environmental management framework - world...
TRANSCRIPT
National Highways
Inter-Connectivity Improvement Project
(NHIIP I)
Environmental Management
Framework
A Guidance Document for dealing with Environmental Issues
during Planning, Design and Construction of Roads Under the Project
Draft Document – November 2011
Ministry of Road Transport and Highways
Government of India
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Page 2 of 87
ENVIRONMENTAL
MANAGEMENT FRAMEWORK
NATIONAL HIGHWAY INTER-CONNECTIVITY IMPROVEMENT PROJECT I
Page 3 of 87
Table of Contents
Chapter 1 - Project Background
Chapter 2 - Regulatory Framework
Chapter 3 - Environmental Management - Approach and Tools
Chapter 4 – Potential Environmental Impacts and Management Measures
Chapter 5 – Institutional Arrangements
Page 4 of 87
List of Acronyms
BOD Biological Oxygen Demand
CGWB Central Ground Water Board
CO Carbon Mono-oxide
COD Chemical Oxygen Demand
CoI Corridor of Impact
CPCB Central Pollution Control Board
CRZ Coastal Regulation Zone
CSC Construction Supervision Consultant
CSR Corporate Social Responsibility
CWW Chief Wildlife Warden
dB(A) Decibel (A)
DPR Detailed Project Report
EA Environmental Assessment
EC Environmental Clearance
E-coli Escherichia coli
EHS Environmental, Health and Safety
EIA Environmental Impact Assessment
EMF Environment Management Framework
EMP Environment Management Plan
EO Environmental Officer
ESR Environmental Screening Report
F1 Form 1
GI Galvanized Iron
GoI Government of India
HE Highway Engineers
IAHE Indian Academy of Highway Engineers
IS Indian Standards
K Potassium
Km Kilometer
LAP Land Acquisition Plan
M Million
m Meter
MoEF Ministry of Environment and Forests
MoRTH Ministry of Road Transport and Highways
MT Metric Ton
Page 5 of 87
N Nitrogen
NAAQS National Ambient Air Quality Standards
NGO Non-Governmental Organization
NH National Highways
NHAI National Highways Authority of India
NHIIP National Highway Interconnectivity Improvement Project
NO Nodal Officer
NOC No Objection Certificate
NOx Oxides of Nitrogen
OP Operational Policies
P Phosphorous
PAP Project Affected Person
Pb Lead
PCU Passenger Car Units
PIC Project In Charge
PIU Project Implementation Unit
PM10 Particulate Matter 10
PM2.5 Particulate Matter 2.5
PMC Project Management Cell
PWD Public Works Department
RAP Resettlement Action Plan
RO Regional Officer
ROW Right of Way
SBD Standard Bidding Document
SIA Social Impact Assessment
SO2 Sulfur Dioxide
SPCB State Pollution Control Board
TA Technical Assistance
TOR Terms of Reference
WB World Bank
Page 6 of 87
Chapter 1
PROJECT BACKGROUND
1.1 Introduction
Roads form a critical link in the transport sector accounting for about 60 percent of
passenger movement, 67 percent of freight movement and close to 70 percent of
transport sector contribution to the GDP. Forming only 2 percent of total length of roads
in India, the national highway network carries over 40 percent of total traffic in the
country. As India continues to emerge as one of the fastest growing economies
worldwide, effective and efficient transportation and connectivity is needed to facilitate
equitable distribution of economic growth. This is critical especially in rural areas and
isolated backward regions of the country, where poor road infrastructure is hampering
development.
To improve connectivity through road infrastructure, the Ministry of Road Transport and
Highways (MoRTH), Government of India plans to up-grade all the single lane/
intermediate lane National Highways to at least two lane standards. Some of these
stretches are proposed to be taken up through the assistance from World Bank. The
basic proposition includes strengthening of road pavement in addition to widening to 2
lane/2 lane with paved shoulder standards.
The National Highways Inter-connectivity Improvement Project I (NHIIP I) proposed for
funding support from the World Bank forms part of the Government of India‟s plan to
rehabilitate and upgrade about 6,700 km of non-National Highway Development Network
to a two-lane standard configuration.
1.2 Project Objective
The Project Development Objective (PDO) is to improve and sustain integration of less
developed areas in the project states by enhancing their road connectivity with the
National Highways network. The total cost of the project is estimated at Rs. 6,445
crores, the equivalent of US$ 1,345 million. This is calculated on a 9-year period
including construction and 5 years of performance-based maintenance. The Ministry of
Road Transport and Highways (MoRTH) will be the implementing agency.
1.3 Project Components
The operation will finance civil works with expanding and upgrading from single/
intermediate to two lane standard configuration with paved shoulders, and strengthen
implementation efficiency and the sustainability of project roads through improved
maintenance roads. It will also support a transformational technical assistance agenda of
setting national standards for road sector management, road safety, work site safety and
piloting innovative “green national” highway codes. Through the TA support, the project
will also strengthen the capacity of the PIUs that will be involved in implementing and
monitoring the sub-projects and with the compliance with environmental management
Page 7 of 87
measures. The proposed approach will enable MoRTH and the Bank to concentrate on
elements that support systemic improvements with the focus on improving maintenance
of the highway system. Two sets of outcome indicators have been proposed: to measure
extent of integration; and level of sustained integration of the project.
The project will have four components:
A. Road Improvement Component: The component includes up-grading of selected
sections (with a total length of about 1,250 km) of existing single/intermediate lane
National Highways to standard two-lane/two lane with paved shoulder configuration..
The roads to be finally included under the component will be selected on the basis of
economic analysis as well as results from environment and social assessment
studies.
Towards this end, screening results have identified twelve proposed roads/sub-
projects for inclusion under NHIIP-I located in low income states of Bihar, Orissa,
Rajasthan and in remote areas of middle income states of Karnataka, West Bengal.
However, these or other roads meeting the project (technical) criteria in addition to
environment (process/requirements specified in Environment Management
Framework) and social (process/requirements specified in RPF) requirements would
be considered for inclusion under the project.
B. Road Safety Component
Development and network-wide implementation of a new NH road accident
database, including „one-off‟ baseline data collection
Review and updating IRC Road Safety standards
Development and implementation of RS-specific Monitoring and Evaluation
capability in MoRTH
Multi-agency / multi-sector pilot project(s) on non-NHDP road corridors involving
improved RS engineering, innovations in public information, driver and user
education, community involvement and safety enforcement
Operationalization of the NRS&TM Board
This component will finance: (i) technical advisory and consulting services, training
costs and fees, logistics, consumables and publications; (ii) software (IP), goods and
equipment, and (iii) minor civil works (TBC) for the above sub-components.
C. Institutional Performance & Governance Improvement Component
Resource Management – Phased MoRTH-wide roll-out of tailored (NHAI-TA
derived) ERP systems including implementation of supporting equipment, user
training and operational support, action to support changes in MoRTH prompted
by the ERP, plus transfer to the ERP platform of the non-NHDP Project
Preparation and Management tools and the new non-NHDP contract database
E-Procurement – implementation MoRTH-wide of E-Procurement for non-NHDP
purposes - may be linked to ERP and states‟ facilities
Page 8 of 87
Network Asset Management – upgrading systems, policies and skills as well as
comprehensive road data collection for effective and comprehensive non-NHDP
asset planning, development and management; review and piloting of axle load
enforcement, and updating of MoRTH / PWD „execution-delegation‟ framework
Project Preparation and Management – Comprehensive enhancement of
guidelines, manuals/documentation and supporting systems, MoRTH staff training
and on-site technical assistance for more efficient delivery of non-NHDP projects
and works, including strengthening of projects progress/performance monitoring,
reporting and evaluation processes and integration of new „Construction Zone
Safety‟ requirements and „Green Highway‟ guidelines; piloting and (after
evaluation) implementation of guidelines on Value Management; and
implementation (pre-ERP) of new non-NHDP contract („jobs-wise‟) database
Performance Evaluation – Implementation in MoRTH of new (NHAI-TA derived)
Risk Management framework; strengthening MoRTH (NHAI-TA influenced) „third
party works quality and performance audit‟ framework / capacity, and piloting on
non-NHDP projects and works of new (NHAI-TA derived) Performance Rating
System for all „suppliers‟
MoRTH Staff Training and HRD – Application of new (NHAI-TA derived) Training
Needs Assessment (TNA) MoRTH-wide, followed by implementation of new 3-year
Project-supported TNA-based staff training, HRD programs and „exposure‟
placements for MoRTH staff and for selected PWD staff with ongoing non-NHDP
responsibilities
This component will finance: (i) technical advisory and consulting services, domestic
and international training costs/fees, logistics, consumables and publications; and (ii)
software (IP/licenses), miscellaneous goods and equipment.
D. Sector Research, HRD & Capacity Development Component
Development and initial implementation of new collaborative „research,
HRD/training and manpower development‟ strategy to reduce national Highway
Engineers (HE) and construction industry manpower shortages
Initiation of new medium-term sector research / study program via fellowship
model to target critical knowledge and capability „gaps‟ and sector innovation
Development of new GOI strategy and action plans for initiation of Center(s) of
Excellence in the roads / HE sector in India, and for further development for IAHE
(ex-NITHE) in that context; and
Review and enhancement of IRC operations and capacity
This component will finance: (i) consulting services, training costs and fees, research
Awards, associated travel / logistics, communication, consumables and publications
costs; and (ii) limited amount of IT equipment, software (licenses) and
miscellaneous goods.
Page 9 of 87
1.4 Need for Environment Management Framework
Although the general thrust and broad project interventions are well understood, the
specific details about multiple sub-projects located across various states, and thereby
the nature and scale of their potential impacts, will be known only later. In such a
situation, where sub-projects traversing multiple districts are located across five states
with varying geographical, topographical and socio-economic conditions, a need was felt
to prepare a document that will „guide‟ the planning, design and construction elements of
sub-projects and help in harmonizing the principles/approaches for project preparation
and execution. In this context, an Environment Management Framework has been
prepared for the project.
1.5 Purpose and Objectives of Environment Management Framework
Good environmental management practices are essential and integral elements of sound
project preparation and implementation. More specifically, the EMF seeks to :
1. Establish clear procedures and methodologies for environmental planning, review,
approval and implementation of subprojects to be financed under the Project.
2. To provide practical guidance for planning, designing and implementing the
environmental management measures.
3. Specify appropriate roles and responsibilities, and outline the necessary reporting
procedures, for managing and monitoring environmental and related social concerns
of the sub-projects and;
4. Determine the institutional arrangements, including those related to training,
capacity building and technical assistance (if required) needed to successfully
implement the provisions of the EMF .
The application and implementation of the EMF therefore, will:
1) Support the integration of environmental aspects into the decision making process
of all stages related to planning, design, execution, operation and maintenance of
sub-projects, by identifying, avoiding and/or minimizing adverse environmental
impacts early-on in the project cycle.
2) Enhance the positive/sustainable environmental and social outcomes through
improved/ sensitive planning, design and implementation of sub-activities.
3) Minimize environmental degradation as a result of either individual sub-projects or
through their indirect, induced and cumulative effects, as much as possible.
4) Protect human health and
5) Minimize impacts on cultural property.
The use / implementation of the EMF will also support the achievement of compliance
with applicable laws and regulations as well as with the requirements of relevant Bank
policies on environment aspects.
Page 10 of 87
1.6 Key Contents of the Environment Management Framework
The framework describes the principles, objectives and approach to be followed for
selecting, avoiding, minimizing and/or mitigating the adverse environmental impacts
that are likely to arise due to the project. The framework details out the various policies,
guidelines and procedures that need to be integrated during the planning, design and
implementation cycle of the Bank-funded project. It also outlines the indicative
management measures required to effectively address or deal with the key issues that
have been identified. The required institutional arrangements for effective environment
management have also been outlined as a part of this framework.
Specifically, the Environmental Management Framework includes the following:
Information on GoI‟s environmental legislations, standards and policies and World
Bank safeguard policies that are relevant in the over-all project context.
Process to be followed for environmental screening to guide decision-making
about proposed sub-projects
Steps and process to be followed for conducting environmental impact
assessment and preparation of Environmental Management Plans for selected
sub-projects
Preliminary assessment of anticipated environmental impacts in the context of
broad/known project interventions.
Generic environment management measures to avoid, minimize and mitigate
anticipated impacts
Institutional arrangements for environment management, including monitoring
and reporting.
1.7 Application of the EMF
The EMF needs to be integrated into the preparation and implementation stages of the
various project components. It is an essential ingredient aligned with the project/sub-
project activities and is to be followed through the entire project cycle from planning,
including site identification; design; implementation and operation/maintenance to attain
the above outlined purpose and objectives.
1.8 Revision/Modification of the EMF
The EMF will be an „up-to-date‟ or a „live document‟ enabling revision, when and where
necessary. Unexpected situations and/or changes in the project or sub-component
design would therefore be assessed and appropriate management measures will be
incorporated by updating the Environment Management Framework. Such revisions will
also cover and update any changes/modifications introduced in the legal/regulatory
regime of the country/ state. Also, based on the experience of application and
implementation of this framework, the provisions and procedures would be updated, as
appropriate in consultation with the World Bank and the implementing agencies/
departments.
Page 11 of 87
Chapter 2
REGULATORY FRAMEWORK
This section is provided as a reminder that all activities under the proposed project must
be consistent with all applicable laws, regulations, notifications that are relevant in the
context of the proposed project interventions. It is the responsibility of the various
Project Implementing Entities to ensure that proposed activities are consistent with the
regulatory/legal framework, whether national, state or municipal/local. Additionally, it is
also to be ensured that activities are consistent with World Bank‟s operational policies
and guidelines. This section is not a legal opinion on the applicability of the law but
serves as guidance in the application of the law to the current project context.
2.1 Key Applicable National Laws and Regulation – Project Preparation Stage
The following paragraphs highlight some salient features of select laws, which have a
particularly important bearing on the design and implementation of the proposed project.
A summary of such applicable rules and regulation is furnished in the table below:
Summary of Environmental Legislation Applicable to the Proposed Project
Act Year Objective Responsible
Institution
Environment (Protection)
Act. 1986
To protect and improve the
overall environment MoEF, CPCB
Notification on Environment
Impact Assessment of
Development projects (and
amendments) (referred to
as the Notification on
Environmental Clearance)
2006
2009
2010
To provide environmental
clearance to new
development activities
following environmental
impact assessment.
MoEF, CPCB
Wildlife Protection Act 1972
To protect wild animals and
birds through the creation of
National Parks and
Sanctuaries
MoEF
Water (Prevention and
Control of Pollution) Act
(and subsequent
amendments)
1974
To provide for the
prevention and control of
water pollution and the
maintaining or restoring of
wholesomeness of water.
CPCB
Air (Prevention and Control
of Pollution) Act (and
subsequent amendments)
1981
To provide for the
prevention, control and
abatement of air pollution,
and for the establishment of
Boards to carry out these
purposes.
CPCB and
Road
Authorities
Page 12 of 87
Act Year Objective Responsible
Institution
Forest (Conservation) Act 1980 To protect and manage
forests MoEF
Central Motor Vehicle Act
Central Motor Vehicle Rules
1988
1989
To control vehicular air and
noise pollution. To regulate
development of the
transport sector, check and
control vehicular air and
noise pollution.
State
Transport
Department
Ancient Monuments and
Archaeological Sites and
Remains Act
1958 Conservation of Cultural and
historical remains found in
India.
Archaeological
Dept. GOI
1) Environment (Protection) Act, 1986 and EIA Notification, 2006
The Environment (Protection) Act, 1986 was introduced as an umbrella legislation that
provides a holistic framework for the protection and improvement to the environment. In
terms of responsibilities, the Act and the associated Rules requires environmental
clearances to be sought for specific types of new / expansion projects (addressed under
Environmental Impact Assessment Notification) and for submission of an environmental
statement to the State Pollution Control Board annually.
As per section 3 of EIA Notification S.O. 1533 dated 14th September 2006, the
Central Government forms a State Level Environment Impact Assessment Authority
(SEIAA). All projects and activities are broadly categorized into two categories as
Category A and B.
All projects or activities included as Category „A‟ in the Schedule, including expansion
and modernization of existing projects or activities and change in product mix, shall
require prior environmental clearance from the Central Government in the Ministry of
Environment and Forests (MoEF) on the recommendations of an Expert Appraisal
Committee (EAC) to be constituted by the Central Government for the purposes of this
notification
All projects or activities included as Category „B‟ in the Schedule, including expansion
and modernization of existing projects or activities as specified in sub paragraph (ii) of
paragraph 2, or change in product mix as specified in sub paragraph (iii) of paragraph 2,
but excluding those which fulfill the General Conditions (GC) stipulated in the Schedule,
will require prior environmental clearance from the State/Union territory Environment
Impact Assessment Authority (SEIAA).
The SEIAA shall base its decision on the recommendations of a State or Union territory
level Expert Appraisal Committee (SEAC) as to be constituted for in this notification. In
the absence of a duly constituted SEIAA or SEAC, a Category „B‟ project shall be treated
as a Category „A‟ project.
Page 13 of 87
Environment Clearance Procedure
Per the MoEF EIA Notification, 2006 (and subsequent amendments of 2009 and 2011),
“expansion of national highways greater than 30km, involving additional right of way
greater than 20meters involving land acquisition” are categorized as „A‟ and require a
comprehensive Environmental Impact Assessment study and prior environmental
clearance from the Ministry prior to project/sub-project commencement. Responsibility
for obtaining Environmental Clearance will be vested with the DPR/Feasibility Consultants
on behalf of the Project Proponent (MoRTH/State Units) with assistance from the State‟s
Nodal Officer.
For GoI Category A projects, the process for acquiring an Environmental Clearance (EC)
involves submitting an F1 application package. The package includes details of the
proposed intervention including scope, nature, spatial and temporal dimensions of likely
environmental impacts along with preliminary/suggested measures to avoid, reduce or
mitigate the impacts to alleviate adverse impacts on project affected people; proposed
ToR for carrying out the EIA; the feasibility report; and certified receipt of application for
all related permission and clearances especially with forest diversion.
Once the application is received, MoEF (after a presentation by the consultants) will
determine whether or not the proposed operation will require further environmental
studies; and determine the comprehensive ToR to be followed for the EIA (within 60
days communicates the approval or rejection of the ToR) by the proponent to begin the
assessment. Draft EIAs are circulated with State Pollution Control Board (SPCB) in whose
jurisdiction (district level) the project is located for public hearings with local affected
persons and others who have a possible stake/interest/concern related to potential
environmental impacts of the project. Over-all, the EC procedure would take about 345
days or more.
2) Forest (Conservation) Act, 1980
Forest (Conservation) Act, 1980 pertains to the cases of diversion of forest area and
felling of roadside plantation. Depending on the size of the tract to be cleared, clearances
are applied for at the following levels of government:
If the area of forests to be cleared or diverted exceeds 20 Ha (or, 10 Ha in hilly area)
then prior permission of Central Government is required.
If the area of forest to be cleared or diverted is between 5 to 20 Ha, the Regional
Office of Chief Conservator of Forests is empowered to approve.
If the area of forest to be cleared or diverted is below or equal to 5 HA, the State
Government can give permission.
If the area to be clear-felled has a forest density of more than 40 percent, permission
to undertake any work is needed from the Central Government, irrespective of the
area to be cleared.
Page 14 of 87
Restrictions and clearance procedure proposed in the Forest (Conservation) Act applies
wholly to the natural forest areas, even in case the protected/designated forest area
does not have any vegetation cover.
Feedback from the screening exercise show that the operation could possibly result in
diversion of forest lands across various forest categories – reserve forests, protected
forests such as notified roadside plantations. Under the Forest Conservation Act (1980)
and Forest Conservation Rules (2003) forest land diversion and tree felling on forest
lands (including notified protected road-side plantations) requires a Forest Clearance and
tree cutting permission from the State, and/or Central Government. Having adopted
proactive environmentally conscious engineering design for road re-alignments,
rehabilitation and up-gradation works, the potential result would be/should be relatively
minimal diversion of forest and tree felling.
Forest Clearance Procedure
According to the Forest Conservation Amendment Rules, 2004, proposal for diversion of
forest land (protected and reserve forest) up to 5 hac is processed at the state level and
more than that is processed at the MoEF level. The proposal with requisite information
and documents is sent to the Nodal officer of the State Government, or the Union
Territory Administration (UTA). The State Government or UTA submits the proposal to
the Chief Conservator of Forests or the Conservator of Forests. This is further processed
by the concerned Regional Office of MoEF, where decision is made within a period of 45
days for proposed forest diversion of up to 5 ha. For diversion of 5hac up to 40 hac land,
proposal is forwarded with recommendations from the state/regional office to the central
MoEF for decision making. Overall, the Forest Clearance process may take up to one
year.
3) Water and Air (Prevention and Control of Pollution) Acts
Water Act and Air Acts provide for the prevention and control of water and air pollution
respectively. These acts empower the Pollution Control Boards to collect effluent and
emission samples, entry to industrial units for inspection, power to prohibit on use of any
water bodies for waste disposal and creation of new discharge outlets, provide consent to
set up and operate certain facilities likely to create air and water pollution including
power to give directions and prosecuting offenders.
The Air and Water Act are particularly applicable to all civil works activities. All
construction work contractors need to obtain the consent-to-establish and consent-to-
operate for plants i.e. concrete batching, stone crushing and hot mix plants and other
machinery that they may be required for the purpose of construction. The NOC
certificates need to be obtained from the regional offices of the SPCB. Wherein the
existing plants are used, the contractor shall ensure that all applicable consents are
obtained for operating the plant/equipment.
Page 15 of 87
4) Ramsar Convention on Wetlands of International Importance, 1971
The Ramsar Convention is an international treaty for the conservation and sustainable
utilization of wetlands i.e. to stem the progressive encroachment on and loss of wetlands
now and in the future, recognizing the fundamental ecological functions of wetlands and
their economic, cultural, scientific and recreational value.
According to the Ramsar list of Wetlands of International Importance, there are 25
designated wetlands in the country which are required to be protected. Activities
undertaken in the proximity of these wetlands should follow the guidelines of the
convention.
5) Ancient Monuments and Archaeological Sites and Remains Rules, 1959
As per the Act, area within a radius of 100m and 300m from the “protected property”
are designated as “protected area” and “controlled area” respectively. No development
activity (including mining operations and construction) is permitted in the “protected
area” and all development activities likely to damage the protected property are not
permitted in the “controlled area” without prior permission of the Archaeological Survey
of India (ASI). Protected property entails the site/remains/ monuments are protected by
ASI or the State Department of Archaeology.
Activities in, then the PMU/implementing agency/line department needs to undertake the
protected areas should not be undertaken. If activities are to be done in the controlled
area of protected properties necessary clearances from ASI.
2.2 Key Statutory Clearance Requirements – Construction Stage
During the construction stage, some of the key statutory requirements that need to be
obtained by the Contractor as part of mobilization (pre-construction) have been listed in
thetable given below.
Key Statutory Clearances to be Obtained by the Contractor
S.No. Clearance Required for Statute under which
clearance is required
Statutory
Authority
1 Hot mix plants, Crushers
and Batch Mix Plants
Air (Prevention and Control of
Pollution) Act, 1981 and Noise
Pollution (Regulation and
Control) Rules, 2000
State Pollution
Control Board
2
Storage, handling and
transport of hazardous
materials
Hazardous Waste (Management
and Handling) Rules, 1989 and
Manufacturing, Storage and
Import of Hazardous Chemicals
Rules, 1989
State Pollution
Control Board
Page 16 of 87
S.No. Clearance Required for Statute under which
clearance is required
Statutory
Authority
3
Location/ layout of
workers camp, equipment
and storage yards
Environment Protection Act, 1986
and Manufacturing, Storage and
Import of Hazardous Chemicals
Rules, 1989
State Pollution
Control Board
4 Quarries (in case of
opening of new quarries) Environment Protection Act, 1986
Dept. of Mining;
Concerned District
Administration
5 Discharges from Labor
Camp
Water (Prevention and Control of
Pollution) Act, 1974
State Pollution
Control Board
6
Permission for withdrawal
of groundwater for
construction
Environment Protection Act, 1986 State Ground Water
Board
7 Permission for sand
mining from river bed Environment Protection Act, 1986
Irrigation
Department;
Concerned District
Administration
8 Disposal of bituminous
wastes
Hazardous Waste (Management
and Handling) Rules, 1989
As per state norm/
Local Civic Body
2.3 World Bank Policies
The World Bank's environmental and social safeguard policies (ten of them) are a
cornerstone of its support to sustainable poverty reduction. The objective of these
policies is to prevent and mitigate undue harm to people and the environment in the
development process. These policies provide guidelines for the identification,
preparation, and implementation of programs and projects. The following operational
policies are relevant in context of the Project from an environmental viewpoint:
Applicable Safeguards Policies of the World Bank
World Bank Policy
Description Applicability Measures to be incorporated
Environmental Assessment
OP 4.01
This policy is triggered if a project is likely to have significant adverse environmental impacts in its area of influence. For category A projects, a
comprehensive EIA is required with emphasis on
integrating environmental measures in project planning, design, implementation and operation.
The project may have impacts on the environmental components such as on
water bodies, trees, and hill
slopes.
Application of EMF in project planning, DPR preparation and project implementation.
Integration of EHS requirements in standard
bidding documents will provide enabling
mechanism for required enforcement.
Page 17 of 87
World Bank Policy
Description Applicability Measures to be incorporated
Natural Habitats OP 4.04
This policy supports the protection, maintenance and rehabilitation of natural habitats. The Bank doesn‟t finance projects that involve the conversion of designated
critical Natural habitats.
Some projects are likely to be in close proximity to sensitive natural
habitats.
Development of environmental screening tool and conduction of the said exercise to determine the nature and magnitude of impacts on sensitive and
ecologically critical areas. Appropriate measures to deal with such findings, including exclusion of some project roads, as may be necessary.
Forests OP 4.36
Policy covers all projects that affect natural or planted forests, whether positively or negatively.
Some projects are in close proximity to or traverse forest areas and may need forest land diversion.
Avoidance and/or minimization of forest uptake by appropriate methods in the engineering design; Forest Clearances prior to award of works; Use of EMF to
address impacts as necessary; Compensatory Afforestation.
Consultation and Disclosure
Requirements (BP 17.50)
The policy requires the borrower to consult Project
Affected People and local NGOs through the various phases of the project: before EIA TORs are finalized and when the draft EIA is available. It requires that groups being consulted be
provided on-time, comprehensible and easily accessible information before consultations. The policy also requires that the borrower to make the EA summary
available in the state (in a local language) and a public
places to all the stakeholders prior to appraisal.
For each sub-project road,
comprehensive consultations will be required during the design, planning and implementation
stages: to determine the baseline conditions/ issues; locally viable
mitigation measures for
addressing environmental impacts; consensus on engineering
designs especially where realignments and bypasses are concerned; community involvement/
support for supervising and monitoring
project implementation.
Feasibility/DPR consultants have carried out
consultations during the screening exercises. Where reports from the consultations have been found to be grossly insufficient, the Bank has provided further guidance
for additional consultations with regards to ensuring representativeness in both number and categories of stakeholders, prior notification and
methodology to adopt in order to ensure usefulness
of the consultations to both the affected groups and the borrower in terms of design, planning, implementation,
supervision and maintenance of the roads projects. Another important dimension of the consultations is with seeking consensus on road engineering designs where
realignments and bypasses are concerned.
Page 18 of 87
1) Environmental Assessment (OP 4.01)
Environmental Assessment is used in the World Bank to identify, avoid, and mitigate the
potential negative environmental impacts associated with Bank‟s lending operations
early-on in the project cycle. The policy states that Environment Assessment (EA) and
mitigation plans are required for all projects having significant adverse environmental
impacts or involuntary resettlement. Assessment should include analysis of alternative
designs and sites, or consideration of “no option” and require public participation and
information disclosure before the Bank approves the project.
In World Bank operations, the purpose of Environmental Assessment is to improve
decision making, to ensure that project options under consideration are sound and
sustainable, and that potentially affected people have been properly consulted and their
concerns addressed.
The World Bank's environmental assessment policy and recommended processing are
described in Operational Policy (OP)/Bank Procedure (BP) 4.01: Environmental
Assessment.
2) Natural Habitat (OP 4.04)
The policy implementation ensures that Bank-supported development projects give
proper consideration to the conservation of natural habitats, in order to safeguard their
unique biodiversity and ensure the sustainability of the environmental services and
products which natural habitats provide to human society.
This policy is applicable when a project (including any subproject under a sector
investment or financial intermediary loan) with the potential to cause significant
conversion (loss) or degradation of natural habitats, whether directly (through
construction) or indirectly (through human activities induced by the project).
3) Forest Policy (OP 4.36)
The implementation of the policy ensures that envisaged forest sector activities and
other Bank sponsored interventions which have the potential to impact significantly upon
forested areas:
(a) Do not encroach upon significant natural forest areas that serve important social,
environmental or local economic purposes.
(b) Do not compromise the rights of local communities to continue their traditional use
of forests in a sustainable fashion.
(c) Do not finance commercial logging operations, in the case of primary tropical moist
forest, nor any purchase of equipment for this purpose.
4) Cultural Property (OP 4.11)
The World Bank Policy OP/BP 4.11 defines physical cultural resources as movable or
immovable objects, sites, structures, groups of structures, natural features and
landscapes that have archaeological, paleontological, historical, architectural, religious,
Page 19 of 87
aesthetic, or other cultural significance. Physical cultural resources may be located in
urban or rural settings, and may be above or below ground, or under water. Their
cultural interest may be at the local, provincial or national level, or within the
international community.
The Bank assists countries to avoid or mitigate adverse impacts on physical cultural
resources from development projects that it finances. The impacts on physical cultural
resources resulting from project activities, including mitigating measures, may not
contravene either the borrower‟s national legislation, or its obligations under relevant
international environmental treaties and agreements.
The borrower addresses impacts on physical cultural resources in projects proposed for
Bank financing, as an integral part of the environmental assessment (EA) process.
2.4 MoRTH and IRC Specifications
All road works in India are to be in accordance with the MoRTH specifications for Road
and Bridge works and guidelines of Indian Roads Congress (IRC). The MoRTH
specifications have special provisions towards protection of environment under Clause
501, Annexure A and the contractor is to satisfy the provisions. Apart from the Annexure
A to clause 501, there are provisions for control of erosion, drainage, dust suppression,
borrow area and haul road management under relevant sections. Provisions of clause
501 Annexure A, cover the environmental aspects as:
General
The contractor shall take all necessary measures and precautions to
carry out the work in conformity with the statutory and regulatory
environmental requirements.
The contractor shall take all measures and precautions to avoid nuisance
or disturbance from the work. It shall be precautionary measures than
abatement measures taken after generation of nuisance.
In the event of any spoil, debris, waste or any deleterious material from
site being deposited on adjacent land, the same shall be removed and
affected area shall be restored to its original state.
Air
The contractor to devise and arrange methods to control dust, gaseous
or other airborne emissions in such a way that adverse impacts on air
quality are minimized.
Dust shall be minimized from stored material and stockpiles by spraying
water.
Covering of material likely to generate dust during transportation is to be
covered with tarpaulin.
Spraying of water on haul roads, if found necessary.
Page 20 of 87
Water
The contractor shall prevent any interference with supply/abstraction of
water resources.
Water used for dust suppression shall be reused after settlement of
material in collected water.
Liquid waste products to be disposed off such that it does not cause
pollution.
No debris is to be deposited or disposed into/adjacent to water courses.
Control of
wastes
No uncontrolled disposal of wastes shall be permitted. The contractor
shall make specific provisions for disposal of all forms of fuel and engine
oil, all types of bitumen, cement, surplus aggregate, gravels, bituminous
mixtures etc. conforming to local regulations and acceptance of the
engineer
Noise
The contractor shall use all necessary measures to reduce noise from
construction equipment and maintain all silencing equipment in good
condition.
Emergency
Response
The contractor shall plan and provide for remedial measures in case of
occurrence of emergencies as spillages of oil, bitumen or chemicals.
In addition to the above conditions, avoidance measures and control of activities having
potential for generation of environmental impacts are devised. These include:
Section 111 Precautions for safeguarding the environment
Clause 201.2 Preservation of Property/Amenities during clearing and grubbing
Clause 301.3.2 Stripping and storing of topsoil for reuse during excavation for
roadway and drains
Clause 302.4 Restriction on timings for blasting operations
Clause 304.3.6 Public safety near towns/villages where excavation is carried out
Clause 305.2.2.2 Locations of borrowing and relevant regulations
Clause 305.3.3 Stripping and storing of topsoil at borrow locations
Section 306 Soil erosion and sedimentation control
Clause 407.4.2 Provisions for turfing on median and islands
Page 21 of 87
Section 517 Recycling of bituminous pavement and excavated material
Clause 701.2.1 Use of geo-textiles for control of soil erosion
Section 810 Use of Metal beam crash barriers for safety, relevant regulations
and specifications
Clause 2501 Precautions during river training works
2.5 Other Applicable Laws
Environmental issues during road construction stage generally involve equity, safety and
public health issues. The road construction agencies require complying with laws of the
land, which include inter alia, the following:
Workmen's Compensation Act 1923: The Act provides for compensation in case of injury
by accident arising out of and during the course of employment;
Contract Labour (Regulation and Abolition) Act, 1970: The Act provides for certain
welfare measures to be provided by the contractor to contract labour;
Minimum Wages Act, 1948: The employer is supposed to pay not less than the Minimum
Wages fixed by appropriate Government as per provisions of the Act;
Payment of Wages Act, 1936: It lays down as to by what date the wages are to be paid,
when it will' be paid and what deductions can be made from the wages of the workers;
Equal Remuneration Act, 1979: The Act provides for payment of equal wages for work of
equal nature to Male and Female workers and not for making discrimination against
Female employees;
Child Labour (Prohibition and Regulation) Act, 1986: The Act prohibits employment of
children below 14 years of age in certain occupations and processes and provides for
regulation of employment of children in all other occupations and processes.
Employment of child labour is prohibited in Building and Construction Industry;
Inter-State Migrant Workmen‟s (Regulation of Employment and Conditions of Service)
Act, 1979: The inter-state migrant workers, in an establishment to which this Act
becomes applicable, are required to be provided certain facilities such as housing,
medical aid, travelling expenses from home to the establishment and back, etc.;
The Building and Other Construction Workers (Regulation of Employment and Conditions
of Service) Act, 1996 and the Cess Act of 1996: All the establishments who carry on any
building or other construction work and employs 10 or more workers are covered under
this Act; the employer of the establishment is required to provide safety measures at the
Page 22 of 87
building or construction work and other welfare measures, such as canteens, first-aid
facilities, ambulance, housing accommodation for Workers near the workplace, etc.;
The Factories Act, 1948: The Act lays down the procedure for approval of plans before
setting up a factory, health and safety provisions, welfare provisions, working hours and
rendering information-regarding accidents or dangerous occurrences to designated
authorities;
Hazardous Wastes (Management and Handling) Rules, 1989: Occupiers generating
hazardous wastes given in the list shall take all practical steps to ensure that such
wastes are properly handled, i.e. collection, reception, treatment, storage, and disposed
of without any adverse effects to human health and environment (Rule 4 Such occupier
shall apply for authorization in prescribed format to the State Pollution Control Board)
Chemical Accidents (Emergency Planning, Preparedness and Response) Rules, 1996: The
Rules provide for mandatory preparation of On-Site Emergency Plans by the industry and
Off-Site Plans by the district collector and the constitution of four tier crisis groups at the
centre, district, and local levels for the management of chemical disaster.
2.6 Applicability of Regulations/Policies
The applicability of any of the national/state level regulation and World Bank safeguard
policy needs to be ascertained separately for each sub project/road considered in the
NHIIP I as each law/rule/regulation has its own legal implication and process for
compliance. The regulatory framework as described in this EMF as serves as a guiding
document and a quick point of reference on the applicable regulatory framework.
Each of the proposed candidate roads identified till date for inclusion in the project has
already been screened from this perspective. However, the precise applicability of the
regulations will ultimately depend on the location, proposed intervention and design of
the sub-project and this will be determined during the detailed (sub-project specific)
environmental assessment exercise.
Should there be any changes in the provisions in the various acts rules or notifications
enacted by the Government of India/concerned state Government during the course of
implementation of the project, then compliance to the amended rules and regulations as
applicable on the sub-projects will become mandatory.
2.7 Other Relevant Technical Guidance Materials
The guidelines endorsed by MoEF for the application of Environmental Protection Act,
1986 for highway projects (including the Environmental Impact Assessment Guidance
Manual for Highways, February 2010) and World Bank‟s operational policies on
environment shall be adopted/followed for the environment screening, conducting EIA
and preparing/implementing the EMP.
In addition, the methods of measuring air pollution should be in conformance with IS:
5182-1977 and in case of noise pollution, IS: 3028-1980 for measurement of noise
Page 23 of 87
emitted by moving road vehicles; IS: 4758-1968 for measurement of noise emitted by
machines; IS: 10399-1982 for measurement of noise emitted by stationary road vehicles
are to be followed. As regards Highway aesthetics, use of provisions made in IRC: SP:
21-1979 - Manual on Landscaping of roads and its subsequent revised versions are to be
followed. Some other references include the International Roads Congress (IRC)
Guidance note on Highways, May 2011 and Roads and the Environment Handbook,
World Bank, 1997.
Page 24 of 87
Chapter 3
ENVIRONMENTAL MANAGEMENT - APPROACH AND TOOLS
The Chapter describes the principles and approach to be followed for selecting, avoiding,
minimizing and/or mitigating the adverse environmental impacts that are likely to arise
due to the project. Each of the sub-projects proposed under the project will follow the
approach suggested here to achieve the objectives of environmental management.
3.1 Key Steps to be Followed
A comprehensive environmental management approach for the project will involve the
following key steps and processes:
1. Preliminary Environmental Screening
2. Detailed Environmental Screening
3. Environmental Impact Assessment
4. Environmental Management Plans
5. Environmental Monitoring (including Audits) and Reporting
The following section aims to provide a description of the environment management
approach and tools to evaluate the potential impacts from the proposed project
interventions. The Environment Management tools aim to support at the early stages of
Preliminary Environmental Screening
Environmental Screening
Environmental Impact Assessment
Environmental Management Plans
Implementation of EMPs, - Monitoring,
Auditing and Reporting
Preliminary knowledge of
applicable GoI national,
legislations state and local
polices and regulations; and
World Bank safeguard
policies
Based on specific application
of required policies and
regulations, process,
timeframe and responsibility
Page 25 of 87
planning and decision-making and selection of environmental measures including
mitigation/technologies based on the nature and scale of identified potential impacts.
Step 1: Preliminary Environmental Screening
This step will involve an initial desk review of the available information about the road
and the sub-project area. A preliminary environment and social screening format would
be filled-up using such available information and field visits would be undertaken to
understand the general overview in context of the scope of the proposed operation. The
exercise will help in identifying the key/significant potential environmental impacts and
in determining the project specific context and the focus required for carrying out the
detailed environmental screening exercise.
Without narrowing the focus of the detailed field investigations/assessments, having this
knowledge provides an early sense on the spatial and temporal dimension about the
likely issues on-hand.
Step 2: Environmental Screening
Detailed screening exercise is the second step in the EMF process. The purpose of
environmental screening is to get an overview of the nature, scale and magnitude of the
issues in order to determine the project feasibility and further if findings permit, it allows
for proper scoping of the detailed EIA and SIA that would be subsequently carried out.
After identifying key issues, the applicability of the Bank‟s environment safeguard
policies is to be established along with Government of India‟s / State Government‟s
regulatory requirements. Based on this, boundaries and focus areas for the EIA and SIA
along with the use of specific instruments would be determined.
The key sub-steps involved in the screening process are outlined below:
Ascertain presence of any environmentally sensitive areas (as detailed in screening
checklist) through primary/secondary information.
Confirm applicability of regulations and policies in context of broad sub-project
interventions.
Conduct reconnaissance site visits for ground truthing and incorporate required/
additional information in the screening format (see annex).
Obtain details about land availability and broad categories of ownership
(forest/govt./private)
Preparation of a screening report as per the structure provided in Annex.
The outcome of the screening process will help select and/or prioritize the various
investments and where required, start the clearance process in a timely manner.
Safeguards screening usually consist of checking and identifying environmental risks,
impacts and opportunities and the requisite measures that are applicable within the local
context for addressing them. Findings from the screening will be used to determine
ecological and as well as economic viability of the sub-projects. Particular focus will be
required for proposed realignments and bypasses.
Page 26 of 87
To ensure well targeted field assessment during the screening process, the World Bank
has prepared a Guidance Note for use by the Consultants and the respective state
executing agencies that outlines the steps and key data that is to be collected for
determining the feasibility of the sub-project from an environmental stand point. The
note provides detailed guidelines for collecting information on environmental, natural,
biological, and physical and socio economic conditions without which it becomes
cumbersome to determine the likely potential impacts that may result from the project
interventions. The process enables proper targeting of issues requiring further technical
research and in-depth assessments during the EIA and SIA preparation. Without the
proper screening, deficient planning and engineering design of sub-projects using
unreliable information can result in weak arrangements to conserve critical natural
ecosystems and may result in creating adverse environmental impacts.
Key outputs of the detailed environmental screening would include:
determination (with a degree of confidence), of all national and state and local
regulations and policies that will apply to the sub-projects
preliminary judgment on the sub-project category per the MoEF EIA Notification,
2006 (including recent amendments)
decision on the environmental categorization (A, B, or C)1 in line with World
Bank‟s safeguards policies; and
process, timeframe and responsibilities for securing the requisite clearances and
permissions per GoI guidelines.
It is critical at this stage for Consultants to review the list of applicable legislations or
polices and regulations with the project proponent and the World Bank first to diffuse
inconsistencies in understanding and second, to mobilize assistance both at the central
and state levels to facilitate applications process.
Experience with preparing the F1 applications for Environmental Clearances shows that
Nodal Officers and Regional Officers play an essential role and involving them early on in
the process is critical. Based on the screening results, a decision can be made on
whether the sub-project road would require further field assessments and studies or not.
The Guidance note also gives an outline for presenting data with necessary explanation
for recording likely environmental impacts.
The screening process enhances implementation by screening out or enhancing
acceptability of sub-project proposals on the basis of environmental criteria. Apart from
the screening of sub-projects for proposed inclusion in the project (NHIIP-1), the
results/findings from this exercise would be used to determine the scope of
Environmental (Impact) Assessment requirement.
1 World Bank safeguards policies
Page 27 of 87
Step 3: Environmental Impact Assessment
An EIA consists of a comprehensive study that involves thorough documentation of
existing conditions, and identification of impacts with a comparison of alternative project
design options including without the project option. If implemented early, the EIA can be
an excellent “preventative tool”2. Usually, EIA has three objectives: assist decision
makers in getting a clear picture of the potential impact on the overall environmental
quality; provision of impact prevention and enhancement of benefits and minimization of
impacts in the long term; and provide a forum that allows direct input from stakeholders
in the managements of the project. Towards this end, the MoEF has developed an EIA
Guidance Manual for Highways, which will be used along with WB‟s operational policy
notes.
Ideally, an EIA will have:
A general information on highway project, requisite environmental clearance
process and a gist of the project component
the location of the road corridor, map and topographical sheets including the
potential benefits and need for the project, description of alignment options,
implementation schedule and the projected costs for the project
characterize the relevant features of the current (“baseline”) state of the
receiving environment biological, physical and socioeconomic description of the
corridor and the region
description of the potential interactions between the intervention and the baseline
environment
analysis of alternatives with particular reference to location of project corridor and
the applicable engineering technologies
management measures to avoid, mitigate, compensate and monitor any
potentially significant adverse impacts and cost of management measures in an
environmental management plan
summarize significant concerns and recommend needed actions to address each
concern
Conclusion – stating that either (a) the EIA is the completed environmental
assessment for the intervention or (b) further assessment work is required and
will be incorporated in a revised EIA. For example, project roads that would need
follow up biodiversity assessments to track changes will be stated in the EIA
Disclosure of the Consultants that prepared the EIA
The GoI EIA Guidance Manual for Highways clearly outlines the contents and
comprehensive description of the chapters in an EIA. The note also provides sample
ToRs for EIAs, international best practice on road construction and management, codes
of practices as advocated by the International Road Congress, India (IRC).
Key steps will include the following:
2 Roads and Environment Handbook, The World Bank, 1997
Page 28 of 87
Define the scope of the EIA: In this case, the scope of the EIA study will be
shaped by the findings from the environmental screening exercise and the TORs
prepared by the MORTH. Where relevant, the World Bank OP‟s will
supplement/guide the information to be added and process to be followed.
Characterize the project interventions (type of project, location, need for the
project, alignments, utilities to be shifted, activities, schedules, estimated budget
, etc.),
Building on findings from screening exercise, identify likely interactions between
the project and the environment especially where project roads are abutted by
critical forest and river ecosystems
Establish an effective stakeholder participation program
Identify key environmental issues and assess range and potential severity of
impacts on the existing environment (adverse; and beneficial, direct and indirect)
by (i) project phase; (ii) engineering technologies and other non-built
infrastructure mechanisms to be used and (ii) by ecological component,
community and other sub-units of the study area
Assess the risks and implications of improper operation, failures, disasters and
other (lower probability) events
Consider the implication of project alternatives with and without the interventions
with respect to both location and technologies. Where realignments and bypasses
are being considered, assess the feasible design options with inputs from the
potential project affected people incorporated
Prepare an EMP, which is implementable program of measures to avoid, mitigate,
manage and monitor adverse impacts and enhance benefits.
Assess the residual impacts remaining after implementation of EMP measures
The following is the recommended table of contents of EIA:
- Executive summary
- Policy, legal and institutional framework
- Project description
- Status of the environment (baseline data)
- Environmental impacts
- Analysis of alternatives
- Additional studies (if applicable)
- Project Benefits
- Environmental Management Plan
- Stakeholder consultations
- Summary and recommendations
- Conclusions
- Annexes
Page 29 of 87
The model outline does not explicitly provide section/subsection headings for many of
EIA activities. Therefore DPR/feasibility consultants will create their own customized
outline from this model that provides sections/subsections for EIA activity undertaken for
the sub-project road under consideration.
Step 4: Preparation of Environmental Management Plan (EMP)
EMP is the next step in the EIA process after identifying potential impacts. It involves the
identification and development of measures aimed at avoiding, mitigating, offsetting
and/or reducing impacts to levels that are environmentally acceptable during
implementation and operation of the project road. EMPs provide an essential link
between the impacts predicted and mitigation measures specified within the EIA and
implementation and operation activities.
Certain activities/interventions will have an impact on the natural environment, the scale
of which would depend on the existing baseline conditions along the corridor and thus
would require a specific plan to institute and monitor mitigation measures and take
desired actions in a timely manner. An EMP must be sub-project specific, clearly
describing adverse impacts and mitigation actions to be taken. The magnitude and
temporal scale of the sub-project road will determine the contents/coverage of the EMP.
Depending on extent of issues that are to be avoided, minimized and/or mitigated, the
EMP will have concrete/specific mitigation actions, timelines and responsible persons.
For each sub-project road, an EMP should address the following:
Mitigation, enhancement, protection and compensation measures for each phase
including design pre-construction, construction, operation and maintenance
Mitigation performance monitoring (i.e. monitoring the operation and
maintenance of mitigation measures and their targeted impacts)
PAP participation arrangements by project development phase
Disaster management contingency plan where applicable especially in areas with
potential flooding, earthquake zones
Institutional arrangements for implementation, monitoring and reporting
Cost estimates for all EMP activities
Standard construction environmental safeguards clauses for engineering and civil
works
For developing the EMP, DPR consultants will consider findings from the stakeholder/
public consultation process, including suggestions from domain experts and Project
Affected People (PAP) and vulnerable people. For NHIIP project roads, a standalone EMP
will be needed for a sub-project.
For Category A projects, World Bank guidelines require detailed EMPs. EMPs for the
respective roads projects would be prepared using guidelines provided in the Annex C of
OP 4.01 of the World Bank safeguards.
Page 30 of 87
Below are the proposed elements of an EMP:
Identified Impacts and Description of Mitigation Measures: Under this sub-heading, the
EMP will describe the identified impacts that may result from the project interventions.
With reference to each impact, it will describe feasible and cost effective measures to
minimize impacts to acceptable levels. This section will also provide details on the
conditions under which the mitigatory measures will be implemented whether as a
routine or in the event of contingencies. The EMP will also distinguish between type of
solution proposed (structural & non structural) and the phase in which it should become
operable. Measures that can be taken to avoid, minimize or mitigate the extent of
environmental damage have been detailed out in the annex.
Enhancement Plans: Positive impacts or opportunities arising out of the project will be
identified during the EA process. Some of these opportunities can be further developed
to draw environmental benefits to local communities within the project road corridor and
the sub-region. The EMP will identify such opportunities and develop a plan to
systematically harness any such benefit.
Monitoring Plan: In order to ensure that the proposed mitigatory measures have the
intended results and comply with GoI and World Bank requirements, an environmental
performance monitoring program will be included in the EMP with the following
suggested details:
Monitoring indicators to be measured for evaluating the performance of each
mitigatory measure. Indicators should include principles adopted for alignments,
applicable GoI engineering standards for road widening, etc)
Monitoring mechanisms and methodologies
Monitoring frequency
Monitoring locations
Expected cost of monitoring
Responsibility
Institutional Arrangements: Institutions/parties responsible for implementing mitigatory
measures and for monitoring their performances will be clearly identified along with any
legal instruments that define their obligations. Where necessary, mechanisms for
institutional co-ordination will be identified as often monitoring tends to involve more
than one institution.
Implementation Schedules: Timing, frequency and duration of mitigation measures with
links to overall implementation schedule of the project will be specified.
Reporting Procedures: Feedback mechanisms to inform the relevant parties on the
progress and effectiveness of the mitigatory measures and monitoring itself will be
specified. Guidelines on the type of information wanted and the presentation of feedback
information will also be highlighted.
Page 31 of 87
Cost Estimates: Implementation of mitigatory measures mentioned in the EMP will
involve an initial investment cost as well as recurrent costs. The EMP should include
costs estimates for each measure and also identify sources of funding.
3.2 Key Principles/Guidelines for Engineering Design
In order to avoid and minimize adverse environmental and social impacts at sub-project
level, the following principles are being adopted for alignment finalization:
1. The proposed right of way for bypasses will be 30 meters if the projected traffic is
less than 15,000 PCUs in 2030 and 45m if the traffic is more than 15,000 PCUs in
2030.
2. The alignment would as far as possible stay within the existing right of way in
forest areas. In case of exception, both options (within the existing right of way
and the alignment proposal with forest land diversion) would be analyzed before a
final decision is made.
3. The corridor of impact (CoI) for the project will broadly range between 15m to 18
m to fit the typical cross sections, space for drains, roadside furniture and utilities.
However, in specific locations, CoI of less than 15m will also be considered to
minimize the impact on properties. Whereas, in urban areas, if the available land
width is found more than the required to fit the cross section, entire available space
may be paved from building line to building line to facilitate parking etc.
4. Decision on bypasses and realignments is being taken based on a comparison of
options with or without the proposed change in design on a case to case basis.
More so, findings from the environmental and social screening report provide the basis
for developing engineering designs. In certain cases where results from the field
assessments are not duly factored into project drawings, ecological footprints that could
result from such proposed engineering designs are found to be significant. To eliminate
such complexities, Highway Engineers will work hand in hand with the respective
Environmental and Social Experts ensuring that proposed designs are environmentally,
socially and economically viable. Until the EIAs are publicly disclosed and approved,
engineering drawings would undergo a series of changes to incorporate all
recommendations from the environmental and social stand point.
3.3 Consultation and Disclosure Requirements
Consultation with affected people, subject/domain experts and NGOs in preparing the
EIA/EMP is critical for Category A projects. For all Category A projects/sub-pojects, the
project proponent is expected to consult project-affected groups and local
nongovernmental organizations (NGOs) about the project's environmental aspects and
take their views into account. The project proponent should initiate such consultations at
each stage of the project cycle. The disclosure of documents shall be as per
requirements of GoI and WB procedures.
Page 32 of 87
3.4 Integration of EMP into Bidding Documents
Sections relevant for the construction stage will be integrated into the Bid Documents.
More guidance has been provided in Annex. Contract documents will need to be
incorporated with clauses directly linked to the implementation of environmental
mnagement measures. Mechanisms such as linking the payment schedules to
implementation of the said clauses need to be explored and implemented, as
appropriate.
Page 33 of 87
Chapter 4
POTENTIAL ENVIRONMENTAL IMPACTS
Overall, the project is classified as environmental category A. This is based on the review
of findings from the preliminary and detailed screening exercises. The following sections
of the framework summarize possible environmental impacts that could arise and
presents possible ways of addressing them.
4.1 Potential Environmental Issues and Impacts
The proposed expansion of the project roads and associated rehabilitation works will
have varying levels of impacts on the surrounding environment – on natural and planted
forests, on lands with agricultural, cultural and other socioeconomic and religious values,
and to an extent on factors wildlife and wildlife habitats, particularly those located
outside the designated protected areas such as National Parks and Sanctuaries.
Observations during preliminary field visits, desk study and results from the screening
exercise identified that potential impacts could range from immediate to long term, could
be direct or indirect including induced development, reversible or irreversible, and or
cumulative as a result of interaction with other development activities ongoing in the
sub-region.
The screening exercises also identified the environmental policies and regulations that
are potentially triggered. Also, since most of the sub-projects serve as lifelines in the
backward areas, the findings also indicate an over-all positive project outcome that is
expected to be beneficial. However, the proposed expansion of the project roads and
associated rehabilitation works will also create some adverse environmental and social
impacts, particularly in project corridors involving realignments and bypasses beyond
existing right of way (ROW). The exact quantum and significance of the likely
environmental and social impacts will be determined after the completion of EIAs and
SIAs, which are currently under preparation.
The direct, indirect and induced adverse impacts resulting as a result of widening of the
project roads (Component 1) may cause adverse environmental impacts in the project
area, if not addressed properly. The proposed works may have adverse impacts on
reserved/protected forest areas through which the road corridors traverse, road-side
plantation, water bodies, local drainage, public water supply sources, material sources,
sensitive receptors, religious sites and common property resources located along the
road.
While no roads will be financed in ecologically sensitive habitats such as national parks,
tiger/elephant reserves and sanctuaries under this project, the presence of wildlife
habitats and/or crossings outside the protected environs in some cases has been
identified in the environment screening exercise. Further analysis/assessment for such
sub-projects, which include NH-234 in Karnataka and NH-200, 201 and 217 in Orissa will
determine the specific nature, magnitude and scale of such impacts.
Page 34 of 87
Diversion of Forest Lands
It is envisaged that engineering designs largely maintain road widening within the
existing ROW limiting extent to which new land will be diverted except in built up
stretches where realignments and bypasses are proposed as the most cost effective and
environmentally benign alternative.. Findings from field assessments show that in
majority of the roads, lands abutting the carriage way within the ROW and the Direct
Impact Zone are mostly forest lands except in built up areas. Forests are categorized as
protected forests or reserve forests. Construction works will involve removing trees in
the ROW and in specified locations for workers camps, temporal connecting roads,
temporary storage sheds for construction materials, temporal diversion of routes, etc.
Depending on expanse of contiguous area cleared, forest loss could affect soil
characteristics and soil stability increasing dust pollution and potential erosion. Where
roadside forests provide assist with connecting larger forests, tree removal could affect
its value as wildlife corridors.
Where road works involve bypasses or realigning existing carriageways, critical natural
habitats such as protected areas, wildlife sanctuaries and reserves, under private or
tribal ownership could be impacted. Such roads will need more robust planning and
design to avoid, minimize and manage adverse environmental impacts.
From the screening reports, estimates of forest land to be diverted range from 0.5 ha to
10 hectares. These sub-projects will be subjected to applicable forest regulatory
clearance as required by GoI and the concerned state governments. For stretches that
are in close proximity (within 10km) of wildlife sanctuaries, biodiversity assessment will
be carried in addition to results from environmental screening to ascertain potential
direct and indirect impact on wildlife particularly where charismatic fauna and
endangered species are involved.
Uptake of Agricultural Lands
In addition to uptake of forest lands, fertile agricultural lands could also be diverted. This
may put pressure on less arable lands and could lead to environmental degradation of
the area.
Impact on Wildlife
When project roads traverse close to natural forest reserves and wildlife sanctuaries (the
road itself would be outside designated protected areas), construction process could
increase noise levels, cause affect migration paths, impact availability and access to food
especially for obligate herbivores and carnivorous faunal species. In corridors where
surface water bodies usually used as watering holes by wildlife are affected, dependent
wildlife will be affected.
Transportation and hauling of material and increased vehicular activity within the road
corridor may introduce invasive species, increase noise and air pollution associated
destroy plants with conservation value. Extraction of raw material for construction such
as gravel, sand, etc outside designated locations could create further disturbance to the
Page 35 of 87
ecosystem by degrading habitat conditions. Also, one of the risks would be the possibility
of increased wildlife poaching during construction.
Extraction and Management of Input Materials
Road construction will involve use of materials such as aggregates, sand, earth and
water and other chemical inputs including bitumen, Grease, oil, petrol, kerosene and
other substance considered to hazardous to human health or the environment according
to the Management Storage and Import of Hazardous Chemicals (MSIHC) Rules of India.
Uncontrolled extraction practices such as river sand quarrying, water extraction from
both underground and ground sources, earth excavation could result in irreversible
effects including depressions that may demand huge restorative actions. Improper
disposal of construction material waste could affect local water sources and agricultural
lands with related health issues.
Road Topography
Topography of most of the road corridors are flat plains, undulating with mild slopes and
to a small degree, rolling terrains and mountainous with steep slopes. In Bihar, the flat
terrains affect drainage conditions with increased potential for flooding, overtopping and
soil erosion. Road works may thus involve raising the road to offset frequent
overtopping. For road works that will involve slope cutting, concerns will evolve around
increased potential for soil erosion, landslides especially during monsoonal seasons,
debris storage, management and disposal.
Demolition Exercise
Bridge shifting works can generate debris which can obstruct waterways if not properly
disposed.
Other Impacts
Increased traffic from upgraded roads may cause safety concerns for both road-users
and road-side residents, occupational health related risks faced by construction workers
and construction stage nuisances such as dust and noise. In towns with touristic sites
and potential medium to large scale industrial plants/hubs, new commercial and public
activities may lead to an increase in pressure on local and regional natural resources.
Potential long-term impacts could include changes in land use patterns (from agriculture,
natural habitats to real estate, or other non-farming purposes) and changes in
occupational patterns.
4.2 Positive Impacts/Project Benefits
On the positive side, strengthened human capital from enhanced habitation connectivity
and increased access to employment centers is important benefits of the project. Since
the project road development is expected to be largely limited to the existing RoW,
improvements will far outweigh the temporal disincentives to the surrounding
environment in the corridors.
Page 36 of 87
Over-all, the project is expected to have positive impacts in terms of providing better
connectivity and improved access to populations in less developed or remote areas to
more advanced socio-economic centers. Local businesses and inhabitants in the area of
influence of the project roads as well as users of the project roads will be direct
beneficiaries of the project. These people will have improved access to higher service
level highways and transport services. Benefit will also accrue from the savings in travel
time and transportation costs. Other expected positive outcomes of the project include
improved access to a larger number of economic opportunities, better health services,
facilities and higher levels of education, and improved road safety.
Page 37 of 87
Chapter 5
STAKEHOLDER CONSULTATION
Stakeholder consultations form a very crucial part of all development projects, including
infrastructure and are usually carried out as a continuous process through the project
cycle. Public and stakeholder consultations and workshops during the design and project
planning stages provide the medium for sharing information about the project objectives
and scope, alternative design options, and stakeholder perceptions regarding proposed
investment plans. Ensuring an open and transparent information exchange about the
project at this stage, lays a good foundation for an inclusive and participatory
implementation process.
In view of the scope of interventions giving reference to the GoI regulatory policies on
EIAs along with provisions under the Bank's safeguard requirements, the project is
generally categorized as A. It has triggered the World Bank O.P/B.P 4.01- Environmental
Assessment. For a category A operation, both the GoI EIA guidelines and the World
Bank‟s safeguards policies require comprehensive consultations with all key stakeholders
including communities residing in the project corridor particularly women, disabled,
youth; NGOs; civil society groups; road users; private sector; local traditional leaders,
district and state government officers involved in the project; and other categories of
stakeholders that may be peculiar to the area under consideration such as scheduled
castes, scheduled tribes, forest dwellers, etc.
Conforming to the GoI Right to Information Act, 2005 and the World Bank Consultation
and Disclosure Policy, and to meet the project‟s needs for an inclusive participatory
process during project planning, design, implementation, supervision and monitoring,
MORTH PIC with guidance and assistance from the World Bank will facilitate (public and
focused group) consultations/workshop plan for each project road that covers the
following key stages:
- Preliminary consultative session at the very early stages of the project design
when the first set of engineering designs are developed
- Second round of consultations on the engineering design once recommendations
from the first consultations have been considered in revised designs taking into
considerations concerns about bypasses, realignments, land acquisitions, forest
diversions, tribal forest land concerns
- When the draft EIA TORs are complete
- Public consultations on the draft EIAs with the respective SPCB (where an
Environmental Clearance is required)
- Once the final EIA are cleared for official release into the public domain
During the first sets of public discussions, the DPR/Feasibility Consultants will carry out a
series of stakeholder consultations in the project areas to present and to seek inputs and
Page 38 of 87
feedback on the project objectives, design options, activities plan, and to determine
stakeholder interest to participate in project activities.
Before finalizing the EIA reports, another round of consultations would be carried out to
ensure that all key stakeholders are well aware of the project, the potential impacts
(positive and negative) and mitigation measures, and to lay out a plan for participation
in monitoring, implementation and supervision/auditing. The active participatory
process would ensure that the local communities, ultra poor groups in the communities
and ethnic groups and women, in the project areas will not be worse off and that
benefits or positive effects are well distributed.
To ensure that consultations are useful to the affected groups, the client and the agency
conducting it, this case the DPR consultants, the consultants will ensure an environment
where participants, irrespective of social status, would be able to express their opinions
and preferences freely. The consultants will provide relevant material in a timely manner
prior to the consultations in a form and language that are comprehensible and accessible
to the groups that are participating in the consultations.
Over-all, the consultations would:
Learn about the community needs and preferences with respect to the project
objective to improve connectivity through widening and rehabilitating project
roads
Identify and agree on alignment options that have relatively lesser impact on
affected people
Discuss the environmental and social safeguard implications/impacts that might
be associated with the suggested alignment or bypass options, along with the
impact mitigation guidelines and measures adopted in the EMF
Where voluntary lands are involved, identify the donors
Discuss compensatory afforestation plans
Have the community identify grievance and redress mechanisms for resolving
project design and implementation concerns
Determine the main pillars of a communication/consultation strategy that will be
adopted throughout the project phases
Determine options for engaging local community and NGOs in the operation
Page 39 of 87
Chapter 6
INSTITUTIONAL ARRANGMENTS
FOR ENVIRONMENTAL MANAGEMENT
The Environment Management Framework needs to be applied and implemented at all
stages of the project. This requires an institutional mechanism to deal with various
processes and issues.
6.1 Project Implementation Structure
The over-all proposed project implementation structure is depicted in the following
diagram:
NHIIP-1 EMP Implementation Arrangements and Responsibilities
Project Management Consultant Cell (PMC) Environmental Officer -
ECO
Project Implementation Cell . Envtal
Coordinator/Nodal Officer
MORTH Regional Officer (RO)
Integrated Performance Auditor (IPA)
Environmental Monitoring Consultant
Project Implementation Unit --State Public Works Dept (PWD)
Environmental Officer/Forest Officer
Contractor at state level – Safety and Environmental Officer
Construction Supervision Consultant (CSC) –
Environmental Expert
NHIIP-1 Proposed EMP Implementation Arrangements and Responsibilities at the National, State and Project Level
rep
ort
ing
Mo
nit
ori
ng
&
Co
ntr
act
M
gt
Re
po
rtin
g
Ad
vice
De
cisi
on
De
cisi
on
Advice
Project Information
Re
po
rtin
g
Re
po
rtin
g
Re
po
rtin
g
Project Information
Within the institutional framework proposed for the project, preparation,
implementation, supervision and monitoring of environment functions, particularly the
Environment Management Plans (EMP), will be carried out at the three levels - national
Page 40 of 87
center, state level and the project/community level with an inbuilt mechanism for
coordinating activities at all levels.
Specific functions will be delegated to the Environmental Experts assigned to the MORTH
at the national center ( Project Implementation Cell), the National Highways wings of the
respective state Public Works Departments (Project Implementation Unit), Construction
Supervision Consultants, and the civil works engineering contractors, some Non-
Governmental Organizations (NGOs) and other local civil society bodies.
National Level
At the central level, the Project Implementation Cell within the MORTH will serve as a
facilitator, overseeing overall responsibilities spanning policy development, fund
disbursement, learning coordination and information sharing as well as monitoring and
evaluation. Specifically towards managing environmental issues, the PIC will contract a
Project Management Consultant (PMC) with a designated Environment Expert who will
provide advisory services to the MoRTH‟s (PIC) National Level Nodal Environmental
Officer.
The PMC Environment Officer will support PIC on critical issues and provide up to date
guidance and recommendations for effectively managing environment related project
activities at the state and project levels. The PMC EO will facilitate cross learning
between state PIUs and civil contractors and enhance coordinated reporting on progress
with implementation of the EMP. The PMC EO will liaise with the Social and engineering
Experts on the PMC to ensure a comprehensive and coordinated approach to the EMPs.
State Level
For each state, a Project Implementation Unit (PIU) will be created in the State (PWD)
with a multidisciplinary staff expertise in environment and social safeguards, project
management, monitoring and supervision, procurement and fiduciary issues.
Institutional structures for the Project Implementation Unit (PIU) may differ relatively to
reflect the unique requirements of the state.
The Environment and/ Forest Officer (E/FO) designated to the PIU will over-see and co-
ordinate various aspects related to the environment management as envisaged under
each sub-project. The E/FO will provide specific guidance on policy and regulatory
requirements specific to the state and local setting to the DPR consultants. The E/FO will
also provide guidance on the process and steps for obtaining any requisite clearances.
The Environment /Forest Officers will support in terms of building PIU team capacity for
incorporating environmental concerns in design, implementation and operation of the
sub-project. The E/FO will collaborate strongly with counterpart social and engineering
specialist on the PIU as well as the Construction Supervision consultant and will report to
the Project Management Consultant through the PIC. Where there are multiple sub-
project roads within one state, separate sub- PIUs will be established within the State
PWD to reduce overburdening with implementing multiple sub-projects.
Together with the Social Expert on the PIU, the Environment/Forest Officer will :
Page 41 of 87
ensure integration of the EIA and resulting EMP into the sub-project design and
implementation plans (contract documents)
monitor implementation of the mitigation measures by the Contractors
assist the engineers at site by providing appropriate environmental advice, and
developing/revising environmental mitigation measures for the sub-projects
assist the PIU to carry out participatory consultation during planning, design and
implementation of sub-project
document experiences associated with and lessons learned from environmental
mitigation and prepare useful training materials for both internal and external
capacity building
prepare regular periodic progress reports on the implementation of the EMP
throughout project implementation
Project Level
Actual civil works and reconstruction of the project roads will be carried out by the
Construction Consultants/Contractors under the direct supervision of Construction
Supervision Consultants. The Environmental Expert on the Contractor team will ensure
strict compliance with the environmental contractual clauses and will report on progress
or challenges to the Construction Supervisory team.
6.2 Monitoring Arrangements for Effective Environmental Management
In order to ensure that the proposed mitigatory measures have the intended results and
complies with GoI and World Bank requirements, an environmental performance
monitoring program would be carried out. This could be achieved through daily and more
sequenced monitoring by the Environment Experts on the contractor, CSC and PMC
respectively.
Construction Phase Monitoring
In selecting the monitoring parameters, care will be taken to choose parameters
according to the characteristic features of the existing environmental baseline conditions
ensuring that parameters are both cost effective and viable for identifying changes that
deviate from predetermined impacts. The plan will be designed on the premise that civil
works and related activities will have relatively less significant effects on existing
conditions and residual impacts will be controlled using the EMP. Results from the
monitoring the environmental parameters will be compared to MOEF and CPCB/SPCB
legal limits.
Operational Phase Monitoring
It is envisaged that operation of the reconstructed highways will present fewer
environmental impacts compared to the construction phase. Monitoring indicators for the
operation phase will be based on feedback from local surveys and from planned social
responsibility/peripheral development activities. Monitoring during the operational phase
Page 42 of 87
will be carried out more frequently especially during the first year of operation to ensure
that any complaints about the road operation is readily captured and resolved.
Auditing
A Third Party Audit will review the effectiveness of the implementation of environmental
management plan. Primarily the auditing exercise will determine whether the sub-
projects comply with all environmental regulatory performance standards in addition to
any GoI stipulated highway construction and operation standards. Auditing process will
test the accuracy of reports from field assessments and cost effectiveness of
management measures. It entails a systematic, documented and periodic review of
project implementation and could be a very useful tool to improve project management
performance.
Instituted environmental audits at the project road level and at the overall operation
level is critical for an operation of this dimension. In this regard, the operation will
incorporate a series of independent verification and audit mechanisms both at design
and implementation phases. At the preparation phase, the project will launch a one-
time independent technical audit of the EMF and the EIAs. During the construction
phase, NHIIP will contract chartered accounting firms to conduct bi-annual or annual
performance audit that will include financial management, procurement and safeguard
compliance. As Integrated Environmental and Social Performance Auditor, the firm(s)
will review all sub-project documents and visit a representative sample of project roads
for validation of safeguards compliance. These will complement system enhancements
that are aimed at monitoring efficiency and quality of expenditure within the NHIIP-1
project.
With respect to environmental issues, the performance audits will:
collect, analyze and interpret monitoring results to detect changes related to
implementation and
operation of specific activities
verify if monitoring parameters are in compliance with national set standards
compare the predicted impacts with actual impacts and evaluate the accuracy of
predictions in view of proposed mitigation measures
evaluate the effectiveness of implementation of the EMP
loop back into the EMP, any short comings identified from the auditing
identify and report if there is non-compliance with the EMP and where applicable
identify replicable lessons from the monitoring
To facilitate auditing process, auditors may first develop a structured questionnaire
based on the EMP and this can be administered to state officers involved in the project,
construction engineers, PAP, etc. Depending on specific characteristics of the sub-project
road, audits can be carried out at regular intervals or on ad hoc basis or when mitigation
is not carried out as defined by the EMP leading to public concern.
Page 43 of 87
6.3 Measures to Introduce/Strengthen Institutional Capacity
To meet the multiple and varied nature of environment challenges that the project
poses, capacity needs will be built at the central, state and project levels responsible for
planning and designing and implementing the sub-projects and the EMPs. In this
respect, NHIIP-1 will also initiate some key activities with MORTH and the participating
states as enumerated below:
a) Capacity Building and Mainstreaming Environmental Dimensions in the Technical
Standards: The existing limited implementation capacity can affect environmental
outcomes despite safeguard provisions. This dearth in capacity will be addressed
through enhanced technical assistance and training, and sharing of environmental
and social lessons from similar national highway projects. Technical assistance
component (TA) and training on the management of key environmental issues of
highway roads development program, such as planning, design and/or
construction of roads in ecologically sensitive areas; drainage design and
management; slopes and debris management in hilly terrain and materials
management, will be provided to the engineers and contractors. The NHIIP-1 may
provide assistance in revising IRC codes on highway construction. This can also
include a manual towards creation of „green highways‟.
b) Integration of Environmental Aspects in the Operations Manual: The Operations
Manual (OM) of NHIIP ( a key document that lays out the detailed procedures)
will be prepared to reflect the environmental management procedure that will
govern the operation
c) Integration of EHS requirements in the Standard Bidding Document:
Inappropriate construction practices can cause adverse environmental, health and
safety (EHS) impacts, especially from the improper scheduling of works, unsafe
handling of hazardous materials and haphazard dumping of construction wastes
(including earth cuts in hills). To ensure improved environmental management
during the construction stage, a section clearly specifying preventive and
mitigation measures to be taken by the contractor will be introduced in the
Standard Bidding Document (SBD). Compliance with these specifications will be
supervised as part of project technical supervision.
6.4 EMP Implementation Budget
In view of the environmental management measures suggested above and factoring in
the limited implementation capacity of the state PIUs, necessary budgetary provisions
should be made for different sub-projects. Tentative budget for each of the sub-projects
should include environmental management cost, monitoring cost.
6.5 Environment Management – Additional Guidance/Tools
Page 44 of 87
In addition to the above tools, many aspects of the environmental codes of practice
developed by the National Rural Roads Development Agency, Ministry of Rural
Development are very relevant to the operation. Annex provides a preliminary list of the
applicable codes of practice from the National Rural Development Agency‟s ECoP.
The EMF adopts and applies the India Environmental Codes of Practice for rural roads.
Even though the ECoPs are designed for rural roads, these are useful and provide
technical solutions that incorporate principles of environmentally sound and sustainable
planning and design for expanding and rehabilitating the project highways. The ECOP
provides appropriate guidance useful in enhancing positive impacts and to avoid,
minimize and mitigate adverse impacts.
The activity-specific codes address design, construction and operation-stage issues
associated with: (a) site preparation; (b) construction camps and plant sites; (c) borrow
and quarry areas; (d) water management; (e) slope stability and erosion control
(including introduction of bio-engineering practices); (f) waste management; (g)
drainage; (h) public and workers health and safety; (i) cultural properties (including
handling of „chance-find‟); and (j) tree plantation.
Page 45 of 87
ANNEXURES
Page 46 of 87
Annex 1
Generic Terms of Reference for Conducting an EIA
Environment Assessment (EA) is a decision support mechanism to ensure that the
project design and implementation are environmentally sound and sustainable. During
the preparation phase, the objective of the EA is to provide inputs to the selection of
sub-projects, feasibility study; preliminary and detailed design as well as assist
development of a holistic development of the project package. During the
implementation phase, environmental management plans (developed as a part of the EA
during the preparation phase) are to be used for executing the environmental mitigation,
enhancement and monitoring measures.
Objectives of EA
In the preparation phase, the EA shall achieve the following objectives:
1. Identify and analyze upstream environmental issues that may affect the project
and the sector.
2. Establish the environmental baseline in the study area, and identify any significant
environmental issues (direct/indirect/induced/cumulative)
3. Assess impacts of the project, and provide for measures to address the adverse
impacts by the provision of the requisite avoidance, mitigation and compensation
measures
4. Integrate the environmental issues in the project planning and design; and
5. Develop appropriate management plans for implementing, monitoring and
reporting of the suggested environmental mitigation and enhancement measures.
The environmental assessment studies and reporting requirements to be undertaken
under these TOR must conform to the GoI/GoB regulations and the Bank guidelines.
Description of the Project
(Include description of the project; covering geographical location, type of development
envisaged, including a description of project activities. Also include current status of the
project. Provide brief information on any other study already completed/on-going or
proposed) ... to be added by Client.
Scope of Work
The EA comprises the following 3 components: (i) Environmental screening for the entire
project; (ii) Environmental Assessment (EA) for the individual project/sub-projects, as
required; and (c) Environmental Management Plans (EMPs) for the individual
project/sub-projects.
The following section gives the detailed scope of work in each of these stages.
Page 47 of 87
Inception
The Consultants shall use the inception period to familiarize with the project details. The
Consultants shall recognize that the remaining aspects of the project, such as
engineering and social, would be studied in parallel, and it is important for all these
aspects are integrated into the final project design to facilitate their successful project
implementation. The Consultants should also recognize that due care and diligence
planned during the inception stage helps in improving the timing and quality of the EA
reports.
During the inception period the Consultants shall: (a) study the project information to
appreciate the context within which the EA has to be carried-out; (b) identify the sources
of secondary information on the project, on similar projects and on the project area; (c)
carry out a reconnaissance survey and (d) undertake preliminary consultations with
selected stakeholders.
Following the site visits and stakeholder consultations, as well as a review of the
conditions of contract with the Client, the consultant shall analyse the adequacy of the
allocated man-power, time and budget and shall clearly bring out deviations, if any. The
Consultant shall study the various available surveys, techniques, models and software in
order to determine what would be the most appropriate in the context of this project.
The Consultant shall interact with the engineering and social consultants to determine
how the EA work fits into the over-all project preparation cycle; how overlapping areas
are to be jointly addressed; and to appropriately plan the timing of the deliverables of
the EA process. These shall be succinctly documented in the Inception Report.
Environmental Screening
Consultants shall summarize the known sub-project/s into different categories that relate
to the magnitude potential environmental impacts. During such categorization,
consideration shall be paid to: (i) location of sub-project with respect to environmentally
sensitive areas; and (ii) volume, nature and technology of construction. The screening
parameters should be such that their identification and measurement is easy, and does
not involve detailed studies. The screening criteria shall also contain exclusion criteria,
for sub-projects, which should not be taken up due to potential significant environmental
impacts that cannot be mitigated (including, but not limited to, permanent obstruction to
wildlife corridors, or opening up increased access to threatened biodiversity resource
hotspots, or construction on top of eroded and vulnerable flood embankments).
Environmental Scoping
Based on result of the environmental screening exercise, consultants shall suggest the
scope of Environmental Assessment to be undertaken. It shall include a listing of other
environment issues that do not deserve a detailed examination in the project EA
(covering, for example, induced impacts that may be outside the purview of the client)
along with a justification. The scoping needs to identify and describe the specific
Page 48 of 87
deviations or inclusions vis-à-vis the EA ToR provided, if any, along with a justification;
modify this ToR for the sub-project EA, if required; and recommend studies that need to
be conducted in parallel but are outside the EA process.
Baseline
All regionally or nationally recognized environmental resources and features within the
project‟s influence area shall be clearly identified, and studied in relation to activities
proposed under the project. These will include all protected areas (such as national
parks, wildlife sanctuaries, reserved forests, RAMSAR sites, biosphere reserves,
wilderness zones), unprotected and community forests and forest patches, wetlands of
local/regional importance not yet notified, rivers, rivulets and other surface water bodies.
and sensitive environmental features such as wildlife corridors, biodiversity hotspots,
meandering rivers, flood prone areas, areas of severe river erosion, flood embankments
(some of which are also used as roads). Consultants shall consolidate all this information
in a map of adequate scale.
Stakeholder Identification and Consultation
Consultation with the stakeholders shall be used to improve the plan and design of the
project rather than merely having project information dissemination sessions. The
consultants shall carry out consultations with Experts, NGOs, concerned Government
Agencies and other stakeholders to: (a) collect baseline information; (b) obtain a better
understanding of the potential impacts; (c) appreciate the perspectives/concerns of the
stakeholders; and (d) secure their active involvement during subsequent stages of the
project.
Consultations shall be preceded by a systematic stakeholder analysis, which would: (a)
identify the individual or stakeholder groups relevant to the project and to environmental
issues; (b) include expert opinion and inputs; (c) determine the nature and scope of
consultation with each type of stakeholders; and (d) determine the tools to be used in
contacting and consulting each type of stakeholder group. A systematic consultation plan
with attendant schedules will be prepared for subsequent stages of project preparation
as well as implementation and operation, as required.
Identification of Relevant Macro/Regional Level Environmental Issues
Consultants shall determine the Valued Environment Components (VECs) considering the
baseline information (from both secondary and primary sources), the preliminary
understanding of the activities proposed in the project and, most importantly, the
stakeholder (and expert) consultations, which would need to be carefully documented.
Use of iterative Delphi techniques is recommended.
Based on the identification of VECs, consultants shall identify information gaps to be
filled, and conduct additional baseline surveys, including primary surveys. The
consultants shall conduct a preliminary analysis of the nature, scale and magnitude of
the impacts that the project is likely to cause on the environment, especially on the
Page 49 of 87
identified VECs, and classify the same using established methods. For the negative
impacts identified, alternative mitigation/management options shall be examined, and
the most appropriate strategy/technique should be suggested. The preliminary
assessment should clearly identify aspects where the consultants shall also analyse
indirect and cumulative impacts during all phases and activities of the project. For the
positive measures identified, alternative and preferred enhancement measures shall be
proposed.
Environmental Assessment
The Consultants shall undertake necessary impact analysis on the basis of primary and
secondary information and outputs from the stakeholder consultation process.
In the cases of very significant environmental losses or benefits, the consultants shall
estimate the economic/financial costs of environment damage and the
economic/financial benefits the project is likely to cause. In the cases, the impacts or
benefits are not too significant, qualitative methods could be used. In addition, wherever
economic and financial costs of the environmental impacts cannot be satisfactorily
estimated, or in the cases of significant irreversible environmental impacts, the
consultants shall make recommendations to avoid generating such impacts.
Environmental Management Plan
The consultants shall prepare an EMP to address identified planning, design, construction
and operation stage issues. For each issue, the consultants shall prepare a menu of
alternative avoidance, mitigation, compensation, enhancement and/or mitigation
measures, as required/necessary. Consultants shall provide robust estimates of costs for
environmental management measures. These costs shall be verified for common works
items in line with the rate analysis for other works. The consultants shall organize
consultations with line departments and will the finalize the EMP.
Environmental Inputs to Feasibility Study and Preliminary Project Design
The EA consultants shall make design recommendations, related to alignment, cross-
sections, construction material use, mitigation and enhancement measures. The EA
consultants shall interact regularly with the Client and familiarize themselves with the
project‟s over-all feasibility analyses models, so that the EA inputs are in conformity to
the needs of the over-all feasibility study.
Capacity Building and Training Plan Preparation
Based on the preliminary findings of the environmental screening, stakeholder
consultations and institutional analysis of the implementing agency‟s capacity to manage
environmental issues, the consultants shall prepare a Capacity Building Plan to
mainstream environmental management in the implementing agency‟s activities by the
end of project implementation period. Earmarking staff for environmental management
and improving their skill-sets would be simultaneously pursued during project
Page 50 of 87
preparation and implementation. In addition, recommendations should be made
concerning any changes to guidelines, standards and regulations, which would improve
medium and long term environmental management in the line departments works.
A detailed training plan shall be prepared to develop and strengthen environmental
capacities of the client and other associated agencies/departments. The strategy should
include a mix of hands-on training for key staff involved in project preparation, site visits
to similar projects, and whenever required, full-fledged academic programs on
environmental management at well-recognized institutions.
The consultants shall conduct orientation training for the key client, early in the
assignment. Periodic training at various levels should continue during project preparation
to ensure that the knowledge, skills and perspectives gained during the EA assignment
are transferred to the Client and are utilized effectively during project implementation.
Mechanisms for improved co-ordination between Client and Line departments
The consultants shall examine the various options available for improved and timely co-
ordination between various state government departments. These could take the form of
written MoUs for specific activities, apex co-ordination committee of top bureaucrats, or
any such mechanism that can be effective in reducing delays in ancillary activities such
as, but not limited to, shifting of utilities and obtaining required regulatory permissions.
Co-ordination among Engineering, Social, Environment and Other Studies
The consultants, with assistance from the Client, shall establish a strong co-ordination
with the other project-preparation studies – engineering, social and/or institutional
development. The consultants shall keep in mind the specific requirements of the project
in general, and the engineering/design studies in particular, and shall plan their outputs
accordingly. It is recommended that some of the consultation sessions may be organised
in co-ordination with the social and engineering consultants, as feasible, and when the
stakeholders consulted are the same.
The consultant shall review the contract documents – technical specifications, and rate
analysis, to ensure that there are minimal conflicts between the EMP stipulations and
specifications governing the execution of works under the project.
Public Disclosure
The consultants shall prepare a non-technical EA summary report for public disclosure
and will provide support to the client in meeting the disclosure requirements, which at
the minimum shall meet the World Bank‟s policy on Public Disclosure. The consultants
will prepare a plan for in-country disclosure, specifying the timing and locations;
translate the key documents (including executive summary of EA/EMP) in local
language; draft the newspaper announcements for disclosure; and help the client to
place all the EA reports in the client‟s website.
Page 51 of 87
Consultant’s Inputs
The Consultants are free to employ resources as they see fit. Additional expertise, shall
be provided as demanded by the context of the project. The consultants are encouraged
to visit the project area and familiarize themselves, at their own cost, before submitting
the proposal; and propose an adequate number and skill-set for the senior specialists
and technical support staff for the EA assignment. Further, the consultant will allocate
adequate number of field surveyors, distinct from the technical support staff, to
complete the study in time. Timing is an important essence for any EA study, which shall
be closely co-ordinated with the works of the engineering and social teams,
simultaneously involved in preparation of the project.
The consultants shall provide for all tools, models, software, hardware and supplies, as
required to complete the assignment satisfactorily. These should be widely recognized or
accepted. Any new model or tool or software employed should be field-tested before use
or the purpose of this EA.
The consultants shall make formal presentations, co-ordinated by the client, at key
milestones on the (a) proposed work plan after submitting the Inception Report; (b)
recommendations from the environmental screening; and (c) EA findings, design and
EMP recommendations. All supporting information gathered by the consultant in
undertaking these terms of reference would be made available to the client.
Consultant’s Outputs
The consultant is expected to provide the following outputs, as per the schedule given in
the ToR. The Consultants are expected to allocate resources, such as for surveys,
keeping this output schedule in mind.
Page 52 of 87
Annex 2
Guidance Note for Incorporation of Environment
Management Plan into Contract Documents
The purpose of the annex is to provide some guidance on the integration of the EMP/
GEMP into the contract documents of a sub-project.
Environment requirements in the pre-bid documents
1. The project implementing agency, i.e. PIU / the Line Departments issue the pre-bid
documents to shortlist a few contractors, based on their expression of interest and
capability. While details on environmental requirements are really not required in the
pre-bid stage, it is useful to mention that the contractor is expected to have good
environmental management capability or experience.
Incorporating EMP in the Bid Document
2. The project implementing agency (line department) issues the bid documents to the
pre-qualified contractors. There are two kinds of bid documents, for International
Competitive Bids (ICB) and National Competitive Bids (NCB). In Bank projects, these
documents are prepared based on templates (separate for ICB and NCB) provided by
the Bank. The ICB documents are based on the FIDIC (i.e., an acronym for the
International Institute of Consulting Engineers) guidelines, while the NCB is closer to
the national contracting procedures, i.e. the Central PWD contract documents in
India. The bid documents contain separate volumes. For instance, a typical ICB
document contains:(i) General Conditions of Contract, which is based on the FIDIC;
(ii) Technical Specifications, which is based on the applicable specifications in India
for similar infrastructure related works; (iii) Bill of Quantities and (iv) Drawings.
3. The EMP parts/sections should be included in the relevant locations of the bid
documents in the following way:
Mitigation/enhancement measures & monitoring requirements tables
The cross-reference to these tables should be included in the “conditions of
particular application (COPA)”, which is a part of the General Conditions of
Contract (e.g. Section IV, Item 19.1 of the ICB). As a standard practice, there is
an over-all reference to the laws that have to be followed in this section/item.
The relevant laws need to be mentioned here. In addition, the adherence to the
mitigation/enhancement measures and table on monitoring requirements
should be included. The two tables will have to be added as Annexes or the
entire EMP (without cost and drawings) as a whole should be attached. Either
the Annexes or the appropriate section in the EMP should be cross-referred in
the description of this item.
Modifications/additions to the technical specifications
Page 53 of 87
Due to the mitigation/enhancement measures included in the EMP, there may
be (a) additions/alterations required to the applicable specifications and/or (b)
there may be a need to add new specification/s. These are to be referred in the
section on “Supplementary Specifications” in the Technical Specifications
Volume of the bid document. Generally, the GoI applicable specifications are
already referred/listed and are not repeated in the bid documents. However,
changes and additions to these specifications are made through the inclusion of
a section “Supplementary Specifications.” This section should also include
additional technical specifications related to the EMP or should provide a cross-
reference to the specific section of the EMP.
Cost table
All the items in the EMP cost table relevant to the contractor have to be
referred in the Bill of Quantities (BoQ) table, which is a separate volume of the
bid documents. It is to be noted that the BoQ table in the bid document
includes the various tasks to be done by the contractor under different
categories. Against each task, the contractor will have to indicate a unit rate
while completing the bid documents.
Drawings
All EMP drawings are to be reflected in the „Drawings‟ volume of the Bid
document. If the drawings are included in the EMP, then a cross-reference
should be provided in the Drawings Volume.
Developing the EMP to suit the bid/contract document
4. As one of the intentions is to integrate the EMP requirements into the bid
documents/contract Agreement, the EMP should be developed keeping the following
in mind:
a. Mitigation/enhancement measures: In the Mitigation/Enhancement Measure
table, the text describing each measure should not include/repeat what is already
covered under the technical specification/s, and this should only be cross-
referred. The text should be short, clear and succinct. The description should
focus on “what” and “where” of the mitigation / enhancement measure as the
“how” of the measure is covered under the specification.
b. Monitoring requirements table: There are certain monitoring requirements for the
contractor. While developing the Monitoring Requirement table, those that pertain
to the contractor should be clearly mentioned.
c. Technical specifications: The modifications to the specifications and the additional
specifications should be separately listed. These should be included as Annexure
in the EMP. The (added or modified) technical specifications should be adequately
detailed to avoid problems (including that of interpretations) at site.
d. Drawings: The modifications to the drawings and the additional drawings should
be included as Annexure in the EMP. It is important to note that all drawings
Page 54 of 87
included/ added should be “execution drawings” detailed as per requirement of
the particular item so as to execute at site with adequate quality control and
workmanship. Also, it is important to note that the quality of BoQ [or cost
estimate] and technical specifications part of the contract document depends on
the degree of detailing in the drawings.
e. Cost table: The items pertaining to the contractor should be clearly separated
from the expenditures that are to be incurred by the project implementing
agency, supervision consultant and/or any other agency/organization.
f. Timing for finalizing EMP: It is best to finalize the EMP before the finalizing the bid
documents. This is required to fully reflect the sections of the EMP relevant to the
contractor in the bid document and to ensure its proper integration.
Other Notes
Once the completed bids have been received from prospective contractors, the project
implementing agency takes a decision based on the costs and the technical merit of the
bids. Following the decision, the implementing agency and the chosen contractor sign
and counter-sign the completed bid documents. It becomes the contract agreement
thereafter. If issues have been missed in the bid documents, it cannot be amended at
the time of signing the contract agreement stage unless there is a really strong
justification for the same. If there is an EMP cost item that is not reflected in the BoQ of
the signed contract agreement, the supervision consultant/engineer may issue a
variation order, if such case has merit. Contractor will quote a rate and the task gets
done. This issue of variation orders is a standard practice and can be used, if found
necessary. However, the intent of the good contracting practices should be to minimize
variation orders and therefore EMP should be carefully prepared and integrated in the bid
document.
Page 55 of 87
Annex 3
Detailed Environment Screening Guidance Note
A. Purpose/Objectives of Environment Screening
The environmental screening exercise is undertaken to determine the key environmental
issues/concerns and the nature and magnitude of the potential environmental impacts
that are likely to arise on account of proposed project/sub-project interventions. The
major or key environmental issues to be identified will be determined by the type,
location, sensitivity and scale of the project/sub-project. The results/findings from this
exercise are/will be used to determine:
- the extent and type of Environmental (Impact) Assessment requirement
- the environmental category of the project/sub-project
The screening result will also be an important input for analyzing the „feasibility‟ of the
project/sub-project along with engineering/economics and social criteria.
B. Environmental Screening - Report Structure
The table of contents/presentation structure of the Environment Screening Report has
been mentioned below:
Table of Contents
Executive Summary
Chapter 1: Introduction
Project Description
Project Proponent
Description of the sub-project
(including its location, proposed start and end points, regional setting, scale and
size)
Over-view of major key sub-project activities
Need for the sub-project
Expected benefits from the sub-project
Various studies/reports being prepared for the project and how the environment
screening study relates to/feeds into the over-all project preparation
Chapter 2: Methodology Adopted for Environment Screening Exercise
Purpose/Objectives of the Environment Screening Exercise
Methodology (step-by-step process) adopted for Environment Screening Exercise
Page 56 of 87
Project Influence Area (mention the direct and indirect spatial zone considered
for the environment screening study)
Types and sources of data collection
Weightage/ranking system used (kindly refer annex 1)
Data gaps/constraints, if any
Structure of the Environment Screening Report
Chapter 3: Baseline Environmental Conditions
Natural Environment
Over-all environmental setting of the project (including topography)
Natural resource availability
Natural hazards and vulnerability of the sub-project area
Air Quality
Water availability and quality (include both surface and ground water sources)
Drainage conditions/issues
Slope stability (soil type/s; erosion; landslide/landslip problems, if any)
Visual resources (if any)
Biological Environment
Protected Natural Habitats
(Biosphere Reserves; National Parks and Sanctuaries)
Wildlife Habitats (outside designated protected areas) (including bird habitats,
aquatic habitats, as relevant)
Presence of Forest (Reserved, Protected or of any other category)
Flora/vegetation (general)
(include a broad estimate of trees (no.) that may get affected)
Presence of vulnerable, threatened and/or endangered species of flora and
fauna, if any
Physical and Socio-economic Environment
Land-use
Socio-economic characteristics of the project influence area
(including transportation network; existing economic/ employment base)
Cultural resources
(archeological heritage; religious structures; local built heritage and art
forms)
Page 57 of 87
Safety
Presence of sensitive receptors such as schools/colleges/health
centers/hospitals
Local level features and issues
(features such as presence of mandis/markets/haats or pastures and issues
like noise, vibration, congestion, waste dumping along the road, presence of
contaminated sites)
Chapter 4: Stakeholder Consultation
Definition of stakeholder
Types/categories of stakeholders consulted for the Feasibility/Screening studies
Details about the consultations carried out
Provide summary in the chapter and supporting details in the annex.
In the summary, kindly mention when, where, how many people attended,
key topics discussed and information shared.
Clearly list out findings including areas/issues that are of concern to the
stakeholders and need attention.
Chapter 5: Regulatory and Institutional Regime
Environmental policies and their implications/application in the sub-project
context
Environmental acts and their implications/application in the sub-project context
Environmental categorization
Inter-national/national conventions and their implications/application in the sub-
project context
Environmental permits/approvals that will be required for the sub-project (include
specific local requirements, if any)
Existing institutional arrangements/set-up (both in terms of environmental
regulatory agencies and project proponent set-up)
Chapter 6: Assessment of Key Environmental Impacts
Link-up existing environmental conditions with proposed project intervention/s
and identify/assess the potential environmental issues/impacts on natural,
biological and physical environmental attributes that may result in this process.
Look at the key issues that may result purely on account of proposed project
intervention/s (such as safety issues; drainage alterations)
Page 58 of 87
Analyze/propose alternative options that can avoid and/or reduce the identified
potential impacts
Chapter 7: Findings/Recommendations of Environmental Screening Exercise
Summary of results (weightage) from the environment screening exercise
Key issues/concerns identified
Summary of key benefits from the sub-project/project intervention
Key recommendations from the stakeholder consultation exercise
Summary - opportunities and constraints at the sub-project level
Scoping (focus) of the EA
(mention specific areas/aspects that need to be studied in detail)
Recommendation(s)/conclusion
References
Annexure/s
Names and contact details of key staff involved in the Feasibility (including
Environment and Social Screening exercise)
Stakeholder consultation details
Details of the data collected
Note
This is a typical or generic reporting structure and so kindly do include any specific
environmental feature/issue that is unique to the sub-project and has not been
mentioned here. This can/should also include any specific local regulatory
requirement.
Please use the „weightage matrix‟ provided in Annex 1 and format for presenting
results given in Annex 2. This will help in making a more objective comparison
between various sub-projects at the central level. The environmental sensitivity or
ranking will clearly emerge through this and will influence decision-making at the
over-all project level. However, for meaningful and factual analysis at the central
level, consultants must ensure that the information is clearly captured/presented in
the Environmental Screening Report, including a clear mention about data
gaps/constraints, if any. Not doing so can otherwise lead to erroneous decisions and
affect project planning and delivery at a later date, requiring mid-course correction.
An objective screening process is an attempt to avoid/minimize such unwarranted
situation/s.
Kindly ensure that any map/s, cross-section/s and photographs provided in the
report are legible and correctly labeled.
Page 59 of 87
Environment Screening Methodology – Tabulating Screening Results
Use the format given below to tabulate the result of the environmental screening
exercise. It will provide inputs for the „feasibility study‟ and will give direction to the
„scoping exercise‟ for the EIA.
1. Natural Environment
S. No. Environmental Attribute Total Weight Score
1 Topography 4
2 Vulnerability to natural hazards 4
3 Surface water resources 5
4 Drainage Conditions 5
5 Ground water resources 4
6 Materials Availability 4
7 Soil Erosion 4
Total 30
2. Biological Environment
S. No. Environmental Attribute Total Weight Score
1 Designated Protected Areas 10
2 Wildlife habitat/s (outside designated PAs) 6
3 Migratory route/crossing of wild animals
and birds (outside designated PAs) 6
4 Reserved Forests (RFs) 5
5 Protected or Other Forest/s 5
6 Green tunnels 4
7 Road side trees 4
Total 40
Page 60 of 87
3. Physical and Socio-economic Environment
S. No. Environmental Attribute Total Weight Score
1 Settlements 5
2 Sensitive Receptors 5
3 Drinking water sources 4
4 Religious Structures 4
5 Cultural Properties 4
6 Market Places 4
7 Common Property Resources* 4
Total 30 -
Page 61 of 87
Annex 4
Brief Description of Short-Listed Project Roads
(based on screening results)
NH
No. State
Length
(km)
Proposed
Bypass Relevant Features of Project Corridor
98 Bihar 117.49 1
No significant impact3 on the natural environment
expected. Potential drainage and erosion
conditions and issues related to the floodplains
detected. Proposed bypass. Road expansion will
affect roadside plantations - 6100 trees. Water
bodies in close proximity with potential flooding
and sedimentation concerns. Need for and
location of bypass being reviewed with PAPs.
104 Bihar 166.16 7
No significant impacts on natural environment
expected if construction activities are kept within
the ROW and if bypass options are dropped.
Similar to NH 30A, hydrological conditions are of
concern due to potential flooding and overtopping
and sedimentation. Models of the critical
stretches vulnerable to overtopping and
sedimentation will be factored into project design.
Forest diversion.
106 Bihar 106.00 0
Perceived environmental impacts are not
significant. Due to potential overtopping
concerns, road will be raised 1.5 to improve
drainage conditions. This engineering procedure
may alter the hydrological/flow pattern in the
area of interest. About 4000 trees are expected
to be affected
30A Bihar 69.00 2
The road passes through two districts and four
main towns/villages. The topography is mainly
flat plains with subsequent vulnerability to
flooding, drainage and erosion issues. As part of
civil works, 14 bridges will be shifted. The road is
abutted by protected forests and green tunnels.
About 1815 of roadside trees will likely be
affected as a result of the road widening Green
tunnels No significant impacts on natural and
biological environment expected.
3 When an impact is described as having no significance on the environment, it means that the impact is physically removed in space and time from the environment or that the impact is so small that it cannot be measured
Page 62 of 87
NH
No. State
Length
(km)
Proposed
Bypass Relevant Features of Project Corridor
234
Karnataka
(Madhughiri
-AP border
171.21 4
Moderate significant impact on the natural
environment. Bypass strongly advocated for to
limit conversion of land in the settled locations.
Communities advocating for bypass. About 14 km
of the road in various stretches within the
corridor run proximate to five Reserved Forests
(RF): Kurudi; Narasihma Devara Betta; Alamgiri;
Kallur; and the Srinivaspur. Of the five RF only
Narasihma Devara Betta RF could be affected
from the road widening with potential diversion of
about 0.37 ha of the reserve. Two protected
areas are located within a 15km radius of the
road: Jayamangali Black Buck Conservation
reserve (11.5 km aerial distance) and the
Kaundiniya Wildlife Sanctuary situated in the
Chitoor district of Andra Pradesh (2.6km aerial
distance). The third PA is the Bennerghatta
National Park located about 71 km from the road.
The corridor terrain is largely hilly with sections
of rolling and flat terrain
About 4000 trees are likely to be affected.
234
Karnataka
(Mangalore-
Belur)
129.4 0
The road is abutted by five reserve forests all
within 15 km radius in two forest divisions of
Mangalore and Chikamagalur: Mundaje Kap,
Dharmasthala-Mundaje, and the Charmudi
Kanapadi, Balur and Gonibidur at various
stretches totalling 28 km. Except for the
Chamrudi Kanapadi and the Balur RF which are
likely to affected with potential conversion of 2.2
ha and 2.73 ha respectively, remaining 3 RF will
not affected in terms of forest diversions.
Also within 15 radius is the Kudremukh national
Park, a Protected area of both national and
international significance. The park is the second
largest wildlife protected area in the Western
Ghats. It harbours tigers and is recognized under
the Global Tiger Conservation Priority-1 with
WCS. Two other charismatic endangered
mammals are located in the park – Leopard and
Wild Dog with a large supporting base of other
endangered mammals. The road has two
proximate points with the park boundary, 3.2 km
and 8 km respectively. Wildlife sightings have
been reported along the road.
Page 63 of 87
NH
No. State
Length
(km)
Proposed
Bypass Relevant Features of Project Corridor
Topographically, the road has a mountainous
terrain with issues of land erosion and landslides
capable of disrupting traffic during the monsoon
season.
Over 7000 trees are likely to be affected.
200 Orissa 58.40 1
Moderate to significant impacts expected
Hilly and rolling terrain
22.96 km of road traverses reserved forest area
Wildlife spotting in certain stretches of the road.
Elephant reserves located 50 km from corridor. A
wildlife reserve in 12km from the corridor
Bypass will result in conversion of road side
activities. Not favored as an option by the
surrounding communities
Further discussions to drop the bypass
Slope cutting and subsequent debris
management, erosion and sedimentation control
in the hilly areas
201 Orissa 55.00 0
The project road traverse two districts and five
towns/villages. He road is linear protected forests
in strip plantations abutting it on teh road sides
Dear park is located at km 32.4 near
Papadahandi village within 17 of the project
carriage way As such there could be indirect
impacts on wildlife.
Construction work will involve rehabilitation of 14
minor bridges and causeway with minor
topographical changes
217 Orissa 68.00 0
Reported elephant sighting. Additional field
survey and consultations needed to determine if
this poses an issue. Total number of trees to be
impacted will be about 4773. Road passes
through a reserved forest in the Naupada district.
A dam located 5-6 km from the corridor could
pose flooding and overtopping problems
113 Rajasthan 97.451 1
The road corridor starts at Pratapgarh and ends
near Padi village traversing two districts and
through 6 major towns. Topographically the road
alternates between flat, rolling terrain and hilly
areas. 54 water bodies abutting road within 500m
Page 64 of 87
NH
No. State
Length
(km)
Proposed
Bypass Relevant Features of Project Corridor
Expected negative biological and environmental
impacts moderate to high. The road traverses
protected and reserved forest within the 15 km
radius. Estimated 1.92 ha of reserve forest and
1.52 ha of protected forest to be diverted.
Estimated 1593 trees to be affected Potential
tribal issues are registered in the region but hte
specific project corridor is not affected.
11B Rajasthan 85.00 2 No significant impacts
60A West Bengal 84.00 2
Rolling, undulating terrain. Soil erosion is of great
concern. Some amount of water stagnation.
Potential effect on wildlife. Public and private
waterbodies located within ROW. Compensatory
afforestation.
Page 65 of 87
Annex 5
Potential Environmental Impacts
Activity Potential Impacts
Construction
Workforce
Impacts during construction include:
- Tensions between outside workers and local communities
- Affected living standard and income of local residents due
to occupation of farmland
- Market distortion due to temporary inputs to local economy
- Unemployment of local labor
- Disruption to livelihoods, cultural activities, and wellbeing
of locals
- Competition for employment with locals.
Worker’s Camp and
Site Installation
Impacts during construction include:
- Generation of significant volumes of wastewater and solid
waste.
- Stockpiling of waste and illegal dumping
- Contamination of land, surface water and groundwater
caused by spillage and leakage from storage of hazardous
materials including petroleum products, chemicals,
hazardous substances or hazardous wastes.
- Water courses, nearby rice paddies, and agricultural land
can be easily contaminated with wastewater and solid
wastes.
Erosion and
Sedimentation
Roadbed and side slopes digging, roadbed filling, road surface
paving, bridge foundation treatment, materials stack, concrete
plants, construction machinery operation etc. can:
- Destroy surface vegetation
- Aggravate soil erosion
- Weakened soil conservation capacity
- Temporarily change water flow patterns
Emissions and Dust
(Air Quality)
Sources or air pollution during construction that can be a
nuisance and cause health problems are:
- Fugitive dust emissions due to exposure of slope surface,
uncovered stockpiling area, earth moving and excavation
activities
- Dust emission due to blasting of rock
- Dust from vehicles and unpaved roads
- Wind blow during transportation of material by vehicles and
Page 66 of 87
Activity Potential Impacts
when transporting on unpaved access roads
- Gases emissions from batching plants and concrete mixing
stations
- Gases emissions during payment of road surface by asphalt
plant; and
- Air pollutant emissions from exhaust of construction plant
and vehicles such as CO, CO2, NOx, and SO2.
Air pollution problems during the operation phase are:
- Exhaust from vehicles (e.g. CO, NOx) that may deteriorate
air quality in tunnel and at nearby sensitive receptor
locations; and
- Gases emissions during road maintenance and re-surfacing
of road surface (e.g. asphalt plant).
Noise and Vibration
Disturbances to livelihoods and damage to structures can be
cause by:
- Operation of the various equipment during construction (air
compressor, concrete mixers, powered mechanical
equipment, bulldozers, excavators, etc);
- Vehicles transporting materials within construction site and
beyond the construction boundary;
- Piling activities during construction of foundations / piers;
- Ventilation systems during tunnel construction;
- Blasting and vibration during tunnel construction
- During the operation phase, noise may be generated by:
- Traffic noise from road and horning of vehicles;
- Noise from service areas and car parking areas; and
- Construction plant during road maintenance.
Earthworks, Fill
Slopes, Cuts,
Borrow Pits,
Quarries, Disposal
sites, Stockpiles
Impacts include:
- Loss of topsoil affecting productive land.
- Land instability from incorrect earth removal or unstable
deposition of spoil, leading to landslides or erosion events.
- Discharge of sediments into watercourses, rice paddies,
drainages, and irrigation canals.
- Erosion of riverbanks, slopes, and productive land
- Noise and vibration
- Dust emissions affecting health.
- Disturbances or damage to physical cultural resources.
- Damage to agricultural land and native vegetation
- Visual Impacts
Page 67 of 87
Activity Potential Impacts
Disposal of Debris,
Demolition of
Structures
Impacts include:
- Damage of local forest areas, contamination of drainage
watercourses and impacts on land by Improper disposition
of Construction and vehicle waste
- Injure of workers and the general population by falling
debris and flying objects
Clearing of
Construction Areas
Large-scale moving activities, disturbance of soil profile and
removal of vegetation can result in:
- Soil erosion and visual impact
- Loss of productive plots / trees affecting livelihoods and
habitat
- Loss of habitat and vegetation for animals
- Discharging sediment and vegetation material into water
courses affecting in-stream habitat
- Discharging sediment and vegetation material into rice
paddies, and irrigation canals
Landscape, Visual
Impacts and Site
Restoration
Landscape and visual impacts during construction can result
from:
- Poor/inadequate aesthetic design and landscaping design of
the proposed road structures
- Poorly implemented temporary mitigation measures and
slope protection measures during excavation and slope
work.
- After the completion of construction and before operation
of the project, landscape and visual impact may occur
because of:
- Lack of appropriate compensatory planting at the end of
construction or non-native species
- Planting of species visually incompatible to the background
environment;
- Lack of proper maintenance/watering of newly planted
vegetation during the post-construction period.
- Lack of proper restoration of cleared areas, such as borrow
pits, stockpiles and disposal areas, construction camp
areas, areas under bridges, and any areas occupied
temporarily
Water Quality
Pollution of watercourses, groundwater, natural habitats and
productive land caused by:
- Wastewater generated from construction equipment (e.g.
uncontrolled release of bentonite from tunnel drilling
machine);
Page 68 of 87
Activity Potential Impacts
- Wastewater from bored piling locations. Re-suspension of
bottom sediment and mud caused by cut-trench river
crossings and construction of bridge foundation within
rivers;
- Soil erosion / flush away from uncovered stockpiling
locations, uncovered excavation site and unprotected slope
surface during adverse weather conditions;
- Uncontrolled surface water run-off carrying sediment laden
discharges directly into natural water bodies such as
streams, fish ponds, rivers and local irrigation channels;
- Domestic sewage generated by construction workers, such
as kitchen, shower, campsite, etc.
Main water quality issues during operation phase are:
- Wastewater generated during routine road surface cleaning
and surface runoff from road surface during heavy rain
falls;
- Pollution of nearby water body due to vehicle accidents
leaking fuel, hydraulic oil, toxic materials or dangerous
goods; and
- Wastewater discharge from service areas, car parking and
toll station
Solid Waste,
Hazardous and
Chemical Waste
Damage to local forest areas, pollution of drainage
watercourses and natural habitats, and impact on agricultural
land caused by:
- Surplus excavated materials requiring disposal due to earth
moving activities and slope cutting;
- Disposal of used wooden boards for trenching works,
scaffolding steel material, site hoarding, packaging
materials, containers of fuel, lubricant and paint;
- Waste generated by demolition of existing houses /
buildings affected by the project or breaking of existing
concrete surface;
- Domestic solid waste generated by construction workers,
construction campsite, kitchen, toiletries,
- Improper disposition of hazardous wastes such as waste
oil, spent lubricant, solvents, and contaminated materials
resulting from leakage of oil and fuel.
- Improper handling and storage of hazardous and chemical
substances and construction materials
Page 69 of 87
Activity Potential Impacts
Work on Bridges
- Discharges of sediment into water courses affecting in-
stream habitat.
- Erosion of river banks
- Introduction of invasive species.
- Changing water course paths blocking fish passage and
affecting in-stream habitat from fallen debris from the
construction process
- Discharges of oil and fuel to water courses affecting water
quality.
Ecological
Considerations
(Fauna and Flora)
Impacts during construction include:
- Destruction of native vegetation and land outside proposed
working areas
- Damage of forest areas
- Loss of habitat and vegetation for animals due to site
clearance
- Temporary destruction or disturbance of aquatic life due to
bridge works
- Land occupation at ecological sensitive areas
- Damage of forests and waterways adjacent to camps and
work areas.
- Illegal hunting of wild animals by construction workers
- Lack of re-construction of lost habitats and re-creation of
diverse ecosystems.
Impacts during operation phase include:
- Traffic noise and lighting can force wildlife to leave their
natural habitats
- Lack of evaluation of the success of recreation of habitat
and identification of further measures to improve ecological
conditions
- Traffic accidents with wildlife crossing the expressway
Construction Site
Safety
Impacts include:
- Risk associated with working in enclosed environment such
as inadequate ventilation and fire fighting within tunnel /
tunnel shaft
- Seepage of water into tunnel during the tunnel
construction;
- Collapse within tunnel when drilling through geologically
unstable ground layers
- Risk of falling objects and unstable working platform
- Risk associated with blasting and fire
- Risk associated with equipment and traffic movements, on
and off the construction sites.
Page 70 of 87
Activity Potential Impacts
Traffic Management
Impacts include:
- Traffic congestion during construction due to the increase
of heavy traffic (of the construction itself and from traffic
detours) in high traffic avenues and exit ramps, community
roads;
- degradation of local roads due to heavy equipment
machinery and traffic detours;
- Pedestrian safety specially for school children during
construction;
- Increase in traffic accidents
Access and Linking
Roads
Impacts include:
- Increase noise, dust t and air pollutants caused by
construction vehicles that will use existing local and
provincial roads;
- Pedestrian safety specially for children and pupils
- Additional vehicles used for transportation of materials may
cause traffic jams and accidents in existing access roads
such as NH1A, NH1B4, NH14E which already exceed traffic
capacity
- Newly developed access roads may impact water quality,
destroy existing vegetation cover, cause changes in the
landform in certain areas, impact and create bare surface
more prone to erosion
Community
Relations
Lack of communication and consultation with local
communities can lead to an opposition to a road project,
delays in the construction process increased costs and
unsatisfactory solutions.
Health Issues
Impacts include:
- Spread of disease due to poor housekeeping and
accumulation of domestic waste within the construction site
- Stagnant water may result in mosquitoes breeding.
- Unsafe sex conduct could bring the HIV/AID risk to the
local communities.
- Illnesses brought by outside construction workers.
Page 71 of 87
Annex 6
Environmental Guidelines for
Developing Environment Management Plans
General Issues
Issue Key Principle /
Mitigation Standard Mitigation Measures
Water supply
affecting ecology
or neighboring
community water
supply.
Camp to provide its own
water supply that does
not affect village water
supply.
Any water supply sources should be
located so that it does not
adversely affect the villages supply.
The intake of water from streams
for water supplies should leave
residual flows in the watercourses.
Storage tanks should be used to
buffer water supplies.
Wastewater
discharges
affecting water
quality
Wastewater to be
treated prior to
discharge.
Sewerage disposal methods should
be designed to the standards
outlined by the Vietnamese
government
Solid waste
polluting the
environment and
causing health
hazards
No waste to be burnt or
buried on site.
All solid wastes shall be removed
from site and disposed of at a
municipal landfill.
Camps using local
services and
resources, at the
expense of
villagers.
Refer to section on Village impacts
Workers intruding
on village life and
disrespecting
traditional cultural
values.
Refer to section on Village impacts
General Construction Issues
Issue Key Principle /
Mitigation Standard Mitigation Measures
Noise of machinery
associated with
construction
activities
Noise must not
unreasonably intrude on
traditional village life.
Keep a current list of all noise
producing machinery and noisy
activities
Operate machinery only during
Page 72 of 87
Issue Key Principle /
Mitigation Standard Mitigation Measures
designated hours in agreement with
local communities
Adopt a complaint mechanism that
will enable capturing and
addressing issues upfront
Work to be carried out in daylight,
in typical working hours.
Concrete batching plants and other
noisy equipment to be located as
far as practical from settlements
Dust generation
from construction
activities
Dust must not cause a
hazard or nuisance to
village life.
Dusty operations to occur only
during designated hours.
Adopt complaint mechanism
Concrete batching plants and other
dusty equipment to be located as
far as practical from settlements.
Vibration
disturbance from
construction
activities
Vibration must not
unreasonably intrude on
traditional village life.
Keeps a list of all vibration
producing machinery and activities
causing vibration.
This machinery operation to occur
only during designated hours (to be
confirmed by contractor in
agreement with villages).
Use of complaints register and
procedures to address issues as
they arise.
Increased
utilization of roads
by traffic
associated with
construction
activities
There should be no
significant increased
risk to local populations
from traffic associated
with the development.
Road upgrades, including signage,
speed humps, re-grading.
Training of locals regarding the
hazards of traffic.
Training of vehicle drivers regarding
the driving risks through villages
and along remote roads.
Use of complaints register and
procedures to address issues as
they arise.
Pollution risk
activities occurring
on site
Develop appropriate
storage, transport and
use practices for storage
and handling of mixed
classes of dangerous
goods in packages and
intermediate bulk
containers.
Keeps a current list of all potentially
contaminating materials used on
site.
Develop and implement appropriate
storage, transport and use
practices to recognized standards.
Solid waste disposal shall be taken
off site.
Page 73 of 87
Issue Key Principle /
Mitigation Standard Mitigation Measures
There shall be no solid
or liquid waste disposal
directly or indirectly to
any water course
(whether flowing or
not).
Excavation and Blasting
Issue Key Principle /
Mitigation Standard Mitigation Measures
Noise disturbance
of local
populations
Noise must not
unreasonably intrude on
traditional village life.
Keep lists of all noise producing
equipment.
This machinery operation to occur
only during designated hours (to be
confirmed by contractor in
agreement with villages).
Blasting to occur at the same time
each day, and / or a warning siren
should sound prior to blasting.
Vibration
disturbance of
local populations
Vibration must not
unreasonably intrude on
traditional village life.
Keep current lists of all vibration
producing machinery
This machinery operation to occur
only during designated hours (to be
confirmed by contractor in
agreement with villages).
Blasting to occur at the same time
each day, and / or a warning siren
should sound prior to blasting.
Material Stockpiling
Issue Key Principle /
Mitigation Standard Mitigation Measures
Runoff of
suspended
sediments from
stockpiles
Stockpiling activities
should not give rise to
storm water containing
elevated suspended
solids.
Provide treatment to
achieve 75% reduction
in suspended solids.
No direct discharge of sediment
laden water without treatment.
Stockpiles should be compacted as
much as practical and not be
exposed for extended periods.
Storm water should be diverted
around stockpiles.
Page 74 of 87
Issue Key Principle /
Mitigation Standard Mitigation Measures
Dust generation
from stockpiles
Dust must not cause a
hazard or nuisance to
village life.
Stockpiles should be compacted
and not exposed for extended
periods.
Stockpiles should be reused as
soon as practicable.
Soil / Overburden Removal and Placement
Issue Key Principle /
Mitigation Standard Minimum Mitigation Measures
Generation of
suspended solids
from bare ground
and runoff into
watercourses
Development activities
should not give rise to
storm water containing
elevated suspended
solids.
Provide treatment to
achieve 75% reduction
in suspended solids.
No direct discharge of sediment
laden water without treatment.
Earthworks and land clearance
should be minimized and phased.
Any discharges to watercourses
should occur during high flow and /
or discharged as close to the outfall
as possible to maximize mixing.
Stockpiling should occur at least
10m from a water course.
Re-vegetation of exposed areas as
soon as practicable.
Timing of works around the drier
seasons where possible.
Provision of storm water cut off
drains wherever possible.
Introduction of
invasive species
Fill material should not
contain invasive
species.
The use of imported fill shall be
minimized.
Machinery should be cleaned prior
to working on site to reduce the
opportunity of the spread of weed
seeds.
Disturbance of
natural habitats
for spoil / alluvial
material.
Soils should be reused
where possible in the
development – to
reduce the need for
spoil sites and the need
to import fill.
Stockpile and reuse soils before
excavating new soils / alluvium.
Efficiency of
control measures
over time
Control measures
should continue to work
appropriately
throughout the
construction period.
Earthworks control measures
should be inspected and maintained
in efficient operating condition over
the construction period.
Page 75 of 87
Concrete Manufacture
Issue Key Principle /
Mitigation Standard
Minimum Mitigation Measures
Contaminants in
water discharged
from concrete
manufacturing,
including rise in pH.
No direct discharges of
concrete batching water
to any water course.
Provide treatment prior
to discharge to achieve
75% reduction in
suspended solids.
Settlement ponds and / or
sediment infiltration gallery.
Monitoring immediately upstream
and 50m downstream of the
discharge with a clarity tube to
estimate any effects on clarity; for
pH to detect alkali discharges.
Any storm water discharges to
watercourses should occur during
high flow and / or discharged as
close to the outfall as possible to
maximize mixing.
Water to be reused where possible
in the process.
Procedures for handling of un-
hydrated cement material and wet
cement to avoid spills.
Community
nuisances.
Noise and dust must not
unreasonably intrude on
traditional village life.
Concrete batching plants and other
noisy / dusty equipment to be
located as far as practical from
villages.
Page 76 of 87
Fuel Storage and Use
Issue Key Principle /
Mitigation Standard Minimum Mitigation Measures
Pollution risk
associated with
the storage and
use of fuels for all
plant, generators
and vehicles
No oil, lubricants, fuels
or containers should be
drained or dumped to
ground or waterways.
Accidental spills shall be
minimized, and
procedures put in place
to clean up the
environmental damage.
Keep a current list of all fuels
stored on site.
Keep the Safety Data Sheet of all
hazardous materials used on site.
Develop appropriate storage,
transport and use practices to
recognized standards.
Diesel to be stored in truck tankers
or in overhead tanks to a maximum
of 5000 liters.
Diesel to be stored on flat ground,
and 100m from a waterway.
Dikes to capture 100% of fuel must
be placed around fuel storage
areas.
All refueling of vehicles and plant to
be done on flat ground.
All significant vehicle and plant
maintenance shall be undertaken
offsite where possible.
Spill kits and emergency
procedures should be used and
staff trained.
There shall be no deliberate
discharge of oil, diesel, petrol or
other hazardous materials to the
surrounding soils and waterways.
Works in and near Rivers
Issue Key Principle /
Mitigation Standard Minimum Mitigation Measures
Sediment
discharges arising
from working in
and near the river.
For blasting in or
near the river,
refer to the
blasting issues,
above.
Work in the wetted area
of the riverbed should
be minimized, and only
in relation to the
construction of the
power house, weir and
intake structure or to
insert culverts for
stream crossings.
Stabilize works at the end of each
working day and prior to storm
events.
Do the work during low flow
periods.
Works shall be minimized.
Diversion of the river around the
work area where possible.
Page 77 of 87
Village impacts
Issue Key Principle /
Mitigation Standard Minimum Mitigation Measures
Key Considerations
for a
Communication
Strategy to avoid
deterioration of
current quality of
life and traditional
livelihoods
Communication
channels are
established between
Villagers, Construction
Supervisors, and state
PCUs to facilitate
information flow and
easier process for
lodging complaints
Set up a communication network
for discussing issues between
Construction supervisors
Contractors and the villagers and
the state PCUs built on recognized
negotiation structures
Construction Supervision
Consultant and the Contractors will
have an Environmental Specialist
on site to ensure daily conformance
with environmental health and
safety guidelines and to respond to
complaints
A Health Program to be included in
the Contractor‟s Construction and
Workers Camp Management Plan.
This will be made available to the
communities
Education and orientation of
outside workers to local culture and
social norms before the start of
work.
Camps to be self sufficient in
resources and services. (refer to
the workers camp table below)
Villagers shall be adequately
informed of all potential hazards to
health and safety with regards to
increased traffic, blasting,
machinery operation.
Traffic causing
safety risks to
road users
Construction traffic will
be managed to
minimize the impact on
existing road users.
Signage to be used to identify
current risks to road users.
Construction Supervision
consultancy and Contractors to
discuss major traffic issues with
village representatives prior to the
event to discuss course of action.
Heavy traffic to avoid the hours
when school children walk to and
from school.
Sediment affecting
river water uses.
Sediment discharges to
the river shall be
minimized.
Refer to the sections above
discussing erosion and sediment
control.
Page 78 of 87
Annex 7
Forest Clearance Procedure – A Typical Activity and Timeline Chart
Step No. Activity No. of
Days
1 Preparation of case / application letter that is submitted to
Revenue and Forest Department 7
2
Area calculation to identify land diversion requirement with the
help of Revenue Department represented by( provide name of
person responsible) 30
3 Joint visit by Executive Engineer, and District Forest
Officer(DFO)
4 Enumeration of trees by the Forest Department after the visit
of Forest Guard and Range Officer 7
5 List is forwarded by the Range Officer to DFO for approval 15
6
Preparation of a combined „case‟ papers (documents prepared
by Revenue Department, list of trees enumerated by Forest
Department and actual area calculation for diversion of forest
land are enclosed)
7
7 Case submitted to DFO - DFO Office will examine the case and
further send to Conservator of Forests 7
8
Conservator of Forests will examine the papers and further
forward the case (subject to the fact that no short-
comings/deficiencies are found) to Prin. Chief Conservator of
Forests
7
9 Case is further examined by the Prin. Chief Conservator of
Forests and forwarded to Additional Secretary (Forests) 4
10 Additional Secretary (Forests) recommends the case for the
approval of the Forest Minister. 3
11 Forest Minister approves the case and returns the case file to
Additional Secretary (Forests) 8
12
Case file is sent to CF, Chandigarh (MoEF) after the counter
signature of Chief Secretary, GoHP. (The case file is counter-
signed by the Chief Secretary as the case file goes to MoEF).
2
13
CF (Chandigarh) examines the case. May opt for conducting a
site inspection or may provide an „in- principle‟ clearance
without conducting the site visit.
90
(primarily
due to work
load)
Page 79 of 87
Step No. Activity No. of
Days
14
If CF, Chandigarh provides „in-principle‟ approval, it is
conveyed to DFO. The concerned DFO works out the cost for
compensatory afforestation and NPV and the total cost/amount
is conveyed to the concerned Executive Engineer.
3
15
Executive Engineer requests RIDC for releasing the said
amount. The Project Director‟s Office/RIDC directly deposits the
specified amount into the bank account of the concerned DFO.
2
16 The DFO communicates the amount deposition to CF,
Chandigarh and requests to provide final/formal approval 2
17 CF, Chandigarh conveys (in writing) the final/formal approval
to the concerned DFO. 30
18 DFO conveys the final/formal sanction to the Executive
Engineer 2
19
DFO further directs the concerned Range Officer (Forest
Department) to mark (process is formally known as
„hammering‟) the trees for cutting.
1
20 Range Officer hammers/ marks the trees in presence of
Executive Engineer or his field representative 10
21 The Range Officer sends the final list of trees to the concerned
DFO for information 1
22 DFO forwards the case to Forest Corporation to call „tender‟ for
cutting the marked trees 3
23 DM, Forest Corporation calls for bid and fixes date/s to receive
the tender documents 30
24 After opening of the tenders and their evaluation, tree cutting
work is awarded to the selected contractor 15
25 Contractor mobilizes the required lab our and machinery at site 15
26 Contractor cuts the trees. 30
Total Number of Days ( numbers indicate ideal situations) 331
Page 80 of 87
Annex 8
Tree Cutting Procedure – A Typical Activity and Timeline Chart
Step No. Activity No. of Days
1
Preparation of case / application letter to the Revenue
and Forest Department for felling of trees falling within
the Right of Way
7
2 Area to be cleared of trees is verified on the ground with
the help of Revenue Department
30
3
Joint visit by Executive Engineer, DFO and Revenue
Department staff for the verification of the land and trees
falling within the ROW
4
Enumeration of trees by Forest Department after the
visit of Forest Guard and Range Officer (both from Forest
Department). The details cover number of trees to be cut
along with chainage, species and girth information.
7
5 List of trees to be cut is forwarded by the Range Officer
to the concerned DFO for approval 15
6
The combined case paper is prepared by enclosing the
documents received from Revenue and Forest
Department (as prepared in the steps mentioned above).
7
7
Case is submitted to the concerned DFO – the DFO Office
examines the case and if there are no observations,
sends it to the Conservator of Forests (CF)
7
8 The CF office will examine the case and if there are no
observations, will approve the felling proposal. 7
9
The approval from CF office is conveyed to the concerned
DFO, who further conveys the final sanction (in writing)
to Executive Engineer.
2
10
DFO further directs the concerned Range Officer (Forest
Department) to mark (process is formally known as
„hammering‟) the trees for cutting.
1
Page 81 of 87
Step No. Activity No. of Days
11 Range Officer hammers/ marks the trees in presence of
Executive Engineer or his field representative. 10
12 The Range Officer sends the final list of trees to the
concerned DFO for information. 1
13 DFO forwards the case to Forest Corporation to call
„tender‟ for cutting the marked trees. 3
14 DM Forest Corporation calls for bids and fixes date/s to
receive the tenders. 30
15 After opening of the tenders and their evaluation, tree
cutting work is awarded to the selected contractor. 15
16 Contractor mobilizes the required labor and machinery at
site. 15
17 Contractor cuts the trees 30
Total Number of Days ( numbers indicate ideal situations) 187
Page 82 of 87
Annex 9
Findings of the Preliminary Environment Screening Exercise (Initial List of Proposed Sub-Projects)
S. no.
State National Highway
no. Corridor
Length (in km)
(approx)
Chainage (from/to)
Name of Districts
Existing/ Available RoW (m)
Issues/Remarks
1 Andaman & Nicobar Islands
223 Port Blair-
Mayabunder-Diglipur
277 / 333 0-61,104-142 & 155-
333
South Andaman; North and
Middle
Andaman
10 to 20
Stretches from km 61 to 104 in South Andaman and from km 142 to 155 in Kadarntala area of Middle Andaman are Jarawa Tribes Reserved Areas - only simple improvement/maintenance can be taken-up in
these areas as per Ministry of Home Affairs direction. Widening not permitted here.
2 Bihar 30 A Fathua-Harnaut-
Barh 69.5 0-69
Patna; Nalanda
15 to 30
Reseved/Protected Forest; Public Water Sources at Harnaut and Barh; Bypass sought at Hamaut and Barh and RoB at Hamaut,
Dariyama and Barh
3 Bihar 106
Birpur-Bihpur
(Madhepura km 73)
136 0-136
Bhagalpur; Madhepura;
Saharsa; Supual
30 to 45 Drainage/Flooding Issues
4 Bihar 2 C Akabarpur-
Yadunathpur-Jardag
65 40-105 Rohtas 15 to 20
Forest clearance will be required; Passes through Protected Forest Areas; Wildlife Crossing Issue; Passes through mineral rich areas (lime and phosphate); Naxal infested near Kaimur range and Sone River
5 Bihar 104
Sheohar-Sitamarhi-Jaynagar-Narhiya
176 40-216 Sheohar; Sitamarhi; Madhubani
7.60 to 24.40
Flood Prone Zone; Indo-Nepal Border road
Page 83 of 87
S. no.
State National Highway
no.
Corridor Length (in km)
(approx)
Chainage (from/to)
Name of Districts
Existing/ Available RoW (m)
Issues/Remarks
6 Bihar 98 Anishabad-
Aurangabad-Hariharganj
149 / 151.62
0-149 Arwal,
Aurangabad and Patna
15 to 30
Bypass sought at Arwal, Dandnagar and Obra; Passes through Protected Forest; Wildlife Crossings and Habitat; Patna-Sone canal
within 1 km
7 Bihar 28 B Betiah-
Kushinagar 87 25-112
Betiah; Bagha
25 to 30
Forest Clearance will be required from km 99 to km 112 - Reserved/Protected Forest between km 99 to 112; Valmikinagar Tiger Reserve and Sanctuary between km 99 to km
112; Swampy land between km 106 to 112; Ashok Stambh near Loria in km 51
8 Bihar 80 Munger-
Bhagalpur-Mirzachauki
125 65-190 No
Information No
Information No Information
9 Himachal Pradesh
22 Narkanda- Wangtoo
111 224-335 Shimla; Kinnaur
10 to 30
Safety Issues; Forest Land; Proposed Luhri
HEP at Nirath about 5 to 10 mts. Away from NH; Existing Reservoir of SJVNL at Nathapa about 10 to 15 mts. from NH; Many hydro-power plants are coming-up along this road
10 Himachal Pradesh
72 B Paonta- Guma 97 /
18.50 0-97
Sirmour; Shimla
8 to 32.50
Forest Area Constraint - Reserved/Protected Forest at Various Locations; Paonta Sahib Gurudwara (about 1 km); Big cement plant to come-up at Gumma
11 Himachal Pradesh
88 / 86.900
Shimla- Hamirpur
147.6 0-147.6
Shimla; Solan;
Bilaspur; Hamirpur;
Kangra
8 to 24
Entire road is in a hilly terrain; Catchment area of Bhakra Dam; Road crosses Satluj river
at Kandrour (lake backwaters); Dhami Wildilife Sanctuary about 2 kms away; Reserved Forest (Dhami) of about 2 kms; Accidents is a cause of concern; Small land holdings
Page 84 of 87
S. no.
State National Highway
no.
Corridor Length (in km)
(approx)
Chainage (from/to)
Name of Districts
Existing/ Available RoW (m)
Issues/Remarks
12 Himachal Pradesh
70 Hamirpur- Mandi 124 141-265
Una; Kangra;
Hamirpur; Mandi
3 to 20
Hilly terrain and Safety Issues (Geometrics); Land Acquisition; Houses; Forestland; Reserved Forest for 10 kms at Janetri Dhar;
Accidents is a cause of concern; Small land holdings
13 Himachal Pradesh
20 A Nagrota-
Mubarakpur 91 0-91 Kangra; Una 3 to 13
Entire road is in a hilly terrain; Beas
Backwater near Dehra; Catachment area of Pong Band Dam; Accidents is a cause of
concern; Small land holdings
14 Himachal Pradesh
20 Ghatta- Mandi 69.7 134.3-204 Mandi; Kangra
3.70 to 24
RoW is 3.70 mts. between km 143.443 to 143.625 and other stretches; Row is 24 mts. between km 175 to 180; Stretches between km 160 and 165 are faced with sinking/sliding problem that requires stabilization (expert
opinion needed); Involves Forest Land; Reserved/Protected Forest in Urla, Gawali, Ghatasni, Chhanag and Galoo between km 155
to 170; Accidents due to blind curves
15 Karnataka 206 Tumkur-
Hannavara 348
22-370 /
19.82-87.51
Dakshin Kannada
7 to 15
Charmandi Ghat for 13 kms with 11 hair pin
bends; Widening constraint in built-up areas and ghat section
16 Karnataka 234
Madhugiri-Chikkaballapura-
Chinthamani-Andhra border
165.7
343.8-509.5 /
343.800-401.200
Chikkaballapura
No Information
Chikkaballapur Drinking Water Supply Scheme (about 5 kms or so); Road traverses an area of commercial agriculture (mangoes, grapes, vegetables, sericulture) - also exported
17 Karnataka 234
Mangalore-Beltangadi-
Mudigere-Janapura-Belur
149.2 /
60.455 0-149.2
Chikkamangalore; Hassan
8 to 16
Km 87.51 to 99 is a Ghat Section in Reserved Forest Area on both sides with RoW between 9 to 15 mts. - will be a constraint; Km 99 to 148 is on a plain terrain with RoW between 11 to 16 mts
Page 85 of 87
S. no.
State National Highway
no.
Corridor Length (in km)
(approx)
Chainage (from/to)
Name of Districts
Existing/ Available RoW (m)
Issues/Remarks
18 Orissa 23 Pallhara-Pitri
junction 68
337.47-405.45
(Old chainage:1
6-84)
Angul, Dhenkanal
10 to 20
Limited RoW in Village and Forest Areas; Two-lane standard except between km 337 to 339 and km 347 to 355, where it has intermediate
lane; Passes through built-up areas of Pallahara and Khamar - persistent local demand for bypass construction at both these places; Reserve Forest Present; Km 351 to
371 is elephant corridor; Dadarghat Reservoir at km 391; Khamar and Pallhara Public Water
Supply Sources.
19 Orissa 217 Belgaon-Baliguda 116.11 202.89-
319
Bolangir, Kalahandi, Kandhmal
15 to 20
Leopard and Elephant Crossings; Traverses through Five Reserved Forests; Limited RoW in Village and Forest Areas; Single Lane Road for 108 kms and intermediate lane for 8.24 kms ; Thickly Tribal Dominated Area;
20 Orissa 217 Nuaparha-Bango
Munda 68 90-158
Nuapada;
Kalahandi 18 to 20
Limited RoW in Village and Forest Areas; Single Lane Road for 49.290 kms,
intermediate lane for 5 kms and two lane for 13.7 kms of length ; Thickly Tribal Dominated Area.
21 Orissa 200 Bhojpur-
Chhatabar 61 131-192
Sambalpur; Deogarh
8 to 28
Passes through built-up area of Kuchinda - persistent demand for by-pass construction; Reserved/Protected Forest between km 133 to 156 and 158 to 167; Limited RoW in Village and Forest Areas; Single Lane Road for 43.6 km and intermediate lane for 17.4 km ;
Thickly Tribal Dominated Area; Hot bed of Maoist Activities
22 Orissa 201 Navrangpur-
Koksara 55 25-80
Nawarangpur; Kalahandi
15 to 20
Reserved Forest (km 25 to 28; 30 to 34; 39 to 41, 45 to 47 and 53 to 59); Limited RoW in Village and Forest Areas; Single Lane Road for 40 kms and intermediate lane for 15 kms ;
Thickly Tribal Dominated Area
Page 86 of 87
S. no.
State National Highway
no.
Corridor Length (in km)
(approx)
Chainage (from/to)
Name of Districts
Existing/ Available RoW (m)
Issues/Remarks
23 Orissa 200 Rengali-Talchar 68 227-295 Deogarh;
Angul 12 to 30
Reserved Forest between Km 228 to 232 ; Rengali Reservoir at 0.900 km away at Km 245; Limited RoW in Village and Forest Areas;
Single Lane Road for 46 kms, intermediate lane for 6.23 kms and two lane for 15.77 kms of length ; Thickly Tribal Dominated Area; Hot bed of Maoist Activities.
24 Orissa 217 Daraingbadi-
Saroda 64.365
375-439.365
Kadhamal, Ganjam
15 to 22
Reserved/Protected Forest between km 378 to
390; Sorada Reservoir between km 412 to 415; Public Water Supply Areas from km 434.5 to km 439.6; Limited RoW in Village and Forest Areas; Single Lane Road ; Thickly Tribal Dominated Area.
25 Orissa 224 Daspalla-
Madhhapur 57 102-159
Nayagarh,
Boudh 12 to 20
Passes through Reserved Forest at many
places; Wildlife Crossing at km 139.900, km 140.500, km 144.650, km 153 and km 155.200; Kuanria Dam; Public Water Supply
Areas of four villages; Limited RoW in Village and Forest Areas; Thickly Tribal Dominated Area.
26 Rajasthan 11-B Lalsot - Karauli -
Dholpur 116
0 - 85, 155-186
Dausa, Sawai
Madhopur, Karauli,
Dhopur
20 to 30
Passes through Wildlife Sanctuary - Kesharwbagh for 6 kms (km 175 to 181); Forest in 1 km (km 181 to 182); Traverses 4 dams/reservoirs - Bindori Sagar (km 10), Nazim Bada (km 43 to 46), Husainpur Bandh (km162), Urmila Sagar Dam (170 to 172); In
case of Husainsagar, the service road of the dam is the alignment of NH-11-B; Talshahi
Lake (km 160
27 Rajasthan 113 Nimbahera-
Pratapgarh-Padi 180/100
0-180/80-
180
Pratapgarh,
Banswara 30 to 45
Traverses Protected Forest; Very fertile canal
irrigated area.
Page 87 of 87
S. no.
State National Highway
no.
Corridor Length (in km)
(approx)
Chainage (from/to)
Name of Districts
Existing/ Available RoW (m)
Issues/Remarks
28 Uttarakhand 119 Kotdwar-Satpuli-Jwalpa-Srinagar
137/116.200
139-276/159-275.200
Pauri Garhwal
12 to 16 Reserved Forest under Pauri Division
29 Uttarakhand 121 Sald Mahadev-
Thailisain-Salondhar
111 78-189 Pauri
Garhwal 12 to 20
Reserved Forest under Pauri Division for 14
kms
30 Uttarakhand 87 Ext. Ghigarikhal-
Gairsain-Diwalikhal
91 109-200 Almora, Chamoli
8
Some parts pass through landslide zones and
very steep mountainous region. Forest land transfer proposal rejected by GoI (km 108 to 120) for 2701 trees; Maha Mritunjay Mandir, Dwarahat (Km 137-138)
31 Uttarakhand 87 Ext Jeolikot-
Ghigarikhal 109 0-109
Nainital,
Almora 8
Some parts pass through landslide zones and very steep mountaineous region. Forest land
transfer proposal rejected by GoI (km 89 to 101) for 2000+ trees
32 West
Bengal 55
Salbari-Kurseong & Kurseong-
Darjeeling
77 0-77 Darjeeling 10 to 30
Mahananda Wildife Sanctaury; Mahananda Forest; Padmaja Naidu Zoological Park; Loyd Botanical Garden, Darjeeling; Seven
Elelephant corridors between Km 66 and 74; Darjleeling Himalayan Raiway is passing all along; Netaji Museum near Kurseong; Landslides between Km 35 to 45 causing road bench failure/subsidence - bypass suggested. Widening Difficult along parallel railway line section; Out of 77 kms, only about 10 kms
length has 7 mt. or more of carriage way
width.
33 West
Bengal 60 A Purulia-Bankura 84 0-84
Bankura,
Purulia 20 to 30 No specific comments