errors of observation in concrete testing labs

Upload: suryasis-dasgupta

Post on 13-Oct-2015

25 views

Category:

Documents


0 download

DESCRIPTION

errors computation technique

TRANSCRIPT

  • ACT (concrete techonlogy practicles)

    Slump Test

    Objective: To determine the consistency of concrete mix of given proportions.

    Scope and Significance

    Unsupported fresh concrete flows to the sides and a sinking in height takes place. This

    vertical settlement is known as slump.

    In this test fresh concrete is filled into a mould of

    specified shape and dimensions, and the settlement or slump is measured when

    supporting mould

    is removed. Slump increases as water-content is increased. For different works

    different slump

    values have been recommended.

    The slump is a measure indicating the consistency or workability of cement concrete. It

    gives an idea of water content needed for concrete to be used for different works. A

    concrete is

    said to be workable if it can be easily mixed, placed, compacted and finished. A

    workable

    concrete should not shown any segregation or bleeding. Segregation is said to

    occur when

    coarse aggregate tries to separate out from the finer material and a concentration of

    coarse

    aggregate at one place occurs. This results in large voids, less durability and strength.

    Bleeding

  • of concrete is said to occur when excess water comes up at the surface of concrete. This

    causes

    small pores through the mass of concrete and is undesirable.

    By this test we can determine the water content to give specified slump value. In this test

    water content is varied and in each case slump value is measured till we arrive at water

    content

    giving the required slump value.

    This test is not a true guide to workability. For example, a harsh mix cannot be said to

    have same workability as one with a large proportion of sand even though they may have the

    same slump.

    Apparatus Iron pan to mix concrete, slump cone, spatula, trowels, tamping rod and graduated

    cylinder.

    Slump test apparatus

  • Procedure Four mixes are to be prepared with water-cement ratio (by mass) of 0.50, 0.60, 0.70 and

    0.80, respectively, and for each mix take 10 kg of coarse aggregates, 5kg of sand and 2.5kg

    of cement with each mix proceed as follows

    1)

    Mix the dry constituents thoroughly to get a uniform colour and then add water

    2)

    Place the mixed concrete in the cleaned slump cone mould in 4 layers, each

    approximately of the height of the mould. Tamp each layer 25 times with

    tamping rod distributing the strokes in a uniform manner over the cross-section of

    the mould.

    For the second and subsequent layers the tamping rod should

    penetrate in to the underlying layer.

    3)

    Strike off the top with a trowel or tamping rod so that the mould is exactly filled.

    4)

    Remove the cone immediately, raising it slowly and carefully in the vertical

    direction.

    5)

    As soon as the concrete settlement comes to a stop, measure the subsidence of

    concrete in mm which will give the slump.

  • Note: Slump test is adopted in the laboratory or during the progress of work in the field for

    determining consistency of concrete where nominal maximum size of aggregate does not

    exceed

    40mm

  • Any slump specimen which collapses or shears off laterally gives incorrect results and if

    this occurs the test is repeated, only the true slump should be measured.

    Observations & Calculations

    Compaction Factor Test Objective: To determine the workability of concrete mix of given proportions by the

  • compaction

    factor test.

    Scope and Significance Compaction factor test is adopted to determine the workability of concrete, where nominal

    size of aggregate does not exceed 40mm, and is primarily used in laboratory.

    It is based upon

    the definition, that workability is that property of the concrete which determines the amount

    of

    work required to produce full compaction. The test consists essentially of applying a standard

    amount of work to standard quantity of concrete and measuring the resulting compaction. To

    find the workability of freshly prepared concrete, the test is carried out as per specification of

    IS:

    1199-

    1959. Workability gives an idea of the capability of being worked, i.e., idea to control the

    quantity of water in cement concrete mix to get uniform strength.

    It is more sensitive and precise than slump test and is particularly useful for concrete mixes

    of low workability. The compaction factor (C.F.) test is able to indicate small variations in

    workability over a wide range.

    Apparatus

    Compaction factor apparatus, trowels, Graduated cylinder, balance, tamping rod and iron

    buckets

  • Essential dimension of the compacting factor apparatus for use with aggregate not exceeding 40 mm Nominal Maximum Size

    Procedure

    1.

    Keep the compaction factor apparatus on a level ground and apply grease on the inner

    surface of the hoppers and cylinder.

    2.

    Fasten the flap doors.

    3.

    Weigh the empty cylinder accurately and note down the mass as W kg.

  • 1 4.

    Fix the cylinder on the base with fly nuts and bolts in such a way that the central

    points of hoppers and cylinder lie on one vertical line. Cover the cylinder with a

    plate.

    5.

    Four mixes are to be prepared with water-cement ratio (by mass) 0.50, 0.60, 0.70, and

    0.80, respectively. For each mix take 9 kg of aggregate, 4.5 kg sand 2.25 kg of

    cement. With each mix proceed as follows:

    a)

    Mix sand and cement day, until a mixture of uniform colour is obtained. Now

    mix the coarse aggregate and cement-sand mixture until coarse aggregate is

    uniformly distributed throughout the batch.

    b)

    Add the required amount of water to the above mixture and mix it thoroughly

    until concrete appears to be homogeneous.

    6.

    Fill the freshly mixed concrete in upper hopper gently and crefully with hand scoop

    without compacting.

    7.

    After two minutes, release the trap door so that the concrete may fall into the lower

    hopper brining the concrete into standard compaction.

    8.

    Immediately after the concrete has come to rest, open the trap door of lower hopper

    and allow the concrete to fall into the cylinder bringing the concrete into standard

    compaction.

    9.

    Remove the excess concrete above the top of the cylinder by a pair of trowels, one in

    each hand will blades horizontal slide them from the opposite edges of the mould

    inward to the centre with a sawing motion.

    10.

    Clean the cylinder from all sides properly. Find the mass of partially compacted

    concrete thus filled in the cylinder, say W kg. 2 11.

    Refill the cylinder with the same sample of concrete in approximately 50mm layers,

    vibrating each layer heavily so as to expel all the air and obtain full compaction of the

    concrete.

    12.

    Struck off level the concrete and weigh and cylinder filled with fully compacted

    concrete. Let the mass be W kg. 3

    Observations, Calculations & Results

    Mass of cylinder W1 =

  • Compressive strength of

    concrete:

    Out of many test applied to the concrete, this is the utmost important which gives an

    idea about all the characteristics of concrete. By this single test one judge that whether

    Concreting has been done properly or not. For cube test two types of specimens either

    cubes of 15 cm X 15 cm X 15 cm or 10cm X 10 cm x 10 cm depending upon the size of

    aggregate are used. For most of the works cubical moulds of size 15 cm x 15cm x 15 cm

    are commonly used.

    This concrete is poured in the mould and tempered properly so as not to have any voids.

    After 24 hours these moulds are removed and test specimens are put in water for curing.

    The top surface of these specimen should be made even and smooth. This is done by

    putting cement paste and spreading smoothly on whole area of specimen.

    These specimens are tested by compression testing machine after 7 days curing or 28

    days curing. Load should be applied gradually at the rate of 140 kg/cm2 per minute till

    the Specimens fails. Load at the failure divided by area of specimen gives the

    compressive strength of concrete.

    Following are the procedure for Compressive strength test of

    Concrete Cubes

    APPARATUS

    Compression testing machine

    PREPARATION OF CUBE SPECIMENS

    The proportion and material for making these test specimens are from the same

    concrete used in the field.

    SPECIMEN

    6 cubes of 15 cm size Mix. M15 or above

    MIXING

    Mix the concrete either by hand or in a laboratory batch mixer

    HAND MIXING

  • (i)Mix the cement and fine aggregate on a water tight none-absorbent platform until the

    mixture is thoroughly blended and is of uniform color

    (ii)Add the coarse aggregate and mix with cement and fine aggregate until the coarse

    aggregate is uniformly distributed throughout the batch

    (iii)Add water and mix it until the concrete appears to be homogeneous and of the

    desired consistency

    SAMPLING

    (i) Clean the mounds and apply oil

    (ii) Fill the concrete in the molds in layers approximately 5cm thick

    (iii) Compact each layer with not less than 35strokes per layer using a tamping rod

    (steel bar 16mm diameter and 60cm long, bullet pointed at lower end)

    (iv) Level the top surface and smoothen it with a trowel

    CURING

    The test specimens are stored in moist air for 24hours and after this period the

    specimens are marked and removed from the molds and kept submerged in clear fresh

    water until taken out prior to test.

    PRECAUTIONS

    The water for curing should be tested every 7days and the temperature of water must be

    at 27+-2oC.

    PROCEDURE

    (I) Remove the specimen from water after specified curing time and wipe out excess

    water from the surface.

    (II) Take the dimension of the specimen to the nearest 0.2m

  • (III) Clean the bearing surface of the testing machine

    (IV) Place the specimen in the machine in such a manner that the load shall be applied

    to the opposite sides of the cube cast.

    (V) Align the specimen centrally on the base plate of the machine.

    (VI) Rotate the movable portion gently by hand so that it touches the top surface of the

    specimen.

    (VII) Apply the load gradually without shock and continuously at the rate of

    140kg/cm2/minute till the specimen fails

    (VIII) Record the maximum load and note any unusual features in the type of failure.

    NOTE

    Minimum three specimens should be tested at each selected age. If strength of any

    specimen varies by more than 15 per cent of average strength, results of such specimen

    should be rejected. Average of there specimens gives the crushing strength of concrete.

    The strength requirements of concrete.

    CALCULATIONS

    Size of the cube =15cm x15cm x15cm

    Area of the specimen (calculated from the mean size of the specimen )=225cm2

    Characteristic compressive strength(f ck)at 7 days =

    Expected maximum load =fck x area x f.s

    Range to be selected is ..

    Similar calculation should be done for 28 day compressive strength

    Maximum load applied =.tones = .N

    Compressive strength = (Load in N/ Area in mm2)=N/mm2

    =.N/mm2

    REPORT

    a) Identification mark

    b) Date of test

  • c) Age of specimen

    d) Curing conditions, including date of manufacture of specimen

    f) Appearance of fractured faces of concrete and the type of fracture if they are unusual

    RESULT

    Average compressive strength of the concrete cube = .N/ mm2 (at 7 days)

    Average compressive strength of the concrete cube =. N/mm2 (at 28 days)

    Percentage strength of concrete at various ages:

    The strength of concrete increases with age. Table shows the strength of concrete at

    different ages in comparison with the strength at 28 days after casting

    Age Strength per cent

    1 day 16%

    3 days 40%

    7 days 65%

    14 days 90%

    28 days 99%

    Compressive strength of different grades of concrete at 7 and 28 days Grade of

    Concrete Minimum compressive

    strength N/mm2 at 7 days

    Specified characteristic compressive

    strength (N/mm2) at 28 days

    M15 10 15

    M20 13.5 20

    M25 17 25

    M30 20 30

    M35 23.5 35

    M40 27 40

    M45 30 45

    ACI METHOD

  • for remaining practicles join this site (see the column in right hand side)

    , content is uploaded but waiting for

    the publishing until i get 50 member on google and 200 likes on page of

    facebook (see the column in left top side) ........ :))))