environmental manual appendix adot.alaska.gov/nreg/projects/60911-daltonhwymp0-9... · project...
TRANSCRIPT
2 Project Name: Dalton Highway MP 0-9 Reconstruction Project Number: 60911/STP-0652(16)
Description The project involves reconstructing the Dalton Highway between mileposts 0-9 to improve substandard
sections. Relocation of the highway for the first 6.5 miles is being proposed due to the existing highway
alignment’s substandard vertical and horizontal geometry and the associated extensive effort to meet
reconstruction design criteria.
The existing Dalton alignment begins at MP 73 of the Elliott Highway. It crosses over three ridges and
through two creek valleys along the project length. The proposed realignment begins near MP 74 of the
Elliott Highway as shown on Figure 1. Unlike the existing alignment that traverses hills and valleys, the
proposed realignment follows the valley bottoms of West Fork Creek and Lost Creek. The proposed
realignment would require a new bridge crossing at Lost Creek and new culverts at unnamed tributaries
to West Fork and Lost Creek. See Figure 1 for crossing locations. Portions of the existing highway are
proposed to be obliterated. Coordination would be conducted with Alyeska Pipeline to ensure that the
proposed realignment provides adequate access to the pipeline as some of the existing access points may
be removed.
The Dalton Highway Dalton 6 Mile Pit (65-3-020-2) would likely be utilized to supply material for the
project. The existing and proposed alignments cut through this site. The site location is shown on
Figure 1. Material needs not supplied by the 6 Mile Pit are expected to be obtained from on-site
excavation within the proposed road right-of-way. Potential on-site material sources are shown on
Figure 2.
Resource Setting
Streams & Fish
A new bridge is proposed over Lost Creek and new culverts at unnamed tributaries of Lost Creek and
West Fork. See Figure 1. The Alaska Department of Fish and Game (DFG) online fish database does
not identify these streams as supporting anadromous fish. The streams likely support resident fish. In
response to this agency scoping document, information is requested regarding knowledge of the fish-
bearing status of project area streams (West Fork, Lost Creek, and unnamed tributaries to Lost Creek
and West Fork) and any request to provide for fish passage at specific stream crossing locations. Work
within fish-bearing streams would be coordinated with the DFG. With implementation of DFG Fish
Habitat Permit provisions, no substantial impacts to fish or fish habitat are anticipated.
Wetlands
Shrub and forested-dominated wetlands occur throughout the project within creek and river valleys
bottoms. Forested uplands dominate the surrounding ridge tops. An estimated 41acres of low to
moderate value wetlands would be permanently impacted by the proposed project.
Right-of-Way
All lands surrounding the project appear to be state-owned by the Alaska Department of Natural
Resources (DNR). Up to 400 acres of new right-of-way acquisition are estimated to be needed from
DNR lands for the project. The DNR’s Tanana Basin Area Plan for State Lands (TBAP) notes that
DOT&PF has plans to reconstruct and realign much of the Dalton Highway into the future. The TBAP
states that DOT&PF will work with the DNR planning team to choose the routing that best meets the
land use objectives described in the TBAP and that complies with the appropriate highway standards
and project costs.
Cultural Resources
A cultural resources field survey was started by the State of Alaska Office of History and Archeology in
the fall of 2013 but was not completed due to poor weather conditions. This survey will begin again in
spring of 2014. The primary cultural resource potential is for archeological sites to be found on ridge
tops overlooking the creek valleys. Survey results would be coordinated with the State Historic
Preservation Officer and other consulting parties in accordance with Section 106 of the National Historic
Preservation Act. We welcome any information from agencies concerning known cultural resources
3 Project Name: Dalton Highway MP 0-9 Reconstruction Project Number: 60911/STP-0652(16)
sites in the project vicinity.
II. Purpose and Need of Project
The purpose of this project is to improve the safety and performance of the Dalton Highway from its
beginning (junction with Elliott Highway) to milepost 9. The Dalton Highway is part of the National
Highway System and provides the only vehicle access across Interior Alaska from Fairbanks to
Deadhorse, serving as a critical supply route between commerce and industrial centers. The original
roadway was built in 1974 as a private haul route to support the Trans-Alaska Pipeline System and was
constructed to the former State of Alaska Department of Highways secondary road standards. The
Dalton Highway was opened to the public in 1994 and is now designated as a rural principal arterial that
supports heavy truck and tourism traffic. DOT&PF anticipates an increase in future traffic with
continued industrial development, regional tourism, and renewed interest in the Alaska natural gas
pipeline.
There is need for the project corridor to be updated to current safety standards since more than a third of
the existing alignment has substandard grades and curves that need correction. The geometry of the
roadway makes truck travel difficult due to steep grades and sharp curves, which is considerable on a
route with truck traffic comprising 60% of its total traffic volume.
III. Environmental Consequences
A. Right-of-Way (ROW) Impacts:
1. ROW required:
a. Property required from a state or federal agency.
(1) State Park? Name: None
(2) State Refuge or Critical Habitat Area? Name: None
(3) Federal Park? Name: None
b. Property required from local government entity.
Type Property: None Anticipated, All properties appear to be State-owned.
c. Business or residential property required.
(1) Residential: (indicate number) None (2) Business: (indicate number) None
d. Property required from a Tribe or ANSCA corporation. Name: None
2. Describe:
An early estimate of up to 400 acres of permanent right-of-way acquisition would be needed
from State DNR-owned lands. B. Socio-Economic Impacts:
1. Project could affect community cohesion, neighborhoods, or other community facilities. No
2. Project could affect economic development, such as established area businesses. Adjacent lands
are undeveloped. The project could result in minor short-term traffic delays during
construction where the project occurs on existing alignment.
3. Project could affect travel patterns and accessibility. During construction short term traffic
delays could occur. In the long term the project would extend the service life of the highway
thereby maintain existing travel patterns and accessibility.
4. Project could disproportionately affect minorities or disadvantaged persons (E.O. 12898) No
4 Project Name: Dalton Highway MP 0-9 Reconstruction Project Number: 60911/STP-0652(16)
C. Impacts to Historic Properties:
1. Historic properties listed on or potentially eligible for the National Register of Historic Place
(NRHP) in project’s area of potential effect (APE). A cultural resources field survey was started by the State of Alaska Office of History and
Archeology in the fall of 2013 but was not completed due to poor weather conditions. This
survey will begin again in spring of 2014. The primary cultural resource potential is for
archeological sites to be found on ridge tops overlooking the creek valleys. Survey results
would be coordinated with the State Historic Preservation Officer and other consulting
parties in accordance with Section 106 of the National Historic Preservation Act. We
welcome any information from agencies concerning known cultural resources sites in the
project.
2. Places of traditional religious or cultural importance to Tribes are present in the project area.
None known. Tribal groups are requested to provide any information they may have
concerning places of traditional religious or cultural importance or other historic properties.
Further opportunity to comment and provide information will be provided when tribal
groups are consulted during the Section 106 process.
3. A historic properties survey may be required to identify if sites are present.
A cultural resources survey will be completed in spring of 2014. See question C1 above.
4. Possible adverse effect on historic properties. A determination will be made on the project’s affects historic properties after the cultural
resources survey has been completed and input has been solicited from consulting parties
(including the State Historic Preservation Officer, agencies, tribes, and the public).
D. Fish & Wildlife Impacts:
1. Project could affect anadromous or resident fishes.
A new bridge is proposed over Lost Creek and new culverts at the unnamed tributaries to Lost
Creek and West Fork. See Figure 1. The DFG online fish database does not identify these streams
as supporting anadromous fish. The streams likely support resident fish. In response to this agency
scoping document, information is requested regarding knowledge of the fish-bearing status of any
project area streams (West Fork, Lost Creek, unnamed tributary to Lost Creek and West Fork)
and any request to provide for fish passage at specific stream crossing locations. Work within fish-
bearing streams would be coordinated with the DFG. With implementation of DFG Fish Habitat
Permit provisions, no substantial impacts to fish or fish habitat are anticipated.
2. Problem fish pass culverts within the project area. The DFG Online fisheries database has information
on two stream crossings on the existing Dalton Highway alignment. The unnamed tributary to
West Fork is identified as not having a completed survey for fish pass conditions. Lost Creek is
identified as having likely impact to fish passage. DOT&PF is requesting additional information
agencies may have concerning the need for fish passage at specific stream crossing locations in the
project vicinity.
3. Essential Fish Habitat (EFH) present in the project area. No essential fish habitat occurs in the project
area.
5 Project Name: Dalton Highway MP 0-9 Reconstruction Project Number: 60911/STP-0652(16)
4. Wildlife Resources:
a. Project in area of high wildlife/vehicle accidents. No
b. Project could bisect migration corridors. No
c. Project could segment habitat. No
d. Species of concern to ADF&G in the project area None known
5. Bald Eagle and Golden Eagle Protection Act: Information on the presence of active bald eagles in the
project vicinity is not known at this time. We request bald eagle activity information from the
database of the U.S. Fish and Wildlife Service or any other agency with knowledge of current or
historic bald eagle activity in the project vicinity.
E. Threatened and Endangered (T&E) Species Impacts:
1. Listed T&E species present. No
2. T&E species migrate through the project area. None known
3. Proposed species present in project area. No
4. Candidate species present in the project area. No
5. Critical habitat in the project area. No
6. Describe:
No federally recognized threatened, endangered, proposed, or candidate species or critical habitat are
known to occur in the project vicinity.
F. Waters of the U.S and Water Bodies:
1. Project affects Waters of the U.S. (as defined by USACE), Section 404/10/103. Yes, the project is
expected to affect Lost Creek, unnamed tributaries to Lost Creek and West Fork, and
wetlands in the project area.
2. Project affects Navigable Waters of the U.S. (as defined by USACE), Sec. 10. No
3. Project affects a Cataloged Anadromous Fish Stream (i.e., 41.14.870). No
4. Proposed river or stream involvement:
a. Temporary
Riprap Culvert Work Cofferdam Fill Relocation Diversion
b. Permanent
Riprap Culvert Embankment Fill Relocation Diversion
6 Project Name: Dalton Highway MP 0-9 Reconstruction Project Number: 60911/STP-0652(16)
G. Wetlands Impacts:
1. Project involves wetlands as defined by USACE. Yes
2. Acres: The estimated project permanent impact on wetlands is approximately 41 acres.
3. Fill: Fill quantity unknown at this time.
4. Dredge: Dredging is not proposed.
5. USACE authorization required: Corps of Engineers Section 404 Permit
Describe: Shrub and forested-dominated wetlands occur throughout the project within creek
valley bottoms. Forested uplands dominate the surrounding ridge tops. An estimated 41acres of
low to moderate value wetlands would be permanently impacted by the proposed project.
H. Hazardous Waste:
1. Known or potentially contaminated sites along the corridor. No
2. ROW required from, or extensive excavation adjacent to, a known hazardous waste site. No
3. The existing and/or proposed ROW is contaminated. None known
4. Potential for encountering hazardous waste during construction is high. No
5. Describe:
A review of the Alaska Department of Environmental Conservation (ADEC) contaminated site
databases was completed on 11/19/13. Two sites were found located in the project vicinity: Tower
Hill Mines – Livengood Camp (DEC file #180.38.007) and the Dalton Highway Mile Post 7 Tanker
Rollover (DEC file #330.38.113).
The Tower Hill Mines Livengood Camp contains soil contaminated with heating oil from a leaking
pipe. The potential realignment passes adjacent to but not through the camp. No right-of-way
acquistion or excavation is anticipated within the limits of the camp where the contaminated occurs.
Dalton Highway Mile Post 7 Tanker Rollover site resulted when a tanker truck rolled over and
released 6685 gallons of diesel fuel into the roadside ditch. Cleanup actions were effective in
recovering some of the spilled product. The vertical and horizontal extents of contamination were
not reached during initial removal actions. On 3/28/07 additional excavation was performed to a
depth of 2.5 to 3.5 feet below the bottom of the ditch line. The cleanup contractor estimated there
were approximately 1,881.4 gallons of fuel remaining under or near the road. A 12-mil liner was
installed on the bottom of the excavation to prevent contamination of surface water runoff in areas
of remaining soil contamination. The site history notes that the remaining contamination, contained
within the roadway, will attenuate over time or shall be addressed when or if it is excavated during
road construction or maintenance activities. Based on the project’s early design there is potential
for encountering residual contamination at this site during road construction. This potential will be
assessed in more detail as the design phase progresses. If contamination is expected to be
encountered a plan would be developed in coordination with the DEC to property handle, treat,
and/or dispose of the encountered contaminated soil.
A review of Environmental Protection Agency National Atlas revealed no sites of concern for
encountering hazardous materials within the project area.
7 Project Name: Dalton Highway MP 0-9 Reconstruction Project Number: 60911/STP-0652(16)
I. Air Quality Impacts (NEPA and Conformity):
1. NEPA (all projects):
a. The project is located in an air quality nonattainment or maintenance area (i.e. CO or PM-10). No
If yes, indicate CO or PM-2.5
b. The project is of the type exempt from an air quality analysis per 40 CFR 93.126 (Table 2 and
Exempt Projects).
Not Applicable. Project is not within an air quality nonattainment or maintenance area.
2. Conformity (projects in nonattainment areas only): Not Applicable
a. The project is identified in the approved STIP.
b. The project is in the most current air quality conformity (i.e., TIP).
c. Have there been any changes in the project design concept and scope, as described in the STIP and
TIP conformity analysis?
3. Describe: Not Applicable.
J. Floodplains Impacts (23 CFR Part 650, Subpart A):
Project encroaches onto a 100-year floodplain.
The project is not located within a FEMA-mapped 100-year floodplain.
1. Project involves a regulatory floodway. No
2. Project is located within an area protected by local flood hazard ordinances. No
3. Flood hazard permit is required from local government. No
4. Describe: Not Applicable.
K. Noise Impact (23 CFR Part 772):
1. There are noise-sensitive receivers/land uses adjacent to the proposed project? No
2. The project is located on new location, would result in substantial changes in vertical or horizontal
alignment, or would increase the number of through lanes?
The project does not reduce the roadway distance to a sensitive receptor by half or less. The
proposed vertical alignment does not remove visual shielding or open up a new line of sight to
sensitive receptors. The project would not increase the number of through lanes or add an
auxiliary lane.
L. Water Quality Impact:
1. Project could involve a public or private drinking source. No
2. Project could result in a discharge of storm water to Waters of the U.S. Runoff only
3. Project could affect a designated impaired water body. No
List name(s) and location(s): Not Applicable.
8 Project Name: Dalton Highway MP 0-9 Reconstruction Project Number: 60911/STP-0652(16)
4. 4. Is there a municipal separate storm sewer system (MS4) NPDES permit or will runoff be mixed with
discharges from an NPDES permitted industrial facility? No
5. If extensive dewatering (>250,000 gallons) is anticipated, is the area to be dewatered within 1 mile of a
contaminated site? Not Applicable
6. Describe:
It is anticipated that some storm water runoff will leave the constructions site and with it some sediment
may be transported to down gradient waters of the U.S. during construction. Off-site sedimentation is
expected to be minimal and best management practices will be implemented for the purpose of meeting
state and federal water quality standards. A project-specific erosion and sediment control plan will be
developed prior to construction initiation. A Storm Water Pollution Prevention Plan (SWPPP) will be
developed and implemented by the construction contractor. The SWPPP will comply with the Alaska
Pollution Discharge Elimination System (APDES) General Permit for Construction Activities.
M. Section 4(f)/6(f):
1. There would be a “use” of land from 4(f) properties. No
2. Section 6(f) properties affected by the proposed action. No
3. List agency(s) with jurisdiction: Not Applicable.
4. Describe: Not Applicable.
The project has Section 4(f) or 6(f) involvement. No Section 4(f) or 6(f) lands are located in the
project vicinity.
Lands surrounding the project and proposed for acquisition are within DNR management
Subunits 2J2 and 2J4 as shown on Map 3-6 of the Tanana Basin Area Plan (TBAP). The TBAP
land management plan (page 3-76) identifies the primary purpose of Unit 2J to be for multiple use
management. The TBAP (page 3-77) identifies the designated primary land use of Subunit 2J2 to
be fish and wildlife habitat and the secondary use to be forestry (personal use of low value timber).
The TBAP (page 3-77) identifies the primary land use of Unit 2J4 as low value resource
management. The TBAP does not identify park, refuge, or recreational uses as an emphasis or
primary use for Units 2J2 or 2J4 other than dispersed uses such as hunting, fishing, and trapping.
Based on the TBAP information, Section 4(f) does not apply to DNR lands in the vicinity of the
project. In accordance with the FHWA Section 4(f) Policy Paper (July 20, 2012) Part II, #4
regarding public multiple-use land holdings, Section 4(f) does not apply to those areas within a
multiple-use public property that function primarily for any purpose other than significant park,
recreation or refuge purposes. N. Permits and Authorizations
1. USACE, Section 404/10/103: Yes
2. USCG, Section 9: No
3. ADFG, Fish Habitat Permit: Yes
4. Flood Hazard: No
5. ADEC 401: Yes
6. ADEC Storm Non-domestic Storm Water Disposal Plan Approval: Yes
7. APDES: Compliance with ADEC’s APDES General Permit for Construction Activities
8. ADEC Dewatering: Possible
9. ADF&G Special Area: No
10. Other. If “yes,” list.
STATE OF ALASKA Department of Transportation and Public Facilities
Dalton Highway MP 0-9 Reconstruction STP-0652(16)/60911
DATE: 11/22/13 Figure 1
Livengood, Alaska
Lost
Potential New Bridge Proposed Realignment
Existing Alignment
Stream Crossings
Dalton 6-mile Pit (65-3-020-2)
NO SCALE
O JUNEAU
O NENANA
O HEALY
O FAIRBANKS RUBY O
TANANA O
ANCHORAGE O O VALDEZ O BETHEL
COLDFOOT O
CIRCLE O
O EAGLE
LOCATION MAP
O POINT BARROW
O TOK PROJECT LOCATION
O DEADHORSE
O NOME
O DELTA JCT.
1 inch ~ 1 mile