  • INSTALLATION AND OPERATING

    INSTRUCTIONS

    VERTICAL TURBINE PUMPS

  • IMPORTANTThis instruction book should be used as a guide only as pumpinstallation should only be carried out by qualified and experiencedpersonnel using certified lifting and handling equipment.

  • 1PRELIMINARY PRECAUTIONSRISK OF DAMAGE T O THRUST BEARING ASSEMBLY

    WARNING: Do not restrict or shut o the discharge of the pump. The pumping characteristics of

    discharge is throttled down from its operating duty point.

    OVERPUMPING OF BORESThe warranty covers the failure of parts due to faulty materials or workmanship only and does not

    cover failure or excessive wearing of pump components or shafting due to overpumping of bores.

    of overpumping.

    Where possible pumps should be installed in properly screened and developed bores. Wheninstalled in uncased or slotted cased bores, care should be taken to ensure that the bore is not beingoverpumped (solids being discharged with the water), causing damage to both the pump and bore.

    Frequent or continuous pumping of sand indicates that erosion is occurring in the bore, forminga cavity in the water bearing strata, which will ultimately result in the bore collapsing, causing lossof water supply and possible loss of pump and piping etc.

    In properly screened and developed bores, damage to the bore by over pumping is less rapid, butdamage to pump bearings and shafting will result from intermittent supply of water to the pump inletimposing varying tension on the line shaft causing it to whip in the column pipe. This damage canalso result from overpumping in uncased and slotted cased bores.

    To guard against overpumpingdo not use the pump to clean out or test bores. This should be done before installation by the

    well borer using the correct type of pump and measuring equipment.accurately determine the capacity of the bore, and pumping levels before installation so that the

    pump can be set at the correct pumping level.the amount of water discharged should not exceed 80% of the rate at which the bore will deliver

    absolutely clear water.

    CHECKING THE BORE OR WELLThe Bore or Well should be checked forstraightness of hole. A misaligned bore can bend the column pipe and cause excessive vibration

    and rapid wear on the shaft and bearings.diameter of casing. Must be of su cient diameter to allow the pump to easily installed and

    retrieved.depth. The bore depth must be checked before pump installation. The pump strainer must have

    a minimum of 1.5 metres clearance from the bottom of the bore.

    AIR OR GAS IN BOREAir or gas can be the cause of poor pump performance, vibration and damage, or even prevent

    the pump from delivering any water at all.

    HANDLING OF PARTS All parts should be handled with care to prevent damage. Particular care must be taken with

    column and shafting to avoid misalignment resulting in poor performance and eventual failure.Check all parts for transport and handling damage before installation.

  • 2LINESHAFT COUPLING

    PUMP SHAFT

    LINESHAFT

    COLUMN PIPE COUPLINGRUBBER SHAFT BEARING

    ELECTRIC MOTOR

    MOTOR STOOL

    DISCHARGE HEAD

    TOP COLUMN PIPE

    SHAFT PACKING GLAND

    HEAD SHAFT ADJUSTING NUT

    THRUST BEARING

    FLEXIBLE COUPLING

    HEAD SHAFT

    NON-REVERSE RATCHET

    INLET STRAINER

    SUCTION CASE

    IMPELLER

    SUCTION CASE BEARING

    IMPELLER LOCKINGCOLLET

    DISCHARGE CASE

    DISCHARGE CASE CAP

    DISCHARGE CASE BEARING

    RUBBER BOWL

    PUMP BOWL

    COLUMN PIPE

    SHAFT BEARING SPIDER

    SUCTION CASE PLUG

    SAND CAP

    BRONZE BOWL BEARING

    DISCHARGE HEAD PLUG

    DEFLECTOR RING

    DEFLECTOR RING

    DRIVE SHAFT SPINDLE

    PARTS IDENTIFICATIONCHART ELECTRICMOTOR DRIVE UNIT

    LINESHAFT COUPLINGPUMP SHAFT

    LINESHAFT

    COLUMN PIPE COUPLING

    RUBBER SHAFT BEARING

    RIGHT ANGLE GEAR DRIVE

    DISCHARGE HEAD

    TOP COLUMN PIPE

    SHAFT PACKING GLAND

    HEAD SHAFT ADJUSTING NUT

    HEAD SHAFT

    INLET STRAINER

    SUCTION CASE

    IMPELLER

    SUCTION CASE BEARING

    IMPELLER LOCKING COLLET

    DISCHARGE CASE

    DISCHARGE CASE CAP

    DISCHARGE CASE BEARING

    RUBBER BOWL

    PUMP BOWL

    COLUMN PIPE

    PARTS IDENTIFICATIONCHART RIGHT ANGLEGEAR DRIVE UNIT

    SHAFT BEARING SPIDER

    SUCTION CASE PLUG

    SAND CAP

    BRONZE BOWL BEARING

    DISCHARGE HEAD PLUG

    DEFLECTOR RING

    DEFLECTOR RING

    DRIVE KEY

  • 3INSTALLATIONPUMP FOUNDA TIONThe foundation is usually constructed as a reinforced, cast, concrete block approximately 150mm

    wider than the base of the discharge head around all sides. Size of the foundation is dependent onallowable soil loadings and must be capable of carrying the combined weight of the pump, columnpipe, shafting, drive head, discharge head and column full of water. Vital pump and shaft adjustmentsand alignments will be disturbed if the foundation subsides.

    For installations incorporating direct coupling to right angle gear drive head, the foundation for thepump and driver should be integral.

    Use of a wooden template will ensure accurate location of discharge head foundations bolts in theconcrete foundation and will also ensure that the column pipe and pump will be centrally located inthe bore casing.

    HOISTINGLifting equipment must be of su cient capacity to safely lift and hold the entire pump unit, and must

    reach a height of 5 metres above the foundation. Column pipes and shafting require special attention,as these parts are manufactured to accurate alignment, and if dropped or sprung in any way, shouldnot be installed.

    INSTALLING THE PUMPThe pump should be handled carefully to prevent damage. Secure a pump lifting tool and raise the

    pump assembly into a vertical position taking care not to damage the strainer. Lower pump assembly

    remove the lifting tool. Note: Wrap sacking or similar material around pump to avoid damage.

    COLUMN PIPE AND SHAFTINGNote Drive shafts and drive shaft couplings are screwed left-hand thread.

    Column pipes and column pipe sockets are screwed right-hand thread.Assemble 3 metre lengths of column and shafting incorporating two 1.5 metre lengths of column

    metre length of shaft. Clean all faces andthreads and inspect for damage or burrs etc. Pipe threads must be thoroughly cleaned and lubricated.

    together and tighten with chain wrenches.

    and damaging the threads. Lift the assembly over the pump and connect shaft to pump shaft couplingusing anti-seize compound on the threads. Shaft faces must butt solidly with an equal amount of shaftthread showing at each side of the coupling. Lock shafts using two stilsons.

    Clean and lubricate the column pipe and pump discharge case threads and screw the column fullyinto the pump outlet and tighten using chain wrenches. Column pipe threads are right-hand and careshould be taken to start the threads squarely by hand to avoid cross threading.

    Take the weight of the pump and length of column pipe on the lifting equipment and remove thepipe clamp from the pump. Lower the assembly into the well and support on the foundation with pipe

    Measure the length of shaft protruding from the column pipe and ensure this remains constant onall sections added. Any variation will indicate incorrect butting of parts which must be corrected.

    Repeat this procedure for the remaining 3 metre lengths of column and shaft .

  • 4INSTALLATION (CONTD)

    DISCHARGE HEADWhen all of the 3 metre sections of column pipe have been installed in the bore the discharge head

    shafting so that the long threaded end with the keyway is to the top. Tighten the shaft coupling securely. Remove packing gland from discharge head and screw top column pipe (short length of columnwithout socket) into base of discharge head and tighten. Lift discharge head with top column pipe

    of column pipe and tighten securely.Take the weight of the discharge head assembly and column pipe and remove the pipe clamps.

    Lower the complete assembly, guiding the discharge head over the foundation bolts, onto thefoundation. Check that the head shaft is centralised in the packing box. If not accurately aligned thedischarge head base will have to be shimmed at the corners to centre the shaft. T e

    under the discharge head leaving the shims in place. Allow 48 hours before tightening down thefoundation bolt nuts.

    transmitted to the discharge head to disturb the alignment.

    PACKING GLAND into position just below the packing gland.

    Fit the packing gland assembly over the shaft and bolt into the discharge head. If packing has been

    packing rings are staggered. Do not tighten gland onto packing at this stage. (see adjusting packinggland).

    MOTOR STOOL WITH THRUST ASSEMBLY

    shaft and bolt to discharge head. Rotate shaft spindle to align y. Screw head shaftadjusting nut onto shaft (right-hand thread). Thrust bearings are pre-greased during factory assemblyand no further grease should be added during installation, as excessive greasing could causeoverheating. A small amount of grease should be added every 1,000 hours of running.

    ADJUSTING IMPELLER SETTINGSSlowly raise the impellers by screwing adjusting nut on head shaft until impellers break free from

    the bowls allowing free rotation of pump and no binding of impellers in bowls. Final adjustment is nowmade by raising impellers to measurements calculated using the following formula and multiple Xfor di erent pump models as per following table.

    To calculate impeller lift multiply X by pump setting and total discharge head (T.D.H.) of theparticular pump.

    Example: 200F Pump with 1 ShaftPump Setting = 45mT.D.H. = 70mImpeller Lift = .00115 x 45 x 70 = 3.6mm

    Secure adjusting nut with the locking screw. This setting is extremely important to the performanceand life of the pump and should be rechecked after a running-in period.

  • 5INSTALLATION (CONTD)

    IMPELLER SETTING T ABLE

    PUMP MODEL COLUMN SHAFT DIAM. X MULTIPLIER

    150R 25.4 (1) .00045

    180R 25.4 (1) .0007631.75 (1-1/4) .0005

    200F 25.4 (1) .0011531.75 (1-1/4) .00075

    250R 25.4 (1) .0012031.75 (1-1/4) .0007838.1 (1-1/2) .00054

    250F 25.4 (1) .00231.75 (1-1/4) .001338.1 (1-1/2) .0009

    300F 31.75 (1-1/4) .001538.1 (1-1/2) .0010644.4 1-3/4) .00077

    FITTING ELECTRIC MOTORFit motor shaft key and motor shaft coupling to electric motor, lock with setscrew and temporally

    direction of rotation. It must run ANTI-CLOCKWISE when viewed from the top. Fit drive pins andbushes and adjust clearance between coupling halves to a maximum of 1.5mm and tighten lockingscrews securely onto the coupling driving half key. T edrive pin nuts must be tightened evenly and progressively.

    ADJUSTING PACKING GLANDAdjust the shaft packing gland with the pump operating by slowly tightening the gland nuts until it

    leaks slightlyquickly.

  • 6PRE-LUBRICATION

    Each time the pump is started the rubber lineshaft bearings may have to be pre-lubricated withwater. Pre-lubrication varies with pump size and setting. Where a supply of water for pre-lubricationis not available a tank must be installed to gravity feed into the tapping in the discharge head locatedon the opposite side to the discharge. Connecting pipe should be of equal size to the tapping in thedischarge head, and include an automatic or manual gate valve. For the initial start-up the tank will

    e pump for future starts. Allow 75% ofthe water to drain into the column before starting pump. The gatevalve on the pre-lubrication line is

    Pre-lubrication is required on all installations where the distance from the static water level to the

    lubrication of the bearings irrespective of the interval between start up, as the bearings may burnt out.

    The recommended pre-lubrication tank capacity for various column sizes and settings is as follows

    Column Size (mm) Pump Setting ( m)

    75 60 105100 45 90

    130 35 75 150150 30 60 120

    200 45 120250 35 105300 35 60

    TANK SIZELITRES 100 200 400

    Pre-LubricationWater Storage

    Tank

  • 7INSTALLATION AND OPERATION OFAIR LINE GAUGE

    If accurate Standing or Static water levelreadings or Pumping Level and Drawdownreadings are required, an air line gauge isinstalled.

    Standing or Static water level readingsshould be taken when the pump has beenstopped for a sufwater level to return to normal.

    Pumping Level and Drawdown readingsare taken after the pump has been operatingagainst normal head for a su cient period oftime for the water level to remain stationary.

    The air line may be copper, plastic orgalvanised steel pipe and should be securelyfastened to the column pipe at regular intervalsto prevent slipping during installation of thecolumn.

    To use an airline, it is necessary to knowthe exact length of the line.

    During pump assembly the lower end ofthe air line should be attached to the pumpapproximately 1 metre above the pump suctionstrainer, as illustrated, and the overall length

    .

    g

    air line charging valve mounted to dischargehead. All joints must be completely air tightand should be sealed with pipe jointingcompound.

    To operate the air line gauge pump air intothe system until the maximum reading isreached. The gauge will return to and hold apressure reading (kPa) from where the waterlevel can be calculated using the followingformula.

    Depth H metres = L 0.102 P 1Depth of Water J = 0.102 P + 1(P = Pressure Gauge Reading in kPa)

    Centre line ofPump Discharge

    WaterLevel

    Top of Strainer

    Approx.1

    metre

    H

    J

    L

  • 8NON-REVERSE RATCHET

    Eve ow turbine pump drive heads are tted as standard with non-reverse ratchets to prevent thereceding column of water in the column pipe from driving the pump in the reverse direction whenthe pump unit is stopped. At deep settings high reverse pump speeds can be attained, which cancause serious damage to the equipment through column pipe or shaft couplings unscrewing orbearings burning out.

    Non-reverse ratchet should be used on all electric motor installations as the motor is free to runin the reverse direction once it is switched of f.

    For right angle gear drive heads the non-reverse ratchet is required when engine driven via aclutch. When engine drive has no clutch the ratchet pins should be removed from the drive head assome engines kick back when stopped.

    PUMP ASSEMBLY PROCEDURE

    Tshaft to the dimension in the table(page 9). Slip the collet withsmaller diameter down, over the shaft and into the impeller hubopening. Use a screwdriver blade or wedge tool in collet slot toallow sliding on shaft, and drive collet into place with several sharpblows using the collet driver. On new components the collet willproject above impeller hub from 0 to 3 mm. On previously assembledunits the collet may drive further into the impeller hub.

    Slide bottom bearing sand cap onto shaft from bottom, smallend up. Do not Lock setscrews. Slide suction case onto shaft from

    cap over inlet case bushing projection, slide inlet case o shaft case,

    insert bolt through suction case grease hole and screw intotapping in bottom of shaft. Tighten securely using washers

    sealingdiameter.

    Slide intermediate bowl onto shaft from top and bolt orscrew into section case. Slip next impeller over shaft and

    eas before.

    Loosen tie down bolt in bottom of shaft after each impelleris set to check that shaft and impellers rotate freely. Alsocheck lateral movement by sliding shaft with impellers allthe way in and out to be sure of adequate end play (refer toShaft and Impeller Running Clearances Table).

    Top bowl has

    into bowl when assembled to top of pump. Fit discharge casecap onto shaft and screw into position in discharge case.Fit pump shaft coupling so that end of shaft is in middle ofcoupling. Check again for free shaft rotation and adequateend movement. Remove grease plug from suction case and

    The pump is now ready for installation.

    IMPELLERCOLLETDRIVER

    PUMPSHAFT

    IMPELLERLOCKINGCOLLET

    IMPELLER

    IMPELLER COLLETDRIVER

    PUMP SHAFT

    IMPELLER LOCKINGCOLLET

    IMPELLER

    INTERMEDIATEBOWL

    ASSEMBLEDIMPELLER

    SUCTION CASE

    BOLT SCREWEDINT O SHAFT(W ashers as required)GREASE PLUG (Removed)

  • 9IMPELLERCOLLETDRIVER

    PUMPSHAFT

    IMPELLERLOCKINGCOLLET

    IMPELLER

    F G H D

    E

    A

    B BC C1 x 45 Chamfer

    1 x 45 Chamfer

    C Diam.

    LFirst Stage

    ShaftLength

    BStage

    Length

    ATo End of

    Seal Surface

    Pump Shaft A B C D E F G HDiam. mm mm mm mm mm mm mm mm

    25.4 mm (1) 130 25 8 58 48 35 25.80 32.3031.75mm (1-1/4) 150 30 10 65 55 42 32.15 39.6038.1mm (1-1/2) 180 35 10 75 68 53 38.60 49.2044.4 mm (1-3/4) 180 35 10 82 70 59 45.00 55.8050.8 mm (2) 200 40 12 90 80 64 51.40 60.80

    PUMP DISASSEMBLY PROCEDURERemove shaft coupling and unscrew discharge case cap

    from discharge case. Discharge case and top bowl need notbe separated for pump disassembly but can be treated as onepart. Remove top bowl. Slip collet driver onto shaft from top,pull shaft out as far as possible so that impellers are well of fseats, and knock impeller of f collet (see illustration). Use screwdriver to spread collet and side o shaft. Continue dismantlingprocedure down to suction case using reversal of assemblyprocedure.

    IMPELLERCOLLETDRIVER

    DIMENSIONS

    Pump A B C L150R 130 130 25.4 590180R 130 150 31.75 725200F 160 180 31.75 810250R 175 212 38.1 930250F 230 222 44.4 990300F 203 280 50.8 1040

    IMPELLER LOCATION TABLE

  • 10

    SHAFT AND IMPELLER RUNNING CLEARANCES(mm)

    Pump Impeller Bowl Diam. Lateral Impeller Shaft & BearingSkirt O/D Bore I/D Clearance Movement K Factor Clearance

    Min. Max. Min. Max. Min. Max. Min. Max.150R 79.05 79.07 79.38 79.43 0.31 0.38 8 4.67 0.10 0.15180R 107.57 107.62 107.95 108.00 0.33 0.43 16 7.90 0.15 0.25200F 126.62 126.67 127.00 127.05 0.33 0.43 17 11.8 0.15 0.25250R 132.94 133.00 133.35 133.40 0.35 0.46 10 12.4 0.15 0.25250F 167.87 167.92 168.27 168.33 0.35 0.46 10 20.7 0.18 0.28300F 183.72 183.77 184.15 184.20 0.38 0.48 11 24.5 0.18 0.28

  • Problem Cause Action

    Pump Shaft Hard to T urn Head nut Check nut adjustmentImpeller or intake blocked Unblock as necessaryRubber Bearings Dry Lubricate bearingsMisalignment in Pump Check dimensions

    Pump will not start Motor wired in reverse Check motor directionBlown fuses Replace fusesSupply fault Check supplyStarter fault Check starter

    No Flow Pump Running in Reverse Check motor directionShaft coupling disconnected Connect couplingShaft broken Replace shaftSpeed too low Increase speedTotal lift too high Check water levelWater Level Too low Raise water level to min

    Low Flow InsuTotal lift too high Check total liftSpeed too low Increase speedInlet Blocked Unblock inletLeaks in column or pipe Check for leaksValve partially closed Open valve

    Power excessive Impeller rubbing Check settingMotor fault Check motorLift too high Check water level

    Pump vibration Worn bearings Replace bearingsMotor out of balance Overhaul motorDrive coupling misaligned Check couplingPump sucking air Check pipe connectionsSpeed incorrect Operate at correct speed

    Excessive wear d Check screeningBent shafting Replace shaftFluid is corrosive Revise materialsMisalignment in Pump Check alignmentIncorrect lubrication Check lubrication

    Excessive Noise Faulty bearings in motor or Replace bearingsthrust assemblyMisalignment in Pump Check alignmentIncorrect lubrication Check lubrication

    11