environmental monitoring report - adb.org · 1.1.2. construction works 11 1.2. changes in project...
TRANSCRIPT
Environmental Monitoring Report Bi-annual Report July 2014
TAJ: CAREC Corridor 3 (Dushanbe-Uzbekistan Border) Improvement Project Prepared by SMEC Company for the Ministry of Transport of the Republic of Tajikistan and the Asian Development Bank.
Bi-annual Environmental Monitoring Report____
Project Number: G0245-TAJDate: July 2014
Republic of Tajikistan: CAREC Corridor 3(Dushanbe-Uzbekistan Border) ImprovementProject(Financed by the Asian Development Bank)
Prepared by Dr. Malika Babadzhanova, the National Environmentalspecialist, of SMEC Company, for the Ministry of Transport of theRepublic of Tajikistan
TABLE OF CONTENTS
INTRODUCTION 1Part I. Construction aspects 11.1. Construction activities and Project Progress during previous 6 months11.1.1. Construction facilities 31.1.2. Construction works 111.2. Changes in project organization and Environmental management team 171.3. Relationships with Contractors, owners, landers 17
PART II. ENVIRONMENTAL MONITORING 172.1. Noise and Vibration 172.2. Water Quality 182.3. Air Quality 192.4. Flora and fauna monitoring 222.5. Other aspects of monitoring and observations 22
PART III. ENVIRONMENTAL MANAGEMENT 233.1. EMP, SSEMP (CEMP) and work plans 233.2. Site Inspections and audits 233.3. Non-compliance notices 233.4. Corrective action plans 253.5. Consultation and complaints 27
ANNEXES 28Annex 1. Monitoring data for 6 months 29Annex 2. EMP Monitoring Report (provided by Contractor) 63
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
1
INTRODUCTION1. This fifth biannual environmental monitoring encompasses the road sections from West Gate of
Dushanbe to the Uzbekistan border of the ADB Grant 0245-TAJ (SF) CAREC Corridor 3Improvement Project (Dushanbe-Uzbekistan Border)1. The Project was determined to be aCategory A environmental project for which an EIA was processed. Within the framework of theproject’s environmental management, the supervision tasks consist of continuous monitoringby the SMEC (the Environmental specialist), environmental monitoring and management ofproject implementation and assistance in ensuring the implementation of environmentalmanagement practices at each stage of the construction. The monitoring is done to complywith the environmental management plan (EMP) in line with ADB’s environmental safeguardspolicies and the environmental regulations of Republic of Tajikistan. The monitoring reportcovers the construction activities during the 6 months of the year – January-June 2014.
2. The environmental monitoring consists of two parts, and these are: (1) monitoring of thecompliance with the environmental management plan (EMP); and (2) monitoring of the ambientenvironmental conditions. The assessment of compliance with the EMP commenced with thereview of the environmental management conditions required for compliance during theconstruction stage of the project.
3. The other part of the biannual environmental monitoring is the monitoring of ambientenvironmental condition.
4. The construction activities were observed during site visits taking note of the obviousenvironmental impacts of the construction activities
5. This report was prepared on the basis of; (1) the daily checklists on selected parameters, filledby SMEC engineers; (2) monthly reports of Contractor (including environmental monitoringinformation), (3) assessment made during the site visits; and (3) and other information neededfrom the Contractor.
6. At this stage of the project, the Contractor has improved in operating an environmental system.
PART I. CONSTRUCTION ASPECTS
1.1. Construction activities and Project Progress during previous 6months
7. The Contractor has extensively worked and the construction activities in the previous six-monthare as follows:
Table 1: Previous Six Month Construction ProgressNo. Month Construction Activities1 January
2014o Bridge construction (Km6, km42)o Side ditch construction (Km35-KM36)o Relocation of channel (Km35-km36)o Roadbed excavation (Km35 to km36)o Traffic management during construction
2 February2014
o Bridge construction (Km6, km42)o Ditch construction (Km23-Km24)o Relocation of channel (Km35-km36)
1 The project entails the improvement of the road section from West Gate of Dushanbe to the Tajikistan-Uzbekistanborder crossing, a total length of 56,9 km. The road is divided into four sections. The three sections will be widenedto four lanes, and some minor realignment will also take place as well as improvement of drainage structures.These sections are West Gate to Gissar Junction, Gissar Junction to Shakhrinav, and Shakhrinav to Tursunzadejunction. On the final section, from Tursunzade junction to the Uzbekistan border, the road will initially berehabilitated within the existing two-lane road, but will eventually be widened to a four lane highway.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
2
o Roadbed excavation (Km35 to km36)o Traffic management during construction
3 March2014
o Bridge construction (Km40,km55)o Retaining wall construction (Km5 to km6)o Roadbed excavation (Km6 to km8, Km40 to km41)o Traffic management during constructiono Stripping topsoil (Km6 to km8, Km20 to km22, Km40 to km41)o Removal of trees (Km40 to km41)o Removal of existing asphalt (Km40 to km41)o Dismantle of the concrete structure (Km38 to km41)
4 April 2014 o Stripping topsoil (Km19 to km20)o Removal of existing asphalt (Km5 to km6, Km17 to km20, Km39 to km40,
Km60 to km62)o Removal of trees (Km39 to km40)o Dismantle of the concrete structure (Km18 to km19, Km39 to km40,
Km60 to km61)o Retaining wall construction (Km4 to km6, Km21 to km22, Km37 to km38)o Bridge construction (Km6, km19, km24, km40+100, km40+601, km51,
km55, km61)o Relocation of channel (Km43 to km44)o Culvert construction (Km19-km20, Km23-km25, Km38-km39)o Sub-grade construction (Km5-km6)o Ditch construction (Km42-km43, Km60-km61)o Roadbed excavation (Km18 to km20, Km37 to km39, Km60 to km62)o Traffic management during construction
5 May 2014 o Sub-grade construction (km60 to km 62)o Sub-base construction (km4 to km7, Km22 to km27, km50 to km52)o Base course construction (km22 to km26, km55 to km57, km60 to km62)o Bituminous base coarse construction (km55 to km57, km60 to km62)o Prime coat (km55 to km57, km60 to km62)o Tack coat (km55 to km57)o Removal of trees (km18 to km19, km38 to km39, km61 to km62)o Dismantling of the concrete structures (km17 to km18, km19 to km20,
km61 to km62)o Retaining wall construction (Km4 to km6, km20 to km22, km38 to km39)o Bridge construction (Km6, km19,km24, km40+100, km40+601, km42,
km51)o Culvert construction (Km4-km7, km24-km25, km37-km38, km41-km42)o Ditch construction (km4 to km6, km41 to km44, km55 to km56, km60 to
km61)o Roadbed excavation (Km5 to km6, km18 to km20, km26 to km27, km39
to km41, km50 to km51, km61 to km61)o Traffic management during construction
6 June 2014 o Removal of existing asphalt (Km16 to km17, km35 to km38)o Sub-base construction (km4 to km8, Km18 to km22, km25 to km27,
km37 to km39, km43 to km 44)o Base course construction (km4 to km 8, km22 to km27)o Bituminous base coarse construction (km22 to km26)o Prime coat (Km22 to km26)o Relocation of channel (Km16 to km17, Km34 to km35)o Street lighting construction (Km28 to km30, km32 to km33)o Retaining wall construction (Km17 to km18, Km20 to km22)o Bridge construction (Km24, km40+100,km40+601, km46, km51, km55,
km61)o Culvert construction (Km4-km7, km24-km25, km35-km38, km41-km42)o Ditch construction (km4 to km8, km20 to km21, km23 to km25, km26 to
km27, km37 to km38, km41 to km44)
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
3
o Footpath construction (km5 to km7)o Roadbed excavation (Km16 to km17, Km19 to km20, km35 to km36)o Traffic management during construction
8. As stated in the Environmental Monitoring Plan of the EIA Report and CEMP, theContractor should undertake regular parametric monitoring of (i) noise and vibration; (ii)surface water quality; (iii) drinking water quality; and (iv) air quality. All this issues areconsidered and described further in the text of this report - in Part II. Environmentalmonitoring.
1.1.1. Construction Facilitiesa. KM 13, KM 29, KM 40, KM 40+100, KM40+160, KM51, KM56 Quarries and
crushing plants
9. These facilities were operating during the period of January-June 2014 and activitiesincluded quarrying and production of sub-grade (KM13, KM29, KM51), sub base (KM13,KM56) and base (KM13, KM40, KM40+100, KM40+160) materials.
Figure 1. Crashing facility at KM 29, materials transported from km13 quarry
Figure 2. Crashing plants and its arrangements at KM40, KM40+100
10. All approvals from the State environmental expertise were received and submitted toSMEC.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
4
11. Quarry and crusher at KM56 are working according to project plan. The permission fromlocal authorities for such arrangement of equipment and plant were received.
12. Following volume of inert materials were extracted in reporting period:
In January 2014 – 68000 m3
In March 2014 – 121261 m3
In April 2014 – 74881 m3
In June 2014 - 57023 m3.
13. As there was good precipitation in reporting period no any problems with dust wereobserved.
b. Borrow pit at KM13
14. Borrow pit at KM13 is located about 1 km from the main road. Permission from localauthorities was issued. The conditions of its using comply with requirements of EMP andCEMP.
Figure 3. Using of borrow pit at km13
c. Asphalt plants and Concrete Batching plants at KM 29, KM5115. The asphalt plants at km 29 is located at the territory of jamoat Chust (Shahrinav district).
All permissions from SEE were received: positive conclusion from SEE - from 20.06.2013No.479-15 and Permission for discharges of pollution into the atmosphere (or projectEmission Limit (PEL) – from 03.01.14, No915/13-13.
16. Anti-fire and protection means are in use in this place and comply with requirements ofEMP and CEMP.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
5
Figure 4. Asphalt plant at KM29
17. There are a lot of used drums (barrels) from black oil used on the territory of asphalt plant.They placed on specially prepared site. After use they go for further treatment: recycling,and part of them passed to local people for applying as embankment strengtheningmeans.
Figure 5. Used drums (barrels)
18. However in one place the oil leakages from used drums to ground were observed.Contractor was advised to take out the spoilt soil and put in relevant place in accordancewith requirements of EMP and CEMP.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
6
Figure 7. Operating asphalt plant at KM51 – status in June 2014
Figure 5. Oil leakage from usedbarrels.
Figure 6. Barrels after use - forfurther recycling
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
7
19. Arrangement of this facility complies currently to requirements of EMP and CEMP and
relevant permissions were issued by SEE on 3.01.2014 (No914/13-13).
d. Construction campsConstruction camp at km 19
20. Construction camp was established at km 19+600. There were following number ofworkers staying in camp in reporting period: January – 37, February – 37, March – 86,April – 150, May – 150, June - 165 workers.
Figure 8. Residential premises for workers
21. The other facilities of the camp as dining room, kitchen, and stores comply withrequirements of EMP and EMP.
Figure 9. Dining room and other washing facilities for workers
22. The store of the fuel done in proper way, however fire extinguishers had no labeledinstructions and it was unclear are they outdated or no – see photos below. Contractorwas advised to change these ant-fire means.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
8
Figure 10. Improved store of fuel and fire extinguishers without any labels
23. The area of campsites includes maintenance sites for vehicles. Some small oil spills spotswere found here.
Figure 11. Vehicles area in the camp and some spills of oil on the ground
24. There are storehouses for different spare parts. The barrels from lubricants are placed infenced area but they are not on concreted area.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
9
Figure 12. Improved status of storehouses at the area of camp
Construction camp at km 38
25. The following number of workers were in camp at km38 in reporting period: January – 14,February – 14, March - 31 workers. Since April 2014 it closed and no any workers there.
Figure 13. View of camp area in March 2014
Construction camp at KM40
26. There were following number of workers staying in this camp in reporting period: January –30, February – 30, March – 115, April – 148, May – 160, June – 160 workers.
27. The used tires from the tracks wheels were stored near the residential buildings of theconstruction camp. Contractor was advised to store them in appropriate place and coverfrom the direct sun rays. Pictures below shows the status of camp during the inspection inJuly 2014.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
10
Figure 14. Residential part of the camp
28. There is area for concrete-batching activities and produced concrete parts for culvertsplacing on asphalted area – complied with requirements.
Figure 15. Concrete parts of culverts
29. The toilet facilities of the construction camp at KM40 are in compliance currently withrequirements of EMP and CEMP.
30. The anti-fire arrangements are currently comply with requirements of EMP and CEMP –see below.
Figure 16. Anti-fire arrangements
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
11
31. The garbage is regularly taken off the area of construction camp – confirmed by inspectiontrip in July 2014 and by Environmental departments of Shahrinav district.
Figure 17. Status of garbage place at the area of construction camp.
1.1.2. Construction Worksa. Earthworks at Km 4-Km40
Earthworks from KM4-KM40 (status in January-June 2014)32. Earth works at main road, excavation of soil and its transportation is being carried out in
accordance with plan of road construction. At km4-40 currently embankment of subbaseand passageway of road is going on. Partially excavated soil is being used for leveling ofroad at Shaambari area. 7 dumping sites for dumping of wastes were agreed with localauthorities of the regions. Warning measures being taken. At 200m towards theconstruction site, there have been installed warning signs, speed limit signs and signalman assigned.Dumping site 1. Dumping site is located at erosional territory of Urugsoy jamoat Seshanbeof Tursunzade region. Dumping is done on layer bases;Dumping site 2. Khuji Poyon. The old asphalt is being dumped here. Here, 1.5 hectares ofland was given for dumping of wastes. No issues with local residents and authorities.Dumping site 3. Jamoat Chuzi km31. This section is located at torrential area.Dumping site 4. Km21 road-turn to Gissar. Old asphalt is being dumped here. And relateddocumentation is done.Dumping site .5 Shaambari. At this section, soil wastes and old asphalt is being dumped.The land is given for temporary usage.Dumping site 6. Section is used for dumping construction wastes which are produced atkm07-15 and located at Morteppa.
Another dumping section 7 is located at half a kilometer towards north from the main road,which is hilly area with slopes and gully, and used for pasturing of small sized animals andbig sized animals of local residents.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
12
Figure 18. Earth works – status in March, June 2014
33. Fixed speed limits for trucks and they are provided with drop sides. The notations havebeen partially improved; including 3 signal men was assigned, warning signs and barriers wereplaced before closed road lanes on both approaches. Near the highway, where the residencesof the local people are located, construction of curbs and culvers for irrigational waters and rainwaters partially is being carried out on both sides. Fixed speed limits for trucks and they areprovided with drop sides, but their sides are not covered with tarpaulin.
Figure 19. Status of speed limitation and traffic management during the earth works
34. Construction works for culverts are in process which goes through the main road, totallythere being constructed more than 218 culverts – at Km4-km7, km24-km25, km35-km38,km41-km42, km19-km20, km23-km25, km38-km39. Blockage of irrigational canals, waterstreams and irrigational flow channels by sand or other materials (sand, stones, aggregateor soil) used in construction works of culverts through the main road is avoided and fullcleaning on the site after constructions works is carried out daily to avoid water erosions ofthe irrigation canals and the earth.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
13
Figure 20. Status of culverts construction at different road sections
35. Retaining walls were in process of construction – at km4-km6, km17-km18, km20-km22,km38-km39. The process of construction complies with requirements of EMP and CEMP.
Figure 21. Construction of retaining wall – in different sections of the road
b. Installation of flumes
36. Works were in progress at the time of the site visit in March-June 2014.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
14
Figure 22. On-going activities – installation of flumes
37. At the working section signal men are working, warning signs are placed on bothapproaches and barriers are placed before closed road lanes where the construction ofcanal bridges and culverts are being carried out.
38. There were no major problems with environment, except one place where asphalt spoilswere stored near the flume ditch.
Figure 23. Illegal asphalts wastes at km 13+500
39. Suppression of dust and scattered soil has been done from contractor’s side - confirmedby field trip in October 2013.
c. Bridge construction40. Works on bridge construction were continued in period of January-June 2014 – at KM6,
KM19, KM24, KM40, KM40+100, KM40+601, KM42, KM51, KM55, KM61. At the workingsection signal men are working, warning signs are placed on both approaches and barriersare placed before closed road lanes where the construction of bridges are being carriedout.
Figure 24. Bridge construction at km19, km24
d. Widening works at km15 - km3541. In this section there are no major problems with environment, although the shifting of
irrigation canal can have negative effects on farming. Reclamation and construction worksof the culverts that are laid through the road are in process. Therefore, these works andthe widening of road are done with agreement of local people and group of farmers.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
15
Figure 25. Status of road widening in different sections of the road
42. The warning signs are installed and signal men are working where the works are going on.
Figure 26. Warning signs installed
e. Clearing works, Pavement Rehabilitation, Removal of Existing Asphalt Layer,Street lighting construction
43. Removal of existing asphalt pavement were carried out from Km5 to km6, Km16 to km17,Km17 to km20, km35 to km38, Km39 to km40, km40 to km41, Km60 to km62.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
16
Figure 27. Status of removal of asphalt layer at different road sections
44. .Reprocessing of removed asphalt from site and the production of necessary materials(sand and aggregate) was continued.
45. The disposal of asphalt stockpiles was continued on permitted site of Ugrisoy of jamoatSeshanbe.
46. The works on pavement were continued in reporting period in accordance with the projectplan and some road section were asphalted – see pictures below.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
17
Figure 28. Pavement works and completed asphalted sections of the road with bus stations andstreet lightening structures
47. Other notes for works described above:
• Warning signs placed at the working sectors, 3 signal men assigned, traffic safety is incompliance with requirements;
• Electric poles, communication lines, and irrigation canals are being relocated andconstructed in accordance with local residents;
1.2. Changes in project organization and Environmental management team48. No changes in project organization were happened in period of January-June 2014.
Two environmental engineers, appointed by Contractors to supervise that project activities arein compliance with EMP – Mr.Lyang and Mr.Rahimov currently are the responsible personsfor implementation of EMP and SEMP.
1.3. Relationships with Contractor and PIU49. According to agreement Contractor provided six reports for period January-June 2014 and
set of meetings were conducted with responsible environmental engineers.50. The communication with PIU was going directly and also through Team Leader of SMEC
Mr. Davies Doug and by e-mail exchange, face to face meetings.
Part II. ENVIRONMENTAL MONITORING2.1. Noise and Vibration
51. Monitoring of noise showed that rehabilitation work conducted in residential parts werelimited by time – till 20 p.m. and no complaints were received on this item.
52. According to provided monitoring data (Annex 1) no exceed in noise level on dBA wasobserved. Sampling points included km4+800, km40+150, km51+070, km61+400 – seemap below.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
18
Figure 29. Location of points for monitoring of noise in period of January-June 2014
53. The maximum value of measured dBA was 75 near the km4+800.54. As for vibration –pictures of all houses were taken before contraction works have started. It
was recommended to use more weak devices to avoid the cracking of houses. No cracksor other damages were observed during the site visits in period of January-June 2014.
2.2. Water Quality55. Sampling points for measuring water quality of the major rivers traversed by the road
project, Karatag river, Khanaka river and Sherkent river included km 6+434 (50 m from thebridge, upstream); km19+370 (under the bridge), km40+106 (200 m from the bridge,upstream), km40+150 (100 m distance from the asphalt plant), km46+918 (50 m from thebridge, downstream), km51+070 (100 m from the bridge, upstream) – see following mapbelow.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
19
Figure 30. Location of sampling points for monitoring of water quality
56.According to provided monitoring data no exceeding of MAC (maximum allowableconcentration) in period from January-June 2014 were observed.
57. The analytical data for selected parameters of water quality on samplings taken during thisreporting period are shown in attached Protocols (see Annex 1).
2.3. Air Quality58. In accordance with air quality monitoring data measured during reporting period the
sampling points included km4+800 (construction site), km19+370 (crasher site),km40+150 (crasher and asphalt plant area), km51+070 (crasher and asphalt plants),km61+400 (construction site) – see map below.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
20
Figure 31. Location of sampling points for monitoring of air quality
59. No exceeding on recommended parameters (CO, NO, NO2, TSP (total suspendedparticles) were observed in period of January-June 2014 – see Annex 1.
60. Visual observations of the ambient environmental condition of the project corridor weredone during the site visits in reporting period.
Dust Suppression
61. Observation shows that conduction of dust suppressions by watering near the settlementswere much improved in comparison with 2012 – confirmed by field visits in March-July2014. It was also agreed that Engineers visiting road every day will control this processand will make notes in provided diary. The pictures below shows the watering and roadstatus at the different rehabilitating sites of the road.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
21
Figure 32. Status of different road sections watering at the different road sections
62. The special attention on watering issues was paid to more populated areas – see below.
Figure 33. Watering near the markets and populated areas – November 2013
63. Trucks are mostly supplied by tailboards to prevent dropping of transported materials.Trucks hauling materials are only partially (in very few cases) were covered by wateredtarpaulin cover.
Figure 34. Working trucks equipped by tailboards and tarpaulin cover
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
22
2.4. Flora and fauna monitoring64. Due to commencement of road widening works and excavation works part of trees (fruit
trees, mulberries, plane trees) on road sections were removed in reporting period – inMarch from km40 to km41, in April – from km39 to km40, in May – km18 to km19, km38 tokm39, km61 to km62.
65. In total about 28 trees were removed in reporting period. Cutting and relocation of the partof trees trees are done according to the decision of local authorities and agreed withenvironmental protection departments of Gissar, Shahrinav abd Tursunzade districts. Allthese trees were distributed to farmers, jamoats, local people, hospitals, schools andboarding schools.
66. The plan on re-vegetation which was developed and revised in February 2014, were notimplemented now. It was decided jointly with PIU, Contractor and SMEC that this programwill be implemented starting from October-November 2014 and Contractor will have timeto take relevant care for planted trees in defect notification period (expected from 2014-2016).
67. No fauna disturbance was observed during reporting period. There were cases when thelocal population several times brought the tortoises (turtles) to workers in constructioncamp. The workers were strongly instructed not to accept or buy any type of animals. Theenvironmental departments of project districts were also asked to conduct moreawareness works on these issues.
2.5. Other aspect of monitoring and observations68. Big erosion site along the highway near the aluminum plant in Tursunzade were observed
in June 2013. In previous corrective action plan it was proposed to take urgent measuresfor rehabilitation of this site to avoid the road damages in autumn 2013 and spring 2014during the rain. This has been implemented.
69. Contractor filled currently this gully by soil and the water is going to existing rehabilitatedculvert. It is planned in 2014 to complete rehabilitation of this site – install flumes orculvert, and make final soil compaction. The work is in process.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
23
Figure 35. Rehabilitation of erosion site near Tursunzade - water stream does not erode the fieldsand road and goes to the culvert now
PART III. ENVIRONMENTAL MANAGEMENT70. The site inspections were conducted on various environmental aspects of the project and
form part of the Monthly Progress Report. During the inspections, a number ofenvironmental and safety issues were observed and noted. These issues weresubsequently brought to the attention of the personnel concerned on the Engineer’s sideas well as discussed with the Contractor’s side. The issues observed were generallyconcerning with the potential contamination in construction camps, and sanitation atContractor’s camps and some other minor problems.
3.1. EMP, SSEMP (CEMP) and work plans71. Reporting activities of Contractor are on relevant level currently - there were submitted 6
reports for January, February, March, April, May, June 2014.
72. The monitoring data report on EMP, CEMP (SSEMP) implementation and analyticalmeasurements of water, air quality and noise level are attached to this report – for periodof January-June 2014 (see Annexes 1,2).
3.2. Site Inspections and audits73. 6 site inspections and audits (3/03/2014, 26/03/2014, 15/04/2014, 20/05/2014,
10.06.2014, 17.07.2014) were conducted to to verify the effectiveness of environmentalprotection measures in achieving the results specified in the environmental managementplan (EMP), check the compliance with EMP and CEMP during the reporting period ofJanuary-June 2014.
74. During the inspections visual surveys on-site, meetings with workers, contractor,environmental engineers, local environmental authorities and specialists were conducted.
Figure 36. Meeting with environmental authorities of Gissar district
3.3. Non-compliance notices fulfilment75. The status of actions done to fulfill non-compliance notices indicated in previous Bi-annual
report of January-June 2013 is shown in Table 2 below.
Table 2. Status of fulfillment of non-compliance noticesN Non-compliance
noticesCorrective actions to betaken
Deadlines toresolve theissues
Status of fulfilment
1 Documents as PEL(MAE), PPW and MADshould be submitted forall crushing facilities andasphalt plants at KM40,
Submission of issueddecisions of local authorities,department of EA to SMECenvironmental specialist
by 1st March2014
All documents werereceived – copiessubmitted to SMEC
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
24
KM51, KM292 Needed restoration of
roadsides aftercompletion ofconstruction works
Implementation of the Planon re-establishment ofroadside trees of suitablespecies on available landsPlanting of seedlings
Watering of plantedseedlings
February-March2014
March-October2014
The program of treesrestoration was notimplemented in spring2014 as was proposed. Itwas decided jointly withPIU and SMEC that thisactivity will be donestarting from October2014 and during 2 yearsContractor will takerelevant care of trees
3 Asphalt plants (Km29,KM51) – empty barrelswere out in the open,not used anymore tyresfrom trucks
Contractor can give emptybarrels and rubber tyres toenvironmental authorities ofTursunzade for further re-use
By March 2014 Empty barrels partiallypassed to local people toconduct bankstrengthening works,other part goes for furtherrecycling process
4 Not full compliance tosanitary requirementsareas at constructioncamps of KM13, KM19,KM39, KM40 – roof oftoilet facility atKM40campsite was notcompletely repaired- Rubbish was found invarious areas of thecampsites- used constructionscrap materials (steel,timber, wires, etc.) wereimproperly stored at thesite or stored in adisorderly manner – riskof safety (especially incampsites at KM13 andKM38)- oil spills in some smallparts of the campsites- household rubbish isnot taken away from theterritory of all camps
Improve sanitary conditionsin construction camps- repair roof and cleanterritory – campsite at 40 KM- the Contractor shouldmaintain sanitary condition ofthe campsites – collect allrubbish and dispose themproperly, Engineer to monitor- contractor has to storematerials in orderly manneror dispose/sell off scrapmaterials to outside materialhaulers/or recyclers- The Contractor shouldeducate their staff of properwaste management andprovide adequate waste binswithin the premises andsites.- Spilled materials andcontaminated soil should beremoved by Contractor anddisposed properly. Engineerto monitor.- household rubbish shouldbe taken away more oftenand not allowed to be burned
By 15th February2014
Partially done, confirmedby site inspections.
Explanation works areregularly conducted fromenvironmental specialistsof ContractorNot all spilled materials
were removed byContractor and disposed
Household garbage isregularly taken to relevantlandfill and no cases ofburning were observed
5 Tracks hauling thespoils and otherconstruction materialsare still working withoutcover.
Tracks hauling spoils shouldbe relevantly covered
Continue improved dustsuppression process
regularly
regularly
Regularly in dryperiod
Partially done
Done
Done, dust suppressioncomplied with requirement
6 Progress reports Reports for March-June2014 should be submitted intime
by 3rd April, 3rd
May, 3rd June, 3rd
July 2014
All progress reports,including for January andFebruary were submittedin time
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
25
Erosion gully along theroad near Tursunzade
Fully Rehabilitate this gullyby arrangement of relevantmeasures (installation ofculvert, soil compaction, treeplanting)
By April 2014 Partially done. Thepreparations andarrangements for flumesinstalment at this sectionof the road is in theprocess
76. A rather good number of these issues were already solved by the Contractor. The local
environmental specialist conducts continuous monitoring of sites and reports to the
Engineer without delay any evidence of non-conformance.
3.4. Corrective action plans77. For the pending issues further recommendations for next detailed corrective actions plan
coordinated with PIU and Contractor - in Table 3 below.
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
26
Table 3. Corrective Action PlanNo Environmental issues
identifiedCorrective actions to be taken Deadlines to resolve
the issuesResponsibilities forimplementation/supervision
1 Needed restoration of roadsidesafter completion of constructionworks
Implementation of the Plan on re-establishment of roadsidetrees of suitable species on available landsPlanting of seedlings
Watering of planted seedlings
October-November2014
March-October 2015March-October 2016
Contractor (ResponsibleEngineers Mr.Lyang,Mr.Rahimov)
2 Asphalt spoils at km13+500 The asphalt spoils should be taken and disposed in relevantstockpile area
15 August 2014 Contractor (ResponsibleEngineers Mr.Lyang,Mr.Rahimov)
Not full compliance to sanitaryrequirements areas atconstruction camps of KM19, andKM40 - - used construction scrapmaterials (steel, timber, tires,wires, etc.) were improperlystored at the site or stored in adisorderly manner – risk of safety- oil spills in some small parts ofthe campsites- reported cases when wildanimals as tortillas were soldillegally by local people toworkers of construction campsand used for food
Improve sanitary conditions in construction camps- the Contractor should maintain sanitary condition of thecampsites – collect all rubbish and dispose them properly,Engineer to monitor- contractor has to store materials in orderly manner ordispose/sell off scrap materials to outside material haulers/orrecyclers- The Contractor should educate their staff of proper wastemanagement and provide adequate waste bins within thepremises and sites.- Spilled materials and contaminated soil should be removedby Contractor and disposed properly. Engineer to monitor.- continue control that household rubbish should be takenaway more often and not allowed to be burned- regularly control and instruct workers not to buy the wildanimals as tortoises (turtles) and etc.
Regularly Contractor(ResponsibleEngineers Mr.Lyang,Mr.Rahimov)
5 Tracks hauling the spoils andother construction materials arestill working without cover.
Tracks hauling spoils should be relevantly covered
Continue improved dust suppression process
regularly
Regularly in dry period
Contractor
Contractor6 Progress reports Reports for July-December 2014 should be submitted in time by 3rd August, 3rd
September, 3rd October,3rd November, 15th
December
Contractor
7 Erosion gully along the road nearTursunzade
Fully Rehabilitate this gully by arrangement of relevantmeasures (installation of culvert, soil compaction, treeplanting)
By October 2014 Contractor, SMEC engineers
Biannual Environmental Monitoring Report – July 2014ADB Grant 0245 TAJ CAREC 3 Improvement Project
27
3.5. Consultation and complaints78. Complaints from residents are usually go to PIU and to SMEC office in Shahrinav district.
During reporting period PIU and SMEC did not receive any complaints any complaintsfrom residents as they informed national environmental specialist.
ANNEXESAnnex 1. Monitoring Data for January-June 2014(attached)
Annex 2. EMP Monitoring Reports (January-June 2014) provided by
Contractor (attached)
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
30
Environmental Monitoring Report1. Reporting Period, January - June 2014.2. Construction Activities
The Contractor has already carried out the following activity at site
Activity No. Activity Remarks
1 Bridge construction
2 Ditch construction
3 Relocation of channel
4 Roadbed excavation
5 Traffic management during construction
3. Environmental Monitoring
Result of Environmental Monitoring Values
3.1. Routine Periodic Water Quality Monitoring.3.1.1 Water Quality Monitoring Conditions
ParameterWater Quality Monitoring Conditions at Bridge ( Km6+434)
National Standard Monitoring values
Temperature 1.7℃
pH Not less than 6 7.0
Iron (mg/l) 0.008 0.005
Copper (mg/l) 0.02 0.008
Zinc (mg/l) 0.02 0.006
DO Not less than 5 6.8 mg/L
SS Not more than 30 mg/L 25 mg/L
BOD Less than 2mg 1.5mg/L
Fecal coliform Not more than 20000 no./ L 17300 no./ L
Oil grease Not more than 0.5mg/L 0.36mg/L
ParameterWater Quality Monitoring Conditions at Bridge (Km19+370)
National Standard Monitoring values
Temperature 1.5℃
pH Not less than 6 7.2
Iron (mg/l) 0.008 0.006
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
31
Copper (mg/l) 0.02 0.01
Zinc (mg/l) 0.02 0.008
DO Not less than 5 6.5mg/L
BOD Less than 2mg 1.3mg/L
SS Not more than 30 mg/L 23mg/L
Fecal coliform Not more than 20000 no./ L 15700 no./ L
Oil grease Not more than 0.5mg/L 0.32 mg/L
ParameterWater Quality Monitoring Conditions at Bridge (Km 40+106)
National Standard Monitoring values
Temperature 1.3℃
pH Not less than 6 7.0
Iron (mg/l) 0.008 0.005
Copper (mg/l) 0.02 0.006
Zinc (mg/l) 0.02 0.007
DO Not less than 5 6.8mg/L
BOD Less than 2mg 1.5mg/L
SS Not more than 30 25mg/L
Fecal coliform Not more than 20000 no./ L 17300 no./ L
Oil grease Not more than 0.5mg/L 0.35mg/L
ParameterWater Quality Monitoring Conditions at Camp,Crusher and Asphalt
Plant(Km 40+150)
National Standard Monitoring values
Temperature 2.0℃
pH Not less than 6 7.3
Iron (mg/l) 0.008 0.003
Copper (mg/l) 0.02 0.01
Zinc (mg/l) 0.02 0.007
DO Not less than 5 6.7mg/L
BOD Less than 2mg 1.3mg/L
SS Not more than 30 23 mg/L
Fecal coliform Not more than 20000 no./ L 17500 no./ L
Oil grease Not more than 0.5mg/L 0.34 mg/L
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
32
ParameterWater Quality Monitoring Conditions at Bridge (Km 46+918)
National Standard Monitoring values
Temperature 1.7℃
pH Not less than 6 7.1
Iron (mg/l) 0.008 0.005
Copper (mg/l) 0.02 0.007
Zinc (mg/l) 0.02 0.007
DO Not less than 5 7.4mg/L
BOD Less than 2mg 1.0mg/L
SS Not more than 30 20 mg/L
Fecal coliform Not more than 20000 no./ L 15700no./ L
Oil grease Not more than 0.5mg/L 0.31mg/L
ParameterWater quality Monitoring Conditions at Bridge (Km 51+070)
National Standard Monitoring values
Temperature 1.8℃
pH Not less than 6 7.5
Iron (mg/l) 0.008 0.003
Copper (mg/l) 0.02 0.009
Zinc (mg/l) 0.02 0.006
DO Not less than 5 6.5mg/L
BOD Less than 2mg 0.8mg/L
SS Not more than 30 24mg/L
Fecal coliform Not more than 20000 no./ L 16600no./ L
Oil grease Not more than 0.5mg/L 0.31mg/L
3.2. Routine Periodic Air Quality Monitoring
3.2.1. Air Quality Conditions
ParameterAir Quality Monitoring Conditions at Crusher Km19+370 (mg/m3)
National Standard Monitoring values
Particulate Matter (PM) 0.15 0.13
Sulfur Dioxide (SO2) 0.05 0.02
Carbon Monoxide (CO) 3.0 2.0
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
33
Nitrogen Oxide (NO) 0.06 0.04
Nitrogen Dioxide (NO2) 0.04 0.02
TSP 0.5 0.23
ParameterAir Quality Monitoring Conditions at Crusher and Asphalt Plant
Km40+150 (mg/m3)
National Standard Monitoring values
Particulate Matter (PM) 0.15 0.11
Sulfur Dioxide (SO2) 0.05 0.032
Carbon Monoxide (CO) 3.0 2.2
Nitrogen Oxide (NO) 0.06 0.03
Nitrogen Dioxide (NO2) 0.04 0.023
TSP 0.5 0.25
ParameterAir Quality Monitoring Conditions at Camp,Crusher and
Asphalt Plant Km51+070 (mg/m3)
National Standard Monitoring values
Particulate Matter (PM) 0.15 0.13
Sulfur Dioxide (SO2) 0.05 0.03
Carbon Monoxide (CO) 3.0 1.6
Nitrogen Oxide (NO) 0.06 0.02
Nitrogen Dioxide (NO2) 0.04 0.026
TSP 0.5 0.2
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km4+800 (mg/m3)
National Standard Monitoring values
Particulate Matter (PM) 0.15 0.12
Sulfur Dioxide (SO2) 0.05 0.03
Carbon Monoxide (CO) 3.0 1.7
Nitrogen Oxide (NO) 0.06 0.04
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
34
Nitrogen Dioxide (NO2) 0.04 0.02
TSP 0.5 0.2
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km61+400 (mg/m3)
National Standard Monitoring values
Particulate Matter (PM) 0.15 0.12
Sulfur Dioxide (SO2) 0.05 0.02
Carbon Monoxide (CO) 3.0 2.3
Nitrogen Oxide (NO) 0.06 0.04
Nitrogen Dioxide (NO2) 0.04 0.015
TSP 0.5 0.3
3.3. Noise LevelLocation Chainage National
Standard(dBA)Base line (dBA) Monitoring
result (dBA)Time
RoadRehabilitation
Site
Km4+800 80 75 72
Camp, Crusherand Asphalt Plant
40+150 80 55 51
Camp, Crusherand Asphalt Plant
51+070 80 51 52
RoadRehabilitation
Site
Km61+400 80 63 62
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
35
Environmental Monitoring Report1. Reporting Period, February 2014.2. Construction Activities
The Contractor has already carried out the following activity at site
Activity No. Activity Remarks
1 Bridge construction
2 Ditch construction
3 Relocation of channel
4 Roadbed excavation
5 Traffic management during construction
3. Environmental Monitoring
Result of Environmental Monitoring Values
3.1. Routine Periodic Water Quality Monitoring.3.1.1. Water Quality Monitoring Conditions
Parameter
Water Quality Monitoring Conditions at Bridge ( Km6+434) (measuringplace:400m far from the bridge, upstream )
National Standard Monitoring values Measuring time
Temperature 0.7℃ Feb 13th
pH Not less than 6 7.0 Feb 13th
Iron (mg/l) 0.008 0.010 Feb 13th
Copper (mg/l) 0.02 0.007 Feb 13th
Zinc (mg/l) 0.02 0.006 Feb 13th
DO Not less than 5 6.8 mg/L Feb 13th
SS Not more than 30 mg/L 27 mg/L Feb 13th
BOD Less than 2mg 2.4mg/L Feb 13th
Fecal coliform Not more than 20000 no./ L 18500 no./ L Feb 13th
Oil grease Not more than 0.5mg/L 0.42mg/L Feb 13th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
36
Parameter
Water Quality Monitoring Conditions at Bridge (Km19+370)(measuring place:300m far from the bridge, downstream )
National Standard Monitoring values Measuring time
Temperature 0.5℃ Feb 13th
pH Not less than 6 7.4 Feb 13th
Iron (mg/l) 0.008 0.009 Feb 13th
Copper (mg/l) 0.02 0.04 Feb 13th
Zinc (mg/l) 0.02 0.006 Feb 13th
DO Not less than 5 6.8mg/L Feb 13th
BOD Less than 2mg 2.0mg/L Feb 13th
SS Not more than 30 mg/L 23mg/L Feb 13th
Fecal coliform Not more than 20000 no./ L 18700 no./ L Feb 17th
Oil grease Not more than 0.5mg/L 0.42 mg/L Feb 18th
Parameter
Water Quality Monitoring Conditions at Bridge (Km 40+106)
(near the bridge )
National Standard Monitoring values Measuring time
Temperature 0.3℃ Feb 21st
pH Not less than 6 7.3 Feb 21st
Iron (mg/l) 0.008 0.009 Feb 21st
Copper (mg/l) 0.02 0.005 Feb 21st
Zinc (mg/l) 0.02 0.006 Feb 21st
DO Not less than 5 7.5mg/L Feb 21st
BOD Less than 2mg 1.5mg/L Feb 21st
SS Not more than 30 25mg/L Feb 21st
Fecal coliform Not more than 20000 no./ L 17300 no./ L Feb 21st
Oil grease Not more than 0.5mg/L 0.35mg/L Feb 21st
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
37
Parameter
Water Quality Monitoring Conditions at Camp,Crusher and AsphaltPlant(Km 40+150) (measuring place:50m far from the Plant )
National Standard Monitoring values Measuring time
Temperature 0.43℃ Feb 15th
pH Not less than 6 7.3 Feb 15th
Iron (mg/l) 0.008 0.009 Feb 15th
Copper (mg/l) 0.02 0.04 Feb 15th
Zinc (mg/l) 0.02 0.007 Feb 15th
DO Not less than 5 6.7mg/L Feb 15th
BOD Less than 2mg 1.3mg/L Feb 15th
SS Not more than 30 23 mg/L Feb 15th
Fecal coliform Not more than 20000 no./ L 18500 no./ L Feb 15th
Oil grease Not more than 0.5mg/L 0.34 mg/L Feb 15th
Parameter
Water Quality Monitoring Conditions at Bridge (Km 46+918)(measuring place:600m far from the bridge, upstream )
National Standard Monitoring values Measuring time
Temperature 0.37℃ Feb 15th
pH Not less than 6 7.1 Feb 15th
Iron (mg/l) 0.008 0.009 Feb 15th
Copper (mg/l) 0.02 0.005 Feb 15th
Zinc (mg/l) 0.02 0.006 Feb 15th
DO Not less than 5 6.4mg/L Feb 15th
BOD Less than 2mg 2.7mg/L Feb 15th
SS Not more than 30 28 mg/L Feb 15th
Fecal coliform Not more than 20000 no./ L 16700no./ L Feb 15th
Oil grease Not more than 0.5mg/L 0.41mg/L Feb 15th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
38
Parameter
Water quality Monitoring Conditions at Bridge (Km 51+070) (under thebridge )
National Standard Monitoring values Measuring Time
Temperature 0.48℃ Feb 7th
pH Not less than 6 6.9 Feb 7th
Iron (mg/l) 0.008 0.010 Feb 7th
Copper (mg/l) 0.02 0.007 Feb 7th
Zinc (mg/l) 0.02 0.005 Feb 7th
DO Not less than 5 6.6mg/L Feb 7th
BOD Less than 2mg 1.8mg/L Feb 7th
SS Not more than 30 26mg/L Feb 7th
Fecal coliform Not more than 20000 no./ L 17600no./ L Feb 7th
Oil grease Not more than 0.5mg/L 0.41mg/L Feb 7th
3.2 Routine Periodic Air Quality Monitoring
3.2.1 Air Quality Conditions
ParameterAir Quality Monitoring Conditions at Crusher Km19+370 (mg/m3)
National Standard Monitoring values Measuring time
Particulate Matter (PM) 0.15 0.13 Feb 7th
Sulfur Dioxide (SO2) 0.05 0.03 Feb 7th
Carbon Monoxide (CO) 3.0 2.5 Feb 7th
Nitrogen Oxide (NO) 0.06 0.04 Feb 7th
Nitrogen Dioxide (NO2) 0.04 0.03 Feb 7th
TSP 0.5 0.35 Feb 7th
ParameterAir Quality Monitoring Conditions at Crusher and Asphalt Plant
Km40+150 (mg/m3)( (measuring place:100m far from the plant ))
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.13 Feb 7th
Sulfur Dioxide (SO2) 0.05 0.036 Feb 7th
Carbon Monoxide (CO) 3.0 2.7 Feb 7th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
39
Nitrogen Oxide (NO) 0.06 0.04 Feb 7th
Nitrogen Dioxide (NO2) 0.04 0.036 Feb 7th
TSP 0.5 0.42 Feb 7th
ParameterAir Quality Monitoring Conditions at Camp,Crusher and Asphalt
Plant Km51+070 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.13 Feb 7th
Sulfur Dioxide (SO2) 0.05 0.04 Feb 7th
Carbon Monoxide (CO) 3.0 2.6 Feb 7th
Nitrogen Oxide (NO) 0.06 0.04 Feb 7th
Nitrogen Dioxide (NO2) 0.04 0.036 Feb 7th
TSP 0.5 0.4 Feb 7th
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km4+800 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.13 Feb 7th
Sulfur Dioxide (SO2) 0.05 0.03 Feb 7th
Carbon Monoxide (CO) 3.0 2.7 Feb 7th
Nitrogen Oxide (NO) 0.06 0.04 Feb 7th
Nitrogen Dioxide (NO2) 0.04 0.03 Feb 7th
TSP 0.5 0.35 Feb 7th
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km61+400 (mg/m3)
National Standard Monitoring values Measuring time
Particulate Matter (PM) 0.15 0.13 Feb 13th
Sulfur Dioxide (SO2) 0.05 0.036 Feb 13th
Carbon Monoxide (CO) 3.0 2.6 Feb 13th
Nitrogen Oxide (NO) 0.06 0.05 Feb 13th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
40
Nitrogen Dioxide (NO2) 0.04 0.027 Feb 13th
TSP 0.5 0.34 Feb 13th
3.3. Noise Level
Location Chainage NationalStandard(dBA)
Base line(dBA)
Monitoringresult (dBA)
Time
RoadRehabilitation
Site
Km4+800 80 75 60-72Feb 13th
Camp,Crusher andAsphalt Plant
40+150 80 55 51-55Feb 13th
Camp,Crusher andAsphalt Plant
51+070 80 51 40-50Feb 13th
RoadRehabilitation
Site
Km61+400 80 63 60-70Feb 13th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
41
Environmental Monitoring Report1. Reporting Period, March 2014.2. Construction Activities
The Contractor has already carried out the following activity at site
Activity No. Activity Remarks
1 Stripping topsoil
2 Removal of existing asphalt
3 Removal of trees
4 Bridge construction
5 Dismantle of the concrete structure
6 Retaining wall construction
7 Roadbed excavation
8 Traffic management during construction
3. Environmental Monitoring
Result of Environmental Monitoring Values
3.1. Routine Periodic Water Quality Monitoring.3.1.1. Water Quality Monitoring Conditions
Parameter
Water Quality Monitoring Conditions at Bridge ( Km6+434) (measuringplace:300m far from the bridge, upstream )
National Standard Monitoringvalues Measuring time
Temperature 0.35℃ Mar. 20th
pH Not less than 6 7.1 Mar. 20th
Iron (mg/l) 0.008 0.005 Mar. 20th
Copper (mg/l) 0.02 0.008 Mar. 20th
Zinc (mg/l) 0.02 0.01 Mar. 20th
DO Not less than 5 7.5 mg/L Mar. 20th
SS Not more than 30 mg/L 24 mg/L Mar. 20th
BOD Less than 2mg 1.3mg/L Mar. 20th
Fecal coliform Not more than 20000 no./ L 17500 no./ L Mar. 20th
Oil grease Not more than 0.5mg/L 0.39mg/L Mar. 20th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
42
ParameterWater Quality Monitoring Conditions at Bridge (Km19+370) (measuring
place: under the bridge )
National Standard Monitoring values Measuring timeTemperature 0.6℃ Mar. 20th
pH Not less than 6 7.1 Mar. 20th
Iron (mg/l) 0.008 0.007 Mar. 20th
Copper (mg/l) 0.02 0.009 Mar. 20th
Zinc (mg/l) 0.02 0.005 Mar. 20thDO Not less than 5 7.0mg/L Mar. 20th
BOD Less than 2mg 1.3mg/L Mar. 20th
SS Not more than 30 mg/L 26mg/L Mar. 20th
Fecal coliform Not more than 20000 no./ L 17700 no./ L Mar. 20thOil grease Not more than 0.5mg/L 0.37 mg/L Mar. 20th
Parameter
Water Quality Monitoring Conditions at Bridge (Km 40+106)
(measuring place:50m far from the bridge, downstream )
National Standard Monitoring values Measuring time
Temperature 0.52℃ Mar. 18th
pH Not less than 6 7.2 Mar. 18th
Iron (mg/l) 0.008 0.005 Mar. 18th
Copper (mg/l) 0.02 0.007 Mar. 18th
Zinc (mg/l) 0.02 0.004 Mar. 18thDO Not less than 5 6.7mg/L Mar. 18th
BOD Less than 2mg 1.2mg/L Mar. 18thSS Not more than 30 22mg/L Mar. 18th
Fecal coliform Not more than 20000 no./ L 18100 no./ L Mar. 18th
Oil grease Not more than 0.5mg/L 0.36mg/L Mar. 18th
ParameterWater Quality Monitoring Conditions at Camp,Crusher and Asphalt
Plant(Km 40+150) (measuring place:50m far from the Plant )
National Standard Monitoring values Measuring time
Temperature 0.62℃ Mar. 18th
pH Not less than 6 7.0 Mar. 18thIron (mg/l) 0.008 0.004 Mar. 18th
Copper (mg/l) 0.02 0.006 Mar. 18th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
43
Zinc (mg/l) 0.02 0.004 Mar. 18th
DO Not less than 5 7.2mg/L Mar. 18th
BOD Less than 2mg 0.9mg/L Mar. 18th
SS Not more than 30 24 mg/L Mar. 18thFecal coliform Not more than 20000 no./ L 16800 no./ L Mar. 18th
Oil grease Not more than 0.5mg/L 0.35 mg/L Mar. 18th
ParameterWater Quality Monitoring Conditions at Bridge (Km 46+918)
(measuring place:100m far from the bridge, downstream )
National Standard Monitoring values Measuring time
Temperature 0.57℃ Mar. 21st
pH Not less than 6 7.0 Mar. 21st
Iron (mg/l) 0.008 0.006 Mar. 21st
Copper (mg/l) 0.02 0.008 Mar. 21st
Zinc (mg/l) 0.02 0.006 Mar. 21st
DO Not less than 5 7.3mg/L Mar. 21st
BOD Less than 2mg 1.2mg/L Mar. 21st
SS Not more than 30 24 mg/L Mar. 21st
Fecal coliform Not more than 20000 no./ L 17300no./ L Mar. 21st
Oil grease Not more than 0.5mg/L 0.36mg/L Mar. 21st
ParameterWater quality Monitoring Conditions at Bridge (Km 51+070) (under the
bridge )
National Standard Monitoring values Measuring Time
Temperature 0.75℃ Mar. 24th
pH Not less than 6 7.2 Mar. 24th
Iron (mg/l) 0.008 0.006 Mar. 24th
Copper (mg/l) 0.02 0.008 Mar. 24th
Zinc (mg/l) 0.02 0.008 Mar. 24th
DO Not less than 5 6.8mg/L Mar. 24thBOD Less than 2mg 1.1mg/L Mar. 24th
SS Not more than 30 22mg/L Mar. 24th
Fecal coliform Not more than 20000 no./ L 16500no./ L Mar. 24th
Oil grease Not more than 0.5mg/L 0.37mg/L Mar. 24th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
44
3.2. Routine Periodic Air Quality Monitoring
3.2.1. Air Quality Conditions
ParameterAir Quality Monitoring Conditions at Crusher Km19+370 (mg/m3)
National Standard Monitoring values Measuring time
Particulate Matter (PM) 0.15 0.11 Mar. 20th
Sulfur Dioxide (SO2) 0.05 0.04 Mar. 20th
Carbon Monoxide (CO) 3.0 1.8 Mar. 20th
Nitrogen Oxide (NO) 0.06 0.03 Mar. 20th
Nitrogen Dioxide (NO2) 0.04 0.01 Mar. 20th
TSP 0.5 0.32 Mar. 20th
ParameterAir Quality Monitoring Conditions at Crusher and Asphalt Plant
Km40+150 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.13 Mar. 18th
Sulfur Dioxide (SO2) 0.05 0.03 Mar. 18th
Carbon Monoxide (CO) 3.0 1.5 Mar. 18th
Nitrogen Oxide (NO) 0.06 0.05 Mar. 18th
Nitrogen Dioxide (NO2) 0.04 0.036 Mar. 18th
TSP 0.5 0.42 Mar. 18th
Parameter
Air Quality Monitoring Conditions at Camp,Crusher and AsphaltPlant Km51+070 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.11 Mar. 24th
Sulfur Dioxide (SO2) 0.05 0.03 Mar. 24th
Carbon Dioxide (CO2) 3.0 2.0 Mar. 24th
Nitrogen Oxide (NO) 0.06 0.02 Mar. 24th
Nitrogen Dioxide (NO2) 0.04 0.032 Mar. 24th
TSP 0.5 0.2 Mar. 24th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
45
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km4+800 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.1 Mar. 20th
Sulfur Dioxide (SO2) 0.05 0.04 Mar. 20th
Carbon Dioxide (CO2) 3.0 2.5 Mar. 20th
Nitrogen Oxide (NO) 0.06 0.02 Mar. 20th
Nitrogen Dioxide (NO2) 0.04 0.01 Mar. 20th
TSP 0.5 0.33 Mar. 20th
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km61+400 (mg/m3)
National Standard Monitoring values Measuring time
Particulate Matter (PM) 0.15 0.08 Mar. 24th
Sulfur Dioxide (SO2) 0.05 0.025 Mar. 24th
Carbon Monoxide (CO) 3.0 1.7 Mar. 24th
Nitrogen Oxide (NO) 0.06 0.04 Mar. 24th
Nitrogen Dioxide (NO2) 0.04 0.02 Mar. 24th
TSP 0.5 0.31 Mar. 24th
3.3. Noise LevelLocation Chainage National
Standard(dBA)Base line(dBA)
Monitoringresult (dBA)
Time
Road RehabilitationSite
Km4+800 80 75 67-75 Mar. 20th
Camp, Crusher andAsphalt Plant
40+150 80 55 50-60 Mar. 18th
Camp, Crusher andAsphalt Plant
51+070 80 51 43-50 Mar. 24th
Road RehabilitationSite
Km61+400 80 63 60-65 Mar. 24th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
46
Environmental Monitoring Report1. Reporting Period, April 2014.
2. Construction ActivitiesThe Contractor has already carried out the following activity at site
Activity No. Activity Remarks
1 Stripping topsoil
2 Removal of existing asphalt
3 Removal of trees
4 Bridge construction
5 Dismantle of the concrete structure
6 Retaining wall construction
7 Relocation of channel
8 Culvert construction
9 Subgrade construction
10 Ditch construction
11 Roadbed excavation
12 Traffic management during construction
3. Environmental Monitoring
Result of Environmental Monitoring Values
3.1. Routine Periodic Water Quality Monitoring.3.1.1. Water Quality Monitoring Conditions
ParameterWater Quality Monitoring Conditions at Bridge ( Km6+434) (measuring
place: 100m far from the bridge, downstream )
National Standard Monitoring values Measuring time
Temperature 1.9℃ Apr. 13th
pH Not less than 6 7.2 Apr. 13th
Iron (mg/l) 0.008 0.003 Apr. 13th
Copper (mg/l) 0.02 0.005 Apr. 13th
Zinc (mg/l) 0.02 0.007 Apr. 13thDO Not less than 5 6.7 mg/L Apr. 13th
SS Not more than 30 mg/L 22 mg/L Apr. 13th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
47
BOD Less than 2mg 1.0mg/L Apr. 13th
Fecal coliform Not more than 20000 no./ L 16300 no./ L Apr. 13th
Oil grease Not more than 0.5mg/L 0.34mg/L Apr. 13th
ParameterWater Quality Monitoring Conditions at Bridge (Km19+370) (measuring
place: 50m far from the bridge, upstream ))
National Standard Monitoring values Measuring timeTemperature 1.1℃ Apr. 13th
pH Not less than 6 7.0 Apr. 13thIron (mg/l) 0.008 0.005 Apr. 13th
Copper (mg/l) 0.02 0.007 Apr. 13th
Zinc (mg/l) 0.02 0.007 Apr. 13thDO Not less than 5 6.8mg/L Apr. 13th
BOD Less than 2mg 0.9mg/L Apr. 13th
SS Not more than 30 mg/L 25mg/L Apr. 13thFecal coliform Not more than 20000 no./ L 16700 no./ L Apr. 13th
Oil grease Not more than 0.5mg/L 0.35 mg/L Apr. 13th
Parameter
Water Quality Monitoring Conditions at Bridge (Km 40+106)(measuringplace: 50m far from the bridge, upstream )
National Standard Monitoringvalues Measuring time
Temperature 2.0℃ Apr. 10thpH Not less than 6 6.8 Apr. 10th
Iron (mg/l) 0.008 0.003 Apr. 10th
Copper (mg/l) 0.02 0.006 Apr. 10th
Zinc (mg/l) 0.02 0.008 Apr. 10thDO Not less than 5 6.5mg/L Apr. 10th
BOD Less than 2mg 1.0mg/L Apr. 10thSS Not more than 30 26mg/L Apr. 10th
Fecal coliform Not more than 20000 no./ L 17500 no./ L Apr. 10thOil grease Not more than 0.5mg/L 0.33mg/L Apr. 10th
ParameterWater Quality Monitoring Conditions at Camp,Crusher and Asphalt
Plant(Km 40+150) (measuring place:30m far from the Plant )
National Standard Monitoring values Measuring time
Temperature 1.2℃ Apr. 10th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
48
pH Not less than 6 7.2 Apr. 10thIron (mg/l) 0.008 0.005 Apr. 10th
Copper (mg/l) 0.02 0.006 Apr. 10th
Zinc (mg/l) 0.02 0.009 Apr. 10th
DO Not less than 5 7.0mg/L Apr. 10thBOD Less than 2mg 0.6mg/L Apr. 10th
SS Not more than 30 22 mg/L Apr. 10thFecal coliform Not more than 20000 no./ L 17000 no./ L Apr. 10th
Oil grease Not more than 0.5mg/L 0.32 mg/L Apr. 10th
ParameterWater Quality Monitoring Conditions at Bridge (Km 46+918)
(measuring place: under the bridge )
National Standard Monitoring values Measuring time
Temperature 2.0℃ Apr. 23rd
pH Not less than 6 7.3 Apr. 23rd
Iron (mg/l) 0.008 0.005 Apr. 23rd
Copper (mg/l) 0.02 0.01 Apr. 23rd
Zinc (mg/l) 0.02 0.007 Apr. 23rd
DO Not less than 5 6.6mg/L Apr. 23rd
BOD Less than 2mg 1.1mg/L Apr. 23rd
SS Not more than 30 23 mg/L Apr. 23rd
Fecal coliform Not more than 20000 no./ L 16700no./ L Apr. 23rd
Oil grease Not more than 0.5mg/L 0.35mg/L Apr. 23rd
Parameter
Water quality Monitoring Conditions at Bridge (Km 51+070)
(measuring place: 200m far from the bridge, downstream )
National Standard Monitoring values Measuring Time
Temperature 1.8℃ Apr. 26th
pH Not less than 6 7.0 Apr. 26th
Iron (mg/l) 0.008 0.003 Apr. 26th
Copper (mg/l) 0.02 0.008 Apr. 26th
Zinc (mg/l) 0.02 0.006 Apr. 26th
DO Not less than 5 7.1mg/L Apr. 26th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
49
BOD Less than 2mg 0.8mg/L Apr. 26th
SS Not more than 30 21mg/L Apr. 26th
Fecal coliform Not more than 20000 no./ L 17300no./ L Apr. 26th
Oil grease Not more than 0.5mg/L 0.34mg/L Apr. 26th
3.2. Routine Periodic Air Quality Monitoring
3.2.1. Air Quality Conditions
ParameterAir Quality Monitoring Conditions at Crusher Km19+370 (mg/m3)
National Standard Monitoring values Measuring time
Particulate Matter (PM) 0.15 0.11 Apr. 13th
Sulfur Dioxide (SO2) 0.05 0.02 Apr. 13th
Carbon Monoxide (CO) 3.0 1.6 Apr. 13th
Nitrogen Oxide (NO) 0.06 0.04 Apr. 13th
Nitrogen Dioxide (NO2) 0.04 0.03 Apr. 13th
TSP 0.5 0.2 Apr. 13th
Parameter
Air Quality Monitoring Conditions at Crusher and Asphalt PlantKm40+150 (mg/m3)
NationalStandard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.10 Apr. 10th
Sulfur Dioxide (SO2) 0.05 0.02 Apr. 10th
Carbon Monoxide (CO) 3.0 1.3 Apr. 10th
Nitrogen Oxide (NO) 0.06 0.03 Apr. 10th
Nitrogen Dioxide (NO2) 0.04 0.036 Apr. 10th
TSP 0.5 0.33 Apr. 10th
ParameterAir Quality Monitoring Conditions at Camp,Crusher and Asphalt
Plant Km51+070 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.12 Apr. 26th
Sulfur Dioxide (SO2) 0.05 0.04 Apr. 26th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
50
Carbon Monoxide (CO) 3.0 1.6 Apr. 26th
Nitrogen Oxide (NO) 0.06 0.03 Apr. 26th
Nitrogen Dioxide (NO2) 0.04 0.025 Apr. 26th
TSP 0.5 0.27 Apr. 26th
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km4+800 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.13 Apr. 13th
Sulfur Dioxide (SO2) 0.05 0.02 Apr. 13th
Carbon Monoxide (CO) 3.0 2.3 Apr. 13th
Nitrogen Oxide (NO) 0.06 0.04 Apr. 13th
Nitrogen Dioxide (NO2) 0.04 0.02 Apr. 13th
TSP 0.5 0.31 Apr. 13th
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km61+400 (mg/m3)
National Standard Monitoring values Measuring time
Particulate Matter (PM) 0.15 0.1 Apr. 27th
Sulfur Dioxide (SO2) 0.05 0.03 Apr. 27th
Carbon Monoxide (CO) 3.0 1.8 Apr. 27th
Nitrogen Oxide (NO) 0.06 0.04 Apr. 27th
Nitrogen Dioxide (NO2) 0.04 0.01 Apr. 27th
TSP 0.5 0.3 Apr. 27th
3.3. Noise LevelLocation Chainage National
Standard(dBA)Base line(dBA)
Monitoringresult (dBA)
Time
Road Rehabilitation Site Km4+800 80 75 65-75 Apr. 13thCamp, Crusher and
Asphalt Plant40+150 80 55 55-60 Apr. 10th
Camp, Crusher andAsphalt Plant
51+070 80 51 45-55 Apr. 26th
Road Rehabilitation Site Km61+400 80 63 55-65 Apr. 27th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
51
Environmental Monitoring Report1. Reporting Period, May 2014.2. Construction Activities
The Contractor has already carried out the following activity at site
Activity No. Activity Remarks
1 Subbase construction
2 Base course construction
3 Bituminous base course construction
4 Prime coat
5 Tack coat
6 Removal of trees
7 Bridge construction
8 Dismantle of the concrete structure
9 Retaining wall construction
10 Culvert construction
11 Subgrade construction
12 Ditch construction
13 Roadbed excavation
14 Traffic management during construction
3. Environmental Monitoring
Result of Environmental Monitoring Values
3.1. Routine Periodic Water Quality Monitoring.3.1.1. Water Quality Monitoring Conditions
ParameterWater Quality Monitoring Conditions at Bridge ( Km6+434) (measuring
place: 30m far from the bridge, downstream )
National Standard Monitoring values Measuring time
Temperature 2.0℃ May 10th
pH Not less than 6 7.0 May 10thIron (mg/l) 0.008 0.004 May 10th
Copper (mg/l) 0.02 0.005 May 10th
Zinc (mg/l) 0.02 0.008 May 10th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
52
DO Not less than 5 6.5 mg/L May 10thSS Not more than 30 mg/L 20mg/L May 10th
BOD Less than 2mg 0.8mg/L May 10thFecal coliform Not more than 20000 no./ L 16800 no./ L May 10th
Oil grease Not more than 0.5mg/L 0.31mg/L May 10th
ParameterWater Quality Monitoring Conditions at Bridge (Km19+370) (measuring
place: 100m far from the bridge, upstream )
National Standard Monitoring values Measuring timeTemperature 1.8℃ May 10th
pH Not less than 6 7.1 May 10th
Iron (mg/l) 0.008 0.004 May 10th
Copper (mg/l) 0.02 0.009 May 10th
Zinc (mg/l) 0.02 0.007 May 10th
DO Not less than 5 6.5mg/L May 10th
BOD Less than 2mg 1.1mg/L May 10th
SS Not more than 30 mg/L 23mg/L May 10th
Fecal coliform Not more than 20000 no./ L 17100 no./ L May 10th
Oil grease Not more than 0.5mg/L 0.35 mg/L May 10th
Parameter
Water Quality Monitoring Conditions at Bridge (Km 40+106)
(measuring place: under the bridge )
National Standard Monitoring values Measuring time
Temperature 2.1℃ May 16th
pH Not less than 6 7.0 May 16thIron (mg/l) 0.008 0.005 May 16th
Copper (mg/l) 0.02 0.006 May 16th
Zinc (mg/l) 0.02 0.008 May 16thDO Not less than 5 6.8mg/L May 16th
BOD Less than 2mg 0.8mg/L May 16thSS Not more than 30 24mg/L May 16th
Fecal coliform Not more than 20000 no./ L 17400 no./ L May 16th
Oil grease Not more than 0.5mg/L 0.33mg/L May 16th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
53
ParameterWater Quality Monitoring Conditions at Camp,Crusher and Asphalt
Plant(Km 40+150) (measuring place:50m far from the Plant )
National Standard Monitoring values Measuring time
Temperature 2.0℃ May 16th
pH Not less than 6 6.8 May 16thIron (mg/l) 0.008 0.003 May 16th
Copper (mg/l) 0.02 0.008 May 16th
Zinc (mg/l) 0.02 0.01 May 16thDO Not less than 5 7.2mg/L May 16th
BOD Less than 2mg 0.9mg/L May 16thSS Not more than 30 22 mg/L May 16th
Fecal coliform Not more than 20000 no./ L 16800 no./ L May 16thOil grease Not more than 0.5mg/L 0.35 mg/L May 16th
ParameterWater Quality Monitoring Conditions at Bridge (Km 46+918) (measuring
place: 30m far from the bridge, downstream )
National Standard Monitoring values Measuring time
Temperature 1.9℃ May 18th
pH Not less than 6 7.0 May 18th
Iron (mg/l) 0.008 0.006 May 18th
Copper (mg/l) 0.02 0.008 May 18th
Zinc (mg/l) 0.02 0.007 May 18th
DO Not less than 5 7.2mg/L May 18thBOD Less than 2mg 1.0mg/L May 18th
SS Not more than 30 25 mg/L May 18thFecal coliform Not more than 20000 no./ L 16500no./ L May 18th
Oil grease Not more than 0.5mg/L 0.32mg/L May 18th
ParameterWater quality Monitoring Conditions at Bridge (Km 51+070) (measuring
place: under the bridge )
National Standard Monitoring values Measuring Time
Temperature 2.2℃ May 20th
pH Not less than 6 7.1 May 20thIron (mg/l) 0.008 0.004 May 20th
Copper (mg/l) 0.02 0.008 May 20th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
54
Zinc (mg/l) 0.02 0.007 May 20th
DO Not less than 5 7.0mg/L May 20thBOD Less than 2mg 0.8mg/L May 20th
SS Not more than 30 24mg/L May 20thFecal coliform Not more than 20000 no./ L 17200no./ L May 20th
Oil grease Not more than 0.5mg/L 0.30mg/L May 20th
3.2. Routine Periodic Air Quality Monitoring
3.2.1. Air Quality Conditions
ParameterAir Quality Monitoring Conditions at Crusher Km19+370 (mg/m3)
National Standard Monitoring values Measuring time
Particulate Matter (PM) 0.15 0.10 May 10th
Sulfur Dioxide (SO2) 0.05 0.03 May 10th
Carbon Monoxide (CO) 3.0 1.7 May 10th
Nitrogen Oxide (NO) 0.06 0.04 May 10th
Nitrogen Dioxide (NO2) 0.04 0.02 May 10th
TSP 0.5 0.25 May 10th
ParameterAir Quality Monitoring Conditions at Crusher and Asphalt Plant
Km40+150 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.12 May 16th
Sulfur Dioxide (SO2) 0.05 0.02 May 16th
Carbon Monoxide (CO) 3.0 1.4 May 16th
Nitrogen Oxide (NO) 0.06 0.03 May 16th
Nitrogen Dioxide (NO2) 0.04 0.03 May 16th
TSP 0.5 0.35 May 16th
ParameterAir Quality Monitoring Conditions at Camp,Crusher and Asphalt
Plant Km51+070 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.11 May 20th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
55
Sulfur Dioxide (SO2) 0.05 0.03 May 20th
Carbon Monoxide (CO) 3.0 1.5 May 20th
Nitrogen Oxide (NO) 0.06 0.02 May 20th
Nitrogen Dioxide (NO2) 0.04 0.03 May 20th
TSP 0.5 0.26 May 20th
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km4+800 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.12 May 10th
Sulfur Dioxide (SO2) 0.05 0.01 May 10th
Carbon Monoxide (CO) 3.0 2.0 May 10th
Nitrogen Oxide (NO) 0.06 0.04 May 10th
Nitrogen Dioxide (NO2) 0.04 0.03 May 10th
TSP 0.5 0.3 May 10th
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km61+400 (mg/m3)
National Standard Monitoring values Measuring time
Particulate Matter (PM) 0.15 0.12 May 26th
Sulfur Dioxide (SO2) 0.05 0.03 May 26th
Carbon Monoxide (CO) 3.0 1.7 May 26th
Nitrogen Oxide (NO) 0.06 0.03 May 26th
Nitrogen Dioxide (NO2) 0.04 0.02 May 26th
TSP 0.5 0.28 May 26th
3.3 Noise LevelLocation Chainage National
Standard(dBA)Base line (dBA) Monitoring
result (dBA)Time
RoadRehabilitation
Site
Km4+80080 75 70-75 May 10th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
56
Camp,Crusher andAsphalt Plant
40+15080 55 55-60 May 16th
Camp,Crusher andAsphalt Plant
51+07080 51 45-50 May 20th
RoadRehabilitation
Site
Km61+40080 63 50-60 May 26th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
57
Environmental Monitoring Report1. Reporting Period, June 2014.2. Construction Activities
The Contractor has already carried out the following activity at site
Activity No. Activity Remarks
1 Subbase construction
2 Base course construction
3 Bituminous base course construction
4 Prime coat
5 Relocation of channel
6 Street lighting construction
7 Bridge construction
8 Removal of existing asphalt
9 Retaining wall construction
10 Culvert construction
12 Ditch construction
Footpath construction
13 Roadbed excavation
14 Traffic management during construction
3. Environmental Monitoring
Result of Environmental Monitoring Values
3.1. Routine Periodic Water Quality Monitoring.3.1.1 Water Quality Monitoring Conditions
ParameterWater Quality Monitoring Conditions at Bridge ( Km6+434) (measuring
place: 50m far from the bridge, upstream )
National Standard Monitoring values Measuring time
Temperature 6.5℃ June 5th
pH Not less than 6 7.1 June 5thIron (mg/l) 0.008 0.005 June 5th
Copper (mg/l) 0.02 0.003 June 5th
Zinc (mg/l) 0.02 0.006 June 5th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
58
DO Not less than 5 6.2 mg/L June 5thSS Not more than 30 mg/L 23mg/L June 5th
BOD Less than 2mg 0.7mg/L June 5thFecal coliform Not more than 20000 no./ L 16500 no./ L June 5th
Oil grease Not more than 0.5mg/L 0.30mg/L June 5th
ParameterWater Quality Monitoring Conditions at Bridge (Km19+370)
(measuring place: under the bridge )
National Standard Monitoring values Measuring timeTemperature 6.1℃ June 7th
pH Not less than 6 7.0 June 7th
Iron (mg/l) 0.008 0.003 June 7th
Copper (mg/l) 0.02 0.007 June 7th
Zinc (mg/l) 0.02 0.005 June 7th
DO Not less than 5 6.7mg/L June 7thBOD Less than 2mg 1.3mg/L June 7thSS Not more than 30 mg/L 25mg/L June 7th
Fecal coliform Not more than 20000 no./ L 16500 no./ L June 7thOil grease Not more than 0.5mg/L 0.32 mg/L June 7th
Parameter
Water Quality Monitoring Conditions at Bridge (Km 40+106)
(measuring place: 200m far from the bridge, upstream )
National Standard Monitoring values Measuring time
Temperature 5.3℃ June 12th
pH Not less than 6 7.2 June 12th
Iron (mg/l) 0.008 0.004 June 12th
Copper (mg/l) 0.02 0.007 June 12th
Zinc (mg/l) 0.02 0.007 June 12th
DO Not less than 5 6.5mg/L June 12th
BOD Less than 2mg 1.0mg/L June 12th
SS Not more than 30 21mg/L June 12th
Fecal coliform Not more than 20000 no./ L 16700 no./ L June 12th
Oil grease Not more than 0.5mg/L 0.30mg/L June 12th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
59
ParameterWater Quality Monitoring Conditions at Camp,Crusher and Asphalt
Plant (Km 40+150) (measuring place:100m far from the Plant )
National Standard Monitoring values Measuring time
Temperature 5.1℃ June 20th
pH Not less than 6 6.8 June 20thIron (mg/l) 0.008 0.005 June 20th
Copper (mg/l) 0.02 0.009 June 20th
Zinc (mg/l) 0.02 0.008 June 20thDO Not less than 5 6.7mg/L June 20th
BOD Less than 2mg 1.1mg/L June 20thSS Not more than 30 20 mg/L June 20th
Fecal coliform Not more than 20000 no./ L 17200 no./ L June 20th
Oil grease Not more than 0.5mg/L 0.37 mg/L June 20th
ParameterWater Quality Monitoring Conditions at Bridge (Km 46+918)
(measuring place: 50m far from the bridge, downstream )
National Standard Monitoring values Measuring time
Temperature 5.6℃ June 23rd
pH Not less than 6 7.4 June 23rd
Iron (mg/l) 0.008 0.005 June 23rd
Copper (mg/l) 0.02 0.009 June 23rd
Zinc (mg/l) 0.02 0.005 June 23rd
DO Not less than 5 7.0mg/L June 23rd
BOD Less than 2mg 0.8mg/L June 23rd
SS Not more than 30 26 mg/L June 23rd
Fecal coliform Not more than 20000 no./ L 16300no./ L June 23rd
Oil grease Not more than 0.5mg/L 0.33mg/L June 23rd
ParameterWater quality Monitoring Conditions at Bridge (Km 51+070)
(measuring place: 100m far from the bridge, upstream )
National Standard Monitoring values Measuring Time
Temperature 5.3℃ June 25th
pH Not less than 6 7.2 June 25th
Iron (mg/l) 0.008 0.006 June 25th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
60
Copper (mg/l) 0.02 0.008 June 25th
Zinc (mg/l) 0.02 0.008 June 25thDO Not less than 5 6.6mg/L June 25th
BOD Less than 2mg 0.7mg/L June 25th
SS Not more than 30 25mg/L June 25th
Fecal coliform Not more than 20000 no./ L 17500no./ L June 25thOil grease Not more than 0.5mg/L 0.34mg/L June 25th
3.2 Routine Periodic Air Quality Monitoring
3.2.1 Air Quality Conditions
ParameterAir Quality Monitoring Conditions at Crusher Km19+370 (mg/m3)
National Standard Monitoring values Measuring time
Particulate Matter (PM) 0.15 0.13 June 7th
Sulfur Dioxide (SO2) 0.05 0.04 June 7th
Carbon Monoxide (CO) 3.0 1.5 June 7th
Nitrogen Oxide (NO) 0.06 0.02 June 7th
Nitrogen Dioxide (NO2) 0.04 0.02 June 7th
TSP 0.5 0.35 June 7th
Parameter
Air Quality Monitoring Conditions at Crusher and Asphalt PlantKm40+150 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.10 June 20th
Sulfur Dioxide (SO2) 0.05 0.05 June 20th
Carbon Dioxide (CO2) 3.0 1.8 June 20th
Nitrogen Oxide (NO) 0.06 0.05 June 20th
Nitrogen Dioxide (NO2) 0.04 0.03 June 20th
TSP 0.5 0.32 June 20th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
61
ParameterAir Quality Monitoring Conditions at Camp,Crusher and Asphalt
Plant Km51+070 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.12 June 25th
Sulfur Dioxide (SO2) 0.05 0.04 June 25th
Carbon Monoxide (CO) 3.0 2.1 June 25th
Nitrogen Oxide (NO) 0.06 0.03 June 25th
Nitrogen Dioxide (NO2) 0.04 0.01 June 25th
TSP 0.5 0.27 June 25th
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km4+800 (mg/m3)
National Standard Monitoring values Measuring Time
Particulate Matter (PM) 0.15 0.11 June 5th
Sulfur Dioxide (SO2) 0.05 0.03 June 5th
Carbon Monoxide (CO) 3.0 2.2 June 5th
Nitrogen Oxide (NO) 0.06 0.03 June 5th
Nitrogen Dioxide (NO2) 0.04 0.02 June 5th
TSP 0.5 0.26 June 5th
Parameter
Air Quality Monitoring Conditions at Rehabilitation Site
Km61+400 (mg/m3)
National Standard Monitoring values Measuring time
Particulate Matter (PM) 0.15 0.10 June 27th
Sulfur Dioxide (SO2) 0.05 0.03 June 27th
Carbon Monoxide (CO) 3.0 1.4 June 27th
Nitrogen Oxide (NO) 0.06 0.02 June 27th
Nitrogen Dioxide (NO2) 0.04 0.01 June 27th
TSP 0.5 0.36 June 27th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
62
3.3 Noise Level
Location Chainage NationalStandard(dBA)
Base line(dBA)
Monitoringresult (dBA)
Time
RoadRehabilitation
Site
Km4+80080 75 65-80 June 5th
Camp,Crusher andAsphalt Plant
40+15080 55 50-60 June 20th
Camp,Crusher andAsphalt Plant
51+07080 51 50-55 June 25th
RoadRehabilitation
Site
Km61+40080 63 50-65 June 27th
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
63
ANNEX 2. ENVIRONMENTAL MANAGEMENT PLAN (EMP)
MONITORING REPORTS, PROVIDED BY CONTRACTOR
FOR PERIOD OF
JANUARY-JUNE 2014
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
64
EMP Implementation Monitoring for January 2014
Date Location /Stations
Activities During ReportingPeriod Mitigating Measures Implemented
NotedEnvironmental
Effects
Corrective ActionTaken
ROAD WORKS
1st Januaryto 31th
January
Km35 to km36 Ditch construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucks
Nil
Km35 to km36 Relocation of channel Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucks
Nil
Km6, km42 Bridge construction Maintaining the traffic on existing bridgeor diversions,Depress the noise to local resident;Information signs installed.
Nil
Km35 to km36 Roadbed excavation Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
QUARRYING AND CRUSHINGKm13 Quarry Quarrying and production of
subgrade, sub base andbase materials
Quarrying away from flowing water; Nil
Km29 Quarry Quarrying and production ofsubgrade materials
Quarrying away from flowing water Nil
Km 40+000 RHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
Km40+100 LHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
65
Km40+160 Quarry Quarrying and production ofaggregate and basematerials
Quarrying away from flowing water; Nil
Km51 Quarry Quarrying and production ofsubgrade materials
Quarrying away from flowing water; Nil
Km56 Quarry Quarrying and production ofsubbase materials
Quarrying away from flowing water; Nil
ASPHALT PLANT & CONCRETE BATCHING PLANTKm 51 AsphaltPlant
completeinstallation and testthe equipment
Km29 AsphaltPlant
Not commenced
BORROW PITK6,k29+500,
k56+000Borrow pit Water not standed or collected
CONSTRUCTION CAMPKm 19 37 workers All wastes are cleaned by local
environmental authorities or by ourselves.Km 38 14 workers
Km40 (RHS andLHS)
30 workers
OTHER CONCERNSNil
By:
Liang Hao ShengEnvironmental Engineer
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
66
EMP Implementation Monitoring for February 2014
Date Location /Stations
Activities During ReportingPeriod Mitigating Measures Implemented
NotedEnvironmental
Effects
Corrective ActionTaken
ROAD WORKS1st Februaryto28th
February
Km23 to km24 Ditch construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucks
Nil
Km35 to km36 Relocation of channel Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km6, km42 Bridge construction Maintaining the traffic on existing bridgeor diversions,Depress the noise to local resident;Information signs installed.
Nil
Km35 to km36 Roadbed excavation Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
QUARRYING AND CRUSHINGKm13 Quarry Quarrying and production of
subgrade, sub base andbase materials
Quarrying away from flowing water; Nil
Km29 Quarry Quarrying and production ofsubgrade materials
Quarrying away from flowing water Nil
Km 40+000 RHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
Km40+100 LHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
67
Km40+160 Quarry Quarrying and production ofaggregate and basematerials
Quarrying away from flowing water; Nil
Km51 Quarry Quarrying and production ofsubgrade materials
Quarrying away from flowing water; Nil
Km56 Quarry Quarrying and production ofsubbase materials
Quarrying away from flowing water; Nil
ASPHALT PLANT & CONCRETE BATCHING PLANTKm 51 AsphaltPlant
completeinstallation and testthe equipment
Km29 AsphaltPlant
Not commenced
BORROW PITK6,k29+500,
k56+000Borrow pit Water not standed or collected
CONSTRUCTION CAMPKm 19 37 workers All wastes are cleaned by local
environmental authorities or by ourselves.Km 38 14 workers
Km40 (RHS andLHS)
30 workers
OTHER CONCERNSNil
By:
Liang Hao ShengEnvironmental Engineer
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
68
EMP Implementation Monitoring for March 2014
Date Location /Stations
Activities During ReportingPeriod Mitigating Measures Implemented
NotedEnvironmental
Effects
Corrective ActionTaken
ROAD WORKS1st March to31st March
Km6 to km8Km20 to km22Km40 to km41
Stripping topsoil Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucks
Nil
Km40 to km41 Removal of existing asphalt Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km40 to km41 Removal of trees Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km38 to km41 Dismantle of the concretestructure
Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km5 to km6 Retaining wall construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km40, km55 Bridge construction Maintaining the traffic on existing bridgeor diversions,Depress the noise to local resident;
Nil
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
69
Information signs installed.Km6 to km8Km40 to km41
Roadbed excavation Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
QUARRYING AND CRUSHINGKm13 Quarry Quarrying and production of
subgrade, sub base andbase materials
Quarrying away from flowing water; Nil
Km29 Quarry Quarrying and production ofsubgrade materials
Quarrying away from flowing water Nil
Km 40+000 RHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
Km40+100 LHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
Km40+160 Quarry Quarrying and production ofaggregate and basematerials
Quarrying away from flowing water; Nil
Km51 Quarry Quarrying and production ofsubgrade materials
Quarrying away from flowing water; Nil
Km56 Quarry Quarrying and production ofsubbase materials
Quarrying away from flowing water; Nil
ASPHALT PLANT & CONCRETE BATCHING PLANTKm 51 AsphaltPlant
complete installationand test the equipment
Km29 AsphaltPlant
Not commenced
BORROW PITK6,k29+500,
k56+000Borrow pit Water not standed or collected
CONSTRUCTION CAMPKm 19 86 workers All wastes are cleaned by local
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
70
Km 38 31 workers environmental authorities or by ourselves.
Km40 (RHS andLHS)
115 workers
OTHER CONCERNSNil
By:
Liang Hao ShengEnvironmental Engineer
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
71
EMP Implementation Monitoring for April 2014
Date Location /Stations
Activities During ReportingPeriod Mitigating Measures Implemented
NotedEnvironmental
Effects
Corrective ActionTaken
ROAD WORKS1st April to30th April
Km19 to km20 Stripping topsoil Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucks
Nil
Km5 to km6Km17 to km20Km39 to km40Km60 to km62
Removal of existing asphalt Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km39 to km40 Removal of trees Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km18 to km19Km39 to km40Km60 to km61
Dismantle of the concretestructure
Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km4 to km6Km21 to km22Km37 to km38
Retaining wall construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km6,km19,km24,km40+100,km40+601,km51,
Bridge construction Maintaining the traffic on existing bridgeor diversions,Depress the noise to local resident;
Nil
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
72
km55,km61 Information signs installed.Km43 to km44 Relocation of channel Signal men assigned,
Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
Km19-km20Km23-km25Km38-km39
Culvert construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
Km5-km6 Subgrade construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
Km42-km43Km60-km61
Ditch construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Km18 to km20Km37 to km39Km60 to km62
Roadbed excavation Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
QUARRYING AND CRUSHINGKm13 Quarry Quarrying and production of
subgrade, sub base andbase materials
Quarrying away from flowing water; Nil
Km29 Quarry Quarrying and production of Quarrying away from flowing water Nil
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
73
subgrade materialsKm 40+000 RHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
Km40+100 LHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
Km40+160 Quarry Quarrying and production ofaggregate and basematerials
Quarrying away from flowing water; Nil
Km51 Quarry Quarrying and production ofsubgrade materials
Quarrying away from flowing water; Nil
Km56 Quarry Quarrying and production ofsubbase materials
Quarrying away from flowing water; Nil
ASPHALT PLANT & CONCRETE BATCHING PLANTKm 51 AsphaltPlant
completeinstallation and testthe equipment
Km29 AsphaltPlant
Not commenced
BORROW PITK6,k29+500,
k56+000Borrow pit Water not standed or collected
CONSTRUCTION CAMPKm 19 150 workers All wastes are cleaned by local
environmental authorities or by ourselves.Km40 (RHS andLHS)
148 workers
OTHER CONCERNSNil
By:Liang Hao ShengEnvironmental Engineer
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
74
EMP Implementation Monitoring for May 2014
Date Location /Stations
Activities During ReportingPeriod Mitigating Measures Implemented
NotedEnvironmental
Effects
Corrective ActionTaken
ROAD WORKS1st May to31st May
Km60 to km62 Subgrade construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucks
Nil
Km4 to km7Km22 to km27Km50 to km52
Subbase construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km22 to km26Km55 to km57Km60 to km62
Base course construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km55 to km57Km60 to km62
Bituminous base courseconstruction
Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km55 to km57Km60 to km62
Prime coat Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km55 to km57 Tack coat Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucks
Nil
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
75
Little affect on water supply
Km18 to km19Km38 to km39Km61 to km62
Removal of trees Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km17 to km18Km19 to km20Km61 to km62
Dismantle of the concretestructure
Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km4 to km6Km20 to km22Km38 to km39
Retaining wall construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km6,km19,km24,km40+100,km40+601, km42,km51
Bridge construction Maintaining the traffic on existing bridgeor diversions,Depress the noise to local resident;Information signs installed.
Nil
Km4-km7Km24-km25Km37-km38Km41-km42
Culvert construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
Km4-km6Km41-km44Km55-km56Km60-km61
Ditch construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
76
Km5 to km6Km18 to km20Km26 to km27Km39 to km41Km50 to km51Km61 to km62
Roadbed excavation Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
QUARRYING AND CRUSHINGKm13 Quarry Quarrying and production of
subgrade, sub base andbase materials
Quarrying away from flowing water; Nil
Km29 Quarry Quarrying and production ofsubgrade materials
Quarrying away from flowing water Nil
Km 40+000 RHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
Km40+100 LHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
Km40+160 Quarry Quarrying and production ofaggregate and basematerials
Quarrying away from flowing water; Nil
Km51 Quarry Quarrying and production ofsubgrade materials
Quarrying away from flowing water; Nil
Km56 Quarry Quarrying and production ofsubbase materials
Quarrying away from flowing water; Nil
ASPHALT PLANT & CONCRETE BATCHING PLANTKm 51 AsphaltPlant
completeinstallation and testthe equipment
Km29 AsphaltPlant
Not commenced
BORROW PITK6,k29+500,
k56+000Borrow pit Water not standed or collected
CONSTRUCTION CAMPKm 19 150 workers All wastes are cleaned by local
environmental authorities or by ourselves.Km40 (RHS and 160 workers
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
77
LHS)
OTHER CONCERNSNil
By:
Liang Hao ShengEnvironmental Engineer
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
78
EMP Implementation Monitoring for June 2014
Date Location /Stations
Activities During ReportingPeriod Mitigating Measures Implemented
NotedEnvironmental
Effects
Corrective ActionTaken
ROAD WORKS1st June to30th June
Km16 to km17Km35 to km38
Removal of existing asphalt Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucks
Nil
Km4 to km8Km18 to km22Km25 to km27Km37 to km39Km43 to km44
Subbase construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km4 to km8Km22 to km27
Base course construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km22 to km26 Bituminous base courseconstruction
Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km22 to km26 Prime coat Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
79
Km16 to km17Km34 to km35
Relocation of channel Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km28 to km30Km32 to km33
Street lighting construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
Km17 to km18Km20 to km22
Retaining wall construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksLittle affect on water supply
Nil
km24,km40+100,km40+601,km46,km51,km55,km61
Bridge construction Maintaining the traffic on existing bridgeor diversions,Depress the noise to local resident;Information signs installed.
Nil
Km4-km7Km24-km25Km35-km38Km41-km42
Culvert construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
Km4 to km8Km20 to km21Km23 to km25Km26 to km27Km37 to km38Km41 to km44
Ditch construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
Km5 to km7 Footpath construction Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areas
Nil
CAREC Corridor III Dushanbe-Uzbekistan Border Road Upgrading WorksADB Grant No. 0245-TAJ
80
Imposed speed limit for trucksMaintaining the traffic on half road
Km16 to km17Km19 to km20Km35 to km36
Roadbed excavation Signal men assigned,Warning signs at approach 200 metersfrom work site;Dust suppression in populated areasImposed speed limit for trucksMaintaining the traffic on half road
Nil
QUARRYING AND CRUSHINGKm13 Quarry Quarrying and production of
subgrade, sub base andbase materials
Quarrying away from flowing water; Nil
Km29 Quarry Quarrying and production ofsubgrade materials
Quarrying away from flowing water Nil
Km 40+000 RHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
Km40+100 LHSQuarry
Quarrying and production ofbase materials
Quarrying away from flowing water; Nil
Km40+160 Quarry Quarrying and production ofaggregate and basematerials
Quarrying away from flowing water; Nil
Km51 Quarry Quarrying and production ofsubgrade materials
Quarrying away from flowing water; Nil
Km56 Quarry Quarrying and production ofsubbase materials
Quarrying away from flowing water; Nil
ASPHALT PLANT & CONCRETE BATCHING PLANTKm 51 AsphaltPlant
completeinstallation and testthe equipment
Km29 AsphaltPlant
Not commenced
BORROW PITK6,k29+500,
k56+000Borrow pit Water not standed or collected
CONSTRUCTION CAMP