social
Management Plan and ongoing stakeholder engagement requirements. The Plan will be regularly
revisited, updated and improved over the life of the Project as more information is gained about
stakeholders and their needs.
As part of this Plan, a Community Grievance Mechanism will be established and communicated.
Roles and Responsibilities
The ESMP describes the key roles and responsibilities for all personnel (Woodside and contractors;
onshore and offshore) who will be involved in the Project.
Monitoring, Record Keeping and Reporting
The ESMP details all of the monitoring, record keeping and reporting requirements for the 2D and 3D
MSS and associated activities in the AD-5 operational area.
Auditing and Review
Environmental performance auditing will be undertaken to confirm that all significant environmental and
social aspects of the seismic survey activity are covered by the ESMP. It will also confirm that the
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
OFFSHORE SEISMIC STUDIES FOR AD-5, RAKHINE BASIN, MYANMAR
Page | ES-24
standards to achieve environmental and social performance are being implemented and identify
opportunities for continuous improvement and potential non-conformances.
Emergency Response
Project-specific Emergency Response Plans (ERP) will be developed by the survey contractors and
submitted to Woodside for review and approval prior to commencement of the surveys.
All vessels (seismic, support and chase vessels) involved in the Project will have onboard equipment
for responding to emergencies, including but not limited to medical and firefighting equipment, and spill
response equipment.
CONCLUSIONS
With the control and mitigation measures that will be employed, the environmental and social impacts
of the proposed Project in AD-5, offshore Myanmar, are expected to be localised and temporary.
Overall, the proposed 2D and 3D MSS, gravity and magnetic data acquisition, and seabed sampling
are not expected to have any long-term effects on local or regional biodiversity. The data acquisition
will not adversely impact ecosystem structure and function, for any of the key environmental and social
sensitivities and values identified for the marine environment of the operational area and surrounding
waters. The characteristics of the activities, particularly their relatively short duration and separation
(temporal and/or spatial) from sensitive environmental and social resources, mitigate many of the
potential environmental and social effects of the Project.
The risk assessment indicates that, with appropriate management, the residual environmental and
social impacts associated with the proposed Project are all ranked Low, are ALARP and acceptable.
There are no High, Medium or Severe ranked environmental and social impacts associated with the
Project.
This IEE describes the potential environmental and social impacts associated with the proposed Project
in AD-5, offshore Myanmar. The environmental and social impacts arising from the Project will not have
any significant negative effects on the environment during and after the proposed activities. This
outcome will be assured, by the implementation of the management and mitigation measures described
in this IEE (i.e. in the ESMP).