environmental monitoring report€¦ · environmental monitoring report loan 3293 january-june 2017...
TRANSCRIPT
Environmental Monitoring Report Loan 3293 January-June 2017
ARM -Sustainable Urban Development Investment
Program, Tranche 2
Prepared by the Yerevan Municipality for the Asian Development Bank.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Environmental Monitoring Report
Bi-annual Report
January-June 2017
ARM: Sustainable Urban Development Investment
Program, Tranche 2
Project Number: 42417-033
Loan Number: L3293-ARM
Prepared: July 2017
Prepared by the Yerevan Municipality
Yerevan Project Implementation Unit
2
2
ABBREVIATIONS
ADB Asian Development Bank
AP affected people
EARF environmental assessment and review framework
EIA environmental impact assessment
EMP environmental management plan
EMR environmental monitoring report
ES environmental specialist
GRM grievance redress mechanism
IEE initial environmental examination
PIU project implementation unit
PPMS project performance monitoring system
REA rapid environmental assessment
RA Republic of Armenia
RE resident engineer
SEMP site-specific environmental management plan
SPS (2009) Safeguards Policy Statement (2009)
SUDIP Sustainable Urban Development Investment Program
YM Yerevan Municipality
3
3
Contents
I. Introduction .................................................................................................................................................... 4
A. Project Description ..................................................................................................................................... 4
B. Implementation Progress ........................................................................................................................... 5
a. Construction Implementation Progress for Argavand-Shirak street road link, Tender 3 ........................... 5
b. Construction Implementation Progress for Davitashen-Ashtarak road link Tender 4 ............................... 5
c. Babajanyan-Ashtarak road link Tender 5 .................................................................................................... 6
C. Institutional Arrangements of the Project .................................................................................................. 6
II. Environmental Management .......................................................................................................................... 7
A. Environmental Safeguards Program ........................................................................................................... 7
a. ADB mission ................................................................................................................................................ 8
b. Archaeological Works Program, Tender 3 .................................................................................................. 8
c. Grievance Redress Mechanism and Public Consultation ............................................................................ 8
d. Meetings and Communication.................................................................................................................... 9
e. Awareness Raising and Environmental Training ....................................................................................... 10
III. Environmental Monitoring ........................................................................................................................... 11
A. Environmental Monitoring Program ......................................................................................................... 11
a. Environmental Monitoring for Tender 4 ................................................................................................... 11
B. Non-compliance Notices ........................................................................................................................... 15
C. Corrective Action Plans ............................................................................................................................. 15
IV. Findings and Recommendations .................................................................................................................. 15
V. Future program ............................................................................................................................................. 16
VI. Annexes ........................................................................................................................................................ 17
A. Annex 1: List of training participants for Tender 4 ....................................................................................... 17
B. Annex 2: List of training participants for Tender 4 conducted by Contractor .............................................. 18
C. Annex 3: Status of the action from previous environmental monitoring report ......................................... 23
D. Annex 4: Corrective action plan for Tender 4 ............................................................................................... 23
E. Annex 5: Status of the previous weekly environmental site monitoring reports for Tender 4 ................... 25
F. Annex 6: The results of air quality, noise and vibration monitoring for Tender 4 ....................................... 26
G. Annex 7: Example of weekly environmental monitoring checklist ............................................................. 27
4
4
I. Introduction
1. This bi-annual environmental monitoring report covers the time period of January-June 2017. The
report was prepared by PIU ES.
A. Project Description
2. The Government of Armenia received a loan in October of 2015 from ADB to finance SUDIP,
Tranche 2. The main objective of the Project is to complete the missing links of Yerevan bypass:
Argavand - Shirak road link Tender 3, Davitashen-Ashtarak road link Tender 4 and Babajanyan –
Ashtarak road link Tender 5. The two captioned road projects will help to divert through-traffic around
the city center.
Figure 1: Map showing the Tranche 2 location
5
5
B. Implementation Progress
a. Construction Implementation Progress for Argavand-Shirak street road link, Tender 3
3. The contract is terminated with Serenissima Construction S.p.A., (Italy) Contractor for Argavand-
Shirak road link Tender 3 and the new bidding process will be announced by the end of this year.
Figure 2: Map showing Tender 3 for the Argavand-Shirak street road link location
b. Construction Implementation Progress for Davitashen-Ashtarak road link Tender 4
4. On 20 December 2016 SUDIP signed the contract with Уoint venture “Company BlacФ Sea Group”
LTD (Georgia) with “Vahagn and Samvel” LLC (Armenia) Contractor for Davitashen-Ashtarak road
link Tender 4. The works comprise of 2.4 km of new road. The duration of the construction will be 18
months. The partial commencement for the area of Davitashen-Ashtarak main road (0+000;0+660)
RAMP 8_small cloverleaf interchange (0+000; 0+400), RAMP 7_Big cloverleaf interchange (0+100;
0+253), RAMP 1_Ashtarak-Chaush (0+040;0+130), RAMP 6_Chaush-Melkumov (0+000; 0+188),
RAMP 2_Chaush street (0+000; 0+301) construction works is provided on 14 April 2017 and the date
for access to the site was on 28 April 2017.
6
6
Figure 4: Map showing Tender 4 for the Davitashen-Ashtarak road link location
c. Babajanyan-Ashtarak road link Tender 5
5. The bidding documents including IEE for Babajanyan-Ashtarak road link Tender 5 is in the tender
process.
Figure 5: Map showing Tender 5 for the Babajanyan-Ashtarak road link location
C. Institutional Arrangements of the Project
6. The major tasks of the PIU ES are to carry out the overall environmental management ensuring full
compliance of the Project implementation with Armenian legislation and ADB SPS (2009). The ES
serves as a liaison between the safeguard team of Egis International Company, YM, the executing
7
7
agency, MNP of the RA and Ministry of Culture of the RA, project affected people, ADB and develops
and maintains direct relationships with government authorities, with the help of Engineer ES
organizes and conducts public consultations, etc. PIU ES Ruzanna Voskanyan manages all
construction site activities related to the environmental issues and PIU land acquisition and
resettlement specialist Sirak Gyulbudaghyan manages all resettlement and social aspects issues.
7. Engineer environmental management team is responsible for the preparation of environmental
assessment of Tranche 2 documents and is responsible for environmental supervision of construction
works for Davitashen-Ashtarak road link Tender 4. Marta Lazarska international ES and Edita
Vardgesyan national ES are supervision of the construction works of Davitashen-Ashtarak road link
Tender 4. Arus Harutyunyan social specialist of the supervision company is responsible for all
aspects of the social issues.
8. “Vahagn & Samvel” LTD Contractor’s ES David Harutyunyan is responsible for the preparation and
implementation of the SEMP in accordance with IEE/EMP, monitoring of the construction activities for
Tender 4. Contractor’s ES is reporting to Engineer ES after which the Engineer ES is reporting to PIU
ES.
II. Environmental Management
A. Environmental Safeguards Program
9. The implementation of the environmental safeguards program started in January 2013 and was in
progress during the reporting period.
10. Based on ADB comments PIU together with the consultants is revising the IEE for Babajanyan-
Ashtarak road link Tender 5 on 3 April 2017. The revised IEE was submitted to ADB on 28 April 2017
which was approved by ADB on 5 May 2017. English version of the approved IEE was posted on
ADB and PIU websites and Armenian version is in translation stage.
11. SEMP for Davitashen-Ashtarak road link Tender 4 developed by the Contractor based on the
IEE/EMP and conditionally was approved by the RE on 28 April 2017. Based on ADB, PIU and
Engineer ESs comments Contractor’s ES updated and submitted SEMP on 29 June 2017 which is
under revision stage. Also further updates should be implemented; especially survey methodology of
nearby properties should be incorporated in the SEMP.
8
8
a. ADB mission
12. An ADB mission to check compliance of Tender 4 activities to the ADB SPS (2009) safeguard
requirements took place on 08 June 2017. The mission was implemented by Armine Yedigaryan,
ADB National Environmental Consultant, the PIU’s Ruzanna VosФanyan ES, Engineer’s Edita
Vardgesyan ES and Contractor’s representatives also Уoined the mission. The mission visited
construction site at Davitashen-Ashtarak road link. The recommendations of the mission audit on
further actions were related to:
some open holes;
The Contractor has placed more plastic tape as a safety measure for demarcation of holes
and hazards.
finalization of traffic management plan which was not approved by RE;
The traffic management plan has been provisionally approved on 27 June 2017.
coverage of all trucks
All trucФs observed by the Engineer’s team have been properly covered for more than two
weeks.
safety posters- should be bigger and in local language;
Posters are now in English and Armenian.
mitigation measure that should be applied to the fuel tank;
Contractor implemented mitigation measure for fuel tank.
b. Archaeological Works Program, Tender 3
13. Based on the IEE archaeology is only relevant for Tender 3 section, so as no work in this section
carried out in this reporting period.
c. Grievance Redress Mechanism and Public Consultation
14. For feedback, concerns and complaints from the APs, a GRM, inspired by the problem solving
function of ADB’s guidelines and policies should be maintained for the duration of the ProУect. The
GRM is intended to assist aggrieved persons in lodging their complaints and to describe the
mechanism designed to redress their grievances in a timely and effective manner. The parties
9
9
potentially involved are: the complainants, Contractor, Engineer, PIU, EA, NGOs, and the courts. The
details of the GRM operation could be found in EIA for Tender 3 and in IEEs of Tender 4 and 51.
15. A proper GRM has been established to meet environmental related concerns of affected people in
Davitashen-Ashtarak road link Tender 4. The availability of the logbook and registered complaints in
the Contractor’s field office was regularly checФed during the monitoring site visits.
16. During the reporting period a pre-construction public hearing was organized by Contractor’s
EHSS under the Davitashen-Ashtarak road link Tender 4 held on 12 April 2017 in Davitashen
community. General social and environmental issues, GRM had been discussed with APs. APs were
informed that the grievance redress mechanism to address the complaints/suggestions of APs on
excessive dust, noise, improper waste dumping and on other construction related issues is
established by the Contractor. Also special posters with contact information are posted at highly
visible places next to residential area (Please see below pictures). The posters are informing that in
order to ensure permanent communication with APs the complaints register log-books are kept
available at the Contractor's mobile on- site offices. No environment related concerns were raised by
the participants of the pre-construction public hearing.
17. The proper functioning of GRM in all important communities was regularly checked by contractor
and reported. No environmental related complaints were raised both verbally and in written by
impacted population during the reporting period.
d. Meetings and Communication
18. During the reporting period environmental safeguards issues were regularly discussed during the
joint meetings with YM, PIU and Engineer. Particularly the following issues were repeatedly
discussed: preparation and finalization of the IEEs for Babajanyan-Ashtarak road link Tender 5
approval process and related issues.
1 EIA/EMP for Tender 3 H.2. Grievance Redress Mechanism, page 47 of 62, in IEE/EMP for Davitashen-Ashtarak road link Tender 4 H.2.
Grievance Redress Mechanism, page 45 of 61 and in IEE/EMP for Babajanyan-Ashtarak road link Tender 5 H.2. Grievance Redress Mechanism, page 68 of 85.
10
10
19. Joint meeting at ADB office with ADB Deputy Country Director, ADB national environmental
consultant, PIU, Engineer and Contractor’s environmental and social specialists took place in April
2017. Preparation and finalization of the SEMP before commencement of the construction works
were discussed.
20. Regular meetings and discussions within PIU, Engineer and the Contractor’s environmental team
during the reporting period took place via joint meetings, official correspondence and emails, phone
calls and personal contacts. Particularly the issues on SEMP and instrumental measurements of
environmental parameters were discussed.
e. Awareness Raising and Environmental Training
21. The awareness raising and environmental orientation program was developed in the scope of
capacity building in the EIAs/IEEs and EMPs for Tender 3 and Davitashen-Ashtarak road link road
links. According to the program the Contractor should be responsible to arrange general orientation
session about project activities and environmental awareness. During this session, all the people
working on the site should focus their efforts to protect environment and insure the safe handling of
the social issues during construction period in accordance with ADB SPS (2009), Armenian
environmental legislation, EIA/IEE and EMP. Further details about the awareness raising and
environmental orientation program could be found in final EIA/EMP for Argavand Junction Tender 3,
in IEE/EMP for Davitashen-Ashtarak road link Tender 4 and in IEE/EMP for Babajanyan-Ashtarak
road link Tender 5 2.
22. An awareness raising training session was held by Marta Lazarska, Engineer international ES on
15 May 2017. Marta LazarsФa explained the topics via PP Presentations: “Health & Safety
Management” and “Environmental Management”. Contractor’s Фey staff including environmental,
social specialists and engineers were also participated (list of participants is attached in Annex 1).
23. According to IEE, Annex 7 EMP and SEMP for Tender 4 the Contractor organized trainings on
environmental, health and safety safeguards for the Contractor's and sub-contractor's staff on 06 and
25 May 2017, as well as regular trainings during all next months for newly hired staff during this
reporting period to use PPE and safety of works on the overpass structures, as well as dust control,
waste disposal issues and trucФs using covers. During the session Contractor’s doctor provided the
lecture on regular appropriate orientation on HIV/AIDS/STI prevention and treatment, to reduce the
2 EIA/EMP for Tender 3, I.3. Implementation arrangement, c) Awareness raising and environmental training, page 58 of 60; Annex 4, Table
1, para 7, page 7 of 36, IEE/EMP for Davitashen-Ashtarak road link road link Tender 4 I.3. Implementation arrangement, c) Awareness raising and environmental Training, page 55 of 61; Annex 3, Table 1, para 6, page 5 of 31 and IEE/EMP for Babajanyan-Ashtarak road link road link Tender 5 I.3. Implementation arrangement, c) Awareness raising and environmental Training, page 80 of 85; Annex 3, Table 1, para 6.
11
11
risk factors of and vulnerability to HIV/STI infections (see Annex 2: list of training participants for
Tender 4). The following topics had been discussed in detail during sessions and stressing the
significance of strict implementation of the points.
Occupational Health and Safety plan;
Emergency response plan;
Vegetation clearing plan and;
Environmental Protection plan.
III. Environmental Monitoring
A. Environmental Monitoring Program
24. Environmental monitoring program with a view to ensure compliance with the ADB’s
environmental requirements and all applicable environmental laws, regulations and standards for
environmental protection of RA has been developed in the scope of IEEs/EIA and EMPs for Tranche
2. The IEEs/EIA and EMPs contain monitoring activities to be considered during project
implementation: management during engineering design phase, preconstruction, construction through
the operation and maintenance periods. Details of monitoring activities and reporting requirements
are presented in approved final EIA and EMP for Argavand junction Tender 3, IEE and EMP for
Davitashen-Ashtarak road link Tender 4 and IEE and EMP for Babajanyan-Ashtarak road link Tender
53.
a. Environmental Monitoring for Tender 4
25. Monitoring checklist template is developed in order to standardize monitoring parameters
between the PIU/ Engineer and the Contractor. The template is being agreed with PIU/ Engineer and
Contractor and is approved within the SEMP. The checklist shall be used for monitoring implemented
by all the project parties: PIU/ Engineer and Contractor.
26. During the reporting period construction work site monitoring visits (see Annex 7: Example of
weekly environmental monitoring checklist) and dump site monitoring visits were organized jointly
with PIU, Contractor’s and Engineer’s ESs. RE and other responsible representatives of the
Contractor participated in some of the monitoring visits.
3 EIA/EMP for Tender 3, I. Environmental Management Plan,I.2 Monitoring page 56 of 62; Annex 4 Table 2,page 28 of 36, IEE/EMP for
Tender 4, I. Environmental Management Plan,I.2 Monitoring page 54 of 61; Annex 3 Table 2, page 23 of 31 and , IEE/EMP for Tender 5, I. Environmental Management Plan,I.2 Monitoring page 78 of 85; Annex 3 Table 2.
12
12
27. Contractor has recognized the environmental parameters on air quality, noise and vibration
provided in the IEE report (IEE, section D1 Table D-1 and Annex 6) as baseline for the regular
monitoring. The contract was signed between Contractor and "Lernametalurgie" Limited Liability
Company specialized laboratory (sub-contractor) for regular measurements of environmental
parameters of noise, vibration, and dust concentrations.
28. Relationship with Contractors, Owners, Lenders, etc. PIU's relationships with Contractor are
implemented through the Engineer/RE who is implementing the supervision (including environmental
and health & safety) of works. All the documents submitted by the Contractor are being reviewed and
approved/disapproved by RE. Communication with PIU and Contractor’s environmental team taФes
place via joint meetings, official correspondence and emails, phone calls and personal contacts.
29. The status of environmental permits and licenses submitted by the contractors/sub-contractors
are reflected in the Table 1 below:
Table 1: Status of environmental permits and licenses
Item status Comment
Tender 4
Commencement of works Open Permission to start civil works (commencement permission)
issued by PIU on 25 April 2017.
Disposal of construction
waste
Open Agreement from «X-Y» LLC for disposal of construction
wastes (excavated soil material, construction debris
generated from demolition of existing structures and from
stockpiles) into their territory on 07 April 2017. (Temporary
permission from YM is pending). Application to YM for waste
management services that include organization of waste
collection, assigning dump sites for construction waste dump
site is underway.
Permission on cutting
trees hindering
construction process
Open Trees hindering construction process were identified within
IEE/ EMP. Permission on cutting trees was issued by YM on
04 April 2017.
Construction camp Open Contract signed between “KamurУshin” CJSC and Contractor for temporary establishment of Contractor's construction
camp on 06 April 2017. The commencement of the
construction works for this section is not provided.
Preliminary accumulation
sites
Open The Contractor has applied to “HuУsi Avan” district and “GIACONIA” Charitable Foundation’s administrations with the request to allocate area for storage of construction
material and the latter responded adequately to the
13
13
Contractor's request on 20 June 2017.
Disposal of municipal and
construction waste
Open Permission of YM on the use of landfill for disposal of
household waste and garbage.
Crash machine installation Open Service Delivery Agreement has been signed between
Contractor and «X-Y» LLC for processing services of road
construction materials on 07 April 2017.
Treatment of excavated
usable subsoil
Open Service Delivery Agreement has been signed between
Contractor and «X-Y» LLC for processing services of road
construction materials on 07 April 2017.
Borrow pits Open The part of embankment materials used in construction are
delivering from existing licensed quarry - «X-Y» LLC and
borrow pit
“VZGO” LLC. Usable excavated material from construction
site will also be used for embankment. The Delivery
Contracts with aforementioned organizations are provided.
Inventory of Emissions of
hazardous substances in
to ambient air from
batching plant.
Not
needed
Contractor has no batching plant. In the future the Contractor
will buy concrete material from licensed subcontractor.
30.Contractor’s Environmental Monitoring Procedures and Health and Safety Management. In
accordance with the IEE/EMP, and the Contractor's SEMP, the Contractor is required to undertake
parametric instrumental measurements and observations on dust, noise, vibration and water quality,
Locations for the measurements were identified in the SEMP together with RE. Measurements are
being implemented through the contracted specialized laboratory two times per month. Frequency
can be re-considered depending on necessity.
31. The measurements were implemented according to approved SEMP at the points approved by
RE on 28 April 2017. Noise & vibration monitoring were performed by a certified noise & vibration
consultant in April 2015 at 5 locations it is included in IEE for Tender 4. Those locations are
recognized to be sensitive receptor (hospital/military school, residential private houses and buildings)
found along Project corridor. Also the measurement points are selected based on the principle of on-
14
14
going works during the construction works. According to the contract the specialized monitoring
company implemented the measurements in accordance with the approved measurement of
environmental parameters: air pollution, noise, vibration plan during the reporting period May-June
2017.
32. During the reporting period the measurements were implemented on 05 and 22 May, and on 09
and 30 June 2017. The reports containing data on the measurements are provided to PIU/ Engineer
and are available at PIU/Engineer's office. The levels of dust, noise, vibration and emitting
pollutants (SO2, NO2 and NO) have been tested using the following equipment’s:
А и ен -TOTAL №168613 noise meter-vibro meter equipment,
Dust level has been measured by aspirator П -4Э №5839 and А А В-10 filter papers
gravimetrical method,
Emission gases have been measured by MRU Optima 7 №306732 equipment.
33. The summary of the measurements could be presented as follows: Noise levels recorded during
daytime periods were generally above the average equivalent levels taken during baseline collection.
Whilst these levels are in a number of cases above project standards (3dB above baseline), impacts
are not thought significant as works at each location are temporary and no complaints were received.
Nevertheless, to further reduce noise impacts the following mitigation is now in place and being
implemented by the contractor:
I. Minimize noise generation at source. Locate noisier activities away from sensitive receptors
where practicable.
II. Where sensitive receptors occur limit operation of noisy equipment to daylight hours.
III. Minimize the need for heavy vehicles to pass through residential areas by specifying routes
along public roads, site access points and haul routes. Apply Traffic Management Plan to
haul routes.
IV. Installing and maintaining effective exhaust silencing systems on vehicles and equipment to
meet national noise standards.
V. Installing temporary hoarding around noise sources if other mitigation measures are not
sufficient or practicable.
Measurement is not implemented during night time as no construction is going on during night time.
Noise measurements are conducted for closest sensitive receptors located near the construction
sites. The locations of measurement points are selected before every monitoring measurement based
on the criteria of on-going civil works (at least 4 points) during the reporting period.
15
15
34. According to the results of vibration instrumental measurements, no vibration exposures were
detected near the all measurement points. Dust emissions at the selected 5 points were measured in
different daytime periods. The dust level exceeded (for the point Dust 3 at Km 0+350 for up to 3
times) Armenian legislative standards required for residential areas. Contractor was required and was
implementing intensive water spraying at the exposed areas.
35. Detailed information on the results of regular monitoring measurements are available at
Contractor’s and Engineer's offices being attached to the Contractor’s monthly progress reports and
are summarized in Annex 6 of the present report.
B. Non-compliance Notices
36. Non-compliance notices were not issued during the reporting period.
37. All the non-conformances which were detected during the upcoming monitoring visits are treated
according to the adopted procedure: Contractor was being requested via PIU/Engineer’s monitoring
report to correct the non-conformances within the deadline set for correction otherwise the non-
compliance notice shall be issued. Correction will being checked during the upcoming site visits.
C. Corrective Action Plans
38. During the reporting period construction site monitoring visits were held by Engineer ES once a
week and by PIU ES on 06.05.2017, 15.05.2017, 08.06.2017 in Davitashen-Ashtarak road link
Tender 4 (see Annex 3: Status of the previous weekly environmental site monitoring report). Dump
site monitoring visit were conducted with ADB, PIU, Engineer and Contractor ESs on 08 June 2017.
39. Corrective action plans were developed to address each non-conformance found during
monitoring (see Annex 4: Corrective action plan for Tender 4).
IV. Findings and Recommendations
40. During the joined site monitoring visited mission with ADB, PIU, Engineer and Contractor ESs
conducted on 08 June 2017 at Davitashen-Ashtarak road link the findings and recommendations
issue raised to provide mitigation measures of some open holes, finalization of traffic management
plan which was not approved by RE, coverage of all trucks, safety posters- should be bigger and in
local language, mitigation measure that should be applied to the fuel tanks.
16
16
V. Future program
N Action Time frame Responsible
1. Review and approval of the construction updated
SEMP for Tender 4
Next reporting period PIU,
Engineer,
Contractor
2. Regular monitoring visits of construction works
according to the SEMP for Tender 4
Once a month/once a
week
PIU/
Engineer
3. Review of the environmental monitoring data on dust,
noise, vibration and NO/NO2/SO2 for Tender 4
Every month /twice a
month
PIU/
Engineer
4. Contractors new staff safeguard training for Tender 4 During reporting period
2017
PIU/
Engineer,
Contractor
5. Review and addressing the GRM for Tender 4 End of every month/
every week
PIU/
Engineer
6. Other routine issues Upon the need PIU,
Engineer,
Contractor
7. Reporting on environmental safeguards Weekly, Monthly,
Quarterly, Bi-annual
PIU,
Engineer,
Contractor
17
17
VI. Annexes
A. Annex 1: List of training participants for Tender 4
18
18
B. Annex 2: List of training participants for Tender 4 conducted by Contractor
19
19
20
20
21
21
22
22
23
23
C. Annex 3: Status of the action from previous environmental monitoring report
N Action Time frame Status of the action from
previous EMR
1. Finalization of IEE for Babajanyan-Ashtarak road link for Tender 5
March 2017 implemented
2. Finalization of SEMP for Tender 4 April 2017 implemented
3. Public consultations (if needed) On July-October 2017
Conducted by Contractor
Tender 4 before
commencement of the
construction works
4. Regular monitoring visits of construction works according to the EMP/SEMP for Tender 3 & Tender 4
Once a month/once a week
Implemented for Tender 4
The contract is terminated
with Contractor for Tender 3
5. Review of the environmental monitoring data on dust, noise, water quality, vibration and NO/NO2/SO2 for Tender 3 & Tender 4
Every month /twice a month
Implemented for Tender 4
The contract is terminated
with Contractor for Tender 3
6. Review and approval of the construction updated SEMP for Tender 3 (if needed)
Next reporting period (July-December 2017)
The contract is terminated
with Contractor for Tender 3
7. Contractors staff safeguard training for Tender 3 & Tender 4
During reporting period 2017
Implemented for Tender 4
The contract is terminated
with Contractor for Tender 3
8. Review and addressing the GRM for Tender 3 & Tender 4
End of every month/ every week
Implemented for Tender 4
The contract is terminated
with Contractor for Tender 3
9. Other routine issues Upon the need implemented
10. Reporting on environmental safeguards Monthly, Quarterly Bi-annual
implemented
D. Annex 4: Corrective action plan for Tender 4
Corrective action plan for Tender 4 the construction period from May to June 2017:
N Deadline for request
Corrective action request Date of corrective action
Corrective action status
1. 6.05.2017 Unsafe practice on- site was detected 6.05.2017 Corrected
2. 6.05.2017 Copy of ERP and emergency contact list were not
available, not posted in a visible place at all work
sites.
12.05.2017 Corrected
3. 6.05.2017 Job-specific environmental and safety training for
workers was not provided
12.05.2017 Corrected
24
24
4. 12.05.2017 Exclusion barriers and at least tape fencing around
work site areas next to residential area and around
the excavated deep pits are needed.
25.05.2017 Corrected partly
5. 6.05.2017 Unauthorised people are entering the work site 25.05.2017 Corrected partly
6. 6.05.2017 Some workers were detected on-site without uniform.
Contractor is requested provide uniforms.
15.05.2017 Corrected
7. 6.05.2017 The fire extinguisher available at mobile house was
outdated and not fit for operation.
15.05.2017 Corrected
8. 15.05.2017 First aid kit was missing by sub- contractor 25.05.2017 Corrected
9. 6.05.2017 The operating machinery present on- site were not
provided with and were not using covers while
entering the public roads
25.05.2017 Corrected partly
10. 12.05.2017 Contractor is requested remove all the material from
unpermitted areas
25.05.2017 Not corrected
N Deadline for request
Corrective action request Date of corrective action
Corrective action status
1.06.2017 First aid kit was missing by sub- contractor 2.06.2017 Corrected
1.06.2017 Job-specific environmental and safety training for workers was not provided
2.06.2017 Corrected
1. 8.06.2017 Unprotected and unsafe open pits are detected
during the last visit 8.06.2017 Corrected partly
2. 8.06.2017 Many workers and drivers were detected on- site
without uniform.
15.06.2017 Corrected partly
3. 8.06.2017 Contractor is being requested provide the availability
of medical records on- site for inspection
25.06.2017 Corrected
4. 8.06.2017 Proper scaffolding and staircases for working on
structures were missing.
25.06.2017 Corrected partly
5. 15.06.2017 Contractor is being requested communicate with
community on alternative road. People should be
notified on the close of their habitual pathway.
25.06.2017 Corrected
6. 1.06.2017 Unauthorised people are entering the work site 25.06.2017 Corrected partly
7. 8.06.2017 Bins for garbage collection are on- site but are not
properly emptied.
25.06.2017 Corrected
8. 8.06.2017 Mostly the previously generated waste is removed
from the construction area but some small amount
remains on- site for more than a month.
25.06.2017 Corrected partly
9. 8.06.2017 Mud spread preventive measures are needed at the
entrances to the site.
15.06.2017 Corrected partly
10. 8.06.2017 Some of the operating machinery present on- site
were not provided with and were not using covers
while entering the public roads.
25.06.2017 Corrected partly
11. 1.06.2017 Contractor is requested obtain permission for
temporary disposal of the material
25.06.2017 Corrected
12. 25.06.2017 Very unsafe working practice has been detected on-
site. No uniform, no safety belts or other PPE.
30.06.2017 Corrected partly
25
25
Contractor should be requested stop the work and
ensure proper safety measures: belts, scaffoldings,
back protecting railings, etc
13. 1.06.2017 Exclusion barriers and at least tape fencing around
work site areas next to residential area are needed.
- Not corrected
14. 15.06.2017 Warning signs on the first entrance to the site from
Artashat HW was needed
- Not corrected
E. Annex 5: Status of the previous weekly environmental site monitoring reports for Tender 4
During the reporting period regular weeФly and monthly monitoring visits by PIU and Engineer’s ESs
and the monitoring sheets were completed. Improvement of the detected non- conformances was
checked during the next site visit. The summary of compliance/ non- conformance is presented in the
Matrix below:
Monitoring visit
Fully compliant
Partly compliant
Non- conformity
Non- conformities corrected (F/P)
Non- conformities not corrected
Week 1 May 6
24 6 2 - -
Week 2 May 12
26 4 4 3/1 1
Week 3 May 15
26 4 3 0/0 1
Week 4 May 25
20 15 1 1/4 0
Monitoring visit
Fully compliant
Partly compliant
Non- conformity
Non- conformities corrected (F/P)
Non- conformities not corrected
Week 1 June 2
18 13 5 2/1 8
Week 2 June 8
21 14 3 0/7 0
Week 3 June 16
20 13 6 1/2 3
26
26
F. Annex 6: The results of air quality, noise and vibration monitoring for Tender 4
G. Annex 7: Example of weekly environmental monitoring checklist MITIGATION COMPLIANCE &INSPECTION MONITORING Report № 6
Project: SUDIP – Tranche_2 Tender 4 Implementing Agency: PIU Scope of Inspection: Artashat Highway to Davtashen link Pk 0+000- 0+660 Date: June 8, 2017 Weather Condition: sunny Attendees Name &Position: Mrs Ruzanna Voskanyan, PIU EO Mrs Armine Yedigaryan, ADB NC Mrs, Edita Vardgesyan, EGIS HSE Monitoring visit was carried out with the presence of: Mr. David Harutyunyan, Contractor's ES
WORK SITE: General
Environmental management: environmental team, health& safety, emergency, trainings, grievance redress mechanism
Construction Activity Mitigation Measure (as per EMP/SEMP) Mitigation
Implement
ed
Yes/No/NA
Mitigation Effective*
1 to 5
Corrective
Action Request
(CAR) including
deadline for
effective CA.
Resolution Status of
previous CAR
(resolved/outstandin
g actions required)
Environmental team
All activities 1. Person in charge on environmental
management is appointed and is present
on-site.
Y 1
All activities 2. Person in charge on H&S management is
appointed and is present on-site
Y 1
Health& safety
All activities 3. Warning signs and exclusion barriers
erected around work site areas.
N 3
Warning signs were
missing at the first
entrance from Artashat
HW
Contractor is
requested
implement
fencing of the
construction
sites (at least
tape fencing)
and appoint a
flagman
Corrected partly
28
28
Exclusion barriers and
at least tape fencing
around work site areas
next to residential area
and around the
excavated deep pits
are needed.
The community public
road is not closed yet
and the regulation of
traffic is needed to
escape the dangerous
situations and
accidents
regulating the
traffic before
June 15, 2017
All activities 4. Access of strangers and outsiders is
excluded.
N 3
Contractor has
attached prohibiting
posters but they were
not sufficiently visible
Contractor installed the
metallic bars but the
measure is not
sufficiently effective
Contractor is
requested make
posters more
visible, appoint
a flagman at the
accesses to the
road and
properly fence
the area before
June 15, 2017
Non- conformance
repeated
29
29
All activities 5. Workers are provided with and are using
the uniform, applicable safety/protection
equipment for site conditions
Y 2
Almost all the staff is
provided with and is
using uniform.
For PPE see 7.
Mostly corrected
All activities 6. Unsafe practices on-site are excluded Y 2
Open pits detected
during the last visit are
now fenced.
Proper scaffolding and
staircases for working
on structures are also
provided but in some
Correct before
June 15, 2017
Mostly corrected
30
30
places are still missing.
Works on bridge 7. Safety on the bridge is ensured N 5
Protective equipment
on overpasses is
missing
Correct
immediately
All activities 8. WorФer’s health checks implemented N 4
According to
Contractor the medical
observation of
Contractor's staff was
implemented by
medical worker but the
records were not
available for inspection
Contractor is
being requested
provide the
availability of
medical records
on- site for inspection before
June 15, 2017.
31
31
All activities 9. Sanitary-hygienic conditions for workers
are provided: drinking and washing water
supply, mealtime utilities, toilets, rest
time, etc.
Y 1
The mobile house,
meal time facilities and
toilet are in place
All activities 10. First aid kit is available on-site and is
accessible to all workers.
Y 1
All activities 11. Fire extinguisher available Y 1
All activities 12. Safety of the public is ensured N 3
See 3 and 4
Emergency Response Plan
All activities 13. Person in charge on emergency is
appointed and is present on-site
Y 1
Mr Aram Asatryan and
Mr. Tigran Gharibyan
are responsible for
safety and emergency
situations were on- site
and jointed the
inspection
All activities 14. Copy of ERP and emergency contact list
are available, updated and posted in a
visible place at all work sites.
Y 1
32
32
All activities 15. Accident report maintained
N/A -
All activities 16. Damage of utilities and/or other
structures managed.
N/A -
Trainings and orientation courses
All activities 17. Workers briefed on SEMP at time of
starting employment.
Y 1
All activities 18. Workers briefed on ERP at time of
starting employment.
Y 1
All activities 19. Job-specific environmental and safety
training for workers provided
Y 1
Work site cleanliness
All activities 20. The work site kept clean from debris,
garbage, etc.
Y 1
All activities 21. Bins for garbage collection are installed N 3
Bins for garbage
collection are on- site
but are not properly
emptied.
Contractor
should organize
that the bins are
timely emptied
Correct before
June 15, 2017
All activities using
machinery
22. Tires of trucks are cleaned before
entering city roads and roads are not
dirtied by mud and other construction
related dirt
N 5
There was an
excessive amount of
mud spread on the
public roads. Mud
spread preventive
measures are needed
at the entrances to the
site
Correct before
June 15, 2017
33
33
All activities using liquid
materials
23. Spillages are managed properly N/A -
Public communication and grievance redress mechanism: environmental issues
All activities 24. Meeting with community members on
construction activities, environmental
impacts and mitigation measures held
Y 1
Pre-construction
meeting with
Davtashen community
residents took place on
April 12, 2017
All activities 25. Register of complaints maintained,
Complains observed during the last visit
addressed
Y
N/A
1
-
All activities 26. People are notified on inconveniences: N/A -
34
34
water, electricity breaks, etc.
Environmental parameters: Dust control
Earth works, material
delivery, removal of
existing pavement,
asphalt pavement
27. Trucks are operating using covers Y 2
The operating
machinery is now
mostly provided with
covers but not all the
trucks are using covers
before entering public
roads and also 2
trucks were detected
on-site which were not
provided with covers.
Contractor is
being requested
ensure that all
trucks are
provided with
and are using
covers
Correct before
June 15, 2017
28. Dust control measures are effective Y 2
Contractor is
implementing regular
watering of sites
including the
temporarily stockpiled
materials. 2 water
trucks are operating
on- site. The level of
dust emissions was
mostly not excessive.
Nevertheless
Contractor is
requested implement
also the water
sprinkling on the
excavated material in
areas close to
residential areas. Dust
preventive measures
are also needed at
material stockpiling
which are exposed to
the
wind.
Effectiveness of dust
emission control
equipment is assessed
by visual monitoring
35
35
29. Equipment and haul vehicles are fitted
with effective emission control equipment
Y 1 Effectiveness of
emission control
equipment is assessed
by visually monitoring
of the level of gas
emissions which was
not excessive.
Noise control
Operation of machinery
while earth works,
material delivery,
removal of existing
pavement, asphalt
pavement
30. Construction noise levels are acceptable
at closest sensitive receptor
Y 1 Noise levels were
exceeded, however
impacts were
temporary, no
complaints were
received and mitigation
was subsequently
implemented.
31. Equipment fitted with effective silencers Y 1 Effectiveness of
silencers is assessed
by visually monitoring
of the noise level which
was not excessive.
32. Managed by restricting operating hours Y 1
33. Managed by portable noise barrier panels N/A -
Vibration control
Operation of machinery
while removal of
existing pavement,
asphalt pavement
34. Managed by reducing time exposed to
vibration
Y 1
Erosion control:
36
36
Earth works 35. excavated slopes stabilised Y 1
Water control
Earth works 36. Sediment laden runoff is prevented
entering water course
N/A -
Water course is not
impacted by current
works
The mitigation
measures according to
SEMP shall be
implemented when
needed.
Earth works 37. Water course is kept open and is not
blocked by sediment.
N/A -
Earth works and
pavement
38. Storm water flows from construction site
are treated before entering water bodies
N/A -
There are no storm
water flows originating
from the construction
site detected on- site.
Tree planting
All activities 39. Proper maintenance of re-planted trees
and shrubs, protection of existing
vegetation and lawns.
N/A -
Construction waste management
Earth works 40. Materials and newly generated
construction waste is retained in spoil
dumps at temporary accumulation sites
agreed with Engineer.
N 3
Material is disposed in
the sites not agreed
with Engineer
Contractor is
reminded on the
responsibility not
to dispose
material or waste
outside the RoW
and escape
occupation of
private lands.
Also Contractor is
requested
remove all the
material from
unpermitted
areas or obtain
Engineer's
37
37
approval before
June 21.
Earth works 41. Remains of materials and previously
detected construction waste is hauled
from work site
Y 2
Mostly the previously
generated waste is
removed from the
construction area but
some small amount
remains on- site for
more than a month.
Contractor is
requested
remove all the
waste from the
non- permitted
areas.
Removal of existing
asphalt pavement
42. Hazardous waste is managed in
accordance with SEMP
N/A -
Earth works, demolition
of structures,
43. Non-hazardous waste (excavation
material, rocks, concrete and metallic
parts, etc.) is managed in accordance
with SEMP.
Y 2
Unsuitable waste is
being removed from
the site to the XY site
conditionally approved
by Engineer.
Contractor is
requested
provide proper
information (at
least the
application
letter) on the
progress in
obtaining YM's
waste disposal
permission
Correct before
June 15, 2017
Partly corrected
Contractor provided
to Engineer an
information that he
has applied to YM for
approval of waste
disposal site.
The YM approval is
awaited
Dismantling of utilities 44. Utilities are dismantled and managed in
accordance with SEMP
Y 1
Contractor has got
negotiations with the
owners of utilities and
agreed their removal
by owners as soon as
dismantled. The
dismantled utilities are
accumulated in regular
heaps at the
preliminary
38
38
accumulation site
Use of chemicals, fuel,
lubricants, etc. while all
activities
45. Leakages and liquid waste is managed in
accordance with SEMP.
N/A -
There were no traces
of leakages detected
on- site
Contractor’s facilities and equipment Contractor’s facility
area establishment
46. Site Management Plan for the
Contractor’s facility area is available. N/A -
Contractor didn't
establish a
construction camp. All
facilities are installed
temporarily within
RoW
Parking of machinery 47. Machinery is parked in approved area Y 1 Contractor provided
draft updated SEMP
Mobile house 48. Mobile house is installed in approved
area
Y 1 Contractor provided
draft updated SEMP
Storage of materials 49. Materials are stored in regular heaps and
in approved areas
N 3
See 40
Contractor is
requested not to
39
39
increase the area
of stockpiling and
make marking of
the occupied area
before June 8,
2017.Contractor
is being reminded
on the
responsibility not
to dispose
material outside
the RoW and
escape
occupation of
private lands
otherwise obtain
the permission of
the owner and
make update of
the CEMP.
Compliance with SEMP
50.
Contractor’s facilities are established according to SEMP
Y 2
Partly corrected
Contractor provided
draft updated SEMP
* Mitigation Effectiveness Rating Criteria
1. Very Good 21 2. Good 7 3. Fair 7 4. Poor 1 5. Very Poor 2
Attachments (Eg. Photos, Remarks, laboratory reports etc) Remarks:
40
40