· currency equivalents (as of 30 november 2011) currency unit – nepali rupees (npr) npr1.00 =...
TRANSCRIPT
Initial Environmental Examination
November 2011
NEP: Second Small Towns Water Supply and
Sanitation Sector Project- Shivanagar Town
Project
Prepared by Department of Water Supply and Sewerage, Ministry of Urban Development for the Asian Development Bank.
CURRENCY EQUIVALENTS (as of 30 November 2011)
Currency unit – nepali rupees (NPR)
NPR1.00 = $0.1200 $1.00 = NPR83.312
ABBREVIATIONS
ADB – Asian Development Bank amsl – above mean sea level CMA – Community Medical Auxiliary DI – ductile iron Dia. – diameter DSC – Design and Supervision Consultant DWSS – Department of Water supply and Sewerage EIA – Environmental Impact Assessment EMP – Environmental Management Plan EPA – Environment Protection Act EPR – Environment Protection Rule GI – galvanized iron GoN – Government of Nepal HDPE – high density polyethylene pipe HHs – households IEE – Initial Environmental Examination lpcd – liter per capita per day lps – liters per second MOUD – Ministry of Urban Development NDWQS – National Drinking Water Quality Standard NEA – Nepal Electricity Authority NGO – Non Government Organization Nrs. – Nepali Rupees O&M – operation & maintenance OD – outer diameter PMC – Project Management Consultant PMO – Project Management Office TDF – Town Development Fund VAT – Value Added Tax VDC – Village Development Committee WHO – World Health Organization WSSDO – Water Supply and Sanitation Division Office WUSC – Water User’s and Sanitation Committee
NOTES
(i) The fiscal year (FY) of the Government of Nepal and its agencies ends on 15 July. “FY” before a calendar year denotes the year in which the fiscal year ends, e.g., FY2011 ends on 15 July 2011.
(ii) In this report, "$" refers to US dollars unless otherwise stated. This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Initial Env
Shivanaga Se
Minis
Second Small Tow Departm
nvironmental Examinationof
gar Water Supply and SanSector Project, Kailali
(Batch I, Package I)
Submitted To:
Ministry of Physical Planning Works
Government of Nepal
Singhdurbar, Kathmandu
Submitted By:
Project Management Office
Towns Water Supply and Sanitation Sector
artment of Water Supply and Sewerage
Panipokhari, Kathmandu
November 2011
on (IEE)
anitation
ctor Project
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
iii
TABLE OF CONTENTS
ABBREVIATIONS…………………………………………………………………………………………………………………………………..v
EXECUTIVE SUMMARY (Nepali)……………………………………………………………………………………………………………vii
EXECUTIVE SUMMARY (English)…………………………………………………………………………………………………………..x
A. INTRODUCTION .............................................................................................................................1
1. Name and Address of the individual institution preparing the report ............................................... 1
a. Name of the proposal .............................................................................. .................................... 1
b. Name and address of the proponent ............................................................................................ 1
c. Consultant preparing the report ................................................................................................... 1
2. Basis and extent of the IEE study.................................................................. .................................... 2
a. ADB Policy (ADB’s Safeguard Policy Statement, 2009) ............................................... ................... 2
b. National Laws, Policies, Acts, Regulations, Standards and Guidelines ........................................... 3
c. Objectives and Scope of the Environmental Study ........................................................................ 6
d. Relevancy of the Project .......................................................................... .................................... 6
e. Approach and Methodology ......................................................................................................... 8
B. DESCRIPTION OF THE PROJECT ..................................................................................................... 11
1. Existing Water Supply and Sanitation situation .................................................... .......................... 11
a. Water Supply system ............................................................................... .................................. 11
b. Sanitation facilities ............................................................................. ........................................ 12
2. Type, category and need of the subproject .................................................................................... 12
3. Size or magnitude of operation .................................................................... .................................. 13
4. Proposed schedule for implementation ......................................................................................... 13
5. Description of the subproject ......................................................................................................... 14
a. Project components ................................................................................................................... 14
b. Project requirements ................................................................................................................. 20
C. DESCRIPTION OF THE ENVIRONMENT ........................................................................................... 28
1. Physical Resources ......................................................................................................................... 28
a. Topography ................................................................................................................................ 28
b. Geology and Soils ....................................................................................................................... 29
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
iv
c. Climate and Rainfall .............................................................................. ..................................... 29
d. Hydrology .................................................................................................................................. 29
2. Ecological Resources .............................................................................. ........................................ 30
a. National Parks and Protected Areas ........................................................................................... 30
b. Forests ....................................................................................................................................... 30
c. Aquatic Species .......................................................................................................................... 32
3. Social and Cultural Resources ..................................................................................................... 33
a. Demography .............................................................................................................................. 33
b. Health facilities .......................................................................................................................... 33
c. Educational facilities ............................................................................ ....................................... 34
d. Physical or cultural heritage ..................................................................... .................................. 34
e. Employment .............................................................................................................................. 35
4. Economic Development and Prospect for Growth ...................................................... .................... 35
a. Land use........................................................................................... .......................................... 35
b. Infrastructure..................................................................................... ........................................ 35
c. Economic Characteristics .......................................................................... .................................. 37
d. Development organization .......................................................................... ............................... 38
e. Major Environmental problems ...................................................................... ............................ 39
D. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ....................................... 40
1. Beneficial Impacts and augmentation measures ............................................................................ 40
a. Construction Phase .................................................................................................................... 40
b. Operation Phase ................................................................................... ..................................... 41
2. Adverse impacts and mitigation measure............................................................. .......................... 41
a. Pre-construction Phase ............................................................................ .................................. 42
b. Construction Phase .................................................................................................................... 43
c. Operational Phase ................................................................................. ..................................... 45
d. Resettlement, relocation and compensation issue ..................................................................... 46
3. Implementation of Mitigation Measures ....................................................................................... 55
a. Project Design ............................................................................................................................ 55
b. Project Contract ......................................................................................................................... 55
c. Bill of Quantities ......................................................................................................................... 55
E. ANALYSIS OF ALTERNATIVES WITH AND WITHOUT PROJECT SITUATIONS ...................................... 56
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
v
1. Design Alternative ......................................................................................................................... 56
2. Project Site/Location Alternative ................................................................. .................................. 56
3. Alternative in Technology, Implementation Procedure and Raw Materials ..................................... 57
4. No Project Option .......................................................................................................................... 57
F. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION ............................................... 58
G. GRIEVANCE AND REDRESS MECHANISM ....................................................................................... 60
H. MATTERS TO BE MONITORED WHILE IMLEMENTING THE PROJECT AND ENVIRONMENTAL
MANAGEMETN PLAN (EMP) ............................................................................................................. 61
1. Mitigation and Monitoring ............................................................................................................. 61
a. Monitoring Costs ........................................................................................................................ 63
2. Environmental Procedures and Institutions .................................................................................... 63
4. Potential Environmental Enhancement Measures ...................................................... .................... 64
5. Reporting Procedures .................................................................................................................... 65
6. Procurement Plan and Cost Estimates ............................................................................................ 65
7. Work Plan ......................................................................................... ............................................. 66
I. CONCLUSIONS AND RECOMMENDATIONS ..................................................................................... 68
ANNEXES:…………………………..
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
vi
LIST OF TABLES
Table 1: Name and address of the proponent……………………………………………………………………………………1
Table 2: Name and address of the consultant………………………………………………………………………………..….1
Table 3: National policies, acts, regulations and guidelines…………………………………………………………….…3
Table 4: Criteria for requirement of IEE and/or EIA for drinking water supply project against the
conditions defined by EPA/EPR, 1997………………………………………………………………………………………………..7
Table 5: Water supply demand over the years…………………………………………………………………………………13
Table 6: Salient features of Dhangadi Municipality Water Supply and Sanitation Project…………….….19
Table 7: Materials required…………………………………………………………………………………………………………..…21
Table 8: Human resource.………………………………………………………………………………………………………….…...22
Table 9: Project activities..……………………………………………………………………………………………………………...23
Table 10: List of mammals.……………………………………………………………………………………………………………..30
Table 11: List of birds…………………………………..……..………………………………………………………………………….31
Table 12: List of fishes…………………………..………………………………………………………………………………………..31
Table 13: Population distribution by Ethnicity…………………………………………………………………………………32
Table 14: List of schools in the project area………………………………………………………………………………….…33
Table 15: Existing sources of water supply …..…………………………………………………………………………………35
Table 16: List of other institutions in the area…………………………………………………………………………………37
Table 17: Evaluation of environmental impacts………….………………………………………………………………..…45
Table 18: Overview of potential environmental impacts and mitigation measures/ Shivanagar……..49
Table 19: FGDs held at different locations……………………………………………………………………………………….57
Table 20: Environmental monitoring schedule……………………………………………………………………………..…61
Table 21: Monitoring costs……………………………………………………………………………………………………………...62
Table 22: Institutions involved in the proposed project…………………………………………………………………..62
Table 23: Annual costs for EMP……………………………………………………………………………………………………….65
LIST OF FIGURES
Figure 1: Schematic layout of project components………………………………………………………………………...25
Figure 2: Design layout of project components ………………………………………………………………………………26
Figure 3: Location map of Dhangadi municipality, Kailali district…………………………………………………..…27
Figure 4: Grievance Redress Mechanism………………………………………………………………………………………...59
Figure 5: Implementation schedule of the project………………………………………………………………………..…66
ANNEX
Annex 1: Approved Terms of Reference
Annex 2: Rapid Environmental Assessment (REA)
Annex 3: Public Notice
Annex 4:Deed of Inquiry (Muchulka)
Annex 5:Recommendation letters from concerned authorities
Annex 6:List of persons contacted
Annex 7: Water Quality Test Report
Annex 8: Survey Questionnaire
Annex 9:Photographs
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
vii
ABBREVIATIONS
ADB Asian Development Bank
asl above sea level
DDC District Development Committee
DIZ Direct Impact Zone
DSC Design and Supervision Consultant
DWSS Department of Water Supply and Sewerage
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EMAP Environmental Management Action Plan
EPA Environmental Protection Act
EPR Environmental Protection Rules
FGD Focused Group Discussion
GoN Government of Nepal
GRM Grievance Redress Mechanism
HH Household
IIZ Indirect Impact Zone
lpcd litres per capita per day
IEE Initial Environmental Examination
MPPW Ministry of Physical Planning and Works
NEA Nepal Electricity Authority
NDWQS National Drinking Water Quality Standard
NWSC Nepal Water Supply Corporation
PMO Project Management Office
REA Rapid Environmental Assessment
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
viii
RP Resettlement Plan
STWSSSP Small Town Water Supply and Sanitation Sector Project
SSTWSSSP Second Small Town Water Supply and Sanitation Sector Project
TDF Town Development Fund
WUSC Water User and Sanitation Committee
VDC Village Development Committee
ZOI Zone of Influence
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
ix
sfo{sf/L ;f/f+z
k[i&d"ld
of] kl/of]hgfsf] k|:tfjs vfg]kfgL ljt/)f tyf (n lgsf; ljefu (DWSS) cGtu{t kl/of]hgf Joj:yfkg sfo{no (PMO) xf] . of] kl/of]hgf g]kfn ;/sf/sf] bf];|f] r/)fsf] ;fgf zx/L vfg]kfgL tyf ;/;kmfO{ cfof]hgf (SSTWSSSP) xf] h;sf] d"n p@]Zo b]zsf ;fgf zx/x?df vfg]kfgL ljt/)f k|)FfnLsf] lgdf{)f÷j[l$, s'nf] / ;/;kmfO{ ;'ljwf lbg' tyf ;d'bfonfO{ ;/;kmfO{ :jf:Yo lzIff k|bfg ug'{ xf] . of] kl/of]hgf ;d'bfosf] dfu nlIft b[li^sf])fn] ag]sf] % / P]lzofnL ljsf; a}+ssf] ¥)f ;xof]udf z'? ePsf] xf] .o; sfo{qmdaf^ wgu(L gu/kfnLsf cGtu{t lzjgu/ j*f g+ 1, 5, 7 / 8 sf hgtf nfeflGjt x'g] %g\ . k|f/lDws jftfj/l)fo kl/If)fsf] p@]Zo, P]lzofnL ljsf; a}+ssf] lgtL / g]kfn / g]kfn ;/sf/sf] P]g / lgod o; k|f/lDws jftfj/)fLo kl/If)f ug{sf] nflu d"n p@]Zo jftfj/)fdf gsf/fTds c;/ gk/f]; eGgsf] nflu xf] / ;fy;fy} tL c;/x?sf] kl/)f ug'{ xf] / tL c;/x?nfO{ lg{d'n jf l:js[tl;dfdf Nofpg'sf] nflu ;'emfj lbg' xf] .
b'j} g]kfn ;/sf/ / P]lzofnL a}+s lgtL cg';f/ s'g} klg ljsf;sf] of]hgf tyf lg)f{o lg{df)f k|lqmofdf jftfj/)FLo c;/x?sf] Wofg k'/ofpg' k%{ .
g]kfn ;/sf/sf] sfg'gL k|lqmof cg';f/ of] k|:tfljt kl/of]hgfn] jftfj/)fLo ;+/If)f P]g 2053, / jftfj/)f ;+If/)f lgodfjnL, 2054 / -;+zf]wg_ sf] kfngf ug'{k%{ . k|:tfljt k|f/lDes jftfj/)fLo kl/If)fn] jftfj/)fLo ;+/IF)f lgodfjnsf] tflnsf 1 cGtu{t lgod 3 / ;'rL "G" sf] kfngf ub{% . To:t} ul/ P]lzofnL ljsf; j}+ssf] jftfj/)fLo cWoog lgb]{lzsf cg';f/ of] kl/fof]hgf >])fL "B" df kb{% / P]lzofln ljsf; j}+ssf] r]slni^ cg';f/ of] k|f/lDes jftfj/)fLo kl/If)f ul/Psf] % .
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
x
kl/of]hgfsf d'Vo c+zx?
k|:tfljt lzjgu/ zx/ vfg]kfgL ljt/)f tyf ;/;kmfO{ kl/of]hgf, e"ldut hndf cfwfl/t Joj:yf xf] . o;sf b'O{j^f efux? %g\ . vfg]kfgL ljt/)f / ;/;kmfO{ . kfgL ljt/)f efu cGtu{t b'O{j^f ulx/f] ^o'a j]n / -Pp^f gd'gf af]l/é_ af^ e"ldut kfgL tflgG% . o;afx]s kfgL ;'l$s/)f, kfgL e)*f/)f }̂+°L / kfgL ljt/)f Joj:yf % . bf];|f] efudf ;/;kmfO{ sfo{qmd % h; cGtu{t ljBfnox?df zf}rfno agfOg]% . o;df kmf]x/ kfgL Joj:yfkgsf] klg k|:tfj ul/Psf] % / o;sf] sfo{Gjog lg)f{o rflx+ Tolx zx/n] ug]{%g\ .
ljBdfg l:ytL
wgu(L gu/kflnsfsf] ljBdfg vfg]kfgL ljt/)f k|)ffnLsf] ljZj;lgotf sd b]lvG% / ;'ljwfsf] u')f:t/ / ljt/)f If]q klg sd /x]sf] % . k|:tfljt If]qdf lg/Gt/ kfOkaf^ cfpg] kfgL sd % h;sf] sf/)f clwsf+z #/w'/Lx? ^o'a j]n, xft] kKdaf^ cfpg] e"ldut kfgL k|of]u ul/ /x]sf %g\ . To; kfgLdf ld;fjf]̂ sf] ;Defjgf / kmnfdsf] dfqf w]/} kfOPsf] %. wgu(L gu/kfnLsfdf ;/;kmfO{ ;'ljwf klg ;fdfGo dfq b]lvG% . w]/} h;f] #/x?df ;]kl^s ^of°df hf]*]sf] ;'wfl/Psf] rkL{ / km\N; hl*t rkL{ kfOG% . Toxf¤ (Nf lgsf; / kmf]x/d}nf Joj:yfkg klg ;fdfGo dfq %g\ . cfsf;sf] kfgL aUg] s'nf] klg s]jn d'Vo ahf/df yf]/} &fp¤df dfq % .
;f] If]qsf] ;fdflhs cfly{s cj:yf dWod b]lvG% . w]/} h;f] afl;Gbfsf cfdbfgLsf] >f]q s[lif, hflu/ / Jofkf/ /x]sf] % . ;d'bfodf hftLo ljljwtf /fd|f] % -yf? hftLsf yf}/} jfx'Notf_ / ;a} hftsf dfl;x? ldn]/ a;]sf %g\ . s}nfnL lhNnf, jlb{of /fli <̂o lgs'Gh / ;'SnfkGt ;+/If)f >f]t glhs ePsf]n] Toxf¤ h}ljs ljljwtf klg w]/} kfOG% .
jftfj/)fLo k|efj, gsf/fTds k|efj Go"lgs/)f pkfox? / cg'udg
s'g} vf;} dxTjk")f{ gsf/fTds jftfj/)fLo k|efj b]lvb}g / ;+efljt gsf/fTds k|efjx? klg :yflgo / lgDg :t/sf] b]lvG% . vfg]kfgL ljt/)f k|)ffnLsf d"Vo jftfj/)fLo d'@f lgdf{)f;+u ;DalGwt lqmofsnfk h:t} e"ldut kfgL tfGg / ljt/)fsf] nflu vlgg] "af]/xf]n" / ;*ssf] ;tx v's'nf] x¤bf x'g] e"IFo h:tf %g\ . ltgsf] gsf/fTds k|efj Go"lgs/)f ug{ ;fjwfgL pkfox? h:t}M vlgPsf vfN^fx? /fd|/L k'g]{ / hlt ;Sbf] ?v tyf af]̂ lj?jfx? sf \̂g
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
xi
Go"g ul/Gf]%. To:t} u/L ;/;kmfO{ ;DalGwt d"Vo d'@f ;+rfng r/)fsf s[ofsnfk h:t}M ":nh" -lxnf]_ ;'sfpg] :yfgaf^ pTkGg x'g] ;d:ofx? x'g]%g\ / To;nfO{ Go"lgs/)f ug{ ":nh" / ";f]s lk^" sflgoldt dd{t ;+ef/ / prLt lj;{hg ul/g]%. kl/of]hgfsf] d'Vo ;+/If)fsf :yfgsf] %gf]̂ pkef]Qmf ;ldtLx?sf] ;Nnfx / ;'emfj cg'?k ul/Psf % / To;sf] nflu s'g} klg #/w'/L / hg ;d'bfonfO{ lj:yflkt jf k'g{:yfkgf ug{ gkg]{ b]lvG% . oL ;a} s/fx?nfO{ Wofgdf /fVbf, k|:tfljt kl/of]hgfaf^ ;f] IF]qsf h}jLs tyf cfly{s ;fdflhs jftfj/)fdf s'g} uxg k|efjsf] ;Defjgf lgs} sd b]lvG% .
gsf/fTds k|efj Go"lgs/)fsf] sfo{Gjog /fd|f] ;+u ePsf] jf gePsf] hf¤r ug{ cg'udg ug'{ h?/L % . To;}n] lgdf{)f / ;+rfng cjlwdf x'g] lqmofsnfkx?nfO{ ;d]̂ ]/ Pp^f j[l:tt cg'udg sfo{qmd tof/ kfl/Psf] % . kl/of]hgf z'? ug'{ cufl*, kl/of]hgf Aoj:yfkg sfo{non] gsf/fTds k|efj Go"gLs/)f pkfox?sf] sfo{Gjog ug{sf nflu j[l:tt sfo{ of]hgf / jftfj/)fLo of]hgf cg';f/sf] cg'udg of]hgf agfOg] % h;nfO{ lgdf{)f / ;+rfng sfo{sf] &]Ssf-k^^f ;+u} ;+nUg ul/g] %.
lgisz{ tyf ;'emfjx?
o; kl/of]hgsf k|s[lt, kl/of]hgf >f]tsf] jftfj/)f Pjd\ cfly{s ;fdflhs cj:yf / :ynut lgl/If)f Pjd\ ;/f]sf/jfnf ;+usf] ;/;NnfxnfO{ dWo gh/ /fVbf o; kl/of]hgfaf^ To; >f]tdf Go"g gsf/fTds jftj/)fLo c;/ kg]{% . ;+efljt k|efjx? w]/} h;f] :yflgo %g] / ;xL Go"lgs/)f pkfo / lgoldt cg'udg ul/Pdf oL k|efjx?nfO{ ;lhn} Pjd\ sd vr{df Go"lgs/)f ug{ ;lsg] % . o; kl/of]hfgfaf^ :yflgo afl;Gbfx?n] ;'/lIft / k|;:t dfqfdf vfg]kfgL kfpg] %g\ / ;/;kmfO{sf] cj:yfdf ;'wf/ x'g]% h;n] ubf{ wgu(L gu/kfnLsfsf afl;Gbfx?sf] hLjg :t/df ;'wf/ cfpg] % . o; kl/of]hgfnfO{ prLt tl/sfaf^ sfo{Gjog ul/Pdf / jftfj/)fLo d'@fx?nfO{ ;xL (+un] JoQm ul/Pdf, :yflgo afl;Gbfx?sf] :jf:y / jftfj/)fdf dxTjk")f{ ;'wfg x'g] b]lvG% . To;}n] k|f/lDes jftfj/)fLo g} k'Ug] b]lvG% / kl/of]hgf sfo{Gjogsf nflu plrt b]lvG% .
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
xii
EXECUTIVE SUMMARY
Background
The Project Management Office (PMO) of Department of Water Supply and Sanitation (DWSS) is the
proponent of the current project. The sub-project is a part of the second phase of the Small Town Water
Supply and Sanitation Sector Project (STWSSSP) of the Government of Nepal which aims to
construct/extend drinking water supply systems, drainage and sanitation facilities as well as provide
sanitary health education to the community in upcoming small urban towns of the country. The project
embraces the community managed demand responsive approach and is being implemented under ADB
finance. The proposed project will facilitate ward no. 1, 5, 7 and 8 of Shivanagar Town in Dhangadi
Municipality.
Purpose off IEE, ADB policy, GoN acts and rules
The purpose of this Initial Environmental Examination (IEE) is to examine the environmental implication
of proposed project and its activities to ensure that it will not damage the environment and to provide
measures to remove or reduce those impacts into acceptable limits.
Both the Nepali law and ADB policy require that the environmental implications of individual
developments are taken into account in the planning and decision making process.
The statutory requirement of the Government of Nepal, that has to be adhered to for the proposed
project, is the Environmental Protection Act, 1996 and Environmental Protection Regulation, 1997 (and
amendments 2007). The present IEE study fulfills the requirements pertaining to Rule 3, Annex G of
Schedule 1 of EPR, 1997 (including amendments). Similarly, as per ADB guidelines on Environmental
Assessment requirements, the project is classified Environment Category B and IEE is required as per the
checklist suggested by ADB.
Components of the project
The proposed ‘Shivanagar Town Water Supply and Sanitation Project’ is ground water based water
supply system.The project comprises of two major components-Water supply and Sanitation. The water
supply part comprises of pumping scheme in which two new deep tube wells and one test boring tube
well will be used to exploit ground water. The system also consists of water treatment facilities, storage
tanks and overhead tanks from where water will be distributed through distribution pipe lines. The
second component is sanitation services which include constructing school toilets; and waste water
management system that has been prepared but the implementation has yet to be decided by the town.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
xiii
Baseline information
The existing water supply system in Dhangadi has poor reliability and the quality of services availed by
the consumers is very low and services only part of the town. The proposed area does not get regular
piped water supply and the many households have to resort to hand pumps, which are often
contaminated or have high iron content. The sanitary facilities are also quite basic in Dhangadi
municipality. Majority of households have ventilated improved pit latrine and pour flush latrines
connected to septic tank. There is absence of well managed sewerage system and solid waste
management systems. The storm water drainage system is a small stretch along the road only in core
market area.
The socio-economic condition of the area is moderate. Majority of the people depend on agriculture,
service and business for their source of income. The community has good ethnic diversity (Tharu people
in slight majority), with people from various ethnic groups living together. Kailali district lies at the
corridor of Bardiya national park and Suklaphanta conservation area, harnessing good ecological
diversity
Environmental impacts, mitigation and monitoring
No any significant adverse environmental impacts have been predicted and the anticipated negative
impacts are of local in nature and low in magnitude. The main environmental concern for water supply
system is related to construction activities such as digging of boreholes for ground water intake and
distribution line such as unsettling of street surfaces due to excavation and trenches which could lead to
soil erosion and silt run off. The mitigation measures are precautionary types such as proper back filling
of the excavated trenches and avoiding cutting of vegetation. The main issues related to the sanitation
component is during the operational phase such as nuisance due to sludge drying bed and the
mitigation measures are related to the periodic maintenance and proper disposal of sludge and soak
pits. The locations of major structures have been acquired in consultation with the user committee and
no households or community have been displaced or resettled. Therefore there are very less possibilities
of adverse impacts on the biological and socio economical environment of the project area.
Monitoring is necessary to check the implementation of mitigation measures and a detailed monitoring
schedule has been designed specifying the regular and periodic monitoring activities during the project
construction and operation phase. Before the operation of the project, PMO will develop detailed work
plan for implementing mitigation measures and monitoring plans based on Environmental Management
Plan which will be incorporated into the construction and operation contracts.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
xiv
Conclusion and Recommendation
Considering the nature of the project; environmental and socio-economic situation of the area and
based on the detailed field survey and consultation with the relevant stakeholders, it can be concluded
that the proposed project will have only minor negative impacts on the area. The impacts are mostly
local in nature and can be easily and cheaply mitigated with suitable mitigation measures and regular
monitoring schedules. Implementation of the project will benefit the local people with safe and
sufficient supply of drinking water and improved sanitary situation thereby raising the living standard of
the people in Dhangadi municipality.If the project is properly implemented and environmental issues are
duly considered, there will be a significant improvement in the health of the environment and people. It
is proposed that the information suggested in the IEE report be well utilized in next phases of work and
monitoring plan followed up. Hence, IEE is sufficient and proposed project is suitable for
implementation.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
1
A. INTRODUCTION
1. Name and Address of the individual institution preparing the report
a. Name of the proposal
1. The name of the proposal is ‘Initial Environmental Examination (IEE) of Shivanagar Water Supply
and Sanitation Project’ in Kailali District. The location map of the proposal is given in Figure2.
b. Name and address of the proponent
2. The project proponent Second Small Town Water Supply and Sanitation Sector Project
(SSTWSSSP) under Department of Water Supply and Sewerage (DWSS) will be the responsible agency for
the implementation of the proposal. The name and address of the proposal is given below.
Table 1: Name and address of the proponent
Name Address
Proponent
Project Management Office Second Small Towns Water Supply and Sanitation
Sector Project Department of Water Supply and Sewerage
Ministry of Physical Planning Works Government of Nepal
Panipokhari, Kathmandu Tel: 977 1 4423848, 977 1 4412348
Fax: 977 1 4413280 E-mail: [email protected]
Website: www.sstwssp.gov.np
c. Consultant preparing the report
3. ERMC (P) Ltd. has worked on behalf of the proponent for conducting IEE studies and preparing
IEE report using all the prevalent guidelines, acts, policies and regulations. The name and address of the
consultant is given below.
Table 2: Name and address of the consultant
Name Address
Consultant
ERMC (P.) Ltd Environment and Resource Management Consultant
P. O. Box: 12419, Baneshwor, Kathmandu Tel.: 4483064, 4465863,
Fax: 4483064 Email: [email protected] Website: www.ermcnepal.com
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
2
2. Basis and extent of the IEE study
4. Government of Nepal has prepared a fifteen years development plan to implement the water
supply and sanitation programmes in emerging towns or small towns in order to improve the health and
the quality of life of the people living in the project towns by constructing and extending water supply
system, drainage and sanitation facilities and providing health and hygiene education programmes in
the towns. The project follow the community managed demand responsive approach where the
community will be involved from the very planning phase to implementation phase then to operation
and maintenance of the subprojects soon after it being completed. The project, ‘Small Town Water
Supply and Sanitation Sector Project, STWSSSP’ is the outcome of that effort.Asian Development Bank
(ADB) has been providing the financial assistance to implement the project in both the phases.
Department of Water Supply and Sewerage (DWSS) is the implementing agency whereas Ministry of
Physical Planning and Works (MPPW) is the executive agency.
5. Both the Nepali law and ADB policy require that the environmental implications of individual
developments are taken into account in the planning and decision making process and that action is
taken to reduce the impacts to acceptable levels. This is done through environmental assessment
process, which has become an integral part of lending operations and project development and
implementation worldwide.
a. ADB Policy (ADB’s Safeguard Policy Statement, 2009)
6. The operational policies of the Asian Development Bank (ADB) included three safeguard policies:
the Involuntary Resettlement Policy (1995), the Policy on Indigenous Peoples (1998), and the
Environment Policy (2002) which are all due for revision. ADB’s Safeguard Policy Statement (SPS), a
consolidated policy, describes common objectives of ADB’s safeguards, lays out policy principles, and
outlines the delivery process for ADB’s safeguard policy. The SPS is designed for application to current
and future lending modalities and caters to the varying capacities and needs of DMC clients in both the
public and private sectors and will supersede the three current safeguard policies.
7. ADB’s current safeguard policies are generally understood to be operational policies that seek to
avoid, minimize, or mitigate adverse environmental and social impacts, including protecting the rights of
those likely to be affected or marginalized by the development process.
8. ADB’s SPS highlights a number of areas that require attention in ADB's environmental
assessment process. It addresses the need for more upstream environmental assessment at the level of
country programming, the need for more structured consultation in the conduct of environmental
assessments, the need for greater emphasis on monitoring and compliance with environmental
requirements during project implementation, and finally the need to view environmental assessment as
an ongoing process rather than a one-time event
9. ADB requires environment assessment of all project loans, program loans, sector loans, sector
development program loans, financial intermediation loans, and private sector investment operations.
The process of determining a project’s environment category is based on a screening checklist that
considers the type, size, and location of the proposed project. Loans are classified into category A (with
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
3
potentially significant environmental impacts); category B (with potentially less significant
environmental impacts); category C (unlikely to have significant environmental impacts); and a new
category, FI, (credit line for subprojects through a financial intermediary, or equity investment in a
financial intermediary). A project’s environment assessment category is determined by the category of
its most environmentally sensitive component, including both direct and indirect impacts. An IEE is
required for category B projects, and an EIA, requiring greater depth of analysis, for category A projects.
No environmental assessment is required for category C projects although their environmental
implications nevertheless need to be reviewed.
10. The proposed Shivanagar Town Water Supply and Sanitation Project is classified as environment
Category B as per the ADB guidelines and following normal procedures for project loans, an IEE was
conducted. The IEE has been done based on the checklist completed to support the environmental
classification of project under ADB (See Annex 1 for REA checklist).
b. National Laws, Policies, Acts, Regulations, Standards and Guidelines
11. Most of the national policies and laws of the Government of Nepal (GoN) are in favor of
environmentally sound economic development and growth. Following table summarizes the relevant
policies, acts and regulations and guidelines that have been an integral part of the project and have
been reviewed during the preparation of the IEE report.
Table 3: National policies, acts, regulations and guidelines Policies
Three Year Interim Plan (2007-2010) The interim plan provides the most recent guidance on urban sector priorities highlighting, in particular, the need to address the effects of rapid urbanization on service levels, water quality and scheme maintenance. It proposes the full integration of sewerage, on-site sanitation and solid waste management in all urban schemes and specially endorses cost recovery from consumers. Local authorities are responsible for overseeing project implementation but with private sector organizations playing increasing roles.
Interim Constitution of Nepal, 2007 The interim constitution of Nepal realized environmental protection as the policy of the state. Clause (4) of Article (35) of the constitution states that ‘The State shall, while mobilizing the natural resources and heritage of the country that might be useful and beneficial to the interest of the nation, pursue a policy of giving priority to the local community’. The Clause (5) states that ‘The State shall make necessary arrangements to maintain the natural environment. The State shall give priority to special protection of the environment, and rare wildlife, and prevent further damage due to physical development activities, by increasing awareness of the general public about environmental cleanliness. Provision shall be made for the protection of the forest, vegetation and biodiversity, their sustainable use and for equitable distribution of the benefits derived from them’ National Urban Water Supply and Sanitation Sector Policy, 2009 Formulated to provide the overall policy support and guidance towards achieving equity in service delivery by ensuring that the financially marginalized households within the system areas are mainstreamed as valid customers of service through design and implementation of financial incentives where so required. It aims to ensure that the roles and responsibilities of central and local government bodies, external development partners, private sector including NGOs and user groups are clearly defined in scheme implementation and regulation and performance management in accordance with national decentralization policy.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
4
National Policy on Rural Drinking Water Supply and Sanitation, 2004 Provides guidance on water and sanitation service provision in rural areas using community led participatory approaches. While partially relevant t the urban context, particularly around the integration of inputs and local capacity building, it generally fails to address the complex operational challenges to be faced by Municipal authorities in implementing and managing urban services. Acts and Regulations Child Labor Prohibition and Regulation Act, 2001 The section 3 of the act prohibits a child from engaging in work, sub clause 1 of the clause 3 states “Nobody shall engage in work a child who has not completed fourteen years of age as a labor and sub clause 2 states “Nobody shall engage a child in a risk full occupation or work set forth in the Schedule”. The section 4 states “Child not to be engaged in work against his will by temptation or fear or pressure or by any other means” Local Self Governance Act, 1999 & Local Self Governance Regulations, 2000 The Act empowers the local bodies for the conservation of soil, forest and other natural resources and implements environmental conservation activities. It also describes about the user group formation to implement the programs in the local areas. The Regulation has provisions for Village Development Committee (VDC), District Development Committee (DDCs) and municipality to coordinate and implement development projects/programs and to provide approval or clearance of the proposed project.
Water Resources Act, 1992 & Water Resources Regulation, 2000 Water Resource Act is an umbrella act governing water resource management. It declares the order of priority of water use; vests ownership of water in the state; prohibits water pollution; and provides for the formation of Water User Association and system of licensing. The Regulation sets out the procedure to register a WUA and to obtain a license and sets out the rights and obligations of WUA and license holders. Environmental Protection Act (EPA), 1997 & Environmental Protection Regulations (EPA), 1999 (and amendments) EPA and EPR have several provisions to institutionalize environmental consideration in development projects. Section (5) of EPA stipulates that ‘a proponent who is desirous of implementing any proposal shall have to submit such a proposal, accompanied by the report on Initial Environmental Examination or Environmental Impact Assessment of the proposal, to the concerned agency for the approval of such a proposal. The EPR elaborates provisions to prepare and submit the scoping report, Terms of Reference (TOR), and IEE/EIA report for approval and includes public consultation processes. As per the EPR, the Environmental Assessment report, in general, should include detail information on impacts and environmental protection measures, including implementation plan, monitoring and evaluation and environmental auditing. Public consultation is a pre-requisite in all the prescribed projects. Drinking Water Regulations, 1998 Regulates the use of drinking water and deals with the control of water pollution and maintenance of quality standards for drinking water. It also sets out the conditions of service utilization by consumers Forest Act, 1993 & Forest Regulations, 1995 (including amendments) Since forest has an important role in managing water resources, Forest Act has many provisions effecting the integrated water resources management of the country. The basic objective is developing and conserving the forests of the country. The government can provide parts of any type of forest for the implementation of national priority plan with the assurance that it does not adversely affect the environment. The Regulation further elaborate legal measures for the conservation of forests and wild animals.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
5
Labor Act, 1992 The Act emphasizes on occupational health and safety of workers and stipulates provision of necessary safety gears and adopting necessary precautionary measures against potentially hazardous machine/equipment in the workplace. It also stipulates to make arrangements such as removal of waste accumulated during production process and prevention of dust, fume, vapor and other waste materials, which adversely affect the health of workers Nepal Water Supply Corporation Act, 1989 (and amendments) & Water Supply Management Board Act, 2006 & Water Supply Tariff Fixation Commission Act,2006 These acts facilitate the improved management of water and sanitation services. They establish the legal basis for private sector management of schemes and independent fee setting and regulation applicable to all urban schemes Solid Waste Management and Resource Mobilization Act, 1987 & Solid Waste (Management and Resource Mobilization Rules), 1990 As solid waste has direct impact on water supply system, discharge of solid waste in either public or private places have been prohibited under this Act. The rules entrusts Solid Waste Management and Resource Mobilization Centre, established under the Act, to provide necessary service to individual or institution in managing solid waste. As such any water resource projects may obtain such service and maintain the water resource clean. Town Development Act, 1988 The Act has provisions about the formation of town development committee in any town area to implement town planning and in carrying out the developmental and reconstruction work of that town.
Land Acquisition Act, 1977 & Land Acquisition Rules, 1969 The Land Acquisition Act and the Rules are the two main legal instruments that specify procedural matters of land acquisition and compensation. Under these, the Government is allowed to acquire any private land paying reasonable compensation to the affected party for any public purposes or for operation of any development project initiated by government institutions and the water resources laying and originating within such acquired area is spontaneously acquired under this process. Water Tax Act, 1966 Under the Act, the water user who use water through a tap distributed by the government is obliged to pay water tax as fixed by prevalent laws and charges are levied if the tax is not paid within the time as fixed by the law. Standards and Guidelines National Drinking Water Quality Standards (NDWQS) and Directives, 2005 Provides details of the water quality standards to be applied to all water supply schemes. These set out the water quality parameters, which the water suppliers should adhere to. The directives also ensures that the water sampling, testing and analysis procedures used to certify that the drinking water supplied or to be supplied conforms to the NDWQS and also sets the monitoring and surveillance procedures to certify that the quality of supplied water conforms to the standards. Water Resource Strategy, 2002 Provides a systematic framework for water resource development and identifies action plans to avoid and resolve
conflicts and achieve water related development objectives. It has identified the need to integrate and coordinate all the uses of natural resources within the catchment basis and has laid emphasis on the development and management of water resources in a holistic, systematic manner, relying on integrated water resources
management.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
6
National EIA Guidelines, 1993 In the process of implementing National Conservation Strategy (NCS) in 1990, the government of Nepal in collaboration with The World Conservation Union - IUCN developed a locally suitable environmental assessment guideline. Although National EIA guidelines are procedural guidelines, it substantially encouraged the proponent to prepare an EIA report of the prescribed development projects and programmes and serves as the primary source of integrating environmental aspects in major development projects. The National EIA Guidelines contains objectives, methods of screening projects requiring the level of environmental assessment (IEE or EIA), scoping, impact identification and prediction, report review, monitoring and evaluation and impact auditing ensuring public participation during the preparation of the IEE/ EIA report.
c. Objectives and Scope of the Environmental Study
12. The main objective of the present IEE study for Water Supply and Sanitation purpose is to fulfill
the requirements pertaining to Rule 3, Annex G of Schedule 1 of the Environmental Protection Rules,
1997 (including amendments 1999 and 2007) and to ensure the environmental and social sustainability
of the project. It aims to help the decision makers to make informed decision about the project.
13. The specific objectives of the IEE study are as follows.
i. To identify, predict and evaluate the potential beneficial and adverse impacts of the project
on the physical, biological and socio-economical resources in the project area
ii. To suggest enhancement measures to augment the benefits of the project and to propose
suitable mitigation measures to avoid, minimize and compensate the adverse impacts of the
project
iii. To prepare appropriate Environmental Management Action Plan (EMAP)
iv. To consider the environmental impacts of project alternatives
v. To inform public about the proposed project and its impact on their livelihood
vi. To prepare an IEE as per the EPR, 1997
14. Scope: The present IEEE for the water supply and sanitation project is proposed for Shivanagar
Town of Dhangadi municipality in Kailali district. It identifies the environmental impacts and mitigation
measures relating to the location, design, construction and operation of all the project activities.
d. Relevancy of the Project
15. The proposed water supply and sanitation project is an extension of the existing district water
supply and sanitation which is meant primarily for the market area but has also been supplying a part of
the proposed service area. It is based on ground water as the source for water supply. The collected
water will be pumped in four stages to a storage tank positioned at a suitable location for distribution to
the service area.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
7
16. The main objectives of the project are to improve the water supply and sanitation facilities
including drainage and coverage and provide health and hygiene education program. The project aims
to provide improved water supply in the small towns that includes coverage of service area as per the
requirement of User’s Group with continuous 24 hours supply of drinking water and have water quality
confirming the National Drinking Water Quality Standard (NDWQS). The project will support community
participation in the development of water supply and sanitation facilities and promote community
based water quality monitoring.
17. It is expected that on implementation of the project the users of the area will be able to avail of
adequate amount of safe drinking water and need not resort to use of unsafe hand pumps to fulfill their
water needs. The proposed project will be using ground water sources (river or stream) and the
treatment capacity of the proposed units is less than 25 lps. The project does not involve construction of
any tunnels; relocation of people or households isn’t required; there is no need to settle any households
above the gravity source, and construction of river training works (more than 1 km) is not required.
Therefore, based on ADB’s guidelines and GoN’s EPR, 1997, only IEE is sufficient for the proposed
project.
18. The project needs to go through IEE process as stipulated in EPR 1997(Amendments 1999 and
2007). The proposed project will be using ground water sources (boreholes). The treatment capacity of
the proposed units is less than 25 lps. The Project does not involve construction of any tunnels;
relocation of people or households, there is no need to settle any households above the gravity source,
and construction of river training works (more than 1 km) is not required. The project will benefit some
ten thousand persons in the area with higher and better water services. The groundwater abstraction
for the proposed drinking water augmentation is very miniscule compared to the available groundwater
resources of the aquifer.
19. As the proposed project falls within the definitions provided in the EPR 1997(Amendments 1999
and 2007) Annex 1 (G) for drinking water projects; only an IEE shall be necessary. The regulation stated
in Annex 1 (H) shall only be applicable, if the proposal does not fall under categories (A) through (H) of
Annex 3. The following Table 4 compares the status of the project point by point against the conditions
defined by Environment Protection Act 1997 and Environment Protection Regulation 1997 (Annex 1,
Schedule G and Annex 3, Schedule H of EPR, 1997 and amendment 2007 ) for which a drinking water
would require IEE or EIA.
Table 4: Criteria for requirement of IEEand/or EIA for drinking water supply project against the conditions defined by EPA/EPR, 1997
S. N Condition described in the Act
and Regulations
IEE Required as per the Regulation Annex
1 g
EIA Required as per the Regulation Annex
3 h Conditions in the project
1 River Control (training) Up to 1 kilometer Over 1 kilometer NA
2 Channeling Water from one Watershed to Another
Applicable Applicable NA
3 Rain Water Collection and Use of Spewing Wetland
Up to 200 hectares More than 200 hectares
NA
4 Supply of Water in Dry Season from Surface Water Source with a safe yield of
Up to 1 cusec and utilizing up to 50 % of the available quantity
More than 1 cusec and utilizing the total
available quantity
NA
5 Ground Water Recharge Up to 50 % of total aquifer
More than 50 % of aquifer
NA
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
8
S. N Condition described in the Act
and Regulations
IEE Required as per the Regulation Annex
1 g
EIA Required as per the Regulation Annex
3 h Conditions in the project
6 Water Treatment Up to 25 litre per sec More than 25 litre per
sec
Within 25 litre per sec
7 Construction of Tunnel for Channeling Drinking Water
Tunnel constructed Not constructed
8 Water Resource Development which Displaces People Permanent Residents)
25 to 100 people Over 100 people Not done
9 Settlement of People Upstream of Water Source
Settlement of up to 500 people
Settlement of above 500 people
Not done
10 Supply of water to a population of
5, 000 to 50, 000 Over 50, 000 This is an extension of the existing system. Newer
service areas have been added and new sources
are to be tapped.
11 Connection of New Source to Supply Water to existing water supply system for a population
of
10, 000 - 100, 000 More than 100, 000 The current population is and the project is 16425
designed for a final population of 33662
12 Operation of a drinking water supply system with inclusion of sewage disposal system with
sewage treatment system
Installed Installed Sewage treatment plant not yet installed. There is a discussion going on as to the addition of a sewage
treatment plant on the south side of the bridge
over Ratuwa Mai.
13 Extraction of ground water from sources which are
located at point and non-point sources of biological and chemical pollution and/or their
influenced areas.
Not done Done No non point and point sources of pollution in the vicinity of the water source
14 Operation of water supply project included in a
multipurpose project utilizing a source of 25 liter per sec water. (Construction of
Multiple Purpose Reservoir Required)
Not operated Operated This is not a multipurpose project and is solely for
water supply
e. Approach and Methodology
20. The present Initial Environmental Examination report has been prepared based on the Terms of
Reference (TOR) approved by the Ministry of Physical Planning and Works, of the Government of Nepal
(Refer Annex 1). The study has followed the provisions outlined in the Environmental Protection Act,
1996 and Environmental Protection Regulation, 1997 and Environmental Assessment Guidelines, 2003
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
9
of the Asian Development Bank (ADB). The major activities undertaken during the preparation of IEE are
outlined below.
i. Desk study
21. Existing secondary data relevant to the proposed project was collected from various published
and unpublished sources from different governmental and non-governmental organizations. All the
related maps, aerial photographs, newspaper articles were gathered. The engineering report of the
project and other relevant documents were thoroughly reviewed. Policies, legislations and guidelines
relevant to the project were also refereed to.
22. The desk study also involved the preparation of questionnaire/checklists/matrices for detailed
field study to collect the primary data within the Zone of Influence (ZOI). In order to specify the area that
would be covered by the assessment, the geographical boundary of the influence area was delineated
on the topographical map. Depending upon the nature and extent of the expected impact area, the
Zone of Influence (ZOI) was categorized into Direct Impact Zone (DIZ) and Indirect Impact Zone (IIZ).
• Direct Impact Zone (DIZ)
23. The project area directly affected by the project activities are demarcated as Direct Impact Zone.
The service area of the project (ward no 1,5 7, 8) bounded by Urma VDC and Khutiya river in the
east,Behandi and Baiya Behandi in west, Jaligaun and Bijaynagar in north and Mohana river and
Purnabasti in south were delineated as Direct Impact Zone.
• Indirect Impact Zone (IIZ)
The area around the DIZ that could be indirectly affected due to project construction and
implementation activities such as mobility of people, equipment, vehicles, noise, dust, vibration are
demarcated as the Indirect Impact Zone.
ii. Field work
24. A detailed field investigation was carried out during April, 2011 to collect baseline information
on the physical, socio-economic and cultural environment of the project area. The local communities
were consulted to understand the social and physical nature of the area. A walkover survey was carried
out to identify the environmental structures and to gather relevant baseline information. The details of
the field study on various aspects (physical, biological and socio-economical) are as follows and the
questionnaire used for socio-economic survey of the project area is included in Annex 7
• Physical Assessment
25. Existing physical attributes of the project area were studied through topographical map and site
observation, complemented by secondary source of information from reports and interviews.
Information on the location, topography, land use, geology, and soil hydrology were collected during
field work and from the reports obtained from different institutions.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
10
• Biological Assessment
26. The ecological attributes of the area was gathered during the field survey. Information on
vegetation pattern, wildlife, parks and reserves, sensitive habitats were collected. Identification of wild
flora and fauna, rare and endangered species were done during filed observation and by questionnaire
survey. The scientific names of the flora and fauna were later recorded suing secondary data/books.
• Socio-economic Assessment
27. Socio-economic and cultural environment of the project such as population, community
structure, distribution of income and sources of livelihood, and expected water users obtained through
various secondary and primary sources of data. These included literature review, questionnaire survey,
focus group discussion, and the suggestions and comments obtained from all relevant stakeholders
though public notices and public hearing process.
iii. Data processing
28. The information obtained from the desk study and field works were processed in a standard
format to maintain consistency. The data were tabulated and maps were interpreted. The mitigation
and monitoring measures were then proposed based on the impacts identified during the study.
iv. Consultation and Information dissemination
29. Public consultation and information dissemination process has been necessary to inform the
local people and concerned agencies about the project and to obtain their concern, issues and
suggestions. The methods adopted for conducting public consultation included holding meetings with
district officials, concerned departments institutions and NGOs. Focus Group Discussions (FGDs) and
meetings were also held with the stakeholders within the Zone of Influence (ZOI). Written form of
comments and suggestions were collected from all the concerned stakeholders.
30. Similarly the information about the project was disseminated through publication in national
newspaper giving details about the project and by inviting any comments and concerns (Refer Annex 3).
A copy of the publication was also displayed in the VDC offices, educational institutions, health
institutions and other public area in the project. The final IEE report, after incorporating the comments
from concerned department and ADB, will be made available in their respective websites and will be
made available to anyone interested upon request.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
11
B. DESCRIPTION OF THE PROJECT
1. Existing Water Supply and Sanitation situation
a. Water Supply system
31. There is no improved system of drinking water supply built within the project area. The only
source of supply of water for the population of service area is ground water. They are drawing through
shallow tube wells of top layer of aquifer where the water is easily susceptible to pollution and
contamination. Most of these hand-pumps are installed by the dwellers themselves located within their
premises. No sanitary protection has been provided in these hand pumps.
32. Some wards of the municipality within the service area are partially served by Nepal Water
Supply Corporation (NWSC). The source of water for this system is also ground water drawn from deep
aquifer around 200 m deep. There are two overhead tanks, one a low head RCC overhead tank of 180
m3 capacity meant primarily for the market area. The second overhead tank is a modular steel structure
built with Japanese assistance of 200 m3capacity located at Hansapur. NWSC supplies water for six hours
a day .i.e. two hours each in the morning, day and in the evening. Although the operating hours are
inadequate for the urban households, daily water demand is supplemented by shallow hand pumps
which are easily installed in the area.
33. The water supply system operated and managed by NWSC has more than 3400 consumers,
which include domestic and institutional consumers. Initial estimates based on the total water
production and consumption indicates that a volume of about 120-140 liters per connection is being
supplied to the NWSC consumers. Assuming that a household constitutes of 6 persons, the per capita
consumption would be only about 25 lpcd. However, as mentioned earlier, households supplement their
supply by shallow hand pumps. However including the water supplied from NWSC system and shallow
hand pumps, the overall water consumption in Dhangadi including the proposed service area of
Shivanagar is about 100 lpcd
34. As described earlier, the present supply is not adequate to the consumers of the service area
and not safe. People of the service area are fetching water from shallow tube well and traditional
sources except at some area where NWSC system is partially supplying water. In most of the service
area, the present tapped sources are shallows tube well and traditional with limited yield and people are
facing hardship in fetching water. Therefore the demand of safe drinking water is high.
35. The present supply of water in the service area from NWSC system is very limited, therefore
supply is most negligible. Hence, it can be consider that supply of safe water is almost nil in the service
area and daily water demand of service area at base year (2013) at the end of design period will be
2466.cum and 4121 cum respectively. As the supply is negligible, the deficit will be the same.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
12
b. Sanitation facilities
36. Existing sanitation facilities are quite basic in Dhangadhi Municipality and the sanitary situation
of the project area is found reasonably satisfactory. Nearly 80% of households in the project area have
access to some kind of latrines. Majority of households have ventilated improved pit latrines and pour
flush latrinesand connected to septic tanks.Some of the poorer households were found to possess
simple pit latrines. Among 20% who do not build latrine, major reason behind not having latrines is
economic problems and lack of space. Very few people do not know how to build latrine and few have
habit of defecating in open space.
37. At present about 500m of open surface drain exists in the main market area of the service area,
which is not in good condition and need repair and maintenance. As reported recently, a storm water
drainage system of about 6 km long is demanded by the community of Shivanagar area. Due to lack of
proper drainage system, there occurs frequent water logging at different places mainly due to lack of
outfall structure.
38. There is no sewerage system in the project area. But the people felt necessary to have sewerage
system but due to financial constraint people may not be able to construct at present. It is observed that
about 62% of household dispose wastewater in soak pit managed by them. About 31% of households
dispose wastewater to nearby kitchen garden where as remaining household drains into public drain.
Regarding solid waste management about 85% of the household dispose domestic solid wastes in
nearby pit. Remaining households disposes to public places managed by municipality, VDC and others.
2. Type, category and need of the subproject
39. The proposed ‘Shivanagar Town Water Supply and Sanitation Project’ is ground water based
water supply system covering ward no. 1, 5, 7 and 8 of Dhangadi Municipality.The project comprises of
two major components-Water supply and Sanitation. The water supply part comprises of pumping
scheme in which two new deep tube wells and one test boring tube well will be used to exploit ground
water. The system also consists of water treatment facilities, storage tanks and overhead tanks from
where water will be distributed through distribution pipe lines. The second component is sanitation
services which include constructing school toilets; and waste water management system that has been
prepared but the implementation has yet to be decided by the town.
40. The project falls under Category B of ADB’s Environmental Categorization with potentially less
significant environmental impacts thereby requiring only an Initial Environmental Examination (IEE).It is
a demand led project. The local people of the area had submitted their request for the project and the
project has been undertaken accordingly. Although the existing water system in Dhangadhi has been
functioning for over a decade now, the reliability and quality of services availed by the consumers is very
low and services only part of the town. The proposed area does not get regular piped water supply and
majority of the households have to resort to hand pumps, which are often contaminated or have high
iron content. In this scenario, when most of water supplied is poor quality and most of the households
within the service area cannot avail proper drinking water services, the consumers in Shivanagar felt the
need for a reliable and sustainable system. In light of this situation and desire for better and improved
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
13
services, the consumers of Shivanagar organized themselves to approach the Small Towns Water Supply
and Sanitation Sector Project to assist them in their quest. As a result of their efforts, the government
has given the consent and project has been undertaken through SSTWSSSP as per their rules and
regulations.
3. Size or magnitude of operation
41. The system has been designed extract 60lps of ground water from the tube wells. There will be
two new tube wells and one test boring tube well used to exploit the ground water. The system also
consists of water treatment facilities, storage tanks at the ground of 800 m3capacity and RCC overhead
tank of 450 m3capacities that distributes water through distribution pipe line of total length 37.6 km.
42. The scheme has been designed for base population of 14858 in 2819 households (year 2013)
and a design population of 29418 in 5581 households (end of year 2027). The domestic water supply
demand for these years is presented in the following table
Table 5: Water supply demand over the years Service
Year No. of Taps Domestic Demand (cu.m) Non-
Domestic Demand (cu.m)
Total/day (cu.m) Fully
Plumbed Yard Taps
Community Taps
Non- Domestic
Taps
Total Taps
Fully Plumbed
Yard Taps
Community Taps
2013 846 1268 35 150 2299 446 435 64 157 2323 2027 3628 1395 35 260 5318 1912 478 132 378 6048
4. Proposed schedule for implementation
43. The exact schedule for implementation of the project will be known after the work has been
assigned to the contractor. For the feasibility study, detailed engineering design study and construction,
three years period has been assigned. Therefore the base year for the project has been as the year 2013
and the design year has been taken as end of year 2027.
44. The main task associated with the project will be as follows.
i. Review of detailed engineering design
ii. Preparation of working drawings
iii. Preparation of quantity and cost estimates
iv. Carrying out of economic and financial analysis and level of water tariff
v. Preparation of socio technical profile
vi. Environmental study of the sub project area
vii. Preparation of tender documents
viii. Awarding of contract
ix. Construction
x. Operation and Maintenance
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
14
45. The project has been designed in the principles of active community participation from the
design stage itself. The implementation strategy of the project is based on community management
approach. Therefore, user participation at the outset of the planning and design exercise is an essential
requirement. The community has to contribute 50% of the construction cost. Out of it, 5% has to be
deposited before implementation of the project as upfront cash, other 30% to be contributed by taking
loan from TDF, and remaining 15% to be contributed either by direct financing if the community can
afford or by taking loan from TDF. The loan is to be returned within 15 years along with the interest of
5% per annum through their affordable water tariffs. Tariff raised by the service has to support towards
maintenance of the supply system of the water supply system. DWSS is acting as the
initiator/coordinator for the purpose.
5. Description of the subproject
a. Project components
46. The Shivanagar Town Water Supply and Sanitation Project has been designed as a ground water
based water supply system that will provide sufficient quantity and good quality of water to the
residents of Dhangadi municipality. The water supply component of the project consists of construction
of following components-
i. Water supply component
• Potential Source and Intake
47. Ground Water is the only source available for the system. Three numbers of 300 mm/200 mm
diameter deep boreholes have been proposed including one no. test bore. Each borehole will have
borehole platform.
• Well Design
48. Based on the test well data so far obtained, the proposed production well (DTW) has been
designed and proposed for the installation and development. The proposed well will be 150.00 m deep
maximum having size of 300/200 mm diameter and screen of 24 length (SS Screen), The depth may be
changed and it depends on how hydro-geological features changes in the locality. This will be fixed with
lithology and electrical log of the drilled borehole during the designing of the proposed tube well.
Theoretically the well can be pumped up to 40 lps with DWL of up to 20.00 m
49. Two nos. of deep tube well are proposed to construct each with continuous production capacity
of 20 liters per second in addition to the one no of test production tube well which was completed
recently. For the design of tube well, reference has been taken from just recently completed test bore.
The average tube well depth of about 120-150 m is envisaged. The initial casing shall be of 300 mm
diameter and nearly 50 meters deep from the ground level. The screen and other tube well pipes shall
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
15
be of 200 mm diameter. All the tube well casing and pipes will be MS iron ERW. The screen sizes will be
designed to ensure 15% openings.
50. Considering static water level of 10-20 m below ground level and a drawdown of 25 m, the
pumping level below ground will be about 40-50 m. Therefore the submersible pump will be placed at
the 40-50 meters below ground level. The boreholes shall be in operation alternatively to avoid
unnecessary wear and tear and excessive drawdown and reliability.
• Borehole Platform
51. A RCC borehole platform will be constructed at each borehole with GI pipe gantry for the
installation and removal of pumps from boreholes. All the required fittings have been estimated which
will be installed on the top of the boreholes.
• Design of Motor Pump
52. 3 sets of submersible pump have been designed in project to lift up water from tube well to
ground water reservoir via aerator and pressure filter. Similarly, another 3 sets of submersible have
been designed and proposed to lift water from ground reservoir to overhead tank.
• Electrical Facilities
53. The 11 KV transmission line through 11/0.4 KV-125 KVA step down transformer to the
generator/pump house to supply electric power to the system has been proposed. A three phase 11 KV
electrical power line will connect the control panel for the pumps. For well no. 1 and 2 and other
requirements, a 125 KVA transformer is proposed whereas for well no. 3, a 50 KVA transformer is
proposed. A 140 KVA generator (standby) has been proposed with generator house for the emergency
period when there is no electricity. The control panel for generator and pumps will be installed in
generator house.
• Transmission Line
54. Transmissions (From boreholes to ground reservoir then to overhead reservoir) pipe lines has
been designed using the Hazen-Williams formula for calculating head losses in the pipe line. The
minimum and the maximum residual heads as recommended in SSTWSSSP design norms has been
followed as far as practicable. Other criteria technically suitable for smooth and economical design of
pipe lines have been taken into consideration. DI and MS pipes are proposed for conveyance of water
from tube well to treatment plant then to overhead tank (OHT).
• Treatment Facility including Chlorination
55. The quality of water obtained from the test boring has been tested; the test result shows that
quality of water is well within the NDWQS limit except turbidity and iron contents which are slightly
higher than the limit. Therefore proposed water supply system will include treatments like aeration and
filtration (pressure filters). In addition to this, chlorination will be done to remove the bacterial
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
16
contamination. These water treatment units shall treat the water such that the quality of water supplied
is in accordance with NDWQS.
• Ground and Overhead Reservoir
56. There does not exists any storage or service reservoir in the proposed service area and it is
desirable to build a ground reservoir to store treated water and an overhead RCC tank to distribute
water effectively. The ground clean water reservoir shall be a RCC tank with a capacity of 300 cum and
the distribution overhead tank shall also be 450 cum. in size. This shall optimize the system and also
regulate the supply in a reliable manner. The base of the overhead reservoir tank is proposed at an
elevation of at least 20 meters above the ground. This will insure adequate pressure at the pipeline of
the system. The capacity of the reservoir has been determined by the recommended consumption
pattern and proposed pumping hours.
• Distribution System 57. About 36 km of pipe line has been designed for the distribution system of the project. DI, GI and
HDPE pipes has been proposed wherever applicable. DI and GI pipes have been proposed for main
distribution line along the black topped and main feeder road whereas HDPE in other type of road in the
system. The distribution system comprises of a pipe networks with loops and branches. The network has
been analyzed using EPA net, a design analytical software tool based on Hazen-Williams formula for
head loss calculation. DI pipes have been proposed for pipe sizes 150 mm diameter and above. GI pipes
have been proposed up to 100 mm diameter whereas an HDPE pipe size varies between 160 mm to 40
mm diameter. Pipes size with lesser than 40 mm diameter has not been proposed in the system.
• House/Private Connection
58. The system has been designed predominantly as a house connection with a very few shared
community stand posts. The system is analyzed for a design capacity of providing for more than 2000
house connections. Consumers have been classified in two categories depending upon their choice and
present water consumption level and types of connection they want to have. Consumers having high
level of consumption are placed in fully plumbed category i.e. private connection. Consumers of low
income group, who cannot afford the water tariff of private connection, will be delivered service
through community taps.
• Community Connection
59. The opinion and requirement of WUSC has been instrumental in deciding whether community
connection is required in the service area. It has been indicated that a number of households below the
poverty line in the service area and several other households indicated their desire to have community
connection. Therefore about 10 numbers of community connections have been provided in consultation
with WUSC and beneficiaries. Each community connection will be shared among the members only who
are eligible to use it. A locking system will be provided so that only members can use the stand post.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
17
• Other System Appurtenances
60. Some other components have been proposed for the project in addition to components
explained above. Two types of valve chambers at branch points and connection points were settlement
is dense (Bazaar Area) in distribution system, fire hydrant at main corner and junction of main roads,
generator house, pump house etc have been proposed which are essential for smooth and effective
service delivery.
• Water Testing Laboratory 61. A small water testing laboratory has been provided with necessary kits to test water after and
before treatment.
• Guard Water Office Building
62. An office building has been built in the premises of overhead tank compound to run and operate
the system after completion of the project. Similarly one guard quarter has been proposed to take care
of the premises.
• Compound Wall
63. Fencing works at reservoir, treatment plants, office building, and guard quarter is required for
security reasons.
ii. Sanitation component
64. The sanitation component of the project consists of construction of storm water drainage
system (about km) in the market area; onsite sanitation program in the rural part and sewerage system
in the urban core; construction public toilet and training and awareness generation programmes for
solid waste management. A sanitation master plan with its major components such as surface drainage
system, Sewerage system waste with treatment plants, solid waste management, public and
institutional toilets with septic tanks have been conceptualized
• Surface Drainage
65. This plays the vital parts in the improvement of environmental sanitation of the project area.
But the people of the service area are not aware of its importance. At present there is about 500 m long
open drainage exist in the main bazaar area of the municipality from campus mod to Seto pul. The
condition of drainage system is not good and water logging problem has been reported in the market
areas due to lack of outfall structure. There is no other surface drainage facility in other parts. As
reported recently, a storm water drainage system of about 6km long is demanded by the community of
Shivanagar
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
18
• Solid Waste Management
66. Waste management is one of the key issues that have to be addressed to keep the environment
of the area clean. Waste disposal is a key factor for maintaining a healthy community. The solid wastes
like rubbish, garbage etc produced by the community has to be properly disposed off. This issue is more
aggravated among the low class people at low income cluster. They are not aware of the problems
created due to the haphazard dispose of solid wastes in health and hygiene. Regarding other people
having better income, they are using garbage pit near their own house or is the compound to dispose of
the solid wastes. The present situation is that about 85% of the household dispose domestic solid
wastes in nearby pit, very little households given to private collector. Therefore, the project feel and
propose, to conduct a series of training and awareness government programs to the people of the
service area so that people will get aware to reduce, reuse and recycle the wastes from the household
and will help to produce zero waste. Hence its cost has been calculated and kept as part of Conceptual
Sanitation Master Plan.
• Sewerage System and Onsite Sanitation
67. The service area comprises of bothsemi urban and rural is character. The main market area
looks like to be semi urban in character where as other parts of the service area seems to be rural in
character most of the household are scattered. Therefore in these areas, on site sanitation programme
will be suitable rather than the sewerage system. The same programme will be launched. For that public
awareness campaign and training will be conducted so that people will realize about the important of
sanitation. Efforts will be made to help and encourage people to construct private latrines by
themselves. If necessary, some subsidy has to be giving to promote the latrine construction. Even in the
core market area, sewerage system is not so much essential at present. As most of the households use
septic tanks, its timely cleaning and proper disposal of sludge is necessary at present. However, in the
long run sewerage system might be necessary to dispose of the domestic sewerage. The sewerage
system for the core market area will be designed including waste water treatment plant and nearest
efficient disposal point and their cost will be incorporated conceptual master plan
• Public Sanitation
68. Public sanitation under SSTWSSSP primarily counts for public toilets and drainage works.
Shivanagar being a sparsely populated settlement, waste management has not yet become a big
problem. So, there was not much demand for heavy investment in drainage works and public toilets.
However it may be a problem in the long run. Therefore, building of surface drainage at last in the main
core bazaar area is essential in addition to maintaining the existing surface drain. Also construction of
toilets in major service area also essential. The proposed public sanitation requirement of the project
area is constructed of institutional toilet at various schools for betterment of facilities in the schools, and
the construction of surface drain in the core market area for the better environment of the project area.
Regarding toilet construction in the schools, separate toilet units has to be build for boys and girls in
seven schools in the service area.
69. The sanitation investment needs for Shivanagar, as mentioned earlier are, construction of
school, toilet and drinking water spouts, surface drainage works in core market area (about 6km long)
and maintaining of existing drain, construction of sludge drying beds and sewerage system including
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
19
treatment plant and efficient disposal system and cost for awareness campaign and training to be
provided to users.
70. The salient features of the proposed project are presented in the following table.
Table 6: Salient Features of Dhangadhi Municipality Water Supply and Sanitation Project
S.N. Items Description
1 Name of Project Shivanagar (Dhangadhi) Town Water Supply and
Sanitation ProjeProject
2 Type Pumping (Lifting)
3 Study Level Detailed Engineering Design
4 Location Area
Region Far-Western Development Region
Zone Seti
District Kailali
VDC/Municipality Dhangadhi Municipality
Wards 1, 5, 7 and 8
5 Available Facilities
Road East-West Highway
Supply Water System NWSC and Handpumps
Electricity Available
Communication Available
Health Services Available
Banking Facilities Available
6 Source Characteristics
Source Name Deep Tubewell
Source Type Ground Water
No of well 2 (New) + 1 (test)
Source Location W.N. 1 near KM campus
Safe Yield (lps) 20*3= 60lps
7 Type of Structures
(a) Bore Hole Drilling 2 Sets proposed + 1 set existing test bore
(b) Pumps, Electricity line, Transformer and
Generator 6 Sets
(c) Overhead Tank ( Capacity / Nos.) 450 Cu. m. / One
(d) Ground Reservoir 300 Cu. m. / One
(e) Valve Chamber 02 Nos.
(f) Guard House / Boundary Wall 1 No.
(g) Generator House 1 No.
(h) Household Connection 2191 Nos.
(i) Community Tap Stand 30 Nos.
(j) Fire Hydrant 8 Nos.
(k) Electro-Mechanical Treatment Plant 3 Sets
Total Length of pipe:
Distribution Network 36070 m.
Pipe Used:
DI 8338 m. (150 to 350 mm Ø)
GI 8829 m. (125 to 40 mm Ø)
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
20
HDPE No of road crossing Length
18903 m. (40 to 110 mm Ø) Approx 24 nos in major road Approx 6 m in each crossing
8 Social Status
Present Population (2010) 15075
Base Year Population (2013) 17093
Design Year Population (2028) 31665
Weighted Growth Rate % 5 %
9 Total cost of the water supply scheme 178,794,067.00
10 Cost sharing arrangements
GoN component (50%) 89,397,033.50
TDF Loan (45%) 80,457,330.15
WUSC contribution upfront cash (5%) 8,939,703.35
11 Tariff
Average income: monthly bill (NRs/m) 342.88
Minimum HH income: monthly bill (NRs/m) 191.97
12 Economic analysis
FIRR 4.01%
EIRR 54.83%
b. Project requirements
i. Land area
71. Location of proposed components especially Overhead Tank (OHT) and Tube well boreholes
including pump house, ground tank and treatment facilities is in ward no 8 of Dhangadhi Municipality
and the valve chambers are located at various places of service area.
72. The location area of the major project structures were decided by the WUSC after successful
test boring in the site. The land was then subsequently purchased by the WUSC themselves and the
location had been accordingly surveyed and used for detailed engineering design and estimate.
73. The existing land owned by the project is 2880 sq meters which include the location of
boreholes, reservoir, treatment plant and the distribution tank and the entire area is at present non-
cultivated, with few patches of shrubs/grasses. No additional land is required for construction of any
other structures of the project. No temporary land is likely to require during the project execution. The
construction camp will be located within the compound wall of the land owned by the project. The spoil
and waste disposal site is located on the south of the project area at Shantinagar in ward no. 1.
74. The project, especially during distribution, will not entail relocation of any existing public and
private facilities such as power lines, communication lines, water supply and sewerage pipelines, canals,
foot-trails etc. The desire of the community was to have pipe lines on both sides of main roads
especially black topped roads. This will prevent frequent trench digging on this black topped road for
service connection.
75. Additional electricity line, stretching around half kilometers, is necessary from the supply point
to the OHT compound on the location of bore hole in order to pump water and operate the filtration
plant. The additional electricity line will not entail disruption of any public utilities as the adjacent area
has no settlement and cultivation.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
21
ii. Materials
76. The following table gives the main materials required during construction and operation of
Shivanagar Water Supply and Sanitation Project
Table 7: Materials required Particulars Unit Quantity Source Distance Adequacy
Reinforcement M. Ton -
Cement Bag 5798
Dhangadhi bazar
1km sufficient
Bricks Nos. -
Aggregate Cu m 587
Khutiya river
20km sufficient
Sand Cu m 1147
Khutiya river
20km sufficient
Wood Cu m -
Other Kg -
Stone Cu m -
iii. Electricity requirement
77. The power supply is basically required for the following applications:
a) Light and power to the guard house,
b) Light and power to the office building,
c) Light and power to the generator/pump control room,
d) Light and power to the treatment plant/shed,
e) Light to the STWSS compound/site, such lighting to be provided by fitting an arm to the
• Steel tubular poles or
• PCC poles or
• Poles provided solely for compound light.
78. The electrical load demand of such facilities is assessed assuming (i) lighting loads in the Guard
House and Office Building for average 6 hours a day (ii) Diesel Generator/Pump control room, Treatment
plant shed and SSTWSSP compound illumination for average 8 hours a day, while (iii) all pumps are
considered operated for total 24 hours a day.
79. At Shivanagar Wells/Bore Holes and Reservoir site of SSTWSSP, the power supply will be availed
by extending NEA 3 -phase 11 kV feeder line Tap-off from the main-road. The extended 11 kV line up to
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
22
the site (dimensions 130.7x21.48) will be terminated on an H-pole structure for mounting a distribution
transformer of adequate capacity for catering the loads of Well/Bore Hole Nos. 1 & 2.The location of
Well/ Bore No. 3 is envisaged at about 300 m away from the identified RVT/OHT site. In view of the
operational requirements of three phase pumps; three phase power supply will be availed to Well/Bore
Hole No. 3 as well, by extending 3 wire 11 kV lines on PCC poles in triangular configuration from the H-
pole structure of the RVT/OHT site. Separate transformers will cater the loads of the sites including
operational loads of the pumps. Based on average operational load, the capacity of the transformer for
Well/Bore Hole Nos. 1 & 2 is determined as100kVA and that for Well/Bore hole No. 3 as 50kVA
80. The line extensions will use 30 sq. mm. (Weasel) ACSR conductors on PCC poles with cross-arms
as per the accepted norms and practices of NEA. The PCC poles used will be of 11 m. long Type for 11 kV
lines and 9 m. long Type for LV lines and both these poles will be of NEA standard.
iv. Human resource
81. The following table gives the details of human resource (skilled, semi-skilled and unskilled labor)
required during the construction and operation and maintenance of the project.
Table 8: Human resource S.N Activities Type of Labor required (Quantity )
Unskilled labor Semi-Skilled Labor Skilled Labour
Construction work 1. Earthwork 27.08 1 2. PCC work 76.14 8.4 3. Form work and scaffolding 176.947 104.995 4. Concrete mixture and water proofing 0.60 0.50 5. Reinforcement 126 96 6. Brick work 40.35 20
7. Door and window work 10.849 109.49 8. Cement and Plaster 145 113 9. Floor and wall tiles 40 30.50
10. Painting work 25.80 35.30 11. Railing work 20.21 14.22 12. HDPE pipe laying and jointing(butt welded
joint) including fitting 22 11 10.53
13. GI pipe laying and jointing (Socket joint) excluding fittings.
72.784 11 22.485
14. Ductile Iron Pipe Laying & Jointing (Tyton joint) excluding fittings.
74.75 13.25
15 Miscellaneous works 176.661 66.377
Operation and Maintenance work S.N. Personnel (monthly) Number
1. System manager 1 2. Administrative / Account Assistant 1 3. Plant operator/ Pump operator 2 4. Plumber/Maintenance worker 2 5. Meter readers 4 6. Watch man/peon 2
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
24
v. Project activities
The following table gives the details of the project activities during the construction and operation and
maintenance phases of the project.
Table 9: Project activities S.N. Description of Activities
Construction
a. General work
i. Work related to transportation facility, survey equipment and filed assistance,
b. Civil Work
i. Surface Dressing, Earthwork, Sand Filling and Other Earth Material Related Works
ii. Brickwork
iii. Stone work
iv. Concrete Related Work for PCC, RCC, DPC, PCC Finishing & Placing of Prefabricated RCC Elements
v. Form Work for Shuttering, Reinforcement and Scaffolding Works
vi. Surface Finishing Works
vii. Wood Work
viii. Metal & Metal Related Work including Non-Pressurized GI Pipes & Fittings Works
ix. Hume Pipe Work
x. Gabion Work for River Crossing
xi. Dismantling and Re-sealing of Road
xii. Water Quality Lab Establishment
c. Pipe line, Pipe Fitting and Other Pipe Line Related Works
i. Supply of Pipe, Pipe Fitting, Pipe Laying, Pipe Jointing for Plumbing House Connection
ii. House Connection
iii. Borehole Platform
iv. Pipe supply works
v. Pipe laying and jointing works
vi. Supply and Installation of Pipe Fittings for Junction
vii. Supply and Installation of Pipe Fittings for OHT premises
viii. Supply and Installation of Pipe Fittings for OHT
ix. Supply of Pipes, Pipe Fittings for sanitary works of Guard cum Office Building at OHT premises x. Fire Hydrant
xi. Community Tap Stand Connections
d. Electrical & Mechanical Works
i. Supply, install including testing & commissioning of electrical items as per NEA standard and Engineer's instruction
ii. Electrification Works of OHT 450 m3, Guard cum Office Building at OHT premises, Generator House, Dosing
Pump House and Chemical Store
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
25
iii. Supply and Installation of Submersible Pumps
iv. Supply & Installation of Water Treatment Plant
e. Supply of Tools and Equipment
i. Supply of Tools and Equipment for Operation and Maintenance of Water Supply Distribution Network
ii. Bore Hole Drilling and Installation of 300/200mm Diameter Deep Tube Well by Rig Machine
f. Environmental Mitigation Work
i. Supply, plantation and caring of different species of flowers and plants (As per layout of the reservoir/OHT premises) and other measures as described in environmental management plan of the project and as
directed by engineer Operation and Maintenance
i. Operation and Maintenance activities including operating the system and managing personnel, energy, chemicals, office and water safety plan.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
26
Figure 1: Schematic layout of project components
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
27
Figure 2: Design layout of project components
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
28
C. DESCRIPTION OF THE ENVIRONMENT
1. Physical Resources
a. Topography
82. Kailali district is one of the two districts in Far Western Region that lies in the Terai belt of the
country. It is located between 28' 22o and 29' 05o latitude and 80' 30o and 81' 180 longitude.
Geologically, Kailali district is divided into 2 different regions, Chure and Terai belt respectively. The
proposed ShivanagarWater Supply and Sanitation Project lies in Terai belt of Seti Zone and Far Western
Development Region of Nepal. It is surrounded by Urma VDC and Khutiya River to the East, Mohana
River to the West, Geta and Beladevipur VDCs to the North and Mohana River and India to the South.
83. Topographically, the project area Shivanagar of Dhangadhi Municipality lies in the western Terai
region which is a flat terrain with an average elevation of 100 m to 110 m above mean sea level.
Figure 3: Location map of Dhangadi municipality, Kailali district
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
29
b. Geology and Soils
84. Almostthe entire landmass within the municipality consists of flat land. The project area lies in
the Southern Terai Zone and consists of main sediments of Gangetic Plain. This zone is composed of
finer sediments like sand, silt and clay. This zone is composed of finer sediments. The sediments become
finer and also show change of farcies. The water table is about 3 m below the surface.
c. Climate and Rainfall
85. Since the district covers both Terai as well as Chure region, the climate of the project area
ranges from tropical to a temperate climate type. The average maximum temperature ranges about
19oC-43oC where as average minimum temperature ranges about 7.5oC-23.5oC. However, the average
annual temperature of the district is about 38oC. The temperature rises during the pre-monsoon period
(February to May) and declines during the post monsoon season (October to January). The average
rainfall is about 1840 mm of which 80 – 85 % of the total rainfall occurs during monsoon season. The
area receives a small amount of rain brought by the south westerly winds from the Arabian Sea. It lies in
thermo-xero-chimenic bioclimatic zone represented by hot and humid bio-climates with 5-6 dry months.
d. Hydrology
86. There is a small stream, Sukuti Nala, which runs north to south between Ward No. 8 and 1 of the
project area near to the location of the proposed drilling site for the source of ground water. Another
smaller stream Kapani Nala drains from Devariya Forest to this stream. This stream finally joins Mohana
Nadi in the south.There is a pond in the middle of the Dhangadhi VDC. The water table of the area is at a
depth of around 3 meters below the surface. The following natural lakes are found in Devariyaforest in
ward no. 7, namely; Jokhar Tal (0.3 ha), Murfatta Tal (2.3 ha), Murfatti Tal (0.9 ha). Besides, this there is
a lake called Tilke Lake near the project area.
87. Apart from the surface water source as described above (which are not reliable sources), the
most reliable water source for the project area is ground water source. Two types of ground water are
available. One type is shallow tube well (Hand pump) which is used by the people in service area and
another one is deep tube well in which water has to be exploited from the inner aquifer layer. Water
from this aquifer is supposed to be safe biologically and chemically. The average depth of the aquifer is
about 120 m - 150 m inside the ground.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
30
2. Ecological Resources
a. National Parks and Protected Areas
88. No protected area exists in the project area.However Kailali district lie in the corridor of two
important conservation areas in Nepal: Bardiya national park and Suklaphanta conservation area.
Dudhiya national park lies in India across the border. These are not in the vicinity of the project area and
need not be considered for the project.
b. Forests
89. The main natural vegetation of the project are in the eastern border which is a natural forest of
sal, mixed sal-saz forest, riverine hair, jamun forest and grass land and other submerged floating and
emergent species. This can be considered the natural vegetation of the project area. Similarly lots of
mammals and birds are available in the forest and fishes found in Devariya tal.
i. Flora
90. On the eastern border of the Project area is a natural forest of sal (Shorea robusta), mixed sal
saz (Shorea robusta-Terminalia alata), forest, riverine khair-jamun (Acacia catechu-Eugenia jambolina)
forest and grassland (Imperata spp., Saccharum sp). The details of the types of vegetationfound in the
area are as follows:
• Terrestrial Vegetation
91. (a) Sal Forest: Shorea robusta is the most dominant tree species with thick lianas and under
growth. Other tree species include, Amala (Phyllanthus emblica) Bel (Aegle marmelous) Kusum
(Schleichera oleosa), Sindhure (Mallotus philippinensis) and karma (Adina cordifolia). The undergrowth
vegetation is dominated mainly by Clerodendron viscosum, Murraya koenigii and Bauhinia vahlii.
(b) Sal-saj (Shorea robusta- Teminalia alata) Forest: Shorea robusta and Terminalia alata are the
dominant species in between Jakhor Tal and Murfatta Tal. In this forest Bhalayo (Semecarpus
anacardium), Bhogate (Maesa macrophylla), (Mallotus Philippinensis) form secondary stratum.
Forests of the north-east side have a rich growth of Dhanyero (Woodfordia fruticosa).
(c) Riverine forest: The forest located near Jakhor tal, Murfutta tal and Murfutti tal area is relatively
open riverine forest dominated by Eugenia kurzi, Acacia catechu and Dalbergia sissoo, species.
Secondary stratum is composed of curry plant (Murraya koenigii), saplings of Jamun (Eugenia kurzi)
and sindure (Mallotus philippinensis).
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
31
(d) Grassland: The adjacent terrestrial grassland vegetation is equally rich comprising Cyperus
distans, Phragmites karka, Cyperus esculentus. Cyperus imbricatus, Cassia tora, Chrysopogon
acicualatus, Desmodium triflorum, Alternanthera sessilis, Phyllanthas urinaria, Cynodon dactylon,
Centella asiatica, Justicia spimplex, Imperata cylindrica. In the less grazed area, species like Cynodon
dactylon and Centella asiatica are found dominant.
• Wetland vegetation
92. Submerged species: The dominant species are Hydrilla verticillata, Chara sps., Ceratophyllum
demesrum and Utricularia aurea.
(a) Floating Species: The dominant species are Eichornia crassipes, Pistia stroites, Azolla imbicata,
Lemna minor and Wolffia sps. Ludwig sps., Nymphoea nouchalia, Potomogeton natans, and
Nelumbo nucifera . Other floating species are Ipomoea aquatica, Trapa bispinosa
(b) Emergent species: Monochoria vaginalis, Cyperus esculentus, Persicaria hydropiper are found
frequently in the Jakhor Tal. Species like Ranunculus scleratus, Phragmites karka, Saccharum
spontaneum , Marselea quadrifolia, Cyperusspp. Persicaria glabrum are dominant in the nearby
forests.
ii. Fauna
93. The mammals reported to be present in the nearby forests are listed in the table below:
Table 10: List of mammals Common Name Scientific Name Rhesus monkey Macaca mulatta Hanuman langur Presbites entellus
Jungle cat Felis chaus Fishing cat Felis viverrina Leopard cat Felis bengalensis
Panther Panthera pandrus Common mongoose Herpestes edwardsi
Jackal Canis aureus Indian Fox Vulpes bengalensis
Dhole Cuon lurtra Otter Lutra lutra
Squirrel Fanambulus sps Flying squirrel Petaurista petaurista
Jungle rat Bandicota indica Hare Lepus nigrcollis
Blue bull Boselaphus tragocamelus Sambar Cervus unicolor
Swamp deer Cervus duvauceli Chittal Axis axis
94. Some of the birds reported in the forest areas are listed in the table below:
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
32
Table 11: List of birds Common name Scientific Name Indian moor hen Gallunila chloropus
Pigmy goose Nettapus coromandeeliarnus White breasted kingfisher Halcyon smyntensis
Stork-billed kingfisher Pelargopsis indicus Pond Heron Ardeola grayii Purple Heron Ardea purperea
Large golden-backed woodpecker Chrysocolaptes lucidus Gray tit Parus major
Jungle babbler Tudoides striatus Pin tail duck Anal acuta Jungle crow Corvus macrorhynchos Spotted dove Streptopelia chinensis
Blossom headed parakeet Psittacula cyanocephala Rose ringed parakeet Psittacula krameri
Scarlet minivet Pericrococotus pandicerainus Lesser wood shrike Tephrodomis pondicerianus
Gray hornbill Tockus birostris Red whiskered bulbul Pycnonulus jocosus
Gray headed fly catcher Cullcicappa ceylonensis Red jungle fowl Gallus gallus
c. Aquatic Species
95. Fishes found in the Devariya Tal in Dhagadhi municipality are given in the table below:
Table 12: List of fishes Common Name Scientific name
Rawa Cirrhinus sps. Rohu Labeo rohita
Andha bam Amphipnos cuchia Katle Acrossochelius hexagonalepsis Bhoti Chauna gachura Bam Mastacembelus sps.
Garahi Chauna punctatus Mahasir Tor putitora Sahar Tor tor
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
33
3. Social and Cultural Resources
a. Demography
i. Population and settlement pattern
96. The total population of the municipality is 68,680 which are increasing at the rate of 4.5%. Out
of which 35,870 (52.22%) are male and 32,810 (47.77%) are female. The total number of household in
the municipality is 10,028 where 12,037 families are residing. The average household size is 6.53.
97. The total population of the project area as per socio economic survey done by the project is
15075 residing in 2435 households including rented population of 2240. This means the permanent
dwellers are 12635 out of which 6997 are male and 5838 are female.
98. Shivanagar is the part of Dhangadhi Municipality and is relatively densely populated except
some outskirt areas within ward no. 7 which is still growing. Most of the households in the project area
are pucca houses with few rural households.
ii. Caste and Ethnicity
99. The ethnic composition of the beneficiary population is presented in the table below. The major
ethnic groups in the project area are Brahmins, Chhetries and Chaudary and Rana Tharus.
Table 13: Population Distribution by Ethnicity
Ethnicity
Wards Total HHs %
1 5 7 8
Dalit 13 1 16 21 51 2.1
Janjati 161 20 244 358 783 32.2
Other 474 88 466 570 1598 65.6
Muslim 2 1 3 0.1
Total 650 109 727 949 2435 100 (Source: DWSS, 2010)
b. Health facilities
100. The district hospital exists in the municipality although not within the project area itself. There
is an Eye treatment centre and Seti Ayurvedic hospital within the Project area
101. Only about 240 households avail the services of the existing NWSC system and the rest have to
depend upon shallow handpumps. Those who have water supply from NWSC have also to use
handpumps to supplement the supply as the current supply is not adequate. The shallow hand- pump
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
34
water is prone to contamination from various infectious bacteria. The population suffers from water
borne infections.
102. The periphery within the municipality also consist different health institution. Along with Seti
Zonal Hospital there is one community hospital as well as a vaccination center and primary health care
centers whose administrative responsibility has been undertaken by the municipality.
c. Educational facilities
103. The educational status of the project beneficiaries is also quite good. Nearly 90 % of the project
population are literate and / or with higher educational status. The details of the educational status of
the project area are given in the table below.
104. There are eighteen schools and one campus (Kailali Multiple Campus) in the Project area. The
following is the list of the schools, and their locations:
Table 14: List of schools in the project area
S.N. School/ Campus Name Address, Ward No.
1 Kalika Devi English School Basanta Tole-1 2 New Era English Boarding School Laxmi Nagar-1 3 Heaven's Garden Boarding School Laxmi Nagar-1 4 Malika English Boarding School Buddha Marga-1 5 Gyan Jyoti Bidya Niketan Shivanagar-1 6 Greenland English Boarding School Shivanagar-1 7 Delight Boarding School Manehara-7 8 Sarswoti Lower Secondary School Manehara-7 9 Pashupati Boarding School Debariya-7
10 Tharu Hostel Debariya-7 11 Aristo English Boarding School Campus Road-8 12 Dhangadhi Higher Secondary School Dhangadhi Gaon-8 13 Nav Durga English Boarding School Dhangadhi Gaon-8 14 Kailali Bidya Niketan Sichhya Nagar-8 15 Three Star English Boarding School Sichhya Nagar-8 16 Api Bidya Niketan Dhangadhi-8 17 Shining Star Boarding School Dhangadhi-8
d. Physical or cultural heritage
105. There are usual temples at various locations in the project area but no culturally important place
106. However, Kailali district have several cultural and religious sites as listed below:
• Jokhar Baba Lake
• Buddha Temple
• Pashupati Temple
• Nainadevi Temple
• Kalika Bhairav
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
35
• Bandevi Temple
• Godha-Godhi Lake
• Laxmi-Narayaan Temple
• Rajyog Sewa Kendra
107. The main festivals celebrated in the area are Dashain, Tihar, Maghi, Gaura, and Holi.
e. Employment
108. Most of the populations (over 90 %) in the project area are employed. Major occupational
activity is agriculture (29.68%) and service / jobs holder (29.03%). Other activities in the project area are
business and trading (16.52 %) followed by daily wage earners (8.21%). Other occupational activities in
the area are remittance and small scale industries.
4. Economic Development and Prospect for Growth
a. Land use
109. The areas adjoining the project area even within the municipal boundary are agricultural land.
Many of the rural households are dependent upon agriculture products and the area is famous for its
paddy production. The major crops produced here are paddy, wheat, maize and seasonal vegetables
110. Land use pattern of the district shows that almost 65% of the area is covered by forest land.
About 27.8% comprises of agricultural land and only 1.94% comprises of pasture land. The remaining
part of the district has been occupied by rivers and rivulets, market area, etc which makes up about 5.43
%.
b. Infrastructure
i. Transportation
111. The Project area is located on all weather black topped road some 16 kilometers from Attariya,
the major junction of on the East-West Highway. The nearest airport is the Dhangadhi airport at Geta
VDC, where daily flights from Kathmandu provide their services. Beside, this there was airport located in
Tikapur called Tikapur Airport which at present is out of order. In addition to this the project area is near
the Indian Border and thus can also be accessed at Gauri Phanta border.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
36
112. From the bus park located in Dhangadi Municipality number of buses operate to different parts
of Nepal. Both night as well as day bus services are available in the district. Nearly all the wards of the
municipality are linked by all weather black topped road. Ward Nos. 1,2,3,4,5,6,7,8,10 and 13 are
facilitated and linked by all weather black topped road which make up about 70 km. Other than this
within the municipality, 140.4 km road has been graveled where as 200 km road is at vulnerable state as
they are not all weather road. During summer these roads gets very dusty where as during monsoons
travelling through any form of transportation is very difficult. Rickshaws are the major medium of
transportation within the municipality. Most people in the project area have bicycles which is also major
medium of transportation in Dhangadi Municipality.
ii. Drinking Water Supply
113. The existing NWSC water system is a groundwater based system with overhead tanks and
intermittent supply through private household connections. Source of water for the existing system is
groundwater boreholes, over 150 meters in depth and fitted with submersible pumps.In the district
nearly 93% population has got access to drinking water.
114. Altogether there are 3800 private tap and 13 community taps being distributed in the
municipality. The municipality is supplying drinking water through various sources which are shown in
the table below.
Table 15: Existing sources of water supply S.N Source Percent (%) 1 Pipeline 42.9 2 Well/Tube Well 50.96 3 River/Stream 4.86 4 Others 1.38
(Source: District Profile of Kailali District, 2006)
iii. Surface Drainage, Sanitation and Sewerage
115. The topography of the most parts of the service area is flat land so the need of surface drain
system is inevitable. At present there are few surface drains to drain street run-off along the highway
and in the market area but these are not in proper condition and need rehabilitation. In some area the
surface drain has been blocked by masonry materials, plastics and leaf litter as a result of which there is
overflow in certain parts along the surface drain.
116. Existing sanitation facilities are quite basic in Dhangadhi Municipality. The latrine coverage of
the project area is quite satisfactory as nearly 80% of households in the project area have access to
some kind of latrines. Majority of households have ventilated improved pit latrines and pour flush
latrines and connected to septic tanks.Some of the poorer households were found to possess simple pit
latrines.
117. Although the area covered by the municipality is 95 sq.km, the municipality has facilitated
sewerage pipeline of just 14.78 km which has not been enough for proper management of sewerages
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
37
generated in the municipality. There is absence of well managed sewerage system in the project area. It
is observed that about 62% of household dispose wastewater in soak pit managed by themselves. About
31% of households dispose wastewater to nearby kitchen garden where as remaining household drains
into public drain. Regarding solid waste management about 85% of the household dispose domestic
solid wastes in nearby pit. Remaining households disposes to public places managed by municipality and
VDC and others.
iv. Electricity
118. All the wards of the Dhangadimunicipality have electricity for household consumption supplied
by Nepal Electricity Authority (NEA) through its national grid. Altogether there are 8,363 consumers of
electricity in the municipality. A total of 105,650 households have electricity supplied from NEA and
among these only 24.6% of household have metered connection. Apart from NEA, the consumers fulfill
their electricity demand from alternative sources such Solar Home System (SHS).
v. Communications
119. Dhangadi Municipality has been facilitated by telephone and mobile phone services which
include GSM, CDMA,and sky mobile. Most of the organizations in the district have telephone as well as
internet facilities. In the district 5.38 telephone lines have been distributed per thousand people. In the
project area there are 15 cyber cafes which are providing internet facilities to the public residing within
the municipality. Majority of people living in and around municipality have television in their home.
53.7% households of the district have access to radio facility. Municipality is facilitated by different
national daily newspapers like Kantipur, Rising Nepal, Rajdhani, etc. Besides, there are altogether 15
local newspapers which are being published either on daily, weekly or monthly basis. There is also good
facility of postal service in the district as there are one district post office, 13 regional post offices and 33
additional post offices.
c. Economic Characteristics
i. Industries
120. There are no sizeable industries in and around project area but there are 153 industries
operating within the municipalities. Majority of these industries are of small scale or cottage industry.
Regarding commerce, there is no big business in the service area but few small businesses for local
residents are found running well
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
38
ii. Agricultural development
121. The areas adjoining the project area even within the municipal boundary are good for
agriculture and many of the rural households are dependent upon agriculture produce. The area is
famous for its paddy production. The major crops produced are paddy, wheat, maize and seasonal
vegetables. Beside agriculture most of the families maintain some livestock.
iii. Mineral development
122. Mineral exploitation activities are nonexistentin the project area and in the Kailali district
iv. Tourism development
123. The project area hasn’t got any significant tourist attraction, however, tourism industry is
flourishing well in the Kailali district for internal as well as external tourists. Presence of airport in the
district could be the plus point in attracting both national as well as international tourists. Jokhar Baba
and Tilke Lake could be major tourist attracting destination of the district. Jakhaur Lake
is nearestrecreational centre within the municipality for local, domestic as well as international tourists.
Presence of cool and pleasant environment with dense covering of Sal forest is major attraction of the
area around Jokhar Lake. Devariya Botanical garden if maintained and upgraded can generate lot of
national as well as international currency for the municipality through its natural beauty.
d. Development organization
124. The training centre of Agricultural Development Bank of Nepal is located in Ward no. 1. Besides
this there are several government and non-government including private institutions in the project area.
A list of the same is provided in the table below:
Table 16: List of Other Institutions in the Area
Name of the Office / Organization Address
(Ward / Cluster) Type
Agricultural Development Bank, Regional Training Centre
Basanta Tole-1 Bank
Accham Sewa Samiti Shiva Nagar-1 CBO Dudir Consultancy Overseas Shiva Nagar-1 Private
Lok Chakra Buddha Bihar Buddha Marga-1 Private
Spiritual Centre Jan Jagaran Samaj Kendra Debariya-7 NGO
NNDSWO Campus Road NGO Nav Durga Anugaman Kendra Dhangadhi Gaon-8 Spiritual Centre
Nepal Netra Jyoti Sangh Buddha Nagar - 1 NGO
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
39
Kamaiya Pratha Unmulan Samaj Shiva Nagar - 1 NGO
Nepal Dalit Samaj Kalyan Shiva Nagar - 1 NGO Tek Raj Dharmashala Ward no. 8
e. Major Environmental problems
125. Some of the environmental problems prevalent in the municipality are-
i. Lack of landfill site for solid waste management as currently solid wastes are dumped along
river side.
ii. Lack of proper management of medical wastes from Seti zonal Hospital.
iii. During the rainy season there is major problem of river bank erosion along the alignment of
the Mohana river due to which the nearby crop land suffer severe damage to its fertility and
production capability.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
40
D. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION
MEASURES
1. Beneficial Impacts and augmentation measures
126. The development of water and sanitation will have numerous beneficial impacts to individual as
well as to the entire community. Availability of clean and adequate drinking water and sanitary
environment are one of the basic human needs and any development efforts aimed at improving water
and sanitation needs of an area will significantly contribute towards improving the quality of life of that
area.
127. Some of the major beneficial impacts of the project and their maximization measures are
described below.
a. Construction Phase
• Employment generation
128. The project will generate direct employment opportunities to the local people of the area for
the construction work as project will offer opportunities for various skilled and non-skilled work forces.
The amount of money earned by the local people will directly affect the local economy thereby reducing
the chances of seasonal migration of the local people. The project will provide short term direct
employment benefit to majority of the construction workers and even long term employment to few
workers during the operation of the project. In order to augment such benefit, priority will be given to
employ local laborers as far as possible.
• Skill enhancement
129. The construction of the project will not only provide direct employment opportunities but also
ensure the transfer of skills and technical know-how to the local workforce. The project activities such as
drilling, constructing tanks, drains, slope stabilization methods will provide transferable skills. These
skills will directly benefit the local people in long term for similar activities in future. Such benefit will be
augmented by making proper work plan and code of conduct during the construction period.
• Local trade and business opportunities
130. In order to meet the food and other demands of the construction workers, there will be
opportunities to establish small market, tea shops around the vicinity of project area. The demand of
the local food items; beverages and other necessary items of the workshop will provide direct benefit to
the supplier, farmers and retailers. These will increase the local trade and business opportunities in the
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
41
area which can be augmented by providing awareness and ensuring good relation between the local
people and outside work force.
b. Operation Phase
• Improved health and hygiene
131. Deteriorating water quality and unsanitary conditions are often the causes of water borne
communicable diseases. The survey report showed that the people in the project area are mostly
dependent on water drawn from shallow tube wells which have high chances of contamination and have
high content of iron. After the implementation of the project; the health and hygiene of the local
people will improve and will help to reduce the occurrence of water borne communicable diseases in
the area. In order to enhance such benefit regular maintenance of the water supply and sanitation
components should be done so that the project operates smoothly and the benefits are intact.
• Increased economic opportunities
132. After the construction of the project, due to improved living condition, there could be increased
migration towards the town from surround rural areas which will create opportunities for shops and
other business activities in the area. Due to increased economic opportunities, the land value of the area
could increase which will uplift the economic status of the local people. These benefits can be
maximized by ensuring regular maintenance of water supply and sanitation components and by
promoting land development activities in the area.
• Benefits to women
133. Women and girls are mainly responsible for household activities such as fetching water and
cleanliness. Improved water supply and sanitation will improve the health and hygiene of women, girls
and the entire household members. The time they save from fetching water from distant location and
cleanliness can be utilized in other economic activities. The beneficial impacts to women and girls can
be enhanced by conducting health and awareness programs to the local community.
2. Adverse impacts and mitigation measure
134. The potential impacts of the proposed Shivanagar Town Water Supply and Sanitation Project are
of physical, biological and socio-cultural in nature and can occur at various phases of the project such as
design phase, construction phase and operation and maintenance phase. The magnitude of the impacts
will be small, moderate or high depending upon its severity and also will be temporary or last
permanently. The impacts are not necessarily always negative; some impacts are positive as well. The
attempt is to augment the positive impact and remove or minimize the negative impacts by applying
suitable mitigation measures.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
42
135. The summary of the anticipated environmental impacts and the mitigation measures are given
in Table 17.
a. Pre-construction Phase
i. Environmental impacts due to project location
136. Before the commencement of actual construction work, it is necessary to identify the impacts
that not only affect the environmental aspect but could also delay the construction work. Such impacts
are mostly related to the location of the project and its components. It is important to consider such
impacts as they are permanent anddirect in nature and can considerably affect the activities in latter
phase of the project.
137. One of the pre-construction impacts is the related to the location of major structures of the
system such as boreholes, reservoirs, treatment plant and sludge drying bed. There are chances of
conflict with local people during intake selection and especially on choosing the appropriate site for
sludge drying bed. Legal obstruction may result in delay of work and create unnecessary dispute. Such
issues will be mitigated by ensuring proper participation of local people and concerned agencies for
choosing appropriate location; by forming user committees that can own and manage the utility; by
conducting awareness programs and by obtaining necessary letters of approval and agreement for
acquisition of site and properties.
138. There could be risks associated with the abstraction of the ground water such as chances of
inadequate yield of the aquifer and excessive abstraction which could affect the discharge of existing
shallow tube wells and eventually lead to land subsidence. To mitigate such impacts, the design will
consider a yield monitoring program especially to measure the abstraction percentage during the dry
season flow. Project will be redesigned with alternative water sources if the proposed abstraction rate
exceeds sustainable yield. There will be gap on extraction of water and the boreholes which are to be
used alternatively to avoid excessive withdrawal.
139. There is a risk of water contamination especially in those areas where storage and distribution
tank are located.To avoid such risks, a properly protected intake and storage tanks will be constructed
and distribution pipes will be located away from drains to avoid infiltration of drain water. Similarly to
avoid the risk of pollution of ground water from seepage from the sludge drying bed, the beds will be
constructed in such a way that (e.g. use of clay liner or geo-membrane liner at the bed) there is minimal
possibility of pollution. For the risk of arsenic contamination of the ground water, the water quality will
be tested for arsenic contamination
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
43
b. Construction Phase
i. Physical Environment
• Disturbance of land system and soil erosion
140. Construction related activities such as drilling of boreholes, vibration and trench excavation
during lying of pipes and during construction of storm water drainage system, can affect the local land
system and cause soil erosion and silt run off. The unsettled street surfaces could bring about ponding of
water and create disposal problems. Since the proposed area is flat terrain, the chances of slope
disturbances and landslides are minimal. However the land disturbances and soil erosion will be
minimized by taking precautionary measures so that there is minimal vibration drilling boreholes;
excavated soil will be reused and proper backfilling of the trenches will be done and the excavated soil
will be placed safely against erosion.
• Surface and Ground water quality
141. There is a small stream Sukuti nala, which flows North to South between ward no. 8 and 1 of
the project area near to the location of the proposed drilling site and other small streams such as Kapani
nala nearby the project area. The excavated soil during the construction period, if not properly
managed, could eventually find its way to the surface water and may increase the turbidity and
sometimes reduction in dissolved oxygen in such water bodies. As far as possible, construction work will
be avoided during rainy season so that the impact will be minimal.
142. There is also possibility of pollution of ground water from the waste water generated during
drilling of boreholes and during tubewell construction. Proper protection during and after drilling will be
provided and the well will be disinfected after drilling.
• Impact from quarrying of raw materials
143. The construction of intake well, treatment plant, reservoir tanks and other structures of the
project will require river bed materials, boulders, and other construction materials. The extraction of
these materials from inappropriate places or in excessive amount can cause damage to the local
environment and accelerate erosion, landslide, disturb drainage pattern and cause water logging and
water pollution. To mitigate such impacts, unstable and erosion prone sites will be avoided for quarrying
and only safe, approved quarries will be used. Quarrying activities for extraction of construction
materials from rivers and streams will not be done so as to change the river cross sections and
longitudinal profiles. After the extraction is complete, the quarry site will be properly leveled to suit the
local landscape.
• Air and Noise pollution
144. Trucks and tractors used for the transportation of construction materials will create noise and
release emissions. The excavation activities may release dust and particulate matters and the drilling
machine may emit some dust and smokes and create noise. All these effects will be temporary and will
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
44
last during the construction period only. Use of old and worn out equipments and vehicles and low
quality fuel will be prohibited to reduce the noise and air pollution. The equipments will be checked by
technicians before the commencement of work and working night shift with equipments producing high
noise will be prohibited. To minimize the dust and particulate matters, sprinkling of water will be done
and the construction materials will be covered during transportation to avoid dust generation.
ii. Biological Environment
• Degradation of cultivated land and vegetation
145. Some of the major structures of the project will be constructed in private land. There will be no
major disturbance of vegetation in the project area but some ground vegetation has to be cleared for
the construction of those structures. Some of the topsoil and vegetation may also be lost during pipe
laying works. Minimization of vegetation clearing and careful cutting of ground vegetation will be done.
Trees and shrubs will be planted wherever possible.
iii. Socio-economic Environment
• Impact to local residents
146. The construction related activities that generates dust, noise and impede access could disturb
the local residents. To minimize the disturbances, construction work will be conducted as quickly as
possible. The local residents will be consulted and informed about the disturbances in advance.
Temporary diversions and signboards will be provided for the pedestrians.
• Problems from outside work force
147. Haphazard disposal of solid waste and improper sanitary conditions generated by the
construction workers may cause the pollution of surrounding environment and affect the health of local
people. Mechanism of safe disposal of waste will be developed in the project site and construction camp
before the actual commencement of work. Unwanted littering and discharge of waste haphazardly will
be prohibited.
148. Some social problems will arise due to irresponsible behavior of the work force such as
gambling, alcoholism and disrespect to local people and their culture. Contractor should give proper
instructions to the workers for them to act responsibly and prohibit activities such as gambling and
alcohol uptake in the work site. Given that local people are engaged in the work, it minimizes the chance
of cultural discrepancy and conflict.
• Occupational Health and Safety
149. During the construction work, the laborers involved in the construction activities will be exposed
to different level of health risks and are prone to accidents. A site health and safety plan will be
prepared encouraging use of safety measures such as mask, helmet, hand gloves and rubber boots. The
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
45
laborers will be insured for their health and safety. First aid box will be kept at a proper and easily
accessible place. General publicwill be excluded from all the construction sites.
c. Operational Phase
• Contamination of distributed water
150. Improper operation and management could lead to contamination of distributed water
increasing the chances of water related diseases in the consumers. Regular testing and maintenance of
the aeration plant, pressure filter and chlorinator and testing of residual chlorine will be done on a
routine basis and recorded. Regular water quality monitoring of water in the distribution system will be
carried out and the staff will be trained and supervised.
• Production of sub standard effluent
151. If the water treatment plant and the sanitation system does not function properly or the system
is not maintained regularly; sub standard effluent may be produced that may pollute nearby water
sources. In order to avoid that, periodic flushing and cleaning of the settling tank will be done and strong
monitoring unit will be set up. Similarly seepage due to sludge drying bed in rainy season and bed
clogging could also wash unwanted effluents which could pollute nearby water source. Therefore, the
quality of effluent and river water will be regularly monitored and regular operation and maintenance of
the sludge beds (lime spreading on beds) will be done.
• Nuisance due to operation of treatment plant and sanitary facilities
152. The operation of treatment plant and sludge drying beds and the transport of sludge could
generate nasty odor; attract rodents, vectors which couldbring disturbance to the local residents. The
treatment plant should produce no nasty odor in normal operation with proper maintenance. The effect
on air quality due to transport is negligible. However, the proper transportation vehicle will be provided
that covers the waste properly. Similarly, while cleaning of settling tank and emptying of septic tank
some bad odor is generated and health hazard to the workers are possible. The odor is temporary and
insignificant impact. Health hazard to the workers will be minimized by following proper health and
safety measures. The breeding and resting sites of the vectors will be modified or destroyed by using
appropriate chemicals or sprays.
153. There are also chances of blockage of sewer line in dry season due to disposal of solid wastes
into it. When the waste water cannot flow smoothly, it will create nuisance odor. Therefore periodic
flushing of the drain lines will be done and local people will be educated not to dump solid waste on the
drain lines.
• Impact on aquatic life
154. The discharge of sub-standard effluent and the slit runoff that find its way to nearby water
sources. The increased turbidity and effluent can pollute the water thereby affecting the aquatic life. In
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
46
order to mitigate such impacts, strong monitoring unit will be set up and regular monitoring for illegal
connections will be done.
d. Resettlement, relocation and compensation issue
155. The various system alternatives do not require resettlement of households or relocation. The
major structures are to be built either in public land or in area that have been chosen by the WUSC
themselves. The location area has been finalized after consultation with the local community and those
areas have been chosen where no households are located. Similarly, the system network for the
distribution of water will follow public property line. Therefore any issue of resettlement or relocation is
not evident with any need to compensate
Table 17: Evaluation of Environmental Impacts S.N Project Activity
Potential Environmental Impacts Nature Duration Magnitude
Water Supply Component
Location Impact 1. Location of boreholes and
reservoirs 1.1 Dispute in intake selection
1.2 Risk of insufficient yield in
the chosen area
Direct Permanent Moderate
2. Ground water pumping (abstraction)
2.1 Risk of inadequate yield of aquifer
2.2 Excessive abstraction could affect the existing shallow tube
2.3 Excessive abstraction could
lead to land subsidence
2.4 Risk of arsenic contamination
Direct Permanent (during dry
season)
Moderate
3. Location of the storage tank and distribution
system
3.1 Risk of contamination of distributed water
3.2 Spread of water epidemics
Direct Permanent Significant
4. Location of treatment plant
4.1 Conflict with local people Direct Permanent Moderate
Construction Phase Impacts Physical Environment
5. Drilling of Boreholes 5.1 Generation of waste water
5.2 Surface runoff and transportation of excavated materials to nearby bodies
5.3 Disturbance of the land system
Direct Temporary Moderate
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
47
5.4 Contamination of ground water
6. Quarrying of raw materials
6.1 Disturbance of land system, erosion and landslide
6.2 Changes in morphology of
water system
Direct Temporary Moderate
7. Trucks and tractors used for the transportation of
construction material and noise during construction
activity
7.1 Noise pollution
7.2 Air pollution due to release of emissions
Direct Temporary Small
8. Excavation and digging of trenches during drilling and
other construction work
8.1 Unorganized disposal of excavated earth
8.2 Soil erosion, silt runoff
8.3 Possible pollution of surface
water
8.4 Deterioration of air quality due to dust
8.5 Disturbance to the
pedestrians
Direct Temporary Moderate
9. Waste management and disposal
9.1 Generation of excess grease, solid waste and other
construction waste
9.2 Pollution of nearby irrigation canals and water bodies
Direct Temporary Moderate
10. Distribution pipes along the roadside
10.1 Obstruction in pedestrian and traffic movement
10.2 Removal of excavated
material can affect the local land system (erosion and soil
instability)
Direct Permanent Moderate
Biological Environment 11. Clearing of natural
vegetation (cultivated land, agricultural land)
11.1 Loss of vegetation and habitat
Direct Permanent Small
Socio-Economic Environment
12. Local residents
12.1 Local residents could be disturbed by noise, dust and
impeded access
Direct Temporary Small
13. Influx of outside workforce 13.1 Problems due to irresponsible behavior of work
force (e.g. gambling, disrespect to the local area and people)
Indirect Temporary Moderate
14 Occupational and Community Health and
Safety
14.1 Risk of accidents to the workers and public
Direct Temporary Significant
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
48
O&MPhase Impacts Physical Environment
15. Distribution of water 15.1 Risk of contamination of water in distribution system
Direct Permanent Significant
16. Operation of Treatment plant
16.1 Production of substandard effluent
Direct Permanent Moderate
Biological Environment 17. Discharge of effluent from
treatment plant
17.1 Impact on aquatic life
Indirect Permanent Small
Socio-Economic Environment 18. Use of chemicals 18.1 Health hazard to workers
and public due to unmanaged use of chlorine
Direct Permanent Significant
19. Supply connections 19.1 Connection conflict in users
Indirect Temporary Moderate
Sanitation Component
Location Impacts 20. Location of (sewerage
system) and sludge drying bed
20.1 Public health hazard
20.2 Rejection of the location by people
Indirect Permanent Moderate
21. Seepage from sludge drying bed
21.1 Pollution of ground water from seepage from sludge
drying bed
Direct Permanent Moderate
Construction Phase Impact Physical Environment
22. Excavation of soil (during construction of storm water
drainage system, sludge drying bed, latrines)
22.1 Unorganized disposal of excavated earth
22.2 Surface runoff, pollution of
water ways
22.3 Nuisance to pedestrians
22.4 Deterioration of air quality due to dust
Direct Temporary Moderate
Biological Environment 23. Clearing of natural
vegetation (cultivated land, agricultural land)
23.1 Loss of vegetation and habitat
Direct Permanent Small
Socio-Economic Environment 24. Occupational and
Community Health and Safety
24.1 Risk of accidents to the workers and public
Direct Temporary Significant
O & M Phase Impact Physical Environment
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
49
25 Operation of Storm water drainage
25.1 Blocking of drainage especially during dry season by
people throwing waste
Direct Temporary Moderate
26. Operation of sludge drying beds
26.1. Nuisance due to odor and vectors
26.2 Nuisance to the
neighboring areas due to transportation of sludge
26.3 Flooding of bed during
rainy season and bed clogging
26.4 Pollution of nearby river (Sukuti Nala) due to discharge
of effluents
Direct Permanent Moderate
27.
Operation of latrines (public and household)
27.1 Pollution of shallow ground water used for domestic purpose
27.2 Nuisance due to odor,
insects and rodents
Direct Permanent Significant
28. Solid waste management 28.1 Pollution of river water due to waste disposal
28.2 Nuisance to neighboring areas due to transportation of
waste
Direct Permanent Moderate
Biological Environment 29. Discharge of effluent and
wastes 29.1 Impact on aquatic life
Indirect Permanent Small
Socio Economic Environment 30. Cleaning of septic tank,
treatment plant and other maintenance work
30.1. Communicable disease hazard to workers
Indirect Permanent Significant
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
50
Table 18: Overview of potential environmental impacts and mitigation measures/ Shivanagar
SN Potential Environmental Impacts
Proposed Mitigation Measures Implementation timing
Responsible Institutions
Mitigation cost (NRs)
Beneficial Impacts
i Employment generation Maximize the use of local laborers Construction
Phase
Contractor No extra cost
ii Skill enhancement Maximize the use of local laborers
Make standard working plan ad code of conduct
Construction Phase
Contractor No extra cost
iii Local trade and business opportunities
Training program for local people for skill augmentation
Training program on
entrepreneurshipdevelopment
Construction Phase
PMO 50,000
iv Improved health and hygiene Ensure regular operation and maintenance of the water supply
and sanitation system
Operation and Maintenance
Phase
WUSC No extra cost
v Increased economic opportunities
Ensure regular operation and maintenance of the water supply
and sanitation system
Operation and Maintenance
Phase
WUSC No extra cost
vi Benefits to women Provide health and awareness programmes
Operation and Maintenance
Phase
WUSC, PMO 50,000
Adverse Impacts
Water Supply Component
Location Impact
1. 1.1 Dispute in intake selection
1.2 Risk of insufficient yield in the chosen area
Public consultation and awareness program
Formation of users committee
Review of design, estimates and specifications
Pre-construction Phase
DSC, DWSS 50,000
2. 2.1 Risk of inadequate yield of aquifer
2.2 Excessive abstraction could affect the existing
shallow tube
2.3 Excessive abstraction could lead to land subsidence
2.4 Risk of arsenic
contamination
A yield monitoring program, will be developed, especially for the
abstraction percentage during dry season flow
Redesign project with alternative
water source if the proposed abstraction rate exceeds
sustainable yield.
The water is proposed to be drawn from a depth of over 120m, below the impervious level which would
have insignificant effect to the existing shallow tube wells.
Furthermore, the boreholes are to
Pre-construction Phase
DSC, DWSS 20,000 (for water
quality testing)
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
51
be used alternatively to avoid excessive with drawl and pump only required amount of ground
water
Water quality analysis will be done
3. 3.1 Risk of contamination of distributed water
3.2 Spread of water epidemics
Properly protected intake and storage tanks will be constructed
and distribution pipe will be located away from drains (to avoid infiltration of drain water)
Pre-construction Phase
DSC No extra cost
4. 4.1 Conflict with local people Public consultation and awareness program
Pre-construction Phase
DSC, DWSS Covered by cost for S.N.1
Construction Phase Impact 5. 5.1 Generation of waste water
5.2 Surface runoff and
transportation of excavated materials to nearby bodies
5.3 Disturbance of the land
system
5.4 Contamination of ground water
Reuse of water by the consumers in the nearby settlements to irrigate their farmland and
vegetable gardens
While drilling boreholes minimal vibration and disturbances willbe
ensured
Proper protection during and after drilling and disinfecting after
drilling will be done
Construction Phase
WUSC, Contractors
No extra cost
6. 6.1 Disturbance of land system, erosion and landslide
6.2 Changes in morphology of
water system
Unstable and erosion prone sites will be avoided and only approved
quarrying sites will be used
Quarrying activities from rivers/streams will not be done so
as to change the river cross sections and longitudinal profiles
Quarry site will be leveled to suit
the local landscape after extraction is complete
Construction Phase
Contractor, DSC
30,000
7. 7.1 Noise pollution
7.2 Air pollution due to release of emissions
Use of old and worn out equipments and vehicles, low quality fuel will be prohibited to
reduce the noise and air pollution.
The equipments will be checked by technicians before the
commencement of work and working in night shift with
equipments producing high noise will be prohibited.
The construction material will be covered during transportation to
avoid dust generation
Construction Phase
Contractor No extra cost
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
52
8. 8.1 Unorganized disposal of excavated earth
8.2 Soil erosion, silt runoff
8.3 Possible pollution of
surface water
8.4 Deterioration of air quality due to dust
8.5 Disturbance to the
pedestrians
Precautionary measures will be taken during construction to avoid
caving
Excavated soil will be placed against erosion
Reuse of excavated soil and
backfilling of trenches will be done
As far as possible construction activities will be avoided in the
rainy season.
Sprinkling of water to avoid dust
Temporary diversions and signboards will be provided for the
pedestrians
Construction Phase
Contractor 30,000
9. 9.1 Generation of excess grease, solid waste and other
construction waste
9.2 Pollution of nearby irrigation canals and water
bodies
Mechanism of solid waste management will be developed in the project site before the actual
commencement of work
Prohibition of unwanted littering and discharge of waste
Construction Phase
Contractor Municipality
No extra cost
10. 10.1 Obstruction in pedestrian and traffic movement
10.2 Removal of excavated material can affect the local
land system (erosion and soil instability)
While excavating and laying pipes minimal vibration and slope disturbances will be ensured
Excavated soil will be dumped in outer side of trench opposite to roadside and backfilling will be
done properly
Excavated soil will be placed against erosion
Construction Phase
Contractors, No extra cost
11. 11.1 Loss of vegetation and habitat
Provision of minimization of vegetation clearing and careful
cutting of ground vegetation
Plantation of tree and shrub where ever possible
Construction Phase
Contractor WUSC
50,000
12. 12.1 Local residents could be disturbed by noise, dust and
impeded access
Work to be conducted as quickly as possible to minimize
disturbance
Residents will be consulted and informed about the disturbances in
advance
Construction Phase
Contractor No extra cost
13. 13.1 Problems due to irresponsible behavior of work
force (e.g. gambling, disrespect to the local area and people)
All the workers will be instructed to act in a responsible manner
Prohibition of alcohol, gambling
Local people will be employed as far as possible
Construction Phase
Contractor No extra cost
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
53
14 14.1 Risk of accidents to the workers and public
A site health and safety plan including safety measures such as
provision of mask, helmet, hand globes and rubber boots to
workers will be prepared and implemented
First aid will be kept at hand in
working area
General public will be excluded from all construction sites
Insurance will be provided to the
workers
Construction Phase
Contractor 100,000
O&M Phase Impacts 15. 15.1 Risk of contamination of
water in distribution system Regular testing and maintenance
of the aeration plant, pressure filter and chlorinator and testing of
residual chlorine will be done on a routine basis and recorded
Regular water quality monitoring of
water of the distribution system System staff will be trained and
supervised
Operation and Maintenance
Phase
WUSC PMO
100,000
16. 16.1 Production of substandard effluent
Periodic flushing and cleaning of settling tank
Strong monitoring unit will be set
up
Operation and Maintenance
Phase
WUSC, PMO
No extra cost (covered by
S.N.15)
17. 17.1 Impact on aquatic life
Regular monitoring of illegal pipeline connections will be done
Operation and Maintenance
Phase
WUSC No extra cost
18. 18.1 Health hazard to workers and public due to unmanaged
use of chlorine
Usage, handling and storage of chlorine will be prescribed and
guidelines developed
First aid measures will be located in emergencies
Operation and Maintenance
Phase
WUSC 50,000
19. 19.1 Connection conflict in users
Public consultation and awareness
Operation and Maintenance
Phase
WUSC 50,000
Sanitation Component
Location Impact 20. 20.1 Public health hazard
20.2 Rejection of the location
by people
Sludge drying bed will be located after consulting all the
stakeholders
Pre-construction Phase
DSC WUSC
Municipality
No extra cost
21. 21.1 Pollution of ground water from seepage from sludge
drying bed
Sludge drying bed will be properly developed to avoid possibility of pollution (Use clay liner or geo-
membrane liner at the bed)
Pre-construction Phase
DSC No extra cost
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
54
Construction Phase Impact 22. 22.1 Unorganized disposal of
excavated earth
22.2 Surface runoff, pollution of water ways
22.3 Nuisance to pedestrians
22.4 Deterioration of air quality
due to dust
Disposal against erosion and re-use of excavated soil
Sprinkling of water to avoid dust
Temporary diversions and
signboards will be provided to the pedestrians
Construction Phase
Contractors No extra cost (covered by
S.N.8)
23. 23.1 Loss of vegetation and habitat
Provision of minimization of vegetation clearing and careful
cutting of ground vegetation will be done
Trees and shrubs will be planted
wherever possible
Construction Phase
Contractor WUSC
No extra cost (covered by
son 11)
24. 24.1 Risk of accidents to the workers and public
A site health and safety plan will be prepared and implemented
Construction Phase
Contractor No extra cost (covered by
S.N.14)
25 25.1 Blocking of drainage especially during dry season by
people throwing waste
Periodic flushing of the drain lines Educating locals not to dump solid
waste
Operation and Maintenance
Phase
WUSC No extra cost (covered by
S.N.19)
26. 26.1. Nuisance due to odor and vectors
26.2 Nuisance to the
neighboring areas due to transportation of sludge
26.3 Flooding of bed during
rainy season and bed clogging
26.4 Pollution of nearby river (Sukuti Nala) due to discharge
of effluents
Regular O&M of the sludge beds (lime spreading on beds) will be
done
Vector breeding sites and resting sites will be modified (e.g. using appropriate chemicals, spray)
Providing buffer zone around the area and plant trees in the buffer
zones to cover sludge drying area
Properly covered transportation systems will be provided
Quality of effluent and river water
will be regularly monitored
Operation and Maintenance
Phase
WUSC PMO
50000
27. 27.1 Pollution of shallow ground water used for domestic
purpose
27.2 Nuisance due to odor, insects and rodents
The latrines/soak pits will be kept away from tube wells
Periodic maintenance and regular
emptying
Operation and Maintenance
Phase
WUSC Households
No extra cost
28. 28.1 Pollution of river water due to waste disposal
28.2 Nuisance to neighboring areas due to transportation of
waste
Waste sorting and disposal will be managed
Proper transportation systems will be provided (waste will be properly
covered in the vehicle)
Operation and Maintenance
Phase
WUSC PMO
No extra cost
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
55
3. Implementation of Mitigation Measures
156. Most of the mitigation measures specified are part of contractual obligation during the project
constructions and therefore will be integrated into project design and tender documents. By including
mitigation measures in the contract of in specific items in the Bill of Quantities, monitoring and
supervision of mitigation implementation will be covered under the normal engineering supervision
provisions of the contract. The mitigation measures implementation elaborated in Table 18 will be
monitored through direct observation, records of contractors, consultation with people etc weekly or
daily as required.
a. Project Design
157. For most of the adverse environmental impacts likely to occur during project construction and
operational phase, mitigation measures will be integrated in the design of the project itself so as to
strengthen the benefits and sustainability of the project. This will enhance the mitigation measures in
terms of specific mitigation design, cost estimation of the mitigation measure, and specific
implementation criteria. The proponent will ensure that the mitigations measures are included in the
design of the project
b. Project Contract
158. The project contract will clearly specify themitigations measures that are part of the project
construction and the contractor will be bound by the parameters identified in the environmental
assessment pertaining to specific mitigation measures. The proponent will ensure the compliance of the
proposed measures from the contractor and the final acceptance of the completed work will not occur
until the environmental clauses have been satisfactorily implemented.
c. Bill of Quantities
159. The tender instruction to the bidders will explicitly mention the site-specific mitigation measures
to be performed, the materials to be used, labor camp arrangements, and waste disposal areas, as well
as other site specific environmental requirements.
29. 29.1 Impact on aquatic life
Strong monitoring unit will be set up
Operation and Maintenance
Phase
WUSC No extra cost
30. 30.1. Communicable disease hazard to workers
A health and safety plan will be prepared and implemented
Operation and Maintenance
Phase
WUSC No extra cost (covered by
S.N. 15)
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
56
E. ANALYSIS OF ALTERNATIVES WITH AND WITHOUT PROJECT
SITUATIONS
160. The aim of the project is to provide safe and sufficient water supply to the residents of Dhangadi
municipality in Kailali district. The various alternatives to achieve the objectives of the project with
minimum impact to the environment are presented in the following sub-sections.
1. Design Alternative
161. The proposed project has been formulated to provide reliable and continuous drinking water
supply in adequate quantity and quality to the consumers of the service area. In order to achieve that, a
new system needed to be designed with additional sources of water, increased distribution network,
treatment plant and enhanced storage facilities. The additional system need to be integrated with
existing storage facility providing cross-connected distribution network. Ground water is the only source
available for the system. There are few small streams that run across the project area, but their yield is
very low and is not reliable source for water supply. The project has been designed to exploit ground
water from inner aquifer layer through deep tube wells. The average depth of the aquifer is about
120m-150m inside the ground and water from the aquifer is safe biologically and chemically as shown
by the water quality test results. The test boring has shown that the extraction rate is within the safe
yield. Therefore the proposed project has been envisaged to streamline the various systems and
develop a reliable and sustainable system. The present project is designed with due consideration of
these aspects and thus the proposed design has no alternative
2. Project Site/Location Alternative
162. No significant adverse environmental impacts are found with present location of the project.
The location of the treatment site has been finalized after consultation with the local community and
distribution lines are fixed where with minimum impacts on the environment. After successful test
boring, the immediate surrounding area was purchased by the user committee for the construction of
project structures. The location of the new drill sites were finalized on the basis of geo-hydrological
requirements i.e. 150m North and East of the test boring. The location of structures especially the
elevated reservoirs, borehole, and distribution pipe line will be retained as decided during interaction
with WUSC and beneficiaries. Therefore, the proposed location of the project has no alternatives.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
57
3. Alternative in Technology, Implementation Procedure and Raw Materials
163. The technologies proposed in the project are reliable. The source of water, being ground water
exploited from deep aquifer, is a reliable one. Its yield is found to be at the same range at all season.
The yield of proposed tube well is expected to be equal to or more than the yield of existing NWSC tube
wells in Dhangadi Bazaar. Altogether 3 boreholes have been proposed (include one test borehole),
which will be used alternately. For ground water, it has to be pumped against the static head of about
25 m from the borehole by mechanical and electrical equipments. The proposed source is found
technically viable for the proposed system.
164. The work involved is labor intensive and minimum use of mechanical equipments is involved.
Most of the construction work will be done by labor force which will produce minimum environmental
impacts. Trained manpower will be used so that there is minimum disturbance of the local system and
no health and safety hazards to workers arise.
165. The working procedures proposed are participatory one and the beneficiaries will be actively
participating in all the phases of the project. Except from some mechanical equipment for drilling of
boreholes, most of the raw materials used will be local in nature. Similarly, as far as possible, local
people will be employed for the project so that the chances of conflict are minimal.
4. No Project Option
166. The No-project alternative prevents the implementation of the project. Such action will impede
the local people of the area from having the facility of safe and sufficient drinking water and also living
in sanitary environment. If the project is not implemented, the people will have to continue depending
upon the existing shallow hand pumps which are not safe for drinking purpose. It also limits the chances
of socio-economic development of the area.
167. On the other hand, if the project is implemented, the people of the area not only benefit from
the supply of safe and sufficient drinking water but also improve their health and hygiene conditions.
The project implementation will create job opportunities, thereby improving the socio-economic
condition of the local people and help in improving their quality of life. . The Implementation of the
proposed project will produce only negligible and insignificant environmental impacts. The do-nothing
option will be able to avoid some minor environmental impacts; however, difficulty of having safe and
reliable water supply; remoteness and poverty of the area will remain intact.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
58
F. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION
168. One of the important objectives of IEE is to facilitate the participation of all the stakeholders and
general public right from pre-construction phase of the project to its operation. Several consultations
were held with the locals in the project area to understand their views of the project and to get their
consensus.
169. The project has involved a variety of concerned groups, including non-governmental
organizations, line agencies, community based organizations and local people while preparing the IEE
report.After the TOR was approved from MPPW on 13 February 2011, a notice was published in the
Rajdhani daily on 6 March 2011 informing the local people and stakeholders about the project and to
obtain suggestions about the possible environmental impacts and likely mitigation measures during the
implementation of the project. A copy of the notice was also displayed at concerned VDC office, local
school, health posts and other public places (Refer Annex3).
170. During the field survey Focused Group Discussions were held with the local people and public
meeting was held in local area to understand the public attitude and views and to get consensus of the
project. Written forms of suggestions were collected during the meeting and from relevant government
agencies. The recommendation letters from the concerned agency has been attached in Annex5. During
the public consultation, the project objectives were explained and people were requested to give their
opinions and suggestions. The lists of key people contacted are given in Annex 6.
171. The FGDs were held at different settlements along the ZOI of the project
Table 19: FGDs held at different locations Date Activity Address
April 11, 2011 Interaction, discussion with local people Gaurishankar tole, Ward no 5 April 12, 2011 Interaction, discussion with local people Satbhawana tole, Ward no 7 April 13, 2011 Interaction, discussion with local people Campus road, Ward no 8 April 14, 2011 Interaction, discussion with local people Main road, Ward no 1
172. The main issues raised during the public consultation were regarding-
• Information dissemination of the project (SSTWSSSP)
• Roles and responsibilities of WUSC, community and other stakeholders.
• Required cash contribution and modality of project: WUSC and community were fully aware of it
and they are ready to co-operate with the team and others during implementation of the
project.
• Reconfirmation of service area delineation: There is no change in the service area as
demarcated during feasibility study. Few areas that are not interested in the project could be
avoided.
• Change in design of distribution networks:Generally there is no change in distribution networks.
Few areas that are not interested in the project could be avoided.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
59
• Water Quality Assessment: Consumers wanted pure and potable water to drink.
Thereforeappropriate treatments have to be done to meet the quality of water as per National
drinking water quality standard
• Drainage and Sewerage System: These components are equally important to construct. But due to
lack of fund, these could not be constructed at present. Right now, in the urban area septic tanks are
in use and in the rural area pit latrines are in practice. Drainage and sewerage system should be
constructed in near future.
173. Draft IEE was sent to DWSSand ADB for review and comments. After incorporating the
comments and suggestions from all the concerned stakeholders, final IEE report will be prepared and
sent to MPPW for approval.
174. The information about the project is disclosed not just by active participation of stakeholders
during public consultation process but also formally by making the related material available in a form
and at a location that is easily accessible to the stakeholders. This normally involves making the draft
reports available (in local language) at public locations in the community and providing a mechanism to
obtain the comments and suggestions back from the community. ADB encourages governments to
upload all the documents into their website. The Executive Summary of the IEE study is made public
through depository library system and ADB websites. The full IEE of the proposed project is posted on
ADB website and also made available to the interested parties upon request.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
60
G. GRIEVANCE AND REDRESS MECHANISM
175. The projects also aim to facilitate a grievance and redress mechanism to address the
environmental and social concern of the community who are affected by the project activities. The
proposed project doesn’t involve resettlement of any community, and a Resettlement Plan that
addresses the Grievance Redress Mechanism (GRM) is not necessary. However, all the stakeholders are
to be made aware of the project-specific GRM so that there is an appropriate channel of communication
and a formalized procedure to settle dispute.
176. The process requires a GRM committee to be established as a local level to assure accessibility
to the Affected Person or Stakeholder. The committee willconsist of members with sufficient knowledge
about the project, with technical know-how and expertise and someone aware about the socio-cultural
dynamics of the community. The GRM requires that issues and comments are first lodged with the local
level GRM committee for handling of grievances at project site. The GRM committee will conduct their
meeting within 3 weeks of receipt of complaint and solution needs to be provided at meeting or within 3
weeks.
177. If the grievance cannot be solved at the project level, the GRM committees need to submit it to
the PMO. The PMO with assistance from Environmental Specialist and WUSC experts will resolve the
grievance. If the grievance cannot be solved by the PMO, it will be referred to the VDC and district
DWSS. And if the grievance cannot be resolved even by VDC and DWSS, the case will be referred to
court of law to adjudicate the matter
Figure 4: Grievance Redress Mechanism
Affected
Person
VDC
GRM Committee
PMO
WUS
C
Environmental Specialist
DWSS
Redress Grievances
Court of Law
Grievance/
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
61
H. MATTERS TO BE MONITORED WHILE IMLEMENTING THE PROJECT
AND ENVIRONMENTAL MANAGEMETN PLAN (EMP)
1. Mitigation and Monitoring
178. Environmental Monitoring is necessary to check the implementation of environmental measures
in a manner that had been prescribed earlier and to ensure that the project activity complies to the
environmental protection standards. Monitoring can be done before the project construction begins
(Baseline Monitoring); during the construction and operation phase (Impact Monitoring) and
periodically even after completion of the project activity (Compliance Monitoring).
• Construction and operation phase monitoring of the mitigation measures will mainly consider
the following impacts due to
• Construction phase: Soil erosion; sedimentation and slope stabilization; vegetation clearing;
change in hydrology of surface waters; water, air and noise pollution; solid waste; land intake ac
compensation; health, safety and sanitation of the work force; and traffic management
• Operation phase: Drinking water treatment operations; discharge of waste water into surface
waters ; sludge disposal; and quality of drinking water supplies
179. Some of the baseline monitoring that needs to be done before the start of the construction
activities so as to compare the results before and after the construction works are:
• Monitoring of air quality and noise levels (vibration) before and during the construction work
• Water quality analysis of the nearby streams (Sukuti nala, Kapani nala, Mahani nala) in order to
examine the physical, chemical and biological quality of the water.
• Water quality analysis of the shallow water hand pumps and wells at various places that is used
by the local people
180. The Monitoring Plan is designed in a way that the contractor is monitored to ensure that the
mitigation measures are followed during the construction period. It also requires regular and periodic
monitoring of the actual environmental impacts during the project operation over the years following
project completion. Summary of monitoring parameters, monitoring method, frequency and the
monitoring responsibility is presented in the following table.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
62
Table20:Environmental MonitoringSchedule Predicted Impacts
Indicators Location Monitoring Method Monitoring Frequency
Responsibility
Physical Parameters Disturbance to
the land system and soil erosion
Excavation technique
Soil disposal area
Stacking of soil
Construction site
Direct observation and record inspection
Daily during construction
Contractor DSC
Surface and ground water
quality
Water quality (Dissolved oxygen, BOD, Turbidity etc)
Laboratory Record inspection Monthly DWSS DSC
Quarrying Quarrying activity Local aesthetics
Quarry site Direct observation and contractor
records
Once DWSS DSC
Air and Noise pollution
Use of equipments and vehicles
Quality of fuel
Sprinkling of water
Use of mufflers
Construction and Operation
site
Record inspection Weekly DWSS DSC
WUSC
Biological Parameters Loss of
vegetation Cleared area
No of
trees/shrubs planted
Construction site
Observation and record inspection
Weekly Contractor WUSC
Impact on aquatic animals
Quality of effluent Construction site and outlet of treatment
plant
Record inspection Monthly WUSC DWSS
Socio-economic Parameters Problems from
outside workforce Behavior of the
workers
Uses of alcohol Records of fights
Project area Record inquiry
Local survey
Communication with people
Monthly and as needed
Contractor WUSC
Disturbance to the local people
Use of signboards, notice board
Disposal area
Project area Record inquiry Communication with
people
Weekly Contractor WUSC
Occupational Health and Safety
Type and number of accidents
First aid and
emergency services
Construction site
File record Daily DWSS
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
63
a. Monitoring Costs
181. Most of the monitoring cost for the proposed project isrelated to the expenses for experts for
observation and monitoring during construction and operation phases of the project. The following
monitoring costs are to be incurred by the project.
Table 21: Monitoring costs Expert Team Monitoring Cost Duration
(Month) Rate Amount (NRs)
Environmental Management Specialist 3 75,000 225,000 Sociologists 2 50000 100,000 Support Staff 2 20000 40,000
Cost for monitoring by MPPW/DWWS LS 200,000 Transportation and others
Report preparation LS LS
40,000 30,000
Total 635,000
2. Environmental Procedures and Institutions
182. Institutions have a crucial role to play during monitoring. There should be firm institutional
commitment by the agencies responsible for monitoring. The Ministry of Environment (MOE) is in
charge of environmental control and management for all sector agencies. The Ministry of Physical
Planning and Works (MPPW) has the overall responsibility for environmental monitoring of all water
supply and sewerage projects. In case of an EIA, it has to be finally approved by MOE. In case of an Initial
Environmental Examination (IEE), the final approval lies with MPPW.
183. The different agencies involved in the Shivanagar Town Water Supply and Sanitation Project are
as explained in the following table.
Table 22: Institutions involved in the proposed project S.N Organization Roles and Responsibilities 1. Ministry of Physical Planning and Works
(MPPW) It is the executive agency for the implementation of Second Small
Town Water Supply and Sanitation Sector Project. It is responsible for monitoring of project design, construction and
operation activities according to the approved IEE report. It is also responsible for approving the Terms of Reference (TOR) for the
IEE and approving the IEE studies.
2. Department of Water Supply and Sewerage (DWSS)
DWSS is the implementing agency for the SSTWSSP. It is responsible for ensuring that all the environmental measures to
be adopted during different phases of project implementation and operation have been fully adhered to. It is also responsible for
water quality monitoring.
3. Project Management Office (PMO) PMO under DWSS implements the project. It ensures that all the mitigation measures prescribed by approved IEE have been fully adopted. It acquires permits and approval for project construction
and assists WUSC on source registration and transfer of land ownership. It also ensures that responsibilities of other
stakeholders are incorporated as per agreements.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
64
4. Town Development Fund (TDF) TDF provides funding to the WUSC. It ensures that necessary environmental screening and assessments have been carried out
during the funding decisions.
5. Water User and Sanitation Committee (WUSC)
WUSC is responsible for forming member based water user group and registering it. It is responsible for ensuring the
implementation of environmental measures recommended especially during the construction and operation phase. Activities such as public awareness on sanitation and maintaining record of
the water quality data are some of its responsibilities.
6. Design and Supervision Consultant (DSC)
DSC is responsible for conducting the feasibility study and detailed design. It ensures that all the mitigation measures are
incorporated in the final design of the system and the environmental prescriptions are being met by the construction
contractor.
7. Contractor It is responsible to ensure that the mitigation measures are specified during the construction
184. Apart from the above mentioned agencies, there are other institutions that are directly and
indirectly involved in the project and during the IEE studies. Local bodies such as District Development
Committee (Kailali), Municipality (Dhanghadi) and Village Development Committees help in
disseminating information about the project to local people and related stakeholders and in giving
permits to conduct the IEE studies.
4. Potential Environmental Enhancement Measures
185. In parallel to the suggested mitigation measure, it is important to encourage opportunities to
enhance the project and its elements so as to have minimal environmental disturbance. The proposed
project has both positive and negative impacts and the present stage gives an opportunity to enhance
these positive features through innovative measures. Some of such potential environmental measures
include:
• Ensuring resource mobilization and participation of the local community to develop a sense
of ownership and empowerment of the project
• Determining roles and responsibilities of all the stakeholders and institutions to promote
effective coordinated action
• Providing training and awareness program in health and sanitation issues; water cost and
usage; environmental pollution and waste management
• The local youth clubs and NGO within the municipality should be mobilized to monitor the
environment in areas affected by project activity and report back the problems to PMO.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
65
5. Reporting Procedures
186. For an effective implementation of mitigation measures and Environmental Management Plan,
it is necessary to have a mechanism in place to report the entire mitigation operation plus the reports
on progress and status of each mitigation conducted.
187. The contractor has a crucial role in ensuring that the mitigation measures are implemented
during project construction phase. The contractor will develop an Environmental Mitigation Execution
Plan (EMEP) based on EMP. The contractor has to report weekly about the progress of its work together
with day-to-day practical aspect of project implementation to the DSC. It is suggested that a team
comprising of WUSC member and contract workers be established at the onset of the project to make
periodic reporting to the DSC.
188. The DSC then isresponsible for ensuring that all the procedures and final design that includes
the mitigation measures are followed.DSC is responsibleto check the weekly progress report of the
contractor and field verify whether the implementation of mitigation measures have been conducted as
decided in the EMEP or not.
189. DSC then will prepare an environmental monitoring report based on the weekly progress report
of the contractor. DSC will report the status of the project and the monitoring report to the PMO for its
review. PMO will then forward the monitoring report to review by the Environmental Specialist of the
DSC. 10 copies of the reports will be submitted to PMO every month, which will be distributed to the
responsible agencies for review. The Environmental Specialists of the DSC will then review the
comments and suggestions from the various authorities and act accordingly.
190. Monthly progress reports, including bi-annual and annual reports on the implementation of
EMP will be produced on a regular basis. The report will contain information of all the activities
conducted within the given time including the cases of non-compliance. A feedback mechanism of
reporting will be developed and based on the results of monitoring, the Environmental Management
Plan willbe adjusted accordingly.
6. Procurement Plan and Cost Estimates
191. The cost for the recommended mitigation measures and monitoring activities are described in
the section 5.3 and G.1.a. as shown in the following Table 24. Cost of mitigation measures directly linked
to the construction activities (such as erosion control measures) are not included in the cost estimates
as most of these are already included in the construction and operation and maintenance cost of the
project.
192. An independent Third Party Monitoring environmental consultant will be hired once a year for
the duration of the project to monitor whether the EMP of the project has been effectively
implemented.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
66
Table 23: Annual cost for EMP S.N. Item Cost (NRs) 1. Benefit Augmentation Measures 100,000 2. Mitigation Budget 530,000 3. Monitoring Budget 635,000 4. Independent Third Party Monitoring 300,000
Total 1,565,000
7. Work Plan
193. Before operation, PMO/DSC, with the help of its Environmental Specialists will develop detailed
work plans for implementing mitigation measure and monitoring plans based on EMP. These plans will
be incorporated into the project contracts.
194. Before construction, PMO will develop detailed responsibilities and requirements for
contractors and will provide detailed cost estimates of mitigation measures and environmental
monitoring in construction contracts.
195. Before operation, PMO will develop detailed work plans for environmental management and
monitoring during operation based on the EMP which will be submitted to the concerned persons to
help them supervise implementation
196. The EMP implementation schedule is given in following figure for a period of 2 years.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
67
Figure 5: Implementation schedule of the project
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Tendering + Award of Contract
Presentation of Security Performances
Field Mobilization
Procurement of Materials
Transportation of Materials
Structural Works
Installation Works
Piping Works
Mechanical + Electrical Works
Finishing Works
Months
Activities
Te
nd
eri
ng
+
Ap
pro
va
l o
f c
on
tra
ct
Co
ns
tru
cti
on
/ P
roc
ure
me
nt
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
68
I. CONCLUSIONS AND RECOMMENDATIONS
197. Considering the nature of the project; environmental and socio-economic situation of the area
and based on the detailed field survey and consultation with the relevant stakeholders, it can be
concluded that the proposed Shivanagar Town Water Supply and Sanitation Project will have only minor
negative impacts on the physical, biological and socio-cultural aspects of the area. The impacts are
mostly local in nature and can be easily and cheaply mitigated with suitable mitigation measures and
regular monitoring schedules.
198. The implementation of the project will have several beneficial impacts to the people of
Dhangadhi municipality in Kailali district. The local people will benefit from safe and sufficient supply of
drinking water and have improved sanitary situation. All this will significantly raise the living standard of
the people in the Dhangadi municipality.
199. From this IEE study it can be seen that the beneficial impacts of the proposed project outweighs
the negative impact and thus full scale EIA is not required. Both in terms of GoN requirement and ADB’s
requirement, a full scale EIA is not required and IEE is sufficient.
200. The present IEE study with recommended environmental mitigation and monitoring plan
becomes a complete EIA. It is proposed that the information suggested in the IEE report be well utilized
in next phases of work and monitoring plan followed up.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
69
REFERENCES
ADB (2003). Environmental Assessment Guidelines. Asian Development Bank.
ADB (2009). Safeguard Policy Statement. Asian Development Bank.
DWSS(2010). A socio-economic profile of Shivanagar Water Supply and Sanitation Project, Dhangadi
Municipality, Kailali District. Department of Water Supply and Sewerage
District Development Committee (2006). District profile of Kailali.
HMG/N (1996). Environmental Protection Act (with amendments). His Majesty’s Government of Nepal.
HMG/N (1997). Environmental Protection Rules (with amendments). His Majesty’s Government of
Nepal.
Initial Environmental Examination (IEE) on Duhabi Town Water Supply and Sanitation (2009).
Government of Nepal.Project Preparatory Technical Assistance from the Asian Development Bank.
Joshi, S. R. et al. (2010). District and VDC profile of Nepal: a socio-economic database of Nepal. Intensive
Study and Research Centre. Kathmandu.
MPPW (2011). Socio-economic profile of Shivanagar Water Supply and Sanitation Project. Ministry of
Physical Planning and Works. Prepared by Environment and Resource Management Centre. Kathmandu.
Other related Policies, Acts, Regulations and Guidelines.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
70
ANNEXES
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
71
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project Annex 1: Approved Terms of Reference
GOVERNMENT OF NEPAL MINISTRY OF PHYSICAL PLANNING AND WORKS Department of Water Supply and Sewerage
Second Small Towns Water Supply & Sanitation Sector Project
Project Management Office Panipokhari, Maharajgunj, Kathmandu
Initial Environmental Examination
for
Shivanagar Water Supply and Sanitation Project
Kailali District
[ADB GRANT NO. 41022 – (NEP)]
TERMS OF REFERENCE
December, 2010
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
72
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
TABLE OF CONTENTS 1 ORGANIZATION PREPARING THE TERMS OF REFERENCE .......................................................................... 2
2 BACKGROUND AND DESCRIPTION OF THE PROJECT ................................................................................. 22. 1 Relevancy of the Project ................................................................................................................................... 2
2. 2 Project Background .......................................................................................................................................... 4
2.2.1 Existing Water Supply System .................................................................................................................... 4
2. 2. 2 Existing Sanitation Situation ................................................................................................................... 5
2. 2.3 Essential Features of the Sub-Project........................................................................................................... 5
2. 2.4 Components of Sub-Project ......................................................................................................................... 6
2.2.5 Water Supply System................................................................................................................................... 6
2.2.6 Sanitation and Drainage ............................................................................................................................... 8
2.2.7 Sanitation Improvement ............................................................................................................................... 8
2. 3 Base Line Condition of the Project Area .......................................................................................................... 8
2.3.1 Physical Environment .................................................................................................................................. 8
2.3.2 Geo-Physical Profile .................................................................................................................................... 9
2.3.3 Ecological Profile ........................................................................................................................................ 9
2.3.4 Human and Economic Development ......................................................................................................... 12
2.3.5 Infrastructure Facilities .............................................................................................................................. 14
2.3.6 Resettlement, Relocation and Compensation Issue ................................................................................... 15
2.3. 7 Air Pollution .............................................................................................................................................. 15
3 PROCEDURES TO BE ADOPTED WHILE PREPARING THE REPORT ............................................................ 153.1 Environmental Assessment............................................................................................................................. 16
3.2 Socio-Economic Assessment .......................................................................................................................... 16
3.3 Public Participation ........................................................................................................................................ 16
4 POLICIES, LAWS, RULES, DIRECTIVES AND GUIDELINES .......................................................................... 17
5 TIME, ESTIMATED BUDGET AND SPECIALIST/EXPERTS REQUIRED .......................................................... 185.1 Time Schedule and Work Plan ....................................................................................................................... 18
5.2 Estimated Budget............................................................................................................................................ 18
5.3 Resource Persons ............................................................................................................................................ 18
6 ANTICIPATED IMPACTS OF THE PROPOSED PROJECT .............................................................................. 18
7 ANALYSIS OF ALTERNATIVES TO THE PROPOSED PROJECT ..................................................................... 18
8 MITIGATION MEASURES ........................................................................................................................ 19
9 MATTERS TO BE IMPLEMENTED WHILE IMPLEMENTING THE PROJECT .................................................. 199. 1 Environmental Management Plan................................................................................................................... 19
9. 2 Environmental Monitoring Plan ..................................................................................................................... 19
9. 3 Information Disclosure, Public Consultation and Participation ...................................................................... 20
9. 4 Grievance Redress Mechanism ...................................................................................................................... 20
10 REPORTS ................................................................................................................................................ 20
11 RELEVANT INFORMATIONS .................................................................................................................... 21
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
73
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
LIST OF TABLES Table 2.1: Criteria for requirement of IEE and/or EIA for Drinking water supply Projects as per Annex 1 and
Schedule g and Annex 3 schedule h of Environment Protection Regulation 1997 amendment 2007 compared with the situation of the project ...................................................................................3
Table 2.2 : Salient Features of Shivanagar Town Water Supply and Sanitation Project.............................5 Table 2.3 : Mammals in the Project Area .............................................................................................. 10 Table 2.4: List of Birds in the Project Area ............................................................................................ 11 Table 2.5 : List of Fishes Found in the Project Area ............................................................................... 11 Table 2.6 : Population Distribution by Ethnicity .................................................................................... 12 Table 2.7 : Gender Ratio ...................................................................................................................... 12 Table 2.8 : Ownership of Houses in the Project Area ............................................................................ 12 Table 2.9 : Educational Status of the Project Area ................................................................................ 13 Table 2.10 : List of Schools in the Project Area ..................................................................................... 14 Table 2.11 : List of Other Institutions in the Area ................................................................................. 15 Table 5.1 : Proposed Work Schedule .................................................................................................... 18
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
74
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
ACRONYMS AND ABBREVIATIONS ADB Asian Development Bank BPT Break Pressure Tank CAD Computer Aided Design CAP Community Action Plan DDC District Development Committee DWSO District Water Supply Office DWSS Department of Water Supply and Sewerage EIA Environmental Impact Assessment EMAP Environmental Management Action Plan EMP Environment Management Plan EPA Environment Protection Act EPR Environment Protection Regulation FGD Focus Group Discussion FIDIC Federation Internationale Des Ingenerus Conseils GoN Government of Nepal HH (s) Household (s) HMG/N His Majesty's Government of Nepal IEE Initial Environmental Examination KUKL Kathmandu Upatyaka Khanepani Limited LPCD/lpcd Liter per capita per day lpd Liter per day lps Liter per second MOPE Ministry of Population and Environment MPPW Ministry of Physical Planning and Works NGO Non Government Organization PMO Project Management Office PWD Public Work Directories QOL Quality of Life RWSSP Rural Water Supply and Sanitation Program S.N Serial Number STWSSSP Small Towns Water Supply and Sanitation Sector Project TDF Town Development Fund ToR Terms of Reference TPO Town Project Office VDC Village Development Committee WSS Water Supply and Sanitation WSST Water Supply and Sanitation Technician WUC Water Users' Committee WUG Water User's Group WUSC Water User's and Sanitation Committee
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
75
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
INITIAL ENVIRONMENT EXAMINATION Terms of Reference for the Shivanagar Town Water Supply, Drainage and Sanitation Project
1 ORGANIZATION PREPARING THE TERMS OF REFERENCE
The Environment Protection Regulations of 1997 (amended in 2007) mentions that a ToR for an IEE is required. This ToR is prepared to carry out Initial Environmental Examination (IEE) of Shivanagar Water Supply and Sanitation Project in Kailai District. The project proponent, STWSSSP of Government of Nepal, Ministry of Physical Planning and Works, Department of Water Supply and Sewerage (DWSS) is responsible for the preparation of IEE report.
Name of the Proponent: Project Management Office Second Small Towns Water Supply and Sanitation Sector Project Department of Water Supply and Sewerage Ministry of Physical Planning Works Government of Nepal
Address of the Proponent: Panipokhari, Kathmandu Tel: 977 1 4423848, 977 1 4412348 Fax: 977 1 4413280 E-mail: [email protected] Website: www.sstwssp.gov.np
2 BACKGROUND AND DESCRIPTION OF THE PROJECT
2. 1 Relevancy of the Project
As per the TOR issued to the EDCs, it is stated that the Project needs to be studied from the environmental point of view as per EPA 1997 and EPR 1997(Amendments 1999 and 2007). The proposed water supply and sanitation project is an extension of the existing DSTWSS which is meant primarily for the market area but has also been supplying a part of the proposed service area. It is expected that on implementation of the project the users of the area will be able to avail of adequate amount of safe drinking water and need not resort to use of unsafe hand pumps to fulfill their water needs. The project needs to go through IEE process as stipulated in EPR 1997(Amendments 1999 and 2007). The proposed project shall be using ground water sources (boreholes). The treatment capacity of the proposed units is less than 25 lps. The Project does not involve construction of any tunnels; relocation of people or households, there is no need to settle any households above the gravity source, and construction of river training works (more than 1 km) is not required. The project shall benefit some ten thousand persons in the area with higher and better water services. The groundwater abstraction for the proposed drinking water augmentation is very miniscule compared to the available groundwater resources of the aquifer. As the proposed project falls within the definitions provided in the EPR 1997(Amendments 1999 and 2007)
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
76
Annex 1 (G) for drinking water projects; only an IEE shall be necessary. The regulation stated in Annex 1 (H) shall only be applicable, if the proposal does not fall under categories (A) through (H) of Annex 3. Table 2.1 compares the status of the project point by point against the conditions defined by Environment
2
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
77
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Protection Act 1997 and Environment Protection Regulation 1997 (and its amendments 2007) for which a
drinking water would require IEE or EIA. Table 2.1: Criteria for requirement of IEE and/or EIA for Drinking water supply Projects as per Annex 1 and Schedule g and Annex 3 schedule h of Environment Protection Regulation 1997 amendment 2007 compared with the situation of the project S. N Condition described in IEE Required as EIA Required Conditions in the
the Act and Regulations per the Regulation as per the project Annex 1 g Regulation Annex 3
h
1. River Control (training) Up to 1 Over 1 NA
kilometer kilometer
2. Channeling Water from Applicable Applicable NA
one Watershed to Another
3. Rain Water Collection and Up to 200 More than 200 NA
Use of Spewing Wetland hectares hectares
4. Supply of Water in Dry Up to 1 cusec More than 1 NA
Season from Surface Water and utilizing up to cusec and utilizing
Source with a safe yield of 50 % of the the total available
available quantity quantity
5. Ground Water Recharge Up to 50 % of More than 50 NA
total aquifer % of aquifer
6. Water Treatment Up to 25 litre More than 25 Within 25 litre per per sec litre per sec sec
7. Construction of Tunnel for Tunnel Not constructed
Channelling Drinking Water constructed
8. Water Resource 25 to 100 Over 100 Not done
Development which people people
Displaces People
Permanent Residents)
9. Settlement of People Settlement of Settlement of Not done
Upstream of Water Source up to 500 people above 500 people
10. Supply of water to a 5, 000 to 50, Over 50, 000 This is an extension population of 000 of the existing system. Newer service areas have been added and
new sources are to be
tapped.
11. Connection of New Source 10, 000 - 100, More than The current
to Supply Water to existing 000 100, 000 population is and the water supply system for a project is 16425
population of designed for a final
population of 33662
12. Operation of a drinking Installed Installed Sewage treatment water supply system with plant not yet installed. inclusion of sewage There is a discussion
disposal system with going on as to the
sewage treatment system addition of a sewage treatment plant on the south side of the bridge
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
78
over Ratuwa Mai.
13. Extraction of ground water Not done Done No non point and point from sources which are sources of pollution in
located at point and non- the vicinity of the water
3
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
79
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
point sources of biological source
and chemical pollution
and/or their influenced
areas.
14. Operation of water Not operated Operated This is not a
supply project included in a multipurpose project multipurpose project and is solely for water utilizing a source of 25 liter supply
per sec water.
(Construction of Multiple
Purpose Reservoir
Required)
2. 2 Project Background
The proposed Shivanagar (Dhangadhi) Town Water Supply and Sanitation Project has been envisaged to serve ward nos. 1,5,7 and 8 of Dhangadhi Municipality in Kailali District of Far Western Development Region of Nepal. It is a demand led project. The people of the project area had submitted their request for the project and the project has been undertaken accordingly.
The project area Shivanagar (Dhangadhi) is located at 28
0 48' N latitude 80
0 33' E longitudes on the south
of east west highway and about 16km south of Attariya. It is situated in the southern part of Kailali district having about 3.5 km east- west length and about 3 km north south width. The Shivanagar (Dhangadhi) Town Water Supply and Sanitation Project lies within the Dhangadhi Municipality. It is located on all weather black topped road some 16km from Attariya, the major junction on the east west highway. It is connected with the Kohalpur- Mahanedranagar highway. As it is linked with National Highway, day and night bus services are easily available. The nearest airport is at Geta which is only 8 km away, which has regular air services to Kathmandu. The project area is near the Indian border and be accessed at Gauriphanta border.
2.2.1 Existing Water Supply System
There is no improved system of drinking water supply built within the project area. The only source of supply of water for the population of service area is ground water. They are drawing through shallow tube wells of top layer of aquifer where the water is easily susceptible to pollution and contamination. Most of these hand-pumps are installed by the dwellers themselves located within their premises. No sanitary protection has been provided in these hand pumps. However some wards of the municipality within the service area are partially served by Nepal Water Supply Corporation (NWSC). The source of water for this system is also ground water drawn from deep aquifer around 200 m deep. There are two overhead tanks, one a low head RCC overhead tank of 180 cu.m capacity meant primarily for the market area. The second overhead tank is a modular steel structure built with Japanese assistance of 200 cu.m capacity located at Hansapur. Since the existing NWSC system serves the proposed service area only partially, the consultant have carried out a thorough assessment of the system to learn about the features of the system, water resources of the area and operational difficulties among others. Therefore, the existing condition of water supply in the area is good enough to justify a reasonable water supply system for the community.
The existing water supply system managed by NWSC is operated for six hours a day i.e. two hours in the morning, two hours during the day, and another two hours in the evening. Although the operating hours are inadequate for the urban households, daily water demand is supplemented by shallow hand pumps which are
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
80
easily installed. In the area where shallow tube wells are using as source of supply such problem does not visualized.
4
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
81
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
The water supply system operated and managed by NWSC has more than 3400 consumers, which include domestic and institutional consumers. Rests of the people are drawing water from their shallow hand pumps. 2. 2. 2 Existing Sanitation Situation
Existing sanitation facilities are quite basic in Dhangadhi Municipality. The sanitary situation of the project area is found reasonably satisfactory. The latrine coverage of the project area is quite satisfactory. Nearly 80% of households in the project area have access to some kind of latrines. Majority of households have ventilated improved pit latrines and pour flush latrines and connected to septic tanks. Some of the poorer households were found to possess simple pit latrines. Among 20% who do not build latrine, major reason behind not having latrines is economic problems and lack of space. Very few people do not know how to build and few have habit of defecating in open space. At present there is about 500 m of open surface drain exist in the main market area of the service area, which is not in good condition and need repair and maintenance. As reported recently, a storm water drainage system of about 6 km long is demanded by the community of Shivanagar area. Due to lack of proper drainage system, there occurs frequent water logging at different places mainly due to lack of outfall structure. There is no sewerage system in the project area. But the people felt necessary to have sewerage system but due to financial constraint people may not be able to construct at present. It is observed that about 62% of household dispose wastewater in soak pit managed by them. About 31% of households dispose wastewater to nearby kitchen garden where as remaining household drains into public drain. Regarding solid waste management about 85% of the household dispose domestic solid wastes in nearby pit. Remaining households disposes to public places managed by municipality and VDC and others.
2. 2.3 Essential Features of the Sub-Project
The project is designed in the principles of active community participation from the design stage itself. The implementation strategy of this sub-project is based on community management approach. Therefore, user participation at the outset of the planning and design exercise is an essential requirement. The community has to contribute 50% of the construction cost. Out of that 5% have to be deposited before implementation of the project as upfront cash. Another 30% to be contributed taking loan from TDF. Rest 15% to be contributed either b direct financing if the community in capable or by taking loan from TDF The loan is to be returned within 15 years along with the interest of 5% per annum through their affordable water tariffs.Tariff raised by the service has to support towards maintenance of the supply system of the water supply system. DWSS is acting as the initiator/coordinator. The salient features of the Shivanagar (Dhangadhi) Small Town Water Supply and Sanitation Sub-project are:
Table 2.2 : Salient Features of Shivanagar Town Water Supply and Sanitation Project
S.N. Items Description 1 Name of Project Shivanagar (Dhangadhi) Town Water Supply and
Sanitation Project 2 Type Pumping (Lifting) 3 Study Level Detailed Engineering Design
4 Location Area
Region Far-Western Development Region
Initial Environmental Examination(IE
Zone
District
VDC/Municipali
ion(IEE) of Shivanagar Town Water Supply and Sanitatio
Seti Kailali
ipality Dhangadhi Municipality
itation Project
82
lity
5
Initial Environmental Examination(IEE
Initial Environmental Examination
Wards
5 Available Facilities
Road
Supply Water S
Electricity
Communication
Health Services
Banking Facilitie
6 Source Characteristics
Source Name Source Type
Source Location
Safe Yield (lps)
7 Type of Structures
(a) Bore Hole Drillin
(b) Pumps, El
Transformer and Generato
(c) Overhead Tank
Nos.)
(d) Ground Reservo
(e) Valve Chamber
(f) Guard House / B
(g) Generator House
(h) Household Conn
(i) Community Tap S
(j) Fire Hydrant (k) Electro-Mechan
Plant
Total Length of pipe:
Distribution Network
Pipe Used: DI GI HDPE 8 Social Status Present Populat
Base Year Popu
Design Year Pop
Weighted Grow
2. 2.4 Components of Sub-Pr
The major components of a grboreholes with pumps, treatment
2.2.5 Water Supply System
a. Source
n(IEE) of Shivanagar Town Water Supply and Sanitation
ion (IEE) of Shivanagar Town Water Supply and Sanitatio
1, 5, 7 and 8
East-West Highway er System NWSC and Handpumps
Available tion Available ices Available ilities Available
istics
Deep Tubewell Ground Water
tion W.N. 5 lps) 25 lps
rilling 2 Sets Electricity line, 1 Sets
rator
ank ( Capacity / 450 Cu. m. / One
ervoir 800 Cu. m. / One ber 90 Nos. / Boundary Wall 1 No. ouse 1 No. onnection 1941 Nos. ap Stand 71 Nos.
8 Nos. hanical Treatment 1 Set
pe:
ork 45702 m.
6384 m. (150 to 350 mm
14102 m. (125 to 40 mm
25216 m. (40 to 110 mm
ulation (2007) 143
opulation (2013) 164
r Population (2028) 336
rowth Rate % 4.9
Project
groundwater based water supply system in the Tnt units, ground and overhead RCC reservoirs, valv
em
ation Project
83
itation Project
mm Ø) mm Ø) mm Ø)
14331 16425 3362 4.9 %
Terai consists typically of alve boxes and distribution
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
84
The source of water for the system is groundwater and therefore, deep tubewells will be drilled in places with good potential for groundwater yield. The borehole is proposed to be located either near the Kailali Multiple Campus and thereabouts in ward no. 5 of Dhangadhi Municipality (the first alternative) or near
6
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
85
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
the Gauri Shanker Tole in ward no. 5 (the second alternative). At the feasibility stage and based on the assessment of tube wells drilled in the Dhangadhi Municipality and adjoining areas, tubewells of average depth of about 120 meters is envisaged. The initial casing shall be of 300 mm diameter and nearly 50 meters deep from the surface.
b. Pump Submersible pumps with the required capacity to serve the design year demand have been recommended to be installed in the boreholes. Submersible pumps of various capacities ranging from 30 – 35 HP shall be installed in the boreholes to pump water to the groundwater reservoir via the water treatment plant. Similarly, from the ground clean water reservoir to the overhead RCC tank, submersible pumps of 25 – 30 HP capacity will be installed to pump clean water to the overhead tank for distribution. The pumps will be connected to the control board by flat submersible cable. Each borehole shall have pumps installed and one pump will be provided as a standby
c. Treatment Process The proposed groundwater system will have adequate treatment processes comprising of Electro-mechanical treatment plants (aeration and pressure filters) at the proposed overhead RCC tanks. These water treatment units shall treat the water such that the quality of water supplied is in accordance with the Nepal water quality standards and WHO drinking water guidelines/Nepal Drinking Water Quality Standard (NDWQS)-2062.
d. Ground Reservoirs / Overhead Tanks It is proposed to build a ground level reservoir to store treated water and an overhead RCC tank to distribute water effectively. The ground level clean water reservoir shall be a circular RCC tank with a capacity of 800 cu. m and the distribution overhead tank shall be a circular RCC tank of450 cu. m. in size. The base of the overhead reservoir tank is proposed at an elevation of al least 20 meters above the ground to ensure adequate pressure at the pipeline of the system. The Consultants also recommend that appropriate geotechnical investigations be carried out during the design phase at the reservoir locations to determine the soil properties
e. Distribution Pipe Lines The distribution system comprises of a pipe network, which are looped in certain cases and branched in other. The entire system has been designed using GI, HDPE and DI pipes. The size of DI pipes is 150 mm and above. The total pipe length of the proposed distribution system works out to be over 40 km.
f. House Connections The system has been designed predominantly as a house connection with a very few shared community stand posts. The system will have a design capacity of providing for more than 2000 house connections. The house connection shall comprise of about 24 meters of pipe connection and water meter with proper casing.
g. Community Stand Posts Seventy-one numbers of community stand posts has been provided as per the desire and requirement of the community. These stand posts will be made of brick masonry with proper facilities for washing, drainage and placing vessels for water
h. Electrical Supply The 11 kV transmission line through an 11/0.4 kV – 100 and 50 kVA step down transformer to the pump house, will supply electrical power. A three-phase power line will connect the control panel to the pump.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
87
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
i. Office Buildings / Guard House
Guard quarter(s) with minimum space has been proposed at the reservoir site. In addition, boundary wall has been proposed to safeguard storage tanks from vandalism as well as contamination.
j. System Appurtenances
These shall primarily comprise of valve chambers to house flow control valves, control valves for
controlling flow etc. Altogether 90 valve chambers are expected in the system. 2.2.6 Sanitation and Drainage Public sanitation under SSTWSSSP primarily counts for public toilets and drainage works. Shivanagar being a sparsely populated settlement, waste management has not yet become a big problem. So, there was not much demand for heavy investment in drainage works and public toilets. However it may be a problem in the long run. Therefore, building of surface drainage at last in the main core bazaar area is essential in addition to maintaining the existing surface drain. Also construction of toilets in major service area also essential. The proposed public sanitation requirement of the project area is constructed of institutional toilet at various schools for betterment of facilities in the schools, and the construction of surface drain in the core market area for the better environment of the project area. Regarding toilet construction in the schools, separate toilet units has to be build for boys and girls in seven schools in the service area.
2.2.7 Sanitation Improvement
a. Support for On-Site Sanitation at Household Level
On-site sanitation is proposed for the sub-project. However, support in form of subsidy to the household toilet construction also required, targeted for the poor households who are unable to afford the construction of the toilet on their own. Without the subsidy the overall sanitation program will face failure as the poor who cannot afford toilets and will continue open defecation. The subsidy will include the toilet construction materials (pan, pipes, concrete slabs, etc.) to the deserving poor families who are willing to construct a private
b. Storm Water Drainage
Storm Water drainage covering the core area is proposed. Brick masonry covered drains will be constructed along the inner roads and a piped drain constructed where the road is in embankment.
c. Solid Waste Management A land fill site shall be selected at a suitable place.
2. 3 Base Line Condition of the Project Area
2.3.1 Physical Environment
The proposed Shivanagar (Dhangadhi) Town Water Supply and Sanitation Project has been envisaged to serve ward numbers 1, 5, 7 and 8 of Dhangadhi Municipality. The data collected during the feasibility study
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
88
showed that the total number of households are around 2429 (population 7690) within the proposed service area.
8
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
89
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
The Project area is located on all weather black topped road some 25 kilometers from Attariya, the major junction of on the East-West Highway. The nearest airport is the Dhangadhi Airport at Geta VDC, where daily flights from Kathmandu provide their services. In addition to this the Project area is near the Indian Border and also be accessed at Gauri Phanta border.
2.3.2 Geo-Physical Profile
a. Topography Topographically, the project area Shivanagar (Dhangadhi ) lies in the terai region and is generally flat with an average elevation is 100 to 110 m. above the mean sea level.
b. Geology and Soils
The Project area lies in the Southern Terai Zone and consists of main sediments of Gangetic Plain. Basically, sand, silt and clay are the main sediments of the soils of this zone. This zone is composed of finer sediments. The sediments become finer and also show change of farcies. The water table is about 3 m below the surface
c. Climate
The area has a tropical monsoon type of climate. The average rainfall ranges between 1630 – 1705 mm. 80 – 85 % of the total rainfall occurs during mid June to late September) Highest rainfall was recorded as 522 mm in July. The area receives a small amount of rain brought by the south westerly winds from the Arabian Sea. It lies in thermo-xero-chimenic bioclimatic zone represented by hot (mean daily temperature greater
than 15oC) and humid bio-climates with 5-6 dry months. The average monthly maximum temperature
ranges from 21.9oC to 37.2
oC from 5.4
oC to 25.8
oC. The temperature rises during the pre-monsoon period
(February to May) and declines during the post monsoon season (October to January)
d. Surface and Ground Water
There is a small stream, Sukuti Nala, which runs north to south between Ward Nos 8 and 1. of the project area near to the location of the proposed drilling site for the source of ground water. Another smaller stream Kapani Nala drains from Devariya Forest to this stream. This stream finally joins Muhana Nadi in the south. There is a pond in the middle of the Dhangadhi Gaun. The water table of the area is at a depth of around 3 meters. The following natural lakes are found in Devhariya Forest in Ward No. 7, namely; Jakhor Tal (0.3 ha), Murfatta Tal (2.3 ha), Murfatti Tal (0.9 ha). This part of the Ward is not included in the Project area but is now developing into a Botanical garden by the Government. 2.3.3 Ecological Profile The main natural vegetation of the project are in the eastern border is natural forest for sal, mixed sal saz forest, riverive hair, jamun forest and grass land and other submerged floating and emergent species. This can be considered the natural vegetation of the project area. Similarly lots of mamals and birds are available in the forest and fishes found in Devariya tal. The details of the types of flora and fauna found in that area are as follows:
A. Flora On the eastern border of the Project area is a natural forest of sal (Shorea robusta), mixed sal saj (Shorea robusta-Terminalia alata), forest, riverine khair-jamun (Acacia catechu-Eugenia jambolina) forest and
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
90
grassland (Imperata spp., Saccharum spp). This can be considered the natural vegetation of the project area. The details of the types of forest found in that area are as follows:
9
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
91
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Terrestrial Vegetation
(a) In sal forest, Shorea robusta is the most dominant tree species with thick lianas and under growth,
other tree species include, Amala (Phyllanthus emblica) Bel (Aegle marmelous) Kusum (Schleichera oleosa), Sindhure (Mallotus philippinensis) and karma (Adina cordifolia). The undergrowth vegetation is dominated mainly by Clerodendron viscosum, Murraya koenigii and Bauhinia vahlii.
(b) Sal-saj (Shorea robusta- Teminalia alata) Forest: Shorea robusta and Terminalia alata are the dominant species in between Jakhor Tal and Murfatta Tal. In this forest Bhalayo (Semecarpus anacardium), Bhogate (Maesa macrophylla), (Mallotus Philippinensis) form secondary stratum. Forests of the north-east side have a rich growth of Dhanyero (Woodfordia fruticosa).
(c) Riverine forest: The forest located near Jakhor tal, Murfutta tal and Murfutti tal area is relatively open riverine forest dominated by Eugenia kurzi, Acacia catechu and Dalbergia sissoo, species. Secondary stratum is composed of curry plant (Murraya koenigii), saplings of Jamun (Eugenia kurzi) and sindure (Mallotus philippinensis).
(d) Grassland: The adjacent terrestrial grassland vegetation is equally rich comprising Cyperus distans, Phragmites karka, Cyperus esculentus. Cyperus imbricatus, Cassia tora, Chrysopogon acicualatus, Desmodium triflorum, Alternanthera sessilis, Phyllanthas urinaria, Cynodon dactylon, Centella asiatica, Justicia spimplex, Imperata cylindrica. In the less grazed area, species like Cynodon dactylon and Centella asiatica are found dominant.
Wetland vegetation:
(a) Submerged species: the dominant are Hydrilla verticillata, Chara sps., Ceratophyllum demesrum and Utricularia aurea.
(b) Floating Species: The dominant species are Eichornia crassipes, Pistia stroites, Azolla imbicata, Lemna minor and Wolffia sps. Ludwig sps., Nymphoea nouchalia, Potomogeton natans, and Nelumbo nucifera . Other floating species are Ipomoea aquatica, Trapa bispinosa
(e) Emergent species: Monochoria vaginalis, Cyperus esculentus, Persicaria hydropiper, are found frequently in the Jakhor Tal. Species like Ranunculus scleratus, Phragmites karka, Saccharum spontaneum , Marselea quadrifolia, Cyperus spp. Persicaria glabrum are dominant in the nearby forests.
B. Fauna
The mammals reported to be present in the nearby forests are listed in the table
below: Table 2.3 : Mammals in the Project Area
Common Name Scientific Name
Rhesus monkey Macaca mulatta
Hanuman langur Presbites entellus
Jungle cat Felis chaus
Fishing cat Felis viverrina
Leopard cat Felis bengalensis
Panther Panthera pandrus
Common mongoose Herpestes edwardsi
Jackal Canis aureus
Indian Fox Vulpes bengalensis
Dhole Cuon lurtra
Otter Lutra lutra
Bat
Squirrel Fanambulus sps
Flying squirrel Petaurista petaurista
Jungle rat Bandicota indica
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
92
Hare Lepus nigrcollis
Blue bull Boselaphus tragocamelus
Sambar Cervus unicolor
10
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
93
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Swamp deer Cervus duvauceli
Chittal Axis axis
Some of the birds reported in the forest areas are listed in the table below:
Table 2.4: List of Birds in the Project Area Common name Scientific Name
Indian moor hen Gallunila chloropus Pigmy goose Nettapus coromandeeliarnus Whiet breasted kingfisher Halcyon smyntensis Stork-billed kingfisher Pelargopsis indicus Pond Heron Ardeola grayii Purple Heron Ardea purperea Large golden-backed woodpecker Chrysocolaptes lucidus Gray tit Parus major Jungle babbler Tudoides striatus Pin tail duck Anal acuta Jungle crow Corvus macrorhynchos Spotted dove Streptopelia chinensis Blossom headed parakeet Psittacula cyanocephala Rose ringed parakeet Psittacula krameri Scarlet minivet Pericrococotus pandicerainus Lesser wood shrike Tephrodomis pondicerianus Gray hornbill Tockus birostris Red whisekered bulbul Pycnonulus jocosus Gray headed fly catcher Cullcicappa ceylonensis
Red jungle fowl Gallus gallus
Similarly, fishes found in the Devariya Tal area are given in the table below:
Table 2.5 : List of Fishes Found in the Project Area
Common Name Scientific name
Rawa Cirrhinus sps. Rohu Labeo rohita Andha bam Amphipnos cuchia Katle Acrossochelius hexagonalepsis Bhoti Chauna gachura Bam Mastacembelus sps. Garahi Chauna punctatus Mahasir Tor putitora
Sahar Tor tor
C. Protected Areas
No protected area exists in the project area. However Kailali district lie in the corridor of two important conservation areas in Nepal: Badiya national park and Suklaphanta conservation area. Dudhiya national park lies in India across the border. These are not in the vicinity of the project area and need not be considered for the project.
Ini
tia
l
En
vir
on
m
en
tal
Ex
a
mi
na
tio
n(
IE
E)
of
Sh
iv
an
ag
ar
To
w
n
W
at
er
Su
pp
ly
an
d
94
11
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
95
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
2.3.4 Human and Economic Development
a. Socio-Economic Data
The ethnic composition of the beneficiary population is presented in the table below. The major ethnic groups in the project area are Brahmin, Chhetri and Chaudary and Rana Tharu.
Table 2.6 : Population Distribution by Ethnicity
Ethnic Group Total
HH % Pop % No
Bramhin 492 20.28 2816 19.65 Chhetri 623 25.68 3533 24.65 Newar 23 0.95 128 0.89 Gurung 6 0.25 32 0.22 Magar 14 0.58 69 0.48 Rai 1 0.04 6 0.04 Tharu 411 16.94 3128 21.83 Chaudhary 720 29.68 3816 26.63 Kami 35 1.44 22 1.54 0
Sarki 9 0.37 48 0.33 Damai 6 0.25 41 0.29 Musalman 6 0.25 33 0.23 Others 80 3.30 46 3.22 1
Total 2426 100 14331 100
The gender distribution structure of the project area is of general type. The table below gives the detailed analysis of the results found by the field survey.
Table 2.7 : Gender Ratio
Gender Regular Population Total (Regular + Rent) Total Population Percent Population Percent Male 7312 53.68 7722 53.883 Female 6310 46.32 6609 46.117 Total 13622 100 14331 100
Most of the population, i.e. over 90 %, in this area is employed in service and the major occupational activity is agriculture (29.68%) and service / jobs (29.03%). Other activities in the project area are business and trading (16.52 %) followed by daily wage earners (8.21%). Other occupational activities in the area are remittance and small scale industries.
The status of economic condition of the population can be inferred from various parameters such as ownership of dwellings, type of houses, their valuation, etc. Over 90 percent of the project households own their dwellings. Field survey has indicated that nearly 70% of the houses in the project area are either pucca or semi pucca houses.
Table 2.8 : Ownership of Houses in the Project Area
Ownership House Total
No % Own House 2208 91.01 Rented House 185 7.63 Free of Cost House 26 1.07
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
96
Landless 7 0.29 Total 2426 100.00
12
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
97
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
The educational status of the project beneficiaries is also quite good. Nearly 90 % of the project population are literate and / or with higher educational status. The details of the educational status of the project area is given in the table below.
Table 2.9 : Educational Status of the Project Area
Age Group Total No % Illiterate 1481 10.33 Literate 1690 11.79 Primary Level 3526 24.60 Secondary Level 3351 23.38 SLC Pass 1510 10.54 Intermediate 1147 8.00 Bachelor 587 4.10 Master 185 1.29 Others 23 0.16 NA 831 5.80 Total 14331 100
b. Health and Sanitation
Only about 240 households avail the services of the existing NWSC system and the rest have to depend upon shallow hand pumps. Those who have water supply from NWSC have also to use hand pumps to supplement the supply as the current supply is not adequate. The shallow hand- pump water is prone to contamination from various infectious bacteria. The population suffers from water borne infections.
Hospitals
The district hospital exists in the municipality although not within the project area itself. There is an Eye treatment centre and and Seti Ayurvedic hospital within the Project area.
Sanitation
Existing sanitation facilities are quite basic in Dhangadhi Municipality. There are a few surface drains to drain of street run-off and the Municipality employs sweepers and tractors to gather and dispose solid waste from the town area. However, most of the households have pour-flush latrines in the urbanized areas of the municipality. Nonetheless, the semi-urban areas in the periphery of the municipality including parts of ward no. 7 within the proposed service area lack adequate sanitation.
c. Economic Characteristics
• Industries
No sizable industry of middle or large size within the project area.
• Agricultural Development
The areas adjoining the project area even within the municipal boundary are good for agriculture. Many of the rural households are dependent upon agriculture produce. The area is famous for its paddy production.
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
98
The major crops produced here are paddy, wheat, maize and seasonal vegetables.
13
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
99
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
2.3.5 Infrastructure Facilities
Water Supply and Drainage
The existing NWSC water system is a groundwater based system with overhead tanks and intermittent supply through private household connections. The there are two overhead tanks, one a low head RCC overhead tank of 180 cu.m capacity meant primarily for the market area. The second overhead tank is a modular steel structure of 200 cu.m capacity located in Hasanpur. Source of water for the existing system is groundwater boreholes, over 150 meters in depth and fitted with submersible pumps.
Communication
There is a regular service of line and mobile phone service in the project area.
Electricity
The Nepal Electricity Authority (NEA) has provided electricity for household consumption through its national grid.
Irrigation
There is no canal irrigation in the area
Transportation
The Project area is located on all weather black topped road some 25 kilometers from Attariya, the major junction of on the East-West Highway. The nearest airport is the Dhangadhi Airport at Geta VDC, where daily flights from Kathmandu provide their services. In addition to this the Project area is near the Indian Border and also be accessed at Gauri Phanta border.
Educational Institutions
There are Seventeen schools and one campus (Kailali Multiple Campus) in the Project area. The following is the list of the schools, and their locations:
Table 2.10 : List of Schools in the Project Area
S.N Name of the School/ Campus Address, Ward No.
. 1. Kalika Devi English School Basanta Tole-1 2. New Era English Boarding School Laxmi Nagar-1 3. Heaven's Garden Boarding School Laxmi Nagar-1 4. Malika English Boarding School Buddha Marga-1 5. Gyan Jyoti Bidya Niketan Shivanagar-1 6. Greenland English Boarding School
1. Delight Boarding School Manehara-7 2. Sarswoti Lower Secondary School Manehara-7 3. Pashupati Boarding School Debariya-7 4. Tharu Hostel Debariya-7 1. Aristo English Boarding School Campus Road-8 2. Dhangadhi Higher Secondary School Dhangadhi Gaon-8 3. Nav Durga English Boarding School Dhangadhi Gaon-8 4. Kailali Bidya Niketan Sichhya Nagar-8 5. Three Star English Boarding School Sichhya Nagar-8 6. Api Bidya Niketan Dhangadhi-8 7. Shining Star Boarding School Dhangadhi-8
Ini
tia
l
En
vir
on
m
en
tal
Ex
a
mi
na
tio
n(
IE
E)
of
Sh
iv
an
ag
ar
To
w
n
W
at
er
Su
pp
ly
an
d
10
0
14
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
101
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Other Institutions
The training centre of Agricultural Development Bank of Nepal is located in Ward # 1. Besides this there are several government and non-government including private institutions in the project area. A list of the same is provided in the table below:
Table 2.11 : List of Other Institutions in the Area
Name of the Office / Organization Address Type (Ward / Cluster) (Private/GO/NGO)
Agricultural Development Bank, Regional Training Basanta Tole-1 Bank Centre
Accham Sewa Samiti Shiva Nagar-1 CBO Dudir Consultancy Overseas Shiva Nagar-1 Private Lok Chakra Buddha Bihar Buddha Marga-1 Private Spiritual Centre Jan Jagaran Samaj Kendra Debariya-7 NGO NNDSWO Campus Road NGO Nav Durga Anugaman Kendra Dhangadhi Gaon-8 Temple Spiritual Centre
Quality of Life Values
The Project is not expected to adversely affect any cultural or recreational resources but will increase the existing quality of life values due to the improvement in personal, household and community hygiene practices and community health.
Cultural and Religious Sites
There are usual temples at various locations in the project areas as would be expected in a typical Nepali urban centre but no culturally important place.
2.3.6 Resettlement, Relocation and Compensation Issue
The various system alternatives do not require resettlement of households or relocation. The system network has tried to follow public property line and hence the issue of resettlement or relocation is not evident. However, during the environmental assessment process this will be thoroughly assessed and verified in line with the ADB and HMG environmental guidelines and regulations.
There shall be the need to compensate, if private land is required for locating the overhead reservoirs and the tube wells within the service area. Compensation amount shall be as per the local prevailing rates for such land.
2.3. 7 Air Pollution
Air pollution is not a problem in the Shivanagar area as most industries are not located in its area or vicinity and there is low volume of traffic. There may be indoor air pollution from burning of agricultural refuge.
3 PROCEDURES TO BE ADOPTED WHILE PREPARING THE REPORT
The consultant will follow the following methodology for preparation of the report:
• Prepare a comprehensive data base on the corridor of influence on the biophysical and socioeconomic environment
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
102
• Collect Secondary data from published and unpublished reports, maps, aerial photographs, newspaper articles, etc. from different Government and non-government organizations.
• Prepare Questionnaires/checklists/matrices for collection of primary data for both the bio-physical
and socioeconomic assessments.
15
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
103
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
• Provide a description of relevant parts of the Project, using maps with appropriate scale and photographs and aerial photographs, where necessary, including the following information: location, alignment, alternatives, design, standards, pre-construction, construction and post-construction activities, work schedule, staffing and support facilities and services.
• Include information on mitigation, costs associated with construction activities (during design
construction, and operation and maintenance activities) should also be included.
3.1 Environmental Assessment The consultant shall study the existing environmental constraints and potential impacts in the Project area through filed surveys, complemented by secondary information from reports and interviews with a number of government officials, representatives of NGO and international organizations (IO) supported projects and researchers. The consultant shall collect primary and secondary data, evaluate them and describe the relevant environmental characteristics of the area along the pipeline routes and its corridor of influence, including the following information: Physical Environment: topography, soils, climate, and meteorology, geology, surface and ground water hydrology, noise, air and water quality Ecological Environment: flora, fauna, rare and endangered species, religious trees and sensitive habitats (including parks and reserves) 3.2 Socio-Economic Assessment
• Social assessment of the project tries to determine the social implication (issues) in terms of assumed positive and negative impacts related to location, design, construction, and operation. Preparation and actual implementation of the construction activities will create some nuisance and inconvenience for the communities in the area.
• Primary data shall be obtained through Focus Group Discussion (FGD) with communities, along the
pipeline routes under consideration. Additional data shall be collected from various Committees (VDCs, DDCs, NGOs, Community groups, etc) through which the respective pipe alignment pass.
• The Consultant shall collect primary and secondary data, evaluate them and describe the relevant
environmental characteristics of the along the pipe routes and its corridor of influence, along with the following information:
• Population, land use, planned development activities, community structure, government services,
demography, employment, distribution of income and sources of livelihood, goods and services produced, water supply, public health, education, extension services, cultural sites and heritage, tribal people, customs, aspirations and attitudes, expected water users and those benefitting from it, different needs and demands of VDCs, and the present quality of life (QOL), etc
3.3 Public Participation The project has decided to involve a variety of concerned groups, including non-governmental organizations, line agencies, community based organizations local leaders and social workers while preparing the IEE report. A notice will be published in a daily newspaper only after the approval of the TOR to inform the local people and stakeholders about the project and to obtain suggestion about the possible environmental impacts and likely mitigation measures during implementation of the project. A copy of the notice shall also be displayed at the concerned VDC or municipality office, local school, and health posts and public places in the project area, as per the EPR 1997 (Amendments 1999 and 2007).
Ini
tia
l
En
vir
on
m
en
tal
Ex
a
mi
na
tio
n(
IE
E)
of
Sh
iv
an
ag
ar
To
w
n
W
at
er
Su
pp
ly
an
d
10
4
16
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
105
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
4 POLICIES, LAWS, RULES, DIRECTIVES AND GUIDELINES
The IEE should also be conducted in compliance with the following Laws, Policies, Acts, Regulations Standards and Guidelines:
Law • Interim Constitution of Nepal 2063 B.S. (2007 A.D.)
Policies
• Rural Water Supply and Sanitation National Policy, Strategy and Action Plan 2060 B.S. (2004 A.D.)
• Three Year Interim Plan 2063 B.S. (2007 A.D.) • Urban Water Supply and Sanitation Policy 2066 B.S. (2009 A.D.) • ADB’s “Safeguard Policy Statement (SPS)” 2066 B.S. (2009 A.D.)
Acts and Regulations
• Land Acquisition Act 2034 B.S. (1978 A.D.) • Solid Waste Management and Resource Mobilization Acts 2044 (1987) • Solid waste (management& resource mobilization), Rules,2047 (1990) • Water Resources Act 2049 B.S. (1992 A.D.) • Water Tax Act 2023 (1966) • Water Resources Regulations 2050 B.S. (1993) • Labor Act 2048 B.S. (1992 A.D.) • Forest Act 2049 (1992 A.D.) • Forest Regulations 2050 (1993 A.D.) • Environmental Protection Act 2053 B.S. (1997 A.D.) • Environmental Protection Regulations 2054 (1997 A.D.) with Amendment • Local Self Governance Act 2055 B.S. (1999 A.D.) • Local Self Governance Regulations 2056 B.S. (2000 A.D.) • Drinking Water Regulations 2055 B.S. (1998 A.D.) • Child Labor Prohibition and Regulation Act 2056 B.S. (2001 A.D.) • Town Development Act 2045 (1988 A.D.)
Standards and Guidelines
• National EIA Guidelines 2050 B.S. (1993 A.D.) • National Drinking Water Quality Standards 2062 B.S (2005 A.D.) • Water Resources Strategy, 2055 B.S. (2002 A.D.)
Ini
tia
l
En
vir
on
m
en
tal
Ex
a
mi
na
tio
n(
IE
E)
of
Sh
iv
an
ag
ar
To
w
n
W
at
er
Su
pp
ly
an
d
10
6
17
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
107
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
5 TIME, ESTIMATED BUDGET AND SPECIALIST/EXPERTS REQUIRED
5.1 Time Schedule and Work Plan
Time to be devoted for the IEE Study shall be 6 weeks. The Proposed work schedule is as follows: Table 5.1 : Proposed Work Schedule S. N Activity / Work 1 2 3 4 5 6
1 Approval of IEE TOR
2. Public Notification
3. Desk Study
4. Field Work
4.1 Physical Environmental Assessment
4.2 Biological Environment Assessment
4.3 Socio economic and Cultural Assessment
5. Analysis of Field information and Impact Evaluation
5.1 Alternative Assessment
5.2 Development of Mitigative Measures
5.3 Development of Environmental Auditing Process
5.4 Preparation Environmental Monitoring Plan
6. Preparation of Draft report and submission
7. Final Submission after incorporation of comments
5.2 Estimated Budget
The total estimated cost for the IEE study of Shivanagar Small Town Water Supply and Sanitation Project is NRs. 155,000.00 inclusive of all taxes.
5.3 Resource Persons
As the IEE requires different personnel for specific tasks, the following inter-disciplinary manpower will be required. A team leader will be required to co-ordinate the different tasks of the personnel involved. The Team will be consisting of:
• Team Leader/Water Supply and Sanitation Engineer
• Environmentalist
• Sociologist
• Geo-hydrologist
• Botanist/Forrester
•
6 ANTICIPATED IMPACTS OF THE PROPOSED PROJECT
A distinction shall be made between the potentially significant positive and adverse impacts and immediate and long term impacts. Impacts that are unavoidable or irreversible shall be identified. Wherever possible, the significant impacts shall be quantified in terms of environment costs and benefits.
7 ANALYSIS OF ALTERNATIVES TO THE PROPOSED PROJECT
Alternative alignments to the proposed project to meet the same project objectives shall be described (siting, design, technology choice, construction techniques, operation and maintenance). Alternatives in terms of
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
108
potential environmental impacts, capital and operating costs and institutional training and monitoring requirements shall be described. Costs and benefits of each alternative shall be quantified (wherever possible), incorporating the estimated costs of any associated mitigation measures.
18
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
109
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
8 MITIGATION MEASURES Mitigation measures to adverse potential impacts due to location, design, construction and post-construction shall be proposed. Mitigation measures shall be incorporated from the planning stage onwards. These measures shall be outlined in the Environment Management Plan (EMP) and Resettlement Plan (RP)
9 MATTERS TO BE IMPLEMENTED WHILE IMPLEMENTING THE PROJECT
9. 1 Environmental Management Plan An Environmental Management Plan (EMP) has a dual purpose. It is designed to monitor the contractor’s work during the project implementation. It helps to check contractual compliance with the specified mitigation measures. It also helps in making periodic checks on the actual environmental impacts of the Project over the years following the completion of the works, and to compare these with those impacts anticipated at the time of Project appraisal. The EMP therefore provides the necessary feedback required for correcting potentially serious Project deficiencies, and in planning of other projects. Feasible and cost effective measures to prevent/mitigate/reduce significant negative impacts shall be recommended in the Environment Monitoring Management Plan, outlining construction, post-construction measures. The impacts and costs associated with implementing the measures shall be detailed. Issues related to compensation of affected parties for impacts that cannot be mitigated shall be considered. The EMP shall include proposed work programs, budget estimates, schedules, staffing, and training requirements and other support services to implement the mitigating measures. A detailed Resettlement Action Plan (covering compensation and/or resettlement) for the Project affected Persons shall be prepared in addressing the socio-economic impacts. 9. 2 Environmental Monitoring Plan Environmental monitoring plan, which is required under both EPR, 2054 - Annex 6 and NEIAG, 2050 - Chapter 10, helps to provide timely warning of the potential environmental damage and also to check the implementation of mitigation measures to see whether it confirms to the approved plan. The monitoring plan shall include the following critical contents:
i. Identification of environmental parameters/indicators
ii. Development of general monitoring program for assessing the impacts of the project on the physical, biological and socio-economic environment.
iii. Outline a monitoring program for public health in the project camps and surrounding communities
during the construction phase
Monitoring Mechanism The monitoring mechanism during construction will be of regular type whereas baseline monitoring, compliance monitoring and process monitoring shall have to be done during the operation and maintenance phase. The monitoring team shall visit the project site and monitor the effectiveness of the implementation of mitigation measures. Monitoring is one of the components of EMP. Monitoring of physical, biological and socio-economic parameters of the environment of the project site should be carried out. The outcomes of the monitoring
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
110
activities should be maintained in a database. The results of monitoring should also be disclosed in the form of demonstration, charts, figures, graphs, and samples, etc., to the local people, school students and other interested stakeholders. In the process of compliance monitoring of the project construction, local people and construction workers should be consulted.
19
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
111
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
9. 3 Information Disclosure, Public Consultation and Participation Public consultations will be held in the entire process of IEE study. Stakeholders should be consulted regarding the scope of the environmental study before work has commenced in earnest, and should then be informed about the likely impacts of the subproject and proposed mitigation once the draft IEE is under preparation. The report should record the views of stakeholders and indicate how these have been taken into account in project development. Information is disclosed through public consultation and more formally by making docu.ments and other materials available in a form and at a location in which they can be easily accessed by stakeholders. This normally involves making draft reports available (in the local language) at public locations in the community and providing a mechanism for the receipt of comments and making docu.ments available more widely. For Category B-sensitive projects, SEIAs and SIEEs are made available to the public through the depository library system, and are placed on the ADB website no later than 120 days prior to the Board considerations. The full IEE (B-sensitive) is also made available to interested parties upon request. For other category B projects, the environmental analysis is posted on the ADB website as part of the RRP. The full IEE reports are also made available to the interested parties upon request. Public consultation and involvement should be given highest priority in the implementation of mitigation measures. Public consultation should take place and on the basis of decision of the consultation meeting, implementation of mitigation measures should be prioritized and should be carried out with the involvement of the local people. Public consultation program in the project area will be organized to inform the broader communities and to collect the feedbacks and suggestions regarding the issues. This program mainly focus on the awareness about the project plans and programs, building of mutual consensus about the implementation of the project, identification of the key issues to be considered during IEE study and project design. In this regard, a 15 days’ public notice shall be issued in a national daily newspaper as well as in the VDC offices covered by the project to inform the concerned and affected stakeholders about the project and receive the related comments and feedback from them. 9. 4 Grievance Redress Mechanism A Grievance Redress Mechanism will be suggested. This will assist the project management in handling of grievances/ complaints raised by the local communities regarding the loss of assets, water and sanitation issues during implementation of the project. This mechanism will incorporate procedure to redress grievances such as collection of grievances/ complaints from the affected community and to resolve them. This procedure will describe the mechanism through planning, implementation and management stages. The agencies, which will be responsible for conducting the above activities, will also be defined.
10 REPORTS The format for the IEE report shall include the following:
• Executive Summary (in English and Nepali)
• Table of Contents
• List of Tables
• List of Figures/Photographs
• Appendices
• List of Abbreviations
• Acknowledgements
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
112
• Introduction
• Description of the Project
• Description of the Environment
• Anticipated environment impacts and mitigation measures 20
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
113
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
• Analysis of alternatives with and without project situations • Information disclosure, consultation and participation
• Grievance and redress mechanism
• Environment Management Plan
• Conclusions and Recommendations
• References
• Annexes
11 RELEVANT INFORMATIONS Tables, figures, maps photographs and references shall be included in the IEE Report.
Ini
tia
l
En
vir
on
m
en
tal
Ex
a
mi
na
tio
n(
IE
E)
of
Sh
iv
an
ag
ar
To
w
n
W
at
er
Su
pp
ly
an
d
11
4
21
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
115
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Annex 2: Rapid Environmental Assessment (REA)
Rapid Environmental Assessment (REA) Checklist
WATER SUPPLY
Instructions: (i) The project team completes this checklist to support the environmental classification of a project. It is to be attached to the environmental categorization form and submitted to the Environment and Safeguards Division (RSES) for endorsement by the Director, RSES and for approval by the Chief Compliance Officer.
(ii) This checklist focuses on environmental issues and concerns. To ensure that social dimensions are adequately considered, refer also to ADB's (a) checklists on involuntary resettlement and Indigenous Peoples; (b) poverty reduction handbook; (c) staff guide to consultation and participation; and (d) gender checklists.
(iii) Answer the questions assuming the “without mitigation” case. The purpose is to identify potential impacts. Use the “remarks” section to discuss any anticipated mitigation measures.
Country/Project Title: Nepal/Shivanagar Small Town Water Supply and Sanitation Project
Sector Division:
Water Supply and Sanitation
SCREENING QUESTIONS
Yes
No
REMARKS
A. PROJECT SITING
IS THE PROJECT AREA
DENSELY POPULATED? Densely populated in market area and
×
others are scattered and rural in
character
HEAVY WITH DEVELOPMENT ACTIVITIES? Only small developmental activities
× like building construction and so are
going on
ADJACENT TO OR WITHIN ANY ENVIRONMENTALLY ×
SENSITIVE AREAS?
CULTURAL HERITAGE SITE
× No cultural heritage site within or
nearby the project area
PROTECTED AREA × No any protected area within or nearby
the project area
WETLAND
× No wetland area within or nearby the
project area
MANGROVE
× No mangrove area within or nearby
the project area
ESTUARINE
× No estuarine area within or nearby the
project area
BUFFER ZONE OF PROTECTED AREA
× No buffer zone within or nearby the
project area
SPECIAL AREA FOR PROTECTING BIODIVERSITY
× No special area for protecting diversity
within or nearby the project area
BAY
× No any bay within or nearby the
project area
B. POTENTIAL ENVIRONMENTAL IMPACTS
Will the Project cause…
Pollution of raw water supply from upstream wastewater Since ground water being abstracted in
discharge from communities, industries, agriculture, and soil the system, possibility of pollution of
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
116
erosion runoff? ×
raw water supply is not possible.
People have their own toilet and not
connected to drain and there are no big
industries
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
117
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
SCREENING QUESTIONS
Yes
No
REMARKS
Impairment of historical/cultural monuments/areas and All pipes will pass through road side
loss/damage to these sites? ×
and no any industrial/cultural
monuments/area will be damage by the
project within the project area.
hazard of land subsidence caused by excessive ground water ×
Only required amount of water will be
pumping? pumped
social conflicts arising from displacement of communities ? × Communities will not be displaced
conflicts in abstraction of raw water for water supply with other ×
Since raw water being ground water
beneficial water uses for surface and ground waters? possibility of conflict do not exist
unsatisfactory raw water supply (e.g. excessive pathogens or Water quality after treatment, meeting
mineral constituents)? × with NDWQS standard will be
supplied
delivery of unsafe water to distribution system? ×
Treatment facility is provided to ensure
quality of supplied water
inadequate protection of intake works or wells, leading to ×
Boundary wall has been provided
pollution of water supply?
over pumping of ground water, leading to salinization and ×
Only required quantity will be pumped
ground subsidence?
excessive algal growth in storage reservoir? ×
Only treated water will be collected
and reservoir will be cleaned
periodically
increase in production of sewage beyond capabilities of Most of the household have their own
community facilities? × toilet and not connected to drain.
Conceptual design of waste water
management has been prepared
inadequate disposal of sludge from water treatment plants? As water quality is as per NDWQS
× standard only minor sludge will be
produced
inadequate buffer zone around pumping and treatment plants to Pumps have very minimal noise and
alleviate noise and other possible nuisances and protect × treatment plant will not make noise and
facilities? other nuisance
impairments associated with transmission lines and access ×
Transmission line passes through roads
roads?
health hazards arising from inadequate design of facilities for Trained manpower will be used to
receiving, storing, and handling of chlorine and other ×
receive, store and handling of chlorine.
hazardous chemicals. Adequate measures will be taken to
store it properly.
health and safety hazards to workers from handling and Only chlorine will be used as
management of chlorine used for disinfection, other disinfectants. Required training will be
contaminants, and biological and physical hazards during ×
provided to handle it properly and
project construction and operation? trained manpower will be deployed
Therefore health and safety hazard to
workers will not arise
dislocation or involuntary resettlement of people? × No settlement of people required
disproportionate impacts on the poor, women and children, All households will have their own
Indigenous Peoples or other vulnerable groups? ×
private tap. Besides this, these people
will get opportunity to work and earn
during project implementation
noise and dust from construction activities? During construction some noise may be
created and some dust may be
× produced but this will be managed to
minimize using appropriate
construction practices
increased road traffic due to interference of construction During excavation and back filling of
activities? × pipe trench traffic interference may
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
118
occur for short period. Traffic
management will be taken care of
continuing soil erosion/silt runoff from construction operations? ×
Flat terrain and no big amount of
earthwork in one place
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
119
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
SCREENING QUESTIONS
Yes
No
REMARKS
delivery of unsafe water due to poor O&M treatment processes Regular monitoring of plant operation
(especially mud accumulations in filters) and inadequate will be carried out. Trained manpower
chlorination due to lack of adequate monitoring of chlorine will be deployed through users
residuals in distribution systems? ×
committee for O&M of the project.
One well equipped lab will be
established to check water quality on
regular basis. Hence these type of
problem do not arise.
delivery of water to distribution system, which is corrosive due Regular monitoring of plant operation
to inadequate attention to feeding of corrective chemicals? will be carried out. Trained manpower
will be deployed through users
×
committee for O&M of the project.
One well equipped lab will be
established to check water quality on
regular basis. Hence these type of
problem do not arise.
accidental leakage of chlorine gas? × Chlorine gas is not being used
excessive abstraction of water affecting downstream water ×
Only required quantity of water will be
users? abstracted
competing uses of water? No such possibilities exist. All will get
× water for all time since system is
continuous
increased sewage flow due to increased water supply Most of HHs have their own toilet and
×
conceptual design of structures for
waste water management has been
done
increased volume of sullage (wastewater from cooking and Volume of sullage and sludge may
washing) and sludge from wastewater treatment plant × increase in small quantity. It may not
cause serious problems
large population influx during project construction and Population will be increased as per the
operation that causes increased burden on social infrastructure anticipated population growth rate. No
and services (such as water supply and sanitation systems)? need to hire people from outside during
× construction period. Local people will
be used as far as possible. Skilled
manpower if not available locally may
be hired from outside.
social conflicts if workers from other regions or countries are Since local people will be sued for the
hired? × implementation of the project as far as
possible, such conflict may not arise
risks to community health and safety due to the transport, No need to use explosive and other
storage, and use and/or disposal of materials such as explosives, × danger chemicals. Fuel will be properly
fuel and other chemicals during operation and construction? stored.
community safety risks due to both accidental and natural Proper safety measures and precaution
hazards, especially where the structural elements or will be adopted during construction
components of the project are accessible to members of the ×
period. The project structures will be
affected community or where their failure could result in injury made inaccessible providing compound
to the community throughout project construction, operation wall and fencing or few structure
and decommissioning? underground
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
120
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Annex 3: Public Notice
(As on Rajdhani, 06 March 2011)
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
121
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Annex 4: Deed of Inquiry (Muchulka)
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
122
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
123
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
124
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
125
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
126
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Annex 5: Recommendation letters from concerned authorities
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
127
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
128
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Annex 6: List of persons contacted
S.N. Name Designation Address
1 Mr. Narad Muni Rana Chair person, WUSC Shivanagar, Dhangadi
2 Mr. Govind Bahadur Shahi Vice chair person, WUSC Shivanagar, Dhangadi 3 Mr. Nanda Krishna Secretary, WUSC Shivanagar, Dhangadi Bhattarai
4 Mr. Gana Singh Chaudhary Planning Section, Shivanagar, Dhangadi Dhangadi Municipality
5 Ms. Babin Joshi Municipality Facilitator Shivanagar, Dhangadi
6 Ms. Puspa Ghimire Member, WUSC Shivanagar, Dhangadi 7 Ms. Janaki Tuladhar Advisor, WUSC Shivanagar, Dhangadi
8 Ms. Bhanu Devi Lohar Local Basant tole, ward no. 1 9 Mr. Gokarna Math Local Basant tole, ward no. 1 10 Ms. Laxmi Jisi Laxmi nagar, ward no. 1 11 Mr. Purna Lal Paudel Puspal lal tole, ward no. 1 12 Ms. Sonu Rana Dhangadi gaun, ward no. 8 13 Ms. Sushma Sitaula Local Biddha Marg, ward no. 8 14 Mr. Krishna Prasad Ghimire Local Purano Fulbari Buspark, ward no. 8 15 Mr. Maniraj Joshi Local Purano Fulbari Buspark, ward no. 8 16 Ms. Sabita Chand Dhangadi gaun, ward no. 8 17 Mr. Sankhar Khadka Gaurishankar tole, ward no. 5 18 Mr. Dayaram Chaudhari Gaurishankar tole, ward no, 5 19 Mr. Kalu Singh Kuwar Local Shivanagar, ward no. 5 20 Ms. Aruna Singh Local Shivnagar, ward no. 5 21 Mr. Panchu Ram Local Satbhawana tole, ward no. 8 22 Ms. Bimla Bi Ka Local Campus road, ward no. 8 23 Ms. Sushila Thapa Basant tole, ward no. 7 24 Mr. Pushpa Raj Ojha Manehara tole, ward no 7 25 Ms. Benu Koirala Local Debariya, ward no. 7 26 Mr. Pillu Rana Local Manehara tole, ward no. 7 27 Ms. Sita Devi Chaudhary Local Satbhawana tole, ward no. 7 28 Mr. Jitu Khushmi Chatrabas, ward no 7
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
129
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Annex 7: Water Quality Test
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
130
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Annex 8. Survey questionnaire
bf]>f] ;fgf zx/L vfg]kfgL tyf ;/;kmfO{ If]qut cfof]hgf
3/w'/L ;j]{If0f k|ZgfjnL lhNnf============================ gu/kflnsf÷uf=lj=;===================== j8f g+============
gu/ cfof]hgfM ============================ 3/ g+= ==========
cGt/jftf{ lng]sf] gfd M ========================================= cGt/jftf{ ldlt M=============
;'kl/j]Ifssf] gfd M ===============================================
!= ;fdflhs–cfly{s ljj/0f
-pko'Qm sf]7fdf-√ _ of] lrGx nufpg' xf];\
!=! cGt/jftf{ lbg]sf] gfd M
!=@
3/d'lnsf] gfd ===================== lnË M k'?if
dlxnf
!=# o; kl/jf/df ckfËtf ePsf] s'g} ;b:o x'g' x'G5< 5 5}g
!=$ hfthfltdWo] s'g xf]< s_ cflbjf;L hghflt v_ blnt u_ cNk;+Vos 3_ cGo
-cGtjf{tf lng]n] y/sf] cfwf/df pko'Qm ju{df lrGx
nufpg] _
!=% cGt/jftf{ lbg] JolQmsf] gftfM ====================
!=^ o; kl/jf/sf ;b:ox?sf] ljj/0f lbg';\
qm=;+= 3/d'lnl;tsf] gftf÷gfd pd]/ lnË lzIff :t/ k]zf
Gff]6M k]zf M != s[lif @= Jofkf/ #= gf]s/L $+= pBf]uwGbf %=
/]ld6]G;-a}b]lzs /f]huf/_ ^= Hofnf &= cGo
lzIff M != lg/If/ @= ;fIf/ #= k|fylds;Dd $= dfWolds;Dd %= P;=Pn=;L= plt0f{
^= cfO{=P= &= lj=P= *= Pd= P= (= cGo
!=& o; kl/jf/df a;f]af; ug]{ cGo ;b:ox?sf] ;xof]uL s'n ;+Vof
!=* o; gu/÷zx/df slxn] b]lv a:b} cfpg' ePsf] 5 <
:jjf;L a;fO ;/]sf] a;fO{ ;/L cfPsf] eP s'g lhNnfaf6 ===================<
!=( a;fO{ ;g'{sf] sf/0fM k|fs[lts k|sf]k Jofkf/÷Joj;fo lzIff åGb kfh{glhljsf] ;fdflhs ljnog
!=!) slxn] b]lv o; 3/df a:b} cfpg' ePsf]
<
!=!! of] 3/ cfk\mg} xf] < xf]Og olb xf] eg] xfnsf] d'No slt xf]nf cg'dflgt
v_ ef8fdf a;]sf]
xf]Og
xf] eg] dfl;s 3/ efF8fltg'{x'G5slt < ?=
u_
;'s'Daf;L xf] xf]Og
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
131
!=!@ o; 3/df efG5f sf]7f afx]s cGo slt j6f sf]7fx? \<5g
! sf]7f @ sf]7f # sf]7f $ sf]7f jf ;f] eGbf
!=!# 3/sf] cjnf]sg u/L 3/sf] lsl;d n]Vg] . cw{ sRrL
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
132
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project -kSsL M 5t 9nfg, cw{ kSsLM 9'Ëf÷O§fsf] ufx|f], 6Lgsf] 5fgf÷9'Ëf÷:n]6,lemu6L÷6fonsRrLcflb,M df6f] ufx|f] / v/÷6fonn]
5fPsf]_
!=!$ o; kl/jf/;+u hUuf hdLg 5 < 5
5}g
olb 5 eg] % /f]kgL-)=@% x]S6/_ eGbf jl9 jf % /f]kgLeGbf sd
!=!% oxfFsf] hUufsf] lsl;dM s_ v]t jf af/L ÷cl;+lrt- =========lj3f÷/f]kgLhUuf_
v_ v]t jf af/L ÷l;+lrt hUuf -===========lj3f÷/f]kgL_
!=!^ oxfFn] ufO{÷e};L kfNg' ePsf]5 5 5}g , 5 eg] sltj6f Pp6f b'O{j6f jf jl9
!=!& tkfO{sf] kl/jf/df tn pNn]lvt s'g s'g ;fdfg\< -5gePsf] ;fdfgsf] ;+Vof n]Vg]_
qm=;+= ;DkQL ;+Vo s}lkmot
f
! ;fOsn÷l/S;f
@ Dff]6/;fO{sn
# a}nuf8f
$ sf/÷lhk
% ldgLa;÷a;
^ 6«ofS6/÷6«s
& /]l8of]÷Sof;]6
* 6]lnlehg÷lel8of];]6
( :6f]e÷Uof; r'nf]
!) /]lk|mh]6/
!! jfl;Ë d]lzg
!@ jf6/ lkmN6/
!# sDKo'6/
!$ Od]n÷OG6/g]6sf] kx'Fr
!% cGo eP pNn]v ug]{ .
!=!* olb d'n k]zf s[lif eP slt dlxgf vfg k'U5< # dlxgf ^ dlxgf !@ dlxgf olb gk'u ePdf s;/L x'G5wfGg'<
k;n÷3/ef8f tnj k]G;g cGo
!=!( tkfO{sf] kl/jf/sf] cf};t jflif{s vr{ slt 5 pNn]v ug'{xf]; .
vr{sf] lzif{s / lsl;d
dfl;s vr{ ?=
s}lkmot
-s_ s[lif tkm{
/;folgs dn, ljp, ls6gfzs cfbL vl/b ug{
Dff6f]sf] t}of/L, /f]Kg],g],a\uf]8nL sf6\g], leqfpg], 9'j
/ laqmL ubf{ x'g] vr{
cGo eP -pNn]v ug'{;\
-s_ sf] hDdf
-v_ u}x| s[lif tkm{
vfBfGg -cGg / b}lgs pkef]Uo j:t'_
sk8f
lzIff
3/ ef8f÷3/ dd{t
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
133
oftfoft÷;+rf/
ljB't
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
134
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
kfgL kf]t ÷dd{t ;Def/
Cf}{iflw÷pkrf/-kfgLaf6 x'g] /f]u_ ========== jflif{s
vr{
Cf}iflw÷pkrf/- cGo /f]u_ ========== jflif{s
vr{
cGoM rf8ka{ sd{sf08 ;+:sf/ cflb pNn]v ug]{ ========== jflif{s
vr{
-v_ sf] hDdf
s±v sf] s'n hDd
!=@) tkfO{sf] kl/jf/sf] cf};t dfl;s sltcfo 5 < pNn]v ug'{xf]; .
;+nUg kl/jf/ k|fKt x'g]
cfo;|f]t cfo s}lkmot
k'?if dlxnf
-?= dfl;s_
-s_ s[lif tkm{
s[lif pTkfbgsf] ljqmLaf6 cfo
-ds}, ux'F, wfg, t/sf/L, kmnk"mn_
kz'hGo pTkfbg- b'w, bxL, £o", afv|f, s'
cflb_
-s_ sf] hDdf
-v_ u}x| s[lif tkm{
gf]s/L ÷ hflu/
Hofnf dhb'/L
k]G;g÷pkbfg cfbL
j}b]zLs /f]huf/-/]ld6]G;_
k;n÷Jofkf/
pBf]u
k;n÷3/ ef8f
uf8L÷9'jfgL Joj;fo
cGo eP pNn]v ug]{
-v_ sf] hDdf
s±v s'n hDdf
!=@! oxfFsf] kl/jf/n] s'g} 7'nf] C0f af]Sg' k/]sf] 5 < 5
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
135
@= vfg]kfgL tyf ;/;kmfO{ Joj:yfkg
@=! tkfO{sf] kl/jf/sf] nfuL vfg, vfgf ksfpg, g'xfpg, efF8fjt{g tyf n'uf w'gsf nfuL k|of]u ul/g] kfgLsf] >f]t Pp6}xf] xf] < xf]Og
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
136
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project @=@ tkfO{sf] vfgkfgLsf] d'Vo >f]t sxFf 5 < 3/ sDkfp08 leq};fj{hlgs :yndf
@=# tkfO{sf] kl/jf/n] lkpg, vfgf ksfpgsf] nfuL k|of]u ug]{ kfgLsf] >f]t s'g xf] < b}lgs slt ln6/ kfgL vr{g' x'G5]7fdf-<�s[koflrGx tnsf] sf
nufpg'xf];\.
qm=;+= jiff{ofddf
� ln6/÷ ;'Vvf ofddf
� ln6/÷ b}lgs
b}lgs
!= O{gf/÷s'jf-v'Nnf_ Á O{gf/÷s'jf-v'Nnf_ Á
@= O{gf/÷s'jf-9Ssg ePsf] _ Á Ogf/÷s'jf 9Ssg ePsf]_ Á
#= 6\o"a]n÷x\of08kDk Á 6\o"a]nof08kDk\x Á
$= l8k 6\o"a]n Á l8k 6\o"a]n Á
%= O{gf/÷s'jf d];Lgn] tfGg] Á O{gf/÷s'jf d];Lgn] tfGg] Á
^= ;fj{hlgs wf/f Á ;fj{hlgs wf/f Á
&= lghL wf/f Á lghL wf/f ] Á
*= d"n, vf]nf, gbL, kf]v/L Á d"n vf]nf, gbL, kf]v/L Á
(= laqm]tf;Fu kfgL lsg]/ Á laqm]tf;Fu kfgL lsg]/ Á
!)= jiff{tsf] kfgL ;+sng u/]/ Á aiff{tsf] kfgL ;+sng u/]/ Á
!!= cGo Á cGo Á
!@= yfxf 5}g Á yfxf 5}g Á
@=$ b}lgs vfg]kfgL cfjZos k"lt{ kfgL ;+sngaf/] lgDg lj:t[t ljj/0f\. lbg'xf];
qm=;+= ljj/0f jiff{ ofddf ;'Vvf ofddf
k'?if dlxnf aflnsf Affns k'?if dlxnf aflnsf afns
!= slt v]k÷k6s
@= ln6/÷v]k
#= s'n kl/df0f
$= kfgL Nofpg nfUg] ;do-
ldg]6_÷v]k
• kfgLsf] d'xfg ;Dd k'Ug
• d'xfgdf kv{g' kg]{ ;do
• kms{bf nfUg] ;do
%= k|lt v]k nfUg] ;do
gf]6 McGt/jftf{ lng] JolQmn] kfgLsf] efF8f] x]/L ;f]sf] Ifdtf olsg ul/ pNn]v ug]{ .
@=% efF8f dfem\g, g'xfpg / n'uf w'g tyf cGo sfdsf] nfuL s'g >f]ts]f kfgL k|of]u ug'{x'G5 < slt kfgL vkt�ug'{lrGx'G5< s[kof nufpg'xf];\.
qm=;+= jiff{ofdddf
� ln6/÷ ;'Vvf ofddf
� ln6/÷ b}lgs
b}lgs
!= O{gf/÷s'jf-v'Nnf_ Á O{gf/÷s'jf-v'Nnf_ Á
@= O{gf/÷s'jf 9Ssg ;lxt Á O{gf/÷s'jf 9Ssg ;lxt Á
#= 6\o"a]nof08kDk\x ;lxt Á 6\o"a]nof08kDk\x ;lxt Á
$= l8k 6\o"a]n Á l8k 6\o"a]n Á
%= O{gf/÷s'jf d];Lgaf6 tfGg] Á O{gf/÷s'jf d];Lgaf6 tfGg] Á
^= ;fj{hlgs wf/f Á ;fj{hlgs wf/f Á
&= 3/s} lghL wf/f Á 3/s} lghL wf/f Á
*= D"fn,vf]nf, gbL, kf]v/L Á d"n vf]nf, gbL, kf]v/L Á
(= kfgL laqm]tf;Fu lsg]/ Á kfgL laqm]tf;Fu lsg]/ Á
!)= cfsf;] kfgL ;+sng u/]/ Á cfsf;] kfgL ;+sng u/]/ Á
!!= cGo Á cGo Á
!@= Yfxf 5}g Á Yfxf 5}g Á
@=^ n'uf w'g / g'xfpg 3/af6 kfgLsf] d'xfg ;Dd hfg slt ;do nfUb5-olb >f]t÷d'xfg. 5'§f5'§} ePdf- ldg]6df;do_ pNn]v ug]{_
s_ n'uf w'g hfg] g'xfpg efF8fg\ dfem
v_ jiff{ofddf ;do ldg]6 ;'Vvf ofddf nfUg] ;do ldg]6
@=& olb wf/fsf] kfgL oxfFsf] cfjZostf kl/k'lt{ug{ kof{Kt 5}g eg] s;/L cfk'lt{ ug'{ x'G5<
kfgLsf] >f]t kl/df0f vr{g' kg]{ ;do-306f _ b}lgs Yfk vr{ dfl;s
ln6/
s'jf Ogf/
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
137
cfsf;] kfgL ;+sng
lghL 6}+s/af6 kfgL lsGg]
Xf08\kDk,6\o'jj]n
ldgn/ jf6/ hf/
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
138
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project cGo
@=* ufO{a:t'sf] nflu rflxg] kfgL s'g >f]taf6 slt dfqfdf pkef]u ug'{x'G5 .
s_ k|of]u ePsf];|f]t========================================================
v_ kl/df0f -ln6/÷b}lgs_ ================================================
u_ >f]t;Dd hfg cfpg nfUg] ;do-ldg]6_=========================
#= lghL wf/f h8fg
#=! s] tkfO{n] 3/df kfOk wf/f h8fg ug'{ ePsf] 5 < 5
5}g
olb 5 eg] slt vr{ nfUof]< ?=
#=@ s] tkfO{ cfkm\gf] 3/df wf/f hf]8\g rfxg' x'G5 < rfxG5'
rfxGg rfxg' x'G5 eg] s:tf] k|sf/sf] wf/f h8fg ug{ OR5f /fVg' x'G5 <
s_ 3/leq lghL wf/f
v_ sDkfp08leq lghL wf/f
u_ ;fd'bflos wf/f
#=# olb tkfOsf] 3/df lghL wf/f h8fg ePsf] 5}g eg], lsg h8fg gu/]sf] <
s_ vr{ ug]{ Ifdtf gePsf]n]
v_ h8fg z'Ns w]/} kg]{ ePsf]n]
u_ dfl;s kfgL lan w]/} cfpg] ePsf]n]
3_ kfgLsf] dfqf kof{Kt gePsf]n]
ª_ kfgLsf] cfk"lt{ lgoldt gePsf]n]
r_ o; If]qdf kfOknfOg h8fg ug{] Joj:yf pknAw gePsf]n]
5_ kfgLsf] u'0f:t/ /fd|f] gePsf]n]
h_ cGo sf/0f pNn]v ug]{
em_ yfxf 5}g
#=$ xfn tkfO{n] kfghL wf/f afkt uPsf] dlxgfdf kfgLsf] dxz'n slt ltg'{ eof]? <
#=% uPsf] dlxgfdf lt/]sf] lan b]vfpg ;Sg' -x'G5lan pknJw< eP ;f]sf] ljj/0f eg]{_
s_ lt/]sf] /sd ? v_ vkt ePsf] kfgLsf] dfqf ln6/
#=^ kfgLsf] lan s'g cfwf/df ltg'{x'G5� lrGx< nufpg'xf];\.
s_ dfl;s lglZrt tf]lsPsf]/sd
v_ ld6/ l/l8Ë adf]lhd
u_ vfg]kfgL sfof{non] eg] hlt
3_ ltg'{ kb]{g
ª_ cGo
r_ yfxf 5}g
#=& tkfO{nfO{ kfgLsf] lan ltg{ s'g tl/sf dg k5{ <
s_ lglZrt tf]lsPsf] dfl;s z'Ns
v_ ld6/ l/l8Ë lan cg';f/
#=* 3/sf] wf/fdf kfgL gcfpFbf klg kfgL dxz'n ltg'{ k5{ < k5{ kb}{g
#=( lghL wf/fsf] kfgL afx]s tkfO{n] slxn] yk kfgL lsGg' kg]{
ePsf]
jiff{ofddf ln6/ ;'Vvfofddf ln6/ kb}{g
#=!) lghL:t/sf kfgL laqm]tfaf6 lsGbf slt kl/df0f s'g b/df kfgL lsGg' ePsf] 5<
ln6/ ?=
÷k|lt ln6/sf] b/ ?=
#=!! tkfOsf] 3/sf] wf/f slt e/kbf]{ 5 <
s_ kfgL lg/Gt/ cfp5
v_ kfgL slxn] cfpF5 / slxn] cfpFb}g
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
139
u_ kfgL Ps lbg la/fP/ cfpF5
3_ kfgL k|To]s lbg s]xL 306fcfpF5
#=!@ vfg]kfgL ljt/0f k|0ffnL cj?4 x'bf dd{t ;Def/ ubf{ nfUg] vr{ Joxf]g]{ lhDdf s;sf] xf] <
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
140
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project s_ g]kfn ;/sf/
v_ vfg]kfgL pkef]Qmf ;/;kmfO ;ldlt
u_ ;d'bfo ÷ 5/ l5d]sL
3_ cGo pNn]v ug]{ =========================================================================
#=!# vfg]kfgLsf] kfOk÷wf/f dd{t ;'wf/sf] nflu jflif{s slt /sd vr{ ug'{x'G5 < u5'{ ulb{g
#=!$ ;fj{hlgs wf/f k|of]u u/] jfkt kfgL kf]t ltg'{ k5{<
5{,k eg] slt < /sd dfl;s÷jflif{s
kb}{g k5{
#=!% 5'5}g
kfgLsf] u'0f:t/M tkfO{n] k|of]u ug]{ kfgLsf] u'0f:t/k|lt ;Gt'i6 x'g'x'G5<
olb 5}g eg], kfgLsf] u'0f:t/ ;DalGw ;d:of s:tf 5g <
c_ kfgL uGxfpF5
cf_ :jfb g/fd|f] 5
O_ kfgL k|b"lift÷wldnf] 5
O{_ cGo s]lx ;d:of eP pNn]v ug]{ ===================================
#=!^ o;/L k|of]u ug]{ kfgLsf] u'0f:t/ sfod ug{ s] ug'{ x'G5
kfgLsf] k|zf]wgsf 3/]n' ljlw Yfk vr{ dfl;s
pdfNg]
lkmN6/ ug]{
5fGg]
Snf]l/g- lko';_, cfnd, kf]6f;
o'/f] uf8{
;f]l8;
;x–nufgL cjwf/0ff ;DaGwL k|fyldstf
$=! olb tkfO{sf] gu/kflnsf÷uf=lj=;= df ljleGg of]hgf ;~rfng ug{ /sd pknAw 5 eg] lgDglnlvt dWo] s'g s'g @ of]hgfnfO{stfklxnf] k|fyld
lbg'x'G5 <
s_ ;8s aQL
v_ sfnf]kq] ;8s
u_ ljBfno
3_ c:ktfn
ª_ Jojl:yt vfg]kfgL k|0ffnL
r_ k}bnofqL ;8s
5_ ljB't
h_ ;+rf/
em_ ;/;kmfO{÷;'ljwf
`_ l;rfO{
6_ kf6Lkf}jf wd{zfnf
7_ cGo ===============================
$=@ olb tkfO{ Jojl:yt vfg]kfgL ljt/0f k|0ffnLnfO{ dxTjk"0f{ 7fGg' x'G5 eg], s:tf] ]kfgLlsl;dsf]ljt/0fvfgk|0ffnLsf] rfxgf ug'{ ePsf] 5 <
s_ 3/÷ sDkfp08leq} JolQmut÷lghL wf/f h8fg
u_ z'Ns ;lxtsf] ;fd'bflos wf/f h8fg
3_ ;'wfl/Psf] s'jf,of08kDk\x hl8t
ª_ ;'wfl/Psf] s'jf, ljB'tLo oGq hl8t
r_ xfn pknJw ;]jfdf ;'wf/ cfjZos 5}g
5_ cGo -pNn]vug'{xf];\=======================================
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
141
$=# olb tkfO{sf] 3/df wf/f 5}g / lghL wf/f /fVg OR5's x'g'x'G5 eg], slt–nufgL/sd ;xug{ ;Sg'x'G5 < s[kof tn lbO{Psf] tflnsfdf lglh wf/f
/fVg slt /sd ;Dd nufgL ug'{x'G5 nufgLsf] /sdsf] ;Ldfdf�lrGx nufpg'xf]; .
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
142
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
qm=;+=
nufgLsf] ljj/0f
� lrGx nufpg]
!= !%))) eGbf dfyL �
@= ())! b]lv !%))) ;Dd �
#= ^))! b]lv ())) ;Dd �
$= #))! b]lv ^))) ;Dd �
%= !%)! b]lv #))) ;Dd �
^= !%)) eGbf sd �
$=$ lghL wf/f h8fg afkt nfUg] z'Ns Joxf]g'{ kg]{5< � dGh'/dGh'/5 5}g� $=% gofF vfg]kfgL of]hgf z'? ePdf / ;f] of]hgfaf6 rf}lj;} 306f kof{Kt dfqfdf u'0f:t/o'Qm kfgL pknJw ePsf] v08df s] t
cfkm\gf] 3/df wf/f h8fg ug{ OR5's x'g' x'G5< 5'
5}g
olb OR5's eP gofF lgodfg';f/ dfl;s kfgL dxz'nldtlgoa'´fpg' x'G5<
5'
olb OR5's x'g' x'G5 eg] tn lbO{Psf] tflnsfdf kfgL dxz'nsf]�lrGx;LdfdfnufP/ cfkm\gf] O{R5f JoQm ug'{xf]; . 5}g
qm=;+= Dffl;s kfgL dxz'n � lrGx nufpg]
!= ? %)) eGbf dfyL �
@= ? $%! b]lv %)) �
#= ? $)! b]lv$%) �
$= ? #%! b]lv $)) �
%= ? #)! b]lv #%) �
^= ? @%! b]lv #)) �
^= ? @)! b]lv @%) �
&= ? !%! b]lv @)) �
$=^ gofF vfg]kfgL ljt/0f k|0ffnLsf] Joj:yf x'g tkfO{sf] kl/jf/af6 klg k|ltj4tf :j?k clu|d /sd of]ubfg ug'{ kg]{f/dfx'G5,slt oxfFsf] ljr k|ltzt of]ubfg x'g ;S5<
nfutsf] %Ü !)Ü !%Ü
$=& gofF ;/;kmfO{ ;'ljwf-d'bflos zf}rfno tyf ;txLn9 lgdf{0fsf] nflu ;x nufgL :j?k !%Ü :yfgLo lgsfo / pkef]Qmfn] ;xnufgL ug{ OR5's x'g'x'G5< 5' 5}g olb rfxg'x'G5 eg], slt ;Dd<
$=* oxfFnfO{ geO gx'g] tyf eP /fd|f] x'g] k|fylds cfjZostf s'g xf]< lghL wf/f h8fg lghL rkL{ lgdf{0f b'j} %=n}lËs b[li6sf]0faf6 dlxnf ;xeflutf -cfof]hgfsf] ljleGg r/0fdf dlxnf ;xeflutf ;DalGw hfgsf/L ;+sng ug{ k|To]s 3/b}nf]df, nlIft ;d'x 5nkmnaf6 / 5'§} dlxnfdfq;f]lwg];d'x;Fu k|Zgx?_
s_ dlxnfx?sf] pkl:ylt / ;xefuLtf
%=! cfof]hgfsf]af/]df 5nkmn ug{ s'g} a}7s af]nfO{Psf] lyof] < lyof] lyPg
%=@ s] cfof]hgfsf] 5gf}6 ug{ a}7sdf dlxnf pkef]Qmfx?sf] pkl:ytL lyof] < lyof] lyPg olb lyof] eg]
<
dlxnf pkef]Qmfx?sf] e'ldsf s:tf] lyof]
;'Gg] dfq cGtlqm{ofTds lg0ff{os
%=# cfof]hgfsf] lqmofsnfkx?sf] /]vb]v ug{ s] vfg]kfgL pkef]Qmf tyf ;/;kmfO{
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
143
;ldlt÷;+:yf u7g ePsf] 5 < 5 5}g
%=$ vf=kf=p=;=;ldltsf ;b:ox? dWo] slt dlxnf ;b:ox? 5g\< -cGtjf{tf ng]l JolQmn] vf=kf=p=;=;=l;t ;ldltsf] kbflwsf/L tyf ;b:ox?sf] gfdfjnL tyf tnlj sd{rf/Lsf] ljj/0f dfu u/L pknJw u/fpg] _
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
144
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project v_ n}lËstfsf cfwf/df sfo{ ljefhg
%=% tnsf] tflnsfdf lbOPsf] sfdx? cS;/ s:n] ug]{ (ub{5<√)lrGx nufpg';\ b}lgs 306fdf qm=;+ 3/fol; lqmofsnfkx? k'?if Dflxnf s'n ;do ! Vffg]kfgL eg]{, af]Sg], e08f/0f / k|of]u ug]{
@ efG5f tof/ ug]{, ef8fF dfem\g
# Affnaflnsf / j[4j[4fsf] :ofxf/
$ n'uf w'g]3/ ;kmf ug]{
% vfBfGg e08f/0f tyf tof/L
^ cGo
u_ kfl/jfl/s Joj:yfkg, cfo >f]t / cGo ljifodf dlxnfx?sf] lgoGq0f / kx'Fr %=^ tnsf] tflnsfdf pNn]lvt kfl/jf/Ls ljifo jf If]qx?df lg0f{o ubf{ oxfFsf] 3/ dlxnf÷k'?ifsf]kl/jf/df egfO{sf] ;'g'jfO{ x'G5 < pko'Qm sf]7fdf
(√)lrGx nufpg';\ qm=;+ ljifo jf sfo{If]qx?
x'G5(√)
x'b}g(√)
! cfly{s ;/f]sf/sf s'/fx?
@ s]6fs]6Lsf] lzIff lbIff
# s]6fs]6L / j[4j[4fsf] :jf:Yo / :ofxf/
$ crn ;Dklt lsgj]r- 3/ hUuf_
% b}lgs lqmofsnfkx?
^ ;fdflhs ljlw Jojxf/, ljjfx, at{jGw, rf8kj{ tyf
;fdflhs÷kfl/jf/Ls ;';DjGwg cflb
& cGo
%=& oxfFsf] kl/jf/df kfl/jf/Ls ;Dkltsf lgDg ljifodf dlxnfsf] kxF'r / :jfldTj /x]sf] 5 5}g tnsf] tflnsfdf pko'Qm(√)lrGxsf]7fdfnupg';\
qm ;+ ljj/0f kx'Fr :jfldTj
! hUuf hldg
@ 3/ tyf cGo ;+/rgfx?
# rn ;Dklt÷;l+rt k};f
$ B}lgs lqmofsnfkx?
% cGo
3_ vf=kf=p=;=;= tyf ;d'bfodf dlxnfsf] :t/-x}l;ot_- lgDg a'Fbfx? cGt/jftf{ lng] JolQmn] u/]sf] cjnf]sgsf cfwf/ x'g]5 _
qm;+ ljifo pRr dWod lgDg
! cfTd;Ddfgaf]w
@ cfTdljZjf; g]t[Tj zLk
# bfloTjaf]w / Ifdtf
$ Nofst, ts{ ;+ut, w}o{ / d]xgt
% cGo
^= ;d ljsf;df kx'Frsf cfwf/df ;fdflhs ;dfj]zL ;xeflutf
-cfof]hgfsf] ljleGg r/0fdf u}/nfeflGjt ljkGg ju{sf,] cflbjf;Lhghflt, blnt tyf k5fl8 k/]sf ju{sf] ;dfj]zL ;xeflutf ;DalGw hfgsf/L ;+sng ug{ k|To]s 3/b}nf]df, nlIft ;d'x 5nkmnaf6 / 5'§} dlxnf ;d'x;Fu 5nkmn ubf{ ;f]Wg] k|Zgx?_
s_ cfof]hgf lqmofsnfkdf u}/nfeflGjt ljkGg ju{x?, hfthflt, blnt, ckfËtf ePsf] JolQmsf] ltpkl:y
^=! cfof]hgfsf]af/]df 5nkmn ug{] s'g} e]nf÷a}7sdf ;dfj]zL tj/n] af]nfO{Psf] lyof] <
lyof] lyPg
^=@ s] cfof]hgfsf] 5gf}6 ug{ a}7sdf ;dfj]zLtfsf] cfwf/df ;xefuLx?sf] pkl:ytLyof] lyof]<lyPg
^=# s] vf=kf=p=;=;=sf] u7gdf ;dfj]zLtf c+uLsf/ePsf] lyof]< lyof]
lyPg
v_ lg0f{o k|lqmofdf ;dfj]zL k|s[of ckgfPsf] lyof] <
^=$ cfof]hgf 5gf}6 ug{ hfthfltx?sf] s:tf] e"ldsf s:tf] lyof] <
pRr dWod lgDg
^=% ;fgf ;x/L
vfg]kfgL cfof]hgf sfof{Gjog ug{ ;fdflhs ;dfj]zL cfwf/df pkef]Qmfx?sf] kl/rfng ug{ ePsf] k|of; s:tf] lyof]<
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
145
/fd|f] dWod lgDg
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
146
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
&= :jf:Yo / ;/;kmfO s= vfg]kfgL ! tkfO{Fsf] ljrf/df kfgLsf] u'0f:t/ -g/fd|f]v/faePdf s] ;d:ofx? lvgb] ;S5 < -Ps eGbf a9L pQ/ cfpg ;Sg]_
!=! b'u{Gw cfpg] ÷ gld7f] :jfb
!=@ bfFt ljlu|g]÷/+uLg]
!=# la/fdL agfpg]
!=$
cGo -pNn]v ug]{_ =================
@= s] tkfO{FnfO{ kfgL eg]{ / /fVg] efF8f] kfgL eg'{ / e08f/ ug'{ ug'{k5{ eGg]
yfxf 5 < 5 5}g
olb 5 eg], kfgL /fVg] efF8f] s;/L ;kmf ug'{ x'G5 <
vfnL kfgL dfqn] v/fgL kfgLn] e';÷lk7f] / kfgLn]
;fa'g kfgLn] cGo-pNn]v ug'{;\ =============================
#= tkfO{ 3/df kfgL s;/L /fVg' 5x'G<
-Ps eGbf a9L pQ/ cfpg ;Sg]_
#=! kfgL eg'{ klxn] efF8f ;kmf ug]{
#=@
af;L kfgL km\ofFSg]
#=# kfgL /fVg] efF8f] /fd|f];Fu 9fs]/÷5f]k]/ /fVg]
#=$ cGo -pNn]v ug]{_============================
$= tkfO{ ufu|f] jf 3}+6f]af6 kfgL s;/L lgsfNg'x'G5 <
$=! kfgL ;fg'{ cl3 cDvf]/f, nf}6f, s?jf, du wf]P/
$=@ lunf;, du, sk ufu|Ldf 8'afP/
$=# ufu|f]af6 nf]6f, c+Dvf]/f, s?jf, lunf;df kfgL ;f/]/
$=$= cGo -pNn]v ug]{_ ===============================
v= rkL{
!= rkL{ k|of]usf kmfO{bfx? s] \<s]-PseGbf5g j9L pQ/ cfpg ;Sg]_
!=! a'9f, afns tyf la/fdLnfO{ ;'ljwf
!=@ 3/ tyf jftfj/0f ;kmf x'g]
!=# uf]Kotf x'g]
!=$ /f]uaf6 arfj6 x'g]
!=% cGo -pNn]v ug]{_===================================
@= s] tkfO{FnfO{ lb;faf6 /f]u ;5{ eGg] nfU5nfU5< nfUb}g
olb nfU5 eg], dflg;sf] lb;faf6 ;g]{ /f]ux?sf] gfd \<eGg'xf];================================
#= s] tkfO{Fsf] 3/df rkL{ 5 < 5 5}g
#=! olb 5 eg], s:tf] k|sf/sf] rkL{ 5 <
! vfN8] rkL{
@ e]lG6n]6]8 vfN8] rkL{
# jf6/ l;n÷kf]/ km\n;
$ l;:6g{ km\n;
% cGo =================
=@
olb 5 eg], tkfOF{sf] 3/df rkL{ s;s;n] k|of]u ug'{x'G5
-!= ;a}n], @= aRrf afx]s ;a}n] #= jo:s / k|f}9n] dfq} $= lj/fdL dfq}n]_
#=# olb 5}g eg], lsg rkL{ gagfpg' ePsf] xf] <
-s= agfpg] tl/sf yfxf geP/, v= nufgL ug{ g;s]/, u= v'Nnf d}bfgdf lb;f ug]{ afgL eP/, 3= hUufsf] cefjn]cGo ª -pNn]v
ug]{+_===============_
#=$ olb 5}g eg,] lb;f ug{ sxfF hfg'x'G5
-s= Vff]nf÷hËn÷lsgf/ v= v'Nnf d}bfg÷7fpF u= 3/÷;8s 5]p 3= hxfF ;lhnf] x'G5_
#=% olb 5}g eg], rkL{ agfpgslt nufgL ug{ ;Sg' x'G5 < ?=
u= vfg]s'/fsf] ;/;kmfO
!= vfBkbfy{ b"lift x'gaf6 s;/L arfpg'x'G5-Ps <eGbf a9L pQ/ cfpg;Sg] _
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
147
!=! ksfPsf] vfgf 5f]k]/÷9fs]/ /fVg]
!=@ af;L aRg] u/L w]/} gksfP/
!=# sfFr} vfOg] vfg]s'/f /fd|f];Fu kvfn]/ wf]P/ dfq vfg]
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
148
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
!=$ xft uf]8f ;kmf u/]/ dfq efG;fdf k;]/
!=% ;kmf xftn] vfgf k:sg]
!=^ 8f8' kGo', yfn÷efF8fs'F8f ;kmf u/]/ dfq vfgf k:sg]÷vfg]
!=& r'nf] rf}sL ksfpg] ef8f, 9sgx? ;kmf /fVg]
!=* w]/} af;L jf ;8] un]sf kmnkm'n t/sf/L gvfg]
@= s] tkfO{ vfg]s'/f]/÷9fs]/5f]k /fVg'x'G5 < /flVbg
olb /fVg'x'G5 eg], To;af6 s] s] kmfObfx?\< -5gPs eGbf j9L pQ/ cfpg ;Sg]_
@=! w'nf] d}nf], lem+uf, ;fËnf, ls/f, tyf 3/kfn'jf kz'kG5Laf6 arfj6
@=@ d";f÷5'r'Gb|f]÷dfp;'ln÷la/fnf]af6 aRg
@=# vfB k|b'if0faf6 x'g] /f]uaf6 aRg
@=$ cGo -pNn]v ug]{_=====================================
hLjghn agfpg] tl/sf yfxf 5 5}g ;f]Wg], olb yfxf ePdf ;lx tl/sfn] hLjghn agfpg] . hLjghn agfpg] ;l lgDgcg';f/sf] 5 .
!= klxnf ;fa'g kflgn] xft ;kmf ug]{, @= lrof lunf;sf] ^ lunf;-Psln6/_ kfgL Pp6f ;kmf efF8f]df xfNg]-olb kfgL pdfn]sf
ePdf ;]nfpg lbg]_, #=hLjghnsf] Ps Kofs]6leq ePsf] w'nf] k"/} kfgLdf xfnL kfgLnfO{ /fd|/L rnfP/ w'nf]nfO{ 3'N
3= JolQmut ;/;kmfO
!= tkfO{F / kl/jf/sf cGo ;b:on] slxn] / s] u/]kl5 xft w'g'x'G5 < w'g]-� lrGxePo:tf]nufpg'xf];\/ gw'g] eP o:tf]-× lrGx nufpg'xf];- .
Ps eGbf a9L pQ/ cfpg ;Sg]_
% jif{ d'lgsf
qm=;+= lqmofsnfk afnaflnsf dlxnf k'?if
w'g]-�_ gw'g]-×_ w'g]-�_
gw'g]-×_ w'g]-�_ gw'g]-×_
! vfgf vfg' cl3
@ vfgf vfPkl5
# lb;f uPkl5
$ kmf]x/ d}nf 5f]Pkl5
% sfdaf6 kms]{kl5
^ s]6fs]6LnfO{ lb;f lk;fj u/f
;s]kl5
& cGo -pNn]v ug]{_
@= tkfO{ / kl/jf/sf cGo ;b:on]s] n] xft w'g'x'G5 < w'g]df-� _o:tf]lrGx nufpg'xf];\/ gw'g]df o:tf]-× lrGx nufpg'xf]; .
% jif{ d'lgsf
qm=;+= lqmofsnfk afnaflnsf dlxnf k'?if
w'g]-�_ gw'g]-×_ w'g]-�_
gw'g]-×_ w'g]-�_ gw'g]-×_
!= kfgL dfq}
@= v/fgL kfgL
#= e';÷lk7f] kfgL
$= ;fa'g kfgL
%= cGo -pNn]v ug]{_
hDdf
#= tkfO{ / kl/jf/sf cGo ;b:on] slxn] slxn] g'xfpg'x'G5 <
g'xfpg] eP o:tf]-�_ lrGx nufpg'xf];\/ gg'xfpg] eP o:tf]-× lrGx nufpg'xf]; .
qm=;+= k|lqmofsnfk afnaflnsf dlxnf k'?if
-�_ -×_ -�_ -×_ -�_ -×_ != k|To]s lbg
@= Ps lbg la/fP/
#= xKtfdf @ k6s
$= xKtfdf ! k6s
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
149
%= @ xKtfdf ! k6s
^= dlxgfdf Ps k6s
hDdf
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
150
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
ª= kmf]x/ d}nf Joj:yfkg
!= tkfO{sf] 3/af6 lg:sg] 7f]; kmf]x/ d}nf sxfF lj;h{g< ug'{x'G5
!=! 3/ glhs vfN8f]df
!=@ lghL kmf]x/ ;+sngstf{nfO{ lbg]
!=# uf=lj=;=÷gu/kflnsfn] Joj:yf u/]sf] vfN8f] jf Sofgdf
!=$ cGo -pNn]v ug]{_ ===================================================
@= 7f]; tyf t/n kmf]x/ j:t'nfO{ cJojl:yt tl/sfn] lj;h{gugf{n] x'g] g/fd|f c;/x? s]\< s]-Psx'geGbf j9L pQ/ cfpg; Sg]_
@=! kmf]xf]/ jftfj/0fdf j[l4
@=@ nfdv'§], lem+uf, ls/fx?sf] j[l4
@=# /f]u ;g]{df j[l4
@=$ cGo -pNn]v ug]{_ ========================================
#= tkfO{sf] 3/af6 lg:sg] kmf]xf]/kfgLsxfF lj;h{g ug'{x'G5 <
#=! vfN8f]df(Soak pit)
#=@ t/sf/L af/Ldf÷s/];f af/Ldf
#=# ;fj{hlgs 9ndf
#=$ cGo -pNn]v ug]{_ ==========================================
r= j:t'efpsf] kmf]x/ Joj:yfkg
!=
s] tkfO{n] a:t'efp kfNg' ePsf]5 5 <
5}g
-olb 5}g eg] kfgL hGo ;?jf /f]udf hfg]_
olb 5 eg] s'g s'g k|sf/sf\/ 5gltgLx?nfO{ sxfF /fVg' x'G5 <
qm= ;+= a:t'efpsf] k|sf/ 3/leq} /fVg] aflx/ 5'§} uf]7df /fVg]
! ufO{÷e}+;L
@ a+u'/÷;+u'/
# afv|f
$ s'v'/f÷xfF;
% cGo
@= a:t'efpaf6lg:sg] kmf]xf]/ sxfF / s;/L lj;h{g ug'{x'G5 <
@=! dnvfbdf
@=@ cfuf] afNg]÷u'OF{7f agfpg]
@=# uf]j/ Uof; KnfG6df k|of]u ug]{
@=$ cGo -pNn]v ug]{_ ======================================
#= j:t'efpsf] kmf]xf]/ d}nfsf] hyfeflj cJojl:yt tj/n] lj;h{gx'g] ubv/fj{ c;/x? s] s]\< x'g-Ps eGbf j9L pQ/ cfpg ;Sg]_
#=! jftfj/0fL kmf]xf]/df j[l4 x'g]
#=@ nfdv'§,] lem+uf, ls/fx?s]f j[l4 x'g]
#=# /f]uAoflw j9\g] tyf ;g]{
#=$ ufFp, 5/l5d]s tyf gu/ czf]elgo b]lvg]
#=% cGo -pNn]v ug]{========================================
5= kfgLhGo ;?jf /f]ux?
!= kfgLhGo ;?jf /f]usf] sf/0fx? s] s]\< x'g-Ps eGbf j9L pQ/ cfpg ;Sg]_
!=! b"lift kfgL k|of]u ubf{
!=@ b"lift vfgf vfFbf
!=# 3/ tyf ;fj{hlgs :yndf kmf]x/ a9\gfn]
!=$ dflg;sf] nd"q hyfefjL km\ofSg] ubf{
!=% kmf]xf]/ d}nf hyfefjLofFSg]\km ubf{
!=^ :jf:Yo lzIff tyf :j:y afgLsf] cefj
!=& ;/;kmfO{ / :jf:Yo ;DjGwL 1fg / r]tgfsf] cefjn]
!=* cGo ======================================================================================
@= tkfO{Fsf] kl/jf/df sf]xL la/fdL k/]df s] ug'{x'G5-k|fyldstf< cg';f/ gDa/ n]Vg]_
@=! 3/fo;L pkrf/ ug]{
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
151
@=@ wfdL, emfFqmL, k'hf/L sxfF nfg]
@=# cf}iflw k;ndfhfg]
@=$ :Jf:Yo rf}ls jf c:ktfndf hfg]
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
152
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
@=% cGo -pNn]v ug]{_
#= olb kl/jf/df s;}nfO{ emf8fkvfnf nfu]df s] ug'{x'G5-k|fyldstf< cg';f/ gDa/ n]Vg]_
#=! hLjghn v'jfpg]
#=@ 3/fo;L pkrf/ ug]{
#=# wfdL, emf+qmL jf k'hf/L sxfF hfg]
#=$ cf}iflwk;ndf hfg]
#=% :jf:Yo rf}ls jf c:ktfndf hfg]
#=^ cGo -pNn]v ug]{_==========================
$= ut Ps jif{leq kl/jf/sf ;b:ox? tnsf /f]ux? dWo] s'g s'g /f]uaf6 lj/fdL-df]la{l8l6eP< sf] l:ylt_
%= tkfO{sf] kl/jf/df kfgLhGo lgDglnlvt ;?jf /f]uaf6 sf]lxlj/fdL k/]sf] lyof]< tnsf] tflnsfdf ;+Vof pNn]v\. ug'{;
% jif{ d'lgsf jflif{s
qm= ;+= /f]u
afnaflnsf dlxnf k'?if vr{ ?=
! emf8fkvfnf
@ cfpF
# h'sf
$ 6fO{kmfO{8
% x}hf
^ 5fnf ;DaGwL /f]u
& cf}nf]/f]u-dn]l/of _
* sdnlkQ -h08L;_
( cGo
hDdf
^= ut Ps jif{leq tkfO{sf kl/jf/df sf]xL emf8f kvfnf tyf kfgLhGo cGo ;?jf /f]ux?af6 d[To' ePsf]-d[To'5 <cj:yf_
/f]u % jif{ d'lgsf afnaflnsf dlxnf k'?if
emf8f kvfnf
cfpF
kfgLhGo cGo ;?jf /f]ux?
hDdf
&= ut Ps jif{leq tkfO{Fsf] kl/jf/sf ;b:onfO{ emf8fkvfnf / kfgLhGo cGo ;?jf /f]ux?sf] pkrf/df slt /sd vr{ ug'{ eof] <
/f]u Vfr{ /sd- ?=df_
@))) ;Dd @))!—#))) #))!—%))) %))) eGbf dfly
emf8fkvfnf
kfgLhGo cGo ;?jf /f]ux?
hDdf
;xof]usf nfuLwGojfb!
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
153
Initial Environmental Examination (IEE) of Shivanagar Town Water Supply and Sanitation Project
Initial Environmental Examination(IEE) of Shivanagar Town Water Supply and Sanitation Project
Annex 9: Photographs
Photo 1: WUSC Office Building at Dhangadhi Photo 2: OHT Site of Shivanagar Photo 3: Ground water intake (test boring) Photo 4: Land acquired by WUSC Photo 5: Interaction meeting with WSSDO Photo 6: Consultation with WUSC members