example risk management plan

Upload: curbelo

Post on 19-Oct-2015

55 views

Category:

Documents


0 download

DESCRIPTION

Example Risk Management Plan

TRANSCRIPT

  • 5/28/2018 Example Risk Management Plan

    1/8

    Utility Corporation Example Risk Management Plan

    RISK MANAGEMENT PLANALPHA TO OMEGA LINE

    TRANSMISSION LINE PROJECT

    UTILITY CORPORATION

    ST.LOUIS,MO 63103

    APRIL 10,2013

  • 5/28/2018 Example Risk Management Plan

    2/8

    Utility Corporation Example Risk Management PlanTABLE OF CONTENTS

    Introduction ............................................................................................................1

    Risk Management Approach ...................................................................................1

    Risk Owners ...........................................................................................................1Risk Identification...................................................................................................2

    Risk Qualification and Prioritization .......................................................................2

    Risk Monitoring ......................................................................................................4

    Risk Response Strategies ........................................................................................4

    Risk Register ..........................................................................................................5

    Contingency Management ......................................................................................5

    Acceptance .............................................................................................................5

  • 5/28/2018 Example Risk Management Plan

    3/8

    Utility Corporation Example Risk Management Plan

    Page 1of 6

    INTRODUCTION

    The purpose of this Risk Management Plan is to discuss how risks are identified, evaluated,

    ranked, monitored, and addressed as part of this project.

    RISK MANAGEMENT APPROACH

    The project team will undertake a methodical approach to risk management that will include the

    creation and maintenance of a risk register. Risk reviews will be incorporated into the routine

    project meetings as an agenda item to address risks with an approaching due date (two weeks)

    and into the construction meetings once they have begun to provide a more frequent review of

    the items that could affect project success.

    Owners will be identified and assigned to all risks where they will have the responsibility to

    develop triggers to monitor the risk and response plans appropriate for each item identified.

    Each risk owner may, at their discretion, assign someone to develop the response plans and

    monitor the triggers, but the owners will maintain the responsibility to monitor and report the

    status of all risk items back to the project team.

    At project completion, during the closing process, the project manager and team will assess the

    risk management process and will identify any improvements that can be made for future

    projects. Proposed improvements, as well as the final risk register, will be captured as part of the

    lessons learned knowledge base.

    RISK OWNERS

    The following individuals have been identified as the risk owners for the project. This list will be

    updated and maintained throughout the project in order to ensure the appropriate individual with

    the line-of-sight to the risks are named and aware of their roles.

    Role Team Member

    Risk Plan / Register Owner Ringo Starr

    Risk Plan / Register Advisor Darin Hendry

    Environmental Risks David Bowie

    Real Estate Risks Michael Phelps

    Transmission Line Design Risks Calvin Klien

    Materials Paul Newman

    Transmission Line Construction Robert Redford

    Project Scheduling and Controls David Hasselhoff

    Contractor Selection CDT (Sir Elton John)

  • 5/28/2018 Example Risk Management Plan

    4/8

    Utility Corporation Example Risk Management Plan

    Page 2of 6

    RISK IDENTIFICATION

    Risk identification will be done in several stages throughout the lifecycle of the project, but the

    following will be the most prevalent.

    Project ManagerThe project manager solicited team member and risk owner input into potential project

    risks and incorporated these into the project risk register. Risk registers from several

    other projects of similar scope were also reviewed to identify lessons learned and

    potential risks documented on those projects.

    Risk Assessment MeetingsRegular risk assessment meetings have and will continue to be scheduled with key team

    members and stakeholders to review the risk register. The team will review all active

    risks and will ensure appropriate risk ranking, impact, and response strategies have been

    developed and owners assigned to each risk on the register. Any new risks identified

    during the meetings will be added to the project risk register along with the appropriate

    status updates to risks already being monitored.

    Expert Discussions

    The project manager will continue to meet with individual subject matter experts

    throughout the project lifecycle and will capture any new risks during those meetings and

    will assure they are added to the risk register for management.

    RISK QUALIFICATION AND PRIORITIZATION

    In order to determine the severity of the risks identified by the team, a probability and impact

    factor will be assigned to each risk. This process will allow the team to prioritize risks based

    upon the effect they may have on the project. A probability-impact matrix will be used tofacilitate the team in moving each risk to the appropriate ranking on the risk register. Impacts

    will be assigned to several potential project areas including; Technical Performance, Schedule,

    Cost, and Safety.

  • 5/28/2018 Example Risk Management Plan

    5/8

    Utility Corporation Example Risk Management Plan

    Page 3of 6

    The following table assigns some measurable attributes to the probability and impact ratings that

    are used as part of the risk register (shown above).

    Impact Legend:

    Negligible Marginal Significant Critical Catastrophic

    1 2 3 4 5

    Technical Performance Shop Repair Field Repair Field Re-Work Minor Failure Major Failure

    Schedule 1 day 1 week 1 month 6 months 1 year

    Cost $50,000 $100,000 $250,000 $500,000 $1,000,000

    SafetyFirst Aid Doctor Visit Recordable Lost Time Major Injury / Death

    Probability Legend (p=probability of occurrence):

    Rare Unlikely Possible Likely Certain

    1 2 3 4 5

    Probability p < 5% 5% < p < 10% 10% < p < 50% 50% < p < 75% p > 75%

    Legend:Impact Probability1 - Negligible 1 - Rare2 - Marginal 2 - Unlikely

    3 - Significant 3 - Possible4 - Critical 4 - Likely5 - Catastrophic 5 - Certain

  • 5/28/2018 Example Risk Management Plan

    6/8

    Utility Corporation Example Risk Management Plan

    Page 4of 6

    RISK MONITORING

    Once the risks are appropriately ranked, the highest risk items will have triggers identified by

    risk owners, or their designees, that will indicate a risk is about to occur. The triggers will enact

    the appropriate risk response strategy. Risks and their triggers will be reviewed (at a minimum)

    once a month during the design development process and more frequently during construction. If

    a risk trigger event is identified by anyone on the project team between meetings, they will

    contact the project manager immediately in order to begin the appropriate risk response

    measures.

    RISK RESPONSE STRATEGIES

    Risk response strategies will include the following:

    Avoidance

    A risk should be avoided if reasonable. Safety, Quality, Cost, and Schedule impacts will

    need to be evaluated to determine whether the cost of avoidance (in dollars or time) will

    support such a decision.

    AcceptanceThe project team may agree to accept some risks and take no further action with them.

    These would include risks where there is no way to predict or avoid when the risks might

    occur or what impact they would have to the project. These may also include risks with

    an impact small enough (in relation to Safety, Quality, Cost, or Schedule) such that other

    responses would not be justified.

    Mitigation

    If a risk is unavoidable, then reasonable efforts should be taken to minimize the impact to

    the project where warranted. Evaluation of the impact to Safety, Quality, Cost, andSchedule will drive what type of mitigation efforts would be warranted for each risk.

    TransferenceWhen an outside party is better prepared to manage a risk, a risk may be transferred to

    that party. The use of lump-sum contracts can be an effective method of risk transference

    as long as the scope of work is well developed and appropriate and adequate contract

    language is in place to protect Ameren and to treat the contractors or vendors fairly.

    Bonding and/or punitive language can also help to transfer the cost of risks, but often

    come with a base cost impact to the contract as it is implemented and should be evaluated

    closely before being included.

    ResponseIf all attempts to avoid, mitigate, or transfer risks have failed (excluding risks the project

    team chooses to accept), a risk response plan will be developed to outline how the project

    team should react when the risk occurs.

    All risks will be evaluated against Safety, Quality, Cost, Schedule, and Technical performance in

    order to determine which response strategy outlined above is appropriate. Once the risks have

  • 5/28/2018 Example Risk Management Plan

    7/8

    Utility Corporation Example Risk Management Plan

    Page 5of 6

    been ranked, the highest risk items will have detailed response plans written by the risk owners,

    or their designees.

    RISK REGISTER

    A project risk register has been developed for the project and will be the main repository for all

    significant project risks to be identified, ranked, and monitored. The risk register will also

    contain links to the appropriate risk response plans once they have been developed.

    The Risk Register will be maintained separately on the project SharePoint site and shall be

    considered part of this overall risk plan document. Upon project completion, the risk register will

    be copied to the lessons learned repository, and unique risks shared with other project teams.

    CONTINGENCY MANAGEMENT

    Estimates for both maximum exposure and expected exposure will be performed for each of the

    discrete risks identified in the risk register. The sum of the expected numbers for all of the

    discrete risks will become the value of contingency being forecasted and managed for theproject. The sum of the expected exposure and the total project estimate (without contingency)

    will become the expected estimate for the total project. The sum of the maximum exposure

    numbers for all of the open discrete risk will become the maximum value of contingency. The

    sum of the maximum value of contingency with the total project estimate (without contingency)

    will become the high end estimate for the toal project.

    Throughout the project, the project team will closely monitor and manage project contingency.

    Once a project baseline is established at Gate 2 Gate Approval Board, all changes in project

    contingency will be tracked and managed in a contingency checkbook and updated in the project

    forecast in UIP. Changes in contingency may be a result of any of the following:

    Estimated exposure for any discrete risk item changes Contingency is utilized for the purposes of mitigating or transferring a risk

    Contingency is utilized as a result of issuing a Project Change Request (PCR)

    A discrete risk item is closed

    A new risk is identified

    Risk is reallocated from one risk to another risk

    ACCEPTANCE

    ________________________________________ Date: __________________

    Ringo Starr

    Project Manager

  • 5/28/2018 Example Risk Management Plan

    8/8

    Utility Corporation Example Risk Management Plan

    Page 6of 6

    ________________________________________ Date: __________________

    Darin Hendry

    Risk Manager

    ________________________________________ Date: __________________Winston Churchill

    Project Sponsor