environmental monitoring report...clark international airport (cia) with manila and calamba by 2025....

184
Environmental Monitoring Report Semi-annual Environmental Monitoring Report No. 1 March 2020 PHI: Malolos-Clark Railway Project Tranche 1 Volume I September 2019 March 2020 Prepared by the Project Management Office (PMO) of the Department of Transportation (DOTr) for the Government of the Republic of the Philippines and the Asian Development Bank.

Upload: others

Post on 22-Jan-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Monitoring Report

Semi-annual Environmental Monitoring Report No. 1 March 2020

PHI: Malolos-Clark Railway Project – Tranche 1 Volume I

September 2019 – March 2020

Prepared by the Project Management Office (PMO) of the Department of Transportation (DOTr)

for the Government of the Republic of the Philippines and the Asian Development Bank.

Page 2: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

CURRENCY EQUIVALENTS (as of 30 March 2020)

Currency unit – Philippine Peso (PHP)

PHP1.00 = $0.02 $1.00 = PHP50.96

ABBREVIATIONS

ADB – Asian Development Bank BMB – Biodiversity Management Bureau Brgy – Barangay CCA – Climate Change Adaptation CCC – Climate Change Commission CDC – Clark Development Corporation CEMP – Contractor’s Environmental Management Plan CENRO – City/Community Environment and Natural Resources Office CIA – Clark International Airport CIAC – Clark International Airport Corporation CLLEx – Central Luzon Link Expressway CLUP – Comprehensive Land Use Plan CMR – Compliance Monitoring Report CMVR – Compliance Monitoring and Validation Report CNO – Certificate of No Objection CPDO – City Planning and Development Office DAO – DENR Administrative Order DD / DED – Detailed Design Stage / Detailed Engineering Design Stage DENR – Department of Environment and Natural Resources DepEd – Department of Education DIA – Direct Impact Area DILG – Department of Interior and Local Government DOH – Department of Health DOST – Department of Science and Technology DOTr – Department of Transportation DPWH – Department of Public Works and Highways DSWD – Department of Social Welfare and Development DTI – Department of Trade and Industry EA – Executing Agency ECA – Environmentally Critical Area ECC – Environmental Compliance Certificate ECP – Environmentally Critical Project EGF – Environmental Guarantee Fund EHS – Environmental Health and Safety EIA – Environmental Impact Assessment EIS – Environmental Impact Statement EISR – Environmental Impact Statement Report EMB – Environmental Management Bureau EMF – Environmental Monitoring Fund EMoP – Environmental Monitoring Plan EMP – Environmental Management Plan

Page 3: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

ENRO – Environment and Natural Resources Officer EQPL – Environmental Quality Performance Level ERA – Environmental Risk Assessment ERP – Emergency Response Plan ESRD – Environment, Social and ROW Division EU – Environmental Unit FAM – Facility Administration Manual FMB – Forest Management Bureau GAF – Grievance Action Form GCR – Greater Capital Region GPS – Global Positioning System GRM – Grievance Redress Mechanism IEC – Information Education and Communication IEE – Initial Environmental Examination IFC – International Finance Corporation IIA – Indirect Impact Area IRR – Implementing Rules and Regulations ISF – Informal Settler Families JDT – JICA Design Team JICA – Japan International Cooperation Agency LGU – Local Government Unit LIAC – Local Inter-Agency Committee LRT – Light Rail Transit LRTA – Light Rail Transit Authority MCLUPZO – Manila City Comprehensive Land Use Plan and Zoning

Ordinance MCRP – Malolos Clark Railway Project MCRRS – Manila-Clark Rapid Railways System MENRO – Municipal Environment and Natural Resources Office MGB – Mines and Geosciences Bureau MMDA – Metro Manila Development Authority MMSP – Metro Manila Subway Project MMT – Multipartite Monitoring Team MNTC – Manila North Tollways Corporation MOA – Memorandum of Agreement MPDO – Municipal Planning and Development Office MRT – Metro Rail Transit NAMRIA – National Mapping and Resource Information Authority NCCA – National Commission for Culture and the Arts NCR – National Capital Region NECP – Non-Environmentally Critical Project NGO – Non-Government Organization NHA – National Housing Authority NHCP – National Historical Commission of the Philippines NLEX – North Luzon Expressway NLRC – North Luzon Railways Corporation NM – National Museum NSCR – North South Commuter Railway Project NSCR EX – North South Commuter Railway Extension Project

Page 4: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

NSRP – North South Railway Project NTP – Notice to Proceed ODA – Overseas Development Assistance OSH – Occupational Safety and Health PAF – Project Affected Families PAP – Project Affected Persons PD – Presidential Decree PEISS – Philippine Environmental Impact Statement System PEMAPS – Project Environmental Monitoring and Audit Prioritization

Scheme PENRO – Provincial Environment and Natural Resources Office PEPRMP – Programmatic Environmental Performance Report and

Management Plan PH – Public Hearing PMO – Project Management Office PNP – Philippine National Police PNR – Philippine National Railways PNSC – Philippine National Structural Code PO – People Organizations PPE – Personal Protective Equipment PRI – Philippine Railway Institute RA – Republic Act RAP – Resettlement Action Plan RHU – Rural Health Unit RIC – RAP Implementation Committee ROW – Right-of-Way SB – Sangguniang Bayan SCPW – Society for the Conservation of Philippine Wetlands Inc. SCTEX – Subic-Clark-Tarlac Expressway SDP – Social Development Plan SMR – Self-Monitoring Report SPS – Safeguard Policy Statement STPP – Sucat Thermal Power Plant SWMP – Solid Waste Management Plan TIA – Traffic Impact Assessment TMS – Train Management System TOR – Terms of Reference UNDP – United Nations Development Program UNESCO – United Nations Educational, Scientific and Cultural

Organization

Page 5: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

NOTE{S}

(i) In this report, "$" refers to United States dollars This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 6: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 7: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

i

Document Quality Information

Document Overview

Project

Sub Project

Document Name

Date

Reference

Revision History

Rev Date Modification Written by Checked by Approved by

A

B

C

Recipient List

Entity Name, Position

DOTr

DOTr

DOTr

PNR

ADB

ADB

Page 8: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

ii

Reference Documents

ADB. (2015, February). Operations Manual Section D14/BP.

ADB. (2019, July 11). Loan Agreement (Ordinary Operations). Loan Number 3796-PHI (Malolos-Clark Railway Project - Tranche 1) Between the Republic of the Philppines and Asian Development Bank.

ADB. (2019, April). Malolos-Clark Railway Project (RRP PHI 52083). Facility Administration Manual.

ADB and DOTr. (2018, November 15). Memorandum of Understanding. Proposed Multitranche Financing Facility: Malolos-Clark Railway Project: Fact-finding Mission (15- 31 October 2016). Manila.

DOTr. (2020). Environmental Impact Statement for North-South Commuter Railway (NSCR) Calamba Extension Project (Updated Report).

DOTr. (2020). Environmental Impact Statement for North-South Commuter Railway (NSCR) Clark Extension Project (Updated Report).

Page 9: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

iii

Table of Contents

Executive Summary ...................................................................................................................................... 1

I. Project Overview and General Safeguard Matters ............................................................................... 3

1 Project Overview ................................................................................................................................... 3

1.1 ADB Multi-tranche Financing Facility ............................................................................................ 7

1.2 JICA Co-Financing ........................................................................................................................ 7

2 Project Progress .................................................................................................................................... 7

2.1 Implementing Structure ............................................................................................................... 12

2.1.1 The Department of Transportation ...................................................................................... 12

2.1.2 DOTr Roles for Environmental Management Plan Implementation .................................... 12

2.2 Institutional Arrangement for the Implementation of the Environmental Management Plan ...... 13

2.2.1 DOTr Railway Office............................................................................................................ 14

2.2.2 NSCR Clark and Calamba Extension Project Management Office .................................... 15

2.2.3 Environment, Social, ROW and Legal Division ................................................................... 15

2.2.4 Health, Safety and Environment Officer and Pollution Control Officer ............................... 16

2.2.5 Health, Safety and Environment Committee ....................................................................... 16

2.2.6 Multi-partite Monitoring Team ............................................................................................. 17

2.3 Contractor .................................................................................................................................... 19

2.4 General Consultant ..................................................................................................................... 20

2.5 Third Party Monitor - External Environmental Monitoring Agency .............................................. 22

3 Information Disclosure ........................................................................................................................ 22

4 Reporting Requirements for Monitoring .............................................................................................. 23

5 Updated EMPs, Incorporation of Safeguards Requirements into Project Contractual Arrangements 25

II. Environmental Performance Monitoring .............................................................................................. 27

1 Status of Compliance with ECC Conditions ........................................................................................ 27

1.1 NSCR Clark Extension ................................................................................................................ 27

1.2 NSCR Calamba Extension .......................................................................................................... 33

2 Status of EMP Implementation (Mitigation Measures) ........................................................................ 38

3 Health and Safety ................................................................................................................................ 40

4 Environment Effect Monitoring ............................................................................................................ 40

5 Compliance with Safeguards Related Project Covenants .................................................................. 41

6 Compliance with ADB and DOTr Inception Review Mission Requirements ....................................... 43

7 Public consultation, Information Disclosure, Capability Building ........................................................ 43

8 Grievance Redress Mechanism .......................................................................................................... 49

III. Conclusion ........................................................................................................................................... 50

IV. Appendices.......................................................................................................................................... 53

Page 10: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

iv

List of Tables

Table 1: Snapshot of Project Progress ......................................................................................................... 7

Table 2: List of Contract Packages ............................................................................................................... 8

Table 3: Roles and Responsibilities for the EMP Implementation .............................................................. 13

Table 4: Composition of the NSCR Clark and Calamba Extension PMO (Provisional).............................. 15

Table 5: Types of Monitoring Reports ......................................................................................................... 24

Table 6: ECC Compliance Matrix for the NSCR Clark Extension ............................................................... 27

Table 7: ECC Compliance Matrix for the NSCR Calamba Extension ......................................................... 33

Table 8: Compliance with EMP Requirements (Environmental Performance) ........................................... 38

Table 9: Health and Safety Issues .............................................................................................................. 40

Table 10: Environment Effect Monitoring Results ....................................................................................... 40

Table 11: Compliance with Safeguards Related Project Covenants .......................................................... 41

Table 12: Compliance with ADB Review Mission Requirements ................................................................ 43

Table 13: Public Consultations/Stakeholders Consultation Meetings ........................................................ 43

Table 14: Outline of the First Round of Stakeholder Consultation Meetings During Detailed Design........ 45

Table 15: Trainings Attended by DOTr Staff ............................................................................................... 49

Table 16: Grievances Received by the Projects of 19 December 2019 ..................................................... 49

List of Figures

Figure 1: North South Commuter Railway Clark Extension Project Alignment ............................................ 4

Figure 2: North South Commuter Railway Calamba Extension Project Alignment ...................................... 6

Figure 3: NSCR Alignment Map showing Contract Packages .................................................................... 11

Figure 4: Simplified Institutional Plan for Implementing the EMP ............................................................... 13

Appendices

Appendix A: Consents/Permits (Environmental Compliance Certificates)

Appendix B: Environmental Management Plan

Appendix C: External Monitoring Agent Terms of Reference

Appendix D: Directory of Project Staff for the Implementation of the Environmental Compliance Requirements

Appendix E: General Consideration for the SDP (N2)

Appendix F: Compliance Monitoring Reports (Submitted through DENR website https://online.emb.gov.ph/cmr/)

Appendix G: Waste Management Program (N2)

Page 11: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

v

Appendix H: Certificates of No Objection

Appendix I: Traffic Impact Assessment (N2)

Appendix J: NSCR EX PMO Organizational Chart

Appendix K: General Consideration for the SDP (SC)

Appendix L: Waste Management Program (SC)

Appendix M: Traffic Impact Assessment (SC)

Appendix N: Summary of Grievances Received

Appendix O: Monitoring Manual Outline

Appendix P: Summary Registers for Project Supervision

Page 12: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

vi

(This page is intentionally left blank)

Page 13: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

1

Executive Summary

1. This report is the 1st semi-annual report on environmental safeguard compliance for the North South Commuter Railway Clark Extension (NSCR Clark Extension) Project also known as Malolos-Clark Railway Project (MCRP; Loan 3796-PHI: Malolos-Clark Railway Project) covering the period from October 2019 to March 2020.

2. The NSCR Clark Extension Project is part of the government’s flagship North-South Commuter Railway (NSCR) Project, a 167 km suburban railway network connecting New Clark City (NCC), Clark and Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km section Malolos–Solis–Tutuban, which began construction in early 2019 and is expected to start operation in 2022, (ii) the 71-km NSCR Clark Extension Project (the proposed Project), which was slated to commence construction in 2020 and start partial operation in 2022, and (iii) the 58.6-km North South Commuter Railway Calamba Extension (NSCR Calamba Extension) Project also known as South Commuter Railway Project from Blumentritt to Calamba, which is expected to commence construction in 2021 and start operation by 2024. The extension to NCC is expected to commence construction by 2022 and start operation by 2025. An extension for long-haul services to Batangas and Southern Luzon is planned beyond 2025 (ADB, 2019).

3. The NSCR Clark Extension Project has been classified as Category A for Environment as per the Asian Development Bank (ADB) Safeguard Policy Statement (SPS, 2009). An Environmental Impact Statement (EIS) had been prepared and submitted to the Department of Environment and Natural Resource-Environmental Management Bureau (DENR-EMB) following the requirements of both the Philippine Environmental Impact Statement System (PEISS) and ADB Safeguard Policy Statement. The Philippine Environmental Impact Statement System was established under Presidential Decree (PD) No. 1586 and Presidential Proclamation No. 2146 defining the scope of the EIS System.

4. The NSCR Clark Extension Project will be financed in part by ADB through a Multi-tranche Financing Facility (MFF) with three tranches adopting the time-slicing approach for large-scale stand-alone projects. Each tranche will finance slices of a group of contracts for civil works or consulting services. The amount of each tranche will be requested according to the disbursement progress and projection. The Loan Agreement between ADB and the Government of the Philippines was signed on 11 July 2019 and became effective on 26 September 2019.

5. The NSCR Clark Extension Project will be co-financed by Japan International Cooperation Agency (JICA) on a parallel collaborative basis. The JICA loan was approved in December 2018 and signed on 21 January 2019. ADB is financing civil works (i.e., viaducts, bridges, stations, tunnels, and depot buildings), while JICA is financing the core system (i.e., tracks, depot equipment, power supply and electrification, signaling and telecommunication systems, and procurement of rolling stock), and consulting services.

6. Consulting contracts have been awarded to support DOTr in project implementation, as well as institutional capacity building in 2019. However, construction contracts have yet to be awarded and are anticipated to be done within the first quarter of 2020.

7. The Environmental Compliance Certificate (ECC) was issued on 13 August 2018. However, there were changes on the project scope from feasibility study (FS) to detailed design (DD) stage that required supplementary documentation which took additional six months to complete. The additional surveys for wet season were undertaken from June–July 2018, while additional surveys based on detailed design were conducted from December 2018–June 2019 as part of the documentation (DOTr, 2020). An updated EIS report, which incorporates the changes in the DD stage has been submitted to the EMB on 16 January 2020. A request for amendment of ECC (ECC-CO-1807-0017) dated 20 February 2020 (with summary of changes from Feasibility Study EIS to Detailed Design EIS and other relevant annexes) was received by the Environmental Management Bureau Central Office on 4 March 2020. Among the amendments

Page 14: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

2

requested is the change of Project name from Malolos-Clark Railway Project (MCRP) to North South Commuter Railway Clark Extension (NSCR Clark Extension) Project.

8. Pre-construction activities such as continuing stakeholder consultation meetings (SCMs), Information, Education and Communication (IEC) campaigns, and tree inventories related to the preparation of the Resettlement Action Plan (RAP) and land acquisition are being conducted.

9. Meanwhile, compliance with pre-construction requirements are being undertaken by DOTr.

Page 15: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

3

I. Project Overview and General Safeguard Matters

1 Project Overview

10. The proposed NSCR Extension Project will include two sections of new railway services namely: 1) NSCR Clark Extension (Malolos-Clark); and 2) NSCR Calamba Extension (Solis-Calamba). The NSCR Extension Project will connect to the NSCR Project, a 37-km section of railway from Tutuban to Malolos that is financed by JICA and is currently under construction. The ADB loan includes contract packages N-01, N-02, N-03, N-04 and N-05 of the Clark Extension and S-01 of the Calamba Extension. The description of each contract package is given in Table 2. The Department of Transportation (DOTr) is the Executing Agency (EA) with Philippine National Railways (PNR), a government-owned railway company under DOTr, as Co-End-user.

11. The NSCR Clark Extension Project alignment (Figure 1) traverses the municipalities/cities of Malolos and Calumpit in the Province of Bulacan; Apalit, Minalin, Sto. Tomas, San Fernando, Angeles and Mabalacat in the Province of Pampanga; and Bamban and Capas in Province of Tarlac.

12. The NSCR Clark Extension Project ll be developed in two phases. The first phase, which spans from Malolos to Clark and CIA, will provide a high standard suburban commuter rail from Malolos to Clark with the 51.4-km railway line commencing at Malolos, passing through Calumpit, Apalit, Minalin, Santo Tomas, San Fernando, Angeles, and Mabalacat, and ending at the CIA Complex. The first section will include a 1.5-km access rail to the Mabalacat depot. The second phase will cover the extended section of 18.1 km from Clark to NCC traversing Capas and Bamban in the Province of Tarlac. With a total length of 71 km, the Project alignment is comprised of 59.8-km elevated viaduct, 2.4-km at-grade embankment, and 8.8-km underground segments.

13. From Malolos to CIA, DOTr will primarily utilize the existing Right-of-Way (ROW) of PNR. This area is intended for railway infrastructure. From Clark to Capas, the alignment will cross privately owned land in Bamban and the existing arterial road of Bases Conservation and Development Authority (BCDA) in Capas. For the Mabalacat Depot access segment, DOTr will utilize the BCDA properties within the Clark Special Economic Zone (CSEZ).

14. The Mabalacat Depot is located in a 0.33 km2 (33 ha) lot area between Gil Puyat and Prince Balagtas Avenues within Clark Development Corporation (CDC) land near CIA.

Page 16: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

4

Source: (DOTr, 2020)

Figure 1: North South Commuter Railway Clark Extension Project Alignment

Page 17: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

5

15. The second section of the NSCR Extension is the North South Commuter Railway Calamba Extension (NSCR Calamba Extension) Project also known as North South Railway Project–South Line Commuter (NSRP-SC). The NSCR Calamba Extension Project alignment traverses the cities of Manila, Makati, Taguig, Parañaque, and Muntinlupa in the National Capital Region (NCR); and San Pedro, Biñan, Santa Rosa, Cabuyao, and Calamba in the Province of Laguna (Figure 2).

16. The Calamba Extension is divided into two phases. The first phase will extend the NSCR railway line to the south from a junction point between Solis Station and Tutuban Station to a newly constructed station in Blumentritt in Sta. Cruz District of the City of Manila. It will be comprised of around 2-km elevated double track alignment. Blumentritt Station is envisioned to be an important transfer station for passengers, who will be able to change trains and continue their journey with Light Rail Transit (LRT) Line 1, which runs North-South through Manila City and connects as well to LRT Line 2 and the MRT-3.

17. The second phase of NSCR Calamba Extension Project is from Blumentritt Station to Calamba Station. The Blumentritt to Calamba Section will utilize the existing ROW of PNR from Solis Station in the City of Manila to Calamba Station in the City of Calamba, Province of Laguna. However, due to the ongoing NLEx/SLEx Connector Road Project of the Department of Public Works and Highways (DPWH), which was designed to utilize the PNR ROW from Sta. Mesa to Solis, Manila, the Project will traverse private lands adjacent to the PNR ROW from Solis Station to Sta. Mesa Station. DOTr will exercise the power of eminent domain of the government for the acquisition of the private lands in this section, which has an estimated length of 8.0 km.

18. The total length of the NSCR Calamba Extension Project will be approximately 58.6 km from Solis Station to Calamba Station including access going to the Calamba Depot. Based on the preliminary design, 55.6 km section will be elevated main alignment; and 3.0 km of the alignment will be at grade/embankment depot access. The line will have 19 stations, 3 of which are at grade due to site constraints.

Page 18: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

6

Source: (DOTr, 2020)

Figure 2: North South Commuter Railway Calamba Extension Project Alignment

Page 19: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

7

1.1 ADB Multi-tranche Financing Facility

19. The MFF is a flexible financing instrument extended by ADB to borrowers. It allows ADB to provide assistance programmatically by harmonizing the provision of financing with project readiness and the long-term needs of a client. The MFF promotes long-term partnerships between ADB and its clients and provides opportunities for constructive dialogue on physical investments as well as nonphysical (thematic and sector) interventions. The MFF provides critical mass, predictability, and continuity to clients (ADB, 2015).

20. The NSCR Clark Extension Project will be financed by an MFF with three tranches adopting the time-slicing approach for large-scale stand-alone projects. At the time of MFF processing, the design, procurement, and safeguards have been appraised for the entire MFF. Each tranche will finance slices of a group of contracts per the indicative tranche schedule, and the amount for each tranche will be requested per the disbursement progress and projection (DOTr, 2020).

21. The Government of the Republic of the Philippines has requested an MFF in the amount of up to $2.75 billion from the ordinary capital resources of ADB to help finance the civil works (i.e., viaducts, bridges, stations, tunnels, and depot buildings) of the Project. The MFF consists of three tranches, subject to the government’s submission of related periodic financing requests, execution of the related loan agreement for each tranche, and fulfillment of terms and conditions and undertakings in the framework financing agreement. On 11 July 2019, ADB and the Republic of the Philippines signed the loan agreement, which became effective on 26 September 2019.

1.2 JICA Co-Financing

22. The Project will be co-financed by JICA on a parallel collaborative basis. The JICA loan was approved in December 2018 and signed on 21 January 2019.

23. JICA is financing the core system (i.e., tracks, depot equipment, power supply and electrification, signaling and telecommunication systems, and procurement of rolling stock) and consulting services.

2 Project Progress

24. The loan for the Project was signed on 11 July 2019 by the representatives of the Government of the Republic of the Philippines and ADB and became effective on 26 September 2019. Between this period, consultancy contracts were awarded as shown in Table 1 below.

Table 1: Snapshot of Project Progress

Project Number and Title:

52083-002: Malolos-Clark Railway Project (PFR 1)1

Loan Number and Title Loan 3796-PHI: Malolos-Clark Railway Project - Tranche 1

Loan Agreement Signing 11 July 2019

Loan Effectivity 26 September 2019

1 ADB.2015. Operations Manual Section D14 Bank Policies. Manila.

Page 20: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

8

Safeguards Category Environment A

Reporting period: March 2020

Last report date: Not Applicable, first semi-annual environmental monitoring report (SEMR) submission

Key sub-project activities since last report:

This is the first SEMR since loan effectivity. • Contract awards:

a) General Consultant – Greater Capital Railway Consortium (GCR) awarded the contract on 2 September 2019.

b) Civil Works Contractors – No awards made as of the reporting period c) Rolling Stock Provider – No awards made as of the reporting period d) Strengthening of Institutional Capacity - No awards made as of the

reporting period • Progress of Work (% physical completion): No construction activities yet • Status of Safeguard Approvals/Permits/Consents: Environmental

Compliance Certificate (ECC-CO-1807-0017) issued on 13 August 2018 (Refer to Appendix A)

Report prepared by: Project Management Office, NSCR Extension Project Department of Transportation (DOTr) Office of the Undersecretary for Railways

Source: Department of Transportation, 2020

25. The Project has been further divided into six contract packages2. The details of projects and sub-projects (construction packages) and their locations are presented in Table 2 and Figure 3 below:

Table 2: List of Contract Packages3

Contract Package

Contract Package Location

Station Number and Section

(Length) Civil Works Description

Contract Type Status as of this Reporting Period

NSCR Clark Extension (N2)

CP N-01 Calumpit and Malolos in Bulacan, and Apalit and Minalin in Pampanga

Civil 1

Station: 2

34.749 km –51.679 km

(L = 16 km 930 m)

Building and Civil Engineering Works for approximately 17 km of Railway viaduct including four balanced cantilever bridges and two elevated steel framed station buildings.

ADB SBD Procurement of Works (FIDIC MDB Harmonized Construction Contract) *1

Contract not yet awarded.

2 Appendix A: Procurement Plan of the Facility Administration Manual, Project Number: 52093-001, 2019 3 Contract packages N-01, N-02, N-03, N-04, N-05 and S-01 are covered by Loan Agreement No. 3796-PHI.

Page 21: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

9

Contract Package

Contract Package Location

Station Number and Section

(Length) Civil Works Description

Contract Type Status as of this Reporting Period

CP N-02 San Fernando and Minalin, Pampanga

Civil 2

Station: 1

51.679 – 67.449 km

(L = 15 km 770 m)

Building and Civil Engineering Works for approximately 16 km of Railway viaduct, including one extra-dosed suspension bridge and one balanced cantilever bridge, and one elevated station building.

ADB SBD Procurement of Works (FIDIC MDB Harmonized Construction Contract) *1

Contract not yet awarded.

CP N-03 Angeles, Clark, San Fernando, and Mabalacat, Pampanga

Civil 3

Station: 2

67.449 – 83.170 km

(L = 15 km 721 m)

Building and Civil Engineering Works for approximately 16 km of Railway viaduct, including one extra-dosed suspension bridge and one balanced cantilever bridge. Diversions and training are required for an approximately 1 km stretch of the Sapang Balen river. Two elevated steel framed station buildings, and approximately 0.6 km of depot access line are also included.

ADB SBD Procurement of Works (FIDIC MDB Harmonized Construction Contract) *1

Contract not yet awarded.

CP N-04 CIAC/BCDA and Mabalacat, Pampanga

Underground railway and approach to CIA + Access railway to Mabalacat Depot

Station: 1

(L = 3 km 22 m)

Building and Civil Engineering Works for approximately 3 km of Railway track comprising of at-grate, u-shaped semi-underground structure and open-cut tunnel, including the construction of an underground station serving CIA, and approximately 0.5 km of depot access line.

ADB SBD Procurement of Works (FIDIC MDB Harmonized Construction Contract) *1

Contract not yet awarded.

Page 22: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

10

Contract Package

Contract Package Location

Station Number and Section

(Length) Civil Works Description

Contract Type Status as of this Reporting Period

CP N-05 CIAC/BCDA and Mabalacat, Pampanga

Mabalacat Depot Civil Engineering and Building works for the Mabalacat Depot, covering an area of approximately 33 ha., including construction of the Operations Control Center, Stabling Yard, Workshops, Training Center and other Ancillary Buildings. Approximately 0.4 km of depot access line is also included.

ADB SBD Procurement of Works (FIDIC MDB Harmonized Construction Contract) *1

Contract not yet awarded.

NSCR Calamba Extension (SC)

CP S-01 Manila, NCR

Civil 1

Station: 1

1.329 km – 2.405 km

(L = 1 km 076 m)

Building and Civil Engineering Works for five balanced cantilever bridges approximately 1.1 km of Railway viaduct including two steel box girder bridges and one elevated steel framed station building.

ADB SBD Procurement of Works (FIDIC MDB Harmonized Construction Contract) *1

Contract not yet awarded.

(*1) The Standard Bidding Document (SBD) for the Procurement of Works (SBD Works) issued by the Asian Development Bank (ADB) dated June 2018. The General Conditions of ADB’ SBD Works shall be the Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer, Multilateral Development Bank Harmonized Edition, prepared by the FIDIC (FIDIC MDB Harmonized Construction Contract), Edition June 2010 (FIDIC Pink Book).

Notes for Information Only: The Standard Bidding Document (SBD) for Procurement of Electrical and Mechanical Plant and for Building and Engineering Works, designed by the Contractor-Trial Version (SBD Design Build) have been prepared and issued by Japan International Cooperation Agency (JICA) in July 2015. The General Conditions of JICA’ SBD Design Build (standard GC) are prepared based on Conditions of Contract for Plant and Design Build prepared by FIDIC, Edition FIDIC 1999 (FIDIC Yellow Book).

Source: (ADB, 2019)

Page 23: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

11

Figure 3: NSCR Alignment Map showing Contract Packages

26. The main thrust of the Environmental Management Plan (EMP, Appendix B) is to ensure that environmental, socio-economic, political, and public health issues within all contract packages are properly

Page 24: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

12

addressed in a timely manner. It also provides a necessary mechanism that will strengthen the organizational relationship of DOTr with the host communities, concerned government agencies, and other stakeholders.

27. To ensure compliance with the EMP during the detailed design phase, DOTr has initiated addressing several requirements of the ECC4 issued by the DENR-EMB, which includes setting up the Environmental Unit (EU), the Multi-partite Management Team (MMT), the Environmental Guarantee Fund (EGF) and the Environmental Monitoring Fund (EMF).

28. The Project Management Office of the NSCR Extension Project (NSCR EX PMO) have proposed to the Department of Budget and Management (DBM) allocated positions for environmental concerns, which may be dedicated to the establishment of the EU. The EU has been established in 23 December 2019. The NSCR EX PMO has since provided 7 staff members to manage the environmental management requirements of the Project and has provided the required trainings to 3 staff members to serve as Pollution Control Officer(s) (PCOs) for the Project.

2.1 Implementing Structure

2.1.1 The Department of Transportation

29. DOTr is the primary policy, planning, programming, coordinating, implementing, and administrative entity of the executive branch of the Philippine government on the promotion, development, and regulation of a dependable and coordinated network of transportation system, as well as in the fast, safe, efficient, and reliable transportation.

30. As the EA of the NSCR Clark Extension Project, DOTr will supervise and coordinate the implementation of all activities, monitor compliance with the environmental impact statement (EIS) which covers the EMP and environmental monitoring plan (EMoP), secure sufficient funding for all resettlement activities, allocate resources in a timely manner, set target outputs with corresponding timelines, monitor progress, consolidate reports from all sources, and document gaps and its appropriate solutions. The general roles of DOTr as the EA will be largely carried out by a special office created for this purpose, or the NSCR EX PMO. For the Project, the Undersecretary for Railways will directly supervise the NSCR EX PMO and will make critical decisions regarding the implementation of the Project.

2.1.2 DOTr Roles for Environmental Management Plan Implementation

31. DOTr, as the EA, is responsible for providing overall policies and guidance concerning the implementation of the Project. It is also responsible in monitoring the compliance of the Project with the conditions of the ECC, as well as ADB Safeguard Policy Statement, JICA Environmental Policy (2015) and JICA Guidelines for Environmental and Social Considerations (2010) requirements. Further, DOTr ensures that all the provisions necessary for the implementation of the EMP and the EMoP—including budgets and agreements with other concerned national and local government agencies—are included in all contracts in compliance with ADB Safeguard Policy Statement and JICA Environmental Policy and JICA Environmental Guidelines.

4 Document issued by the DENR/EMB after a positive review of an EIS for the Project ECC application, certifying that based on the representations of the proponent, the proposed Project or undertaking has complied with all the requirements of the EIS System and has committed to implement its approved Environmental Management Plan to address the environmental impacts (EMB Memorandum Circular 005, July 2014, Revised Guidelines for Coverage Screening and Standardized Requirements under the Philippine EIS System).

Page 25: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

13

2.2 Institutional Arrangement for the Implementation of the Environmental Management Plan

32. The organizational structure for the EMP implementation constitutes the NSCR EX PMO and its Environment, Social, ROW and Legal Division (PMO-ESRL); the Health, Safety and Environment Committee (HSEC); the General Consultant (GC), the Contractor(s) (including sub-contractors); and the Multipartite Monitoring Team (MMT) as key entities for its effective implementation. Figure 4 presents the simplified institutional chart for the EMP implementation, showing the relationship among the entities.

Source: (DOTr, 2020)

Figure 4: Simplified Institutional Plan for Implementing the EMP

33. DOTr created a new office to serve as the NSCR EX PMO. Under the NSCR EX PMO, the HSEC will be established to implement the EMP during pre-construction and construction phases of the Project. The Contractor is bound by a contract to implement the EMP during construction. The environmental compliance monitoring will be undertaken by the MMT, which monitors Contractor and NSCR EX PMO performance with respect to the ECC conditions, the EMP and the EMoP, evaluating compliance with the guidelines of DAO 2003-305, DAO 2017-156, ADB Safeguard Policy Statement, JICA Environmental Policy and JICA Environmental Guidelines.

34. Main roles and responsibilities of the EMP implementing entities (Table 3) are to ensure compliance with the EMP, the EMoP and other conditions stipulated under the ECC, and manage grievances, if any, arise during construction.

Table 3: Roles and Responsibilities for the EMP Implementation

5 DENR Administrative Order No. 30, Series of 2003: Implementing rules and regulations for the Philippine Environmental Impact Statement System (PEISS) of Presidential Decree (PD) No. 1586

6 DENR Administrative Order No. 15, Series of 2017: Guidelines on public participation under the PEISS

Page 26: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

14

Entity Responsibility

DO

Tr

Ra

ilw

ay

off

ice

NS

CR

EX

PM

O (

Pro

jec

t

Ma

na

ge

men

t O

ffic

e)

PM

O-E

SR

L (

En

vir

on

me

nt

So

cia

l, R

OW

div

isio

n a

nd

Le

ga

l D

ivis

ion

)

HS

EC

He

alt

h,

Safe

ty a

nd

En

vir

on

men

t C

om

mit

tee

)/P

CO

(Po

llu

tio

n C

on

tro

l O

ffic

er)

MM

T (

Mu

ltip

art

ite

Mo

nit

ori

ng

Te

am

)

Co

ntr

ac

tor

GC

(G

en

era

l C

on

su

lta

nt)

Establish the NSCR EX PMO ◎ 〇

Establish the PMO-ESRL ◎ 〇

Appoint the Health, Safety and Environment Officer (HSEO) and Pollution Control Officer (PCO)

◎ 〇

Establish the MMT ◎ 〇 〇

Establish the EGF and the EMF ◎ 〇 〇 〇 〇

Secure fund for the EMP implementation (for the operation of the EGF, the EMF and the PMO-ESRL)

◎ 〇 〇

Ensure the Project's compliance to the ECC, the EMP and the EMoP

◎ 〇 〇 〇 〇

Ensure the Project's compliance to JICA and ADB guidelines

◎ 〇 〇 〇

Handle grievances ◎ 〇 〇 〇 〇

Implement mitigation measures in compliance with the EMP

〇 ◎ 〇

Implement the EMoP in compliance with the EMP

〇 ◎ 〇

Monitor and assess the effectiveness of mitigation measures

◎ 〇 〇 〇 〇

Revise the EMP as necessary ◎ 〇 〇 〇

Audit compliance ◎

Note: ◎ = leading party, 〇 = assisting party

Source: (DOTr, 2020)

35. In addition, an External Monitoring Agent (EMA) shall be engaged to report directly to the NSCR EX PMO and shall provide independent periodic reviews and assessments of RAP and EMP implementation performance of the General Consultant, and the Contractors. The process of engagement is being undertaken by the General Consultant and the EMA is anticipated to be contractually engaged within the next reporting period. The Terms of Reference for the EMA forms part of this report as Appendix C.

2.2.1 DOTr Railway Office

36. The DOTr Railway Office oversees the overall process and progress of each division, office, and other entities working on the Project in compliance with the Philippine laws and regulations, ADB Safeguard Policy Statement, JICA Environmental Policy, and JICA Environmental Guidelines; leads the decision-

Page 27: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

15

making and establishment of the NSCR EX PMO, PMO-ESRL, MMT and its EMF and EGF; and secures availability of funds for EMP implementation.

2.2.2 NSCR Clark and Calamba Extension Project Management Office

37. The NSCR Clark and Calamba Extension PMO (NSCR EX PMO) is established as the representative of DOTr and PNR for all activities pertaining to the planning, design review, and implementation of the Project.

38. The Project Director, the Co-Project Director, and the Management Director are responsible for the decision-making, planning, and the implementation of the overall Project activities, while the Project Manager and the Deputy Project Manager are in charge of the management of the Project (Table 4).

Table 4: Composition of the NSCR Clark and Calamba Extension PMO (Provisional)

No. Position Member

1 Oversight functions

Project Director: DOTr Undersecretary for Railways Co-Project director: PNR General Manager

2 Manager Project Manager: Representative from DOTr Deputy Project Manager: Representative from DOTr

3 Division (a total of 450 staff)

Six divisions headed by division chiefs, supervised by the Management. 1) Civil Works Division 2) System Division 3) Rolling Stock Division (RS Division) 4) Engineering Support Division (ES Division) 5) Environment Social, ROW division and Legal Division (PMO-ESRL) 6) Administration and Support Division (PCS Division)

Source: (DOTr, 2020)

2.2.3 Environment, Social, ROW and Legal Division

39. The PMO-ESRL will be established under the NSCR EX PMO that will be initially staffed with approximately 130 officers including HSEOs, environmental engineers, foresters, project development officers, community development officers, attorneys, other specialists, and office staff who will provide the necessary guidance and technical assistance in order to fulfill the ECC conditions and the activities laid out in the EMP and the EMoP. The Environmental Unit (EU) is an organic unit under the PMO-ESRL. The EU is principally responsible for overseeing the Project’s compliance requirements with the PEISS, ADB SPS 2009 and JICA Environment Policy, and Environmental and Social Considerations Guidelines. The other units under the PMO-ESRL have defined roles and responsibilities as well.

40. The EU, the PMO-ESRL and the NSCR EX PMO in general, whilst already organized is still to be completely provided with staff to an adequate number to be able to carry out its mandated functions.

41. The EU of the PMO-ESRL is responsible for the following:

• Prepares the Environment Protection Clauses, which are based on the EMP and the ECC of the Project and include these clauses as well as other environment-related provisions in the bidding documents.

• Ensures that all engineering interventions and conditions prescribed in the approved EMP, RAP, and ECC and all requirements of ADB Safeguard Policy Statement, JICA Environmental Policy, and JICA Environmental Guidelines are implemented accordingly during pre-construction/construction and operation.

• Supervises the Contractor in the conduct of self-monitoring activities. • Reports periodically the status of compliance to the DENR-EMB following the prescribed formats.

Page 28: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

16

• Reports periodically the status of compliance with the JICA Environmental Policy, JICA Environmental Guidelines, and the ADB Safeguard Policy Statement to JICA and ADB.

2.2.4 Health, Safety and Environment Officer and Pollution Control Officer

42. The HSEO provides the appropriate actions on complaints brought to the PMO-ESRL for resolution. Further, the HSEO closely coordinates with the Health, Safety, and Environment Unit of the Contractor concerning mutual concerns during construction. The HSEO can take the role of the PCO, a technical expert in pollution control and environmental management duly accredited by EMB regional offices. Among others, the HSEO and PCO are responsible for the following:

• PCO to guide PMO-ESRL engineers and technical personnel in the implementation of the ECC conditions and other activities during pre-construction/construction and operation which are laid out in the EMP and the EMoP—both consisting of integral parts of the EIS—and requirements of JICA Environmental Policy, JICA Environmental Guidelines, and ADB Safeguard Policy Statement;

• PCO to prepare environment monitoring reports including CMRs and report them to the DENR-EMB, JICA, and ADB;

• PCO to prepare and include in the bidding documents the Environmental Protection Clauses; • PCO to discuss with bidders the Environmental Protection Clauses for their consideration and

compliance; • HSEO to handle grievances/complaints forwarded from the grievance team and respond to them

within 15 days of receipt; and • HSEO and PCO to represent the NSCR EX PMO for the HSEC.

2.2.5 Health, Safety and Environment Committee

43. The HSEC will be established under the NSCR EX PMO to implement the EMP during pre-construction and construction phases of the Project. The HSEC will be composed of a DOTr Authorized Representative who will sit as the Chairperson; and authorized representatives of the General Consultant (GC) and Contractors. The HSEC will be limited only for the duration of the NSCR EX Project. A directory of project staff for the implementation of environmental compliance requirements including but not limited to the HSEC is provided as part of this report (Appendix D). This directory will be updated from time to time every reporting period.

44. As stated in the DD EIS, the HSEC’s role and responsibilities are as follows:

• Holds weekly grievances/concerns meetings to discuss issues and complaints and resolve them. • Responds to forwarded grievances and complaints within 15 days. In case that they are not

resolved by the committee, it forwards the cases to the MMT or DOTr's board. If the MMT cannot also resolve the critical issue, it will be referred to the DENR-EMB.

• Monitors performance of the Contractor in the EMP implementation. • Identifies sources of pollution issues. • Monitors the effectiveness of mitigating or enhancement measures • Sets forth solutions or alternatives to enhance the EMP based on monitoring results. • Coordinates with the DENR-EMB and other relevant oversight agencies and stakeholders. • Implements regular reporting on compliance with the ECC and its conditions. • Submits self-monitoring reports (SMR), prepared and signed by the accredited works contractor’s

PCO, detailing the status of compliance with the ECC and other environmental regulations to the DENR-EMB, JICA and ADB in a quarterly basis.

45. The HSEC shall meet monthly (Monthly Coordination/Interface Meeting) or as often as necessary depending on the condition prevailing in the work areas. These meetings will be properly documented by the GC, assisted by the Contractors’ HSE Officers. The minutes of meetings shall be concurred by the

Page 29: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

17

Contractors and approved by the HSEC Chairperson for submission to the DOTr Railways Office. Specifically, the HSEC shall:

a) Assist the DOTr Railway Office in the establishment of the EGF and EMF; b) Ensure the Project’s compliance with the ECC, the EMP and the EMoP; c) Ensure the Project’s compliance with the ADB SPS 2009, and JICA Environment Policy, and

Environmental and Social Considerations Guidelines; d) Handle grievances; e) Implement mitigation measures in compliance with the EMP; f) Monitor and assess the effectiveness of mitigation measures; and revise the EMP as necessary.

46. The HSEC and the contractor will implement the EMP in coordination with the following entities:

• The Environmental Management Bureau (EMB)-Central Office (CO) of the Department of Environment and Natural Resources (DENR)

• The EMB-Region 3 of the DENR • The Forest Management Bureau (FMB) and the Biodiversity Management Bureau

(BMB) of the DENR • The DOTr's attached agencies – the Philippine National Railway (PNR) • Other relevant national government agencies (NGAs) – the Bases Conversion

Development Authority (BCDA), the Clark International Airport Corporation (CIAC), the National Commission for Culture and Arts (NCCA), the National Historical Commission of the Philippines (NHCP), the National Museum (NM), the National Commission on Indigenous Peoples (NCIP), the Department of Public Works and Highways (DPWH) and the National Housing Authority (NHA)

• Local government units (LGUs) of Malolos, Calumpit, Apalit, Minalin, Sto. Tomas, San Fernando, Angeles, Mabalacat, Bamban and Capas

• The MMT

47. As of this reporting period, the HSEC has yet to be formally convened to officially operate before/once the contractor is onboard.

2.2.6 Multi-partite Monitoring Team

48. The MMT is an independent third-party entity that will be established after the issuance of the ECC to encourage participation of the Project’s various local stakeholders and monitor the Project’s compliance with the ECC conditions as well as the EMP and EMoP during pre-construction, construction, and operation. The MMT’s compliance validation monitoring reports (CMVRs) as prescribed in the Revised Procedural Manual of DAO 03-30 will be submitted to the DENR-EMB, and will be reported in the environmental monitoring reports required by ADB and JICA.

49. The formation of the MMT is initiated by the NSCR EX PMO through a memorandum of agreement (MOA) between the EMB-CO and the NSCR EX PMO in conformity with identified MMT members. According to DAO No. 2017-15, the MMT is composed of representatives of relevant local stakeholders. As such, the EMB and DOTr, as principal Project parties, will no longer be members of the MMT. Instead, the EMB will provide oversight guidance to the MMT and factor in its reports and recommendations for its impact and compliance evaluation. Further, DAO 2017-15 requires proponents such as DOTr and/or PNR to provide fund for the EMF or MMT activities based on the annual work and financial plan (WFP) approved by the EMB-CO. Key stakeholder members of the MMT are enumerated below.

Page 30: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

18

2.2.6.1 Composition of the MMT

2.2.6.1.1 Local Government Unit

• One (1) representative of the Provincial Government Environment and Natural Resources Office (PG-ENRO) from each affected province

• In case that there is no PG-ENRO, one (1) representative from the Municipal/City Environmental and Natural Resources Office (MENRO/City ENRO) or the Municipal/City Planning and Development Office (M/CPDO) or the chairman of the Sangguniang Barangay (SB) Environment Committee Chairman

• Chiefs of Rural Health Units (RHU) • Concerned Barangay Captains

2.2.6.1.2 Non-government Organization/People’s Organization

• Maximum of one representative from duly registered non-government organizations (NGOs) whose mission is related to environmental management and/or similar to the type and impacts of the proposed Project

• In case that there is no such NGO, membership can be opened to other NGOs

2.2.6.1.3 Community Leaders

• Maximum of two representatives from duly registered and recognized community leaders representing the vulnerable such as indigenous peoples (IPs), women, senior citizen, and/or representatives from academe.

2.2.6.1.4 National Government Agencies

• Maximum of three representatives with relevant mandates regarding the Project • Regarding special environmental concerns, e.g., biodiversity, DENR membership will be endorsed

by the director of the concerned bureau.

2.2.6.2 Roles and Responsibilities of the MMT

50. The specific functions of the MMT include the followings:

• Conduct a quarterly ocular site visit to validate the proponent's compliance with the ECC conditions and the environmental management and monitoring plan (EMMP) including requirements for self-monitoring and submit the corresponding reports regularly;

• Observe sampling activities conducted by the EA; • Prepare and submit its report to the EMB-Central Office, the EMB-Region 3, JICA and ADB using

EMB-prescribed formats at least semi-annually, no later than July 31 for the first-term report and January 30 for the second-term report; and

• Institute an environmental emergency and grievance management mechanism which is expected to provide recommendations for necessary regulatory actions to the EMB in a timely manner to prevent adverse environmental impacts.

51. On 24 January 2019, DOTr held a meeting with the potential members of the MMT. It was attended by concerned PG-ENROs and M/City ENROs. In the meeting, DOTr was advised to call upon mayors of the affected LGUs to designate permanent representatives for the MMT in written form. Further discussion was made on the necessity of the MOA conclusion and the setup of the EMF and the EGF. So far, the 20 affected LGUs have designated permanent members for the MMT. Other ongoing activities include the shortlisting of NGOs and qualified fund managers to be a part of the MMT, the review of costs for budget

Page 31: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

19

allocation and the finalization of the Manual of Operations (MOO) for review and concurrence of the MMT (DOTr, 2020).

2.3 Contractor

52. The Contractor will primarily implement the EMP and comply with the measures, requirements, and other relevant provisions set forth in the EMP and any corrective or preventative actions set out in the safeguard monitoring report7. The Contractor shall be held liable for any penalty sanctioned to the NSCR EX PMO due to non-compliance with the conditions in the ECC. The Contractor will allocate funding for the successful implementation of the EMP as stated in the Environmental Protection Clauses. Along with DOTr, the Contractor shall ensure that all engineering interventions in the approved EMP, RAP, and the ECC are implemented and shall document and report them to the DENR-EMB, JICA, and ADB through the prescribed formats and channels. The Contractor will notify the NSCR EX PMO, JICA, and ADB of any environmental risks or impacts not considered in the EIS, the EMP and the Resettlement Action Plan (RAP) or the Ancestral Domain Sustainable and Protection Plan (ADSDPP) that arise during construction. The following tasks are to be strictly observed by the Contractor:

• Provide sufficient fund and human resources for the proper and timely implementation of required mitigation and monitoring measures stipulated in the EMP and additional measures that may be required to address adverse environmental impacts generated by construction activities;

• Recruit a sufficient number of full-time, qualified, and experienced environmental officers and safety officers before site works commence to ensure compliance with environmental statutory requirements, contractual obligations related to environmental management, and provisions of the EMP as well as timely and adequate monitoring and reporting on the EMP implementation;

• Prioritize employment of project-affected persons for construction works as conditioned in the ECC and submit a monthly report on employment status;

• Conduct joint site investigation with the EA and the GC before commencement of site works, adequately record the conditions of roads, agricultural lands, and other structures or infrastructure along the Project alignment and construction-related facilities that will be affected or may be damaged by civil works—such as damages due to vibration, operation of equipment, etc.—and ensure that such structures and assets will not be removed until relevant permits from the NSCR EX PMO or the GC on the area are obtained;

• Ensure that site clearing and construction works are consistent with unexploded ordnance (UXO) protocols to avoid health and safety hazards at work and against the public;

• Prepare the Contractor’s environmental management and monitoring plan (CEMMP) consistent with the EMP prior to the start of site works;

• Be consistent with the EMP and EMoP requirements, undertake ambient environmental baseline sampling prior to the start of site works and ambient environmental monitoring, and prepare corresponding monitoring reports;

• Prepare monthly monitoring reports on the EMP implementation, e.g., environmental mitigation measures for submission to DOTr and the GC;

• Undertake consultations with affected people and local officials prior to the start of site works and throughout the duration of construction works to ensure that they are properly informed on the grievance redress mechanism and upcoming construction activities and that any environment-related concerns are adequately addressed;

• Provide DOTr with a written notice of any unanticipated environmental impacts that arise during construction and prepare and implement corrective action plan(s);

7 The Semi-annual Environmental Monitoring Report

Page 32: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

20

• Implement additional environmental mitigation measures, as necessary, to avoid, minimize and/or compensate for adverse impacts due to construction works and related activities;

• Fully reinstate pathways, other local infrastructure, and agricultural lands to their pre-project condition at least upon completion of construction; and

• Obtain the ECCs necessary for temporary facilities and environment permits prior to construction.

2.4 General Consultant

53. DOTr has engaged the services of Greater Capital Railway Consortium (GCR8) as the general consultant to support the Project implementation and the overall responsibility for supervising, monitoring and reporting the EMP implementation9. GCR includes international environmental specialists and local environmental specialists who are responsible for supporting the PMO-ESRL and providing training and capacity building programs as required. GCR is tasked to assist the NSCR EX PMO in the following main activities, but not limited to10:

• Update the Environmental Impact Statement (EIS), the EMP, and the EMoP as appropriate if any unanticipated environmental risks and impacts arise and/or if there are any changes to project design that would cause environmental risks or impacts not within the scope of the EIS and submit such updated EIS to the Employer, ADB and JICA for review, clearance and public disclosure prior to the implementation of such changes; incorporate necessary technical specifications with design and contract documentation;;

• Update the EMP and the EMoP or prepare a new EMP and EMoP when unanticipated environmental impacts become apparent during project implementation to assess those impacts, evaluate the alternatives, and outline mitigation measures and resources addressing those impacts, in line with all applicable environmental laws, policies, and regulations of the Philippines, ADB Safeguard Policy Statement, and JICA Environmental Guidelines;

• Update the EMP and the EMoP should there be changes in the Project during implementation such as, but not limited to, the alignment, construction methodology, and other components that shall result to adverse environmental impacts not identified and addressed in the current EIS, EMP, and EMoP;

• Ensure that the Project is constructed and monitored in strict conformity with all applicable environmental laws, policies, and regulations of the Philippines, ADB Safeguard Policy Statement, and JICA Environmental Guidelines;

• Assist the Employer in the following as fulfillment of the conditions stated in the Environmental Compliance Certificate (hereinafter referred to as “ECC”) as well as in the JICA Environmental Guidelines, ADB Safeguard Policy Statement, and other environment-related requirements of the Project: - Survey and preparation of inventory of trees affected by the Project; - Decontamination of toxic sites of the Project as required, - Survey of archaeological sites and preparation of the Archaeological Impact Statement (AIS); - Survey and documentation of affected heritage, historical, and/or cultural structures, sites,

and/or markers;

8 Joint Venture consisting of Oriental Consultants Global Co,. Ltd., Katahira & Engineers International, Pacific Consultants Co., Ltd., Tonichi Engineering Consultants, Inc, and Nippon Koei in association with DCCD Engineering Corporation, Engineering and Development Corporation of the Philippines, J.F. Cancio & Associates, Oriental Consultants Philippines, Inc., Schema Konsult, Inc., and TCGI Engineers 9 Contract between DOTr and GCR was signed on 2 September 2019 10 Actual scope of work of the General Consultant under the following heading, “Task (10) Facilitation of implementation of Environmental Management Plan (EMP), Environmental Monitoring Plan (EMoP), Resettlement Action Plan (RAP) and Gender Action Plan (GAP)

Page 33: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

21

- Protection of affected heritage, historical, and/or cultural structures, sites, and/or markers as required by national and international laws, standards, and guidelines;

- Provision of an Information, Education, and Communication (hereinafter referred to as “IEC”) Plan to advise stakeholders of the implementation of the Project, its impacts, and measures to mitigate the effects of the Project;

• Assist the Employer in the implementation of the measures identified in the EMP; • Monitor the effectiveness of the EMP and recommend measures and solutions to address identified

gaps and mitigate negative impacts of the construction works on the environment; • Clearly define to the contractors their responsibilities in the implementation of the said EMP; • Assist the Employer, prior to mobilization and project construction, in reviewing the Contractors’

Construction Environmental Program/Construction Environmental Management Plan (CEMP) and in ensuring that the Contractors’ CEMP comply with the conditions stated in the ECC, the EMP, the applicable environmental laws, policies, and regulations of the Philippines, the ADB Safeguard Policy Statement, and the JICA Environmental Guidelines;

• Recommend to the Employer any necessary amendments to the CEMP; • Submit the CEMP to the Employer, ADB, and JICA for review; • Undertake close supervision, monitoring, and reporting of the Contractor’s implementation of the

CEMP to ensure timely and satisfactory compliance with the mitigation measures set forth in the EMP and with other conditions in the ADB Safeguard Policy Statement and JICA Environmental Guidelines, and to minimize any adverse environmental impacts arising from the construction and operation of the Project;

• Undertake close supervision, monitoring, and reporting of the Contractor’s environmental baseline sampling and subsequent ambient monitoring (air quality, noise, water quality, etc.) throughout the construction phase;

• Assist the Employer in conducting regular and/or ongoing consultations with the project-affected families project information (e.g. schedule, activities, impacts, mitigation, etc.) as well as documentation and resolution of concerns related to environmental impacts of the Project;

• Assist the Employer, before project construction, in establishing a grievance redress mechanism including the formation of a Grievance Redress Committee, and provide training for the personnel manning the GRM to receive and facilitate resolution of the concerns, complaints, and grievances of the affected people about the Project’s environmental performance, make public the existence of this grievance redress mechanism through public awareness campaigns, review and address environmental grievances of stakeholders in relation to the Project, any of the service providers, or any person responsible for carrying out any aspect of the Project, and proactively and constructively respond to such grievances;

• Undertake monthly monitoring of EMP implementation from commencement until two (2) years after the completion of the Project, in compliance with conditions stated in the ECC as well as in the requirements under JICA Environmental Guidelines and ADB Safeguard Policy Statement. Results of the monthly monitoring report shall be consolidated into an Environmental Monitoring Report (EMR) which shall be submitted to the Employer every three (3) months after the commencement of the services until the completion of the Project, and semi-annually or annually for two (2) years after the completion of the Project;

• Assist in submitting the Compliance Monitoring Report (CMR) to the Department of Environment and Natural Resources (DENR) in the prescribed format after its verification by the Employer in compliance with the ECC for the Project. The CMR shall be submitted to DENR every January and July of the year;

• Assist in submitting the Semi-Annual Environmental Monitoring Report (SEMR) to ADB after the verification of the EMRs by the Employer. SEMRs shall be duly submitted to ADB on the 4th week

Page 34: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

22

of January and July (i.e., 30 days from end of each 6-month monitoring period)11. The SEMR must include consolidated results of monthly environmental monitoring, environmental monitoring data (baseline and routine), review of the progress of environmental measures detailed in the EMP, details of complaints received, and corresponding actions taken, details of safety issues and corresponding action plans as well as other relevant information, environmental issues and corrective measures implemented;

• Assist in submitting the EMR, after its verification by the Employer, to JICA as part of the Progress Status Report every three (3) months after the commencement of the services until the completion of the Project and semi-annually or annually for two (2) years after the completion of the Project;

• Engage an External Monitoring Agent for environmental monitoring, in behalf of the Employer. Ensure that the TOR for the EMA is suitable for the Project needs. Provide available relevant information to the EMA;

• Assist the Employer in responding to requests from ADB and JICA’s advisory committee for environmental and social considerations if necessary;

• Assist the Employer in the capacity building of the Employer’s staff on environmental management through on-the-job training on environmental assessment techniques, mitigation measure planning, supervision and monitoring, and reporting;

• Should there be major non-compliance discovered during the review of the Project, prepare a time-bound corrective action plan for submission to ADB and JICA;

• During ADB processing of subsequent MFF individual tranches, conduct due diligence and prepare a detailed report on: - Project compliance on the environmental assessment and review framework (EARF) and ADB

Safeguard Policy Statement; - Status of implementation of various provisions of the EMP; - Compliance with the loan covenants between ADB and the GOP regarding environmental

safeguards under previous tranches; • Prepare a Project Completion Environmental Monitoring Report after completion of construction,

detailing the status of EMP implementation, outstanding environmental issues and necessary time-bound corrective action plan; and

• Use of Geographic Information System in implementation of the aforementioned scope.

2.5 Third Party Monitor - External Environmental Monitoring Agency

54. DOTr will engage a third-party monitor, or external environmental auditor who will assist the PMO-ESRL in monitoring environmental parameters of the Project. Semi-annual reports will be prepared and submitted by the third-party monitor to JICA and ADB. The Terms of Reference had been reviewed and approved by ADB in March 2020. DOTr is in the process of tendering.

3 Information Disclosure

55. DOTr will disclose relevant information including the potential impacts of the Project and the corresponding mitigating measures to the stakeholders in line with ADB Safeguard Policy Statement and Public Communication Policy (2011), JICA Environmental Policy, and JICA Environmental Guidelines. Information disclosure aims to achieve the following objectives:

11 ADB Loan Effectivity was on 26 September 2019. SEMRs are to be submitted to ADB on the 4th week of March and September, instead of January and July.

Page 35: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

23

• Enhance the sustainability of projects by ensuring that interventions are relevant to the people of the area;

• Learn from the various social groups living in a project area how they perceive the existing situation, recent trends, existing problems, and potential solutions;

• Collect local knowledge, information, and ideas about the technical implications and impacts of project design; and

• Determine potential social, economic, and cultural impacts not always foreseen in survey based socio-economic studies.

56. DOTr will provide the following documents to ADB and JICA for disclosure in their respective websites:

• Draft EISR to be posted on ADB’s website no later than 120 calendar days before Board consideration;

• Final EISR; • A new/updated EISR and corrective action plan prepared during Project implementation if any; and • Environment monitoring reports to be posted by ADB on ADB’s website within two weeks after

receipt by ADB.

57. In addition, DOTr will disclose key information to the project-affected persons (PAPs) and other stakeholders in plain and understandable Philippine language and dialects through suitable communication methods.

58. Key Information includes Project outlines and activities, implementation schedule, Project location, duration and potential impact/risks to be affected and corresponding mitigation measures, consultation process, and GRM.

59. Media that will be used are public consultations, brochures, leaflet, booklet, poster, radio, website, info-graphics, among others.

4 Reporting Requirements for Monitoring

60. The NSCR EX PMO is required to submit internal and external monitoring reports to the DENR-EMB, ADB, and JICA during pre-construction and construction until the Project completion. Additionally, the results of public consultation and information disclosure are likewise submitted as attachments. The said reports are disclosed to the public.

61. The Contractor is required to submit monthly environmental compliance progress reports through the GCR to the NSCR EX PMO throughout the pre-construction and construction phases. The Contractor should highlight the summary of the construction progress and activities undertaken to implement measures outlined in the EMP and EMoP, recording any received community complaints and their resolution.

62. GCR consolidates the results of monthly environmental monitoring into quarterly and semi-annual internal monitoring reports for submission to NSCR EX PMO and then to ADB and JICA. The significant findings and measures undertaken to address any adverse environmental impacts during construction are summarized, and any unforeseen environmental impacts and recommended remedial actions for the next monitoring period are presented in these reports.

63. Once the internal environmental monitoring reports are received by NSCR EX PMO, the Project's compliance with the ECC and EMP is reviewed. After thorough review, the semi-annual internal reports are submitted to ADB and JICA. All internal environmental monitoring reports are subject to disclosure on the websites of ADB and JICA.

Page 36: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

24

64. During operation, EMP monitoring is undertaken by NSCR EX PMO. Semi-annual external environmental monitoring reports are prepared by the third-party environmental auditors (EMA) who are commissioned by NSCR EX PMO. NSCR EX PMO conducts a review of semi-annual external environmental monitoring reports and verifies conformity of the Project with the EMP and semi-annual progress reports, which are subsequently submitted to ADB and JICA.

65. Under the PEISS, quarterly Self-Monitoring Reports (SMRs) and semi-annual Compliance Monitoring Reports (CMRs) will be submitted by NSCR EX PMO to the DENR-EMB by using prescribed formats. DENR-EMB has confirmed that self-monitoring reports shall be prepared and submitted during the construction phase following the Procedural and Reference Manual for DAO 2003-27 (Self-Monitoring Report System) when the required permits have been acquired and when actual Project impacts are taking place. Further, semi-annual CMVRs, otherwise known as the MMT report form will be also submitted by

the MMT to the DENR-EMB.

66. The monitoring reports to be prepared are summarized in Table 5.

Table 5: Types of Monitoring Reports

Type of Report Frequency Responsible Party Place of Submission Status

Pre-Construction and Construction Phase

1

Monthly environmental compliance progress report

Monthly Contractor Contractor ⇒ GC ⇒ DOTr

Not applicable, Project is still in pre-construction phase.

2

Quarterly Environmental Monitoring Report (QEMR)12

Quarterly GC GC ⇒ DOTr ⇒ ADB/JICA

For compliance

3

Semi-annual monitoring Report (SEMR)13

Semi-annual (The results of monthly environmental compliance progress reports are compiled into a semi-annual monitoring report.)

GC GC ⇒ DOTr ⇒ ADB/JICA

First SEMR submitted to ADB in March 2020

4

Environmental Safeguard Evaluation Report

End of the Project GC GC ⇒ DOTr ⇒ ADB/JICA

Not yet applicable.

5 Semi-annual External

Every six (6) months until loan closing

GC EMA ⇒ DOTr, ADB and JICA

Not yet applicable. EMA has yet to be engaged.

12 To be submitted at every quarter after the commencement of the services, presenting the environmental impacts and implementation of environmental mitigation measures during the construction stage, including proposed solutions and suggested revisions. Environmental monitoring forms will be filled and attached to the Report. 13 To be submitted semi-annually after the commencement of the services, up to two (2) years after the completion of the Project, presenting the environmental impacts and implementation of environmental mitigation measures during the construction stage, including proposed solutions and suggested revisions. Environmental monitoring forms will be filled and attached to the Report.

Page 37: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

25

Type of Report Frequency Responsible Party Place of Submission Status

Monitoring Report

6

Environmental Audit/ Evaluation Report/Project Completion Report

6-12 months after project completion or loan closing

EMA EMA ⇒ DOTr, ADB and JICA

Not yet applicable. EMA has yet to be engaged.

7

SMR Quarterly online submission

NSCR EX PMO NSCR EX PMO ⇒ EMB-Central Office, EMB-NCR, EMB-Region 3

Not applicable, Project is still in pre-construction phase.

8

CMR Semi-annual using EMB-prescribed formats (no later than July 31 for the first term and January 30 for the second term)

NSCR EX PMO NSCR EX PMO ⇒ EMB-Central Office, EMB-NCR, EMB-Region 3

First CMR was submitted to DENR-EMB Central Officer in July 2019. Second CMR was submitted to DENR-EMB Central Office in January 2020.

9

CMVR Semi-annual using EMB-prescribed formats (MMT report form)

MMT NSCR EX PMO ⇒ EMB-Central Office, EMB-NCR, EMB-Region 3

Not applicable, Project is still in pre-construction phase and MMT is in progress of establishment.

Operational Phase

1 Compliance monitoring report

Semi-annual Environmental auditors under NSCR EX PMO

Environmental auditors ⇒ NSCR EX PMO ⇒ ADB/JICA

Not applicable, Project is still in pre-construction phase.

2

SMR Quarterly online submission

NSCR EX PMO NSCR EX PMO ⇒ EMB-Central Office, EMB-NCR, EMB-Region

Not applicable, Project is still in pre-construction phase.

3

CMR Semi-annual using EMB-prescribed formats (no later than July 31 for the first term and January 30 for the second term)

NSCR EX PMO NSCR EX PMO ⇒ EMB-Central Office, EMB-NCR, EMB-Region 3

Not applicable, Project is still in pre-construction phase.

4

CMVR Semi-annual using EMB-prescribed formats (MMT report form)

MMT NSCR EX PMO ⇒ EMB-Central Office, EMB-NCR, EMB-Region 3

Not applicable, Project is still in pre-construction phase.

Source: (DOTr, 2020)

5 Updated EMPs, Incorporation of Safeguards Requirements into Project Contractual Arrangements

67. The Environmental Management clauses to be complied with by the Contractor are contained in GS 118 of Volume 2 Part II – Requirements Section 6 – The Employer’s Requirements Part I – The Specifications: A General Specification (GS) Book 1: GS 100 General Specification; which form part of the bidding documents. The supporting documents are included in Appendix 7 of the bidding documents, as follows:

Page 38: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

26

• Annex 7A - Environmental Compliance Certificate • Annex 7B - Environmental Management Plan • Annex 7C - Environmental Monitoring Plan • Annex 7D - The Institutional Plan • Annex 7E - Sample Impact Control Plan • Annex 7F - Resettlement Action Plan • Annex 7G - Environmental Impact Statement

68. A Pre-Construction Conference shall be held between DOTr and the winning bidder in order to clarify and confirm the Environmental Management clauses under GS 118. The updates on the EIS, ECC, EMP and EMoP shall also be discussed with the Contractor.

Page 39: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

27

II. Environmental Performance Monitoring

1 Status of Compliance with ECC Conditions

1.1 NSCR Clark Extension

69. The ECC for the NSCR Clark Extension was issued on 13 August 2018 and subsequent changes on the Project scope from Feasibility Study (FS) to Detailed Design (DD) stage has been assessed and incorporated in the updated EIS report. This report was submitted to the Environmental Management Bureau Central Office (EMB-CO) on 16 January 2020.

Table 6: ECC Compliance Matrix for the NSCR Clark Extension

Description Status Remarks/Further Actions Required

I.General Conditions. Environmental Management.

1 Conduct an effective and continuing Information, Education and Communication (IEC) Program through the use of most effective media to inform and educate all stakeholders, especially the contractors, workers, LGUs, businesses and local residents about the following: a. Project impacts and mitigating

measures embodied in its EIS; b. Conditions stipulated in the ECC; c. Environmental and human safety

features of the project; and d. Health consciousness alerts for

any project-induced discomfort (from dust, smell, noise, vibration) as the project progresses throughout the whole route.

Ongoing progress

Conduct of Stakeholders Consultation Meetings (SCMs) with Project-Affected Persons to update them on the progress of the project is ongoing. Summary of past meetings can be found in the updated Section 6.2 of the EIS. The Proponent is now working on creating fliers/brochures for information dissemination. Coordination meetings with Local Government Units (both Municipal and Barangay Level) including some of their constituents and activist groups within their jurisdiction have been actively undertaken. This is in view of the acquisition of Certificate of No Objection (CNO), specifically for the cutting of project affected trees. In the said activity, the stakeholders are apprised about the project, how many trees are needed to be cleared and the proposed mitigation activities thereon (I.e. Greening Program and Earth-balling)

2 Implement a comprehensive Social Development Program (SDP) and submit a separate report together with the Compliance Monitoring Report (CMR) to the EMB Central Office using CMR Online on a semi-annual basis pursuant to EMB MC 2016-01.

Ongoing progress

Sit-down workshop meetings with LGUs have been conducted in order to plan the appropriate SDPs to be implemented. Attached as Appendix E is the output from the workshops conducted so far. From the gathered data, the Proponent will propose appropriate SDPs, and a manual will also be created to monitor the implementation of SDPs and to serve as a guide for future projects of the Proponent.

Page 40: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

28

Description Status Remarks/Further Actions Required

Appendix F presents the CMRs submitted through DENR website (https://online.emb.gov.ph/cmr/)

3 Submit detailed waste management program (WMP) for proper handling, collection and disposal of solid, hazardous and liquid wastes to EMB Central Office (CO) and EMB Region III within six months prior to project construction. Proof of implementation shall be submitted together with the CMR.

Ongoing progress

The Proponent is preparing the Project Waste Management Plan as a basis for the detailed WMP to be developed by the Contractors as part of the Contractors Environmental Management and Monitoring Plan (CEMMP). Please refer to Appendix G. Similar plans would be required for the site clearance activities (Pre-Construction) and the railway operation (Operations).

4 Ensure that all the existing waterways affected by the proposed project construction are maintained and not obstructed.

Ongoing progress

Certificate of No Objections have been secured for the following purposes: 1. Sapang Balen Improvement (c/o

DPWH Pampanga 1st DEO) 2. Approval of Drainage Connection

to Existing Canals (c/o DPWH Pampanga 1st DEO)

3. Approval of Drainage Connection to Existing Canal along Manila North Road (MNR), from St. Jude to Junction MNR and Jose Abad Santos Ave., San Fernando, Pampanga (c/o DPWH Region III)

4. Approval of Drainage Connection in the jurisdiction of DPWH Pampanga 3rd DEO

5. Approval of Drainage Connection in the jurisdiction of DPWH Bulacan 1st DEO

6. Approval of Drainage Connection to existing creek in Brgy. Malpitic, San Fernando, Pampanga

7. Approval of Drainage Connection to existing creek in Brgy. San Agustin, San Fernando, Pampanga

8. Approval of Drainage Connection to existing creek in Brgy. Quebiawan, San Fernando, Pampanga

9. Approval of Drainage Connection to existing creek in Brgy. Pulung Bulu, San Fernando, Pampanga

(Pease see Appendix H for CNOs) Coordination to secure certificate of no objections from other DPWH Region III and NCR Offices, LGUs, MMDA, and NIA Region III is also ongoing.

Page 41: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

29

Description Status Remarks/Further Actions Required

5 Submit a detailed construction environmental management program, including mobilization and demobilization plans, for the construction yards one month prior to project implementation. The plan should include the coordination with concerned LGUs to promote compatibility of adjoining land uses with the intended project stations including its exit and entrance.

Ongoing preparation of plans, contract not awarded yet

Contracts for civil works have yet to be awarded. No construction works as of submission of CMR. The Proponent, through the General Consultant (GC), will brief the civil works contractors with their commitments in the implementation of the EMP. The Construction Environmental Management Plan (CEMP), which will be submitted by the construction contractors, will be reviewed before Project construction. The CEMP must be aligned with the EMP of the Project. The civil works contractors must observe the measures or mitigations stated in the CEMP.

6 Submit a detailed plan for earth balling and replanting of mature native/endemic trees within three months prior to project construction. The plan should include the following: a. Specific recipient sites which have

already been prepared and conditioned;

b. Ensure high degree of survival; and

c. Provision for regular maintenance until trees have re-establish in their new environment.

Ongoing coordination

The Proponent has coordinated with DENR FMB for the matter. Accordingly, the DENR will conduct validation of the inventoried trees which will further enable them to identify specific trees that are to be earth balled. Moreover, earth balling shall be subject to the following conditions: 1. Only healthy trees shall be earth-

balled; 2. Indigenous species shall be

prioritized; 3. The surrounding of the tree shall

be free from impediments to support digging/moving operations; and

4. A suitable area for transplanting shall be pre-identified

The area for the transplanting shall be identified by the DENR. The Proponent on the other hand, shall maintain and protect the earth-balled trees for a period of at least one year. The DENR will commence its validation once all the requirements for the application of Tree Cutting and/or Earth Balling permits have been completed by the Proponent.

Page 42: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

30

Description Status Remarks/Further Actions Required

7 Implement a greening program in line with the DENR’s thrust for GHG Emission Reduction Program. The program shall be submitted to EMB 60 days prior to the project implementation.

Ongoing coordination

Tentative location indicated in the previous section for Buffer Zone and GHG Program is the Mabalacat Depot area. The coordinates will be updated once location is finalized. The Proponent will participate in the “adopt a site” as part of the Enhanced National Greening Program - a flagship program of the DENR. At the least, a five-hectare degraded site (either upland or mangrove area14) within the province of Bulacan and Pampanga will be developed by the DOTr. DOTr will also engage a registered People’s Organization living within or adjacent to the proposed area who will be our partner in the maintenance and protection of the developed site. A tripartite MOA between the DOTr, PNR and DENR Region III is already drafted and will be signed by April 2020. DOTr, together with the DENR Field Staff have already conducted a site visit to the proposed greening sites of DENR in Bulacan and Pampanga, respectively. The teams gathered as much information in the proposed NGP site.

8 Submit an approved Resettlement Action Plan (RAP) of the affected communities within two months prior to project construction.

Ongoing progress

Finalization of the detailed RAPs is ongoing. The RAP is divided into the following:

1. Mabalacat RAP (CP N04 and N05)

2. Landowner RAP (CP N01, N02, N03)

3. Non-Landowner RAP (CP N01, N02, N03)

14 To be coordinated with the DENR Region 3.

Page 43: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

31

Description Status Remarks/Further Actions Required

9 Conduct a detailed Traffic Impact Assessment (TIA) in coordination with the concerned LGUs for every proposed station prior to project construction integrating proposed road expansion projects of the concerned government agencies. Transport of heavy structures shall be scheduled during the period that may not cause traffic in the area.

Ongoing coordination

The initial draft TIA, has been discussed with LGUs and DPWH Region III. The TIA report has been revised per LGUs and DPWH Region III's inputs. The updated version of the TIA is attached as Appendix I.

II.Conditions. General Conditions.

10 The Proponent shall set-up the following:

10.1 A readily available and replenishable Environmental Guarantee Fund (EGF) to cover the following expenses: a. for further environmental

assessments, compensations/indemnification for whatever damages to life and property that may be caused by the project;

b. rehabilitation and/or restoration of areas affected by the project's implementation; and

c. abandonment/decommissioning of the project facilities related to the prevention of possible negative impacts; and as a source of fund for contingency and clean-up activities

Ongoing progress

EGF is part of contractor's budget. The project is still in the procurement stage. Requirement will be reiterated to contractors when they are on board.

10.2 Establish an MMT composed of representative(s) from the local environmental Non-Government Organization/s (NGOs), People’s Organization/s (POs) and the Local Government Units per DAO 2017-15. The MMT shall primarily oversee the compliance of the Proponent with the Environmental Management and Monitoring Plan (EMMoP) and the ECC conditions.

Ongoing progress

The Proponent is in the process of completing the members of the MMT, selecting the fund manager. The Memorandum of Agreement and Manual of Operations will be finalized with the MMT. DOTr is still in search for an MMT EMF fund manager, through GCR’s assistance in communicating with prospective organizations, including the Natural Resources Development Corporation (NRDC). The NRDC is known to manage review funds for DENR-EMB’s EIA Review Committee. However, in February 2020, NRDC verbally declined due to managing MMT EMFs is not within scope of their MOA with DENR-EMB.

Page 44: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

32

Description Status Remarks/Further Actions Required

GC is also being considered for the role, but needs approval from DOTr, DENR-EMB and GC Management.

10.3 A replenishable Environmental Monitoring Fund (EMF) to cover all costs attendant to the operation of the MMT such as training, hiring of technical experts and resource persons, fieldwork and transportation. The amount and mechanics of EGF, EMF and the establishment of the MMT shall be determined by the EMB Central Office and the proponent through a Memorandum of Agreement (MOA) which shall be submitted in the 60 days prior to construction.

Ongoing progress

The Proponent has requested a budget of PhP2,000,000.00 for the EMF from the DOTr, and is currently working on securing the budget.

11 Establish an Environmental Unit (EU) in 60 days prior to construction that shall competently handle the environment-related aspects of the project. In addition to the monitoring requirements as specified in the EMMoP, the EU shall have the following responsibilities: Monitor actual project impacts vis-à-vis the predicted impacts and management measures in the EIS; Recommend revisions to the EMMoP, whenever necessary subject to the approval of the EMB-CO; Ensure that data gathered during monitoring activities are properly documented, assessed, evaluated, and reported in accordance with the standard formats; and Ensure that monitoring and submission of reports to EMB-CO are carried out as required.

Established The Proponent has submitted the organizational chart (Appendix J) of the Project's EU to DENR EMB CO on December 23, 2019. Designated staff have undergone the 40hour Basic Pollution Control Officer Training last November 18-22, 2019, and the Project Managers have undergone the 8-hour Environmental Training for Managing Heads on January 21, 2020. The Proponent will work on the accreditation of the PCOs on the first half of 2020.

12 The Proponent shall ensure that its contractors and sub-contractors are provided with copies of this ECC, including the EMP, and that they will strictly comply with the relevant conditions of the ECC.

Ongoing progress

The General Consultant (GC) has onboarded and has been provided with the copy of the ECC. The project is still in the process of procuring civil works contractors, but the ECC and the EMP were already disclosed in the bidding documents. The civil works contractors will be briefed of their obligations in the

Page 45: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

33

Description Status Remarks/Further Actions Required

implementation of the EMP once they are onboard. The relevant documents shall be transmitted to the GC and to the civil works contractors.

III.Restrictions

13 No activities shall be undertaken other than what were stipulated in the final EIS. Any expansion and/ or modification of the Project beyond the Project description or change in alignment/ route that will cause significant impacts to the environment shall be subjected to a new Environmental Impact Assessment.

Ongoing progress

The updated EIS has been transmitted to EMB-CO for further review and will undergo the required process if found with any significant modifications or changes.

14 In case of transfer of ownership of this Project, the same conditions and restrictions shall apply to the transferee or grantee who shall secure in writing the corresponding amendment of this ECC from the EMB-CO within 15 working days reflecting such transfer.

Not applicable

Not applicable

1.2 NSCR Calamba Extension

70. The ECC for the Calamba Extension was issued on 13 August 2018 and subsequent changes on the Project scope from the Feasibility Study (FS) to Detailed Design (DD) stage have been assessed and incorporated in the updated EIS report, which has been submitted to the EMB on 16 January 2020. Contract package S-01 is covered by Loan Agreement No. 3796-PHI.

Table 7: ECC Compliance Matrix for the NSCR Calamba Extension

Description Status Remarks/Further Actions Required

I.General Conditions. Environmental Management.

1 Conduct an effective and continuing Information, Education and Communication (IEC) Program through the use of most effective media to inform and educate all stakeholders, especially the contractors, workers, LGUs, businesses and local residents about the following: a. Project impacts and mitigating

measures embodied in its EIS; b. Conditions stipulated in the ECC; c. Environmental and human safety

features of the project; and d. Health consciousness alerts for

any project-induced discomfort (from dust, smell, noise, vibration)

Ongoing progress

IEC Meetings have been continuously held with LGUs to update them on the detailed design phase activities. The Proponent is now working on creating fliers/brochures for information dissemination.

Page 46: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

34

Description Status Remarks/Further Actions Required

as the project progresses throughout the whole route.

2 Implement a comprehensive Social Development Program (SDP) and submit a separate report together with the Compliance Monitoring Report (CMR) to the EMB Central Office using CMR Online on a semi-annual basis pursuant to EMB MC 2016-01.

Ongoing progress

Preparation of the comprehensive SDP is still ongoing. Sit-down workshop meetings with LGUs will be conducted in order to plan the appropriate SDPs to be implemented. Attached as Appendix K is the general considerations for the SDP to be implemented.

3 Waste Management Program (WMP) Submit detailed Waste Management Program (WMP) for proper handling, collection, and disposal of solid, hazardous, and liquid wastes to EMB CO, EMB NCR, and EMB-Region IV-A within six (6) months prior to project construction. Proof of implementation shall be submitted together with the CMR.

Ongoing progress

The Proponent is preparing the Project Waste Management Plan as a basis for the detailed WMP to be developed by the Contractors as part of the Contractors Environmental Management and Monitoring Plan (CEMMP). Please refer to Appendix L Similar plans would be required for the site clearance activities (Pre-Construction) and the railway operation (Operations).

4 Ensure that all the existing waterways affected by the proposed project construction are maintained and not obstructed.

Ongoing progress

The Proponent is currently coordinating with DPWH, MMDA and NIA regarding approval of the Project's design in relation to the affected drainages and waterways in the jurisdiction of said offices. Approval and/or Certificate of No Objections are targeted to be secured within this year 2020.

5 Submit a detailed construction environmental management program, including mobilization and demobilization plans, for the construction yards one month prior to project implementation. The plan should include the coordination with concerned LGUs to promote compatibility of adjoining land uses with the intended project stations including its exit and entrance.

Ongoing preparation of plans, contract not awarded yet

The Project is still in the detailed design stage, and the EIS, EMP and EMoP are also being updated to reflect changes in the design. The Proponent, through the General Consultant (GC), will brief the construction contractors their commitments in the implementation of the EMP. The Construction Environmental Management Plan (CEMP), which will be submitted by the construction contractors, will be reviewed before Project construction. The CEMP must be aligned with the EMP of the Project.

Page 47: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

35

Description Status Remarks/Further Actions Required

The construction contractors must observe the measures or mitigations stated in the CEMP.

6 Submit a detailed plan for earth balling and replanting of mature native/endemic trees within three months prior to project construction. The plan should include the following: a. Specific recipient sites which have

already been prepared and conditioned;

b. Ensure high degree of survival; and

c. Provision for regular maintenance until trees have re-establish in their new environment.

Ongoing coordination

The Proponent has coordinated with DENR FMB for the matter. Accordingly, the DENR will conduct validation of the inventoried trees which will further enable them to identify specific trees that are to be earth balled. Moreover, earth balling shall be subject to the following conditions: 1. Only healthy trees shall be earth-

balled; 2. Indigenous species shall be

prioritized; 3. The surrounding of the tree shall

be free from impediments to support digging/moving operations; and

4. A suitable area for transplanting shall be pre-identified

The area for the transplanting shall be identified by the DENR. The Proponent on the other hand, shall maintain and protect the earth-balled trees for a period of at least one year. The DENR will commence its validation once all the requirements for the application of Tree Cutting and/or Earth Balling permits have been completed by the Proponent.

7 Implement a greening program in line with the DENR’s thrust for GHG Emission Reduction Program. The program shall be submitted to EMB 60 days prior to the project implementation.

Ongoing coordination

Tentative location indicated in the previous section for Buffer Zone and GHG Program is the depot area. The coordinates will be updated once location is finalized. Planning is still ongoing within the EU. Requirements will be submitted once finalized.

Page 48: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

36

Description Status Remarks/Further Actions Required

8 Submit an approved Resettlement Action Plan (RAP) of the affected communities within two months prior to project construction.

Ongoing progress

Finalization of the detailed RAPs is ongoing. The following RAPs are being prepared in advance (as compared to other sections of the alignment):

1. Landowner and Non-Resident Business Owner RAP (CP S01)

2. Non-Landowner RAP (CP S01)

9 Conduct a detailed Traffic Impact Assessment (TIA) in coordination with the concerned LGUs for every proposed station prior to project construction integrating proposed road expansion projects of the concerned government agencies. Transport of heavy structures shall be scheduled during the period that may not cause traffic in the area.

Ongoing coordination

Initial TIA attached as Appendix M. TIA will be updated to reflect changes in the detailed design of the Project.

II.Conditions. General Conditions.

10 The Proponent shall set-up the following:

10.1 A readily available and replenishable Environmental Guarantee Fund (EGF) to cover the following expenses: d. for further environmental

assessments, compensations/indemnification for whatever damages to life and property that may be caused by the project;

e. rehabilitation and/or restoration of areas affected by the project's implementation; and

f. abandonment/decommissioning of the project facilities related to the prevention of possible negative impacts; and as a source of fund for contingency and clean-up activities

Ongoing progress

EGF is part of contractor's budget. The project is still in the procurement stage. Requirement will be reiterated to contractors when they are on board.

10.2 Establish an MMT composed of representative(s) from the local environmental Non-Government Organization/s (NGOs), People’s Organization/s (POs) and the Local Government Units per DAO 2017-15. The MMT shall primarily oversee the compliance of the Proponent with the Environmental Management and

Ongoing progress

The Proponent is in the process of completing the members of the MMT, selecting the fund manager. The Memorandum of Agreement and Manual of Operations will be finalized with the MMT. DOTr is still in search for an MMT EMF fund manager, through GCR’s

Page 49: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

37

Description Status Remarks/Further Actions Required

Monitoring Plan (EMMoP) and the ECC conditions.

assistance in communicating with prospective organizations, including the Natural Resources Development Corporation (NRDC). The NRDC is known to manage review funds for DENR-EMB’s EIA Review Committee. However, in February 2020, NRDC verbally declined due to managing MMT EMFs is not within scope of their MOA with DENR-EMB. GC is also being considered for the role, but needs approval from DOTr, DENR-EMB and GC Management.

10.3 A replenishable Environmental Monitoring Fund (EMF) to cover all costs attendant to the operation of the MMT such as training, hiring of technical experts and resource persons, fieldwork and transportation. The amount and mechanics of EGF, EMF and the establishment of the MMT shall be determined by the EMB Central Office and the proponent through a Memorandum of Agreement (MOA) which shall be submitted in the 60 days prior to construction.

Ongoing progress

The Proponent has requested a budget of PhP2,000,000.00 for the EMF from the DOTr, and is currently working on securing the budget.

11 Establish an Environmental Unit (EU) in 60 days prior to construction that shall competently handle the environment-related aspects of the project. In addition to the monitoring requirements as specified in the EMMoP, the EU shall have the following responsibilities: Monitor actual project impacts vis-à-vis the predicted impacts and management measures in the EIS; Recommend revisions to the EMMoP, whenever necessary subject to the approval of the EMB-CO; Ensure that data gathered during monitoring activities are properly documented, assessed, evaluated, and reported in accordance with the standard formats; and Ensure that monitoring and submission of reports to EMB-CO are carried out as required.

Established The Proponent has submitted the organizational chart (Appendix J) of the Project's EU to DENR EMB CO on December 23, 2019. Designated staff have undergone the 40hour Basic Pollution Control Officer Training last November 18-22, 2019, and the Project Managers have undergone the 8-hour Environmental Training for Managing Heads on January 21, 2020. The Proponent will work on the accreditation of the PCOs on the 1st half of 2020.

Page 50: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

38

Description Status Remarks/Further Actions Required

12 The Proponent shall ensure that its contractors and sub-contractors are provided with copies of this ECC, including the EMP, and that they will strictly comply with the relevant conditions of the ECC.

Ongoing progress

The General Consultant (GC) has onboarded and has been provided with the copy of the ECC. The project is still in the process of procuring civil works contractors, but the ECC and the EMP were already disclosed in the bidding documents. The civil works contractors will be briefed of their obligations in the implementation of the EMP once they are onboard. The relevant documents shall be transmitted to the GC and to the civil works contractors.

III.Restrictions

13 No activities shall be undertaken other than what were stipulated in the final EIS. Any expansion and/ or modification of the Project beyond the Project description or change in alignment/ route that will cause significant impacts to the environment shall be subjected to a new Environmental Impact Assessment.

Ongoing progress

The updated EIS has been transmitted to EMB-CO for further review and will undergo the required process if found with any significant modifications or changes.

14 In case of transfer of ownership of this Project, the same conditions and restrictions shall apply to the transferee or grantee who shall secure in writing the corresponding amendment of this ECC from the EMB-CO within 15 working days reflecting such transfer.

Not applicable

Not applicable

2 Status of EMP Implementation (Mitigation Measures)

71. For this reporting period, there are no EMP implementation issues to report because construction activities have not commenced.

Table 8: Compliance with EMP Requirements (Environmental Performance)

Page 51: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

39

EMP Requirements15 Compliance Status (Yes, No, Partial)

Comment or Reasons for Non-Compliance

Issues for Further Action

Current Issues

Not currently applicable for this reporting period because this monitoring report is the first submission and there are no construction activities yet.

No action required

Contractor responsibility as per General Specification (GS) 118, and referenced to the EMP and EMOP.

Not currently applicable for this reporting period because this monitoring report is the first submission and there are no construction activities yet.

Old Issues from Previous Reports

Not currently applicable for this reporting period because this monitoring report is the first submission and there are no construction activities yet.

Contractor responsibility as per General Specification (GS) 118, and referenced to the EMP and EMOP.

Not currently applicable for this reporting period because this monitoring report is the first submission and there are no construction activities yet.

Source: GC (as of March 2020).

Page 52: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

40

3 Health and Safety

72. For this reporting period, there are no health and safety issues to report because construction activities have not yet commenced.

Table 9: Health and Safety Issues

Issue Required Action Responsibility and

Timing Resolution

Old Issues from Previous Reports

Not currently applicable for this reporting period because this monitoring report is the first submission and there are no construction activities yet.

No action required Contractor responsibility as per General Specification (GS) 117

Not currently applicable for this reporting period because this monitoring report is the first submission and there are no construction activities yet.

New Issues from This Report

Not currently applicable for this reporting period because this monitoring report is the first submission and there are no construction activities yet.

No action required Contractor responsibility as per General Specification (GS) 117

Not currently applicable for this reporting period because this monitoring report is the first submission and there are no construction activities yet.

4 Environment Effect Monitoring

73. Monitoring plan. At the current pre-construction phase of the Project, DOTr will initially implement the EMoP presented in the updated EISR. The EMoP will be updated, if necessary, when the contractors are on board.

74. Monitoring activities in the reporting period. As of this reporting period, the Project is still in the pre-construction phase. Monitoring activities will be conducted in earnest during the construction period.

75. No environment effect monitoring activities have been undertaken as of this reporting period because no construction activities have commenced.

Table 10: Environment Effect Monitoring Results

Location Parameter Date

Monitoring value Relevant government

standard, standard value

Not currently applicable for this reporting period because there are no construction activities yet.

76. Assessment. No assessment can be made during this reporting period because no-construction and monitoring activities have yet commenced.

Page 53: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

41

5 Compliance with Safeguards Related Project Covenants

77. Table 11 presents the compliance status during this reporting period.

Table 11: Compliance with Safeguards Related Project Covenants

Schedule Para No. Covenant Remarks/Issues

(Status of Compliance)

Schedule 4 6 The Borrower shall, through DOTr, ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project and Project Facilities comply with (a) all applicable laws and regulations of Borrower including relating to environment, health, and safety; (b) the Environmental Safeguards; (c) the EARF; and (d) all measures and requirements set forth in the respective EIA and EMP, and any corrective or preventative actions with respect to environment set forth in a safeguards monitoring report.

Provisions provided in General Specifications (GS) 118 of the Standard Bidding Document (SBD). Ongoing compliance.

7 The Borrower shall, through DOTr, ensure that works do not commence until and unless environmental clearance, satisfactory in substance and form to ADB, in respect of the relevant site has been received from the Department of Environment and Natural Resources.

Complied.

Safeguards – Related Provisions in Bidding Documents and Works Contracts 13 The Borrower shall; through DOTr, ensure that

all bidding documents and contracts for Works contain provisions that require contractors to:

(a) Comply with the measures and requirements relevant to the contractor set forth in the EIAs, the EMPs and the RAPs (to the extent they concern impacts on affected people during construction), and any corrective or preventative actions set out in a Safeguards Monitoring Report;

Complied.

(b) Make available a budget for all such environmental and social measures;

Partial compliance. Budget will be continuously adjusted based on actual requirements.

(c) Provide the Borrower with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the EIAs, the EMPs, or the RAPs.

Not complied with. For Ongoing compliance.

(d) Adequately record the condition of roads, agricultural land and other infrastructure prior to the starting to transport materials and construction; and

Complied. For Ongoing on-going monitoring during construction.

(e) Fully reinstate pathways, other local infrastructure; and agricultural land to at least their pre-project condition upon the completion of the construction.

Complied. For Ongoing on-going monitoring during construction.

Safeguards Monitoring and Reporting 14 The Borrower shall, through DOTr, ensure the

following;

Page 54: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

42

Schedule Para No. Covenant Remarks/Issues

(Status of Compliance)

(a) Submit semi-annual Safeguards Monitoring Report to ADB and disclose relevant information from such reports to affected persons promptly upon submission;

Partial compliance with this report. For Ongoing compliance.

(b) If any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the EIAs, the EMPs or the RAPs, promptly inform ADB of the occurrence of such risks or impacts with detailed description of the event and proposed corrective action plan;

Not complied with. For Ongoing compliance.

(c) No later than the date of award of Works contract, engage qualified and experienced external expect or qualified NGO under a selection process and terms of refence acceptable to ADB, to verify information produced through the Project Monitoring process, and facilitate the carrying out of any verification activities by such external experts; and

Partially complied with. Procurement process of External Monitor Agent (EMA) is ongoing.

(d) Report any actual or potential breach of compliance with the measures and requirements set forth in the EMP or the RAP promptly after becoming aware of the breach.

For Ongoing compliance.

Labor Standards, Health and Safety 16 The Borrower shall, through DOTr, ensure that

the core labor standards and the Borrower’s applicable laws and regulations are complied with during Project implementation. The DOTr shall include specific provisions in the bidding documents and contracts financed by ADB under the Project requiring that the contractors, among other things: (a) comply with the Borrower’s applicable labor law and regulations and incorporate applicable workplace occupational safety norms; (b) do not use child labor; (c) do not discriminate workers in respect of employment and occupation; (d) do not use forced labor; (e) allow freedom of association and effectively recognize the right to collective bargaining; and (f) disseminate, or engage appropriate service providers to disseminate, information on the risks of sexually transmitted diseases, including HIV/AIDS, to the employees of contractors engaged under the Project and to members of the local communities surrounding the Project area, particularly women.

Provisions provided in General Specifications (GS) 117 of the Standard Bidding Document (SBD). Ongoing compliance.

17 The Borrower shall, through DOTr, strictly monitor compliance with the requirements set forth in paragraph 16 above and provide ADB with regular reports.

For on-going compliance.

Source: Loan Agreement (Loan Number 3796-PH) dated 11 July 2019. (ADB, 2019)

Page 55: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

43

6 Compliance with ADB and DOTr Inception Review Mission Requirements

78. The status of compliance following the ADB Review Mission conducted in December 2019 is shown

in Table 12 below.

Table 12: Compliance with ADB Review Mission Requirements

Item (Paragraph

Number) Aide Memoire Requirements (Environment)

Remarks (Status of Compliance)

13 First semi-annual safeguard reports (September 2019-March 2020)

14 External Monitoring Agency engagement Not complied. Terms of reference (TOR) drafted and forwarded to ADB on 10 March 2020

15 Submit updated MCRP Environmental Impact Statement (EIS) to DENR-EMB

Complied. Updated MCRP EIS submitted to DENR-EMB on 16 January 2020.

16 Review and provide comments on SCRP EIS to JDT/GCR Complied. Draft SCRP EIS forwarded to GCR

17 Update SCRP EIS Complied. Updated SCRP EIS received by DENR-EMB on 4 March 2020

18 Disclosure of updated SCRP EIS Not complied. EIS was recently submitted and still under review by DENR-EMB.

Source: (ADB and DOTr, 2018)

7 Public consultation, Information Disclosure, Capability Building

79. GC mobilized in early September 2019. For this reason, 2019 meetings, as shown in Table 13 below, are preliminary coordination meetings within project organization. Meetings held with the local project stakeholders were initiated in January 2020. During this reporting period, public consultation and information disclosure were led by GC’s Resettlement Team.

Table 13: Public Consultations/Stakeholders Consultation Meetings

Date Participants Agenda/Subject

October 2019

1 Oct 2019 DOTR and GCR Kick off Meeting in DOTR Central Office Clark Pampanga 2 Oct 2019 JDT and GCR Meeting with JDT RAP Team 3 Oct 2019 DOTR and GCR Meeting with DOTr N1 and N2 RAP Team members 4 Oct 2019 GCR and JDT GCR JDT RAP Meeting 4 Oct 2019 DOTR, GCR and JDT ADB Bi-Weekly Meeting 7 Oct 2019 DOTR, GCR, ADB, PNR,

NHA and HUDCC Team Orientation Meeting at Brgy. Baliti, San Fernando

11 Oct 2019 DOTR and GCR Meeting with DOTr RAP Team 14 Oct 2019 DOTR and GCR N2-SC RAP Meeting with DOTr 15 Oct 2019 DOTR and GCR New Hires Social and Resettlement Orientation 17 Oct 2019 NHA, DOTR, GCR and

HUDCC NHA meeting with DOTr and HUDCC

21 Oct 2019 ADB, DOTr, PNR, JDT and GCR

ADB Bi-Weekly Meeting

23 Oct 2019 DOTr, PNR and GCR Courtesy Meeting with NSCR EX PMO November 2019

4 Nov 2019 DOTr, PNR and GCR DOTr Project Coordination Meeting

Page 56: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

44

Date Participants Agenda/Subject

6 Nov 2019 GCR, LGU, NHA, PNR and DSHUD

Pre-validation Meeting and Workshop on Social Development Program in Calumpit

7 Nov 2019 GCR and PNR Courtesy Meeting with PNR General Manager 8 Nov 2019 DOTR, NHA, LGU, PNR,

ADB, BCDA, GCR, JDT Meeting & Site Inspection in Mabalacat

12 Nov 2019 DOTR and GCR GCR, DOTR Meeting 15 Nov 2019 ADB, DOTR, JDT, PNR

and GCR ADB Bi-Weekly Meeting

15 Nov 2019 DOTR and GCR Meeting on Parcellary Validation 15 Nov 2019 ADB, DOTR, JICA and

GCR ADB Meeting

22 Nov 2019 DOTR and GCR Workshop on NSCR-Ex Project RAP Implementation 26 Nov 2019 LGU, NHA, PNR, DSHUD,

and DOTR Convening of the LIAC in Calumpit

27 Nov 2019 LGU, GCR, DOTR, PNR, and DSHUD

Pre-LIAC Meeting

28 Nov 2019 CDO, GCR, JDT and LGU ADB Meeting December 2019

4 Dec 2019 ADB, PNR, DOTR and GCR

"ADB Inception and 1st Review Mission Meeting with GCR"

5 Dec 2019 ADB, PNR, DOTR and GCR

ADB Mission Meeting with SHFC

10 Dec 2019 LGU, DSHUD, NHA, DOTR and GCR

Pre-Validation and Pre-LIAC Meeting with the LGU of Angeles City

11 Dec 2019 DOTR and GCR GCR RAP meeting with DOTr 13 Dec 2019 JDT, DOTR, PNR and

GCR DOTr-GCR Work Planning Meeting for N2 Mabalacat

January 2020

3 Jan 2020 DOTR, GCA and GCR Locale Housing Boards Meeting for Mabalacat Pampanga 8 Jan 2020 DOTR, GCR, ADB, UPAO,

JDT, SAMANAKA, CAO Locale Housing Boards Meeting for Mabalacat Pampanga

9 Jan 2020 ADB, MMSP-JDT, GCR, ECOSYS CORP, DOTR, OCG-JV

The Detailed Design Study of the Metro Manila Subway Project

9 Jan 2020 ADB, DOTR, ECOSYSCORP, GCR, JDT and OCG- JV

MMSP and SCRP Meeting

10 Jan 2020 PNR, DOTR and GCR PNR SLH Consultative Meeting with GCR 10 Jan 2020 GCR and DOTR Pre-Validation Meeting 14 Jan 2020 GCR, DOTR, PNR, BHW,

ML, PB and CDO Consultation Meeting

14 Jan 2020 GCR and DOTR N2 Coordination Meeting 15 Jan 2020 GCR, PNR, and LGU Consultation and Coordination Meeting in Calumpit Bulacan 16 Jan 2020 GCR, ADB, LGU and NHA Consultation and Coordination Meeting in Calumpit Bulacan 17 Jan 2020 GCR, PNR, DOTR and

LGU Consultation and Coordination Meeting in Calumpit Bulacan

20 Jan 2020 SHFC, DHSUD, DOTR and GCR

SHFC DSHUD Coordination Meeting

23 Jan 2020 GCR, LGU and NHA Consultation and Coordination Meeting in Calumpit Bulacan February 2020

4 Feb 2020 GCR, DOTR and LGU Minalin Pre-Local Housing Board Meeting 4 Feb 2020 GCR, DOTR and LGU Sto. Tomas Ore-Local Housing Board Meeting 4 Feb 2020 GCR LGU, DOTR,

SAMANAKA Tree Validation

4 Feb 2020 GCR LGU, DOTR, SAMANAKA

Tree Ownership Validation

5 Feb 2020 GCR, DOTR and LGU Apalit Pre-Local Housing Board Meeting

Page 57: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

45

Date Participants Agenda/Subject

5 Feb 2020 GCR and LGU Livelihood Meeting with YUMI Farm Owner 6 Feb 2020 GCR, DOTR, LGU Tree Ownership Validation 6 Feb 2020 DOTR and GCR N2-SC ROWSA Meeting 7 Feb 2020 GCR, DOTR, LGU Second Coordination Meeting in Livelihood 12 Feb 2020 DOTR and GCR Coordination Meeting: Tree Ownership Validation in Livelihood 12 Feb 2020 GCR, DOTR, ADB and

LGU Meeting in Minalin with the PAPs

13 Feb 2020 JDT, CSWDO, ADB, PNR, NHA and DHSUD

Meeting with RAP Implementation

14 Feb 2020 Farmer LGU, DOTR and GCR

Coordination Meeting with Mabalacat Farmers

17 Feb 2020 DOTR, LRTA, PNR, ADB MRT3 and GCR

Gender-Based Violence Joint Consultation Meeting

18 Feb 2020 GCR, NHA, PNR and DOTR

Coordination Meting with NHA Region 3, DHSUD and DOTR

20 Feb 2020 GCR and DOTR N2-SC DOTr ROWSA Source: GC, 2019–2020

80. Stakeholders consultation meetings (SCMs) are regularly held with PAPs to update them on the progress of the Project. Summary of past meetings is presented in Table 14 below.

Table 14: Outline of the First Round of Stakeholder Consultation Meetings During Detailed Design

LGU Venue Date and Time

Participant No. of Participants

M F Total

NSCR Clark Extension

Malolos City, Bulacan

Aldaba Hall, Malolos City Integrated School (Malolos Central School), Brgy. Sto. Rosario, Malolos City, Bulacan

17 Jan 2018 08:30 A.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

28 41 69

Municipality of Apalit, Pampanga

Sampaga Covered Court, Brgy. San Vicente, Apalit, Pampanga

17 Jan 2018 08:30 A.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

55 31 86

Municipality of Calumpit, Bulacan

Covered Court, Calumpit Municipal Hall Compound, Calumpit, Bulacan

17 Jan 2018 01:30 P.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

61 88 149

Municipality of Minalin, Pampanga

Technical Training Center, Minalin Municipal Hall, Minalin, Pampanga

17 Jan 2018 01:30 P.M.

LGUs, PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

13 3 16

Municipality of Santo Tomas, Pampanga

Auditorium, Municipal Hall Compound, Santo Tomas, Pampanga

18 Jan 2018 08:30 A.M.

LGUs, PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

24 3 27

City of Angeles, Pampanga

New Legislative Building, City Hall

18 Jan 2018 08:30 A.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team

45 38 83

Page 58: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

46

LGU Venue Date and Time

Participant No. of Participants

M F Total

Compound, Angeles City, Pampanga

Representatives, EcosysCorp, Inc.

City of San Fernando, Pampanga

Covered Court, Brgy. Santo Niño, City of San Fernando, Pampanga

18 Jan 2018 01:30 P.M.

LGUs, PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

57 46 103

Mabalacat City, Pampanga

Xevera Covered Court, Xevera Compound, Brgy. Tabun, Mabalacat, Pampanga

18 Jan 2018 01:30 P.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

186 354 540

Total 469 604 1.073 NSCR Calamba Extension

Manila City Dapitan Sports Complex

22 Jan 2018 09:00 A.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

94 80 174

Covered Court, Brgy. 811

22 Jan 2018 02:00 P.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

114 208 322

Sases Covered Court, Brgy.803

2 Feb 2018 8:30 A.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

125 268 393

Sarmiento Community Center, Brgy. 592

2 Feb 2018 8:30 A.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

62 96 152

Jacinto Ciria Cruz Covered Court, Brgy. 860

2 Feb 2018 2:00 P.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

189 374 563

Basketball Court, Brgy. 511

2 Feb 2018 2:00 P.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

97 214 311

Basketball Court, Brgy. 503

3 Feb 2018 8:30 A.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

21 38 59

Barangay Hall, Brgy. 368

3 Feb 2018 8:30 A.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

101 220 321

Covered Court, 3 Feb 2018 PAPs, BLGUs, DOTr 13 12 25

Page 59: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

47

LGU Venue Date and Time

Participant No. of Participants

M F Total

Brgy. 224 2:00 P.M Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

Domingo Santiago Covered Court, Brgy. 576

3 Feb 2018 2:00 P.M

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

204 361 565

Brgy. 629 Covered Court

11 Apr 2018 9:00 A.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

42 68 110

Aldana Elementary School, Brgy. 422

11 Apr 2018 2:00 P.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

82 145 227

Brgy. 473, Algeciras Cor. Florentino Sts.

12 Apr 2018 9:00 A.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

96 156 252

Brgy. 483, Algeciras Cor. Maria Clara Sts.

12 Apr 2018 2:00 P.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

67 206 273

Brgy. 443, Algeciras Cor. Firmeza Sts.

12 Apr 2018 4:00 P.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

47 75 122

Brgy. 348, Old Antipolo cor. Oroquieta Sts. (Blumentritt Station)

13 Apr 2018 9:00 A.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

126 176 302

Brgy. 224 Covered Court

13 Apr 2018 2:00 P.M.

PAPs, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

20 26 46

Makati City Multi-Purpose Room, 7th Floor, Makati City Hall Building 2

17 Jan 2018 09:00 A.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

4 2 6

Taguig City Covered Court, Brgy. Fort Bonifacio

19 Jan 2018 09:00 A.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

14 34 48

Covered Court, Brgy. South Daang-Hari

19 Jan 2018 02:00 P.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives,

39 52 91

Page 60: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

48

LGU Venue Date and Time

Participant No. of Participants

M F Total

EcosysCorp, Inc. Parañaque City

Brgy, Hall, San Martin De Porres

17 Jan 2018 02:00 P.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

3 2 5

Muntinlupa City Baywalk Covered Court, Brgy. Bayanan

18 Jan 2018 02:00 P.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

39 81 120

Barangay Hall, Brgy. Alabang

31 Jan 2018 08:30 A.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

48 87 135

Brgy. Hall Covered Court, Brgy. Poblacion

31 Jan 2018 02:00 P.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

40 74 114

San Pedro City Pavillion Hall, 5th Floor, San Pedro City Hall

18 Jan 2018 08:30 A.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

28 66 94

Biñan City Biñan People’s Center

18 Jan 2018 02:00 P.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

55 204 259

Sta. Rosa City West Drive Covered Court, Brgy. Labas

19 Jan 2018 08:30 A.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

44 97 141

Cabuyao City AVR, Cabuyao City Hall

18 Jan 2018 02:00 P.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

89 53 142

Calamba City LLC Auditorium, Central 2

19 Jan 2018 02:00 P.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

71 127 198

Covered Court, Brgy. Pansol

1 Feb 2018 09:00 A.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

57 152 209

Covered Court, Brgy. Parian

1 Feb 2018 02:00 P.M.

LGU, BLGUs, DOTr Representatives, JICA Design Team Representatives, EcosysCorp, Inc.

13 61 74

Total 1,996 3,815 5,853 Source: (DOTr, 2020)

Page 61: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

49

81. The EA is working on creating Information, Education and Communication (IEC) materials that include brochures and posters. These materials are distributed through the Grievance Redress Mechanism (GRM) Team and can be found at the Help Desks of each LGUs. These materials are also planned to be distributed in future SCMs of the project.

82. Trainings. During the reporting period, five (5) Key NSCR EX PMO staff attended Environmental Training for Managing Heads, and Basic Pollution Control Officers Trainings as shown in Table 15 below

Table 15: Trainings Attended by DOTr Staff

Training Title DOTr Staff Date

8 Hours Environmental Training for Managing Heads (DENR-EMB COR No. 2019-04-R)

Ahn Meg J. Adonis 21 Jan 2019

8 Hours Environmental Training for Managing Heads (DENR-EMB COR No. 2019-04-R)

Leonel Cray P De Velez 21 Jan 2019

Basic Pollution Control Officers 40-Hours Training Course (DENR-EMB COR No. 2019-04-R)

Monica C. Francisco 18 to 22 Nov 2019

Basic Pollution Control Officers 40-Hours Training Course (DENR-EMB COR No. 2019-04-R)

Rose Venette M. Henson 18 to 22 Nov 2019

Basic Pollution Control Officers 40-Hours Training Course (DENR-EMB COR No. 2019-04-R)

Vincent Jorie Dieg G. Rosales 18 to 22 Nov 2019

Source: DOTr, 2020.

8 Grievance Redress Mechanism

83. A summary of grievances was compiled during the last CMR submission to EMB CO and is attached as Appendix N. The record shows the grievances received as of 19 December 2019, which are mostly regarding resettlement issues.

• Number of new grievances, if any, since last monitoring period: 147

• Number of grievances resolved: 138

• Number of outstanding grievances: 9

Table 16: Grievances Received by the Projects of 19 December 2019

Grievance NSCR Clark Extension NSCR Calamba Extension Total

Compensation 4 9 13 Demolition concerns 3 5 8 Inquiry appraisal 1 1 2 Inquiry master list 0 11 11 Inquiry resettlement 1 3 4 Inquiry ROW map 10 16 26 Inquiry tax declaration 0 1 1 Inquiry timeline 2 4 6 Meeting request 0 3 3 Ownership validation 6 3 9 Relocation concerns 3 10 13 Relocation extra-judicial settlement 3 1 4 Request for fences 1 0 1

Page 62: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

50

Grievance NSCR Clark Extension NSCR Calamba Extension Total

Request for realignment 0 1 1 Request for updates 0 1 1 Survey 4 3 7 Tagging concerns 7 30 37 Total 45 102 147

Source: Grievance Desks of the LGUs

III. Conclusion

84. The Project is essentially still in its pre-construction and preparatory stage. The safeguard elements to be complied with at this stage include the necessary pre-construction requirements that need to be undertaken to facilitate the implementation of the Project such as, but not limited to, the following:

1) Monitoring and reporting of DOTr’s project’s environmental compliance requirements to the DENR EMB CO

2) Incorporating the EIS, EMP and EMoP in the tender documentation 3) Review and updating of the EIS, EMP and EMoP considering the changes during the detailed

design 4) Preparation of the SDP designed for adequately addressing the requirements of Project

stakeholders 5) The continuous conduct of meaningful consultations (Section II.7), wherein stakeholder

consultations were undertaken both during the FS and the DD stages 6) Iinitiation of safeguards capacity building for NSCR EX PMO Staff

85. As construction activities commence, issues on the environment will continue to be given even more further importance and emphasis during stakeholder consultations.

86. When procedural non-compliance and delays occur (especially with ECC conditions and General Specifications indicated in the tender documents), relevant government agencies and offices will be notified and consulted accordingly. DOTr, with the assistance from the GC and EMA, will formally communicate non-compliances and delays, causes, and proposed corrective actions and solutions to comply with mandated requirements.

87. For public information, DOTr, with the assistance from the GC, will initiate dissemination of potential procedural non-compliance and delays to the communities through public consultations, the tri-media, the social media, Project Help Desks, and the GRM, among other means, in coordination with the respective LGUs and the MMT.

88. The DOTr had submitted revised EIS, EMP and EMoP and had informed the EMB-CO and other agencies of the relevant changes in these documents. The DOTr will closely coordinate with EMB-CO regarding their concerns on these submissions. Once the revised EMP and EMoP are concurred by the EMB CO, these shall be officially transmitted to the General Consultant (GCR Consortium, currently on-board), and the civil works contractors. GCR will then provide assistance to the DOTr in the proper implementation of the revised EMP and EMoP. An amended ECC is anticipated to be issued following these submissions. Same shall be forwarded to GCR and the contractors for implementation of the compliance requirements.

89. The project had been prepared and tendered with safeguard requirements of both the Government, ADB, and JICA taken into consideration. These safeguard commitments are incorporated in documents that will eventually become contractual obligations that the Contractors will be required to comply.

90. DOTr has executed the preparatory activities to comply with project safeguards commitments amidst institutional limitations. DOTr continues to build the number of staff, and their environmental

Page 63: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

51

management capability are being strengthened through hands-on experience and through available relevant environment training opportunities. These are necessary to prepare them to take on their roles and responsibilities for the environment safeguards requirements of the project.

91. The major tasks accomplished during the reporting period are those relating to ECC compliance which are deemed very important to proceed with project implementation while waiting for the actual construction activities to commence. The EIS and its component plans, e.g., EMP, EMoP, SDP, have been harmonized with the changes brought about by the improved Project design and has been reported to DENR-EMB CO, ADB, and JICA. Relevant activities such as tree inventory have been conducted, which are done in conjunction with the RAP preparation activities.

92. Overall, Project preparation and pre-construction execution are generally compliant with safeguards commitments. However, as the project nears the construction stage, additional efforts shall still be exerted to meet the environmental management and monitoring requirements of the project. The following are being recommended:

a) Continued coordination among and across teams through timely communication and provision of complete and updated information;

b) A register of lessons learned shall be maintained in order to apply the same in similar future situations;

c) Continued IEC to apprise the stakeholders of project progress and development; d) Increase the number and diversity of DOTr environment staff; e) Continuous capability-building investment on a wider range of safeguard subject matters for the

DOTr staff; f) Contractors when they come on board shall undergo environment (and social) safeguards induction

training to orient them of the environmental (and social) safeguards requirements of the project; g) Contractors must have capable environmental staff (in its Environmental Management Unit) to

manage the environmental management and monitoring requirements of their contracts; and h) Contractor management must provide the resources to enable their staff to perform their work

alongside DOTr and the GC.

93. Activities that are planned in the next reporting period following the completion of the preparatory activities, and award of construction contracts include but not limited to the following:

• Coordinate closely with the EMB-CO for the issuance of an amended ECC following their satisfactory review of the submitted revised EIS, EMP and EMoP;

• Provide copies of the updated DD EIS, ECC and EMP to the Contractors as basis for the preparation of their CEMMP consistent with the requirements of General Specifications 118 (GS118) of the Contractors’ contracts;

• Baseline environmental quality measurements to be conducted by the Contractors as required in the EMP;

• Increase the number of DOTr EMU Staff to oversee GCR and Contractor EMP and EMoP implementation;

• From among the DOTr EMU staff, send as many of these staff for PCO training, and designate adequate number of candidates per region who will be responsible for reporting in compliance with EMB CO requirements under the PEISS;

• GCR to approve the CEMPs and copies provided to DOTr and ADB for review; • Award of the contract for EMA currently being tendered by GCR; • Development and refinement of Monitoring Manual that includes monitoring and reporting

checklists (sample report templates are provided here as Appendix O to this updated SEMR) • Establishment of registers of project activities, documents, incidents, among other information that

will be useful for project supervision, and will form part of important inputs to the project completion report (Appendix P);

• Improved IEC Program and its implementation;

Page 64: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

52

• Conduct public consultations using recent project information to Project-affected communities and LGU officials emphasizing environment, and community health and safety;

• Completion and finalization of draft SDP; • Submission to DENR of the third Compliance Monitoring Report (CMR); • Submission of detailed plan for tree cutting and earth-balling, and replanting of native/endemic

trees to DENR; • Greening Program MOA signing between DENR, DOTr and PNR; • Tree cutting permit issuance by DENR Region 3 and PCA; • Conduct of the detailed Traffic Impact Assessment (TIA) in coordination with the concerned LGUs

for every proposed station prior to Project construction; • Establishment of MMT, EMF and EGF; • Engagement of the EMA; • Establishment and commencement of formal operations of HSEC; • Review and approval of Contractor’s Waste Management Plan (WMP) and Construction

Environmental Management and Monitoring Plan (CEMMP); • Review and approval of updated DD EIS by DENR-EMB; • Diligent updating and coordination with concerned government agencies, LGUs, businesses and

communities on the potential changes in project scope; • DOTr and GCR will monitor compliance to the EMP and EMoP by the Contractors; and • Integrate monitoring results in the next SEMR for submission to the ADB. Copies of the SEMR shall

be provided to the EMA for their assessment as well.

Page 65: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

53

IV. Appendices

Appendix A: Consents/Permits (Environmental Compliance Certificates)

Appendix B: Environmental Management Plan

Appendix C: External Monitoring Agent Terms of Reference

Appendix D: Directory of Project Staff for the Implementation of the Environmental Compliance Requirements

Appendix E: General Consideration for the SDP (N2)

Appendix F: Compliance Monitoring Reports (Submitted through DENR website https://online.emb.gov.ph/cmr/)

Appendix G: Waste Management Program (N2)

Appendix H: Certificates of No Objection

Appendix I: Traffic Impact Assessment (N2)

Appendix J: NSCR EX PMO Organizational Chart

Appendix K: General Consideration for the SDP (SC)

Appendix L: Waste Management Program (SC)

Appendix M: Traffic Impact Assessment (SC)

Appendix N: Summary of Grievances Received

Appendix O: Monitoring Manual Outline

Appendix P: Summary Registers for Project Supervision

Page 66: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Monitoring Report Semi-annual Environmental Monitoring Report No. 1 March 2020

Appendix A: Consents/Permits (Environmental Compliance Certificates)

PHI: Malolos-Clark Railway Project – Tranche 1 Prepared by the Project Management Office (PMO) of the Department of Transportation (DOTr) for the Government of the Republic of the Philippines and the Asian Development Bank.

Page 67: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 68: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 69: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 70: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 71: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 72: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 73: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 74: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 75: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 76: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 77: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 78: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 79: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 80: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 81: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 82: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section
Page 83: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Monitoring Report Semi-annual Environmental Monitoring Report No. 1 March 2020

Appendix B: Environmental Management Plan

PHI: Malolos-Clark Railway Project – Tranche 1 Prepared by the Project Management Office (PMO) of the Department of Transportation (DOTr) for the Government of the Republic of the Philippines and the Asian Development Bank.

Page 84: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-1

4. ENVIRONMENTAL MANAGEMENT PLAN 1651. The DOTr is committed to minimize any adverse impacts, which could arise from the construction, operation, and abandonment of the proposed project. It will do so by formulating an Environmental Management Program (EMP) to manage the Project’s impacts and risks, adopt the best available proven control technologies and procedures, undergo a continuing process of review and positive action in the light of available monitoring results and continuing consultation with the local communities. Regular consultations with the affected people and relevant offices/ agencies will be conducted by the contractor during construction phase and by the DOTr during operation phase to ensure adequate and timely mitigation of project adverse environmental impacts. DOTr will provide notification to DENR-EMB, ADB, and JICA on any unanticipated environmental risks or impacts that arise during construction, implementation, and/or operation of the Project that were not considered in the EIS and EMP.

1652. Basically, the EMP aims to achieve an exemplary environmental performance in the pre-construction, construction, and operation of the Project. In order to meet this goal, the following activities/ measures/ programs will have to be implemented:

Environmental Policy;

Application of Mitigation/ Management Measures;

Environmental Monitoring Program;

Social Development Program;

Emergency and Contingency Plan;

Information, Education and Communication Plan;

Construction Contractor’s Program; and

Institutional Plan and Hiring of an Environmental/Safety Officer.

1653. Overall, the DOTr is the Implementing Agency of the Project. The Project Management Office (PMO) for the North-South Commuter Railway Extension Project (NSCR-Ex), DOTr is the primary point of contact with DENR-EMB, ADB and JICA with regards to environmental management of the Project. The following chapters of the EIS is included in the bid documents: Chapter 4 (Environmental Management Plan), Chapter 8 (Environmental Compliance Monitoring), and Chapter 10 (Institutional Arrangements for EMP Implementation), to ensure that the mitigation measures will be properly implemented and monitored during all phases of the Project. The project will hire General Consultant (GC) that includes an International Environment Specialist and a National Environment Specialist that will assist the DOTr in the monitoring of compliance of the project with the EMP. During project implementation, the DOTr-PMO will be assisted by a third party environmental consultant/monitor in the monitoring of environmental parameters of the Project.

1654. Table 4.1.1 presents the EMP for the proposed Project.

Page 85: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-2

Table 4.1.1 Environmental Management Plan for the Proposed Project

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

GENERAL

Pre-construction, Construction and Operation activities

Land, Water, Air and People

Comply with the relevant laws: RA 6969: Storage, transport, handling, treatment and disposal of hazardous waste Secure hazardous waste generator’s ID from

DENR-EMB;

Provision of hazardous materials storage area;

Hazardous materials/ wastes will be stored in appropriate container properly sealed and labelled;

Hazardous waste will be hauled by an accredited transporter;

Hazardous waste will be treated by a registered treater (TSD Facility)

RA 9003: Management and disposal of solid wastes Waste segregation, recycling, provision of waste

color coded bins, etc.;

Provision of Material Recovery Facility (MRF);

Regular hauling of solid wastes through the LGU or private contractor.

RA 8749: Comprehensive Air Pollution Control Policy Secure permit to operate for all air pollution

source installations (i.e genset);

Regular inspection and preventive maintenance of heavy equipment, machineries and service vehicles to meet the DENR Emission Standard;

Regular cleaning and clearing of construction access / sites surfaces of spoils and debris from construction equipment and vehicles and wetting of ground soil in the construction site when necessary;

Implement: Contractors

Operators

Monitor: DOTr PMO

GC

LGUs

MMT

DENR-EMB

Contractor and operator’s service fee on health, safety and environmental management RA 6969: PhP

100,000 per year

RA 9003: PhP 400,000 per year

RA 8749: PhP 400,000 per year

RA 9275: PhP 400,000 per year

PD 442: PhP 6,000 per worker

PD 856: PhP 50,000 per year

Sanitary facility: PhP 200,000 per site

Emergency Response Plan and Health and Safety Management

EGF/ Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 4th Quarter of 2022

Page 86: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-3

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Control vehicle movement maintaining the speed limit within the construction site to <10 kph and provide cover to loaded trucks.

RA 9275: Comprehensive Water Quality Management and for Other Purposes Secure discharge permit;

Provision of Wastewater Treatment Facility at the depot;

Provision of three-chambered septic tank at each station.

PD 442: Labor Code of the Philippines, as amended (including Occupational Safety and Health Standards) Gender equality will be considered in hiring of

workers;

Include medical certificate in the requirements for hiring of workers to ensure that they are fit to work. Ensure that they are provided with proper training on construction, occupational health and safety, and emergency response procedure;

Provide appropriate personal protective equipment (PPE) to all construction workers, particularly to the personnel working on heights, heavy and electrical equipment;

Establish Health and Safety Desk or Medical Station at the active construction sites to monitor and safeguard the health of the workers and local residents and to provide immediate response during unexpected incidents/emergencies;

Close coordination with the nearest hospitals in the active construction site for immediate transfer and/or further evaluation and medical management of the patient.

RA 8504: Philippine AIDS Prevention and Control Act of 1998

Plan: PhP 300,000

Health and Safety Desk or Medical Station: PhP 200,000 per site

PhP 1,500 per man-hour

Page 87: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-4

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Education of employees on standardized basic HIV/AIDS information and instruction

PD 856: Sanitation Code of the Philippines Provide safe and clean water for drinking;

Provision of appropriate sanitary facilities such as portable toilets and waste bins.

Implementation of Emergency Response Plan and Health and Safety Management Plan to include but not limited to: Distribution of manual/guideline for

workers/employee on health safety and environmental management;

Orientation and continuous training of qualified workers/ employee/ operator on Environment Management, Basic and Construction Occupational Safety and Health, Scaffolding Safety, Fire Safety and Safe Use of Chemicals at Work;

Provision of earthquake, fire drills for workers;

Provision of appropriate PPE for workers;

Provision of security personnel.

Regular monitoring of site condition PRE-CONSTRUCTION / CONSTRUCTION

BASELINE ENVIRONMENTAL QUALITY MEASUREMENTS

Environmental Quality Air Quality Noise Vibration Surface

Water Quality

Groundwater Quality

Soil Contamination

Baseline sampling at the depot site and other locations where necessary as indicated in Environmental Monitoring Plan (Table 8.1.1).

Implement: Contractor

Monitor: GC

DOTr PMO

MMT

Third Party Monitoring Contractor

DENR-EMB

Contract’s service cost

PhP 30,000 to 80,000 per air sampling station

PhP 25,000 per noise monitoring station

PhP 80,000 per vibration

Contract Agreement

Before any activities are started on the sites

Page 88: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-5

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

monitoring station

PhP 25,000 per water sampling station

PhP 25,000 per Soil sampling station

PhP 1,500 per man-hour

CONTRACTOR’S ENVIRONMENTAL MANAGEMENT PLAN (CEMP) Contractor’s EMP EMP

Implemen-tation

[Pre-Construction] Prior to start of site works and within 60 days

upon receipt of the notice to proceed, the contractor shall prepare a site-specific Contractor’s Environmental Management Plan (CEMP) based on the EMP in the EIS. The CEMP will describe the scope of works and schedule, construction methodology, facilities and site conditions, including sensitive receptors in the contract area. The CEMP should include the detailed operational plan for the implementation of the EMP/CEMP with targets/indicators over a specific timeline that would be monitored for milestone highlights. The CEMP will be submitted to the project supervision consultant for approval with copies provided for review by DOTr and ADB. The following specific management plans shall be included in the CEMP:

Dust and Emission Control Plan. The plan shall provide details of mitigation measures, specific location and schedule where such measures shall be implemented to minimize impacts to sensitive receptors (residential areas, schools, hospitals, etc.) due to construction

Implement: Contractor

GC to assist

Monitor: DOTr PMO

GC

MMT

DENR-EMB

Contract’s service cost

PhP 1,500 per man-hour

Contract Agreement

CEMPs will be submitted and cleared no later than one month before site activities are started.

Page 89: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-6

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

works, sourcing and transport of construction materials, operation of construction equipment and other project-related activities.

Noise Control Plan. The plan shall provide details of mitigation measures, specific location and schedule where such measures shall be implemented to minimize impacts to sensitive receptors (residential areas, schools, hospitals, etc.) due to construction works, sourcing and transport of construction materials, and other project-related activities.

Vibration Management Protocol. The protocol shall specify how to pace the piling and other heavy machinery operation to avoid vibration impacts

Construction Camp and Worker Camp Lay-out and Management

Quarry and Construction Layout and Management

Spoils Management and Disposal

Erosion and Sediment Control

Solid and Liquid Wastes Management

Hazardous Materials and Wastes Management – includes measures to address spills of hazardous substances

Water Availability and Pollution Control

Construction and Decommissioning Plan of Worker Camps and other Construction Facilities – includes workshops, fabrication yards, quarries, etc.

Vegetation Clearing, Landscaping and Re-vegetation Plan

Damage to Properties and Facilities Management

Traffic Management and Community Access Plan. The plan shall be designed to ensure that traffic congestion due to construction activities and movement of construction vehicles, haulage

Page 90: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-7

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

trucks, and equipment is minimized. The plan shall be prepared in consultation with concerned traffic agencies, local officials and the general public. The plan shall identify traffic diversion and management, traffic schedules, traffic arrangements showing all detours, necessary barricades, warning/advisory signs, road signs, lighting, and other provisions to ensure that adequate and safe access is provided to motorists and the public in the affected areas.

Occupational Safety and Project Personnel Health Program consistent with the Labor Code of the Philippines and international standards (e.g., the World Bank Group’s Environment, Health and Safety Guidelines of 2012). The plan shall address health and safety hazards associated with construction activities (e.g., excavations, working at heights, etc.), establishment and operation of construction/worker’s camps, use of heavy equipment, transport of materials and other hazards associated with various construction activities; includes HIV/AIDS awareness and prevention.

Community and Public Health and Safety Plan

Emergency Preparedness and Response Plan to prevent, mitigate, respond to and recover from emergency events that could occur due to project activities such as accidents, spills of hazardous substances, fire, extreme weather events, and other crises.

Cultural Resources Protection and Preservation

Personnel Training and Awareness Program

De-commissioning Plan

LAND

Page 91: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-8

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Land acquisition for the project ROW

Land use and Classifica-tion

Incompati-bility with the Existing Land Use

C- [Pre-Construction/ Construction] Maximize the use of existing PNR ROW from

Malolos to Clark and BCDA property from Clark to NCC

Information sharing to the affected LGU to align and ensure that the Project will be accommodated in their future land use plan

Identification of future land use of surrounding areas that will result to a significant increase of transportation-oriented developments (TOD) in cooperation with urban planners of LGUs to adopt in the future developments.

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

[Construction] implement GC

DOTr PMO

Monitor:

MMT

DENR-EMB

DED /GC cost, DOTr IEC Cost PhP 1,500 per

man-hour

Contract agreements

3rd Quarter of 2018 to 2nd Quarter of 2019

Construction at the following: Areas with the

existing old PNR structures

Areas with high risk to typhoon passage, high susceptibility to flooding

Prime agricultural areas in depot

ECA Incompati-bility with Classifica-tion as an ECA

B- [Pre-Construction/ Construction] Plan and design the site, structure foundation,

and structure including construction activities in consideration to the ECAs.

Coordinate with relevant government agencies and stakeholders as required

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

[Construction] Implement: Contractor

DOTr PMO

GC

Monitor: DOTr PMO

GC

LGUs

MMT

DENR-EMB

DED Cost/ GC cost, DOTr IEC cost

PhP 1,500 per man-hour

Contract agreements

3rd Quarter of 2018 to 2nd Quarter of 2019

Page 92: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-9

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Land acquisition for the project ROW

Land Tenure

Involuntary resettle-ment of informal settlers who had encroach-ed portion of the existing PNR ROW; settle-ments outside the existing PNR ROW

B- [Pre-Construction] Implement Resettlement Action Plan in

coordination with KSAs/ NHA, LGUs, lot owners and other concerned stakeholders and agencies to address the issue on land acquisition and relocation of informal settlers.

Implement: DOTr PMO

KSAs

GC

LGUs

Monitor: DOTr PMO (Internal

Monitoring)

External Monitoring Agents

As per RAP Budget

Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2019

Potential conflict with other govern-ment infrastruc-ture projects

B- [Pre-Construction] Coordinate with BCDA, DPWH, and other

relevant agencies

Implement: DOTr PMO

DED Consultant

GC

DED / GC cost, DOTr IEC cost

PhP 1,500 per man-hour

Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2019

Areas with CADT/CADC

B- [Pre-Construction] Coordinate with the NCIP and conduct FBI to

determine the possible overlap with the CADT/CADC

Implement: DOTr PMO

DED Consultant

GC

PhP 1,500 per man-hour

DOTr Budget 3rd Quarter of 2018 to 3rd Quarter of 2019

Construction activities Visual Aesthetic and Land Use

Degrada-tion of aesthetic view and land architect-ture

B- [Pre-Construction/ Construction] Design and install facilities to harmonize with the

surrounding environments (shape, color, size, etc.)

Identify planting area within the ROW that will not be covered by development to act as buffer zone, green corridor and to lessen aesthetic sore brought by construction and railway structures, and plant trees

[Pre-Construction] Implement: DED Consultant

GC

DOTr PMO

[Construction] Implement: Contractor

DED/GC cost, Construction cost

PhP 1,500 per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 93: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-10

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Adequately record the condition of roads, agricultural land and other infrastructure prior to start transport materials and construction

[Construction] Maintain the construction site/ yards tidy and

clean and rehabilitate after construction.

Provision for temporary screens/ walls to minimize the visual clutter.

Fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.

Monitor: DOTr PMO

GC

MMT

Generation and improper handling and disposal of domestic and hazardous solid waste.

Land Value Devalua-tion of land value as a result of improper solid waste manage-ment

B- [Pre-Construction] Prepare a Waste Management Plan (WMP).

[Construction] Implement WMP including strict implementation

of solid waste management plan and proper disposal by contractor in accordance with RA 9003, hazardous waste disposal in accordance with RA 6969

Conduct Social Development Plan (SDP) including waste management to the communities

[Pre-Construction] Implement:

Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

DENR- EMB

[Construction] Implement: Contractors

DOTr PMO

Monitor: GC

DOTr PMO

MMT

DENR-EMB

Contractor’s service cost/ DOTr SDP cost

PhP 1,500 per man-hour

PhP 50,000 per activity

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Generation and improper handling and disposal of excavated

Land Value Devalua-tion of land value as a result of

B- [Pre-Construction/Construction] Plan and Implement the spoils management and

disposal plan.

Implement: Contractors

Construction cost

PhP 1,500 per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 94: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-11

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

soil, leftover concrete by excavation activities

improper handling of excavated soil

Plan and implement recycling and reuse of excavated soil to be utilized for the project/ other project as much as possible. In case of excessive soil to be generated, identify the final spoil disposal site.

[Construction] Place excavated materials on appropriate dump

sites or spoils area and with adequate containment.

Strictly implement construction plan, soil management plan, and proper disposal by contractor in accordance to RA 9003, minimization of waste, segregation.

Monitor: DOTr PMO

GC

MMT

DENR-EMB

Construction of embankment/slope protection

Topography Permanent modifica-tion of the terrain and alteration of landform may cause ground failure

C- [Pre-Construction /Construction] Formulate and implement appropriate design

measures for the protection on slopes and banks, soil improvement / ground reinforcement to minimize ground failure during construction based on the results of the geological survey and geotechnical investigations.

[Pre-Construction] Implement: DED Consultant

DOTr PMO GC

[Construction] Implement: Contractors

Monitor:

DOTr PMO

GC

MMT

DENR-EMB

DED/GC cost,

Construction cost

PhP 1,500 per man-hour

Soil Improvement: PhP 30,000 per m³

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Earthworks, (excavation, backfilling, stockpiling, tunneling/ underground, elevated tracks/platforms) and natural hazards

Geology/ Geomor-phology

Ground Subsi-dence Liquefac-tion Land-slide, Mud/ Debris

B- [Pre-Construction/Construction] Design and implement appropriate foundation

and structures based on combination of geotechnical, geodetic and hydrologic study, and seismicity studies, and in compliance with the National Building Code and the Structural Code of the Philippines and internationally accepted guideline.

[Pre-Construction] Implement:

DOTr PMO DED Consultant

GC

[Construction] Implement:

DED/GC cost, Construction cost

PhP 1,500 per man-hour

Soil Improvement:

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 95: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-12

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Flow, etc.

Founda-tion of piers of elevated struc-tures may cause unequal settle-ment of road surfaces.

Design and install emergency escape route, early warning (alarm) system, emergency power supplies in the design of the structure particularly in the viaduct.

Plan and implement appropriate construction method, schedule, and activities based on combination of geotechnical and geological investigations, and seismicity studies in coordination with the PHIVOLCS.

[Construction] Install sufficient protection measure such as soil

improvements during excavation activities and implement appropriate materials handling program or a site protection and rehabilitation program.

Proper inspection of all installed and constructed / ongoing construction structures and facilities.

Coordinate with the PHIVOLCS during earthquake and volcanic events to adjust construction schedule. Conduct earthquake drills for workers.

Use earth pressure balance (EPB) technique with the Tunnel Boring Machine (TBM) to prevent collapse of soil.

Construct diaphragm wall using polymer and bentonite

Avoid simultaneous excavation in areas near river.

Monitor land subsidence.

Compact soil in excavation area.

The contractor will be required to implement construction methods through underpinning of the existing structures to control vertical and horizontal settlement of road, bridges and other existing buildings.

Contractors

Monitor: DOTr PMO

GC

MMT

DENR-EMB

PhP 30,000 per m³

Clearing and removal of vegetation, stripping of soil cover,

Pedology Soil erosion/

B- [Pre-Construction/ Construction] [Pre-Construction] Implement:

DED /GC cost, Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd

Page 96: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-13

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

excavation of underlying rock, grading or construction of embankments and works in depot.

loss of top soil

Design and install slope protection/ soil erosion control to prevent or minimize slope failure during construction based on the results of the geo-hazard assessment and geotechnical investigations.

[Construction] Minimize the removal of vegetation cover as

much as possible, provision of slope stabilization measure/s, when necessary.

Install surface water runoff drainage systems, protection of slope and bank as required.

Provide drainage system with sedimentation pond and temporary ditches to collect runoff and settle sediments before discharge to the public drainage system.

Clean and de-clog drainage canals surrounding the work sites and depot regularly.

Implement appropriate materials handling program or a site protection and rehabilitation program including but not limited to the following;

Schedule clearing and excavation activities in a speedy manner during dry season if possible.

Installation of temporary erosion ponds or silt traps around the major work areas.

Placement of excavated materials on appropriate staging site or spoils area and with adequate containment. Limit stock pile height up to 2 m high only. Cover stockpile of excavated soil. Also Install silt traps, deviation channels, mounting, barriers or trenches around the stockpiles.

Installation of fence at the stockpiles of sand and gravel to reduce sediment transport during heavy rains including reduction of storage time in the work areas.

Underground works and similar excavation should be adequately braced.

DOTr PMO

DED Consultant

GC

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

MMT

DENR-EMB

Construction cost

Soil Erosion Control: PhP 30,000 per m²

Drainage System: PhP 15,000 per meter

Quarter of 2022

Page 97: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-14

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

For bored pile construction, the use of bentonite or polymer slurry is highly recommended, to stabilize uncased borings in loose soils.

Utilize heavy equipment for transporting, hauling and excavating material from one area to another so as to avoid spills into drainage system

Place construction materials in suitable areas, away from surface waters, canals and drains.

Schedule excavation works, levelling of area, removal of public utilities, e.g. water pipes, drain pipes, electric poles, etc. during the dry season to avoid soil erosion problems.

Designate 2-3 workers to be in-charge of cleaning the site and clearing the construction materials scraps such as soil, rock, sand, and lime that are scattered onto the construction areas and road surfaces every day or within 24 hours to avoid the obstruction of natural flow, especially during the wet season.

Accidental spills of fuels /lubricants from construction vehicles & machineries/ hazardous chemicals. Generation and improper handling/ disposal of construction/ domestic /hazardous wastes.

Pedology Degrada-tion of soil quality because of soil contamina-tion

B- [Construction] Proper inspection and maintenance of machines

and equipment.

Strictly implement solid waste management plan and proper disposal by contractor in accordance with RA 9003, hazardous waste disposal in accordance with RA 6969.

Conduct soil quality monitoring in case of any possible contamination events occur.

Implement: Contractors

Monitor: DOTr PMO

GC

MMT

DENR-EMB

Contractor’s Service Cost: RA 9003: PhP

400,000 per year

RA 6969: PhP 100,000 per year

PhP 25,000 per soil sample

Bid Documents/ Contract Agreement

3rd Quarter of 2019 to 2nd Quarter of 2022

Drilling and excavation at previously contaminated site (e.g. Old Calumpit Dump Site)

Pedology Exposure to contamina-ted soil

C [Pre-Construction/ Construction] Identify a potentially contaminated site and

conduct of soil sampling survey, if necessary.

Conduct Environmental Site Assessment if there is suspected contamination on the proposed location of facilities. In case that toxic substances are found within the project area

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

DED /GC cost, Contractor’s Service cost PhP 1,500 per

man-hour

EGF/Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 98: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-15

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

and/or adjacent sites, prepare contaminated soil management plan and implement necessary remediation measures.

Storage, handling, transport, treatment and disposal of contaminated soil will be in accordance with RA 6969

[Construction] Conduct continuous monitoring of toxic level to

ensure that contaminants will not pose hazards. In case traces are detected, construction activities on affected site will be paused until a soil management plan is developed and implemented in consultation to the DENR – EMB.

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

DENR-EMB

PhP 25,000 per soil sample

ESA Phase I: PhP 150,000 per site

ESA Phase II: PhP 1,000,000 per site

ESA Phase III: depends on the extent of contamination

Removal of vegetation along the proposed project particularly the trees at some areas along the ROW, and depot area

Terrestrial Ecology (Flora)

Loss of Habitat

Threat to Exis-tence and/or Loss of Important Local Species

Threat to Abun-dance, Frequen-cy and Distribu-tion of Important Species

Hind-rance to Wildlife Access

B- [Pre-Construction] Design, plan and implement the project that will

minimize vegetation clearing, alteration of landform particularly in areas adjacent to flora of higher conservation significance (i.e. Antipolo, Is-is, Narra) and in the vicinity of ecological significant areas..

Conduct 100% inventory of the affected trees along the alignment to determine the total counts, category, and characteristics of affected trees and minimize removal particularly in areas adjacent to vegetation of higher conservation significance as much as possible. Native/Endemic/ Indigenous species of trees, shrubs and grasses will be specified.

Wildlings of the endangered and threatened species, if any, will be collected before construction, placed in the nursery, and give priority during nursery operation to be used for rehabilitation of areas that will be affected by project

For tree replanting, areas not part of the development within the ROW, around the stations and depot will be prioritized for

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

Tree Contractors

[Construction] Implement: Tree Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

DENR EMB

DEC/GC Cost, Contractor’s Service cost PhP

1,000,000 for the 100% tree inventory

PhP 1,500 per man-hour

PhP 100 per sapling

Bid Documents/ Contract/ Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 99: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-16

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

replanting activity to create buffer zone and to improve habitat for wildlife. For those that cannot be replanted within the project area, coordination with the DENR and LGUs on the identification of area for the potential trees that will be relocated.

Earth balling of trees (if there are any) will be coordinated with the DENR and LGUs including the site where the earth balled trees will be transplanted

Secure tree cutting permit in compliance with DENR Memorandum Order No. 2012-02.

[Construction]

Prior to any clearing activity, clearly mark the ROW to avoid the unnecessary clearance of tree cutting.

Conduct tree planting activities to compensate site clearing activities. Conduct regular monitoring on survival of replanted trees and replant if necessary.

Earthworks and vehicle movement. Generation of dust and noise, vibration, and illumination pollution

Terrestrial Ecology (Fauna)

Loss of Habitat Threat to Existence and/or Loss of Important Local Species; Threat to Abundance, Frequency and Distribution of Important Species;

B- [Construction] Minimize vegetation clearing, alteration of

landform, generation of noise, vibration, illumination, and vehicular movement particularly in areas adjacent to flora of higher conservation significance (i.e. Antipolo, Is-is, Narra) and in the vicinity of ecological significant areas.

Prepare and implement a tree and vegetation management plan as part of the construction plan considering the significance to fauna (local bird species) such as installing buffer zone, minimizing the use of herbicide and machinery as much as possible.

Coordinate with EMB-DENR and SCPW for the conservation of migratory birds if required.

Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

DENR-EMB

Construction cost

PhP 1,500 per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 100: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-17

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Hindrance to Wildlife Access

WATER

Site preparation, land clearing, removal of vegetation Excavation Construction activities

Hydrology Flooding and inundation by sediment run off, siltation, drainage overflow, clogging

B- [Pre-Construction/ Construction] Design and install sufficient drainage system

including temporary drainage system during construction to accommodate the surface water runoff from the project and avoid any flooding in the area caused by the project, in consideration to the existing drainage system and flood storage capacity.

Based on the hydrological, geological study and local climate change data from PAGASA, design and install train system insusceptible to flood and related extreme events including temporary construction drainage, train structure to be above the flood level, installation of drainage pumping system, slope protection, etc.

Based on the result of hydrological study, design and install viaduct piers considering the potential impacts on flood levels upstream and downstream of the rivers traversed by the project.

Coordinate with DPWH and LGUs on the integration of proposed drainage plan to the project area.

[Construction]

Minimize the removal of vegetation and alteration of topography as much as possible.

Install soil erosion control such as protection of slope and bank silt traps to minimize siltation of waterways as required.

Strictly implement construction plan, operating instructions and solid waste / soil management plan, which include minimization of waste/soil generation, segregation, and proper disposal by contractor in accordance to RA 9003

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

DENR-EMB

DED/GC cost, construction cost PhP 1,500 per

man-hour

Soil Erosion Control: PhP 30,000 per m²

RA 9003: PhP 400,000 per year

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 101: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-18

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Regular inspection and prompt maintenance of the drainage system, all installed structures and facilities and improve/ enhance capacity when possible.

Hydrogeology

Depletion of water resource/ competition in water use

C- [Construction] Utilize surface water from the local water service

provider/s

Conduct regular monitoring of water consumption

Implement water conservation program such as use of rain harvested/ recycled water at construction yard/ camp.

Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

Contractor’s Service Cost Water

conservation program: PhP 300,000 per site

Bid Documents/ Contract Agreement

3rd Quarter of 2019 to 2nd Quarter of 2022

Earthworks, (excavation, backfilling, stockpiling, tunneling/ underground)

Water Quality

Degrada-tion of ground-water quality

C- [Pre-Construction/ Construction] Plan and Implement appropriate construction

methods (i.e. excavation, backfilling, stockpiling) based on geological and geotechnical investigations.

[Construction] Install siltation/filtration pond at tunnel

construction area

Comply with environmental permitting requirements for the storage, transport, handling, treatment, and disposal of hazardous material/ wastes and contaminated soil in accordance with RA 6969, and solid waste / soil management plan, in accordance to RA 9003.

Ensure movement of any existing utilities and underground structures during excavation and construction take into account the effect of the actual in-situ ground condition and construction practices

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

DENR-EMB

DED /GC cost, Construction cost PhP 1,500 per

man-hour

Siltation pond: PhP 200,000

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Earthworks, (excavation, backfilling, stockpiling)

Water Quality

Distur-bance on bottom sediment and degrada-

B- [Pre-Construction] Based on the hydrological and geodetic surveys,

design bridge piers that will minimize number of piers to be installed within the rivers and select appropriate construction materials to be used.

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

DED/GC cost, construction cost

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 102: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-19

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

tion of surface water Siltation Induce of turbidity

Coordinate with NWRB, DPWH and LGUs for necessary permit

[Construction] Implement construction activities in

consideration to the water course, embankment, and dry season.

Minimize the removal of vegetation cover, alternation of topography as much as possible.

Install slope protection (i.e. grouted riprap, gabion wall, gabion mattress or sheet pile) to prevent soil erosion and bottom sediment around the bridge piers if necessary.

Place excavated material in temporary staging area with provision for silt traps/ siltation pond to avoid silt draining to waterways, degradation of surface water quality and clogging of waterways, if necessary.

Conduct regular surface water quality monitoring.

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

Third Party Monitoring Contractor

PhP 1,500 per man-hour

Soil erosion control: PhP 30,000 per m²

PhP 25,000 per sampling station

Freshwater Ecology

Threat to abundance, frequency and distribution of species

C-

River Improvement Construction

Water Quality

Degrada-tion of surface water quality due to siltation; Change in the direction of water flow due to course alteration

C- [Pre-Construction/Construction] Plan and implement construction activities in

consideration to the water course, embankment design, and dry season.

Coordinate with NWRB, DPWH and LGUs for the necessary permits

Minimize the removal of vegetation cover as much as possible.

[Construction] Implementation of slope protection measures to

prevent riverbank erosion

Place excavated material in temporary staging area with provision for silt traps/ siltation pond to avoid silt draining to waterways, degradation of surface water quality and clogging of waterways, if necessary.

Conduct regular surface water quality monitoring.

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

Third Party Monitoring Contractor

MMT

DED/GC cost,

construction cost (to include cost of Third-Party Monitoring Contractor) PhP 1,500

per man-hour

RA 9275: PhP 400,000 per year

RA 6969: PhP 100,000 per year

RA 9003: PhP 400,000.00 per year

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Freshwater Ecology

Threat to abundance, frequency and distribution

C-

Page 103: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-20

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

of species due to siltation and change in water flow

DENR-EMB PhP 25,000 per effluent sampling point

Discharge of wastewater from construction sites/ yards/ camps/ related facilities

Water Quality

Degrada-tion of surface water quality from wastewater discharge, accidental spills, and runoff of fuel, paints and solvents to water bodies near the construct-ion sites

B- [Pre-Construction/ Construction] Design and implement the temporary drainage

of waste water from construction yard/ facilities/ camp, surface water runoff drainage systems to minimize discharge.

Design and install sewage treatment facility and separate non-sewage wastewater for stations and Depot in compliance to the Sanitation Code of the Philippines. In addition, depot will have interceptor tank to remove oil and fuel from surface water.

Compliance with RA 9275, secure discharge permit.

[Construction] Install wastewater treatment, portable sanitary

facilities at construction sites/yards. Toilets and lavatories to be provided at the construction camps should be at a ratio of 10 people per toilet. The mobile toilets with wastewater treatment system will be provided.

Conduct proper inspection and regular maintenance of construction machineries, equipment, vehicles and wastewater treatment equipment and facilities with appropriate measure to collect any leakage

Control oil refueling activities and provide oil bunds in oil storage areas.

Prohibit workers from dumping garbage into drains and canals.

Implement material handling program or a site protection program.

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

Third Party Monitoring Contractor

MMT

DENR-EMB

DED/GC cost, construction cost (to include cost of Third-Party Monitoring Contractor):

PhP 1,500 per man-hour

RA 9275: PhP 400,000 per year

RA 6969: PhP 100,000 per year

RA 9003: PhP 400,000.00 per year

PhP 25,000 per effluent sampling point

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Freshwater Ecology

Threat to abundance, frequency and distribution of species

C-

Page 104: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-21

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Prior to operation of the batching plant, construct settling/retention ponds with sufficient capacity for treatment of wastewater from washing of equipment such as mixer drums, trucks, chutes)

Comply with environmental permitting requirements for the storage, transport, handling, and treatment of hazardous material/ wastes and contaminated soil in accordance with RA 6969 and solid waste / soil management plan, which include minimization of waste/soil generation, segregation, and proper disposal including the temporary storage by contractor in accordance with RA 9003

Properly maintain settling/retention ponds to ensure compliance with the effluent quality.

Conduct of effluent quality monitoring at discharge point.

Generation of hazardous wastes at construction sites

Water Quality

Potential contamina-tion of surface water

B- [Pre-Construction/Construction] Contractor will prepare a list of hazardous

chemicals to be brought at the site including information on the quantity and hazard classification.

Minimize or avoid long storage of hazardous materials onsite.

Comply with the labelling and storage requirements of hazardous materials/chemicals, including the provision of MSDS onsite.

Conduct refueling and equipment servicing only in designated areas with impervious surface.

Provide oil and grease traps and other spill containment measures.

Collect hazardous materials including used fuel, lubricating oil and contaminated containers for proper disposal.

Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

Third Party Monitoring Contractor

Construction cost (to include cost of Third Party Monitoring Contractor)

PhP 1,500 per man-hour

RA 9275: PhP 400,000 per year

RA 6969: PhP 100,000 per year

RA 9003: PhP 400,000.00 per year

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Spillage of fuel and other hazardous substances

B- [Pre-Construction/Construction] Strictly implement the spill management plan.

Page 105: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-22

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Store fuel and hazardous substances in paved areas with embankment. If spills or leaks do occur, undertake immediate clean up.

Ensure availability of spill clean-up materials (e.g. absorbent pads, etc.) specifically designed for petroleum products and other hazardous substances where such materials are being stored and used.

Train construction personnel in handling fuels and on spill control procedures.

Ensure all storage containers are in good condition with proper labelling.

Regularly check containers for leakage and undertake necessary repair or replacement.

Store hazardous materials above flood level.

Equipment maintenance areas shall be provided with drainage leading to an oil-water separator; oil will be regularly skimmed to ensure efficiency. Discharge of contaminated water shall be prohibited.

Store waste oil, used lubricant and other hazardous wastes in tightly sealed containers to avoid contamination of soil and surface water. Transport and off-site disposal of such wastes shall be consistent with national regulations.

Generation of Solid Waste

Water Quality

Solid wastes may pollute the surface waters due to improper handling and disposal

C- [Construction] Comply with environmental permitting

requirements including minimization of waste/soil generation, segregation, and proper disposal including the temporary storage by contractor in accordance with RA 9003.

Provide garbage bins and facilities within the project site for temporary storage of construction waste and domestic solid waste.

Separate solid wastes from hazardous waste and reusable wastes.

Store solid wastes temporarily on-site in secure facilities with weather-proof flooring and roofing.

Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

Third Party Monitoring Contractor

Construction cost (to include cost of Third Party Monitoring Contractor)

PhP 1,500 per

man-hour

RA 6969: PhP 100,000 per year

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 106: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-23

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Ensure that wastes are not haphazardly dumped within the project site and adjacent areas.

Undertake regular collection and disposal of solid wastes to sites approved by local authorities.

RA 9003: PhP 400,000.00 per year

AIR

Operation of construction machinery, equipment and vehicles Removal of trees and other vegetation

Climate Change

Exhaust emissions from movement of equipment and vehicles, excavated soil carried by vehicles and other heavy loaders.

C- [Pre-Construction] Plan and design structures that will minimize the

removal of vegetation and alteration of topography if possible.

[Construction] Conduct proper inspection and preventive

maintenance of heavy equipment, machineries and service vehicles to meet the DENR Emission Standard

Use electric or fuel-efficient equipment, machineries and vehicles and maximize its operation if possible

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

MMT

DENR-EMB

DED/GC cost, / Construction cost

PhP 1,500 per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Climate Risk

Meteorology/ climatology

Restrict-ions/ disruption of construct-ion due to soil erosion/ landslides/ and flooding.

A- [Pre-Construction] Take account of change in local micro climate

such as rainfall, temperature pattern for 2020 and 2050 in project design criteria and schedule of construction works.

Based on the hydrological and geodetic study, design and install train system which is robust to climate change and related extreme events including drainage, passenger facilities and structures (viaduct and embankment) i.e. train facilities to be above the flood level, installation of drainage pumping system.

[Construction] Adjust construction activities in consideration to

local climate / extreme events such as extreme

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

MMT

DED/GC cost , construction cost PhP 1,500 per

man-hour

EGF/ Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Slower drainage, soil erosion, disruption

B-

Page 107: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-24

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

in construct-ion by increased rainfall

heat to avoid overheating of construction equipment and service vehicles and cause heat stress to workers.

Implement Emergency Response Plan.

Overheat-ing of construct-ion equipment, vehicles / heat stress by high tempera-ture and heat waves

C-

Earthworks including excavation activities Site clearance including removal of topsoil at the depot site

Air Quality Degrada-tion of air quality due to dust generation from transporta-tion of excessive soil / spoil to fill area construct-ion activities

B- [Construction] Minimize alteration of topography and removal

of vegetation.

Adjust construction activities in consideration to weather system, identifying periods of high winds and drought that aggravated dust transport.

Conduct prompt inspection and regular maintenance of heavy equipment, machineries and service vehicles to meet the DENR Emission Standards

Check and maintain or monitor engine conditions and machines used in the construction at least once a week.

Conduct weekly maintenance of vehicles and equipment to ensure emissions comply with standards.

Conduct regular cleaning and clearing of construction access / sites surfaces of spoils and debris from construction equipment and vehicles.

Implement: Contractors

Monitor: DOTr PMO

GC

MMT

DENR-EMB

Construction cost

PhP 1,500 per man-hour

PhP 30,000 to 80,000 per ambient air sampling station depending on the parameter to be monitored

Bid Documents/ Contract Agreement

3rd Quarter of 2019 to 2nd Quarter of 2022

Operation of construction machinery, equipment and vehicles

Air Quality Degrada-tion of air quality due to gaseous emissions from machine-ries and

C-

Page 108: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-25

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

service vehicles

Implement materials handling or a site protection and rehabilitation program.

Haul the excavated materials from the construction areas as soon as possible or within 24 hours

Conduct water sprinkling in areas prone to dust emission such as at soil excavation areas or stockpile of aggregates and under the elevated stations. Keep excavated soil and stockpiles moist.

Control vehicle movement maintaining the speed limit within the construction site to <10kph and minimize vehicle transport by maximizing the use of site generated materials

Impose speed limit of no more than 30kph on construction vehicles particularly when passing communities, residential or commercial areas or sensitive areas such as hospitals, schools or religious institutions such as temples, mosques and churches.

Require contractor to wash wheels of vehicles before leaving the construction area particularly at the depot and transition areas to avoid mud tracking on roads that cause dust emission later on.

Require materials delivery trucks to provide cover when transporting materials

Install board-ups or fence at the construction area not less than 2 meters high.

In case of accidental spill of materials during transport, the contractor will be required to immediately clean-up spilled materials.

Prohibit burning of waste materials in accordance to RA 9003. Unauthorized burning of construction materials and wastes shall be subject to penalties for the Contractor.

Ready mixed concrete produced and mixed outside the construction area shall be used to

Page 109: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-26

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

prevent and mitigate impacts on communities around the construction area..

Designate at least 3-4 workers per construction area to clean the site after the completion of daily activities and arrange material piling in order to prevent dust diffusion.

For the elevated structures, provide nets and scaffoldings for falling debris from construction of elevated structures to avoid dust emission and hazards from falling debris.

Monitor air quality at identified nearby sensitive receptors regularly and evaluate effectiveness of the air pollution reduction measures provided.

NOISE

Operation of construction machinery, equipment and vehicles Earthworks Construction of structures and facilities

Acoustic Noise

Increase in ambient noise level

B- [Pre-Construction /Construction] Select sites (i.e. ROW, construction yard,

temporary facilities, access route) in consideration to sensitive receptors including ecologically significant areas (if any) likely to be affected.

Design and install effective noise barriers and absorbers along the alignment during construction especially in areas with sensitive facilities.

Design and adopt long rails and ballast-less track with elastic and absorbent sleeper support to minimize noise generation from train operation

Conduct noise prediction or modelling to determine appropriate specifications and locations of permanent noise barriers and other noise reduction measures to ensure that ambient noise levels during operation phase will meet WB-IFC Environmental, Health and Safety Guidelines for different types of sensitive receptors

[Construction]

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

Contractor

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

Third Party Monitoring Contractor

MMT

DENR-EMB

DED/GC cost, / construction cost

PhP 1,500 per man-hour

PhP 8,000 per worker for PPE

PhP 25,000 per noise monitoring station

PhP 30,000 per meter noise barrier

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 110: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-27

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Implement construction activities in consideration to time, duration, and scale to optimize the use construction equipment, machineries, and vehicles in accordance to the noise emission standard.

Minimize activities like alteration of topography and removal of vegetation which generate noise

Install noise control devices such as mufflers and noise suppressors to all construction equipment and machineries. Use of electric instead of diesel powered equipment, hydraulic tools instead of pneumatic tools.

Conduct regular inspection and preventive maintenance of heavy equipment, machineries and service vehicles to meet the DENR Emission Standard

Monitor noise levels at identified nearby sensitive receptors (residential, school and hospital areas) including ecologically significant area/s (if any) likely to be affected by the operation and evaluate effectiveness of the noise reduction measures provided.

Noise control measures at surface construction include installation of temporary noise barriers and 2.0-meter fence around the construction area.1

Use noise barriers and sound absorption materials with no less than 70% and 80% of sound absorption coefficient at 1,000 and 500 hertz, respectively.

Noise levels from equipment and machinery shall conform to the noise standards and WB-IFC Environmental, Health and Safety Guidelines.

1 Indicative cost from various suppliers ranges from $124.69 - $645.50 per square meter. The actual height of the barriers will be determined by the contractors with guidance from DED and dependent on the requirements for each sensitive receptor listed in the EMP Annex.

Page 111: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-28

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

No construction shall be allowed between nighttime hours of 10 pm to 6 am. In case of activities that will cause noise exceeding the acceptable level, permission from DOTr-PMO and concerned LGU must be secured and advance notice to the public will be issued at least 24 hours before the start of construction activities.

Workers will be required to wear appropriate PPE including ear plugs or ear muffs in areas generating excessive noise.

Properly maintain machinery to minimize noise

Require drivers of construction vehicles to minimize blowing of horn and limit speed when passing through residential areas.

In case of complaints, the DOTr-PMO and contractor will continuously operate GRM to urgently respond to the complaint and resolve the problem.

VIBRATION

Conduct of geotechnical investigation Operation of construction machinery, equipment and vehicles Pile driving for piers

Ground vibration

Increase in ambient vibration level and threat to the health and safety of sensitive receptors

C- [Pre-Construction / Construction] Select sites in consideration to sensitive

receptors including ecologically significant areas (if any) likely to be affected.

Conduct building condition survey of old PNR structures and buildings adjacent to the alignment to provide proper protection provision measures and continuous monitoring from the impact of vibration.

Prepare and submit work plan for building and structures of historic concerns and obtain approval from Cultural Agencies.

[Construction] Implement construction activities in

consideration of time, duration, and scale of construction to optimize the use construction

[Pre-Construction] Implement: DOTr PMO

GC

Contractors

Monitor: DOTr PMO

GC

MMT

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

GC Cost/ Construction cost PhP 1,500 per

man-hour

PhP 80,000 per vibration monitoring station

PhP 15,000 per training

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 112: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-29

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

equipment, machineries, and vehicles with minimal vibration generation.

Select construction equipment and machineries matching the scale of the construction and with minimal vibration generation if possible

Provide training on vibration mitigation and provide appropriate PPE to construction workers;

Monitor vibration levels including identified nearby sensitive receptors, old PNR structures including ecologically significant area/s (if any) likely to be affected by the operation and evaluate effectiveness of the vibration reduction measures provided.

Coordinate with sensitive receptors prior to pile driving.

Strictly control construction activities close to historical/archaeological sites.

If construction activities will cause continuous vibration, especially foundation excavation, it is necessary to reduce energy at each excavation.

Require vehicles transporting construction materials and equipment to follow traffic rules strictly and limit speed not to exceed 30 kph and the load shall not exceed 25 tonnes if passing communities, commercial or sensitive areas (e.g. health premises, schools, educational institutions or religious institutions such as temples, mosques and churches).

In case of vibration due to construction activities of the underground structures and stations using a tunnel boring machine, the construction works will be carried out only in daytime from 8 am to 6 pm to minimize disturbance to people.

LGUs

Third Party Monitoring Contractor

MMT

DENR-EMB

PEOPLE

Disclosure of project information and public consultation

Public Involvement and Support

Commu-nities and

B- [Pre-Construction/ Construction] Prior to start of construction works, local

establishments, local authorities and other

Implement: DOTr PMO

DOTr Project/ IEC cost

N/A Prior to start of construction

Page 113: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-30

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

stakeholders not being provided with the appro-priate informa-tion on the implementation of the Project.

Com-plaints from the commu-nities and stakehol-ders.

stakeholders who are likely to be affected by the project shall be informed on the construction schedule and activities, potential environmental impacts, mitigation measures and grievance redress procedure through public meetings

During pre-construction and construction, public involvement activities will continue based on the framework for public involvement and disclosure. Regular consultations with affected people and relevant offices/agencies will be conducted by the contractor during construction phase and by the DOTr during operation phase to ensure adequate and timely mitigation of project adverse environmental impacts.

Prior to commencement of site works, the DOTr in coordination with the contractors will establish the approved grievance redress mechanism that will allow for the following:

Complaints reported by the affected person(s) are acted based on the following levels:

- Same day by the Grievance Redress Officer deployed to a local Help Desk;

- Three (3) days by the Health, Safety and Environment Officer (HSEO) located in the PMO if not resolved by the Grievance Redress Officer;

- Ten (10) days by the Health, Safety and Environment Committee (HSEC) that convenes weekly if not resolved by HSEO;

- Fifteen (15) days by the MMT or EMB Regional Office if not resolved by the HSEO; and

- If not resolved, Elevated to DENR-EMB Central Office for environment-related grievances and to a regular

DED Consultant

GC

Monitor:

DOTr PMO(internal monitoring)

GC

LGUs

MMT

Third Party Monitoring Agents

PhP 1,500 per man-hour

Page 114: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-31

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

court for health and safety-related grievances.

Installation of notice boards at the construction sites that indicate the name and telephone numbers (hotline) who are tasked to receive and document complaints.

Land acquisition for ROW and involuntary Resettlement for Project Affected Families (PAFs)

Informal Settler Families (ISFs) Vulnerable persons (Women-headed households, elderly, persons with disabilities and the poor)

Displace-ment of ISFs Distur-bance of livelihood Loss of income

A- [Pre-Construction] Design train system maximizing the existing

PNR ROW and minimizing additional land acquisition.

Prepare and implement Resettlement Action Plan (RAP) to ensure that PAFs are provided with proper relocation area and/or justly compensated. The RAP will include the following:

Provision of relocation sites for ISFs

Livelihood and income restoration for head-of-household PAPs of ISFs and vulnerable persons.

Prior to displacement, secure and/or develop relocation sites in coordination with the concerned LGUs, Key Shelter Agencies, and other concerned stakeholders with conducive living condition and basic utilities, services and amenities.

[Pre-Construction/ construction] Conduct external and internal monitoring to

ensure that displacement activities are conducted in compliance to the RAP.

If PAFs raise an issue, ensure prompt response and resolution per established Grievance Redress Mechanism (GRM)

Implement:

DOTr PMO

DED Consultant

GC

LGUs

KSAs

Monitor

DOTr PMO(internal monitoring)

External Monitoring agents

MMT

DED /GC cost, / RAP Budget PhP 1,500 per

man-hour

RAP Budget 3rd Quarter of 2018 to 2nd Quarter of 2022

Legal PAFs Displacement/ Disturb-ance of

A- [Pre-Construction] Prepare and implement Resettlement Action

Plan (RAP) to ensure that PAFs are justly compensated for the loss of income by the project.

[Pre-Construction] Implement: DOTr PMO

DED Consultant

DED /GC cost, RAP Budget/ DOTr IEC cost

RAP Budget 3rd Quarter of 2018 to 2nd Quarter of 2022

Page 115: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-32

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Proper-ties

Change/Conflict in Land Owner-ship

Impact on Liveli-hood and Income (i.e. farming, business)

Payment of compensation prior to displacement.

Coordination with the LGUs, land owners and other concerned stakeholders in acquiring the land and/or securing ROW

[Pre-Construction/ construction] Prepare and implement livelihood and income

restoration for PAF’s whose present means of livelihood is no longer viable and will have to engage in new income activity.

Conduct Social Development Plan (SDP) including livelihood training for business owners, vendors, employers and agricultural landowners affected by project.

Conduct external and internal monitoring agencies to ensure that displacement activities are conducted in compliance to the RAP.

If PAFs raise an issue, ensure prompt response and resolution per established GRM

GC

LGUs

KSAs

Monitor DOTr PMO(internal

monitoring

External Monitoring agents

MMT

[Construction] DOTr PMO

GC

LGUs

KSAs

Monitor DOTr PMO(internal

monitoring

External Monitoring agents

MMT

PhP 1,500 per man-hour

Employment of residents of impact Communities

Social Aspect (Gender Equality and Vulnerable Groups)

Generation of Employ-ment and Livelihood Opportuni-ties and improve-ment of Safety

C+ [Pre-Construction/ Construction] Prepare and implement RAP to ensure that

gender equality and needs of vulnerable group are well addressed including livelihood and skills training program

Design and install train system in consideration to universal design and strategic placement of security and lighting within the vicinity of the stations;

Employ workers in consideration to gender equality.

Include gender sensitive livelihood and skills training program in the SDP with due consideration to vulnerable group.

[Pre-Construction] Implement: DOTr PMO

DED Consultant

Contractors

GC

Monitor DOTr PMO (internal

monitoring)

GC

External Monitoring agents

MMT

DED/ GC cost, Construction Cost/ RAP cost

PhP 1,500 per man-hour

PhP 15,000 per person per training

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 116: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-33

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

[Construction] Implement: Contractors

Monitor: DOTr PMO (internal

monitoring)

GC

LGUs

External Monitoring agents

MMT

Demolition of Buildings Social Component

Temporary disruption of regular activities of sensitive receptors

C- [Pre-Construction] Consult with affected household/land owner

prior to demolition of the building

Implement: Contractor

DOTr PMO

KSA

Monitor: DOTr PMO (internal

monitoring)

External Monitoring agents

MMT

GC cost/ Construction cost PhP 1,500 per man-hour

Bid Documents/ Contract Agreement

Commencing on mobilization on site.

Solid waste manage-ment

Generation of solid waste and demolition debris;

Scave-nging of demolition wastes

C- [Pre Construction] Identify a site for the disposal of demolition

wastes away from sensitive receptors as possible

Provide barriers/security measures on temporary storage areas of demolition wastes to prevent scavenging activities which may compromise the safety of scavengers

Implement: Contractor

Monitor: DOTr PMO

GC

MMT

LGUs

Clearing of the proposed project area

In-migration In-migration to the

C- [Pre-Construction / Construction] [Pre-Construction] Implement:

DOTr SDP cost/ contractor’s

3rd Quarter of 2018 to 2nd

Page 117: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-34

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Resettlement project area

Plan and implement construction schedule to shorten time between the pre-construction and construction as much as possible.

Install fencing and guarding of the proposed project to restrict the public from entering the ROW.

DOTr PMO

Contractor

LGUs

Monitor: DOTr PMO (Internal

Monitoring)

MMT

External Monitoring Agents

[Construction] Implement: Contractors

DOTr PMO

LGUs

Monitor: DOTr PMO

GC

MMT

External Monitoring Agents

Service Cost:/ RAP cost

PhP 1,500 per man-hour

SDP: PhP 15,000 per person

PhP 10,000 per meter fence

Bid Documents/ Contract Agreement/

RAP

Quarter of 2022

Conflict between existing residents and new relocatees

C- [Pre-Construction / Construction] Prepare and Implement SDP in coordination

with host LGU’s to align projects/programs to their development plans.

Pre-construction and Construction activities (Site Preparation, mobilization, etc.)

Social Component

Damage or loss caused by contractor of privately-owned property outside the scope of land acquired under the RAP

C- [Pre-Construction] Compensation to property owner commensurate

with rates set out in the Resettlement Action Plan (RAP).

In migration to new relocation site

Basic Services/ Resources

Increased demand on public infrastruc-ture, Degrada-tion on livelihood

C- [Pre-Construction / Construction]

Prepare and implement RAP in consideration of relocation site to be sufficiently covered the expected demand of basic services and resource and social programs at relocation sites in coordination with LGUs.

Prepare and implement SDP in coordination with the host LGUs to align projects or programs to their development plans

[Pre-Construction] Implement: DOTr PMO

DED Consultant

GC

LGUs

KSA

Monitor DOTr PMO (internal

Monitoring)

DED/GC cost, RAP Budget / the DOTr’s SDP cost

PhP 1,500 per man-hour

SDP: PhP 15,000 per person

RAP t 3rd Quarter of 2018 to 2nd Quarter of 2022

Loss of outdoor spaces

C- [Pre-Construction] Coordinate with respective LGU’s and PNR

regarding the possible measures for the

Page 118: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-35

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

transfer/provision or relocation of public parks and other recreational facility.

External Monitoring agents

MMT

[Construction] Implement: DOTr PMO

GC

LGUs

Monitor DOTr PMO (internal

Monitoring)

External Monitoring agents

MMT

Establishment of construction camps and other construction facilities (casting yard, laydown/storage areas, concrete batching plants)

Public Activities

Temporary Disruption of Normal Activities of Sensitive Receptors; Temporary loss of private land

C- [Pre-Construction] Contractor to secure the necessary approvals

and permits prior to establishment and operation of construction-related facilities.

Coordination with LGUs to identify minimization options, including identification of available public land where possible for access roads, material storage areas, construction yards, etc.

Negotiation for temporary land use with land owners and payment of rent commensurate with market rates and restoration of land to pre-use conditions within 3 months of discontinuation of use. Rent will continue to be paid until the land is restored.

Select construction camps and other construction facilities at least 300m from sensitive receptors such as residential housing areas, hospitals, schools, religious and cultural sites.

Implement: Contractor

DOTr PMO

Monitor: GC

External Monitoring agents

MMT

Contractor’s cost

PhP 1,500 per man-hour

N/A Commencing on mobilization on site

Page 119: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-36

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Disruption to community services due to relocation of utilities such as water supply, electric distribution poles, and communication lines

Public services

Disruption of public services

B- [Pre-Construction] Coordinate with the utility companies prior to

relocation of utilities.

Issue notices or announcements in advance regarding temporary disruption of services.

Implement: DOTr PMO

Contractor

GC

DED consultant

Monitor: MMT

DEC/GC Cost/ Construction Cost

PhP 1,500 per man-hour

N/A Commencing on mobilization on site.

Construction of the proposed project

PAFs/IP Cultural/ Lifestyle Change

C- [Pre-Construction] Conduct Field-Based Investigation in

accordance to the NCIP AO No. 3, 2012. If section of the project site is within an Ancestral Domain, additional measures will be implemented in close coordination with the NCIP and LGUs.

Ensure resolution of issues by the indigenous community (if any) in coordination with NCIP and LGU.

Implement: DOTr PMO

DED Consultant

GC

Monitor: MMT

DENR EMB

DOTr admin Cost

PhP 1,500 per man-hour

N/A 3rd Quarter of 2018 to 2nd Quarter of 2019

Encroachment of the proposed project on historical sites, tourist spots, etc. Excavation activities Construction of the proposed project

Historical Sites, artefacts and archaeological remains

Impacts on Cultural/ Historical resources

B- [Pre-Construction] Conduct literature review and site validation of

the potential historic structures in coordination with PNR and Cultural Agencies (NCCA, National Museum, NHCP),;

Perform measured survey of the identified historic structures including its foundation and building condition

Coordinate closely with the Cultural Agencies, concerned LGUs, and PNR for verifying the qualification of those structures and provide necessary protection measures.

Prepare a protection plan for those identified PNR structures which will be maintained in accordance to the agreed procedure.

[Construction] Implement the approved protection plan

[Pre-Construction] Implement: DED Consultant GC DOTr PMO Contractors

[Construction] Implement: Contractors Monitor: DOTr PMO GC LGUs MMT

DED/GC cost, construction cost:

PhP 1,500 per

man-hour PhP 100,000

per m²

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 120: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-37

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Close coordination with the National Museum on the appropriate course of action in case of any archaeological finds.

Local conflicts of interest

Potential conflict among PAFs, and other govern-ment infrastruc-ture projects

B- [Pre-Construction] Close coordination with BCDA, DPWH, and

other relevant agencies

Prepare and implement Resettlement Action Plan (RAP) to ensure that PAFs are justly compensated for the loss of income by the project prior to displacement.

Conduct external and internal monitoring agencies to ensure that displacement activities are conducted in compliance to the RAP.

Prepare and implement arrangement on financial assistant to the receiving of PAFs.

[Construction] If PAFs raise an issue, ensure prompt response

and resolution per established GRM

Conduct external and internal monitoring agencies to ensure that displacement activities are conducted in compliance to the RAP.

[Pre-Construction] Implement: DED Consultant

DOTr PMO

GC

Monitor: External Monitoring

agents

MMT [Construction] Implement: DOTr PMO

Monitor: DOTr PMO(internal

Monitoring)

LGUs

External Monitoring agents

MMT

DED/GC cost, RAP cost/ construction cost/ DOTr IEC Cost

PhP 1,500 per man-hour

Generation of solid waste, excavated soil and hazardous material

Basic Services/ Resources

Increased demand on waste disposal

B- [Pre-Construction / Construction] Identification of final disposal site for solid waste,

excavated soil, hazardous waste at each LGUs.

Conduct regular monitoring of disposal status in compliance to RA 9003 and RA 6003.

Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

Construction cost

RA 6969: PhP 100,000 per year

RA 9003: PhP 400,000 per year

PhP 1,500 per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Generation of potential air and water pollutants due to:

Public Health and Safety

Degrada-tion of

B- [Pre-Construction / Construction] [Pre-Construction] Implement:

DOTr IEC/SDP Cost,

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd

Page 121: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-38

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Heavy lifting and movement of heavy equipment Construction of the proposed project

public health Increase in accident involving local communi-ties

Formulation and implementation of IEC Plan to inform the affected LGU and local communities and the general public about 1) the project, project activities, duration, possible project impacts and incorporate their comments and inputs in the design, 2) the potential impact of project activities to air quality, noise, vibration, and climate change, and corresponding health and safety mitigation measures, and 3) the Grievance Redress Mechanism to handle complaint/s if any.

Plan for construction sites/facilities/yard and access route in consideration to health and safety of local communities.

Plan and implement SDP including health and safety of local community

[Construction] Provide safety officers to monitor the health and

safety of the local community. If any complains rises, immediately identify the causes and evaluate built-in measures.

Install fencing of the construction site, provision of signage and posters, and guarding of the access point to ensure that the area is not accessible to the public.

Implement Emergency Response Plan and Health and Safety Management Plan.

DOTr PMO

GC

Contractors

Monitor: LGUs

External Monitoring agents

MMT

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

Construction cost

IEC: PhP 50,000 per activity per LGU

PhP 10,000 per meter fence

PhP 1,500 per man-hour

Quarter of 2022

Risks to Workers Occupatio-nal Health and Safety

Increase risk of accidents at construction sites; spread of

infectious disease among workers

B- [Pre-Construction/Construction] Prepare and implement Occupational and

Community Health and Safety Plan and Emergency Response Plan based on the WB-IFC EHS Guidelines.

Include medical certificate in the requirements for hiring of workers to ensure that they are fit to work. Ensure that they are provided with proper training on construction, occupational health and safety, and emergency response procedure.

Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

Contractor’s service fee on health, safety and environmental management

PhP 1,500 per

man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 122: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-39

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Plan construction details such as storage of equipment and machinery and access route of heavy vehicle considering health and safety of workers.

Provide appropriate personal protective equipment (PPE) to all construction workers, particularly to the personnel working on heights, heavy and electrical equipment.

Establish Health and Safety Desk or Medical Station at the active construction sites to monitor and safeguard the health of the workers and local residents and to provide immediate response during unexpected incidents/emergencies.

Provide fire-fighting equipment at work areas and construction camps.

Close coordination with the nearest hospitals in the active construction site for immediate transfer and/or further evaluation and medical management of the patient.

Require the contractor to appoint an environment, health and safety officer to supervise the implementation of environmental mitigation measures and to ensure that health and safety measures are strictly implemented at the construction site and immediate vicinity.

Provide adequate drainage in construction camps to prevent water logging and formation of breeding sites for mosquitoes.

Provide potable water, hygienic sanitation facilities/toilets with sufficient water supply.

Ensure that all wastewater emanating from construction camps are treated and complies with the effluent standards.

Provide fence on all areas of excavation to avoid accidents.

Implement fall prevention and protection measures such as scaffoldings, wearing of

PhP 8,000 per personnel for PPE

Health and Safety Desk or Medical Station: PhP 200,000 per site

Page 123: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-40

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

safety belts by workers, etc. when working in high areas.

Provide sufficient lighting in tunnel areas and underground station excavation sites.

Provide emergency lighting system in case of power shutdown.

Ensure that sufficient fresh air is supplied at confined work spaces at the tunnel and underground station excavation sites. Ensure that air filters are kept clean.

Confined spaces such as tunnels shall be provided with safety measures such as venting, monitoring, and emergency rescue procedures.

Conduct orientation for construction workers regarding health and safety measures, emergency response in case of accidents, fire, etc. and prevention of HIV/AIDS, STIs and other diseases.

Employment of workers

Local Economy

Genera-tion of Local Employ-ment

Hiring of workers from outside the commu-nity might create peace and order and social conflicts

B+ [Pre-Construction /Construction] Close coordination with the host LGUs

(barangay level) regarding the hiring of temporary workers to ensure that the workers being considered are legitimate residents in the area. Those affected by the Project will be prioritized for employment.

Provide skill trainings to PAFs under livelihood and income generation program developed by RAP

Provide HIV/STI awareness and prevention training to construction workers and contractor’s employees/staff

Implement: DED Consultant

GC

Contractors

DOTr PMO

Monitor: GC

LGUs

DOTr PMO

External Monitoring agents

MMT

DED/GC Cost, RAP cost/ DOTr IEC cost/ Contactor’s Service Cost

Skills Training: PhP 15,000 per person

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 124: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-41

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

with local commu-nities and increased

HIV/AIDS risk.

Traffic congestion and access problems

Mobility/ Public Transport

Increase in traffic volume within the project area

B- [Pre-Construction/Construction] Conduct Traffic Impact Assessment (TIA) and

based on the results of TIA, prepare and implement Traffic Management Plan (TMP), Implement the approved TMP. The plan shall be designed to ensure that traffic congestion due to construction activities and movement of construction vehicles, haulage trucks, and equipment is minimized. The plan shall be prepared in consultation with concerned traffic agencies, local officials and the general public. The plan shall identify traffic diversion and management, traffic schedules, traffic arrangements showing all detours, necessary barricades, warning/advisory signs, road signs, lighting, and other provisions to ensure that adequate and safe access is provided to motorists in the affected areas.

Coordinate with the traffic police for traffic management.

Provide traffic advisory signs for the public that construction is in progress and that road narrows in some sections.

Employ flag persons to control traffic at underground station sites.

Provide sufficient lighting at night within and in the vicinity of the construction sites.

Prohibit prolonged side street parking of construction trucks.

[Pre-Construction] Implement: DED consultant

GC

DOTr PMO

[Construction] Implement: Contractors

Monitor: DOTr PMO

GC

LGUs

MMT

DED / GC Cost, Construction cost: PhP 1,500 per

man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 125: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-42

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

As much as possible, schedule delivery and transport of construction materials and spoils during non-peak hours.

Blocking of existing access roads

Public Access

Impact on Public Access

Impact to School Access

Increase in accidents

B- [Pre-Construction/ Construction] Based on the study on public access at affected

barangay, maintain the existing public access as much as possible.

In case of any temporary closure during construction, minimize the impact to the daily life of affected communities such as access to school infrastructure in coordination with the DepEd and host LGUs for the schedule of construction activities.

In case of permeant loss of public access, RAP will be applied.

Disseminate information to the public, barangay, and LGUs on the potential impact to the existing public access and mitigation measure through the project activities.

Provision of diversion route with appropriate health and safety measures. In case of any changes, prompt update on the diverted routes to the concerned communities and LGUs,

Assignment of traffic guide to provide assistance to the road users.

Implement: Contractors

DOTr PMO

Monitor: DOTr PMO (Internal

Monitoring)

GC

LGUs

External Monitoring agents

MMT

Construction Cost / DOTr IEC cost

IEC: PhP 50,000 per activity per LGU

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Movement of construction equipment;

Delivery of construction materials

Additional commuters due to construction workforce

Blocking of access roads

Traffic Management

Traffic Congestion

B- [Pre-Construction/ Construction] Conduct TIA and based on the results of TIA,

prepare and implement TMP, coordinate to the concerned LGUs and transport operator/s and get their inputs and approval

Schedule transport of heavy structures during period when there are fewer vehicles on the road and posting of appropriate traffic signage and warnings.

Disseminate information to the general public, host barangays, and LGUs on the potential

[Pre-Construction] Implement: DED consultant

DOTr PMO

Contractors

[Construction] Implement: Contractors

Monitor:

DED cost/ DOTr IEC Cost/ Construction Cost

TIA: PhP 10,000,000

IEC: PhP 50,000 per activity per LGU

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2022

Page 126: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-43

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

impact of the project to the existing access and provide mitigating measures.

DOTr PMO

GC

LGUs

External Monitoring agents

MMT

Temporary land use for construction purposes.

Temporary loss of private land

[Pre-Construction/ Construction] Coordination with LGUs to identify minimization

options, including identification of available public land where possible for access roads, material storage areas, construction yards, etc.

Negotiation for temporary land use with land owners and payment of rent commensurate with market rates and restoration of land to pre-use conditions within 3 months of discontinuation of use. Rent will continue to be paid until the land is restored.

DOTr PMO

LGUs

Contractors

Construction Cost

Bid Documents/ Contract Agreement

OPERATION

LAND

Operation and maintenance of the Project

ECA Incompati-bility with the area that will be hit hard by natural calamities.

B- Coordinate with PAGASA / PHIVOLCS and adjustment of train schedules.

Implement proper inspection and prompt maintenance of drainage systems.

Implement: Operator

Monitor DOTr PMO

LGUs

Third Party Monitoring Contractor

Included in the operation and maintenance cost

PhP 1,500 per man-hour

Operation and maintenance cost

From 3rd Quarter of 2022

Presence of the proposed project structures (railway, passenger facilities, depot etc.)

Visual aesthetics

Impairment of visual aesthetic

C- Maintain tree planting to minimize the visual impact by the project and harmonize to the surrounding environments in open areas within the ROW, depot and around the stations, to create green corridor.

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost

PhP 1,500 per man-hour

EGF From 3rd Quarter of 2022

Page 127: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-44

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Generation of domestic and hazardous wastes including accidental oil and lubricant spills from passenger facilities (station), depot.

Land value Degrada-tion of land value and of soil quality due to improper handling of domestic and hazardous wastes

C- Conduct proper inspection and prompt maintenance of machines and equipment, and facilities

Strictly implement solid waste management plan in accordance to RA 9003, and treatment of hazardous chemicals and contaminated soil in accordance with RA 6969.

Conduct of soil quality monitoring when necessary.

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost PhP 1,500 per

man-hour

RA 9003: PhP 400,000 per year

RA 6969: PhP 100,000 per year

Operation and maintenance cost/ EGF

From 3rd Quarter of 2022

Generation of solid waste from office and service areas

Solid Waste Management

Degrada-tion of the area of the facilities and surround-ing communi-ties

B- Provide solid waste segregation bins at each office area and at train stations.

Coordinate with the concerned LGUs in the collection and disposal of segregated solid wastes.

Maintain daily record of solid wastes generated and collected.

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost PhP 1,500 per

man-hour

Contract agreement

From 3rd Quarter of 2022

Generation of hazardous waste from maintenance area at Depot and related facilities.

Toxic and Hazardous Waste Management

Degrada-tion of the area of the facilities and surround-ing communi-ties

B- Provide hazardous waste bins at the stabling yard

Record quantities of hazardous wastes generated

Commission the services of a Government-recognized hazardous waste transporter and treater.

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost PhP 1,500 per

man-hour

EGF/ Contract agreement

From 3rd Quarter of 2022

Occurrence of landslides, volcanic hazards, ground shaking and liquefaction

Likely seismic events around the alignment

Subsidence, Liquefaction, Landslide, Mud/Debris Flow, etc.

Damage to tracks Risk to the life of pas-sengers and workers

B- Conduct inspection in the event of natural hazard occurrence to assess damage of structures

Regular Coordination with the PHIVOLCS for earthquake and volcanic events to adjust the train schedule as necessary.

Conduct earthquake drills for train users are also advised

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost: PhP 1,500 per

man-hour

Operation and maintenance cost / EGF

From 3rd Quarter of 2022

Page 128: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-45

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Damage to passenger facilities.

Conduct proper inspection and prompt maintenance checks to every single installed structure and facility and improve/ enhance capacity when possible

Upgrades or install new technological advances when available are also encouraged for the continued operation of the Project

Operation of the project and passenger facility, Depot, service vehicle, Passenger movement

Terrestrial Ecology

Threat to Existence and/or Loss of Important Local Species

Hindrance to Wildlife Access

C- Minimize noise, vibration, illumination, and vehicular movement in significant fauna area (e.g., depot area)

Continuous planting of replacement tress if needed

Conduct monitoring on survival of replanted trees and replant if necessary

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost: PhP 1,500 per

man-hour

PhP 100 per sapling

Operation and maintenance cost / EGF

From 3rd Quarter of 2022

WATER

Operation of passenger trains/facilities, depot:

Discharge of waste water from passenger facilities, depot.

Accidental spills of fuels and lubricants from service vehicles and machineries at depot

Generation and improper handling and disposal of domestic and hazardous wastes.

Hydrology Increase of flood intensity/ occurrence.

C- Conduct proper inspection and prompt maintenance of the installed drainage system, and improve/ enhance capacity when possible

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost

:PhP 1,500 per man-hour

RA 6969: PhP 100,000 per year

RA 9275: PhP 400,000 per year

PhP 25,000 per effluent sample

EGF/ Contract agreement

From 3rd Quarter of 2022

Water Quality

Degrada-tion of groundwa-ter quality

C- Comply with environmental permitting requirements for the storage, transport, handling, and treatment and disposal of hazardous material/ wastes and contaminated soil in accordance with RA 6969.

Compliance to RA 9275 including but not limited to securing of discharge permit.

Hygienic toilets will be provided at all stations and facilities.

Wastewater will be treated by a wastewater treatment system at each station before release of effluent into public waterways.

Degrada-tion of surface water quality

B-

Freshwater Ecology

Threat to abundance, frequency and

C-

Page 129: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-46

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

distribution of species

Recycle train washing to reduce volume of wastewater to be discharged daily.

Conduct proper inspection and prompt maintenance of the installed wastewater treatment facilities & drainage system and treatment facility.

Monitor effluent of the wastewater treatment system to ensure compliance with the effluent standards.

AIR

Climate Change Meteorology/

Climatology Restrict-ions/ disruption of railway operation due to soil erosion/ landslides/ flooding.

A- Regular inspection and preventive maintenance of railway structures and facilities to ensure optimum working condition;

When necessary, install improvement of railway system to make it more resilient to temperature and rainfall increase;

Planting of vegetation as much as possible in open areas at the depot, around the stations and along the railway track;

Implementation of an Emergency Response Plan;

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost: PhP 1,500 per

man-hour

EGF/ Contract agreement

From 3rd Quarter of 2022

Slower drainage, soil erosion, disruption in construc-tion by increased rainfall

B-

Overheat-ing of construct-ion equipment and vehicles and track buckling

C-

Page 130: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-47

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

and signalling problems

Operation of trains, depot, passenger facilities (stations), service vehicles, etc.

Meteorology/

Climatology Reduction of Green-house Gases

B+ Provide incentives and information dissemination activities to encourage commuters to use rail transit and its benefits over other modes of transport (Modal Shift)

Plant and manage vegetation as much as possible to open areas at the depot, around the stations and along the railway track

Conduct energy/water conservation program such as use energy efficient products (i.e. LED lights) and monitor carbon footprint monitoring

Conduct regular inspection and proper maintenance of railway systems and facilities, and equipment and machinery

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost:

IEC: PhP 50,000 per activity per LGU

PhP 1,500 per man-hour

Contract agreement

From 3rd Quarter of 2022

Air Quality Degrada-tion of air quality in the vicinity of the station and in depot area Increase in Vehicle Exhaust emission and entrained dust due of increased movement of people

C- Select appropriate operation and maintenance equipment that are fuel efficient to reduce emission.

Conduct regular inspection and maintenance of heavy equipment, machineries, facilities and service vehicles and facilities such as generator etc. to meet the DENR Emission Standard

Regular cleaning and clearing of road from spoils and debris and wetting of ground in the periphery of the depot when necessary.

Comply with environmental permitting requirements for the storage, transport, handling, and treatment of hazardous material/ wastes and contaminated soil in accordance with RA 6969 at depot area, and provide appropriate PPE for the concerned personnel

Control service vehicle movement by maintaining the speed limit to <10kph within the construction site. Minimize vehicle transport by maximizing the use of site generated materials.

Monitor air quality at the identified sampling stations

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost

PhP 1,500 per man-hour

RA 6969: PhP 100,000 per year

PhP 8,000 per personnel for PPE

PhP 25,000 to 80,000 per ambient air station

EGF/ Contract agreement

From 3rd Quarter of 2022

Page 131: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-48

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

NOISE

Operation of trains, depot, passenger facilities (stations), service vehicles, etc.

Acoustic Noise

Reduction of noise due to decrease in traffic volumes

B+ Provide incentives to and information dissemination activities to encourage commuters to use rail transit over other modes of transport

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost

PhP 1,500 per man-hour

PhP 30,000 per m² noise barrier

PhP 25,000 per noise monitoring station

Contract agreement

Increase in ambient noise level

C- Optimize the number of train operation at night time to reduce generated noise

Provision of 2m high concrete noise barriers for about 59 km length of the alignment especially along areas identified as sensitive receptors.

Provision of noise control device such as muffler to all stationary sources (i.e. generator set)

Install traffic signs in the areas before and after passing all MRCP stations, e.g. directional signs, speed limit signs, no blowing of horn signs, etc.

Inspect the strength and efficiency of sound absorbing materials installed at the routes or areas under the stations at least once a month. Change the material in case these are damaged or their efficiency has decreased by more than 40%.

Regular inspection and proper maintenance of trains and tracks to ensure its optimal operation and functionality

Monitor noise levels including identified nearby sensitive receptors including ecologically significant area/s (if any) likely to be affected by the operation and evaluate effectiveness of the noise reduction measures provided.

EGF/ Contract agreement

From 3rd Quarter of 2022

VIBRATION

Operation of trains, depot, passenger facilities (stations), service vehicles, etc.

Ground Vibration

Increase in ground vibration level

C- Monitor vibration levels including identified nearby sensitive receptors, old PNR structures, historical heritages including ecologically significant area/s (if any) likely to be affected by

Implement: Operator

Monitor DOTr PMO

Included in the operation and maintenance cost:

EGF/ Contract agreement

From 3rd Quarter of 2022

Page 132: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-49

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

the operation and evaluate effectiveness of the vibration reduction measures provided.

The strength and efficiency of rail pads at the train stations or hubs must be inspected at least once or twice a month. In case of damage or decrease in efficiency of the pads by more than 40%, these should be replaced.

Regular inspection, proper maintenance and reconditioning of trains and tracks such as rail grinding, slip-slide detectors and maintenance or replacement of suspension system, brakes and wheels

LGUs PhP 1,500 per man-hour

PhP 80,000 per vibration monitoring station

PEOPLE

Hiring of workers

Local Economy

Generation of Local Benefits Business opportuni-ties

C+ Coordinate closely with the host LGUs, specifically at the barangay level regarding the hiring of regular workers to ensure that the workers being considered are legitimate residents in the area in consideration to gender equality.

Implement: Operator

Monitor: DOTr PMO

LGUs

Included in the maintenance cost PhP 1,500 per

man-hour

Contract agreement

From 3rd Quarter of 2022

Operation of train

In Migration Influx of ISFs

C- Install fencing and provide guards to prevent the settlement of ISFs along the ROW

Implement: Operator

Monitor: DOTr PMO

LGUs

Included in the maintenance cost

Contract agreement

From 3rd Quarter of 2022

Operation of train

Physical/ Cultural resource

Conserva-tion of old PNR structure and parks

C+ Continuous conservation activities of old PNR structures in coordination with PNR and LGUs

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the budget of proponent

Contract agreement

From 3rd Quarter of 2022

Operation of train and station

Public Health and Safety

Increase risk of accidents

B- Provide security guards in all stations to direct passengers on the safe zone.

Implement: Operator

Included in the health and safety and

EGF/ Contract agreement

From 3rd Quarter of 2022

Page 133: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-50

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Maintenance work at Depot

Occupatio-nal Health and Safety

Increase the risk of accidents and infectious disease of employees

B- Implement the Occupational Health and Safety Management Plan.

Provide appropriate PPE to all personnel undertaking maintenance work.

Implement the Emergency Response Plan

Provide sanitary facilities or utilities in all stations and depot.

Monitor DOTr PMO

LGUs

environmental management plan of proponent budget: PhP 1,500 per

man-hour

Occupational Health and Safety Management Plan: PhP 300,000

Public involvement Public Consulta-tion

Immediate response to address adverse impacts during train operation

B+ Regular consultations with affected people and relevant offices/agencies will be conducted by the DOTr during operation phase to ensure adequate and timely mitigation of project adverse environmental impacts.

Implement Operator

DOTr PMO

Monitor DOTr

LGUs

Included in the operation and maintenance cost PhP 1,500 per

man-hour

EGF/ Contract agreement

From 3rd Quarter of 2022

Train Operation Traffic Conditions

Traffic congestion may occur in the areas adjacent to the proposed stations due to pick-up and drop off of passen-gers by transport vehicles

B- Establish a TOD Committee, which compose of the Traffic Management of LGUs, Planning Office, PNR, DPWH, and DOTr to plan and implement TOD in consideration to the loading and unloading area and the circulation of the traffic as well as the integration of transport facility within the station.

Implement: Operator

Monitor: DOTr PMO

LGUs

Included in the operation and maintenance cost PhP 1,500 per

man-hour

EGF/ Contract agreement

From 3rd Quarter of 2022

Page 134: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-51

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Generation of solid waste from office and service areas

Community and workers’ health and safety

Indiscrimi-nate waste disposal may pose risks to the health and safety of the surround-ing communi-ties

B- Provide solid waste segregation bins at each office area and at train stations.

Coordinate with the concerned LGUs in the collection and disposal of segregated solid wastes.

Maintain daily record of solid wastes generated and collected.

Implement: Operator

Monitor: DOTr PMO

LGUs

Included in the operation and maintenance cost PhP 1,500 per

man-hour

EGF/ Contract agreement

From 3rd Quarter of 2022

Generation of hazardous waste from maintenance area at Depot and related facilities

Community and workers’ health and safety

Indiscrimi-nate disposal of toxic and hazardous wastes may pose risks on the health and safety of surround-ing communi-ties

B- Provide hazardous waste bins at the stabling yard

Record quantities of hazardous wastes generated

Commission the services of a Government-recognized hazardous waste transporter and treater.

Implement: Operator

Monitor DOTr PMO

LGUs

Included in the operation and maintenance cost PhP 1,500 per

man-hour

EGF/ Contract agreement

From 3rd Quarter of 2022

Railway operation Community/ public and workers’ health and safety

Risk of accidents from railway operation and mainte-nance

B- Prepare the train safety operations plan before operation of the project

Train workers and staff on implementation of the operations plan and the emergency response plan

Conduct drills on emergency situations at least once a year through professional experts

Conduct internal safety audits at least every six months.

Conduct full audit of the fire protection system every month and conduct daily random checks

Implement: Operator

Monitor: DOTr PMO

LGUs

Included in the operation and maintenance cost PhP 1,500 per

man-hour

EGF/ Contract agreement

From 3rd Quarter of 2022

Page 135: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North-South Commuter Railway Clark Extension Project

4-52

Environmental Aspect

Environ-mental

Compo-nent

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementa-tion

Schedule

Implement the grievance redress mechanism (complaints management system) with complaint desks at all stations

Note: A+/-: Significant positive/negative impact is expected. B+/-: Moderate positive/negative impact is expected to some extent. C+/-: Minor / Negligible positive/negative impact is expected to some extent. D: Extent of impact is unknown.

Page 136: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-1

ENVIRONMENTAL MANAGEMENT PLAN ................................................................... 4-1

Table 4.1 Environment Management Plan for the Proposed NSCR Calamba Extension Project ........................................................................................................................... 4-2

Page 137: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-1

4. ENVIRONMENTAL MANAGEMENT PLAN

1. The DOTr is committed to minimize any adverse impacts, which could arise from the construction, operation, and abandonment of the proposed project. It will do so by formulating an Environmental Management Program (EMP) to manage the Project’s impacts and risks, adopt the best available proven control technologies and procedures, undergo a continuing process of review and positive action in the light of available monitoring results and continuing consultation with the local communities. Regular consultations with the affected people and relevant offices/ agencies will be conducted by the contractor during construction phase and by the DOTr during operation phase to ensure adequate and timely mitigation of project adverse environmental impacts. DOTr will provide notification to DENR-EMB, ADB and JICA on any unanticipated environmental risks or impacts that arise during construction, implementation and/or operation of the Project that were not considered in the EIA and EMP.

2. Basically, the EMP will aim to achieve an exemplary environmental performance in the pre-construction, construction, and operation of the proposed Project. In order to meet this goal, the following activities/ measures/ programs will have to be implemented:

• Environmental Policy;

• Application of Mitigation/ Management Measures;

• Environmental Monitoring Program;

• Resettlement Action Plan;

• Social Development Program;

• Emergency and Contingency Plan;

• Information, Education and Communication Plan;Construction Contractor’s Program; and

• Institutional Plan and Hiring of an Environmental/ Safety Officer.

3. Overall, the DOTr will be the Implementing Agency of the Project. The Project Management Office (PMO) of DOTr will be the primary point of contact with EMB, ADB and JICA with regards to environmental management of the project. The following chapters of the EIS will be included in the bid documents: Chapter 4 (Environmental Management Plan), Chapter 8 (Environmental Compliance Monitoring), and Chapter 10 (Institutional Arrangements for EMP Implementation), to ensure that the mitigation measures will be properly implemented and monitored during all project phases of the project. The Project will hire General Consultant (GC) that includes an International Environment Specialist and a National Environment Specialist that will assist the DOTr in the monitoring of compliance of the project with the EMP. During the operation phase, the DOTr-PMO will be assisted by third party environmental consultant/monitor/auditors in the monitoring of environmental parameters of the project.

4. Table 4.1 presents the EMP for the Project.

Page 138: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-2

Table 4.1 Environment Management Plan for the Proposed NSCR Calamba Extension Project

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

GENERAL

Pre-construction, Construction and Operation activities

Land, Water, Air and People

Comply with the relevant laws: RA 6969: Storage, Transport, Handling, Treatment and Disposal of Hazardous Waste Secure hazardous waste generator’s ID from

DENR-EMB; Provision of hazardous materials storage area; Hazardous materials/ wastes will be stored in

appropriate container properly sealed and labelled;

Hazardous waste will be hauled by an accredited transporter;

Hazardous waste will be treated by a registered treater (TSD Facility).

RA 9003: Management and Disposal of Solid Wastes Waste segregation, recycling, provision of waste

color coded bins, etc.; Provision of Material Recovery Facility (MRF); Regular hauling of solid wastes through the LGU

or private contractor.

RA 8749: Comprehensive Air Pollution Control Policy Secure permit to operate for all air pollution

source installations (i.e genset); Regular inspection and preventive maintenance

of heavy equipment, machineries and service vehicles to meet the DENR Emission Standards;

Regular cleaning and clearing of construction access/ site surfaces of spoils and debris from construction equipment and vehicles and wetting of ground soil in the construction site when necessary;

Control vehicle movement maintaining the speed limit within the construction site to <10kph and provide cover to loaded trucks.

Implement: Contractor Operators

Monitor: DOTr PMO GC LGUs MMT DENR-EMB

Contractor and operator’s service fee on health, safety and environmental management: RA 6969:

PhP 100,000 per year

RA 9003: PhP 400,000 per year

RA 8749: PhP 400,000 per year

RA 9275: PhP 400,000 per year

PD 442: PhP 6,000 per worker

PD 856: PhP 50,000 per year

Sanitary facility: PhP 200,000 per site

Emergency

EGF/ Bid Documents/ Contract Agreement

3rd Quarter of 2018 onwards

Page 139: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-3

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

RA 9275: Comprehensive Water Quality Management and for Other Purposes Secure discharge permit; Provision of Wastewater Treatment Facility at the

depot; Provision of three-chambered septic tank at each

station.

PD 442: Labor Code of the Philippines, as amended (including Occupational Safety and Health Standards) Gender equality will be considered in hiring of

workers; Include medical certificate in the requirements for

hiring of workers to ensure that they are fit to work. Ensure that they are provided with proper training on construction, occupational health and safety, and emergency response procedure;

Provide appropriate personal protective equipment (PPE) to all construction workers, particularly to the personnel working on heights, heavy and electrical equipment;

Establish Health and Safety Desk or Medical Station at the active construction sites to monitor and safeguard the health of the workers and local residents and to provide immediate response during unexpected incidents/emergencies;

Close coordination with the nearest hospitals in the active construction site for immediate transfer and/or further evaluation and medical management of the patient.

PD 856: Sanitation Code of the Philippines Provide safe and clean water for drinking; Provision of appropriate sanitary facilities such as

portable toilets and waste bins.

Implementation of Emergency Response Plan and Health and Safety Management Plan to include but not limited to: Distribution of manual/ guideline for workers/

Response Plan and Health and Safety Management Plan: PhP 300,000

Health and Safety Desk or Medical Station: PhP 200,000 per site

PhP 1,500 per man-hour

Page 140: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-4

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

employee on health, safety and environmental management;

Orientation and continuous training of qualified workers/ employee/ operator on Environment Management, Basic and Construction Occupational Safety and Health, Scaffolding Safety, Fire Safety and Safe Use of Chemicals at Work;

Provision of earthquake, fire drills for workers; Provision of appropriate PPE for workers; Provision of security personnel.

Regular monitoring of site condition

PRE-CONSTRUCTION / CONSTRUCTION

BASELINE ENVIRONMENTAL QUALITY MEASUREMENTS

Environmental Quality

Air Quality

Noise Vibration Surface

Water Quality

Groundwater Quality

Soil Contamination

Baseline sampling at the depot site and other locations where necessary as indicated in the

Environmental Monitoring Plan (Table 8.1.1).

Implement: Contractor

Monitor GC DOTr PMO MMT Third Party

Monitoring Contractor

DENR-EMB

Contract’s service cost PhP 30,000

to 80,000 per air sampling station

PhP 25,000 per noise monitoring station

PhP 80,000 per vibration monitoring station

PhP 25,000 per water sampling station

PhP 25,000 per soil sample

PhP 1,500 per man-

Contract Agreement

Before any activities are started on the sites

Page 141: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-5

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

hour

CONTRACTOR’S ENVIRONMENTAL MANAGEMENT PLAN (CEMP) Contractor’s EMP

EMP Implementation

[Pre-Construction] Prior to start of site works and within 60 days

upon receipt of the notice to proceed, the contractor shall prepare a site-specific Contractor’s Environmental Management Plan (CEMP) based on the EMP in the EIS. The CEMP will describe the scope of works and schedule, construction methodology, facilities and site conditions, including sensitive receptors in the contract area. The CEMP should include the detailed operational plan for the implementation of the EMP/CEMP with targets/ indicators over a specific timeline that would be monitored for milestone highlights. The CEMP will be submitted to the project supervision consultant for approval with copies provided for review by DOTr and ADB. The following specific management plans shall be included in the CEMP:

Dust and Emission Control Plan. The plan shall provide details of mitigation measures, specific location and schedule where such measures shall be implemented to minimize impacts to sensitive receptors (residential areas, schools, hospitals, etc.) due to construction works, sourcing and transport of construction materials, operation of construction equipment and other project-related activities.

Noise Control Plan. The plan shall provide details of mitigation measures, specific location and schedule where such measures shall be implemented to minimize impacts to sensitive receptors (residential areas, schools, hospitals, etc.) due to construction works, sourcing and transport of construction materials, and other project-related activities.

Vibration Management Protocol. The protocol shall specify how to pace the piling and other

Implement: Contractor GC to assist

Monitor: DOTr PMO GC MMT DENR-EMB

Contract’s service cost

PhP 1,500

per man-hour

Contract Agreement

CEMPs will be submitted and cleared no later than one month before site activities are started.

Page 142: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-6

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

heavy machinery operation to avoid vibration impacts.

Construction Camp and Worker Camp Lay-out and Management

Quarry and Construction Layout and Management

Spoils Management and Disposal Erosion and Sediment Control Solid and Liquid Wastes Management Hazardous Materials and Wastes Management

– includes measures to address spills of hazardous substances

Water Availability and Pollution Control Construction and Decommissioning Plan of

Worker Camps and other Construction Facilities – includes workshops, fabrication yards, quarries, etc.

Vegetation Clearing, Landscaping and Revegetation Plan

Damage to Properties and Facilities Management Traffic Management and Community Access

Plan. The plan shall be designed to ensure that traffic congestion due to construction activities and movement of construction vehicles, haulage trucks, and equipment is minimized. The plan shall be prepared in consultation with concerned traffic agencies, local officials and the general public. The plan shall identify traffic diversion and management, traffic schedules, traffic arrangements showing all detours, necessary barricades, warning/ advisory signs, road signs, lighting, and other provisions to ensure that adequate and safe access is provided to motorists and the public in the affected areas.

Occupational Safety and Project Personnel Health Program consistent with the Labor Code of the Philippines and international standards (e.g., the World Bank Group’s Environment, Health and Safety Guidelines of 2012). The plan shall address health and safety hazards

Page 143: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-7

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

associated with construction activities (e.g., excavations, working at heights, etc.), establishment and operation of construction/ worker’s camps, use of heavy equipment, transport of materials and other hazards associated with various construction activities; includes HIV/AIDS awareness and prevention.

Community and Public Health and Safety Plan Emergency Preparedness and Response Plan

to prevent, mitigate, respond to and recover from emergency events that could occur due to project activities such as accidents, spills of hazardous substances, fire, extreme weather events, and other crises.

Cultural Resources Protection and Preservation Personnel Training and Awareness Program Decommissioning Plan

LAND

Land acquisition for the Project ROW

Land use and Classification

Incompatibility with the Existing Land Use

C- [Pre-Construction/ Construction] Maximize the use of existing PNR ROW from

Blumentritt to Calamba. Information sharing to the affected LGU to align

and ensure that proposed project will be accommodated in their future land use plan.

Identification of future land use of surrounding areas that will result to a significant increase of transportation-oriented developments in cooperation with urban planners of LGUs to adopt in the future developments.

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC

[Construction] Implement: DOTr PMO GC

Monitor: DOTr PMO GC MMT DENR-EMB

DED Cost/ GC cost, DOTr IEC cost

PhP 1,500 per man-hour

Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2019

Construction activities at the following:

ECA Incompatibility with Classificatio

B- [Pre-Construction/ Construction] Plan and design the site, structure foundation,

and structure including construction activities in

[Pre-

Construction] Implement:

DED Cost/ GC cost, DOTr IEC

Contract Agreement

3rd Quarter of 2018 to

Page 144: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-8

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

Areas with the existing old PNR structures

Areas with high risk to typhoon passage, high susceptibility to flooding

Prime agricultural areas in depot

n as an ECA consideration to the ECAs. Coordinate with relevant government agencies

and stakeholders as required.

DOTr PMO DED

Consultant GC

[Construction] Implement: DOTr PMO GC

Monitor: LGUs MMT DENR-EMB

cost PhP 1,500

per man-hour

2nd Quarter of 2019

Land acquisition for the Project ROW

Land Tenure

Involuntary resettlement of informal settlers who had encroached portion of the existing PNR ROW; settlements outside the existing PNR ROW between Solis to Sta. Mesa; agricultural area at Depot; and other government project sites

B- [Pre-Construction] Implement Resettlement Action Plan in

coordination with KSAs/ NHA, LGUs, lot owners and other concerned stakeholders and agencies to address the issue on land acquisition and relocation of informal settlers.

Implement: DOTr PMO KSA LGUs GC

Monitor: DOTr PMO

(Internal Monitoring)

External Monitoring Agents

As per RAP Budget

Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2019

Potential B- [Pre-Construction] Implement: DED / GC N/A 3rd

Page 145: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-9

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

conflict with other government infrastructure projects

Coordinate with DPWH and other relevant agencies.

DOTr PMO DED

Consultant GC

cost, DOTr IEC cost PhP 1,500

per man-hour

Quarter of 2018 to 2nd Quarter of 2019

Construction activities

Visual Aesthetic and Land Use

Degradation of aesthetic view and land architecture

B- [Pre-Construction/ Construction] Design and install facilities to harmonise with the

surrounding environments (shape, colour, size, etc.).

Identify planting area within the ROW that will not be covered by development to act as buffer zone, green corridor and to lessen aesthetic sore brought by construction and railway structures, and plant trees.

Adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction.

[Construction] Maintain the construction site/ yards tidy and

clean and rehabilitate after construction. Provision for temporary screens/ walls to

minimise the visual clutter. Fully reinstate pathways, other local

infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC

[Construction] Implement: Contractors

Monitor: DOTr PMO GC MMT

DED/GC cost, Construction cost PhP 1,500

per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Generation and improper handling and disposal of domestic and hazardous solid waste.

Land Value Devaluation of land value as a result of improper solid waste management

B- [Pre-Construction] Prepare a Waste Management Plan (WMP)

[Construction] Implement WMP including strict implementation of

solid waste manangement plan and proper disposal by contractor in accordance with RA 9003, hazardous waste disposal in accordance with RA 6969.

Conduct Social Development Plan (SDP) including waste management to the communities.

[Pre-

Construction] Implement: Contractors

Monitor: DOTr PMO GC LGUs MMT DENR-EMB

Contractor’s service cost/ DOTr SDP cost PhP 1,500

per man-hour

PhP 50,000 per activity

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 146: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-10

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

[Construction] Implement: Contractors

Monitor: GC DOTr PMO MMT DENR-EMB

Generation and improper handling and disposal of excavated soil, leftover concrete by excavation activities

Land Value Devaluation of land value as a result of improper handling of excavated soil

B- [Pre-Construction/Construction] Plan and implement the spoils management and

disposal plan. Plan and implement recycling and reuse of

excavated soil to be utilized for the project/ other project as much as possible. In case of excessive soil to be generated, identify the final spoil disposal site.

[Construction] Place excavated materials on appropriate dump

sites or spoils area and with adequate containment.

Strictly implement construction plan, soil management plan, and proper disposal by contractor in accordance to RA 9003, minimization of waste, segregation.

Implement: Contractors

Monitor: DOTr PMO GC MMT DENR-EMB

Construction cost

PhP 1,500 per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Construction of embankment/

slope protection

Topography

Permanent and major modification of the terrain and alteration of landform may cause ground failure

C- [Pre-Construction /Construction] Formulate and implement appropriate design

measures for the protection on slopes and banks, soil improvement / ground reinforcement to minimize ground failure during construction based on the results of the geological survey and geotechnical investigations.

[Pre-

Construction] Implement: DED

Consultant DOTr PMO GC

[Construction] Implement: Contractors Monitor: DOTr PMO GC

DED/GC cost, Construction cost PhP 1,500

per man-hour

Soil Improvement: PhP 30,000 per m³

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 147: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-11

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

MMT DENR-EMB

Earthworks, (excavation, backfilling, stockpiling, tunneling/ underground, elevated tracks/ platforms) and natural hazards

Geology/ Geomorphology

Ground Subsidence Liquefaction Landslide, Mud/ Debris Flow, etc.

Foundation of piers of elevated structures may cause unequal settlement of road surfaces.

B- [Pre-Construction/Construction] Design and implement appropriate foundation

and structures based on combination of geotechnical, geodetic and hydrologic study, and seismicity studies, and in compliance with the National Building Code and the Structural Code of the Philippines and internationally accepted guideline.

Design and install emergency escape route, early warning (alarm) system, emergency power supplies in the design of the structure particularly in the viaduct.

Plan and implement appropriate construction method, schedule, and activities based on combination of geotechnical and geological investigations, and seismicity studies in coordination with the PHIVOLCS.

[Construction] Install sufficient protection measure such as soil

improvements during excavation activities and implement appropriate materials handling program or a site protection and rehabilitation program.

Proper inspection of all installed and constructed/ ongoing construction structures and facilities.

Coordinate with the PHIVOLCS during earthquake and volcanic events to adjust construction schedule. Conduct earthquake drills for workers.

Use earth pressure balance (EPB) technique with the Tunnel Boring Machine (TBM) to prevent collapse of soil.

Construct diaphragm wall using polymer and bentonite.

Avoid simultaneous excavation in areas near river.

Monitor land subsidence. Compact soil in excavation area.

[Pre-Construction] Implement: DOTr PMO DED

Consultant GC

[Construction] Implement: Contractors Monitor: DOTr PMO GC MMT DENR-EMB

DED/GC cost, Construction cost PhP 1,500

per man-hour

Soil Improvement: PhP 30,000 per m³

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 148: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-12

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

The contractor will be required to implement construction methods through underpinning of the existing structures to control vertical and horizontal settlement of road, bridges and other existing buildings.

Clearing and removal of vegetation, stripping of soil cover, excavation of underlying rock, grading or construction of embankments and works in depot.

Pedology Soil erosion/loss of top soil

B- [Pre-Construction/ Construction] Design and install slope protection/ soil erosion

control to prevent or minimize slope failure during construction based on the results of the geo-hazard assessment and geotechnical investigations.

[Construction] Minimise the removal of vegetation cover as

much as possible, provision of slope stabilization measure/s, when necessary.

Install surface water runoff drainage systems, protection of slope and bank as required.

Provide drainage system with sedimentation pond and temporary ditches to collect runoff and settle sediments before discharge to the public drainage system.

Clean and de-clog drainage canals surrounding the work sites and depot regularly.

Implement appropriate materials handling program or a site protection and rehabilitation program including but not limited to the following;

Schedule clearing and excavation activities in a speedy manner during dry season, if possible.

Installation of temporary erosion ponds or silt traps around the major work areas.

Placement of excavated materials on appropriate staging site or spoils area and with adequate containment. Limit stock pile height up to 2 m high only. Cover stockpile of excavated soil. In addition, install silt traps, deviation channels, mounting, barriers or trenches around the stockpiles.

Installation of fence at the stockpiles of sand and gravel to reduce sediment transport during heavy rains including reduction of storage time in the

[Pre-

Construction] Implement: DED

Consultant

[Construction] Implement: Contractors

Monitor: DOTr PMO GC MMT DENR-EMB

DED /GC cost, Construction cost Soil

Erosion Control: PhP 30,000 per m²

Drainage System: PhP 15,000 per meter

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 149: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-13

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

work areas. For bored pile construction, use of bentonite or

polymer slurry to stabilize uncased borings in loose soils is highly recommended.

Utilize heavy equipment for transporting, hauling and excavating material from one area to another so as to avoid spills into drainage system.

Place construction materials in suitable areas, away from surface waters, canals and drains.

Schedule excavation works, levelling of area, removal of public utilities, e.g. water pipes, drain pipes, electric poles, etc. during the dry season to avoid soil erosion problems.

The contractor will designate sufficient number of workers to be in-charge of cleaning the site and clearing the construction materials scraps such as soil, rock, sand, and lime that are scattered onto the construction areas and road surfaces every day or within 24 hours to avoid the obstruction of natural flow, especially during the wet season.

For the underground structures, double steel sheet piles will be driven in the construction area near soil surface water sources to prevent soil erosion or soft soil displacement.

Polymer solutions mixed with bentonite shall be used in holes to prevent soil erosion and to stabilize the soil, reduce seepage into sand layers and help in soil cohesion.

Accidental spills of fuels /lubricants from construction vehicles & machineries/ hazardous chemical. Generation and improper handling/

Pedology Degradation of soil quality because of soil contamination

B- [Construction] Proper inspection and maintenance of machines

and equipment. Strictly implement solid waste management plan

and proper disposal by contractor in accordance with RA 9003, hazardous waste disposal in accordance with RA 6969.

Conduct soil quality monitoring in case of any possible contamination events occur.

Implement: Contractors

Monitor: DOTr PMO GC MMT DENR-EMB

Contractor’s Service Cost: RA 9003:

PhP 400,000 per year

RA 6969: PhP 100,000 per year

PhP 25,000

Bid Documents/ Contract Agreement

3rd Quarter of 2019 to 2nd Quarter of 2023

Page 150: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-14

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

disposal of construction/ domestic/ hazardous wastes.

per soil sample

Drilling and excavation at previously contaminated site (e.g. Sucat Thermal Power Plant).

Pedology Exposure to contaminated soil

C [Pre-Construction/ Construction] Identify a potentially contaminated site and

conduct soil sampling survey, if necessary. Conduct Environmental Site Assessment if there

is suspected contamination on the proposed location of facilities. In case that toxic substances are found within the project area and/or adjacent sites, prepare contaminated soil management plan and implement necessary remediation measures.

Storage, handling, transport, treatment and disposal of contaminated soil will be in accordance with RA 6969.

[Construction] Conduct continuous monitoring of toxic level to

ensure that contaminants will not pose hazards. In case traces are detected, construction activities on affected site will be paused until a soil management plan is developed and implemented in consultation to the DENR – EMB.

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC

[Construction] Implement: Contractors

Monitor: DOTr PMO GC LGUs MMT DENR-EMB

DED /GC cost, Contractor’s Service cost PhP 1,500

per man-hour

PhP 25,000 per soil sample

ESA Phase I: PhP 150,000 per site

ESA Phase II: PhP 1,000,000 per site

ESA Phase III: depends on the extent of contamination

EGF/Bid Documents/ Contract /Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Removal of vegetation along the proposed Project alignment particularly the trees at some areas along the

ROW and at the

Terrestrial Ecology (Flora)

Loss of Habitat

Threat to Existence and/or Loss of Important Local Species

Threat to

B- [Pre-Construction] Design, plan and implement the project that will

minimise vegetation clearing, alteration of landform, generation of noise, vibration, illumination, and vehicular movement particularly in areas adjacent to flora of higher conservation significance (i.e. Antipolo, Is-is, Narra) and in the vicinity of ecological significant areas.

Conduct 100% inventory of the affected trees

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC Tree

Contractors

DEC/GC Cost, Contractor’s Service cost t: PhP

1,000,000 for the 100% tree

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 151: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-15

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

depot Abundance, Frequency and Distribution of Important Species

Hindrance to Wildlife Access

along the alignment to determine the total counts, category, and characteristics of affected trees and minimise removal particularly in areas adjacent to vegetation of higher conservation significance as much as possible. Native/ Endemic/ Indigenous species of trees, shrubs and grasses will be specified.

Wildlings of the endangered and threatened species, if any, will be collected before construction, placed in the nursery, and give priority during nursery operation to be used for rehabilitation of areas that will be affected by project.

For tree replanting, areas not part of the development within the ROW, around the stations and depot will be prioritized for replanting activity to create buffer zone and to improve habitat for wildlife. For those that cannot be replanted within the project area, coordination with the DENR and LGUs on the identification of area for the potential trees that will be relocated.

Earth balling of trees (if there are any) will be coordinated with the DENR and LGUs including the site where the earth balled trees will be transplanted.

Secure tree cutting permit in compliance with DENR Memorandum Order No. 2012-02.

[Construction] Prior to any clearing activity, clearly mark the

ROW to avoid the unnecessary clearance of tree cutting.

Conduct tree planting activities to compensate site clearing activities. Conduct regular monitoring on survival of replanted trees and replant if necessary.

[Construction] Implement: Tree

Contractors

Monitor: DOTr PMO GC LGUs MMT DENR-EMB

inventory PhP 1,500

per man-hour

• PhP 100 per sapling

Earthworks and vehicle movement.

Generation of dust and

Terrestrial Ecology

(Fauna)

Loss of Habitat

Threat to Existence and/or

B- [Construction] Minimize vegetation clearing, alteration of

landform, generation of noise, vibration, illumination, and vehicular movement particularly in areas adjacent to flora of higher conservation

Implement: Contractors

Monitor: DOTr PMO

Construction cost : PhP 1,500 per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of

Page 152: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-16

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

noise, vibration, and illumination pollution.

Loss of Important Local Species

Threat to Abundance, Frequency and Distribution of Important Species

Hindrance to Wildlife Access

significance (i.e. Antipolo, Is-is, Narra) and in the vicinity of ecological significant areas if any.

Prepare and implement a tree and vegetation management plan as part of the construction plan considering the significance to fauna (local bird species) such as installing buffer zone, minimising the use of herbicide and machinery as much as possible.

Coordinate with EMB-DENR and SCPW for the conservation of migratory birds if required.

GC LGUs MMT DENR-EMB

2023

WATER

Site preparation, land clearing, removal of vegetation

Excavation Construction

activities

Hydrology

Flooding and inundation by sediment run off, siltation, drainage overflow, clogging

B- [Pre-Construction/ Construction] Design and install sufficient drainage system

including temporary drainage system during construction to accommodate the surface water runoff from the project and avoid any flooding in the area caused by the project, in consideration to the existing drainage system and flood storage capacity.

Based on the hydrological, geological study and local climate change data from PAGASA, design and install train system insusceptible to flood and related extreme events including temporary construction drainage, train structure to be above the flood level, installation of drainage pumping system, slope protection, etc.

Based on the result of hydrological study, design and install viaduct piers considering the potential impacts on flood levels upstream and downstream of the waterway.

Coordinate with DPWH and LGUs on the integration of proposed drainage plan to the project area.

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC

[Construction] Implement: Contractors

Monitor: DOTr PMO GC LGUs MMT DENR-EMB

DED/GC cost, construction cost : PhP 1,500

per man-hour

Soil Erosion Control: PhP 30,000 per m²

RA 9003: PhP 400,000 per year

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 153: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-17

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

[Construction] Minimise the removal of vegetation and alteration

of topography as much as possible. Install soil erosion control such as protection of

slope and bank silt traps to minimize siltation of waterways as required.

Strictly implement construction plan, operating instructions and solid waste/ soil management plan, which include minimization of waste/ soil generation, segregation, and proper disposal by contractor in accordance to RA 9003.

Regular inspection and prompt maintenance of the drainage system, all installed structures and facilities and improve/ enhance capacity when possible.

Hydrogeology

Depletion of water resource/ competition in water use

C- [Construction] Utilize surface water from the local water service

provider/s. Conduct regular monitoring of water consumption. Implement water conservation program such as

use of rain harvested/ recycled water at construction yard/ camp.

Implement: Contractors

Monitor: DOTr PMO GC LGUs MMT DENR-EMB

Contractor’s Service Cost Water

conservation program: PhP 300,000 per site

Bid Documents/ Contract Agreement

3rd Quarter of 2019 to 2nd Quarter of 2023

Earthworks (excavation, backfilling, stockpiling, tunneling/underground)

Water Quality

Degradation of groundwater quality

C- [Pre-Construction/ Construction] Plan and Implement appropriate construction

methods (i.e. excavation, backfilling, stockpiling) based on geological and geotechnical investigations.

[Construction] Install siltation/ filtration pond at tunnel

construction area. Comply with environmental permitting

requirements for the storage, transport, handling, treatment, and disposal of hazardous material/ wastes and contaminated soil in accordance with RA 6969, and solid waste / soil management plan, in accordance to RA 9003.

[Pre-

Construction] Implement: DED

Consultant Contractors

Monitor: DOTr PMO GC LGUs MMT

[Construction] Implement: Contractors

Monitor:

DED /GC cost, Construction cost PhP 1,500

per man-hour

Siltation pond: PhP 200,000

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 154: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-18

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

DOTr PMO GC LGUs MMT

Earthworks (excavation, backfilling, stockpiling)

Water Quality

Disturbance on bottom sediment and degradation of surface water

Siltation Induce of

turbidity

B- [Pre-Construction] Based on the hydrological and geodetic surveys,

design bridge piers that will minimise installation within the rivers and select appropriate construction materials to be used.

Minimize the removal of vegetation cover, alternation of topography as much as possible.

Plan and implement construction activities in consideration to the water course, embankment, and dry season.

Coordinate with NWRB, DPWH and LGUs for necessary permit.

[Construction] Implement construction activities in consideration

to the water course, embankment, and dry season.

Minimize the removal of vegetation cover, alternation of topography as much as possible.

Install slope protection to prevent soil erosion and bottom sediment around the bridge piers if necessary.

Place excavated material in temporary staging area with provision for silt traps/ siltation pond to avoid silt draining to waterways, degradation of surface water quality and clogging of waterways, if necessary.

Conduct regular surface water quality monitoring.

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC

[Construction] Implement: Contractors

Monitor: DOTr PMO GC LGUs MMT Third Party

Monitoring Contractor

DED/GC cost, construction cost : PhP 1,500

per man-hour

Soil erosion control: PhP 30,000 per m²

PhP 25,000 per sampling station

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Freshwater Ecology

Threat to abundance, frequency and distribution of species

C-

Discharge of wastewater, from construction sites/ yards/camps/related

Water Quality

Degradation of surface water quality

from wastewater discharge, accidental

B- [Pre-Construction/ Construction] Design, and implement the temporary drainage of

waste water from construction yard/ facilities/ camp, surface water runoff drainage systems to minimise discharge.

Design and install sewage treatment facility and separate non-sewage wastewater for stations and

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC

DED/GC cost, construction cost (to include cost of Third-Party Monitoring

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 155: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-19

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

facilities. Accidental

spills of fuels and lubricants from construction vehicles and machineries, as well as other hazardous chemicals like paints and solvents.

Generation and improper handling and disposal of construction, domestic wastes.

spills and runoff of fuel, paints and solvents to water bodies near the construction sites

Depot in compliance to the Sanitation Code of the Philippines. In addition, depot will have interceptor tank to remove oil and fuel from surface water.

Compliance with RA 9275, secure discharge permit.

[Construction] Install wastewater treatment and portable sanitary

facilities at the construction sites/yards. Toilets and lavatories to be provided at the construction camps should be at a ratio of 10 people per toilet. The mobile toilets with wastewater treatment system will be provided.

Conduct proper inspection and regular maintenance of construction machineries, equipment, vehicles and wastewater treatment equipment and facilities with appropriate measure to collect any leakage

Control oil refuelling activities and provide oil bunds in oil storage areas.

Prohibit workers from dumping garbage into drains and canals.

Implement material handling program or a site protection program.

Prior to operation of the batching plant, construct settling/retention ponds with sufficient capacity for treatment of wastewater from washing of equipment such as mixer drums, trucks, and chutes.

Properly maintain settling/retention ponds to ensure compliance with the effluent quality.

Comply with environmental permitting requirements for the storage, transport, handling, and treatment of hazardous material/ wastes and contaminated soil in accordance with RA 6969 and solid waste / soil management plan, which include minimization of waste/soil generation, segregation, and proper disposal including the temporary storage by contractor in accordance with RA 9003.

[Construction] Implement: Contractors

Monitor: DOTr PMO GC LGUs Third party

monitoring contractor

MMT DENR-EMB

Contractor): PhP 1,500

per man-hour

RA 9275: PhP 400,000 per year

RA 6969: PhP 100,000 per year

RA 9003: PhP 400,000.00 per year

PhP 25,000 per effluent sampling point

Freshwater Ecology

Threat to abundance, frequency and distribution of species

C-

Page 156: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-20

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

Conduct of effluent quality monitoring at discharge point.

Generation of hazardous wastes at construction sites

Water Quality

Potential contamination of surface water

B- [Pre-Construction/Construction] Contractor will prepare a list of hazardous

chemicals to be brought at the site including information on the quantity and hazard classification.

Minimize or avoid long storage of hazardous materials onsite.

Comply with the labelling and storage requirements of hazardous materials/ chemicals, including the provision of MSDS onsite.

Conduct refuelling and equipment servicing only in designated areas with impervious surface.

Provide oil and grease traps and other spill containment measures.

Collect hazardous materials including used fuel, lubricating oil and contaminated containers for proper disposal.

Implement: Contractors

Monitor: DOTr PMO GC LGUs MMT Third Party

Monitoring Contractor

Construction cost (to include cost of Third-Party Monitoring Contractor) PhP 1,500

per man-hour

RA 9275: PhP 400,000 per year

RA 6969: PhP 100,000 per year

RA 9003: PhP 400,000.00 per year

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Spillage of fuel and other hazardous substances

B- [Pre-Construction/Construction] Strictly implement the spill management plan. Store fuel and hazardous substances in paved

areas with embankment. If spills or leaks do occur, undertake immediate clean up.

Ensure availability of spill clean-up materials (e.g. absorbent pads, etc.) specifically designed for petroleum products and other hazardous substances where such materials are being stored and used.

Train construction personnel in handling fuels and on spill control procedures.

Ensure all storage containers are in good condition with proper labelling.

Regularly check containers for leakage and undertake necessary repair or replacement.

Store hazardous materials above flood level. Equipment maintenance areas shall be provided

with drainage leading to an oil-water separator; oil will be regularly skimmed to ensure efficiency. Discharge of contaminated water shall be

Page 157: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-21

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

prohibited. Store waste oil, used lubricant and other

hazardous wastes in tightly sealed containers to avoid contamination of soil and surface water. Transport and off-site disposal of such wastes shall be consistent with national regulations.

Generation of Solid Waste

Water Quality

Solid wastes may pollute the surface waters due to

improper handling and disposal

C- [Pre-Construction/Construction] Comply with environmental permitting

requirements for the storage, transport, handling, and treatment of hazardous material/ wastes and contaminated soil in accordance with RA 6969 and solid waste / soil management plan including minimization of waste/soil generation, segregation, temporary storage and proper disposal by contractor in accordance with RA 9003.

Provide garbage bins and facilities within the project site for temporary storage of construction waste and domestic solid waste.

Separate solid wastes from hazardous waste and reusable wastes.

Store solid wastes temporarily on-site and secure facilities with weather-proof flooring and roofing.

Ensure that wastes are not haphazardly dumped within the project site and adjacent areas.

Undertake regular collection and disposal of solid wastes to sites approved by local authorities.

Implement: Contractors

Monitor: DOTr PMO GC LGUs MMT Third Party

Monitoring Contractor

Construction cost (to include cost of Third-Party Monitoring Contractor): PhP 1,500

per man-hour

RA 6969: PhP 100,000 per year

RA 9003: PhP 400,000.00 per year

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

AIR

Operation of construction machinery, equipment and vehicles

Removal of trees and other vegetation

Climate Change

Exhaust emissions from movement of equipment and vehicles, excavated soil carried by vehicles and other

C- [Pre-Construction] Plan and design structures that will minimise the

removal of vegetation and alteration of topography, if possible.

[Construction] Conduct proper inspection and preventive

maintenance of heavy equipment, machineries and service vehicles to meet the DENR Emission Standards.

Use electric or fuel-efficient equipment, machineries and vehicles and maximize its

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC

[Construction] Implement: Contractors

DED/GC cost, / Construction cost PhP 1,500

per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 158: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-22

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

heavy loaders.

operation, if possible. Monitor: DOTr PMO GC MMT DENR-EMB

Climate Risk

Meteorology/ climatology

Restrictions/ disruption of construction due to soil erosion/ landslides/ and flooding.

A- [Pre-Construction] Take account of change in local micro climate

such as rainfall, temperature pattern for 2020 and 2050 in project design criteria and schedule of construction works.

Based on the hydrological and geodetic study, design and install train system which is robust to climate change and related extreme events including drainage, passenger facilities and structures (viaduct and embankment) i.e. train facilities to be above the flood level, installation of drainage pumping system.

[Construction] Adjust construction activities in consideration to

local climate/ extreme events such as extreme heat to avoid overheating of construction equipment and service vehicles and cause heat stress to workers.

Implement Emergency Response Plan.

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC

[Construction] Implement: Contractors

Monitor: DOTr PMO GC MMT

DED/GC cost, construction

cost

PhP 1,500

per man-hour

EGF/ Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Slower drainage, soil erosion, disruption in construction by increased rainfall.

B-

Overheating of

construction

equipment, vehicles / heat stress by high temperature and heat waves.

C-

Earthworks including excavation activities

Site clearance including removal of topsoil at the depot site

Air Quality Degradation of air quality due to dust generation from transportation of excessive soil/ spoil to

B- [Construction] Minimize alteration of topography and removal of

vegetation. Adjust construction activities in consideration to

weather system, identifying periods of high winds and drought that aggravated dust transport.

Conduct prompt inspection and regular maintenance of heavy equipment, machineries and service vehicles to meet the DENR Emission

Implement: Contractors

Monitor: DOTr PMO GC MMT DENR-EMB

Construction cost: PhP 1,500

per man-hour

PhP 30,000 to 80,000 per

Bid Documents/ Contract Agreement

3rd Quarter of 2019 to 2nd Quarter of 2023

Page 159: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-23

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

fill area construction activities.

Standards Check and maintain or monitor engine conditions

and machines used in the construction at least once a week.

Conduct weekly maintenance of vehicles and equipment to ensure emissions comply with standards.

Conduct regular cleaning and clearing of construction access / sites surfaces of spoils and debris from construction equipment and vehicles and wetting of ground soil in the construction site when necessary. Stock pile and trucks loaded with spoils will be covered.

Implement materials handling or a site protection and rehabilitation program.

Haul the excavated materials from the construction areas as soon as possible or within 24 hours

Conduct water sprinkling in areas prone to dust emission such as at soil excavation areas or stockpile of aggregates and under the elevated stations. Keep excavated soil and stockpiles moist.

Control vehicle movement maintaining the speed limit within the construction site to <10kph and minimize vehicle transport by maximizing the use of site generated materials

Impose speed limit of no more than 30kph on construction vehicles particularly when passing communities, residential or commercial areas or sensitive areas such as hospitals, schools or religious institutions such as temples, mosques and churches.

Require contractor to wash wheels of vehicles before leaving the construction area particularly at the depot and transition areas to avoid mud tracking on roads that cause dust emission later on.

Require materials delivery trucks to provide cover when transporting materials

ambient air sampling station depending on the parameter to be monitored

Operation of construction machinery, equipment and vehicles

Air Quality Degradation of air quality due to gaseous emissions from machineries and service vehicles.

C-

Page 160: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-24

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

Install board-ups or fence at the construction area not less than 2 meters high.

In case of accidental spill of materials during transport, the contractor will be required to immediately clean-up spilled materials.

Prohibit burning of waste materials in accordance to RA 9003. Unauthorized burning of construction materials and wastes shall be subject to penalties for the Contractor.

Ready mixed concrete produced and mixed outside the construction area shall be used to prevent and mitigate impacts on communities around the construction area..

Designate at least 3-4 workers per construction area to clean the site after the completion of daily activities and arrange material piling in order to prevent dust diffusion.

For the elevated structures, provide nets and scaffoldings for falling debris from construction of elevated structures to avoid dust emission and hazards from falling debris.

Monitor air quality at identified nearby sensitive receptors regularly and evaluate effectiveness of the air pollution reduction measures provided.

NOISE Operation of

construction machinery, equipment and vehicles

Earthworks Construction

of structures and facilities

Acoustic Noise

Increase in ambient noise level

B- [Pre-Construction /Construction] Position storage and other large equipment to

function as noise barriers Identify haul roads that minimizes noise impacts Consider traffic re-routing Maximize the use of existing structures like

fences, walls, and other structures as noise barriers.

Select sites (i.e. construction yard, temporary facilities, access route) in consideration to sensitive receptors including ecologically significant areas (if any) likely to be affected.

Design and install absorbers along the alignment during construction especially in areas with sensitive facilities.

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC Contractors

[Construction] Implement: Contractors

Monitor: DOTr PMO

DED/GC cost, / construction cost • PhP 1,500

per man-hour

PhP 8,000 per worker for PPE

PhP 25,000 per noise monitoring station

PhP 30,000

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 161: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-25

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

Design and adopt long rails and ballast-less track with elastic and absorbent sleeper support to minimize noise generation from train operation.

Provision of effective noise barriers on each side of the track (continuous 1 m high concrete wall throughout alignment except 500m length in Buendia Section i.e. from chainage 10+300 to 10+800, where a 2.5-m curved wall will be installed.

[Construction] Implement construction activities in consideration

to time, duration, and scale to optimize the use of construction equipment, machineries, and vehicles in accordance to the noise emission standard.

Minimise alteration of topography and removal of vegetation which generate noise.

Install noise control devices such as mufflers and noise suppressors to all construction equipment and machineries. Use of electric instead of diesel-powered equipment, hydraulic tools instead of pneumatic tools.

Conduct regular inspection and preventive maintenance of heavy equipment, machineries and service vehicles to meet the DENR Emission Standards.

Monitor noise levels at identified nearby sensitive receptors (residential, school, places of worship and hospital areas) including ecologically significant area/s (if any) likely to be affected by the operation and evaluate effectiveness of the noise reduction measures provided.

Noise control measures at surface construction include installation of temporary noise barriers and 2.0-meter fence around the construction area.1

Use noise barriers and sound absorption

GC Third Party

Monitoring Contractor

MMT DENR-EMB

per meter noise barrier

.

Page 162: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-26

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

materials with no less than 70% and 80% of sound absorption coefficient at 1,000 and 500 hertz, respectively.

Noise levels from equipment and machinery shall conform to the noise standards and WB-IFC Environmental, Health and Safety Guidelines.

No construction shall be allowed between nighttime hours of 10 pm to 6am unless proper consultation has been conducted and agreement has been reached with the affected persons and local officials, and all adverse environmental impacts are mitigated to acceptable levels. In case of activities that will cause noise exceeding the acceptable level, permission from DOTr-PMO and concerned LGU must be secured and advance notice to the public will be issued at least 24 hours before the start of construction activities.

Workers will be required to wear appropriate PPE including ear plugs or ear muffs in areas generating excessive noise.

Require drivers of construction vehicles to minimize blowing of horn and limit speed when passing through residential areas.

In case of complaints, the DOTr-PMO and contractor will continuously operate GRM to urgently respond to the complaint and resolve the problem.

VIBRATION

Conduct of geotechnical investigation

Operation of construction machinery, equipment and vehicles

Pile driving for piers

Ground vibration

Increase in ambient vibration level and threat to the health and safety of sensitive receptors

C- [Pre-Construction / Construction] Select sites in consideration to sensitive receptors

including ecologically significant areas (if any) likely to be affected.

Conduct building condition survey of old PNR structures and buildings adjacent to the alignment to provide proper protection provision measures and continuous monitoring from the impact of vibration.

Prepare and submit work plan for building and structures of historic concerns and obtain approval from Cultural Agencies.

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC Contractors

[Construction] Implement:

GC Cost/ Construction cost: PhP 1,500

per man-hour

PhP 80,000 per vibration monitoring station

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 163: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-27

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

[Construction] Implement construction activities in consideration

of time, duration, and scale of construction to optimize the use of construction equipment, machineries, and vehicles with minimal vibration generation.

Select construction equipment and machineries matching the scale of the construction and with minimal vibration generation, if possible.

Provide training on vibration mitigation and provide appropriate PPE to construction workers.

Monitor vibration levels including identified nearby sensitive receptors, old PNR structures including ecologically significant area/s (if any) likely to be affected by the operation and evaluate effectiveness of the vibration reduction measures provided.

Coordinate with sensitive receptors prior to pile driving.

Strictly control construction activities close to historical/ archaeological sites.

If construction activities will cause continuous vibration, especially foundation excavation, it is necessary to reduce energy at each excavation.

Require vehicles transporting construction materials and equipment to follow traffic rules strictly and limit speed not to exceed 30 kph and the load shall not exceed 25 tonnes if passing communities or commercial or sensitive areas (e.g. health premises, schools, educational institutions or religious institutions such as temples, mosques and churches).

In case of vibration due to construction activities, the construction works will be carried out only in daytime from 8am to 6pm unless proper consultation has been conducted and agreement has been reached with the affected persons and local officials, and all adverse environmental impacts are mitigated to acceptable levels to minimize disturbance to people.

Contractors

Monitor: DOTr PMO GC Third Party

Monitoring Contractor

MMT DENR-EMB

PhP 15,000 per training

Page 164: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-28

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

PEOPLE

Disclosure of project information and public consultation

Public Involvement and Support

Communities and stakeholders not being provided with the appropriate information on the implementation of the Project.

Complaints from the communities and stakeholders.

B- [Pre-Construction/ Construction] Prior to start of construction works, local

establishments, local authorities and other stakeholders who are likely to be affected by the project shall be informed on the construction schedule and activities, potential environmental impacts, mitigation measures and grievance redress procedure through public meetings.

During pre-construction and construction, public involvement activities will continue based on the framework for public involvement and disclosure. Regular consultations with affected people and relevant offices/agencies will be conducted by the contractor during construction phase and by the DOTr during operation phase to ensure adequate and timely mitigation of project adverse environmental impacts.

Prior to commencement of site works, the DOTr in coordination with the contractors will established the approved grievance redress mechanism that will allow for the following:

Receiving/recording and immediate response (within 24 hours) by the contractor of any construction-related complaints.

Report issues to DOTr-PMO through GC by the contractor within 24 hours.

Complaints reported by the affected person(s) to DOTr-PMO are recorded and relayed to the contractor within 24 hours for immediate resolution.

Installation of notice boards at the construction sites that indicate the name and telephone numbers (hotline) of contractors who are tasked to receive and document complaints.

Implement: DOTr PMO Contractors GC

Monitor: DOTr PMO

(internal monitoring)

GC MMT Third Party

Monitoring Agents

Part of DOTr project /IEC cost PhP 1,500

per man-hour

Bid Documents/ Contract Agreement

Prior to start of construction

Land acquisition for ROW and involuntary Resettlement for

Informal Settler Families (ISFs)

Displacement of ISFs

Disturbance of

A- [Pre-Construction] Design train system maximising the existing PNR

ROW and minimising additional land acquisition. Prepare and implement Resettlement Action Plan

Implement: DOTr PMO DED

Consultant

DED /GC cost, RAP Budget PhP 1,500

RAP Budget 3rd Quarter of 2018 to 2nd

Page 165: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-29

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

Project Affected Families (PAFs)

Vulnerable persons (Women-headed households, elderly, persons with disabilities and the poor)

livelihood Loss of

income

(RAP) to ensure that PAFs are provided with proper relocation area and/or justly compensated. The RAP will include the following:

Provision of relocation sites for ISFs. Livelihood and income restoration for

head-of-household PAPs of ISFs and vulnerable persons.

Prior to displacement, secure and/or develop relocation sites in coordination with the concerned LGUs, Key Shelter Agencies, and other concerned stakeholders with conducive living condition and basic utilities, services and amenities.

[Pre-Construction/ Construction] Conduct external and internal monitoring to

ensure that displacement activities are conducted in compliance to the RAP.

If PAFs raise an issue, ensure prompt response and resolution per established Grievance Redress Mechanism (GRM).

GC LGUs KSAs Monitor DOTr

PMO(internal monitoring)

External Monitoring agents

MMT

per man-hour

Quarter of 2023

Legal PAFs

Displacement/ Disturbance of

Properties Change/C

onflict in Land Ownership

Impact on Livelihood and Income (i.e. farming, business)

A- [Pre-Construction] Prepare and implement Resettlement Action Plan

(RAP) to ensure that PAFs are justly compensated for the loss of income by the project.

Payment of compensation prior to displacement. Coordination with the LGUs, land owners and

other concerned stakeholders in acquiring the land and/or securing ROW.

[Pre-Construction/ Construction] Prepare and implement livelihood and income

restoration for PAF’s whose present means of livelihood is no longer viable and will have to engage in new income activity.

Prepare and implement Social Development Plan (SDP) including livelihood training for business owners, vendors, employers and agricultural landowners affected by project.

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC LGUs KSAs

Monitor DOTr

PMO(internal monitoring

External Monitoring agents

MMT

DED /GC cost, RAP Budget/ DOTr IEC cost PhP 1,500

per man-hour

RAP Budget 3rd Quarter of 2018 to 2nd Quarter of 2023

Page 166: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-30

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

Involve external and internal monitoring agencies to ensure that displacement activities are conducted in compliance to the RAP.

If PAFs raise an issue, ensure prompt response and resolution per established GRM

[Construction] DOTr PMO GC LGUs KSAs

Monitor DOTr

PMO(internal monitoring

External Monitoring agents

MMT

Social Aspect (Gender Equality and Vulnerable Groups)

Generation of employment and

livelihood opportunities and improvement of safety

C- [Pre-Construction/ Construction] Prepare and implement RAP to ensure that

gender equality and needs of vulnerable group are well addressed including livelihood and skills training program

Design and install train system in consideration to universal design and strategic placement of security and lighting within the vicinity of the stations;

Employ workers in consideration to gender equality.

Include gender sensitive livelihood and skills training program in the SDP with due consideration to vulnerable group.

[Pre-

Construction] Implement: DOTr PMO DED

Consultant Contractors GC

Monitor DOTr PMO

(internal monitoring)

GC External

Monitoring agents

MMT

[Construction] Implement: Contractors

Monitor: DOTr PMO

(internal monitoring)

DED/ GC cost, Construction Cost/ RAP cost t PhP 1,500

per man-hour

PhP 15,000 per person per training

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 167: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-31

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

GC LGUs External

Monitoring agents

MMT

Demolition of Buildings

Social Component

Temporary disruption of regulr activities of sensitive receptors

C- [Pre-Construction] Consult affected household/ land owner prior to

demolition of the structure/ building

Implement: Contractors DOTr PMO GC

Monitor: External

monitoring agents

MMT

GC cost/ Costruction cost PhP 1,500

per man-hour

Bid Documents/ Contract Agreement

Commencing on mobilization on site

Solid waste management

Generation of solid wastes and demolition debris

Scavenging of demolition wastes

C- [Pre-Construction] Identify a site for the demolition wastes away from

sensitive receptors as possible Provide barriers/ security measures on temporary

storage areas of demolition wastes to prevent scavenging activities which may compromise the safety of scavengers

Implement: Contractors

Monitor: DOTr PMO GC MMT LGUs

Clearing of the proposed project area

Resettlement

In Migration

In-migration to the project area

C- [Pre-Construction / Construction] Plan and implement construction schedule to

shorten time between the pre-construction and construction as much as possible.

Install fencing and guarding of the proposed project to restrict the public from entering the ROW.

[Pre-

Construction] Implement: DOTr PMO Contractors LGUs

Monitor: DOTr PMO

(internal monitoring)

MMT External

DOTr SDP cost/ contractor’s Service Cost:/ RAP cost : PhP 1,500

per man-hour

SDP: PhP 15,000 per person

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Conflict between existing residents and new relocatees

C- [Pre-Construction / Construction] Prepare and implement SDP in coordination with

host LGU’s to align projects/programs to their development plans.

Page 168: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-32

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

Pre-construction and construction activities (Site preparations, mobilization, etc.)

Social Component

Damage or loss caused by contractor on privately-owned property outside the scope of land acquired under the RAP

C- [Pre-Construction/ Construction] Compensation to property owner commensurate

with rates set out in the RAP.

monitoring agents

[Construction] Implement: Contractors DOTr PMO LGUs

Monitor: GC MMT External

monitoring agents

PhP 10,000 per meter fence

In migration to new relocation site

Basic Services/ Resources

Increased demand on public infrastructure

Degradation on livelihood

C- [Pre-Construction / Construction] Prepare and implement RAP in consideration of

relocation site to sufficiently cover the expected demand of basic services, resource and social programs at relocation sites in coordination with LGUs.

Prepare and implement SDP in coordination with the host LGUs to align projects or programs to their development plans.

[Pre-

Construction] Implement: DOTr PMO DED

Consultant GC LGUs KSAs

Monitor: DOTr PMO

(internal monitoring)

External Monitoring Agents

MMT

[Construction] Implement: DOTR PMO

DED/GC cost, RAP Budget / the DOTr’s SDP cost PhP 1,500

per man-hour

SDP: PhP 15,000 per person

RAP Budget 3rd Quarter of 2018 to 2nd Quarter of 2023

Loss of outdoor spaces

C- [Pre-Construction / Construction] Coordinate with respective LGU’s and PNR

regarding the possible measures for the transfer/provision or relocation of public parks and other recreational facility.

Page 169: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-33

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

GC LGUs

Monitor: DOTr PMO

(internal monitoring)

External Monitoring Agents

MMT

Establishment of construction camps and other construction facilities (casting yard, laydown/ storage areas, concrete batching plants)

Public Activities

Temporary disruption of normal activities of sensitive receptors

Temporary loss of private lands

C- [Pre-Construction] Contractor to secure the necessary approvals and

permits prior to establishment and operation of construction-related facilities.

Coordination with LGUs to identify minimization options, including identification of available public land where possible for access roads, material storage areas, construction yards, etc.

Negotiation for temporary land use with land owners and payment of rent commensurate with market rates and restoration of land to pre-use conditions within 3 months of discontinuation of use. Rent will continue to be paid until the land is restored.

Select construction camps and other construction facilities at least 300m from sensitive receptors such as residential housing areas, hospitals, schools, religious and cultural sites.

Implement: Contractor DOTr PMO

Monitor: GC External

monitoring agents

MMT

Construction Cost PhP 1,500

per man-hour

Bid Documents/ Contract Agreement

Commencing on mobilization on site.

Disruption to community services due to relocation of utilities such as water supply, electric distribution poles, and communication lines.

Public services

Disruption of public services

C- [Pre-Construction] Coordinate with the utility companies prior to

relocation of utilities. Issue notices or announcements in advance

regarding temporary disruption of services.

Implement: DOTr PMO Contractor GC DED

consultant

Monitor: MMT

DEC/GC Cost, construction cost: PhP 1,500

per man-hour

Bid Documents/ Contract Agreement

Commencing on mobilization on site.

Page 170: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-34

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

Encroachment of the proposed Project to historical sites, tourist spots, etc.

Excavation activities

Construction of the proposed project

Historical Sites, artefacts and archaeological remains

Impacts on Cultural/ Historical resources

B- [Pre-Construction] Conduct literature review and site validation of the

potential historic structures in coordination with PNR and Cultural Agencies (NCCA, National Museum and NHCP);

Perform measured survey of the identified historic structures including its foundation and building condition.

Coordinate closely with the Cultural Agencies, concerned LGUs and PNR for verifying the qualification of those structures and provide necessary protection measures.

Prepare a protection plan for those identified PNR structures which will be maintained in accordance to the agreed procedure.

[Construction] Implement the approved protection plan Close coordination with the National Museum on

the appropriate course of action in case of any archaeological finds.

[Pre-

Construction] Implement: DED

Consultant GC DOTr PMO Contractors

[Construction] Implement: Contractors

Monitor: DOTr PMO GC LGUs MMT

DED /GC cost, construction cost: PhP 1,500

per man-hour

PhP 100,000 per m²

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Local conflicts of interest

Potential conflict among PAFs and other government infrastructure projects

B- [Pre-Construction] Close coordination with BCDA, DPWH, and other

relevant agencies Prepare and implement Resettlement Action Plan

(RAP) to ensure that PAFs are justly compensated for the loss of income by the project prior to displacement.

Conduct external and internal monitoring agencies to ensure that displacement activities are conducted in compliance to the RAP.

Prepare and implement arrangement on financial assistant to the receiving of PAFs.

[Construction] If PAFs raise an issue, ensure prompt response

and resolution per established GRM Conduct external and internal monitoring

agencies to ensure that displacement activities are conducted in compliance to the RAP.

[Pre-

Construction] Implement: DED

Consultant DOTr PMO GC

Monitor: External

Monitoring agents

MMT

[Construction] Implement: DOTr PMO

Monitor: DOTr

DED/GC cost, RAP cost/ construction cost/ DOTr IEC Cost PhP 1,500

per man-hour

Page 171: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-35

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

PMO(internal Monitoring)

LGUs External

Monitoring agents

MMT

Generation of solid waste, excavated soil and hazardous material

Basic Services/ Resources

Increased demand on waste disposal

B- [Pre-Construction / Construction] Identification of final disposal site for solid waste,

excavated soil, hazardous waste at each LGUs. Conduct regular monitoring of disposal status in

compliance to RA 9003 and RA 6003.

Implement: Contractors

Monitor: DOTr PMO GC LGUs

Construction cost RA 6969:

PhP 100,000 per year

RA 9003: PhP 400,000 per year

PhP 1,500 per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Generation of potential air and water pollutants due to:

Heavy lifting and movement of heavy equipment

Construction of the proposed project

Public Health and Safety

Degradation of public health

Increase in accident involving local communities

B- [Pre-Construction / Construction] Formulation and implementation of IEC Plan to

inform the affected LGU and local communities and the general public about 1) the project, project activities, duration, possible project impacts and incorporate their comments and inputs in the design, 2) the potential impact of project activities to air quality, noise, vibration, and climate change, and corresponding health and safety mitigation measures, and 3) the Grievance Redress Mechanism to handle complaint/s if any.

Plan for construction sites/facilities/yard and access route in consideration to health and safety of local communities.

Plan and implement SDP including health and safety of local community

[Construction] Provide safety officers to monitor the health and

[Pre-

Construction] Implement: DOTr PMO GC Contractors

Monitor: LGUs External

Monitoring agents

MMT

[Construction] Implement: Contractors

DOTr IEC/SDP Cost, Construction cost IEC: PhP

50,000 per activity per LGU

PhP 10,000 per meter fence

PhP 1,500 per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 172: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-36

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

safety of the local community. If any complains rises, immediately identify the causes and evaluate built-in measures.

Install fencing of the construction site, provision of signage and posters, and guarding of the access point to ensure that the area is not accessible to the public.

Implement Emergency Response Plan and Health and Safety Management Plan.

Monitor: DOTr PMO GC LGUs MMT

Risks to Workers

Occupational Health and Safety

Increase risk of accidents at construction sites

Spread of infectious disease among workers

B- [Pre-Construction/Construction] Prepare and implement Occupational and

Community Health and Safety Plan and Emergency Response Plan based on the WB-IFC EHS Guidelines.

Include medical certificate in the requirements for hiring of workers to ensure that they are fit to work. Ensure that they are provided with proper training on construction, occupational health and safety, and emergency response procedure.

Plan construction details such as storage of equipment and machinery and access route of heavy vehicle considering health and safety of workers.

Provide appropriate personal protective equipment (PPE) to all construction workers, particularly to the personnel working on heights, heavy and electrical equipment.

Establish Health and Safety Desk or Medical Station at the active construction sites to monitor and safeguard the health of the workers and local residents and to provide immediate response during unexpected incidents/emergencies.

Provide fire-fighting equipment at work areas and construction camps.

Close coordination with the nearest hospitals in the active construction site for immediate transfer and/or further evaluation and medical management of the patient.

Require the contractor to appoint an environment, health and safety officer to supervise the

Implement: Contractors

Monitor: DOTr PMO GC LGUs MMT

Contractor’s service fee on health, safety and environmental management PhP 1,500

per man-hour

PhP 8,000 per personnel for PPE

Health and Safety Desk or Medical Station: PhP 200,000 per site

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 173: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-37

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

implementation of environmental mitigation measures and to ensure that health and safety measures are strictly implemented at the construction site and immediate vicinity.

Provide adequate drainage in construction camps to prevent water logging and formation of breeding sites for mosquitoes.

Provide potable water, hygienic sanitation facilities/toilets with sufficient water supply.

Ensure that all wastewater emanating from construction camps are treated and complies with the effluent standards.

Provide fence on all areas of excavation to avoid accidents.

Implement fall prevention and protection measures such as scaffoldings, wearing of safety belts by workers, etc. when working in high areas.

Provide sufficient lighting in tunnel areas and underground station excavation sites.

Provide emergency lighting system in case of power shutdown.

Ensure that sufficient fresh air is supplied at confined work spaces at the tunnel and underground station excavation sites. Ensure that air filters are kept clean.

Confined spaces such as tunnels shall be provided with safety measures such as venting, monitoring, and emergency rescue procedures.

Conduct orientation for construction workers regarding health and safety measures, emergency response in case of accidents, fire, etc. and prevention of HIV/AIDS, STIs and other diseases.

Employment of workers

Local Economy

Generation of Local Employment

Hiring of workers from

B+ [Pre-Construction /Construction] Close coordination with the host LGUs (barangay

level) regarding the hiring of temporary workers to ensure that the workers being considered are legitimate residents in the area. Those affected by the Project will be prioritized for employment.

Provide skill trainings to PAFs under livelihood

Implement: DED

Consultant GC Contractors DOTr PMO

DED/GC Cost, RAP cost/ DOTr IEC cost/ Contactor’s Service Cost :

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 174: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-38

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

outside the community might create peace and order and social conflicts with local communities and increased HIV/AIDS risk.

and income generation program developed by RAP

Provide HIV/STI awareness and prevention training to construction workers and contractor’s employees/staff

Monitor: GC LGUs DOTr PMO External

Monitoring agents

MMT

Skills

Training: PhP 15,000 per person

Traffic congestion and access problems

Mobility/ Public Transport

Increase in traffic volume within the project area

B- [Pre-Construction/Construction] Conduct Traffic Impact Assessment (TIA) and

based on its results, prepare a Traffic Management Plan (TMP) for approval. Implement the approved TMP. The plan shall be designed to ensure that traffic congestion due to construction activities and movement of construction vehicles, haulage trucks, and equipment is minimized. The plan shall be prepared in consultation with concerned traffic agencies, local officials and the general public. The plan shall identify traffic diversion and management, traffic schedules, traffic arrangements showing all detours, necessary barricades, warning/advisory signs, road signs, lighting, and other provisions to ensure that adequate and safe access is provided to motorists in the affected areas.

Coordinate with the traffic police for traffic management.

Provide traffic advisory signs for the public that construction is in progress and that road narrows in some sections.

Employ flag persons to control traffic at underground station sites.

Provide sufficient lighting at night within and in the

[Pre-

Construction] Implement: DED

Consultant GC DOTr PMO

[Construction] Implement: Contractors

Monitor: DOTr PMO GC LGUs MMT

DED / GC Cost, Construction cost: PhP 1,500

per man-hour

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 175: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-39

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

vicinity of the construction sites. Prohibit prolonged side street parking of

construction trucks. As much as possible, schedule delivery and

transport of construction materials and spoils during non-peak hours.

Blocking of existing access roads

Public Access

Impact on Public Access

Impact to School Access

Increase in accidents

B- [Pre-Construction/ Construction] Based on the study on public access at affected

barangay, maintain the existing public access as much as possible.

In case of any temporary closure during construction, minimise the impact to the daily life of affected communities such as access to school infrastructure in coordination with the DepEd and host LGUs for the schedule of construction activities.

In case of permanent loss of public access, RAP will be applied.

Disseminate information to the public, barangay, and LGUs on the potential impact to the existing public access and mitigation measure through the project activities.

Provision of diversion route with appropriate health and safety measures. In case of any changes, prompt update on the diverted routes to the concerned communities and LGUs,

Assignment of traffic guide to provide assistance to the road users.

Implement: Contractors DOTr PMO

Monitor: DOTr PMO

(internal monitoring)

GC LGUs External

monitoring agents

MMT

Construction Cost / DOTr IEC cost PhP 50,000

per IEC activity per LGU

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Movement of construction equipment

Delivery of construction materials

Additional commuters due to construction workforce

Blocking of

Traffic Management

Traffic Congestion

B- [Pre-Construction/ Construction] Conduct Traffic Impact Assessment (TIA) and

based on the results of TIA, prepare and implement Traffic Management Plan (TMP), coordinate to the concerned LGUs and transport operator/s and get their inputs and approval.

Schedule transport of heavy structures during period when there are fewer vehicles on the road and posting of appropriate traffic signage and warnings.

Disseminate information to the general public, host barangays, and LGUs on the potential

[Pre-

Construction] Implement: DED

consultant DOTr PMO Contractors

[Construction] Implement:

DED cost/ DOTr IEC Cost/ Construction Cost TIA: PhP

10,000,000 IEC: PhP

50,000 per activity per LGU

Bid Documents/ Contract Agreement

3rd Quarter of 2018 to 2nd Quarter of 2023

Page 176: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-40

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

access roads impact of the project to the existing access and provide mitigating measures.

Contractors

Monitor: DOTr PMO GC LGUs External

Monitoring agents

MMT

OPERATION

LAND

Operation and maintenance of the Project

ECA Incompatibility with the area that will be hit hard by natural calamities.

B- Coordinate with PAGASA / PHIVOLCS and adjustment of train schedules.

Implement proper inspection and prompt maintenance of drainage systems.

Implement: Operator

Monitor DOTr PMO LGUs Third Party

Monitoring Contractor

Included in the operation and maintenance cost: PhP 1,500

per man-hour

Operation and maintenance cost

From 3rd Quarter of 2023

Presence of the proposed project structures (railway, passenger facilities, depot etc.)

Visual aesthetics

Impairment of visual aesthetic

C- Maintain tree planting to minimise the visual impact by the project and harmonise to the surrounding environments in open areas within the ROW, depot and around the stations, to create green corridor.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost: PhP 1,500

per man-hour

EGF From 3rd Quarter of 2023

Generation of domestic and hazardous wastes including accidental oil and lubricant spills from passenger facilities (station), depot.

Land value Degradation of land value and soil quality due to improper handling of domestic and hazardous wastes

C- Conduct proper inspection and prompt maintenance of machines and equipment, and facilities.

Strictly implement solid waste management plan in accordance to RA 9003, and treatment of hazardous chemicals and contaminated soil in accordance with RA 6969.

Conduct of soil quality monitoring when necessary.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost: PhP 1,500

per man-hour

RA 9003: PhP 400,000

Operation and maintenance cost/ EGF

From 3rd Quarter of 2023

Page 177: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-41

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

per year RA 6969:

PhP 100,000 per year

Generation of solid waste from office and service areas

Solid Waste Management

Degradation of the area of the facilities and surrounding communities

B- Provide solid waste segregation bins at each office area and at train stations.

Coordinate with the concerned LGUs in the collection and disposal of segregated solid wastes.

Maintain daily record of solid wastes generated and collected.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost

PhP 1,500 per man-hour

Contract agreement

From 3rd Quarter of 2023

Generation of hazardous waste from maintenance area at Depot and related facilities.

Toxic and Hazardous Waste Management

Degradation of the area of the facilities and surrounding communities

B- Provide hazardous waste bins at the stabling yard Record quantities of hazardous wastes generated Commission the services of a Government-

recognized hazardous waste transporter and treater.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost

PhP 1,500 per man-hour

EGF/ Contract agreement

From 3rd Quarter of 2023

Occurrence of landslides, volcanic hazards, ground shaking and liquefaction

Likely seismic events around the alignment

Subsidence, Liquefaction, Landslide, Mud/Debris Flow, etc.

Damage to tracks

Risk to the life of passengers and workers

Damage to passenger facilities.

B- Conduct inspection in the event of natural hazard occurrence to assess damage of structures.

Regular coordination with the PHIVOLCS for earthquake and volcanic events to adjust the train schedule as necessary.

Conduct earthquake drills for train users are also advised.

Conduct proper inspection and prompt maintenance checks to every single installed structure and facility and improve/ enhance capacity when possible.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost: PhP 1,500

per man-hour

Operation and maintenance cost/ EGF

From 3rd Quarter of 2023

Page 178: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-42

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

Upgrades or install new technological advances when available are also encouraged for the continued operation of Project.

Operation of the proposed project and passenger facility, depot, service vehicle

Passenger movement

Terrestrial Ecology

Threat to Existence and/or Loss of Important Local Species

Hindrance to Wildlife Access

C- Minimise noise, vibration, illumination, and vehicular movement in significant fauna area.

Continuous planting of replacement trees, if needed.

Conduct monitoring on survival of replanted trees and replant, if necessary.

Implement vegetation management plan considering significant fauna (local bird species) to minimise the use of herbicide and machinery as much as possible.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost: PhP 1,500

per man-hour

PhP 100 per sapling

Operation and maintenance cost/ EGF

From 3rd Quarter of 2023

WATER

Operation of passenger trains/facilities, depot:

Discharge of waste water from passenger facilities, depot.

Accidental spills of fuels and lubricants from service vehicles and machineries at depot

Generation and improper handling and disposal of domestic and hazardous wastes.

Hydrology Increase of flood intensity/occurrence

C- Conduct proper inspection and prompt maintenance of the installed drainage system, and improve/ enhance capacity when possible.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost: PhP 1,500

per man-hour

RA 6969: PhP 100,000 per year

RA 9275: PhP 400,000 per year

PhP 25,000 per effluent sample

EGF/ Contract agreement

From 3rd Quarter of 2023

Water Quality

Degradation of ground water quality

C- Comply with environmental permitting requirements for the storage, transport, handling, and treatment and disposal of hazardous material/ wastes and contaminated soil in accordance with RA 6969.

Compliance to RA 9275 including but not limited to securing of discharge permit.

Hygienic toilets will be provided at all stations and facilities.

Wastewater will be treated by a wastewater treatment system at each station before release of effluent into public waterways.

Recycle train washing to reduce volume of wastewater to be discharged daily.

Conduct proper inspection and prompt maintenance of the installed wastewater treatment facilities & drainage system and treatment facility.

Monitor effluent of the wastewater treatment system to ensure compliance with the effluent standards.

Freshwater Ecology

Degradation of surface water quality

B-

Threat to abundance, frequency and distribution of species

C-

Page 179: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-43

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

AIR

Climate Change Meteorology/ Climatology

Restrictions/ disruption of railway operation due to soil erosion/ landslides/ flooding.

A- Regular inspection and preventive maintenance of railway structures and facilities to ensure optimum working condition;

When necessary, install improvement of railway system to make it more resilient to temperature and rainfall increase;

Planting of vegetation as much as possible in open areas at the depot, around the stations and along the railway track;

Implementation of an Emergency Response Plan.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost: PhP 1,500

per man-hour

EGF/ Contract Agreement

From 3rd Quarter of 2023

Slower drainage, soil erosion, disruption in construction by increased rainfall

B-

Overheating of construction equipment and vehicles and track buckling and signalling problems

C-

Operation of trains, depot, passenger facilities (stations), service vehicles, etc.

Meteorology/ Climatology

Reduction of Greenhouse Gases

B+ Provide incentives and information dissemination activities to encourage commuters to use rail transit and its benefits over other modes of transport (Modal Shift).

Plant and manage vegetation as much as possible to open areas at the depot, around the stations and along the railway track.

Conduct energy/water conservation program such as use energy efficient products (i.e. LED lights) and monitor carbon footprint monitoring.

Conduct regular inspection and proper maintenance of railway systems and facilities, and equipment and machinery.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost: IEC: PhP

50,000 per activity per LGU

PhP 1,500 per man-hour

Contract Agreement

From 3rd Quarter of 2023

Page 180: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-44

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

Air Quality Degradation of air quality in the vicinity of the station and in the depot area

Increase in vehicle exhaust emission and entrained dust due of increased movement of people

C- Select appropriate operation and maintenance equipment that are fuel efficient to reduce emission.

Conduct regular inspection and maintenance of heavy equipment, machineries, service vehicles and facilities such as generator etc. to meet the DENR Emission Standards.

Regular cleaning and clearing of road from spoils and debris and wetting of ground in the periphery of the depot when necessary.

Comply with environmental permitting requirements for the storage, transport, handling, and treatment of hazardous material/ wastes and contaminated soil in accordance with RA 6969 at depot area, and provide appropriate PPE for the concerned personnel.

Control service vehicle movement by maintaining the speed limit to <10kph within the construction site. Minimise vehicle transport by maximising the use of site generated materials.

Monitor air quality at the identified sampling stations

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost: PhP 1,500

per man-hour

RA 6969: PhP 100,000 per year

PhP 8,000 per personnel for PPE

PhP 25,000 per ambient air station

EGF/ Contract Agreement

From 3rd Quarter of 2023

NOISE

Operation of trains, depot, passenger facilities (stations), service vehicles, etc.

Acoustic Noise

Reduction of noise due to decrease in traffic volumes

B+ Provide incentives and conduct information dissemination activities to encourage commuters to use rail transit over other modes of transport.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost: PhP 1,500

per man-hour

PhP 30,000 per m² noise barrier

PhP 25,000 per noise monitoring station

Contract Agreement

Increase in ambient noise level

C- Optimize the number of train operation at night time to reduce generated noise.

Install effective noise barriers on each side of the track (continuous 1 m high concrete wall throughout alignment except 500m length in Buendia Section (from chainage 10+300 to 10+800) where a 2.5-m curved wall will be installed.

Provision of noise control device such as muffler to all stationary sources (i.e. generator set).

Install traffic signs in the areas before and after passing all stations, e.g. directional signs, speed

EGF/ Contract Agreement

From 3rd Quarter of 2023

Page 181: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-45

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

limit signs, no blowing of horn signs, etc. Inspect the strength and efficiency of sound

absorbing materials installed at the routes or areas under the stations at least once a month. Change the material in case these are damaged or their efficiency has decreased by more than 40%.

Regular inspection and proper maintenance of trains and tracks to ensure its optimal operation and functionality.

Monitor noise levels including identified nearby sensitive receptors such as ecologically significant area/s (if any) likely to be affected by the operation and evaluate effectiveness of the noise reduction measures provided.

VIBRATION

Operation of trains, depot, passenger facilities (stations), service vehicles, etc.

Ground Vibration

Increase in ground vibration level

C- Monitor vibration levels including identified nearby sensitive receptors, old PNR structures, historical heritages such as ecologically significant area/s (if any) likely to be affected by the operation and evaluate effectiveness of the vibration reduction measures provided. Monitor actions on complaints, if any, and attend to unresolved cases based on Grievance Redress Mechanism.

The strength and efficiency of rail pads at the train stations or hubs must be inspected at least once or twice a month. In case of damage or decrease in efficiency of the pads by more than 40%, these should be replaced.

Regular inspection, proper maintenance and reconditioning of trains and tracks such as rail grinding, slip-slide detectors and maintenance or replacement of suspension system, brakes and wheels.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost: PhP 1,500

per man-hour

PhP 80,000 per vibration monitoring station

EGF/ Contract Agreement

From 3rd Quarter of 2023

PEOPLE

Hiring of workers

Local Economy

Generation of Local Benefits

Business opportuniti

C+ Coordinate closely with the host LGUs, specifically at the barangay level regarding the hiring of regular workers to ensure that the workers being considered are legitimate residents in the area in consideration to gender equality.

Implement: Operator

Monitor DOTr PMO

Included in the maintenance cost

Contract Agreement

From 3rd Quarter of 2023

Page 182: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-46

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

es LGUs PhP 1,500 per man-hour

Operation of train

In Migration Influx of ISFs C- Install fencing and provide guards to prevent the settlement of ISFs along the ROW

Implement: Operator

Monitor: DOTr PMO LGUs

Included in the maintenance cost

Contract agreement

From 3rd Quarter of 2023

Physical/ Cultural resource

Conservation of old PNR structure and parks

C+ Continuous conservation activities of old PNR structures in coordination with PNR and LGUs.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the budget of proponent

DOTr Budget From 3rd Quarter of 2023

Operation of train and station Maintenance work at Depot

Public Health and Safety

Increase risk of accidents

B- Provide security guards in all stations to direct passengers on the safe zone.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the health and safety and environmental management plan of proponent budget: PhP 1,500

per man-hour

Occupational Health and Safety Management Plan: PhP 300,000

Contract Agreement/ Operation Cost

From 3rd Quarter of 2023

Occupational Health and Safety

Increase risk of accidents and infectious disease of employee

B- Implement the Occupational Health and Safety Management Plan.

Provide appropriate PPE to all personnel undertaking maintenance work.

Implement the Emergency Response Plan Provide sanitary facilities or utilities in all stations

and depot.

From 3rd Quarter of 2023

Public Involvement

Public Consultation

Immediate response to address adverse impacts

B+ Regular consultations with affected people and relevant offices/agencies will be conducted by the DOTr during operation phase to ensure adequate and timely mitigation of project adverse environmental impacts.

Implement: Operator DOTr PMO

Monitor:

Included in the operation and maintenance cost

EGF/ Contract Agreement

From 3rd Quarter of 2023

Page 183: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-47

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

during train operation

MMT LGUs

Train Operation Traffic Conditions

Traffic congestion may occur in the areas adjacent to the proposed stations due to pick-up and drop off of passengers by transport vehicles

B- Establish a TOD Committee, which compose of the Traffic Management of LGUs, Planning Office, PNR, DPWH, and DOTr to plan and implement TOD in consideration to the loading and unloading area and the circulation of the traffic as well as the integration of transport facility within the station.

Implement: Operator

Monitor: DOTr PMO LGUs

Included in the operation and maintenance cost PhP 1,500

per man-hour

EGF/ Contract agreement

From 3rd Quarter of 2023

Generation of solid waste from office and service areas

Community and workers’ health and safety

Indiscriminate waste disposal may pose risks to the health and safety of the surrounding communities

B- Provide solid waste segregation bins at each office area and at train stations.

Coordinate with the concerned LGUs in the collection and disposal of segregated solid wastes.

Maintain daily record of solid wastes generated and collected.

Implement: Operator

Monitor: DOTr PMO LGUs

Included in the operation and maintenance cost PhP 1,500

per man-hour

EGF/ Contract agreement

From 3rd Quarter of 2023

Generation of hazardous waste from maintenance area at Depot and related facilities

Community and workers’ health and safety

Indiscriminate disposal of toxic and hazardous wastes may pose risks on the health and safety of surrounding communities

B- Provide hazardous waste bins at the stabling yard.

Record quantities of hazardous wastes generated.

Commission the services of a Government-recognized hazardous waste transporter and treater.

Implement: Operator

Monitor DOTr PMO LGUs

Included in the operation and maintenance cost • PhP 1,500

per man-hour

EGF/ Contract agreement

From 3rd Quarter of 2023

Railway operation Community/ public and workers’

Risk of accidents from railway

B- Prepare the train safety operations plan before operation of the project

Train workers and staff on implementation of the

Implement: Operator

Monitor

Included in the operation and

EGF/ Contract agreement

From 3rd Quarter of 2023

Page 184: Environmental Monitoring Report...Clark International Airport (CIA) with Manila and Calamba by 2025. The network comprises the (i) 37-km The network comprises the (i) 37-km section

Environmental Impact Statement Report (EISR) North - South Commuter Railway Calamba Extension Project

4-48

Environmental Aspect

Environmental

Component

Potential Impact

Level of Signifi-cance

Prevention/Mitigation/ Enhancement Measures

Responsible Institution

Estimated Cost (PhP)

Guarantee/ Financial

Arrangement

Implementation

Schedule

health and safety

operation and maintenance

operations plan and the emergency response plan

Conduct drills on emergency situations at least once a year through professional experts

Conduct internal safety audits at least every six months.

Conduct full audit of the fire protection system every month and conduct daily random checks

Implement the grievance redress mechanism (complaints management system) with complaint desks at all stations

DOTr PMO LGUs

maintenance cost PhP 1,500

per man-hour

Note: A+/-: Significant positive/negative impact is expected B+/-: Moderate positive/negative impact is expected to some extent C+/-: Minor/Negligible positive/negative impact is expected to some extent D+/-: Extent of impact is unknown