environmental monitoring report loan 2671 & grant 0218 … · loan 2671 & grant 0218-kgz:...

45
Environmental Monitoring Report Semiannual Report July ─ December 2016 Loan 2671 & Grant 0218-KGZ: Power Sector Improvement Project Prepared by OJSC National Electric Grid of Kyrgyzstan for the Kyrgyz Republic and the Asian Development Bank. This Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In Preparing any country program or strategy, financing any project or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development bank does not intend to make any judgments as to the legal or other status of any territory or area.

Upload: doanhanh

Post on 05-Jun-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

Environmental Monitoring Report Semiannual Report July ─ December 2016

Loan 2671 & Grant 0218-KGZ:

Power Sector Improvement Project

Prepared by OJSC National Electric Grid of Kyrgyzstan for the Kyrgyz Republic and the Asian Development Bank. This Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In Preparing any country program or strategy, financing any project or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development bank does not intend to make any judgments as to the legal or other status of any territory or area.

2

Table of Content Abbreviations ............................................................................................................................ 3

I. INTRODUCTION .............................................................................................................. 4

1.1. Project Information ........................................................................................................ 4

1.1.1. Goal of the Project ...................................................................................................... 4

1.1.2. Project description ..................................................................................................... 4

Upgrading of substations ......................................................................................................... 4

Construction of communications and supervisory control and data acquisition system ... 4

1.1.3. Project implementation area ...................................................................................... 5

1.1.4. Construction activities and project progress during the previous 6 months......... 6

1.2. Changes in project organization and environmental management team ................... 9

Project Organizational Structure ............................................................................................. 9

II. ENVIRONMENTAL MONITORING ................................................................................ 10

III. ENVIRONMENTAL MANAGEMENT ............................................................................. 11

3.1. The environmental management system (EMS), site-specific environmental management plan (SSEMP), and work plans ........................................................................ 11

3.2. On-Site Inspections and Audits .................................................................................. 12

3.2.1. Implementation of environmental safeguards requirements and management of oil-filled equipment and PCBs ............................................................................................... 13

3.2.2. Management of SF6 Equipment ............................................................................... 16

3.2.3. Management of Waste .............................................................................................. 25

Management of oils and equipment not contaminated with PCBs...................................... 25

3.2.4. Management of non-toxic waste .............................................................................. 25

3.3. Non-compliance Notices.............................................................................................. 25

3.3. Grievance Redress Mechanism ................................................................................... 25

3.4. Information Support and awareness activities .......................................................... 26

3.5. Corrective Action Plan ................................................................................................. 26

Appendix 1. List of participants of hands-on training, 27.07.2016, ..................................... 28

Appendix 2. Template of the Minutes of equipment testing for PCBs ................................ 29

Appendix 3. Letter to SAEPF on testing results (translation and original) ......................... 30

Appendix 4. Minutes of testing of transformer oil for PCBs at substation Glavnaya, 3 phases of current transformer, 3 minutes (example) ........................................................... 32

Appendix 5. Example of testing results of transformer oil stored in memory of express analyzer and printed out ........................................................................................................ 35

Appendix 6. Acts of technical inspection for machinery/equipment at ChEHVN, NEHVN, TEHVN, JAEHVN ..................................................................................................................... 36

Appendix 7. Permit for emissions of pollutants into ambient air and placement of waste in environment ........................................................................................................................ 39

Appendix 8. Complaints log book for recording of citizens’ complaints and appeals ...... 45

3

Abbreviations

ADB Asian Development Bank

AMDA automated metering & data acquisition system

BA-EMR Bi-annual environmental monitoring report

CAPS Central Asian Power System

ChEHVN Chui enterprise of high-voltage networks

EHVN enterprise of high-voltage networks

EMP environmental management plan

FOCL fiber optic communication line

IEE Initial environmental examination

JAEHVN Jalal-Abad enterprise of high-voltage networks

KR Kyrgyz Republic

NEGK National Electric Grid of Kyrgyzstan

NEHK National Energy Holding of Kyrgyzstan

NEHVN Naryn enterprise of high-voltage networks

OJSC open type joint stock company

PCBs polychlorinated biphenyls

PIU project implementation unit

SAEPF State Agency for Environmental Protection and Forestry under the

Government of the Kyrgyz Republic

SCIEM State Committee for Industry, Energy, and Mining of the Kyrgyz Republic

SCADA supervisory control and data acquisition system

S-S substation

SSEMP site specific environmental management plan

TEHVN Talas enterprise of high-voltage networks

4

I. INTRODUCTION

1. This sixth bi-annual report on environmental monitoring, which covers the period of 1 July to

31 December 2016 for the Power Sector Improvement Project, was prepared in accordance

with requirements of Initial Environmental examination (IEE) developed in 2014, and approved

by ADB. IEE received a positive conclusion from the State Environmental Expertise Unit of

SAEPF on 08.07.2014 (No. 04-01-28/205).

2. The objective of this semiannual report on environmental monitoring is a follow-up of the

project activity for compliance with the requirements of the EMP.

3. According to Safeguard Policy Statement of ADB (SPS, 2009), the Project is classified as category B. Its potential adverse environmental impacts are site-specific, temporary and can be relevantly mitigated as specified in EMP/SSEMP.

1.1. Project Information 1.1.1. Goal of the Project 4. The major goals of the projects are following:

(i) To advance transparency and accountability of commercial transactions in the power

sector through establishment of the automated metering and data acquisition

system;

(ii) To improve overall efficiency and reliability of Kyrgyz power supply system through

rehabilitation and upgrading of substations, and communications system.

1.1.2. Project description

5. The project aims at: (i) upgrading of substations; and (ii) establishment of Supervisory Control and Data Acquisition System (SCADA) to manage the system of energy equipment.

Upgrading of substations

6. Upgrading of substations through replacing dilapidated circuit breakers and instrument

transformers that have reached their economic lives, are technologically obsolete, or do not

meet the accuracy requirement for regional power trade will improve the reliability of the system.

7. NEGK is implementing Upgrading of Substations, whereas in the field it is implemented by

enterprises of high-voltage networks.

Construction of communications and supervisory control and data acquisition system 8. Establishment of Supervisory Control and Data Acquisition System (SCADA) will connect

seven major substations and the control centers via optical fiber. The system will allow

improving overall efficiency and reliability of Kyrgyz power supply system and the CAPS.

9. The Northern fiber optic communication line (FOCL) will be installed under Lot 2 of the project

for connecting several substations and facilities in Bishkek city, and laying fiber optic cable in

Bishkek city.

5

10. According to the scope of work, FOCL (fiber optic communication line) will be installed for

hanging on supports of transmission lines with a total length of 330 km in the following

transmission lines:

i. 220 kV Glavnaya – Chuiskaya (59.9 km);

ii. 220 kV Frunzenskaya – Kara Balta (63.2 km) iii. 220 kV Kara Balta - Glavnaya (90.5 km);

iv. 220 kV Chuiskaya – Bystrovka (39.4 km);

v. 220 kV Bystrovka – Ala-Archa (93.4 km);

vi. 220 kV Ala-Archa – Frunzenskaya (108.8 km);

vii. 110 kV Glavnaya – Karagachovaya (8.3 km);

viii. 110 kW Power and District Heating Plant (PDHP) Bishkek – Parkovaya (11.8 km);

ix. 110 kV Parkovaya – Ala-Archa (7.8 km).

11. Laying of 16.2 km optical power ground wire in Bishkek city is carried out to connect the

central control office (CCO) of NEGK to the main fiber-optic system. The following sections will

be connected to the new telecommunication system by optical power ground wire (OPGW):

ii. PDHP Bishkek – CCO/NEGK (6.2 km);

iii. PDHP Bishkek – ChuPVES (Chui Enterprise of High-Voltage Networks) (4 km);

iv. SS Karagachevaya – CCO/NEGK (6 km)

12. The Contractor for implementation of this second component, AK-AY ELEKTRIK DIS TICARET KOLLEKTIF SIRKETI, was recruited in July 2015. 1.1.3. Project implementation area 13. The project will be implemented at 107 substations in Chui, Issyk-Kul, Talas, Naryn, Osh

and Jalal-Abad oblasts. Out of 107 substations, at 54 substations oil-filled equipment (oil

switches, current and voltage transformers) will be replaced. Location of area for the

implementation of Lot 1 is shown in Figure 1, for Lot 2 – see Figure 2.

Figure 1. Power Sector Improvement Project implementation area for Lot 1 “Upgrading of Substations”

Scheme of the Main Electric Grid of the Kyrgyz Republic

6

Figure 2. Project implementation area for Lot 2 “Laying of fiber-optic communication line (SCADA) in Chui region”

1.1.4. Construction activities and project progress during the previous 6 months 14. The contractor is actively working according to the Project implementation Plan and construction activity for the last six months from July to December 2016 includes the following (Table 1): Table 1. Project progress in July-December of 2016

№ Period Project Components and Activities

1 July 2016 Upgrading of substations:

• Preparations for testing of transformer oils by express analyzers (trainings were conducted)

Construction of communications and SCADA system:

• Laying out of optical fiber cable (17 km of Glavnaya – Chuiskaya 220 KV line)

2 August 2016 Upgrading of substations:

• Testing of transformer oil for PCBs at sub-stations -121 items of equipment at 12 sub-stations;

• replacing of oil-filled equipment – 21 items

• building of site for temporary storage of equipment not contaminated with PCBs – 4 sites, Glavnaya, Chuiskaya, Frunzenskaya, Kara-Balta, TEHVN;

Construction of communications and SCADA system:

• Laying out of optical fiber cable (42,9 km of Glavnaya – Chuiskaya 220 KV line)

3 September 2016

Upgrading of substations:

• Testing of transformer oil for PCBs - 47 items of equipment at 5 sub-stations

• replacing of oil-filled equipment – 87 items Construction of communications and SCADA system:

• Laying out of optical fiber cable (75 km of Kara Balta - Glavnaya 220 KV line)

4 October 2016 Upgrading of substations:

• Testing of transformer oil for PCBs - 28 items of equipment at 8

7

sub-stations

• replacing of oil-filled equipment – 32 items Construction of communications and SCADA system:

• Laying out of optical fiber cable – 15,5 km of Kara Balta - Glavnaya 220 KV line) and 45 km of Frunzenskaya – Kara-Balta 220 KV line)

5 November 2016

Upgrading of substations:

• Testing of transformer oil for PCBs - 25 items of equipment at 5 sub-stations

• replacing of oil-filled equipment – 44 items Construction of communications and SCADA system:

• Laying out of optical fiber cable – 9 km of Frunzenskaya – Kara-Balta 220 KV line)

6 December 2016

Upgrading of substations:

• replacing of oil-filled equipment – 8 items

Detailed information of activities and project implementation progress are described below. Upgrading of substations 15. In July 2016, NEHK handed over 2 (two) express analyzers for testing transformer oil for

PCBs to NEGK. On 26 July 2016 the national environment safeguards consultant recruited by

the Ministry of Energy, supported by "Ilim" – express analyzer supplying company – conducted

a hands-on training for NEGK personnel working with express analyzers.

16. In August 2016, the testing of transformer oil for PCBs started. In total, from July to

November 2016, 221 oil filled items of equipment were tested at 25 Substations. The testing of

oil showed that there is no PCBs contamination in oils and equipment (oil testing information is

in Table 2). So the works on replacing oil-filled equipment started in August 2016.

17. For period from August to December 2016, 192 units of oil-filled equipment were replaced.

The oil was drained from the circuit breakers on-site, and then transported from sub-stations to

oil facilities, which are available at enterprises of high-voltage electrical networks (HVENs).

Current and voltage transformers are removed in oil-filled status and are transported also to

HVENs. At substations with the largest number of equipment to be replaced as Kara-Balta,

Frunzenskaya, Glavnaya (Chui oblast) – special sites were built for the temporary storage of

equipment not contaminated with PCBs (see photos 1, 2, and 3 below). The following works

were implemented for the construction of the mentioned sites:

18. Enterprises of high-voltage networks (EHVN) constructed the sites for temporary storage of uncontaminated PCB equipment using their own resources and labor. No earth works/excavation and site leveling were carried out. Gravel for covering the sites was purchased at OAO "Kum-Shagyl", concrete curbs and metal supports were taken from EHVNs’ stock.

8

Photos 1 and 2. Constructed sites for temporary storage of removed voltage transformers, current transformers and circuit-breakers not contaminated with PCPs at substations Kara-Balta and Glavnaya – status as of September 2016.

Photo 3. Constructed Site for temporary storage of removed circuit-breakers not contaminated with PCPs at TEHVN – status as of August 2016.

1.4.2. Construction of communications and supervisory control and data acquisition system (SCADA) 19. In July 2016 implementation of Lot 2 has started. Construction activities included laying of

optical fiber cable. From July to October 2016, the work was carried out at 3 transmission lines:

(i) Glavnaya - Chuiskaya 220 kV - 59,9 km of cable;

(ii) Kara-Balta - Glavnaya 220 kV – 90,5 km of cable;

(iii) Frunzenskaya- Kara-Balta 220 kV - 54 km of cable.

Photo 4. Works for laying of optical fiber cable at high voltage power line Glavnaya – Chuiskaya – conducted in August, 2016

9

1.2. Changes in project organization and environmental management team

Project Organizational Structure 20. The Project has Executing Agencies: National Energy Holding of Kyrgyzstan (NEHK), and Open type Joint Stock Company National Electric Grid of Kyrgyzstan (NEGK). Due to the change of the structure of the Government of the Kyrgyz Republic in July 2016, the energy functions of the Ministry of Economy were transferred to the newly established the State Committee for Industry, Energy, and Mining of the Kyrgyz Republic.

21. State Committee for Industry, Energy, and Mining is responsible for:

(i) capacity-building of NEGK regarding corporate and financial management, including development of business plan for NEGK;

(ii) elaborating proposal for establishment of the settlement system for wholesale electricity supply transactions; and;

(iii) supervising NEGK's project implementation performance. 22. NEGK is responsible for following activities:

(I) installing communication system for recording electricity commercial consumption data, and collection of metering data through the national electric grid. This work includes installing meters and related equipment in substations of NEGK and facilities of electric power plants;

(II) rehabilitation of about 54 substations by replacing circuit breakers, and current and voltage transformers;

(III) installing communications and supervisory control and data acquisition system (SCADA) that includes the fiber-optic communication line that connects seven major NEGK substations and control centers;

(IV) ensuring NEGK support in Project implementation management. 23. Contractor for supplying, designing, laying, and commissioning of optical fiber network of SCADA is AK-AY ELEKTRIK DIS TICARET KOLLEKTIF SIRKETI (Turkey), which was contracted in July 2015. 24. In July 2016, AK-AY ELEKTRIK subcontracted the local company ChuiElectroStroy for_Lot 2 for auxiliary works. 25. In December 2015, NEGK signed a Contract with International consultant – expert on SCADA and communications, and with national consultants: electrical engineer, and environment safeguards consultant (Ms.Taisiya Neronova). 26. Environment Safeguards Consultant of NEGK is responsible for the supervision of the EMP implementation and preparation of reports in accordance with ADB requirements.

10

Organizational diagram of project/program implementation and project Environmental team

27. In May 2016 AK-AY ELEKTRIK, which is a contractor of NEGK for the Component 2: SCADA and AMDA, signed a contract with environmental specialist (Ms.N.Asanalieva). 28. ES of Contractor is responsible for the implementation of EMP/SSEMP and ensuring that projects works are carried out in compliance with environmental safeguards requirements.

1.3. Relationships with contractors, customer, lender, etc.

29. For successful implementation of EMP the Environment Safeguards Consultant had regular consultations with ADB KYRM environment safeguards consultant: meetings, telephone discussions, and email communication. 30. In accordance with the contract between NEGK and AK-AY ELEKTRIK No. 22-16/0073 dated 14.07.2015, the contractor has to submit on a quarterly basis an environmental report on Environmental Management Plan implementation. From July to December 2016, AK-AY ELEKTRIK timely submitted 2 reports. 31. During the reporting period the Environment Safeguards Consultant sent to AK-AY ELEKTRIK 2 letters regarding onsite environmental inspection, and submission of reports. The Environment Safeguards Consultant held regular meetings with AK-AY ELEKTRIK, during the reporting period there were 12 meetings.

II. ENVIRONMENTAL MONITORING 32. According to IEE/EMP/SSEMP no instrumental measurements are foreseen for air and water quality, for noise and vibration. The following types of monitoring were used:

• noise and vibration – visual observations

• air monitoring quality - visual observations;

• water quality - visual observations

2.1. Noise and vibration

31. Lot 1. Upgrading of Substations. No works which could produce noise or vibration were conducted. Preparation of sites was done during 3 days and equipment included one truck for delivery of construction materials (gravel, curbs, chain-link fencing), and one machine for leveling gravel.

SCIEM of KR and National Electric Grid of Kyrgyzstan

Environment Safeguards Consultant – T. Neronova

ADB

Construction contractor AK-AY ELEKTRIK

Environmental specialist – N. Asanalieva

11

32. Lot 2. Construction of communications and SCADA system. There were no works which could produce noise or vibration. The works to string fiber optic cable were conducted at a distance of more than 1 km away from settlements. Preparatory works included examination of existing poles to string the cable; machinery was not used. While stringing the fiber optic cable, one vehicle was working from time to time at the construction site.

2.2. Air quality Monitoring 33. No dust was observed. The vehicles used during the works (one truck and one machine for leveling gravel) were in good condition and regularly maintained. Vehicles and machinery that works at construction sites have technical passport of motor vehicle inspection as stipulated by EMP.

34. Lot 1. Upgrading of Substations. While replacing the equipment, a crane is used at substations for lifting equipment, also transportation of uninstalled equipment to the site, and delivery of new equipment to installation site. 35. Lot 2. Construction of communications and SCADA system. In accordance with EMP, for monitoring Lot 2, machinery working on pulling of optical fiber cable under Lot 2 has technical documentation on passing technical inspection, which indicates its serviceability. During the visual inspection during site visits, no oil leaks were found.

Photo 5. Equipment for cable laying is in good condition. Contractor is demonstrating certificate of technical inspection of machinery for laying optical fiber cable.

2.3. Water quality monitoring

36. Lot 1. Upgrading of Substations and Lot 2. Construction of communications and SCADA system.

Works were conducted at the relevant distance from water body. No spills or leakages were

observed along the routes used for the transportation of transformers.

2.4. Flora and fauna monitoring No illegal cutting or cases of poaching recorded for reporting period.

III. ENVIRONMENTAL MANAGEMENT

3.1. The environmental management system (EMS), site-specific environmental management plan (SSEMP), and work plans

37. In accordance with ADB requirements, 12 Site Specific Environmental Management and Monitoring Plans (SSEMP) have been developed for specific construction sites in May and June 2016.

1) SSEMP for Changing Oil-Filled Transformers at Substations of NEGK;

2) SSEMP for Changing Oil-Filled Circuit-Breakers at Substations of NEGK;

12

3) SSEMP for Changing PCB-free equipment: air, vacuum and SF6 circuit breakers,

outdoor switchyards at Substations of NEGK;

4) SSEMP for laying fiber optic communication line (FOCL) between substations (S-S)

Glavnaya – Chuiskaya 220 kV;

5) SSEMP for laying FOCL between S-S Kara-Balta - Glavnaya 220 kV;

6) SSEMP for laying FOCL between S-S Frunzenskaya – Kara-Balta 220 kV;

7) SSEMP for laying FOCL between S-S Ala-Archa - Frunzenskaya 220 kV;

8) SSEMP for laying FOCL between S-S Bystrovka – Ala-Archa 220 kV;

9) SSEMP for laying FOCL between S-S Glavnaya – Karagachovaya 110 kV;

10) SSEMP for laying FOCL between S-S Parkovaya – Ala-Archa 220 kV;

11) SSEMP for laying FOCL between S-S Chuiskaya – Bystrovka 220 kV;

12) SSEMP for laying FOCL between S-S Power and District Heating Plant (PDHP) Bishkek –

Parkovaya 110kV.

All SSEMPs are posted on NEGK website (www.negk.kg) for public awareness in May and June

2016.

3.2. On-Site Inspections and Audits

38. Information of site-inspections and audits is described in Table 2. Table 2. Site Inspections for period from July to December 2016 No. Sites for Inspection Who conducted inspection Date of inspection

Lot 1: Upgrading of substations

S-S Kara-Balta T. Neronova – env safeguards consultant NEGK;

09.09.2016

S-S Glavnaya T. Neronova – env safeguards consultant NEGK;

15.09.2016

S-S Kara-Balta ADB mission comprising safeguards specialist, Central and West Asia Department, ADB (Manila); env safeguards consultant, Kyrgyz Republic Resident Mission, ADB; env safeguards consultant NEGK; Head, OVS, NEGK; Chief Engineer, ChEHVN

16.09.2016

Lot 2. FOCL

Line Glavnaya – Chuiskaya, electricity pylons Nos.: 136-124;

T. Neronova – env safeguards consultant NEGK; N. Asanalieva – env safeguards specialist, AK-AY

08.08.2016

Line Glavnaya – Chuiskaya, electricity pylons Nos.: 42 – 27

T. Neronova – env safeguards consultant NEGK; N. Asanalieva – env safeguards specialist, AK-AY

19.08.2016

Line Glavnaya – Kara-Balta, electricity pylons Nos. 157-172

T. Neronova – env safeguards consultant NEGK; N. Asanalieva – env safeguards specialist, AK-AY

22.09.2016

Line Frunzenskaya – Kara-Balta electricity pylons Nos. 180 – 200

N. Asanalieva – env safeguards specialist, AK-AY.

21.10.2016

39. On 16 September 2016 ADB fielded a mission comprising Mr. Tran T. Thanh Phuong,

Safeguards Specialist, Central and West Asia Department, ADB (Manila); and environment

13

safeguards consultant, Kyrgyz Republic Resident Mission, ADB. The mission visited substation

Kara-Balta in Chui oblast.

40. The following observations and notes were made by Safeguards Specialist, Central and West Asia Department (ADB) Mr. Tran T. Thanh Phuong:

• The works have started for replacement of oil-filled circuit breakers at the substation

after testing transformer oil for PCBs, and it was established that PCBs content is lower

than 50 ppm;

• Specialists of the substation were instructed on safety requirements when working with

SF6 equipment. There is an Instruction for Using SF6 Equipment at the substation. The

Instruction was shown to the mission;

• Site for temporary storage of circuit breakers released from transformer oil: site is

equipped with curbs, it is covered with gravel, and this eliminates the risk of infiltration of

oil and soil/water pollution;

• Prepared area for temporary storage of oil emptied from the unit: Playground equipped

with curbs, covered with gravel, which reduces the risks of oil spills into environment and

soil/water pollution.

41. The Safeguards Specialist, Central and West Asia Department, ADB, recommended

following measures for environment protection during implementation of the project:

- Should PCB contaminated equipment and oil be identified, it will be necessary to

prepare special sites. Requirements for such sites are stipulated in EMP;

- Prepare an interim report on tested equipment by 26 September 2016.

42. While visiting the work sites of stringing fiber optic cable, environment safeguards consultant was conducting briefings regarding compliance with safety requirements.

3.2.1. Implementation of environmental safeguards requirements and management of oil-filled equipment and PCBs

43. In July 2016 NEGK handed over 2 (two) express analyzers for testing transformer oil for

PCBs to NEGK. On 26 July 2016 the national environment safeguards consultant recruited by

the Ministry of Energy, supported by "Ilim" – express analyzer supplying company –conducted a

hands-on training for NEGK personnel to work with express analyzers.

44. In total 15 participants attended the training. Participants of the training were the specialists

of high-voltage electrical networks from Osh, Naryn, Jalal-Abad, Chui, Issyk-Kul and Talas

oblasts, which are part of NEGK. (See list of participants in Appendix 1).

14

Photo 6. Hands-on training on new equipment during the visit to Chui enterprise of high-voltage networks

45. Prior to commencement of civil works, the schedule of transformer oil testing for PCBs was

developed, which included particular schedule of transformer oil testing for PCBs of oil filled

circuit breakers to be replaced under the ADB-funded Power Sector Improvement Project. In

September 2016 the schedule was revised and adjusted.

46. The national environment safeguards consultant and NEGK specialist started oil testing

from August 1, 2016 until 16 November 2016. Oil sampling was conducted in line with

decommissioning of equipment.

47. After November 15, 2016, the works were suspended due to the winter season, when

disconnection of electrical equipment is not allowed. As was noted above (paragraph 1.3),

replacement of oil-filled equipment under the ADB-funded Power Sector Improvement Project

will be conducted at 54 substations out of 107 ones. At the remaining 44 substations oil-free

equipment —air and vacuum circuit breakers and outdoor switchyards—are to be replaced.

48. For oil testing, the Commission was established, composed of NEGK specialists, by NEGK

Order No. 229 dated 01.08.2016. Taking into account that express analyzer prints out and

stores in its memory the test results, specialists of SAEPF were not included into the

commission.

15

Photos 7 and 8. Oil Sampling from circuit breakers at Jetigen sub-station and from current transformers

at sub-station Frunzenskaya – personnel are equipped with personal protective equipment (PPE), and all

health and labor safety requirements were followed.

49. In total, during the period from August to November 2016, 221 items of oil-filled equipment

were tested at 25 substations of Chui, Jalal-Abad, Naryn and Talas oblasts (regions).

Photo 9. Testing of oil for PCB at substation Frunzenskaya

50. The content of PCBs in all the collected samples was below 50 ppm, which indicates the

absence of PCBs contamination in replaced oil-filled equipment and oils. Thus, according to

received information, at replacement of the tested equipment, the EMP for electrical equipment

and oils not contaminated with PCBs will be implemented. The test results of oil-filled equipment

are in Table 3 below.

16

51. Results of tests for each piece of equipment were recorded in minutes signed by

participants who conducted the testing. The template of minutes with printed out file of express

analyzer is shown in Appendix 2. As noted above, information on tests results was submitted to

SAEPF and posted on NEGK website.

52. According to the schedule, in testing of transformer oil for PCB in oil-filled equipment to be

replaced in frame of ADB-funded Power Sector Improvement Project will be done at 29

substations in Osh and Issyk-Kul oblasts, and 2 substations in Jalal-Abad oblast.

3.2.2. Management of SF6 Equipment

53. In order to comply with safety requirements while replacing SF6 gas-insulated equipment at

NEGK substations, an Operation Manual for SF6 circuit breakers was used. The personnel

have been trained by the Supplier on management of SF6 gas-insulated circuit breakers. The

Operation Manual (Instruction) has safety guidelines for installing equipment containing SF6

gas.

17

Table 3. Results of PCBs testing of transformer oil from equipment to be replaced under the ADB-funded Power Sector Improvement

Project at NEGK substations

№№ п/п

Name of substation

Equipment Number, unit.

Date of testing

# of test Test result, ppm

Maximum Permissible

Concentration, ppm

Note

Chui EHVN 1

1.

Substation2 Frunzenskaya Pad for temporary storage of current and voltage transformers equipment is prepared

1. CT3-500 HVL-4–500, L5-509 Ph6-А 1 14.09.2016 00148 2,77 50

2. CT -500 HVL- – 500, L- 509 Ph -С 1 14.09.2016 00147 2,39 50

3. VT7-500 HVL--500, L-509, PH -A/1 1 14.09.2016 00149 12,3 50

4. VT-500 HVL--500, L-509, PH -A/2 1 14.09.2016 00150 11,2 50

5. VT-500 HVL--500, L-509, PH -A/3 1 14.09.2016 00165 3,93 50

6. VT-500 HVL--500, L-509, PH -A/4 1 14.09.2016 00143 8,73 50

7. VT-500 HVL--500, L-509, PH -B/1 1 14.09.2016 00154 10,6 50

8. VT-500 HVL--500, L-509, PH -B/2 1 14.09.2016 00155 11,3 50

9. VT-500 HVL--500, L-509, PH -B/3 1 14.09.2016 00156 8,77 50

10. VT-500 HVL--500, L-509, PH -B/4 1 14.09.2016 00157 11,5 50

11. VT-500 HVL--500, L-509, Ph-С/1 1 14.09.2016 00158 13,8 50

12. VT-500 HVL--500, L-509, Ph-С/2 1 14.09.2016 00159 13,8 50

13. VT-500 HVL--500, L-509, Ph-С/3 1 14.09.2016 00160 7,46 50

14. VT-500 HVL--500, L-509, Ph-С/4 1 14.09.2016 00161 5,81 50

15. CT -500 HVL- – 500, L- «Jambyl» PH -A 1 26.08.2016 00114 3,23 50

16. CT -500 HVL- – 500, L- «Jambyl» Ph-С 1 26.08.2016 00115 2,51 50

17. VT500 HVL--500, L-«Jambyl», PH -A/1 1 26.08.2016 00116 4,18 50

18. VT-500 HVL--500, L-«Jambyl», Ph -A/2 1 26.08.2016 00117 4,23 50

1 ChEHVN - Chui high-voltage electrical networks enterprise 2 S - substation 3 CT- current transformer 4 HVL – high-voltage line 5 L- line 6 Ph- phase voltage 7 ТН – voltage transformer

18

19. VT-500 HVL--500, L-«Jambyl», Ph -A/3 1 26.08.2016 00118 4,60 50

20. VT-500 HVL--500, L-«Jambyl», Ph -A/4 1 26.08.2016 00119 4,23 50

21. VT-500 HVL--500, L-«Jambyl», Ph -B/1 1 26.08.2016 00120 3,02 50

22. VT-500 HVL--500, L-«Jambyl», Ph -B/2 1 26.08.2016 00121 3,48 50

23. VT-500 HVL--500, L-«Jambyl», Ph -B/3 1 26.08.2016 00122 3,84 50

24. VT-500 HVL--500, L-«Jambyl», Ph -B/4 1 26.08.2016 00123 3,53 50

25. VT-500 HVL--500, L-«Jambyl», Ph-С/1 1 26.08.2016 00124 4,33 50

26. VT-500 HVL--500, L-«Jambyl», Ph -С/2 1 26.08.2016 00125 4,56 50

27. VT-500 HVL--500, L-«Jambyl», Ph -С/3 1 26.08.2016 00126 4,80 50

28. VT-500 HVL--500, L-«Jambyl», Ph -С/4 1 26.08.2016 00127 6,50 50

29. CT -500 HVL- – 500, L- «Shu» PH -A 1 17.08.2016 00072 7,17 50

30. CT -500 HVL- – 500, L- «Shu» Ph -С 1 17.08.2016 00073 3,53 50

31. VT-500 HVL--500, L-«Shu», Ph -A/1 1 17.08.2016 00074 10,8 50

32. VT-500 HVL--500, L-«Shu», Ph - A/2 1 17.08.2016 00075 4,69 50

33. VT-500 HVL--500, L-«Shu», Ph -A/3 1 17.08.2016 00076 7,17 50

34. VT-500 HVL--500, L-«Shu», Ph -A/4 1 17.08.2016 00077 11,1 50

35. VT-500 HVL--500, L-«Shu», Ph -B/1 1 17.08.2016 00078 10,1 50

36. VT-500 HVL--500, L-«Shu», Ph -B/2 1 17.08.2016 00079 10,5 50

37. VT-500 HVL--500, L-«Shu», Ph -B/3 1 17.08.2016 00080 10,5 50

38. VT-500 HVL--500, L-«Shu», Ph -B/4 1 17.08.2016 00081 6,01 50

39. VT-500 HVL--500, L-«Shu», Ph -С/1 1 17.08.2016 00082 6,39 50

40. VT-500 HVL--500, L-«Shu», Ph-С/2 1 17.08.2016 00083 9,26 50

41. VT-500 HVL--500, L-«Shu», Ph -С/3 1 17.08.2016 00084-00085 9,64 -10,6 50

42. VT-500 HVL--500, L-«Shu», Ph -С/4 1 17.08.2016 00086 10,6 50

43. VT-220, TFND №3601 1 17.08.2016 00087 8,79 50

44. VT-220, TFND №3532 1 17.08.2016 00088 12,8 50

45. VT-220, TFND №3573 1 17.08.2016 00089 11,5 50

46. VT-220, TFND №801 1 17.08.2016 00090 9,56 50

47. VT-220, TFND №3428 1 17.08.2016 00091 11,3 50

48. VT-220, TFND №3630 1 17.08.2016 00092 9,48 50

49. VT-220, TFND №8953 1 17.08.2016 00093 10,6 50

50. VT-220, TFND №8937 1 17.08.2016 00094 7,26 50

51. VT-220, TFND №8934 1 17.08.2016 00095 6,42 50

52. CT 220 HVL Ala-Archa, Ph- A 1 28.09.2016 00166 2,27 50

53. CT 220 HVL Ala-Archa, Ph- B 1 28.09.2016 00167 12,0 50

54. CT 220 HVL Ala-Archa, Ph- C 1 28.09.2016 00168 8,14 50

55. CT- 220 ZHGRES Ph - A 1 10.10.2016 00194 6,08 50

56. CT- 220 ZHGRES Ph - B 1 10.10.2016 00195 40,2 50

19

57. CT- 220 ZHGRES Ph - C 1 10.10.2016 00196 6,30 50

58. CT- 220 Kemin Ph - A 1 12.10.2016 00197 6,76 50

59. CT- 220 Kemin Ph - B 1 12.10.2016 00198 9,58 50

60. CT- 220 Kemin Ph - C 1 12.10.2016 00199 31,7 50

61. ТТ – 220 ВЛ АТ – 1 Ph- А 04.11.2016 00219 12,9 50

62. ТТ – 220 ВЛ АТ – 1 Ph- А 04.11.2016 00220 12,0 50

63. ТТ – 220 ВЛ АТ – 1 Ph- А 04.11.2016 00221 11,5 50

2. Substation Kara-Balta Pad for temporary storage of transformers equipment is prepared

64. S8-220 В- 1 Frunzenskaya -1, PH -А 1 02.08.2016 00008 7,42 50

65. S-220 В- 1 Frunzenskaya -1, Ph -В 1 02.08.2016 00007 9,99 50

66. S-220 В- 1 Frunzenskaya -1, Ph -С 1 02.08.2016 00006 9,66 50

67 S-220 В- 2 Frunzenskaya - 2, Ph – А 1 02.08.2016 00009 5,72 50

68. S-220 В- 2 Frunzenskaya -2, Ph -B 1 02.08.2016 00010 12,6 50

69. S-220 В- 2 Frunzenskaya -2, Ph -С 1 02.08.2016 00011 15,2 50

70. S-220В- 1 Glavnaya, Ph – А 1 02.08.2016 00015 5,34 50

71. S-220В- 1 Glavnaya, Ph –B 1 02.08.2016 00016 7,47 50

72. S-220В- 1 Glavnaya, Ph – С 1 02.08.2016 00017 5,92 50

73. S-220В- 2 Glavnaya, Ph – А 1 02.08.2016 00014 4,74 50

74. S-220В- 2 Glavnaya, Ph –B 1 02.08.2016 00013 9,61 50

75. S-220В- 2 Glavnaya, Ph – С 1 02.08.2016 00012 5,38 50

76. VT – 10, II SSH – 1-kV 1 02.08.2016 00146 7,54 50

3. Substation Ala-Archa Equipment after replacement will transported to ChEHVN

77. VT – 10, II SSH - 35, №1 1 07.09.2016 00142 14,5 50

78. VT – 10, II SSH - 35, №2 1 07.09.2016 00141 16,3 50

4. Substation Manas Equipment after replacement will transported to ChEHVN

79. VT – 35, PH –A 1 07.09.2016 00138 19,5 50

80. VT – 35, Ph- В 1 07.09.2016 00139 7,28 50

81. VT – 35, Ph- С 1 07.09.2016 00140 22,5 50

5. Substation Kant Equipment after replacement will transported to ChEHVN

82. VT – 35, I SSH - 35, Ph -A 1 07.09.2016 00133 15,8 50

83. VT – 35, I SSH - 35, Ph –В 1 07.09.2016 00134 10,2 50

84. VT – 35, I SSH - 35, Ph -С 1 07.09.2016 00135 8,92 50

85. VT – 35, II SSH - 35, Ph –A 1 07.09.2016 00136 15,6 50

8 S – Switch

20

86 VT – 35, II SSH - 35,Ph –С 1 07.09.2016 00137 12,6 50

6. Substation Glavnaya Pad for temporary storage of transformers equipment is prepared

87. CT – 110, Georgievka, Ph -A 1 07.09.2016 00131 43,0 50

88. CT – 110, Georgievka, Ph -С 1 07.09.2016 00132 16,1 50

89. CT – 110, OV-110, Ph -С, №3044 1 07.09.2016 00130 9,69 50

90. CT – 110, OV-110, Ph -В, №1925 1 07.09.2016 00129 12,9 50

91. CT – 110, OV-110, Ph -A, №648 1 07.09.2016 00128 13,4 50

92. CT – 220, Shu, Ph –A 1 14.09.2016 00145 47,0 50

93. CT – 220, Shu, Ph –В 1 14.09.2016 00144 12,1 50

94. CT – 220, Shu, Ph –С 1 14.09.2016 00153 12,1 50

95. CT-220 OV-220 PH –A 1 21.09.2016 00162 25,8 50

96. CT-220 OV-220 Ph –B 1 21.09.2016 00163 8,81 50

97. CT-220 OV-220 Ph – С 1 21.09.2016 00164 4,8 50

98. VT -220 kV Alma-Ata Ph – A 1 28.09.2016 00169 8,38 50

99. VT -220 kV Alma-Ata Ph – B 1 28.09.2016 00170 10,3 50

100. VT -220 kV Alma-Ata Ph – C 1 28.09.2016 00171 17,4 50

101. VT -220 kV TETSB - 1 Ph – A 1 28.09.2016 00172 7,50 50

102. VT -220 kV TETSB - 1 Ph – B 1 28.09.2016 00173 7,45 50

103. VT -220 kV TETSB - 1 Ph – C 1 28.09.2016 00174 6,76 50

104. VT -220 kV TETSB - 2 Ph – A 1 28.09.2016 00175 10,7 50

105. VT -220 kV TETSB - 2 Ph – B 1 28.09.2016 00176 5,97 50

106. VT -220 kV TETSB - 2 Ph – C 1 28.09.2016 00177 7,54 50

107. CT IСШ 110 kV Ph – A 1 02.11.2016 00216 12,6 50

108. CT IСШ 110 kV Ph – B 1 02.11.2016 00217 14,9 50

109. CT IСШ 110 kV Ph – C 1 02.11.2016 00218 12,7 50

7. Bystrovka Substation Pad for temporary storage of transformers equipment is prepared

110. CT -220kV IIСШ-200 Ph-A Lower Cascade 1 05.10.2016 00178 8,93 50

111. CT -220 KV IIСШ-200 Ph-A Upper Cascade 1 05.10.2016 00179 11,7 50

112. CT -220 kV IIСШ-200 Ph-B Lower Cascade 1 05.10.2016 00180-00181 (0,47) 1,98 50

113. CT -220 KV IIСШ-200 Ph-B Upper Cascade 1 05.10.2016 00182 12,3 50

114. CT -220 kV IIСШ-200 Ph-C Lower Cascade 1 05.10.2016 00183 11,3 50

115. CT -220 KV IIСШ-200 Ph-C Upper Cascade

1 05.10.2016 00184 12,4 50

116. VT-35 Orlovka, Ph – A 1 05.10.2016 00185 18,4 50

117. VT-35 Orlovka, Ph – B 1 05.10.2016 00186 18,2 50

118. VT-35 Orlovka, Ph – C 1 05.10.2016 00187 23,7 50

119. VT-35 Kemin Ph – A 1 05.10.2016 00188 20,7 50

21

120. VT-35 Kemin, Ph – B 1 05.10.2016 00189 9,6 50

121. VT-35 Kemin, Ph – C 1 05.10.2016 00190 19,5 50

122. VT-220 Kemin – 1 Ph – A 1 09.11.2016 00222 5,06 50

123. VT -220 Kemin – 1 Ph – B 1 09.11.2016 00223 1,68 50

124. VT -220 Kemin – 1 Ph – C 1 09.11.2016 00224 15,2 50

125. VT -220 Kemin – 2 Ph – A 1 09.11.2016 00225 5,23 50

126. VT -220 Kemin – 2 Ph – B 1 09.11.2016 00226 6,5 50

127 VT -220 Kemin – 2 Ph – C 1 09.11.2016 00227 6,65 50

128. CT – 220 IСШ Ph – А/Upper Cascade 1 09.11.2016 00228 1,02 50

129. CT – 220 IСШ Ph – B/Upper Cascade 1 09.11.2016 00229 0,84 50

130. CT – 220 IСШ Ph – A/Lower Cascade 1 09.11.2016 00230 17,8 50

131. CT – 220 IСШ Ph – B/Lower Cascade 1 09.11.2016 00231 15,6 50

132. CT – 220 IСШ Ph – C/Lower Cascade 1 09.11.2016 00232 1,03 50

133. CT – 220 IСШ Ph – C/Upper Cascade 1 09.11.2016 00233 13,08 50

8.

Ivanovka Substation Equipment after replacement will transported to ChEHVN

134. VT-35kV ZNOM -3B65-U1 Ph – A 1 05.10.2016 00191 4,0 50

135. VT-35kV ZNOM -3B65-U1 Ph – B 1 05.10.2016 00192 3,05 50

136. VT-35kV ZNOM -3B65-U1 Ph – C 1 05.10.2016 00193 2,79 50

9.

Novo-zapadnaya substation Equipment after replacement will transported to ChEHVN

137. CT - 6 kV NTMI - I СШ 1 12.10.2016 00200 3,22 50

138. CT - 6 kV NTMI - II СШ 1 12.10.2016 00201 10,8 50

10.

Yuzhnaya substation Equipment after replacement will transported to ChEHVN

139. CT - 6 kV NTMI - I СШ -12 1 12.10.2016 00202 9,90 50

11.

Nova-Yuzhnaya Substation Equipment after replacement will transported to ChEHVN

140. CT - 6 kV NTMI - I СШ 1 12.10.2016 00203 18,5 50

12.

Kayinda Substation Equipment after replacement will be transported to ChEHVN

141. CT - 6 kV NTMI -1066 (15 cells) 1 14.10.2016 00205 9,01 50

142. CT - 10 kV NTMI - 10 (5 cells) 1 14.10.2016 00206 4,51 50

13.

Besh-Terek Substation Equipment after replacement will be transported to ChEHVN

143. CT - 10 kV NTMI – 10 No422 1 14.10.2016 00204 1,39 50

14. Zhengi-Zher Substation

144. VT HVL-100 Blagoveschenka Phase A 1 16.11.2016 00234 2,73 50

145. VT HVL-100 Blagoveschenka Phase C 1 16.11.2016 00235 3,95 50

22

146. CT HVL-110 IСШ Phase A 1 16.11.2016 00237 2,06 50

147. CT HVL-110 IСШ Phase B 1 16.11.2016 00236 4,52 50

148. CT HVL-110 IСШ Phase C 1 16.11.2016 00238 0,00 50

149. CT HVL-110 IСШ Phase C 1 16.11.2016 00239 0,00 50

15. Pikovaya-Kotelnaya Substation

150. CT NTMD 10 – UZ 1 16.11.2016 00240 4,51 50

Naryn EHVN

16.

Substation Zhetigen Equipment after replacement will be transported to Naryn EHVN

151. S110, Ph – А 1 05.08.2016 00018 25,9 50

152. S110, Ph – С 1 05.08.2016 00019 11,6 50

153. В MKP, СВ-100, Ph – С 1 05.08.2016 00020 8,16 50

154. S110, Makmal, Ph –А 1 05.08.2016 00021 10,3 50

155. S110, Makmal, Ph –В 1 05.08.2016 00022 32,4 50

156. S110, Makmal, Ph –С 1 05.08.2016 00023 28,9 50

157. S110, Urum-Bash, Ph–А 1 05.08.2016 00024 26,4 50

158. S110, Urum-Bash, Ph–В 1 05.08.2016 00025 12,0 50

159. S110, Urum-Bash, Ph –С 1 05.08.2016 00026 31,0 50

17.

Substation Chaek Equipment after replacement will be transported to Naryn EHVN

160. S СВ-110 (MKP) 1 05.08.2016 00027 10,8 50

161. S ВHVL--110 Kara-Keche, MKP 1 05.08.2016 00030 9,6 50

18.

Substation Naryn-1 Equipment after replacement will be transported to Naryn EHVN

162. CT-35 1 05.08.2016 00029 18,6 50

19.

Substation Ugut Equipment after replacement will be transported to Naryn EHVN

163. CT 35 1 05.08.2016 00028 20,8 50

Jalal-Abad EHVN

20.

Substation Kristall Equipment after replacement will be transported to Torobaev Substation

164. S HVL-220, «Sardar», Ph – А 1 15.08.2016 00031-00032 4,97 50

165. S HVL-220, «Sardar», Ph – В 1 15.08.2016 00033 3,86 50

166. S HVL-220, «Sardar», Ph – С 1 15.08.2016 00034 3,14 50

167. S HVL-220, «Ulduz», Ph – A 1 15.08.2016 00035 6,38 50

168. S HVL-220, « Ulduz », Ph –B 1 15.08.2016 00036 5,18 50

169. S HVL-220, «Ulduz», Ph – С 1 15.08.2016 00037 5,33 50

170. S ОВ-220, Ph – А 1 15.08.2016 00038 7,54 50

23

171. S ОВ-220, Ph –B 1 15.08.2016 00039 7,72 50

172. S ОВ-220, Ph – С 1 15.08.2016 00040 7,94 50

173. S В-220, Kyzyl Ravat Ph –А 1 15.08.2016 00041 4,91 50

174. S В-220, Kyzyl Ravat Ph –В 1 15.08.2016 00043 6,51 50

175. S В-220, Kyzyl Ravat Ph –С 1 15.08.2016 00042 4,59 50

176. S HVL--220, Tash.Ges-1, PH –A 1 15.08.2016 00057 3,98 50

177. S HVL--220, Tash.GES-1, PH –В 1 15.08.2016 00058 5,59 50

178. S HVL--220, Tash.GES-1, PH –С 1 15.08.2016 00059 4,66 50

179. S HVL--220, Tash.GES-2, PH –A 1 15.08.2016 00060 5,58 50

180. S HVL--220, Tash.GES-2, Ph –В 1 15.08.2016 00061 3,87 50

181. S HVL--220, Tash.GES-2, Ph –С 1 15.08.2016 00062 3,86 50

182. S HVL--220, Kurpsaiskaya GES, Ph -A 1 15.08.2016 00063 6,98 50

183. S HVL--220, Kurpsaiskaya GES, Ph -В 1 15.08.2016 00064 7,39 50

184. S HVL--220, Kurpsaiskaya GES, Ph -С 1 15.08.2016 00065 7,27 50

185. SSH 220 Ph –A 1 15.08.2016 00066 7,49 50

186. SSH 220 Ph –B 1 15.08.2016 00067 6,88 50

187. SSH 220 Ph –С 1 15.08.2016 00068 8,03 50

188. S HVL--220, PPM -2, Ph –A 1 15.08.2016 00069 7,67 50

189. S HVL--220, PPM -2, Ph – B 1 15.08.2016 00070 6,61 50

190. S HVL--220, PPM -2, Ph –C 1 15.08.2016 00071 7,98 50

21.

Substation Torobaeva Construction of equipment temporary storage pad is in progress

191. CT 220 «Foton» Ph -A 1 15.08.2016 00044 8,64 50

192. CT 220 «Foton Ph –С 1 15.08.2016 00045 8,3 50

193. CT 220 «Fazylman» Ph -A 1 15.08.2016 00046 16,1 50

194. CT 220 «FазыLман» Ph -С 1 15.08.2016 00047 6,48 50

195. CT 220, АТ – 3, Ph –A 1 15.08.2016 00048 4,97 50

196. CT 220, АТ – 3, Ph –B 1 15.08.2016 00049 6,59 50

197. CT 220, АТ – 3, Ph –С 1 15.08.2016 00050 5,39 50

198. CT 220, АТ – 2, Ph –A 1 15.08.2016 00051 11,7 50

199. CT 220, АТ – 2, Ph –B 1 15.08.2016 00052 28,3 50

200. CT 220, АТ – 2, Ph –С 1 15.08.2016 00053 7,09 50

201. CT 220, АТ – 1, Ph –A 1 15.08.2016 00054 9,55 50

202. CT 220, АТ – 1, Ph –B 1 15.08.2016 00055 7,07 50

203. CT 220, АТ – 1, Ph –С 1 15.08.2016 00056 11,4 50

Talas EHVN

22.

Substation Talas Equipment after replacement will be transported to Talas EHVN

204. S MKP-110 , Т-1, Ph -А 1 24.08.2016 00096 14,3 50

24

205. S MKP-110 , Т-1, Ph -В 1 24.08.2016 00097 16,7 50

206. S MKP-110 , Т-1, Ph -С 1 24.08.2016 00098 16,9 50

207. S MKP-110 , Т-1, Ph -А 1 24.08.2016 00099 16,6 50

208. S MKP-110 , Т-1, Ph – В 1 24.08.2016 00100 17,0 50

209. S MKP-110 , Т-1, Ph -С 1 24.08.2016 00101 18,6 50

23.

Substation Pobeda Equipment after replacement will be transported to Talas EHVN

210. CT- 35, «Ak-Dobo», Ph -А 1 24.08.2016 00102 3,88 50

211. CT- 35, «Ak-Dobo», Ph -С 1 24.08.2016 00103 13,8 50

212. VT 1 SSH-35, Ph –А 1 24.08.2016 00104 9,73 50

213. VT 1 SSH-35, Ph –B 1 24.08.2016 00105 11,6 50

214. VT 1 SSH-35, Ph –С 1 24.08.2016 00106 33,8 50

215. VT 2 SSH-10 1 24.08.2016 00107 6,46 50

216. VT 2 SSH- 35, PH -A 1 24.08.2016 00108 7,44 50

217. VT 2 SSH- 35 Ph –В 1 24.08.2016 00109 26,7 50

218. VT 2 SSH- 35 Ph- С 1 24.08.2016 00110 9,54 50

24.

Substation «Chat-Bazar» Equipment after replacement will be transported to Talas EHVN

219. CT – 35, Т -1 Ph -А 1 24.08.2016 00111 8,13 50

220. CT – 35, Т -1 Ph –С 1 24.08.2016 00112 8,82 50

25.

Substation Manas Equipment after replacement will be transported to Talas EHVN

221. VT – 2, SSH – 10 1 24.08.2016 00113 1,69 50

Total: As of 16 November 2016, 221 oil filled equipment were tested at 25 Substations

25

3.2.3. Management of Waste Management of oils and equipment not contaminated with PCBs 54. Taking into consideration that the tested equipment and oil are not contaminated with PCBs, emptied oil circuit breakers and oil-filled transformers will be stored on the territory of EHVN specially equipped sites in each region until NEGK issues a decision on disposing them as scrap metal, or as a redundant equipment for future use. 55. As noted above, after replacement, the removed tested equipment, oils drained from circuit breakers, oil-filled current and voltage transformers were transported from sub-stations to EHVNs sites in accordance with environmental requirements. No spills or leakages were observed.

3.2.4. Management of non-toxic waste

Lot 1. Upgrading of substations

56. Non-toxic waste generated during construction included: construction waste, rags, unsuitable packaging, adsorbents, etc. 57. Construction waste were transported from substation to sites specified in the permits issued by local departments of environmental protection for waste disposal. (Appendix 7). Lot 2. Construction of communications and supervisory control and data acquisition system 58. No special camp for persons working at optic fiber pulling has been arranged, as these persons live in Bishkek. Municipal wastes are disposed in accordance with ChuEHVN’s permit for waste disposal. Waste in the form of wooden spools for fiber optic cable are stored in the special warehouse rented by AK-AY company (see photo below) .

Photo 10. Warehouse for temporary storage of wastes of fiber optic cable – status in August 2016

3.3. Non-compliance Notices 59. There were no yet any non-compliance cases and no non-compliance notices were issued for reporting period.

3.3. Grievance Redress Mechanism 60. Requirements for grievance redress mechanism of ADB Accountability Mechanism Policy (2012) and ADB Safeguard Policy Statement (SPS, 2009) principally meet the requirements of the Law of the Kyrgyz Republic “On processing of complaints of citizens” (2007). The existing differences in timing of processing the complaints, specified as 30 days in the Law of the Kyrgyz Republic, and 14 days specified in ADB Accountability Mechanism Policy, were eliminated by the Order of the General Director of NEGK issued on May 22, 2014. The Order aims at NEGK’s

26

quick response to process the complaints. The contractor keeps Registration log book for citizens’ complaints and appeals at work sites. (Appendix 8). No complaints or requests were received from local people and working personnel, related to the project, during the reporting period of July-December 2016.

3.4. Information Support and awareness activities

61. In order to inform the public on the project implementation and measures to be taken to ensure environmental safety, NEGK continuously updates the information on project implementation progress, and during the reporting period the SSEMPs for two Lots were also posted at the web-site.

62. The results of transformer oil testing are posted at the NEGK website (www.negk.kg) and on NEGK Facebook page. 63. Information on conducted tests was submitted to SAEPF, and on SAEPF participation in

testing was submitted separately (Appendix 3).

3.5. Corrective Action Plan

64. EMP foreseen the furnishing the sites that protect the soil from contamination by oil with rain water during temporary storage of oil circuit breakers and current and voltage transformers at the sites. However, during the reporting period, these sites have not been relevantly furnished and NEGK is planning to start these works only in 2017. 65. Table 4 below specifies the progress of corrective actions fulfillment to resolve the above mentioned issues. Table 4. Status of Corrective Actions Plan implementation (

# Environmental

issues identified Corrective actions taken

Due Date Compliance Responsible for implementation/ supervision

1. Absence of portable PCB analyzers for rapid test of transformer oils

Procurement of express analyzers for testing transformer oils for PCBs

March 2016 Complied with SCIEM, NEGK

2. Absence or presence of PCBs in transformer oil

Conducting of trainings and testing of transformer oil for presence/absence of PCBs

April – June 2016

Complied with SCIEM, NEGK

3. Absence of sites for temporary storage of old equipment including oil filled equipment

Furnishing the site for temporary storage of old equipment including oil filled equipment

June 2016 Complied with Substations Kara-Balta, Glavnaya, Frunzenskaya

NEGK

4. Testing of transformer oil

Prepare an interim report to ADB on tested equipment

26 September 2016

Complied with NEGK

66. In order to achieve the compliance with project IEE and EMP, the following corrective actions should be carried out in close cooperation with ADB, SCIEM, and Contractor (Table 5).

27

Table 5

Action Plan for January-June 2017 # Environmental issues

identified Corrective actions taken

Due Date Responsible for implementation/ supervision

1. Works on testing of

transformer oil for PCB

are not completed

Continue works on

testing of transformer oil

May – August

2017

NEGK

2 Not completed furnishing

of sites for temporary

storage of oil circuit

breakers

Finalize relevant

furnishing of sites for

temporary storage of oil

circuit breakers

March-April 2017 Contractor

28

Appendix 1. List of participants of hands-on training, 27.07.2016, Place: Bishkek city, office of NEGK

29

Appendix 2. Template of the Minutes of equipment testing for PCBs

Open Type Joint Stock Company “National Electric Grid of Kyrgyzstan” __________________________________________________________________________________

Address: 720200, 326 Jibek Jolu street, Bishkek city Tel.: +996(312)66-04-31; Fax: +996(312)66-06-56; email. [email protected]

Minutes of testing transformer oil for polychlorinated biphenyls

No date: “__” _________ 2016 Location of testing ________________________ Title of equipment _____________________________________ Quantity, volume of sample 1 sample, 5 mg__________________________________

Title of indicator Unit Test results MPC по НД, not

more than

Polychlorinated biphenyls (PCBs)

ppm 50

Testing was performed by: Neronova T. I. National env. safeguards consultant, NEGK Kamalova L. A. OVSiRP, NEGK Vichkanova I. Yu. Operation and technical department, NEGK Riabokon S. Insulation, surge protection and testing,

NEGK

Page 1 of 1

30

Appendix 3. Letter to SAEPF on testing results (translation and original) Informal Translation of the letter (original of the letter is below)

Open Type Joint Stock Company “National Electric Grid of Kyrgyzstan”

__________________________________________________________________________________

720200, 326 Jibek Jolu street, Bishkek city, Kyrgyz Republic

Tel.: +996(312)66-04-31; Fax: +996(312)66-06-56; email. [email protected]

No.22-7/4-1189 04.11.16 Mr. A. A. Rustamov Director of the State Agency for Environmental Protection and Forestry under the Government of the Kyrgyz Republic

Dear Mr. A. A. Rustamov

Hereby OAO “National Electric Grid of Kyrgyzstan” informs you that in accordance with Environmental Management Plan provided for by the Initial Environmental Examination under the ADB-funded Power Sector Improvement Project, testing for PCBs is carried out of transformer oil of equipment to be replaced using express analyzer L2000DX.

As of 15 October 2016, 197 pieces of equipment (current and voltage transformers, oil

switches) to be replaced has been tested under the ADB-funded Project at 23 substations in Chui, Naryn, Talas, Jalal-Abad oblasts. The results of the testing show that there is no PCBs contamination in equipment to be replaced. The testing will continue till end November 2016, and in 2017, the sunny weather permitting.

If SAEPF is interested, it can take part in testing of transformer oil. Taking into account that all equipment is in operation, and collection of samples of oil is

performed only on equipment without power, OAO NEGK cannot provide precise schedule for collection of samples. Thus, SAEPF can send a letter to OAO NEGK should it be interested in this exercise, and relevant SAEPF specialists will be invited to participate in testing.

Results of the tests are posted on NEGK official website. Yours sincerely, First Deputy Director General A. V. Borodin /L. Kamalova Tel. 661152, OVSiRP

31

32

Appendix 4. Minutes of testing of transformer oil for PCBs at substation Glavnaya, 3 phases of current transformer, 3 minutes (example)

33

34

35

Appendix 5. Example of testing results of transformer oil stored in memory of express analyzer and printed out

36

Appendix 6. Acts of technical inspection for machinery/equipment at ChEHVN, NEHVN, TEHVN, JAEHVN

37

38

39

Appendix 7. Permit for emissions of pollutants into ambient air and placement of waste in environment

40

41

42

43

44

45

Appendix 8. Complaints log book for recording of citizens’ complaints and appeals