environmental regulations & nuisance case update€¦ · planned to begin (recommendation but...
TRANSCRIPT
ENVIRONMENTAL REGULATIONS & NUISANCE
CASE UPDATE
IOWA PORK PRODUCERS ASSOCIATION
September 10, 2010
Eldon McAfee
ANIMAL CAPACITY Animal weight
capacity and animal unit capacity
Constructed before 2002 legislation – AWC - maximum number of animals confined at any time in a confinement operation multiplied by the average weight during a production cycle
Constructed or expanded after 2002 legislation – AUC - maximum number of animals confined at any one time in a confinement operation multiplied by the animal unit factor Animal unit factor – swine
.4 - more than 55 pounds, .1 – 15 to 55
AFO – CFO & OFO
Confinement Feeding Operation (CFO)
An AFO in which animals are confined to areas which are totally roofed
Open Feedlot Operation (OFO)
Unroofed or partially roofed AFO if crop, vegetation, or forage growth or residue cover is not maintained as part of the AFO while the animals are confined
CFO cannot discharge under Iowa law
PARTIALLY ROOFED AFO
New DNR rule definition of partially roofed AFO to qualify as OFO:
Animals must have unrestricted access between inside and outside areas
Unroofed area must be at least 10% of square footage inside area
If these requirements not met, the AFO is a CFO even though animals are not confined to areas which are totally roofed
To determine if a permit or manure management plan is required, and if concrete standards apply:
Two CFO’s are considered to be one operation when: At least one of the two is constructed after 5/21/98
There is common ownership or management, and
They are adjacent; or
Utilize a common area or system for manure application
Adjacent – CFO’s within:
1,250 feet if the combined AUC is <1,000
2,500 feet if the combined AUC is >1,000
CONFINEMENT OPERATIONS One or two?
New DNR rule: common area or system for manure disposal:
Includes same manure storage, confinement structure, stockpile, permanent manure transfer piping system or center pivot.
Does not include:
Manure application fields in MMP
Anaerobic digesters
CONFINEMENT OPERATIONS One or two?
To determine required separation distances: Two CFO’s are considered to be one operation when:
At least one of the two is constructed after 3/21/96 There is common ownership or management, and They are adjacent
Adjacent – CFO’s within: 1,250 feet if the combined AUC is <3,000 for
finishing or nursery (<1,250 AUC for farrow-gest. or <2,700 AUC for farrow to fin.)
1,500 ft. if the combined AUC is >3,000 but <5,000 for finishing or nursery (>1,250 but <2,000 AUC for farrow-gest. or >2,700 but <5,400 AUC for farrow to fin.)
2,500 feet if the combined AUC is >5,000 for finishing or nursery (>2,000 AUC for farrow-gest. or >5,400 AUC for farrow to fin.)
CONFINEMENT OPERATIONS One or two?
Two OFO’s are considered to be one operation when:
There is common ownership or management, and
They are adjacent; or
Utilize a common area or system for open feedlot effluent application
Adjacent – OFO’s are adjacent if:
Less than 1,250 feet apart; and
At least one open feedlot operation structure is constructed on or after July 17, 2002.
OPEN FEEDLOT OPERATIONS One or two?
Common ownership: sole or at least a majority
ownership interest
Includes ownership by spouse or dependent
child
Common management
Significant control of day-to-day operations
Does not include control by an owner of animals being fed in two or more CFO’s or OFO’s
New DNR rule changed previous DNR interpretation for CFO’s
CFO’S & OFO’S One or two?
CONSTRUCTION-FORMED STOR. 500 animal units or less (small AFO)
Separation distances from water bodies (500 ft. from creek, etc.) & wells
No construction in 100 yr. floodplain of navigable river, etc. (if on alluvial soils, must get DNR Order that site is not in 100 yr. floodplain)
Tile around footings for below ground storage (or certification that groundwater table is below the structure)
Stormwater discharge permit if area disturbed during construction is more than 1 acre
CONSTRUCTION-FORMED STOR. 500 & 1,000 animal units
MMP & construction design statement to DNR & county 30 days before construction
Note: All information on the MMP & CDS be completed correctly – DNR has taken the position that the 30 day period does not start if certain info is not correct or is missing
DNR construction approval letter – new rule: expires if construction not begun within 1 year or completed within 4 years
Meet construction design stds. (including tile around footings or cert. regarding groundwater level)
CONSTRUCTION-FORMED STOR. 500 & 1,000 animal units
Meet required separation distances
No construction in 100 yr. floodplain of navig. river, etc. (if on alluvial soils, must get DNR Order that site is not in 100 yr. floodplain)
Karst soil determination
Info on other CFO’s under common ownership or management within 2500 ft.
Stormwater discharge permit if area disturbed during construction is more than 1 acre
See www.iowadnr.com/afo/forms.html for forms
CONSTRUCTION-FORMED STOR. 1,000 animal units or more
Construction permit app. to DNR & county (DNR has 60 days to act but can extend for add. 30 days)
New DNR rule: Permit application should be submitted 120 days before construction is planned to begin (recommendation but not required)
New DNR rule: No permit for 120 days after completion of construction without a permit
Engineer required if 3,000 or more a.u.’s (1,250 a.u.’s for farrow gest or 2,750 a.u.’s for farrow to finish)
CONSTRUCTION-FORMED STOR. 1,000 animal units or more
Const. design statement if no engineer req’d
Meet construction design stds. (including tile around footings or eng. cert. regarding groundwater level)
Meet required separation distances
No construction in 100 yr. floodplain of navig. river
MMP & stormwater discharge permit
New rule: any changes to design during construction must be DNR approved first
See www.iowadnr.com/afo/forms.html for forms
CONSTRUCTION-FORMED STOR. 1,000 animal units or more - matrix
Not required if expansion up to 1666 a.u.’s if site constructed as of 4/1/02 or if county has not adopted matrix
Supporting documentation, including design, operation, and maintenance plans. If the necessary supporting documentation
is not included, DNR takes the position that it may reject the permit application (even if a county passes the matrix) because the matrix is a part of the permit
If a county does not pass the matrix, DNR independently scores the matrix, including items the county gave a passing score
CONSTRUCTION-FORMED STOR. 1,000 animal units or more - matrix
DNR interpretation of requirements upon independent review following county denial: Requirements for design, operation &
maintenance plans for: landscaping composting formed storage truck turnaround feeding & watering systems to reduce
manure volume
CONSTRUCTION-FORMED STOR. 1,000 animal units or more - permit
DNR rules require the owner of the site or the structures to be the permit applicant
New rule: Owner means person who has legal or equitable title
Purchase contract contingent upon permit being issued should qualify the permit applicant as an owner as an equitable titleholder
CONSTRUCTION-FORMED STOR. 1,000 animal units or more
Construction permit required if any construction of a manure storage structure occurs on site
Permit required even if no physical construction or alteration if there is an increase in manure volume or a modification in the manner manure is stored. Unless increases or modifications are:
Within the limits of a previously issued const. permit
Determined insignificant by DNR (e.g., double stocking weaned pigs in a wean-to-finish barn)
No permit required for repairs or additions to a building such as fans, slats, gates, roofs or covers
Plans for repair or modification to a manure structure must be submitted to DNR to determine if a permit is required
EARTHEN MANURE STORAGE
New DNR rule: need soils report with permit application
New DNR rule: Must control berm erosion with perennial grass on outer, top and inner (to freeboard line) berm areas unless covered by concrete, riprap synthetic liner or similar erosion control materials or measures
CONSTRUCTION Stormwater discharge permit
Required if the total area disturbed is more than one acre - activities that further cropping are exempt
To obtain a stormwater discharge permit for construction activities: Publish a form notice in 2 newspapers with the
largest circulation in the area Prepare a pollution prevention plan that includes
measures to be implemented to control erosion during construction and until a permanent ground cover is established. This plan must be in place at the time the notice of intent is submitted to DNR and must be kept on site
Submit a notice of intent to be covered by the state general stormwater discharge permit to DNR at least 24 hours before construction begins. Attach proof of publication of public notice to the notice of intent and filing fee.
See www.iowadnr.com/afo/forms.html for forms
SEPARATION DISTANCES Residences, businesses, road rights of way, etc.
CFO’s with formed manure storage and more than 500 AUC are subject to separation distances regardless of whether a DNR permit is required-all new or expanding CFO’s with earthen storage are subject to separation distances
Residences, businesses, churches, schools, public use areas, and road rights-of-way
Public use areas include parks and cemeteries (pioneer cemeteries (6 or fewer burials in the last 50 years) are exempt)
For a worksheet and separation distance tables see: www.iowadnr.com/afo/files/distreq.pdf
SEPARATION DISTANCES Residences, businesses, road rights of way etc.
Exemptions: Written waiver from owner of residence, etc. –
must be recorded with county recorder Also may want to include:
Covenant-not-to sue for nuisance Approval by residence mortgage holder
Expansion of CFO -- use distances in effect at time CFO constructed (if CFO constructed before any distances required, 1995-1999 distances apply)
<2x cap.,<1,000 AUC, and new structure built further from residence, etc.
Residence, etc. built after CFO began operation
SEPARATION DISTANCES Road rights of way
100 feet from the right-of-way Exemptions:
Small animal feeding operations (500 or less animal units)
Waiver from state or county
SEPARATION DISTANCES Water bodies – rivers, creeks, wells, etc.
1,000 feet - Ag drainage wells, sinkholes, navigable waters (major water sources -- rivers, etc. from list in DNR rules – new list goes into effect on 4/16/06)
500 feet - Surface inlets to ag drainage wells & water sources (creeks,etc.) – DNR policy on watersource
2,500 feet - Designated wetlands (designated as protected by U.S. Dept. of Interior or DNR; and owned and managed by the U.S. government or DNR
Wells – formed manure storage
200 feet from a shallow well
100 feet from a deep well
Can request variance from DNR
SEPARATION DISTANCES Water bodies – rivers, creeks, wetlands, etc.
Distances for water sources, major water sources or designated wetlands do not apply to: Farm ponds – defined as body of water:
Wholly on the lands of a single owner, or group of joint owners
No connection to public waters Less than 10 surface acres
Privately owned lakes – defined as any lake: Not subject to federal control covering navigation Owned by an individual, group of individuals, or
a nonprofit corporation Which is not open to the use of the general
public but is used exclusively by the owners and their personal guests.
SEPARATION DISTANCES Water bodies – rivers, creeks, wetlands, etc.
Distances for water sources, major water sources or
designated wetlands do not apply to:
CFO structures using secondary containment
barriers
Contain greater of 120% of manure stored
above grade or 50% of manure below ground
Can be concrete and/or earth
Earthen barriers must meet percolation & design
standards
SEPARATION DISTANCES Water bodies – rivers, creeks, wetlands, etc.
Distances for water sources, major water sources or designated wetlands do not apply to: CFO structures using secondary containment
barriers New DNR rule:
Can have relief outlet or valve – must remain closed & any liquid due to overflow must be land applied per MMP
Must submit site-specific plan with permit app. or CDS if no permit required
Liquid manure: barrier must be designed by an engineer or NRCS
Dry manure storage: No on-site stockpiling outside of structure Contain 10% of manure stored Percolation & design standards do not
apply
MANURE MANAGEMENT PLANS Original (new) filed with DNR & county
Formed storage
More than 500 animal units capacity (
Constructed or expanded after 5/31/85
Earthen storage- DNR construction permit
New DNR rule: For MMP’s after Sept. 15, “dominant critical area” determined under NRCS Tech. Note 29
New DNR rule: Upon transfer of operation
New MMP within 60 days – can use existing MMP for manure application until then
MMP fees and indemnity fund fees
Family transfers & forming a corporation - check with DNR to see if new MMP needed
MANURE MANAGEMENT PLANS Annual updates
To DNR and county
Short form detailing changes in MMP or statement that there are no changes
May use table values in updates submitted to DNR each year & then apply manure based actual sample values if amend plan before manure applied (do not have to submit amended plan to DNR)
Compliance fee - $.15/a.u. – if contract feeding, livestock owner required to pay fee
MANURE MANAGEMENT PLANS Recordkeeping
Records - must be kept on site or at a residence or office of the owner or operator within 30 miles of the site
DNR recordkeeping form – not mandatory, producer can use own form
Current MMP
Rate, methods and date(s) of app.
Field location and number of acres
Get records immediately (or as soon as possible) from the manure applicator
MANURE MANAGEMENT PLANS Recordkeeping – commercial N & P
For manure applications after 8/25/05, MMP records must include dates and application rates of commercial N & P on fields receiving manure – including land farmed by someone else where manure is applied under an application agreement.
DNR cannot bring an enforcement action for over application of N or P on land farmed by someone else unless the producer “knew or should have known” that commercial N or P would result in N or P exceeding legal limits.
MANURE MANAGEMENT PLANS Recordkeeping – commercial N & P
Producer must obtain statement from
farmer who owns, rents, or leases each
field receiving manure specifying the
planned commercial N and P fertilizer
rates to be applied to each field
DNR form, but can use own form for
individual situations
MANURE MANAGEMENT PLANS Phosphorus index –DNR rules
Must be calculated every 4 years, more often if PI inputs change - submitted to DNR as annual update
P Index categories (not the same as soil test):
Very low (0-1)- N based MMP
Low (>1-2) N based MMP
Medium (>2-5)
Manure may be applied at N based rates if current and/or planned soil conservation and P mgt practices predict the PI will not exceed the medium category at the next PI determination
Manure not applied in excess of 2 times the P removed over crop rotation
If follow P based rates in these categories, soil samples can cover up to 20 acres
MANURE MANAGEMENT PLANS Phosphorus index –DNR rules
P Index categories (not the same as soil test): High (>5-15)
(>5-10) Until 12/31/08, manure may be applied at P based rates if practices adopted to reduce the PI to medium for the next determination (intent – be able to continue applying
manure while implementing practices) (>10-15) no manure application
(intent – no additional manure applications until practices implemented to reduce PI to medium)
Very high – no manure application
MANURE MANAGEMENT PLANS Phosphorus index –DNR rules
Phosphorus based rates:
P applications over the crop schedule limited to crop removal unless additional P recommended by soil tests
P from a manure application cannot exceed crop removal from the next 4 planned crops
P crop removal = optimum yield X P removal rate for each crop (.375 lbs. P/bu. of corn, or other credible data)
MANURE MANAGEMENT PLANS Phosphorus index –DNR rules
Fields – PI calculated for each field. Fields must be contiguous-not separated by a road, river, creek, etc.
Soil type to calculate PI must be most erosive soil map unit that is at least 10% of the total field
Soil sampling - Every 4 years Samples for each 10 acres (20 acres if PI vl, l, or m
and apply manure on P rates)(fields up to 15 acres – one sample)
Samples averaged for soil test level of a field Existing soil tests may be used if they meet DNR
requirements MMPs for construction, if previous soil tests are
less than 4 years old and don’t meet requirements, they may still be used if new soil tests meeting DNR requirements are taken within one year after the MMP is approved
MANURE APPLICATOR CERTIF.
New rule: Confinement site applicator who misses course one year must pass exam to remain certified
Commercial manure service: in the business of transporting, handling, storing, or applying manure for a fee
DNR interpretation: If a producer applies the producer’s manure (from a site that requires applicator certification) to someone else’s land and receives money (for either the manure or the application), then the producer must be certified as a commercial applicator instead of as a confinement site manure applicator
COMPOSTING MORTALITIES
500 ft. from a residence other than the producer’s
Not in a wetland
100 ft. from private well, 200 ft. from public well
50 ft. from property lines
100 ft. from flowing or intermittent streams, lakes or ponds
Minimize formation of leachate & prevent runoff into and out of the compost facility
Minimize ponding, any ponding that occurs must be corrected within 48 hours
All weather surface of compacted soil, compacted granular aggregates, asphalt, concrete or other relatively impermeable material
COMPOSTING MORTALITIES
Minimize odors, dust, noise, litter and vectors which may cause nuisance conditions or health hazard
Storage of finished compost for no more than 18 months
Mortalities may be composted off-site at another livestock operation without a permit – no restriction on distance and do not have to be from the same owner or operator
Mortalities that died from infectious disease that can be spread by scavengers or insects or that died from a reportable disease must be disposed of under Iowa Dept. of Ag requirements
COMPOSTING MORTALITIES
Transportation vehicles must be constructed to prevent release of mortality contaminated materials
In transporting, the most direct haul route that avoids biosecurity risks must be used
Compost facilities must be designed for average annual death loss from all sites using the facility, raw materials, and finished compost
Mortalities from catastrophic death losses (fire or power outage) cannot be composted until DNR approves
COMPOSTING MORTALITIES
Mortalities must be in the compost within 24 hours
To control leachate, odors and animal scavenging, must have 12 inch bulking agent cover, 6-12 inches between carcasses, and 12-24 inch base depending on size and number of mortalities
Compost cannot be removed until soft tissue is fully decomposed
Compost (including bones) must be applied to cropland to minimize runoff into waters of the state
Application of compost to other than cropland needs DNR approval (pasture?)
DNR policy: If mortalities are composted in manure, the compost pile must also meet manure storage structure requirements
EPA CAFO RULE
CAFO – 2,500 head of swine over 55 lbs, 10,000 swine less than 55
CAFO must obtain a federal discharge permit (NPDES) if the CAFO discharges or proposes to discharge
CAFO discharges or proposes to discharge if it is designed, constructed, operated, or maintained such that a discharge will occur
Iowa confinement operations cannot discharge by law
Without an NPDES permit, can be no discharge – with an NPDES permit, can discharge from greater than 25-year, 24 hour storm event
EPA CAFO RULE
A discharge also includes discharges from land application
However, ag stormwater discharges do not require an NPDES permit
An ag stormwater discharge – CAFO must apply manure in compliance with a site specific nutrient management plan
This plan is not required to be submitted to EPA or DNR, but must be kept with records on site or “at a nearby office”
EPA CAFO RULE
Is NPDES permit needed for an
“accidental discharge”?
If the cause of an accidental discharge that
has occurred in the past has been changed
or corrected, the CAFO would not be
considered to discharge or propose to
discharge and an NPDES permit would not
be required due to the accidental discharge
EPA CAFO RULE
No Discharge Certification Option Voluntary
For CAFOs that do not discharge or propose to discharge
Why do it?
If discharge occurs, penalties for discharge but not for failure to have an NPDES permit
If discharge occurs without NPDES permit or voluntary certification option, CAFO has burden to prove it did not discharge or propose to discharge
EPA CAFO RULE
No Discharge Certification Option
EPA and DNR do not review the
certification
Requirements for certification are:
Technical evaluation
Signed certification statement
Statement submitted to DNR
EPA CAFO RULE
SETTLEMENT AGREEMENT
Announced May 26, 2010
With Sierra Club, NRDC, Waterkeepers
EPA agreed to:
Issue CAFO Guidance by 5.28.10
Propose new rule within 1 year
requiring all CAFO’s “whether they
discharge or propose to discharge” to
submit the following detailed info to
EPA:
EPA CAFO RULE
SETTLEMENT AGREEMENT
Name & address of CAFO owner &
operator & owner of animals
Location of the CAFO
Type of facility & no. & type of animals
Land application acreage & if has NMP
Whether CAFO transfers manure off-site
& if so, the quantity transferred
Whether CAFO has applied for NPDES
permit
EPA CAFO RULE
SETTLEMENT AGREEMENT
EPA also agreed to:
Require this info to be submitted every 5 years, or
explain why not
Take final action on the proposed rule within 2
years (May 26, 2012)
Release the info to the public, except confidential
business info
Accept a petition for rulemaking (requiring NPDES
permits) from Sierra Club, NRDC & Waterkeepers if
the orgs believe the info shows there are categories
of CAFO’s that “presumptively discharge”
Pay $95,000 in attorney fees & costs
EPA CAFO RULE GUIDANCE
Objective assessment:
CAFO’s conduct objective assessment to
determine if they discharge or propose to
discharge
Ongoing process
Of animal confinement, feed storage,
manure storage, confinement house
ventilation exhaust, land application, & any
pathways for pollutants to reach waters of
U.S.
EPA CAFO RULE GUIDANCE
Objective assessment:
Factors to be assessed include:
Proximity to waters of U.S.
Precipitation
Discharge history
Waste storage
Mortality management
Equipment maintenance protocols
Drainage
Nutrient management planning
EPA CAFO RULE GUIDANCE
Confinement barns – exhaust
Whether “pollutants” exhausted by ventilation fans
will then be transported in precipitation runoff to
waters of the U.S. If so, EPA takes the position that
the facility is proposing to discharge and must apply
for an NPDES permit
However, an NPDES permit is required only if there
is an actual discharge of pollutants to waters of the
U.S. So any exhaust fan pollutants that may come
in contact with precipitation runoff from around
confinement buildings must enter a water of the
U.S. for an NPDES permit to be required
EPA CAFO RULE GUIDANCE
Other key points:
Mortalities-protect from precip or runoff controlled
Manure app on frozen/snow covered ground:
Discharges are non-exempt land application
discharge, even if app complies with state law
Considered proposing to discharge if CAFO is
operated such that a discharge will occur
Factors specific to swine :
Maintenance of hoses for land application
Pipe or hose ruptures or overflows in shallow pit
to outside manure storage systems
CAFO - COMBINE CFO/OFO
EPA rules have never distinguished between OFO’s and CFO’s
Since 2003 when EPA rules established separate categories of animals, EPA rules have required OFO & CFO animals in same category to be added together
Iowa law has always kept OFO & CFO’s separate for purposes of Iowa law
April 2008 - Iowa law incorporated EPA rules combining OFO & CFO animals for NPDES & allowed until 12/31/08 to submit NPDES application
CAFO/NPDES permit requirements: OFO & CFO (within 1,250 feet) animals in same category at an AFO are added together
CAFO EPA - One AFO or two?
2 or more AFO’s under common ownership are one AFO if:
They adjoin; or
They use a common area or system for manure application
EPA: OK with Iowa’s adjacency distances – but if there are runoff problems, will work with DNR to designate as CAFO
CAFO (CONCENTRATED AFO)
CAFO - Three types:
Large CAFO
Medium CAFO
Designated CAFO CAFO must obtain a federal discharge permit
(NPDES) if the CAFO discharges or proposes to discharge pollutants to a water of the US
CAFO discharges or proposes to discharge if it is designed, constructed, operated, or maintained such that a discharge will occur
CAFO
Mixed animal CAFO’s
Do not add animal numbers from different categories to determine if CAFO threshold is triggered, as long as all animal numbers are below the threshold
Once the CAFO number threshold is met for one category, all manure generated by the AFO is subject to NPDES requirements Example, cattle OFO with less than 1,000 head
on the same site as hog CFO with more than 2,500 head -- hog CFO is a CAFO requiring an NPDES permit for the cattle OFO
LARGE CAFO
More than the number of animals in any one of the following categories:
700 mature dairy cows
1,000 cattle
2,500 swine weighing 55 pounds or more
10,000 swine weighing less than 55 pounds
500 horses, 10,000 sheep, 55,000 turkeys
30,000 laying hens or broilers (liquid manure)
125,000 chickens other than laying hens OR 82,000 laying hens (other than liquid manure)
DNR rules: 1,000 animal units where more than one category is kept in the same type of operation
MEDIUM CAFO
The number of animals in any one of the following categories:
200 to 699 mature dairy cows
300 to 999 cattle
750 to 2,499 swine weighing 55 pounds or more
3,000 to 9,999 swine weighing less than 55 pounds
Other categories for horses, sheep, turkeys, chickens
DNR rules: 300-999 animal units where more than one category is kept in the same type of operation
AND meet requirements on next slide
MEDIUM CAFO
Manure or process wastewater is discharged:
Into waters of the US through a man- made ditch, flushing system, or other similar man-made device; or
Directly into waters of the US which originate outside of and pass over, across or through the facility or otherwise come into direct contact with animals in the AFO.
MEDIUM CAFO
Key issue in Iowa: EPA: a road ditch is a “man-made ditch,
flushing system, or other man-made device” under the Medium CAFO definition
No change in this definition from pre-2003 EPA rule and that EPA rule stated that man-made means constructed by man and used for the purpose of transporting wastes
DESIGNATED CAFO
DNR may designate any AFO that is not a Large or Medium CAFO as a CAFO if after an on-site inspection DNR determines it is a significant contributor of manure to waters of the US using the following factors:
AFO size & amount of manure discharged
AFO location near waters of US
Means of conveyance to waters of US
Slope, vegetation, rainfall, and other factors
DESIGNATED CAFO
DNR cannot designate a CAFO with less than the Medium CAFO animal numbers unless:
Manure or process wastewater is discharged:
Into waters of the US through a man- made ditch, flushing system, or other similar man-made device; or
Directly into waters of the US which originate outside of and pass over, across or through the facility or otherwise come into direct contact with animals in the AFO.
DNR EVALUATION
DNR may evaluate an AFO and order remedial action if:
Manure is discharged into a water of the state
Manure is causing or may reasonably be expected to cause pollution of a water of the state
Manure is causing or may reasonably be expected to cause a violation of state water quality standards
IOWA LAW
OFO’s that are not Large CAFO’s, Medium CAFO’s or Designated CAFO’s must meet the following Iowa requirements:
Remove all settleable solids before discharge to a water of the state
Not violate a state water quality standard
CAFO
Without an NPDES permit, cannot discharge
With an NPDES permit
Large CAFO’s can only discharge from greater than 25-year, 24 hour storm event
Medium and Designated CAFO’s
Permit writer (Iowa DNR) must use “best professional judgment” (BPJ) to establish case- by-case appropriate technology-based requirements for each permit
EPA: on case-by-case basis, can have discharge in less than 25 yr 24 hr storm & reduced permit requirements
MANURE APPLICATION All livestock operations
No water pollution No manure app. within 200 feet of designated
area (800 feet if high quality water resource, see DNR website for list) unless: manure injected or incorporated on same date or permanent vegetation 50 ft. around water source &
no manure on 50 ft. area (does not apply to ag drainage wells)
Note: Incidental spillage when incorporating
Designated areas are: Creeks, rivers, lakes, designated wetlands, known
sinkhole, cistern, drinking water or abandoned well, ag drainage well or surface inlet
Excludes terrace tile or surface tile inlets and lakes or ponds with no outlet and which are entirely on one landowner’s land
MANURE APPLICATION Confinement operations – liquid manure
Must be injected or incorporated in 24 hrs. if applied within 750 ft. of residence, bus., church, school or public use area (250 ft. if use low pressure spray irrigation - <25
psi, center pivot < 9 ft. high)
Does not apply if: Waiver from owner of residence, etc. or
Operation has less than 500 animal units capacity
Note: For the separation distances from designated areas and residences, etc., DNR may consider incidental spillage (on endrows, etc.) while incorporating as surface application
MANURE APPLICATION Frozen or snow covered ground
Legislation effective July 1, 2009
New DNR rule on this legislation in effect on Sept. 15
MANURE APPLICATION Frozen or snow covered ground
Does not apply to:
Manure from open feedlot operations
Dry manure (can’t be pumped & doesn’t flow under pressure) (New rule: frozen liquid manure does not qualify as dry manure)
Liquid manure from confinement operations using formed storage with less than 500 animal units (1,250 hogs weighing more than 55 lbs. or 10,000 pigs weighing less than 55 lbs.)
Liquid manure injected or incorporated on the same date of application
MANURE APPLICATION Frozen or snow covered ground
No surface application of liquid manure from a confinement operation on
Snow covered ground from Dec. 21 to Ap. 1
Frozen ground from Feb. 1 to April 1
except in an emergency
Frozen ground
Impermeable to soil moisture
Does not include ground frozen only in top 2” or less
Snow covered ground
At least 1” of snow or ½” of ice
MANURE APPLICATION Frozen or snow covered ground
An emergency is when there is an
immediate need to apply manure due to
unforeseen circumstances beyond the
producer’s control
Includes, but is not limited to:
natural disaster
unusual weather conditions, or
equipment or structural failure
MANURE APPLICATION Frozen or snow covered ground
To apply liquid manure on frozen or snow covered ground due to an emergency, a producer must: Telephone DNR field office before application -
New rule: caller must give: Owner’s name & facility ID No. Reason for emergency app. & app. Date Estimate of gallons to be applied & fields in
MMP to be applied on Apply the manure on land identified in the MMP
– either in the original MMP or the next updated MMP submitted to DNR after the manure is applied
Apply the manure on land with a P Index 2 or less
MANURE APPLICATION Frozen or snow covered ground
To apply liquid manure on frozen or snow covered ground due to an emergency, a producer must: During manure application and for 2 weeks
after, block any surface tile intake on land in the MMP & down grade
Properly manage the manure storage structure – New rule: beginning Dec. 21, 2015, must have storage to avoid application from Dec. 21 to April 1 – before then, can still use emer. app. procedures even though not enough storage
For structures built after July 1, 2009, have at least 180 days of storage
MANURE APPLICATION Frozen or snow covered ground
Other considerations: Does it comply with EQIP requirements? Will it impact federal NPDES permit
requirements? If the operation has a master matrix and
took points for injection or incorporation of manure (item 26(e)), to surface apply because of an emergency producer must obtain written approval for a waiver from a DNR field office
Contact DNR as soon as possible for assistance, even if not required by law
Community and neighbor relations
MANURE APPLICATION Restrictions on manure on soybeans
EPC rule effective May 14, 2008:
100# N/acre limit on land in an MMP to be planted to soybeans
100# N/acre limit “does not apply on or after June 1 of each year” – regular limit of 3.8# N/bu of soybean yield applies
Complete ban on May 14, 2013 if EPC reviews available scientific information and publishes notice that a complete ban will be put in place
STOCKPILING DRY MANURE
Four different categories of regulation depending on type of livestock operation Dry Animal Nutrient Product –regulated by
Iowa Department of Agriculture Open feedlot operations – 2006 legislation Confinement operations – 2009 legislation -
deep bedded cattle and hog barns Confinement operations – 2009 legislation -
other than deep bedded cattle & hog barns Federal EPA & DNR rules: CAFO’s cannot
discharge manure from production areas unless the discharge is pursuant to an NPDES permit. Definition of production area includes stockpiles
STOCKPILING DRY MANURE Dry bedded confinements– 2009 legislation
Dry bedded confinement cattle and hog barns Stockpiling:
At least 1,250 feet from a residence (other than barn owner’s), business, church, school or public use area unless waiver is granted or the manure is from a SAFO (less than 500 animal units)
At least 400 feet from a designated area or 800 feet from a high-quality water resource
At least 200 feet from a surface tile inlet unless steps taken to ensure runoff won’t reach tile inlet
Not in a grass waterway, where water pools, or where water will enter the stockpile
Not on more than 3% slopes unless measures to contain runoff are implemented
Must remove and land apply manure within 6 months.
STOCKPILING DRY MANURE Dry bedded confinements– 2009 legislation
If the stockpile is on Karst terrain or an alluvial aquifer area (both of these areas are marked on maps from DNR) the stockpile must have a concrete floor and any underlying soluble rock, sand or gravel must be at least 5 feet below the surface
Dry bedded manure: dry manure with “crop, vegetation, or forage residue or similar materials” used for the care of livestock
In addition to stockpiling, this legislation also establishes other beneficial requirements such as a 200 ft. separation distance from deep bedded confinements barns to watersources (creeks, etc.) instead of the 500 ft. distance for other confinement barns
DRY ANIMAL NUTRIENT PRODUCT
Must register with Iowa Dept. of Ag., list % of N,P, K & sell through an independent distributor
Also must file an MMP statement with DNR Stockpiling:
Not in a grassed waterway Not on greater than soil survey class B slopes Not within:
200 ft. of shallow private water supply or 100 ft. of deep well
500 ft. of a surface intake, wellhead or cistern of ag drainage well, known sinkhole or major water source (rivers)
200 ft. of creeks, streams, etc.
STOCKPILING DRY MANURE Open feedlot operations – 2006 Iowa legislation
Stockpile - store solids outside of a feedlot or structure or area that drains to a feedlot or structure
Stockpiling: At least 400 feet from a designated area or 800
feet from a high-quality water resource At least 200 feet from a surface tile inlet unless
steps taken to ensure runoff will not reach the tile inlet
Not in a grass waterway or where water pools Not on more than 3% slopes unless measures
to contain runoff are implemented Must remove and land apply solids within 6
months.
RECENT DNR RULE CHANGE Appeals of construction permits to EPC
Went into effect March 17, 2010 Changes to current rules include:
County will continue to have 14 days to file appeal but 30 days to file all documentation (will extend appeal period by 14 days)
EPC will have authority to designate experts (at least 7 days before hearing) to give testimony at the hearing – parties may ask them questions
All appeal materials, including the complete DNR file on the permit application, will be on the DNR website beginning no later than 5 days after county files demand for hearing
Any person may submit written material up to 15 days before the hearing and the material will be considered for inclusion in the appeal record by the chair of the EPC
OPEN BURNING
DNR rules prohibit open burning of combustible materials unless: DNR grants a variance Exemptions include:
Trees and tree trimmings & landscape waste Recreational fires Residential waste Paper or plastic pesticide containers and seed
corn bags. Must be ¼ mile someone else’s building, livestock area, wildlife area or water source. Cannot exceed one day’s accumulation or 50 pounds. If causes a nuisance, DNR may order relocation of burning.
Effect of rule: Burn barrels at livestock buildings are prohibited.
DNR ENFORCEMENT
Environmental self audits
Initiated by business owner to determine environmental compliance
Benefits:
Immunity from penalties if a violation discovered during audit and promptly reported to DNR, before DNR investigates
Confidentiality of audit report
No immunity from penalties if:
DNR not properly notified
Violations are intentional or result in injury to persons, property or environment
Substantial economic benefit giving violator a clear economic advantage over competitors
AG NUISANCE CASES
Iowa
No cases went to trial in 2009 or 2010 and none scheduled for 2010
6 Currently Pending in Iowa District Courts
Swine
Story County 3,300 head finisher
Plymouth County 2,000 head finisher
Tama County 1,200 head finisher
Marshall County 2,400 head finisher
Poultry - Buena Vista County egg oper.
Dairy - Woodbury County 4,000 cows
NUISANCE
Steps to help to avoid lawsuit
Location
Separation distance
Prevailing winds
Tree buffers
Existing trees
Fast growing trees planted with slower growing species
Biofilters
Clean pigs and buildings
Manure treatments and additives
Timing of manure agitation and application
NUISANCE
Protection for producer
Insurance Standard farm liability policies
normally don’t cover – but producer should always check with the insurance company and/or an attorney
Environmental policies available Coverage for claims and costs of
defense
MANURE EASEMENTS
Iowa Court of Appeals
Crop farmer sold site for hog buildings to be
built – receive manure
Deed reserved right to all manure, but manure
easements stated hog producers were not
obligated to provide manure
Hog buildings sold – new owner - manure to
different farmer - farmer who sold site sued
Court ruled deed restriction not legally binding
& that manure easements controlled – farmer
who sold site not entitled manure