ese seminar 25 september 2008
DESCRIPTION
ATLAS Upgrade for SLHC. ESE Seminar 25 September 2008. Philippe Farthouat, CERN. Content: LHC upgrade plans Detector upgrade (except tracker) Electronics upgrade Tracker upgrade Upgrade organisation CERN participation. LHC Evolution – Phase 1. - PowerPoint PPT PresentationTRANSCRIPT
ESE Seminar 25 September 2008
Philippe Farthouat, CERN
ATLAS Upgrade for SLHC
Ph. Farthouat ESE Seminar 25 September 2008 Slide 2
• Content: LHC upgrade plans Detector upgrade (except tracker) Electronics upgrade Tracker upgrade Upgrade organisation CERN participation
Ph. Farthouat ESE Seminar 25 September 2008 Slide 3
• LHC is complete apart from full collimation– Limited to 40 % of nominal for protection until collimators installed– Collimators to be completed in 2010/11 shutdown, allowing rise to ~nominal
luminosity of 1034 cm-2 s-1
– Best current estimate is that one nominal year will deliver 60 fb-1
• Phase-1: 2013-2016– Linac-4
• Approved and work has started; higher brightness– Allows higher LHC current, to “Ultimate” which is 2.3 times nominal
• Ready to run in 2013– New Inner Triplet focusing magnets
• Use spare super-conductor from LHC magnets• Larger aperture, allows * of 0.25 m instead of 0.55 m• Install in 2012/13 shutdown• In principle also gives factor 2 on nominal
– Expectation is that these two improvements will allow a ramp-up to 3 x nominal; Conditions: 70 minimum bias events per BC; ~700 fb-1 before phase 2
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
LHC Evolution – Phase 1
Ph. Farthouat ESE Seminar 25 September 2008 Slide 4
• Several ideas being explored to see the best way to achieve10 x nominal in 2017
• Injector improvements – higher current, higher reliability, shorter fill time
• New machine elements and ideas:– Magnets inside the experiments for “Early Separation” schemes– Crab cavities– Wire correctors– Luminosity Leveling
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
LHC Evolution – Phase 2
Ph. Farthouat ESE Seminar 25 September 2008 Slide 5
• Details in the presentation of Roland Garoby during the LHCC of July 1st, 2008– http://indico.cern.ch/conferenceDisplay.py?confId=36149
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
LHC Evolution – Injectors
Ph. Farthouat ESE Seminar 25 September 2008 Slide 6
• 50 ns scheme gives always more events per crossing – high pileup
• 25 ns also high: – low machine fill means short spill but
fill time the same– needs very high peak luminosity
(15 x nominal) for same integrated luminosity as 50 ns
• Leveling luminosity– Investigate (de-)tuning *, vary
crabbing, or bunch length to have fixed intensity throughout spill
– Win-win: it turns out these schemes can allow a higher machine fill
• Higher integrated luminosity• Very interesting to the experiments
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
SLHC Luminosity
Ph. Farthouat ESE Seminar 25 September 2008 Slide 7
• LHC, ATLAS and CMS agreed to use this as basis for all planning– Approved at LHCC meeting 1 July 2008
• Sets the conditions and timescale– Phase 1 starts with 6 – 8 month shutdown end 2012
• Peak luminosity 3 x 10-34 cm-2 s-1 at end of phase 1– Phase 2 will start with an 18 month shutdown at end of 2016
• Peak 10 x 10-34 cm-2 s-1 in phase 2– 3000 fb-1 integrated luminosity lifetime of detectors minimum in phase 2
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
Anticipated Peak and Integrated Luminosity
Ph. Farthouat ESE Seminar 25 September 2008 Slide 8
• 300 – 400 pile-up events at start of spill (unless luminosity levelling)
• Want to survive at least 3000 fb-1 data taking• B-layer at 37 mm:
– ~30 tracks per cm-2 per bunch crossing – >1016 1 MeV n-equivalent non-ionising – Few 10’s of MGray
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
What are the conditions at sLHC?
CMS event
Ph. Farthouat ESE Seminar 25 September 2008 Slide 9
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
Phase 1
• Limited time for installation – 6 to 8 months in 2012/13 shutdown• Small increase in peak rate above previous estimates (2 --> 3 x 1034)• Total integrated luminosity similar to previous expectations ~700 fb-1
– Limited changes needed• Pixel B-layer to be replaced
– In fact the replacement would take more than a year– A new B-layer will be put inside the current detector, along with a new
smaller diameter beam pipe• TDAQ
– TDAQ will be continuously upgraded to cope with rates and take advantage of new processing power
– Level-1 trigger might need some improvement such as the introduction of topological triggers
• The Central Trigger Processor would be affected (CERN involvement)• Fast track finding might be introduced to speed up Level-2
Ph. Farthouat ESE Seminar 25 September 2008 Slide 10
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
Phase 2 - SLHC
Parts of muon system
Forward calorimeter
Complete Inner detector
Interface to machine:• Beam Pipe• Shielding
• Possible machine magnets inside
Ph. Farthouat ESE Seminar 25 September 2008 Slide 11
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
Beam Pipe & Shielding
• Currently central part of ATLAS beam pipe is Be, rest is Stainless Steel– SS gives large backgrounds, especially to muon system
• SS gets activated Access problems for maintenance– Change to Al in ~2009– Change to all Be for SLHC– Be is expensive compared to SS, but cheap compared to muon chambers!– It gives a big reduction in background in critical areas of muon system
• A factor 2 or better• Shielding
– Already highly optimised, only small improvements possible
Ph. Farthouat ESE Seminar 25 September 2008 Slide 12
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
Muon Spectrometer • Hit rate might be too high in some
places• Large uncertainty on the
background rate– Need to wait for first beam before
knowing what the real rate is – Current detector done with some
safety factor on the simulated hit rate
– If at low end and a complete Be beam pipe in place, the precision chambers can remain
• Replacement or adaptation of the current readout electronics might be needed (see later)
• On going R&D– Micromegas for both tracking and
trigger (CERN involvement) – Thin MDT– TGC for both tracking and trigger
Ph. Farthouat ESE Seminar 25 September 2008 Slide 13
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
Calorimeters
HEC electronics
FCAL
• EM calorimeter should work even with high pile up– Adaptation of the digital filters in the back-
end electronics– Front-end electronics might require some
changes• Detecting elements of the Tile calorimeter
do not need replacement– However electronics does (see later)
• HEC front-end electronics in the cryostat. If a replacement is needed (because of radiation level) it will imply a major work
• Forward calorimeters need some adaptation because the liquid argon might boil…
Ph. Farthouat ESE Seminar 25 September 2008 Slide 14
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
Main topics
• General concern for the electronics in the cavern• Level-1 trigger• Muon readout electronics• Calorimeters readout electronics• New readout electronics for the tracker
Ph. Farthouat ESE Seminar 25 September 2008 Slide 15
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
General concerns
• The electronics installed in the cavern will be affected by the higher level of radiation
• ATLAS rules defined safety factors for the radiation tolerance of the electronics– Don’t know yet if we are on the safe side or not– Major upgrades could be required if not
• Power supplies• FE electronics of the calorimeters and muon chambers• Control devices (ELMBs)
– Wait for the beam for final assessment• A substantial fraction of the front-end electronics will be obsolete at the time of
SLHC– Could need a replacement in case of high level of failure
• R&D starting to be ready in case
Ph. Farthouat ESE Seminar 25 September 2008 Slide 16
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
Level-1 Trigger
• More complexe algorithms needed – For instance, currently level-1 calorimeter only performs object
counting– So far no need for tracking in level-1 although it might change
• Can both the latency and the L1A rate be maintained at their current values (2.5 µs and 75-100 kHz)?• Latency very likely to increase
• Very much linked to what will happen to readout systems of the calorimeters and muon chambers
• Intermediate upgrade for Phase-1
Ph. Farthouat ESE Seminar 25 September 2008 Slide 17
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
Muon chambers readout
• For high rates– Upgrade the TDC
Or– Selective readout based on
level-1 (CSM Upgrade)
• Possible new chambers (Micromegas, TGC, …) will require specific electronics
Ph. Farthouat ESE Seminar 25 September 2008 Slide 18
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
Calorimeters readout
• Additional radiation tests of the front-end electronics needed when LHC background known
• Both Lar and Tile calorimeters are looking at a new front-end system reading out everything at BC rate– Large dynamic range (14-16 bits) ADC @ 40 MHz– High data throughput
• Lar 1600 FE boards, each of them delivering 100 Gbits/s– Backend electronics for readout and level-1 trigger
• High bandwidth backplane (ATCA,…) – A bit brute force but allows very high flexibility for the trigger
Ph. Farthouat ESE Seminar 25 September 2008 Slide 19
Detector layout Readout Detector Control Power Services Schedule On-going developments
• On-going work in the collaboration, still far from being finalised
• Mainly presentation of the strips detector• A lot of what is presented here is very likely to be inaccurate
or even wrong
LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade
Content
Ph. Farthouat ESE Seminar 25 September 2008 Slide 20
Straw man Layout
Detector Readout DCS Power Services Schedule Developments Summary
All silicon detector to replace the current pixel, SCT and TRT: - pixels, - short strips (2.5cm) - long strips (10cm)
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Ph. Farthouat ESE Seminar 25 September 2008 Slide 21
Environmental parameters
Detector Readout DCS Power Services Schedule Developments Summary
Radius in cm Dose in kGy5.05 15800
12.25 254029.9 76051.4 45043.9 300108 70
TID
NIEL
1014
1015
1016
Radiation for 3000 fb-1
• Running up to 3000 fb-1
– Design for 6000 fb-1
– Should take about 6 years (?) hadron rate for SEE• Detector temperature ~-30oC• Magnetic Field ~2T
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Ph. Farthouat ESE Seminar 25 September 2008 Slide 22
Developments for Pixels
• Sensors– 3D Si (Parker, Da Via et al)– Thin silicon + 3D interconnects (Nisius
et al)– Gas over thin pixel (GOSSIP) (van de
Graaf et al)– Diamond pixels (Kagan et al)
• Front-end electronics IC– Willing to have chips 4 times larger as
current one and pixel size 2 times smaller (50 x 250 µm)
– ~22000 channels/chip– Development in 130nm CMOS
technology for B-layer replacement
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Ph. Farthouat ESE Seminar 25 September 2008 Slide 23
Stave concept for strips
Detector Readout DCS Power Services Schedule Developments Summary
• Modules on fully integrated staves– Double sided– 1 to 2-m long
• LS modules 10 x 10 cm2; 1280 strips (10-cm long, 80 µm pitch)• SS modules 10 x 10 cm2; 5120 strips (2.5-cm long, 80 µm pitch)
10 cm
1 to 2 m
Bus cable
Hybrids Coolant tube structure
Carbon honeycomb or foam
Carbon fiberfacing
Readout IC’s
Silicon sensors
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Ph. Farthouat ESE Seminar 25 September 2008 Slide 24
Long Strip Cylinders (4 meter length)
Short Strip Cylinders (2 meter length)
Strips Detector in numbers
Detector Readout DCS Power Services Schedule Developments Summary
Layer Type Radius
[cm]Phi
segmentation
Modules per half single sided
stave
128-ch FEIC per half single sided
stave0 Short Strips 38 28 10 4001 Short Strips 49 36 10 4002 Short Strips 60 44 10 4003 Long Strips 75 56 19 1904 Long Strips 95 72 19 190
23614,336
270,0801,15257,088327,168
41,877,504Total number of 128-channel FEICs
Total amount of channels
Endcap
Barrel
Total number of staves for the Barrel
Total number of FEIC for the BarrelTotal number of staves for one End-cap
Total number of 128-ch FEIC for the two End-cap
Total number of modules for the Barrel
• Current SCT detector– 4088 modules– 49k 128-channel FEIC– 6.3M channels
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Ph. Farthouat ESE Seminar 25 September 2008 Slide 25
Working Assumptions
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
• Binary readout as in the current detector– 1 hit = 1 bit
• L1A rate unchanged (?) and L1 latency increased
• Read-out architecture as identical as possible for the strips and the pixels– Avoid extra design diversity – Share as much as possible design
efforts and costs – From the front-end electronics up the
off-detector electronics• Material budget is a key element for
the upgraded tracker – Solutions minimising the amount of
material always preferred
• Extremely harsh radiation environment for the front-end electronics– High level of single event upsets
expected.– Read-out architecture as simple as
possible; complex tasks such as partial event building, data integrity check, etc. to be avoided
• Amount of services connected to the tracker to be kept as low as possible– To maintain an overall low material
budget – Available volume for services routing
severely limited
Ph. Farthouat ESE Seminar 25 September 2008 Slide 26
Readout Organisation
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Generic readout model
• In the current detector the readout unit is the module– Large number of low speed
readout links– Large number of power supply
lines• Not affordable for the upgrade
• Hierarchical readout scheme– FEIC– Module controller– Stave controller (GBT) – Low number of high speed links
Ph. Farthouat ESE Seminar 25 September 2008 Slide 27
Readout Organisation (Barrel Strips)
Detector Readout DCS Power Services Schedule Developments Summary
Service bus
TTC, Data
( & DCS)
fibers
PS cable
DCS env. IN
Cooling In
Opto
SC
DCS
interlock
SC Hybrid
Module #1 Module #2 Module #10
Cooling Out
(DCS link)
MC
F
E
I
C
s
• Half single sided stave as a readout unit• Readout hybrids as sub-elements
– 2 hybrids with 20 FEICs per module for SS– 1 hybrid with 10 FEICs per module for LS
Short Strip Single Sided Half Stave
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Ph. Farthouat ESE Seminar 25 September 2008 Slide 28
Quantity of Data
Detector Readout DCS Power Services Schedule Developments Summary
Event size for a short strips module (40 128-channel FEICs). Current ATLAS SCT detector coding scheme
Mean size ~1600 bits
0 hit 41%1 cluster 34% >1 clusters 21%
Number of hits per FEIC
Simulation for worst case scenario:1035 cm-2 luminosity 50 ns BC period (400 overlapping events per BC)Short Strips
A. Weidberg etal.
A. Weidberg etal.
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Ph. Farthouat ESE Seminar 25 September 2008 Slide 29
Data Rates
Detector Readout DCS Power Services Schedule Developments Summary
• Long strips and short strips are well balanced – 400 versus 380 FEIC
• Numbers without so much safety margin– Detector layout very likely to change
– L1A rate could increase– Luminosity could increase– Data format might change
• Pixel will require more bandwidth• Better design for more x2
Service bus
TTC, Data
( & DCS)
fibers
PS cable
DCS env. IN
Cooling In
Opto
SC
DCS
interlock
SC Hybrid
Module #1 Module #2 Module #10
Cooling Out
(DCS link)
MC
F
E
I
C
s
1600 bits/event100kHz L1 rate
160 Mbits/s
800 bits/event100kHz L1 rate
80 Mbits/s 1.6 Gbits/s (20 * 80 Mbits/s) 1.6 Gbits/s
160 Mbits/s
3.2 Gbits/s 3.2 Gbits/s
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Ph. Farthouat ESE Seminar 25 September 2008 Slide 30
Data Links
Detector Readout DCS Power Services Schedule Developments Summary
• FEICs to MC– Electrical, 160 Mbits/s
• MC to SC (GBT)– Electrical, 160 Mbits/s – Up to 20 links per half single sided SS stave
• DC balanced code mandatory if serial powering is used, desirable in all cases
• On-going work to assess what is achievable at different places
• Optical links at >3.2 Gbits/s– Rely on the versatile link project
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Ph. Farthouat ESE Seminar 25 September 2008 Slide 31
TTC Links
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
• The TTC links are used to transmit to the front-end:– A clock synchronised with the beam (either the LHC clock or a multiple of it)– The L1A– Synchronous commands such as the bunch counter reset (BCR) or the event counter
reset (ECR)– Control data to be stored in the FEICs, MCs and SMCs (e.g. threshold, masks, …)
• Unidirectional links to minimise the number of lines– To read a register, command transmitted on TTC link, data transmitted on the read-out
data link • TTC links bandwidth dictated by :
– Clock frequency to be transmitted• Might be better to transmit a clock at higher frequency than the BC to be used directly by the
readout logic (e.g. 160 Mhz if reading out at 160 Mbits/s. Avoid some PLL) – Necessity to transmit simultaneously the L1A and commands (e.g. Bunch Counter Reset)– Need for forward error correction to fight SEUs– Need for DC balanced codes and self clock recovery protocols
• Bandwidth greater than or equal to 80 Mbits/s
Ph. Farthouat ESE Seminar 25 September 2008 Slide 32
Electrical Links
Detector Readout DCS Power Services Schedule Developments Summary
• Protocols not defined– Clock and data separated versus single encoded link– Several low speed links versus a single high speed– Multi-drop or point-to-point
• A few pictures of some promising tests
80 Mbits/s on an hybrid with 10 and 20 FEICs
A. Greenall
320 Mbits/s on a 60-cm Kapton tape with 4 loads
V. Fadeyev
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Ph. Farthouat ESE Seminar 25 September 2008 Slide 33
Need for Redundancy?
Detector Readout DCS Power Services Schedule Developments Summary
• Redundancy has a lot of impact on the readout architecture– Possible schemes for redundancy on the hybrids shown– Full redundancy required for the optical links (?)
• Difficult to implement redundancy without increasing the number of ASICs or the amount of services
• Some work necessary to assess the needs– Impact of loosing a FEIC, a readout hybrid, a half single sided stave– Define the maximum losses allowed within the life time– Define the minimum reliability level needed to be better after the life time of the
experiment
altMC
10 FEICs
MC
To SMC
One failing FEIC: one of the 160-Mbits/s link Is reading-out more than 10 FEICs
Ext
ra D
ata
Pat
hfo
r rev
erse
dire
ctio
n
160-
320
Mbi
ts/s
10 FEICs
X160 Mbits/s
160 Mbits/s
altMC
10 FEICs
MC
To SMC
Normal data flow: each 160-Mbits/s link reads out 10 FEICs
160-
320
Mbi
ts/s
10 FEICs
160 Mbits/s
160 Mbits/s
Unu
sed
Dat
a P
ath
Ext
ra D
ata
Pat
hfo
r rev
erse
dire
ctio
n
altMC
MC
To SMC
Normal data flow: each 80-Mbits/s link reads out 5 FEICs
160-
320
Mbi
ts/s
2 x 5 FEICs
80 Mbits/s
Unu
sed
Dat
a P
ath
2 x 5 FEICs
Unu
sed
Dat
a P
ath
80 Mbits/s
altMC
MC
To SMC
One failing FEIC: one of the 80-Mbits/s link Is reading-out more than 5 FEICs
160-
320
Mbi
ts/s
2 x 5 FEICs
80 Mbits/s
2 x 5 FEICs
Unu
sed
Dat
a P
ath
80 Mbits/s
X
Possible redundancy schemes to cope with the loss of a FEIC or of a Module Controller
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Ph. Farthouat ESE Seminar 25 September 2008 Slide 34
Data Format
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
• Data format used in the current detector is highly optimised in size– Necessary to look at each single bit to
know what it is and what is following and requires synchronisation between FEICs
• “On the fly” event building and decoding• Might be a problem when a large
amount of SEU are expected• Could be better to consider the system
as a network and to push packets of data from the FEIC up to off-detector electronics
• Pros and cons– Enough to only protect the headers
against errors• Data unprotected
– No synchronisation expected in the data transmission in the FE
• System cannot hang– More complex task in the off-detector
electronics• A lot of resources available in big FPGA
– Extra data volume• To be simulated
Stave ID Module ID Chip ID Data TypeData L1ID BCID DataDCS Sensor1 Sensor2 …Register Register # Data ……
Payload
Ph. Farthouat ESE Seminar 25 September 2008 Slide 35
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
• In the current detector, a lot of direct connections of sensors – Not applicable for the upgrade
• A lot of discussions concerning the need for a fully separated DCS system– Separately powered and separate communications– Separate ASICs– Additional services….
• Still possible to run safely the detector even with the DCS integrated in the readout
Integrated with the readout or separated?
Ph. Farthouat ESE Seminar 25 September 2008 Slide 36
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Mode of Operation
• A few sensors directly connected – Used also for interlock
• Powering sequentially the different components only when it is safe to do so– Note that it is easy to do with DC-DC converters but may be less with serial power
• DCS functionalities in the module controllers and the stave controllers• Separation of the DCS data and the readout data in the off-detector
electronics– Does not require the DAQ to work
Service bus
TTC, Data
( & DCS)
fibers
PS cable
DCS env. IN
Cooling In
Opto
SC
DCS
interlock
SC Hybrid
Module #1 Module #2 Module #10
Cooling Out
(DCS link)
MC
F
E
I
C
s
Humidity sensorTemperature
sensors (cooling pipes and Stave
Controller)
Ph. Farthouat ESE Seminar 25 September 2008 Slide 37
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
Total Power for the Strips
• Assumptions:– Pessimistic 1.5mW [1mW] per channel for the strip FEIC and 1.3V Vdd – 150mA [100mA] per 128-channel FEIC.
• Total current (for the barrel and both end-caps): 48.5kA [33kA] • 80% efficiency of front-end power devices would lead to 78.5kW
[52kW] dissipated in the tracker volume– 70% efficiency would lead to 90kW [60kW]
• Current SCT and TRT detectors are fed with about 12kA • Assuming the amount of services cannot be increased, the powering
scheme to be used must limit the amount of current to be fed at that level – That’s about 1/6th (1/5th) of the current needed by the front-end
electronics. Hence either a factor 5 to 6 (at least) DC-DC conversion or a serial powering scheme of at least 5 to 6 modules has to be used.
Ph. Farthouat ESE Seminar 25 September 2008 Slide 38
DC-DC or Serial Power
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
• Developments are on-going: serial powering and DC-DC conversion– Cf last ESE seminar (Federicco) and the presentations during TWEPP08
• Reducing the current to be fed by a factor of 5-to-10 minimum is reachable with both solutions
• DC-DC converters offer some interesting flexibility– Can separate different supplies easily
• Analog – digital saving in overall power• Stave controller, module controller and FEICs capability of controlling the
operation– Radiation hardness not solved
• Serial powering scheme has some system issues which are being tackled
• Options to be kept opened for a while• Real estate is an important issue for both solutions
Ph. Farthouat ESE Seminar 25 September 2008 Slide 39
Space available for the power devices
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
• Readout hybrid with 20 FEIC (ABCn 0.25 device)• Not so much space for the power devices and the module
controller…
A module could look like…
SensorDigital I / O
Power, DCS, HV
TTC (multi- drop LVDS)
Data Links (point- to- point LVDS)
100mmBus cable From A. Greenall
Ph. Farthouat ESE Seminar 25 September 2008 Slide 40
Rough Estimate
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
DC-DC SerialNo
redundancyFull
redundancy
One HV per
module
One HV for 2 modules
Half single sided short strips stave
2 wires 8-mm2
copper + shield (total cross-
section of the cable 138 mm2)
2 wires 4-mm2
copper + shield (total cross-
section of the cable 89 mm2)
12 twp (cross-section
1.57 mm2)
15 twp (cross-section
1.57 mm2)
2 fibres (cross-
section 1.57 mm2)
4 fibres (cross-
section 1.57 mm2)
10 (cross-section
1.73 mm2)
5 (cross-section 1.73
mm2)
Half single sided long strips stave
2 wires 4-mm2
copper + shield (total cross-
section of the cable 89 mm2)
2 wires 2-mm2
copper + shield (total cross-
section of the cable 60 mm2)
12 twp 15 twp 2 fibres 4 fibres19 (cross-
section 1.73 mm2)
10 (cross-section 1.73
mm2)
Total cross-section [cm2]
1052 692 89 111 15 30 243 126
Min total [cm2] 922Max total [cm2] 1436
1.54-cm thickness at R=95cm. 75% LV, 9.5% DCS, 13.5% HV, 2% Fibres2.41-cm thickness at R=95cm. 73% LV, 8% DCS, 17% HV, 2% Fibres
LV Fibres
DCS min DCS max
HV
• Services for the barrel strips at the entrance of the tracker volume– 1 mW/ch– DC-DC or serial power introduces a factor
10 saving on the current
– 2-V drop max– Packing factor of 2
LV is still the dominant part by far
Ph. Farthouat ESE Seminar 25 September 2008 Slide 41
Total Fantasy ?
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
• LoI, TP and TDR in 2009, 2010 and 2011
• LHC stop: October 2016• SLHC start: Spring 2018• Tracker installation: January
2017 (?)• Stave assembly start:
January 2013 (?)• Very little time left for fully
specifying the components
and designing them• Choice of technology to be
used (130nm or 90nm or lower) as late as possible– Most of the work done in
130nm so far– Some early work with 90nm (or
lower) necessary to be able to make the decision in due time
• Analogue performances• Radiation hardness
Ph. Farthouat ESE Seminar 25 September 2008 Slide 42
Total Fantasy? (cont)
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
• Architecture definition complete with options Nov-08• Decision on options (powering, electrical links, opto) Dec-09• Component specifications complete Feb-10
• Prototype sensitive blocks (design, MWP fab, test) Sep-08 to Dec-09• Prototype complete component design, fab and test Feb-10 to Aug-11• Stave assembly & test (system test of electronics) Aug-11 to Feb-13
• Pre-production component design, fab and test Feb-12 to Feb-13• Pre-production stave assembly & system test Feb-13 to Jul-13
• Production Readiness Review Aug-13• Component Production
– First production wafer batch (fab and test) Aug-13 to Feb-14
– Deliver first production batch to module assembly sites Feb-14– Start component series fabrication Sep-13
(Assumes no design change from pre-production)– Start of component series delivery to assembly sites Apr-14
No contra
ctual value!
Ph. Farthouat ESE Seminar 25 September 2008 Slide 43
ASICs developments and specifications
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
• Working document on architecture available since about a year– Reviewed and presented to the collaboration
• Two working groups in place to try and define more precisely the specifications of the different components. One for the pixels and one for the strips– Inputs to the “common projects” teams (e.g. GBT)– ~350k FEIC but only ~20k MC and ~5k SC(GBT)
• ABCn 0.25 chip as test vehicule for sensor studies– Also contains some features for testing different power schemes and
readout speeds• Preliminary study of the front-end part (preamplifier-shaper-
discriminator) in 0.13– Very good power performances: <200µW per channel – See J. Kaplon’s presentation during the TWEPP workshop
• Evaluation of SiGe
Ph. Farthouat ESE Seminar 25 September 2008 Slide 44
Fixed Barrel Length
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
• SS longer more modules more data (+20%)• LS shorter less modules and less data
Ph. Farthouat ESE Seminar 25 September 2008 Slide 45
Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary
• The readout architecture of the ATLAS upgraded tracker has to be different from the current one
• Detector organised in staves. Hierarchical readout following this segmentation– Fewer but higher speed links
• Some elements of the readout are not to be produced in very high quantity– Points towards common solutions with CMS and others
• Power distribution requires special efforts to maintain reasonable services– Saving factor 5 - 10 on the current
• Schedule looks uneasy– Not so much time for the electronics development– Decision on technology to be used for the FE electronics at the latest in 2012
Ph. Farthouat ESE Seminar 25 September 2008 Slide 46
• Two major coordination bodies– Develop a realistic and coherent
upgrade plan– Steer R&D activities– Cover engineering aspects from the
beginning
• Upgrade Steering Group (USG)– Representatives from systems,
software, physics and technical coordination
• Project Office– Part of the technical coordination– Project Office should technically guide
the upgrade activities• Conceptual design and R&D• Prototyping• Pre-series and construction• Installation and commissioning
• Upgrade addressed during each ATLAS overview week and during dedicated workshops– Several devoted to the tracker
Upgrade Organisation CERN Involvement
Ref: https://edms.cern.ch/file/690177/1/Upgrade_Org_PO.docIndico pages:
http://indico.cern.ch/categoryDisplay.py?categId=350
Ph. Farthouat ESE Seminar 25 September 2008 Slide 47
• Proposal made to the USG– Established lightweight review
procedure for approval
• Circulation to collaboration board– More groups joining?
• Second discussion in USG– Sufficient resources?
• Decision about recommendation by USG
• Review procedure during the lifetime of the project– Review office
• A number of proposals issued so far– <
https://edms.cern.ch/cedar/plsql/navigation.tree?cookie=7849675&p_top_id=1310970533&p_top_type=P>
• ATLAS welcome joint R&D activities with other experiments (CMS)– Versatile link and GBT– 130 nm or lower processes– Power distribution
Upgrade Organisation CERN Involvement
R&D Activities
Ph. Farthouat ESE Seminar 25 September 2008 Slide 48
• Technical coordination– PO engineering– Tracker engineering– Electronics coordination– Interface to machine (beam pipe and
shielding)• Level-1
– Central Trigger Processor upgrade for phase-1 and SLHC
• Si Strips– ABCnext design– Micro-electronics design and project
management– Tests and qualification of devices, modules
etc.– Could make a major contribution to the end-
cap• Would make sense to have also a strong
participation in the FE system
• Micromegas development and evaluation– Will need electronics
• Some interest of individuals here and there– e.g. in the back-end electronics of the
calorimeters• There is not today a clear picture of
where the CERN ATLAS Team will contribute – No MOU or alike defining yet the upgrade
activity– Still little specific funding available so far
• Rely on common projects– Versatile Link– GBT– Support for µelectronics– TTC upgrade – Power
Upgrade Organisation CERN Involvement