environmental monitoring report · rice field or water body nearby the embankment of the railway,...
TRANSCRIPT
![Page 1: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/1.jpg)
Environmental Monitoring Report
Monthly Report February 2014
GMS: Rehabilitation of Railway in Cambodia
Prepared by Nippon Koei in association with JARTS, for the Ministry of Public Works and Transport, the Kingdom of Cambodia, and the Asian Development Bank.
![Page 2: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/2.jpg)
CURRENCY EQUIVALENTS (as of 1 March 2014)
Currency unit – riel (KR) KR1.00 = $0.000251
$1.00 = KR3,980
ABBREVIATIONS
NOTE
In this report, "$" refers to US dollars unless otherwise stated.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
ADB – Asian Development BankCSC – construction supervision consultantEMP – environmental management planGMS – Greater Mekong Subregion
IEE – initial environmental examinationMPWT – Ministry of Public Works and Transport
NR – national roadPIU – project implementation unit
PPE – personal protective equipmentRRL – railroad line
![Page 3: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/3.jpg)
KINGDOM OF CAMBODIA
MINISTRY OF PUBLIC WORKS AND TRANSPORT
RAILWAY REHABILITATION MANAGEMENT OFFICE
ADB LOAN NO 2288-CAM [SF], OFID P1125
ADB LOAN NO 2602, AUSAID GO187
GMS: REHABILITATION OF RAILWAY IN CAMBODIA
ENVIRONMENTAL MONITORING REPORT No. 29
February 2014
NIPPON KOEI CO., LTD.
In association with JARTS
![Page 4: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/4.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 1
Table of Content
Page
1. General Background .......................................................................................................................... 2
1.1 Project overall .................................................................................................................................. 2
1.2 Project progress .............................................................................................................................. 2
1.3 Purpose of the report ..................................................................................................................... 2
2. Environmental Monitoring Program ................................................................................................ 3
2.1 Scope of works ................................................................................................................................ 3
2.2 Methodology .................................................................................................................................... 3
3. Results of Environmental Monitoring .............................................................................................. 4
3.1 Reviewing on Environmental Report of TSO, SINOHYDRO ...................................................... 4
3.1.1 Summary of Contractor’s Environmental Report ................................................................ 4
3.2 Field monitoring by CSC/Local Environmental Specialist .......................................................... 4
3.2.1 Southern Line ........................................................................................................................... 4
3.2.2 Northern Line ........................................................................................................................... 9
4. Summary and recommendations ..................................................................................................... 9
4.1 Summary .......................................................................................................................................... 9
4.2 Recommendations ........................................................................................................................ 10
List of Annex
ANNEX 1: Environmental Monitoring Matrix ............................................................................................ 11
ANNEX 2: Status of EMP Compliance ........................................................................................................ 14
![Page 5: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/5.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 2
1. General Background
1.1 Project overall
The GMS Rehabilitation of the Railway in Cambodia (RRC) involves two lines, Southern
Line and Northern Line. Southern Line connected from Phnom Penh to Sihanoukville with
total length of 265 km, and Northern Line connected from Phnom Penh to Poipet (Thai
border) with total length of 386 km.
The project is under management of Ministry of Public Works and Transport (MPWT). The
design and construction supervision consultant is NIPPON KOEI CO., LTD in association
with JARTS. The construction contractor for RRL1 (Southern Line) and RRL2 (Northern
Line) is TSO-AS & NAWARAT Joint Venture (France and Thailand), but for RRL1, JV
partners were changed to TSO-SPCC Consortium since October 21, 2011).
1.2 Project progress
The project activities include design, platform improvement, bottom ballast relay, sleeper
and track relay, sleeper tamping, top ballast relay, welding (for Southern Line), and
rehabilitation/reconstruction some culverts in both lines, rehabilitation of bridge in SL, and
reconstruction of drainage system in Sihanoukville Station.
Site observation for SL in this month indicated that all work activities including maintenance
works was completed on 25 January, 2014 as well. However, base course activities have
been constructing at Sihanoukville Container Terminal inside Sihanoukville Port.
The specific work outputs for this period are presented as follows:
RRL-1: Rehabilitation of Southern Line, the track from Bifurcation to Sihanoukville Port was
connected. From June 2013, most of the civil works were substantially completed. Taking
over certificate as of 15 July 2013 was issued on 10 August 2013.
ICB3-W3: Welding of P43 rails on SL: The works under the original scopes and integrated
rail management under Variation Order No 3 were totally completed.
ICB3-W17: Construction of Sihanoukville Container Terminal is on-going. The actually site
works was fully started in August 2013. The works in February 2014 are mostly
embankment, and production of interlocking concrete blocks (ICB) near the construction site
within the Port of Sihanoukville. To the end of February 2014, the work progress achieved
progress was only 20% and the accumulated progress to the end of February 2014 was
approximately 35%.
1.3 Purpose of the report
As full implementation of the IEE procedure of the project, the Environmental Specialists of
Construction Supervision Consultant (CSC) have two main roles as following:
- Supervise the monitoring of implementing mitigation measure of the contractor
during the construction stage; and
- Submission of the Environmental Monitoring Report (EMR) to MPWT-PIU and ADB.
![Page 6: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/6.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 3
The environmental monitoring report is to follow up the contractor’s implementation on
environmental mitigation measure in construction stage as stated in EMP and other
environmental safeguards in construction contract documents. Guidance and instruction will
be prepared to enforce the contractor to follow the environmental mitigation measure as
stated in IEE report and construction contract documents.
2. Environmental Monitoring Program
2.1 Scope of works
The major tasks for the environmental monitoring in construction stage include:
Field monitoring on contractor’s environmental mitigation measure performance
in both project lines (Northern and Southern lines);
Guidance to Contractor’s personnel on environmental monitoring aspect, in the
field practice;
Recommend to TSO, SINOHYDRO to implement all EMP as stated in IEE report
and other environmental safeguards in construction contract documents; and
Instruct TSO/SPCC, SINOHYDRO to take an action to mitigate or rectify on
other issues that find out.
2.2 Methodology
At this stage, mainly site observations are conducted for monitoring the implementation of
environmental mitigation measures:
Site monitoring: Use environmental monitoring matrix, borrow pit matrix, hearing
(directly ask the question to the project workers and people living nearby the
project sites), and visual: During the field observation on environmental
mitigation measure that implemented or rectified by contractor (TSO/SPCC and
SINOHYDRO), the CSC/Environmental Specialist used the environmental
monitoring matrix for construction phase (Annex1). Visual and hearing
methodology also has been applied for other environmental monitoring items,
and degree of impact have be recorded and photograph to proof the impacts
(good or bad) are used.
![Page 7: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/7.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 4
3. Results of Environmental Monitoring
3.1 Reviewing on Environmental Report of TSO, SINOHYDRO
Referring to the specification was reported that the contractors must prepare the monthly
progress report for submission to CSC/Local Environmental Specialist for reviewing and
taken action to minimize reverse environment, whereas contractors did not prepare this
report.
3.1.1 Summary of Contractor’s Environmental Report
For this month there is no Environmental reports has sent by the contractors (TSO, SINOHYDRO), although we have suggested them to include the environmental issues in their monthly progress report based on the contraction.
During that time, the maintenance activities of TSO/SPCC was completed on 25 January,
2014, while embankment work activities at Sihanoukville Container Terminal is completed
and on-going sub-base and base course construction activities.
3.2 Field monitoring by CSC/Local Environmental Specialist
The task work includes follow up on the environmental issues and monitoring on
environmental activities of the contractors (TSO/Sinohydro) in both project lines (SL and
NL), and investigation on other environmental items that had been occurred by the project
construction activities.
The field observation was conducted on 2-3 March, 2014 at Southern Line for ICB3-W17:
Construction of Sihanoukville Container Terminal, while the other line at the Northern Line is
not activity, and TSO stopped all the activities and moved all project’s equipment from the
site since 21 July 2012.
The environmental issues and environmental mitigation measure were described in
following paragraph, and the field recorded is included environmental compliance (the detail
in Annex 2).
3.2.1 Southern Line
Site observation was carried out at the Southern Line, since it is located in the Port
Authority of Sihanoukville (PAS) for ICB3-W17: Construction of Sihanoukville Container
Terminal, at there, sub-base and base course construction activities was done. The results
of environmental condition can be described in following:
1. Leaks and spills of hazardous material: Improper oil/fuel container storage at
Sihanoukville for ICB3-W17: Construction of Sihanoukville Container Terminal (photo
1), the contractor (SINOHYDRO) should have provided a suitable tank. At the
workshops and storage area of Sihanoukville Container Terminal construction was
observed that (i) improper oil/fuel drum storage, (ii) insufficient housekeeping.
![Page 8: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/8.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 5
Photo 1 : leakage of lubricant oil at SHV Photo 2 : Construction material storage at SHV
2. Soil erosion: In generally no sign of soil erosion for Southern Line during the site
monitoring in this month, due to the site activities was finished for operation phase at
the end of January 2014 from Kampot to Sihanouk stations and most of the
embankment are covered by vegetation that naturally grew and grass planted by
contractor since July and August 2012. On the other hand, at the site construction of
Sihanoukville Container Terminal, it is accelerated works base course activity due to
this month is the dry season. Therefore, this area the soil erosion may be not occurred
at the place.
Photo 3 : At Takeo Station Photo 4: Base course activity at ICB3-W17
3. Borrow pits/quarries: By February 2014, it is observed that no all borrow pits activities
were used as construction materials for Southern Line project.
4. Water quality: During field observation there was not signed of water laden into the
rice field or water body nearby the embankment of the railway, due to the
implementation phase was completed. At construction of Sihanoukville Container
Terminal, top of sub grade activity is also nearly complete for ICB3-W17.
5. Air pollution: Based on the field observation can be noted that no dust and emission
air from any polluted sources.
![Page 9: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/9.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 6
6. Noise disturbance: Noise and vibration come from the construction machineries at
inter locking concrete block maker is loudly outside to the residential area; however,
earplug protection were provided to workers who are working at the place.
Furthermore, base course still have been done at Sihanoukville Container Terminal
and at daytime only, photos 5 & 6.
Photo 5 & 6: SINOHYDRO’s workers worked at inter locking concrete were provided ear plug
7. Waste management: The workshops and storage areas in Kampot station have been
cleaned. The platform space in Sihanoukville is well cleaned after removing of the
workers camps.
However, the solid waste management at Sihanoukville Container Terminal is still poor
managed and strewed on the space around the site photo 7 & 8.
Photo 7& 8: Poor waste management at SHV ContainerTerminal
Photo 9 & 10: Workshop in Sihanoukville (ICB3-W17)
![Page 10: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/10.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 7
8. Liquid waste generation/Drainage: In generally no sign of liquid waste generation
from the project during the site monitoring in this month, most of the work activities
were completed at Kampot and sihanoukville stations due to the maintenance stage
were completed at all.
For ICB3-W17 at Sihanoukville, however; no bathroom and toilet facility, the workers
are always bathing or excreting at improperly place in the open space in the
construction site (photos 11&12). Therefore contractor should have provided properly
bathroom/toilet facility at there.
Photo 11: Temporarily bathroom at SHV for
construction workers
Photo 12: No toilet at SHV, workers always go
to excreting here.
9. Traffic problem: During the field observation, the monitoring team did not see any
traffic congestion as well as accident that caused by the project activities.
10. Damage road and bridge: Damaged culvert or bridge was not found on date of field
environmental monitoring.
11. Adequacy of facilities/equipment for workers: SINOHYDRO’s workers/staffs that are
working at Sihanoukville Container Terminal were provided this kind of PPE to all
workers/staffs (photo 13&14).
Photo 13&14: SINOHYDRO’s workers were provided PPE at all
12. Safety: Generally, the workshops and storage places have been equipped with
extinguisher capacity of 8kg (at least 2 bottles), but in the workshops and storage
![Page 11: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/11.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 8
places of Construction for Sihanoukville Container Terminal have not equipped with
extinguisher, however; first aid kits were provided insufficiently (photo 15), according
site observation and question to the leader of group worker.
SINOHYDRO’s workers whom are working at inter locking concrete were provided ear
plug for prevention the noise disturbance from their machinery at the place.
Photo 15: First aid kits were provided
(ICB3-W17) Photo 16: Water bottle were provided at
construction site (ICB3-W17)
Photo 17: Base course activities at SHV
(ICB3-W17) Photo 18: Inter locking concrete activities
at SHV (ICB3-W17)
Basically, the certificate of mines/UXOs clearance completion and the mine/UXOs
clearance completion must be submitted the report to the project director of GMS:
Rehabilitation of Railway in Cambodia before the project implementation, which stated
that mines/UXOs had been removed and destructed with no accident encountered.
Unfortunately at SHV Container Terminal subproject there are two suspected
unexpected Ordnances in excavation activity on 8th November 2013 at the site work,
but these issues were resolved already.
13. Construction-related complaint: No any complains by letter/verbal from villagers/Local
authorities had been occurred during this observation.
14. Other issues: During this month no any issues has happened.
SINOHYDRO CORPORATION LIMITED’s representative has promised with
CSC/Environmental Specialist that they will provide PPE at all to the workers who are
working at inter locking concrete block maker. On the other hand, first aid kits were
![Page 12: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/12.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 9
provided, but insufficient medical equipment, and equipped with extinguisher will be
install if possible.
3.2.2 Northern Line
No activity in the Northern Line, TSO stopped all the activities and moved all project’s
equipment from the site since 21 July 2012. The environmental condition is same as
September 2012.
4. Summary and recommendations
4.1 Summary
The result on environmental monitoring in February 2014 can be concluded as following:
(1) During that time, it is also observed, the project has no significant impacts on the
environment and people as well. The implementation of the above mitigation
measures reduces the occurrence of the following negative impacts: damage to
existing structures, dust generation control, generation of wastes, safety and
health, traffic congestion, while the generation of employment is enhanced.
(2) No sign of soil erosion during the site monitoring during this month.
(3) No sign of water laden into the rice field or water body nearby the embankment of
the railway.
(4) At Container Terminal construction site are poor managed of solid waste, because
no garbage bin had been provided.
(5) There is not traffic problem during site monitoring.
(6) Workers/staffs of SINOHYDRO were equipped with PPE at all, e.g. workers whom
are working at inter locking concrete at SHV Container Terminal such as ear plug,
gloves and mask see the above photos.
(7) CSC had coordinated with SINOHYDRO’s staffs to deal with environmental issues
that occurred during the implementation stage.
![Page 13: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/13.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 10
4.2 Recommendations
As requirement of the EMP in IEE report and missing environmental mitigation measure or environmental improvement of Contractors during construction stage as well as the comments from ADB on EMR, the CSC’s environmental specialist recommends in following points:
1. Contractor must daily control scheduling of construction activities such inter locking
concrete at SHV Container Terminal to avoid any noise and vibration to villagers who living around the project area, doing locking concrete should only be done in day time;
2. Contractor must provide immediately eye glass, and musk to workers/teams are working with interlocking concrete block maker regulator machine as well as the workers whom are working around the machinery;
3. Contractor must immediately provide adequate/sufficient PPEs/safety tools to all project workers/staffs in appropriated working place/type, and ensure all the workers are properly use PPEs during working time. The workers no wearing properly PPE are not allowed to work in construction site;
4. Contractor must immediately provide adequate first aid kits to construction site;
5. Contractor must immediately inform any risks of mines or UXO are necessary during earthwork and do good cooperation with local de-mining authority CMAC or other local de-mining agency to deal on this issue;
6. Proper storage of toxic materials like fuel and oil;
7. Regular collection and disposal of spoils and excavated materials to designated location to avoid sedimentation/siltation of nearby water bodies;
8. Contractor should have provided/equipped with extinguisher capacity of 8kg (at least 2 bottles) to each construction sites.
![Page 14: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/14.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 11
ANNEX 1:
Environmental Monitoring Matrix
![Page 15: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/15.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 12
Project name: GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA Environmental Monitoring Matrix (Construction Phase) Location: Kampot Station and Sihanoukville Container Terminal Inspection Date: 3-4 March 2014 (for February, 2014) Name of Inspector: Bun San
No. Description Impact Location Extent1 Mitigation Measures Degree
2 Remarks
3
1 Hazardous wastes generation; possible leakage and spillage of hazardous material
Fuel storage area; Construction site of SHV Container Terminal (Workshop & Storage material)
N
Storage area is sited away from watercourse, drains 4
Storage area has concrete floor, bund/dike, wall; pallets are used 1
Hazardous wastes handling and management training 2
Safety signal, posters 2
Cleanup equipment and procedure are in place 3
Key person in charge 3
2 Soil erosion Construction sites; Earthwork area
Slope design
Embankment at the site of SHV container terminal.
Compaction
re-vegetation
3 Borrow pit/quarry hazards Borrow pit/quarry areas (see separate matrix for all pits)
Slope
No need construction material from borrow pit at RRL1.
Depth (m)
Perimeter fences
Warning signs
4 Water quality; sedimentation
Project site
N
Dust-generating activities away from waterways 4
Drain discharges have low (suspended) solid 4
5 Water quality: floating wastes
Project site N
Proper waste disposal 2
Waste management training 2
Cleanup 2
6 Air quality: dust generation Project site; Access road; Community N
Water spray 4
Covers on transport materials, storage area 3
Mask for workers 2
7 Noise Project site
M
Ear muffs for workers 1
Insulation/muffler for noisy equipment 2
Noisy activities at daytime only 2
8 Solid waste generation Project site; Workshop
N
Solid waste management training for workers 2 Garbage bins are in place 1
![Page 16: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/16.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 13
No. Description Impact Location Extent1 Mitigation Measures Degree
2 Remarks
3
Disposal site/method identified 3
Signage, posters 2
Key person assigned 3
9 Liquid waste generation Project site; Worker camp
Liquid waste management training for workers
Workers camps were moved away due to the project completion.
Sanitary toilets for workers
Functional drainage canals
Signage, posters
Key person assigned
10 Traffic problems Access road; Level crossing
N
Signage, directions 4
Traffic barrier 4
Traffic management plan 4
11 Damage to roads, culverts, bridges
Roads; culvert; bridge
Proper planning/preparation
Immediate repair of damaged structures
12 Adequacy of facilities/equipment for workers
Project site
N
Potable water supply 2 No toilet facility at SHV Container Terminal construction site Washing/bathing water supply 2
Sanitary toilets 1
Comfortable sleep/rest quarters 2
13 Safety issues Project site
N
Information/training 3 First aid kits, and equipped with extinguisher capacity of 8kg were not equipped at the site Signage, posters 2
Safety tools for workers 4
First aid kits 2
14 Possible conflict with communities and complaints from residents
Project site; workshop
N
Coordination with communities/leaders 3
Key person assigned 3
Documentation and resolution of complaints 3
Note: 1 - Describes the magnitude of impact: write N-nominal/minimal; M- moderate; E- extensive
2 - Describes the quality of mitigating measure: write 5- excellence; 4- very good; 3- good; 2- poor; 1- very poor
3 - Provide specifics/details on problem identified (e.g., exact location, specific concern, etc.), additional necessary mitigation measures and
corresponding target date of implementation, and other observations.
![Page 17: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/17.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 14
ANNEX 2:
Status of EMP Compliance
![Page 18: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/18.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 15
Status of EMP Compliance (Construction phase)
Project Activity Potential Environmental
Impacts Proposed Mitigation Measures Status of Compliance
Embankments,
site clearing,
piling works, and
construction
wastes to spoil
sites
1. Dust generation
The Contractor will be required to formulate and implement a Dust Abatement Program that includes spraying of water on roads and work areas within villages close to the road in the coming dry season.
Vehicles transporting materials should be covered with tarpaulin or similar material
Regular sprinkling of water is being done.
Base course as potential source of dust and noise is far from the project area.
2.Noise and vibration
The Contractor should consider proper scheduling of construction activities particularly in sensitive areas. Acoustic barriers or enclosures for working areas should be provided
No complaints from the people have been received so far as proper scheduling of works is being done.
![Page 19: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/19.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 16
Project Activity Potential Environmental
Impacts Proposed Mitigation Measures Status of Compliance
3. Water contamination
Waste/used oil should be collected, properly stored and disposed to an approved site (according to national standard). Storage should be in drums raised off the ground and properly covered to keep rain water out. Lining or pan should be provided to contain any spills and simplify clean up.
The Contractor shall prepare a Spill Management Plan (including measures to be taken and equipment to be used) to ensure adequate cleanup of any spills
The contractors were also advised to improve oil/fuel storage facilities.
4. Loss of agricultural
land for borrow pits The contractor will use only licensed borrow
operators. There will be no side borrow permitted, unless agreed to with roadside residents.
Being complied.
5.Generation of wastes
Sufficient garbage containers should be provided in construction camps and work sites
Employ regular disposal of waste in an approved landfill or site at SHV Container Terminal
Maintain cleanliness/orderliness at workshop and work sites
Poor waste management at construction site in SHV port for ICB3-W17.
6. Safety and Health The Contractor should formulate and implement a
Health and Safety Plan to protect both the public and the workers. A trained first aid personnel and health facility should be provided on site.
Provide potable water and sanitary facilities to workers
Install warning signs like “safety first” at the
PPE should be provided to workers at all
Facilities such as toilet, bathroom, first aid kits, and potable water are provided to workers.
![Page 20: Environmental Monitoring Report · rice field or water body nearby the embankment of the railway, due to the implementation phase was completed. At construction of Sihanoukville Container](https://reader034.vdocuments.mx/reader034/viewer/2022042020/5e77bdd8992a59143c0ea755/html5/thumbnails/20.jpg)
GMS: REHABILITATION OF THE RAILWAY IN CAMBODIA ADB LOAN NO. 2288-CAM, OFID P1125, ADB LOAN NO. 2602, AUSAID G0187 Nippon Koei in association with JARTS
Environmental Monitoring Report 28, February 2014 Page 17
Project Activity Potential Environmental
Impacts Proposed Mitigation Measures Status of Compliance
construction area
Provide Protective Personal Equipment (PPE) to workers e.g. safety shoes, hardhats, earplugs, etc.
7. Risk of land mine or
UXO Consultative meetings with local communities are
necessary to know clearly where there are risks of mines or UXO.
Guidelines have been issues and contractors are proceeding with necessary screening.
Taken into account – The demining group investigated the presence of UXOs
UXOs found at SHV Container Terminal site were removed as an emergency measure. The contractor sent the team back to the area. This should be done and a Clearance Certificate will be issued upon completion.