ese seminar 25 september 2008

48
ESE Seminar 25 September 2008 Philippe Farthouat, CERN ATLAS Upgrade for SLHC

Upload: trory

Post on 25-Feb-2016

66 views

Category:

Documents


4 download

DESCRIPTION

ATLAS Upgrade for SLHC. ESE Seminar 25 September 2008. Philippe Farthouat, CERN. Content: LHC upgrade plans Detector upgrade (except tracker) Electronics upgrade Tracker upgrade Upgrade organisation CERN participation. LHC Evolution – Phase 1. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ESE Seminar 25 September  2008

ESE Seminar 25 September 2008

Philippe Farthouat, CERN

ATLAS Upgrade for SLHC

Page 2: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 2

• Content: LHC upgrade plans Detector upgrade (except tracker) Electronics upgrade Tracker upgrade Upgrade organisation CERN participation

Page 3: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 3

• LHC is complete apart from full collimation– Limited to 40 % of nominal for protection until collimators installed– Collimators to be completed in 2010/11 shutdown, allowing rise to ~nominal

luminosity of 1034 cm-2 s-1

– Best current estimate is that one nominal year will deliver 60 fb-1

• Phase-1: 2013-2016– Linac-4

• Approved and work has started; higher brightness– Allows higher LHC current, to “Ultimate” which is 2.3 times nominal

• Ready to run in 2013– New Inner Triplet focusing magnets

• Use spare super-conductor from LHC magnets• Larger aperture, allows * of 0.25 m instead of 0.55 m• Install in 2012/13 shutdown• In principle also gives factor 2 on nominal

– Expectation is that these two improvements will allow a ramp-up to 3 x nominal; Conditions: 70 minimum bias events per BC; ~700 fb-1 before phase 2

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

LHC Evolution – Phase 1

Page 4: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 4

• Several ideas being explored to see the best way to achieve10 x nominal in 2017

• Injector improvements – higher current, higher reliability, shorter fill time

• New machine elements and ideas:– Magnets inside the experiments for “Early Separation” schemes– Crab cavities– Wire correctors– Luminosity Leveling

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

LHC Evolution – Phase 2

Page 5: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 5

• Details in the presentation of Roland Garoby during the LHCC of July 1st, 2008– http://indico.cern.ch/conferenceDisplay.py?confId=36149

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

LHC Evolution – Injectors

Page 6: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 6

• 50 ns scheme gives always more events per crossing – high pileup

• 25 ns also high: – low machine fill means short spill but

fill time the same– needs very high peak luminosity

(15 x nominal) for same integrated luminosity as 50 ns

• Leveling luminosity– Investigate (de-)tuning *, vary

crabbing, or bunch length to have fixed intensity throughout spill

– Win-win: it turns out these schemes can allow a higher machine fill

• Higher integrated luminosity• Very interesting to the experiments

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

SLHC Luminosity

Page 7: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 7

• LHC, ATLAS and CMS agreed to use this as basis for all planning– Approved at LHCC meeting 1 July 2008

• Sets the conditions and timescale– Phase 1 starts with 6 – 8 month shutdown end 2012

• Peak luminosity 3 x 10-34 cm-2 s-1 at end of phase 1– Phase 2 will start with an 18 month shutdown at end of 2016

• Peak 10 x 10-34 cm-2 s-1 in phase 2– 3000 fb-1 integrated luminosity lifetime of detectors minimum in phase 2

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

Anticipated Peak and Integrated Luminosity

Page 8: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 8

• 300 – 400 pile-up events at start of spill (unless luminosity levelling)

• Want to survive at least 3000 fb-1 data taking• B-layer at 37 mm:

– ~30 tracks per cm-2 per bunch crossing – >1016 1 MeV n-equivalent non-ionising – Few 10’s of MGray

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

What are the conditions at sLHC?

CMS event

Page 9: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 9

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

Phase 1

• Limited time for installation – 6 to 8 months in 2012/13 shutdown• Small increase in peak rate above previous estimates (2 --> 3 x 1034)• Total integrated luminosity similar to previous expectations ~700 fb-1

– Limited changes needed• Pixel B-layer to be replaced

– In fact the replacement would take more than a year– A new B-layer will be put inside the current detector, along with a new

smaller diameter beam pipe• TDAQ

– TDAQ will be continuously upgraded to cope with rates and take advantage of new processing power

– Level-1 trigger might need some improvement such as the introduction of topological triggers

• The Central Trigger Processor would be affected (CERN involvement)• Fast track finding might be introduced to speed up Level-2

Page 10: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 10

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

Phase 2 - SLHC

Parts of muon system

Forward calorimeter

Complete Inner detector

Interface to machine:• Beam Pipe• Shielding

• Possible machine magnets inside

Page 11: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 11

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

Beam Pipe & Shielding

• Currently central part of ATLAS beam pipe is Be, rest is Stainless Steel– SS gives large backgrounds, especially to muon system

• SS gets activated Access problems for maintenance– Change to Al in ~2009– Change to all Be for SLHC– Be is expensive compared to SS, but cheap compared to muon chambers!– It gives a big reduction in background in critical areas of muon system

• A factor 2 or better• Shielding

– Already highly optimised, only small improvements possible

Page 12: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 12

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

Muon Spectrometer • Hit rate might be too high in some

places• Large uncertainty on the

background rate– Need to wait for first beam before

knowing what the real rate is – Current detector done with some

safety factor on the simulated hit rate

– If at low end and a complete Be beam pipe in place, the precision chambers can remain

• Replacement or adaptation of the current readout electronics might be needed (see later)

• On going R&D– Micromegas for both tracking and

trigger (CERN involvement) – Thin MDT– TGC for both tracking and trigger

Page 13: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 13

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

Calorimeters

HEC electronics

FCAL

• EM calorimeter should work even with high pile up– Adaptation of the digital filters in the back-

end electronics– Front-end electronics might require some

changes• Detecting elements of the Tile calorimeter

do not need replacement– However electronics does (see later)

• HEC front-end electronics in the cryostat. If a replacement is needed (because of radiation level) it will imply a major work

• Forward calorimeters need some adaptation because the liquid argon might boil…

Page 14: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 14

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

Main topics

• General concern for the electronics in the cavern• Level-1 trigger• Muon readout electronics• Calorimeters readout electronics• New readout electronics for the tracker

Page 15: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 15

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

General concerns

• The electronics installed in the cavern will be affected by the higher level of radiation

• ATLAS rules defined safety factors for the radiation tolerance of the electronics– Don’t know yet if we are on the safe side or not– Major upgrades could be required if not

• Power supplies• FE electronics of the calorimeters and muon chambers• Control devices (ELMBs)

– Wait for the beam for final assessment• A substantial fraction of the front-end electronics will be obsolete at the time of

SLHC– Could need a replacement in case of high level of failure

• R&D starting to be ready in case

Page 16: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 16

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

Level-1 Trigger

• More complexe algorithms needed – For instance, currently level-1 calorimeter only performs object

counting– So far no need for tracking in level-1 although it might change

• Can both the latency and the L1A rate be maintained at their current values (2.5 µs and 75-100 kHz)?• Latency very likely to increase

• Very much linked to what will happen to readout systems of the calorimeters and muon chambers

• Intermediate upgrade for Phase-1

Page 17: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 17

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

Muon chambers readout

• For high rates– Upgrade the TDC

Or– Selective readout based on

level-1 (CSM Upgrade)

• Possible new chambers (Micromegas, TGC, …) will require specific electronics

Page 18: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 18

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

Calorimeters readout

• Additional radiation tests of the front-end electronics needed when LHC background known

• Both Lar and Tile calorimeters are looking at a new front-end system reading out everything at BC rate– Large dynamic range (14-16 bits) ADC @ 40 MHz– High data throughput

• Lar 1600 FE boards, each of them delivering 100 Gbits/s– Backend electronics for readout and level-1 trigger

• High bandwidth backplane (ATCA,…) – A bit brute force but allows very high flexibility for the trigger

Page 19: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 19

Detector layout Readout Detector Control Power Services Schedule On-going developments

• On-going work in the collaboration, still far from being finalised

• Mainly presentation of the strips detector• A lot of what is presented here is very likely to be inaccurate

or even wrong

LHC upgrades Detector upgrade Electronics upgrade Tracker upgrade

Content

Page 20: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 20

Straw man Layout

Detector Readout DCS Power Services Schedule Developments Summary

All silicon detector to replace the current pixel, SCT and TRT: - pixels, - short strips (2.5cm) - long strips (10cm)

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Page 21: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 21

Environmental parameters

Detector Readout DCS Power Services Schedule Developments Summary

Radius in cm Dose in kGy5.05 15800

12.25 254029.9 76051.4 45043.9 300108 70

TID

NIEL

1014

1015

1016

Radiation for 3000 fb-1

• Running up to 3000 fb-1

– Design for 6000 fb-1

– Should take about 6 years (?) hadron rate for SEE• Detector temperature ~-30oC• Magnetic Field ~2T

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Page 22: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 22

Developments for Pixels

• Sensors– 3D Si (Parker, Da Via et al)– Thin silicon + 3D interconnects (Nisius

et al)– Gas over thin pixel (GOSSIP) (van de

Graaf et al)– Diamond pixels (Kagan et al)

• Front-end electronics IC– Willing to have chips 4 times larger as

current one and pixel size 2 times smaller (50 x 250 µm)

– ~22000 channels/chip– Development in 130nm CMOS

technology for B-layer replacement

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Page 23: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 23

Stave concept for strips

Detector Readout DCS Power Services Schedule Developments Summary

• Modules on fully integrated staves– Double sided– 1 to 2-m long

• LS modules 10 x 10 cm2; 1280 strips (10-cm long, 80 µm pitch)• SS modules 10 x 10 cm2; 5120 strips (2.5-cm long, 80 µm pitch)

10 cm

1 to 2 m

Bus cable

Hybrids Coolant tube structure

Carbon honeycomb or foam

Carbon fiberfacing

Readout IC’s

Silicon sensors

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Page 24: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 24

Long Strip Cylinders (4 meter length)

Short Strip Cylinders (2 meter length)

Strips Detector in numbers

Detector Readout DCS Power Services Schedule Developments Summary

Layer Type Radius

[cm]Phi

segmentation

Modules per half single sided

stave

128-ch FEIC per half single sided

stave0 Short Strips 38 28 10 4001 Short Strips 49 36 10 4002 Short Strips 60 44 10 4003 Long Strips 75 56 19 1904 Long Strips 95 72 19 190

23614,336

270,0801,15257,088327,168

41,877,504Total number of 128-channel FEICs

Total amount of channels

Endcap

Barrel

Total number of staves for the Barrel

Total number of FEIC for the BarrelTotal number of staves for one End-cap

Total number of 128-ch FEIC for the two End-cap

Total number of modules for the Barrel

• Current SCT detector– 4088 modules– 49k 128-channel FEIC– 6.3M channels

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Page 25: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 25

Working Assumptions

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

• Binary readout as in the current detector– 1 hit = 1 bit

• L1A rate unchanged (?) and L1 latency increased

• Read-out architecture as identical as possible for the strips and the pixels– Avoid extra design diversity – Share as much as possible design

efforts and costs – From the front-end electronics up the

off-detector electronics• Material budget is a key element for

the upgraded tracker – Solutions minimising the amount of

material always preferred

• Extremely harsh radiation environment for the front-end electronics– High level of single event upsets

expected.– Read-out architecture as simple as

possible; complex tasks such as partial event building, data integrity check, etc. to be avoided

• Amount of services connected to the tracker to be kept as low as possible– To maintain an overall low material

budget – Available volume for services routing

severely limited

Page 26: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 26

Readout Organisation

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Generic readout model

• In the current detector the readout unit is the module– Large number of low speed

readout links– Large number of power supply

lines• Not affordable for the upgrade

• Hierarchical readout scheme– FEIC– Module controller– Stave controller (GBT) – Low number of high speed links

Page 27: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 27

Readout Organisation (Barrel Strips)

Detector Readout DCS Power Services Schedule Developments Summary

Service bus

TTC, Data

( & DCS)

fibers

PS cable

DCS env. IN

Cooling In

Opto

SC

DCS

interlock

SC Hybrid

Module #1 Module #2 Module #10

Cooling Out

(DCS link)

MC

F

E

I

C

s

• Half single sided stave as a readout unit• Readout hybrids as sub-elements

– 2 hybrids with 20 FEICs per module for SS– 1 hybrid with 10 FEICs per module for LS

Short Strip Single Sided Half Stave

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Page 28: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 28

Quantity of Data

Detector Readout DCS Power Services Schedule Developments Summary

Event size for a short strips module (40 128-channel FEICs). Current ATLAS SCT detector coding scheme

Mean size ~1600 bits

0 hit 41%1 cluster 34% >1 clusters 21%

Number of hits per FEIC

Simulation for worst case scenario:1035 cm-2 luminosity 50 ns BC period (400 overlapping events per BC)Short Strips

A. Weidberg etal.

A. Weidberg etal.

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Page 29: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 29

Data Rates

Detector Readout DCS Power Services Schedule Developments Summary

• Long strips and short strips are well balanced – 400 versus 380 FEIC

• Numbers without so much safety margin– Detector layout very likely to change

– L1A rate could increase– Luminosity could increase– Data format might change

• Pixel will require more bandwidth• Better design for more x2

Service bus

TTC, Data

( & DCS)

fibers

PS cable

DCS env. IN

Cooling In

Opto

SC

DCS

interlock

SC Hybrid

Module #1 Module #2 Module #10

Cooling Out

(DCS link)

MC

F

E

I

C

s

1600 bits/event100kHz L1 rate

160 Mbits/s

800 bits/event100kHz L1 rate

80 Mbits/s 1.6 Gbits/s (20 * 80 Mbits/s) 1.6 Gbits/s

160 Mbits/s

3.2 Gbits/s 3.2 Gbits/s

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Page 30: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 30

Data Links

Detector Readout DCS Power Services Schedule Developments Summary

• FEICs to MC– Electrical, 160 Mbits/s

• MC to SC (GBT)– Electrical, 160 Mbits/s – Up to 20 links per half single sided SS stave

• DC balanced code mandatory if serial powering is used, desirable in all cases

• On-going work to assess what is achievable at different places

• Optical links at >3.2 Gbits/s– Rely on the versatile link project

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Page 31: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 31

TTC Links

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

• The TTC links are used to transmit to the front-end:– A clock synchronised with the beam (either the LHC clock or a multiple of it)– The L1A– Synchronous commands such as the bunch counter reset (BCR) or the event counter

reset (ECR)– Control data to be stored in the FEICs, MCs and SMCs (e.g. threshold, masks, …)

• Unidirectional links to minimise the number of lines– To read a register, command transmitted on TTC link, data transmitted on the read-out

data link • TTC links bandwidth dictated by :

– Clock frequency to be transmitted• Might be better to transmit a clock at higher frequency than the BC to be used directly by the

readout logic (e.g. 160 Mhz if reading out at 160 Mbits/s. Avoid some PLL) – Necessity to transmit simultaneously the L1A and commands (e.g. Bunch Counter Reset)– Need for forward error correction to fight SEUs– Need for DC balanced codes and self clock recovery protocols

• Bandwidth greater than or equal to 80 Mbits/s

Page 32: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 32

Electrical Links

Detector Readout DCS Power Services Schedule Developments Summary

• Protocols not defined– Clock and data separated versus single encoded link– Several low speed links versus a single high speed– Multi-drop or point-to-point

• A few pictures of some promising tests

80 Mbits/s on an hybrid with 10 and 20 FEICs

A. Greenall

320 Mbits/s on a 60-cm Kapton tape with 4 loads

V. Fadeyev

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Page 33: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 33

Need for Redundancy?

Detector Readout DCS Power Services Schedule Developments Summary

• Redundancy has a lot of impact on the readout architecture– Possible schemes for redundancy on the hybrids shown– Full redundancy required for the optical links (?)

• Difficult to implement redundancy without increasing the number of ASICs or the amount of services

• Some work necessary to assess the needs– Impact of loosing a FEIC, a readout hybrid, a half single sided stave– Define the maximum losses allowed within the life time– Define the minimum reliability level needed to be better after the life time of the

experiment

altMC

10 FEICs

MC

To SMC

One failing FEIC: one of the 160-Mbits/s link Is reading-out more than 10 FEICs

Ext

ra D

ata

Pat

hfo

r rev

erse

dire

ctio

n

160-

320

Mbi

ts/s

10 FEICs

X160 Mbits/s

160 Mbits/s

altMC

10 FEICs

MC

To SMC

Normal data flow: each 160-Mbits/s link reads out 10 FEICs

160-

320

Mbi

ts/s

10 FEICs

160 Mbits/s

160 Mbits/s

Unu

sed

Dat

a P

ath

Ext

ra D

ata

Pat

hfo

r rev

erse

dire

ctio

n

altMC

MC

To SMC

Normal data flow: each 80-Mbits/s link reads out 5 FEICs

160-

320

Mbi

ts/s

2 x 5 FEICs

80 Mbits/s

Unu

sed

Dat

a P

ath

2 x 5 FEICs

Unu

sed

Dat

a P

ath

80 Mbits/s

altMC

MC

To SMC

One failing FEIC: one of the 80-Mbits/s link Is reading-out more than 5 FEICs

160-

320

Mbi

ts/s

2 x 5 FEICs

80 Mbits/s

2 x 5 FEICs

Unu

sed

Dat

a P

ath

80 Mbits/s

X

Possible redundancy schemes to cope with the loss of a FEIC or of a Module Controller

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Page 34: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 34

Data Format

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

• Data format used in the current detector is highly optimised in size– Necessary to look at each single bit to

know what it is and what is following and requires synchronisation between FEICs

• “On the fly” event building and decoding• Might be a problem when a large

amount of SEU are expected• Could be better to consider the system

as a network and to push packets of data from the FEIC up to off-detector electronics

• Pros and cons– Enough to only protect the headers

against errors• Data unprotected

– No synchronisation expected in the data transmission in the FE

• System cannot hang– More complex task in the off-detector

electronics• A lot of resources available in big FPGA

– Extra data volume• To be simulated

Stave ID Module ID Chip ID Data TypeData L1ID BCID DataDCS Sensor1 Sensor2 …Register Register # Data ……

Payload

Page 35: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 35

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

• In the current detector, a lot of direct connections of sensors – Not applicable for the upgrade

• A lot of discussions concerning the need for a fully separated DCS system– Separately powered and separate communications– Separate ASICs– Additional services….

• Still possible to run safely the detector even with the DCS integrated in the readout

Integrated with the readout or separated?

Page 36: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 36

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Mode of Operation

• A few sensors directly connected – Used also for interlock

• Powering sequentially the different components only when it is safe to do so– Note that it is easy to do with DC-DC converters but may be less with serial power

• DCS functionalities in the module controllers and the stave controllers• Separation of the DCS data and the readout data in the off-detector

electronics– Does not require the DAQ to work

Service bus

TTC, Data

( & DCS)

fibers

PS cable

DCS env. IN

Cooling In

Opto

SC

DCS

interlock

SC Hybrid

Module #1 Module #2 Module #10

Cooling Out

(DCS link)

MC

F

E

I

C

s

Humidity sensorTemperature

sensors (cooling pipes and Stave

Controller)

Page 37: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 37

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

Total Power for the Strips

• Assumptions:– Pessimistic 1.5mW [1mW] per channel for the strip FEIC and 1.3V Vdd – 150mA [100mA] per 128-channel FEIC.

• Total current (for the barrel and both end-caps): 48.5kA [33kA] • 80% efficiency of front-end power devices would lead to 78.5kW

[52kW] dissipated in the tracker volume– 70% efficiency would lead to 90kW [60kW]

• Current SCT and TRT detectors are fed with about 12kA • Assuming the amount of services cannot be increased, the powering

scheme to be used must limit the amount of current to be fed at that level – That’s about 1/6th (1/5th) of the current needed by the front-end

electronics. Hence either a factor 5 to 6 (at least) DC-DC conversion or a serial powering scheme of at least 5 to 6 modules has to be used.

Page 38: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 38

DC-DC or Serial Power

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

• Developments are on-going: serial powering and DC-DC conversion– Cf last ESE seminar (Federicco) and the presentations during TWEPP08

• Reducing the current to be fed by a factor of 5-to-10 minimum is reachable with both solutions

• DC-DC converters offer some interesting flexibility– Can separate different supplies easily

• Analog – digital saving in overall power• Stave controller, module controller and FEICs capability of controlling the

operation– Radiation hardness not solved

• Serial powering scheme has some system issues which are being tackled

• Options to be kept opened for a while• Real estate is an important issue for both solutions

Page 39: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 39

Space available for the power devices

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

• Readout hybrid with 20 FEIC (ABCn 0.25 device)• Not so much space for the power devices and the module

controller…

A module could look like…

SensorDigital I / O

Power, DCS, HV

TTC (multi- drop LVDS)

Data Links (point- to- point LVDS)

100mmBus cable From A. Greenall

Page 40: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 40

Rough Estimate

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

DC-DC SerialNo

redundancyFull

redundancy

One HV per

module

One HV for 2 modules

Half single sided short strips stave

2 wires 8-mm2

copper + shield (total cross-

section of the cable 138 mm2)

2 wires 4-mm2

copper + shield (total cross-

section of the cable 89 mm2)

12 twp (cross-section

1.57 mm2)

15 twp (cross-section

1.57 mm2)

2 fibres (cross-

section 1.57 mm2)

4 fibres (cross-

section 1.57 mm2)

10 (cross-section

1.73 mm2)

5 (cross-section 1.73

mm2)

Half single sided long strips stave

2 wires 4-mm2

copper + shield (total cross-

section of the cable 89 mm2)

2 wires 2-mm2

copper + shield (total cross-

section of the cable 60 mm2)

12 twp 15 twp 2 fibres 4 fibres19 (cross-

section 1.73 mm2)

10 (cross-section 1.73

mm2)

Total cross-section [cm2]

1052 692 89 111 15 30 243 126

Min total [cm2] 922Max total [cm2] 1436

1.54-cm thickness at R=95cm. 75% LV, 9.5% DCS, 13.5% HV, 2% Fibres2.41-cm thickness at R=95cm. 73% LV, 8% DCS, 17% HV, 2% Fibres

LV Fibres

DCS min DCS max

HV

• Services for the barrel strips at the entrance of the tracker volume– 1 mW/ch– DC-DC or serial power introduces a factor

10 saving on the current

– 2-V drop max– Packing factor of 2

LV is still the dominant part by far

Page 41: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 41

Total Fantasy ?

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

• LoI, TP and TDR in 2009, 2010 and 2011

• LHC stop: October 2016• SLHC start: Spring 2018• Tracker installation: January

2017 (?)• Stave assembly start:

January 2013 (?)• Very little time left for fully

specifying the components

and designing them• Choice of technology to be

used (130nm or 90nm or lower) as late as possible– Most of the work done in

130nm so far– Some early work with 90nm (or

lower) necessary to be able to make the decision in due time

• Analogue performances• Radiation hardness

Page 42: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 42

Total Fantasy? (cont)

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

• Architecture definition complete with options Nov-08• Decision on options (powering, electrical links, opto) Dec-09• Component specifications complete Feb-10

• Prototype sensitive blocks (design, MWP fab, test) Sep-08 to Dec-09• Prototype complete component design, fab and test Feb-10 to Aug-11• Stave assembly & test (system test of electronics) Aug-11 to Feb-13

• Pre-production component design, fab and test Feb-12 to Feb-13• Pre-production stave assembly & system test Feb-13 to Jul-13

• Production Readiness Review Aug-13• Component Production

– First production wafer batch (fab and test) Aug-13 to Feb-14

– Deliver first production batch to module assembly sites Feb-14– Start component series fabrication Sep-13

(Assumes no design change from pre-production)– Start of component series delivery to assembly sites Apr-14

No contra

ctual value!

Page 43: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 43

ASICs developments and specifications

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

• Working document on architecture available since about a year– Reviewed and presented to the collaboration

• Two working groups in place to try and define more precisely the specifications of the different components. One for the pixels and one for the strips– Inputs to the “common projects” teams (e.g. GBT)– ~350k FEIC but only ~20k MC and ~5k SC(GBT)

• ABCn 0.25 chip as test vehicule for sensor studies– Also contains some features for testing different power schemes and

readout speeds• Preliminary study of the front-end part (preamplifier-shaper-

discriminator) in 0.13– Very good power performances: <200µW per channel – See J. Kaplon’s presentation during the TWEPP workshop

• Evaluation of SiGe

Page 44: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 44

Fixed Barrel Length

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

• SS longer more modules more data (+20%)• LS shorter less modules and less data

Page 45: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 45

Tracker UpgradeDetector Readout DCS Power Services Schedule Developments Summary

• The readout architecture of the ATLAS upgraded tracker has to be different from the current one

• Detector organised in staves. Hierarchical readout following this segmentation– Fewer but higher speed links

• Some elements of the readout are not to be produced in very high quantity– Points towards common solutions with CMS and others

• Power distribution requires special efforts to maintain reasonable services– Saving factor 5 - 10 on the current

• Schedule looks uneasy– Not so much time for the electronics development– Decision on technology to be used for the FE electronics at the latest in 2012

Page 46: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 46

• Two major coordination bodies– Develop a realistic and coherent

upgrade plan– Steer R&D activities– Cover engineering aspects from the

beginning

• Upgrade Steering Group (USG)– Representatives from systems,

software, physics and technical coordination

• Project Office– Part of the technical coordination– Project Office should technically guide

the upgrade activities• Conceptual design and R&D• Prototyping• Pre-series and construction• Installation and commissioning

• Upgrade addressed during each ATLAS overview week and during dedicated workshops– Several devoted to the tracker

Upgrade Organisation CERN Involvement

Ref: https://edms.cern.ch/file/690177/1/Upgrade_Org_PO.docIndico pages:

http://indico.cern.ch/categoryDisplay.py?categId=350

Page 47: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 47

• Proposal made to the USG– Established lightweight review

procedure for approval

• Circulation to collaboration board– More groups joining?

• Second discussion in USG– Sufficient resources?

• Decision about recommendation by USG

• Review procedure during the lifetime of the project– Review office

• A number of proposals issued so far– <

https://edms.cern.ch/cedar/plsql/navigation.tree?cookie=7849675&p_top_id=1310970533&p_top_type=P>

• ATLAS welcome joint R&D activities with other experiments (CMS)– Versatile link and GBT– 130 nm or lower processes– Power distribution

Upgrade Organisation CERN Involvement

R&D Activities

Page 48: ESE Seminar 25 September  2008

Ph. Farthouat ESE Seminar 25 September 2008 Slide 48

• Technical coordination– PO engineering– Tracker engineering– Electronics coordination– Interface to machine (beam pipe and

shielding)• Level-1

– Central Trigger Processor upgrade for phase-1 and SLHC

• Si Strips– ABCnext design– Micro-electronics design and project

management– Tests and qualification of devices, modules

etc.– Could make a major contribution to the end-

cap• Would make sense to have also a strong

participation in the FE system

• Micromegas development and evaluation– Will need electronics

• Some interest of individuals here and there– e.g. in the back-end electronics of the

calorimeters• There is not today a clear picture of

where the CERN ATLAS Team will contribute – No MOU or alike defining yet the upgrade

activity– Still little specific funding available so far

• Rely on common projects– Versatile Link– GBT– Support for µelectronics– TTC upgrade – Power

Upgrade Organisation CERN Involvement