environmental impact assessment review
DESCRIPTION
Environmental impact assessment and the decommissioning of nuclear power plants—a review and suggestion for a best practicable approach.Alan Bond a, Mark Bussell b,TRANSCRIPT
Environmental impact assessment and
the decommissioning of nuclear power
plants—a review and suggestion for
a best practicable approach
Alan Bonda,*, Mark Bussellb, Patrick O’Sullivanc,1,Juan Palermd
aEIA Unit, Institute of Biological Sciences, University of Wales, Aberystwyth, Wales SY23 3DD, UKbOxford Biosphere Ltd., P.O. Box 1122, Oxford OX3 8YS, UK
cUnited Kingdom Nirex Ltd., Curie Avenue, Harwell, Didcot, Oxfordshire, OX11 0RH, UKdECA S.A., Quatre Camins 9-15, 10B, 08022 Barcelona, Spain
Received 1 January 2002; received in revised form 1 September 2002; accepted 1 October 2002
Abstract
This paper reviews the current legislative and guidance framework for the Environ-
mental Impact Assessment (EIA) of projects to decommission nuclear power plants. It
considers, in particular, the potential use of EIA as a tool for harmonising relevant consent
processes across the European Union member states and accession countries. To this end, a
best practicable approach for carrying out EIA for the decommissioning of a nuclear
installation, based on consultation with a range of stakeholders across the European Union,
is proposed which can both lead to better harmonisation by virtue of its practicability, and
prevent unnecessary duplication of effort. The approach has been developed in the context
of the legal framework provided by the relevant Directives and takes heed of European
Commission guidance on various aspects of environmental assessment. It draws on
extensive feedback obtained from a 2-day workshop attended by the range of stakeholders
0195-9255/02/$ – see front matter D 2002 Elsevier Science Inc. All rights reserved.
doi:10.1016/S0195-9255(02)00091-4
* Corresponding author. Tel.: +44-1970-622-387; fax: +44-1970-622-307.
E-mail address: [email protected] (A. Bond).1 Now at NRG, Westerduinweg 3, P.O. Box 25, 1755 LE Petten, The Netherlands.
www.elsevier.com/locate/eiar
Environmental Impact Assessment Review
23 (2003) 197–217
associated with decommissioning activities in 18 countries and the European Commission,
and including public representatives.
D 2002 Elsevier Science Inc. All rights reserved.
Keywords: European Union; Environmental impact assessment; Nuclear power plants; Public
participation; Decommissioning
1. Introduction
Over 110 nuclear facilities, most of which are nuclear power plants, are at
various stages of the decommissioning process in the European Union at the
present time and it is forecast that another 160 nuclear facilities will need to be
decommissioned in the next 15 years (Vankerckhoven, 1998) (a brief overview of
decommissioning nuclear power plants and the alternative strategies available is
described by Braeckeveldt, 2001). For each new project involving the decom-
missioning or significant modification of a nuclear power plant and most research
reactors it is now obligatory that ‘development consent’ is granted by an
appropriate national competent authority and that an EIA is undertaken prior to
that consent being granted (a list of the current status of the sites currently being
decommissioned across the EU can be found at http://europa.eu.int/comm/
energy/nuclear/decomm5.htm). The expansion of the European Union to include
the Baltic and Central European countries is expected to lead to a rapid increase
in the number of facilities to be decommissioned by at least another 50 sites
(Vankerckhoven, 1998).
Against this background, a collaborative study was undertaken for the Nuclear
Safety Unit, now part of the Directorate-General for Energy and Transport, of the
European Commission (Ref.: EC Contract B4-3040/99/MAR/C2) on the applica-
tion of Environmental Impact Assessment (EIA) to the decommissioning of
nuclear facilities in EU member states and the applicant countries. This study
provided the basis for the information provided in this paper.
1.1. Legislative and guidance context for decommissioning nuclear power plants
Nuclear energy is covered by the Euratom Treaty, one of the founding
Treaties of the European Union, which came into force on January 1, 1958 and
leaves member states the main responsibilities in matters of nuclear safety,
largely sidelining the EU institutions (Anon., 2000). The reason for this is that
the Euratom Treaty was primarily drafted as a means for facilitating civilian
nuclear power programmes, at which time installation safety issues and
radioactive waste management were not a paramount public concern. That this
is the case is reflected by the fact that the Euratom Treaty has only one specific
reference to radioactive waste, in its Article 37 (Taylor, 2000). As a result, there
are a wide variety of approaches to nuclear safety issues across the European
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217198
Union. With this being the case, the Environmental Assessment Directive may
be seen as a potential means of achieving greater harmonisation, particularly as
it already allows for two-way communication with the public when used
properly (Forsstrom and Taylor, 2000). Indeed, the Environmental Assessment
Directive has previously been identified as a potential means of harmonising
practice related to the decision-making process in the siting of geological
repositories for radioactive waste (see Bond et al., 2001; O’Sullivan et al.,
1999a,b).
The relevant legal framework at the European level is provided by the
Environmental Assessment Directive and Directive 96/29/Euratom on safety
standards against the changes arising from ionising radiation (Council of the
European Union, 1996) and including specific requirements arising from Article
37 of that Treaty. In addition, further influence can be expected from the Arhus
Convention on access to information, public participation in decision-making and
access to justice in environmental matters (United Nations Economic Commis-
sion for Europe, 1998) which will require greater public involvement at the
earlier stages of the EIA process. Indeed, the European Commission has now
adopted a Proposal for a Directive amending the EIA (and other) Directives
(Commission of the European Communities, 2001) to take account of the
changes which will be required by the Arhus Convention. Thus, the implications
of the Environmental Assessment Directive, the Euratom Treaty and the Arhus
Convention on the decommissioning of nuclear power plants will be considered
in turn below.
The requirements for EIA within the EU are currently set out in Council
Directive 97/11/EC (Council of the European Union, 1997) amending Directive
85/337/EEC (Council of the European Communities, 1985). This Directive
already incorporates the requirements of the Espoo Convention covering Envir-
onmental Impact Assessment in a Transboundary Context (United Nations
Economic Commission for Europe, 1991), and its obligations on member states
are set out in Fig. 1.
The specific requirements of the Directive have been well covered in other
literature and guidance documents and will not be repeated here (see, for
example, Bond, 2000; Environmental Resources Management, 2001a,b,c). In
the case of decommissioning power reactors and most research reactors an EIA
must always be undertaken, following paragraph 2 of Annex I of the Directive,
except in exceptional cases covered in Article 2(3).
The Directive sets out the minimum contents requirements for an Envir-
onmental Impact Statement which documents the EIA itself, and Article 37 of the
Euratom Treaty states that member states provide the Commission with ‘general
data’ relating to any plan for the disposal of radioactive waste, to allow them to
determine whether the plan will cause environmental impacts.
On December 6, 1999, the European Commission published a recommenda-
tion on the application of this article (Commission of the European Communities,
1999). Section 1, subsection 9, of this Recommendation defines ‘‘any planned
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217 199
disposal or accidental release of radioactive substance associated with . . . thedismantling of nuclear reactors and reprocessing plants’’ as falling within the
Article 37 definition of the disposal of radioactive waste. The same recom-
mendation contains, in Annex 2, what the Commission would expect to see as the
‘general data’ to be submitted prior to decommissioning. This Annex is
comprehensive and, although it is a separate requirement from the need for
Fig. 1. The EIA process specified in the Environmental Assessment Directive.
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217200
EIA, there is scope to save duplication of effort by ensuring that the EIA for
decommissioning covers at least the general data specified in this Annex 2, the
main headings of which are duplicated in Table 1.
In terms of legal obligations imposed by this Commission Recommendation,
Article 161 of the Euratom Treaty makes it clear that Recommendations have no
binding force. In practice however, the Commission would expect the Recom-
mendation to be followed and could have recourse to Article 38 of the Euratom
Table 1
Main headings of the ‘general data’ to be submitted to the European Commission under Commission
Recommendation of December 6, 1999 (Commission of the European Communities, 1999)
1 The site and its surroundings
1.1 Geographical, topographical and geological features of the site and the region
1.2 Hydrology
1.3 Meteorology
1.4 Natural resources and foodstuffs
2 The installation
2.1 Brief description and history of the installation to be dismantled
2.2 Ventilation systems and the treatment of gaseous and airborne wastes
2.3 Liquid waste treatment
2.4 Solid waste treatment
2.5 Containment
3 Release from the installation of airborne radioactive effluents in normal conditions
3.1 Authorisation procedure in force
3.2 Technical aspects
3.3 Monitoring of discharges
3.4 Evaluation of transfer to man
4 Release from the installation of liquid radioactive effluents in normal conditions
4.1 Authorisation procedure in force
4.2 Technical aspects
4.3 Monitoring of discharges
4.4 Evaluation of transfer to man
5 Disposal from the installation of solid radioactive waste
5.1 Categories of solid radioactive wastes and estimated amounts
5.2 Processing and packaging
5.3 Storage arrangements
5.4 Radiological risks to the environment, precautions taken
5.5 Arrangements for the movement and destinations of classified waste transferred off-site
5.6 Criteria for contaminated materials to be released from the requirements of the Basic Safety
Standards, for disposal, recycling or reuse
5.7 Envisaged types and amounts of released materials
6 Unplanned releases of radioactive effluents
6.1 Review of accidents of internal and external origin which could result in unplanned releases of
radioactive substances
6.2 Reference accident(s) taken into consideration by the competent authorities for evaluating possible
radiological consequences in the case of unplanned releases
6.3 Evaluation of the radiological consequences of the reference accident(s)
7 Emergency plans; agreements with other Member States
8 Environmental monitoring
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217 201
Treaty, enabling them to issue a Directive requiring a member state to take
stipulated measures where the data have not been supplied.
The Arhus Convention was signed on June 25, 1998 by 39 countries and by
the European Union and came into force after receiving the 16th ratification on
October 30, 2001.
The Arhus Convention is based upon three principles (Palerm, 1999):
� access to environmental information,� public participation in environmental decision making,� access to justice.
The Arhus Convention sets stricter provisions for public participation than
those of the Environmental Assessment Directive and these apply to the
permitting process of any activity listed in Annex I of the Convention, including
the decommissioning of nuclear reactors.
The Convention defines ‘the public’ as ‘‘one or more natural or legal persons,
and . . . their associations, organisations or groups’’. A separate definition for the
‘public concerned’ is provided as ‘‘the public affected or likely to be affected by, or
having an interest in, the environmental decision making; non-governmental
organisations promoting environmental protection . . . shall be deemed to have
an interest’’.
Therefore the public which must be given an opportunity to participate should
include any person or group (including NGOs) who have an interest in the
decision making process.
Article 6 of the Arhus Convention concerns public participation in decisions on
specific activities. Provisions of the article need to be taken into account when
deciding on whether proposed activities under Annex I of the Convention should
be permitted. The energy sector is the first activity listed in Annex I which refers to
nuclear power stations and other nuclear reactors and includes ‘‘the dismantling or
decommissioning of such power stations or reactors . . .’’. Article 6 sets more
detailed conditions than the Environmental Assessment Directive for notification
of the public concerned specifying that this should take place ‘‘by public notice or
individually, early in the environmental decision making procedure, and in an
adequate, timely and effective manner’’. Palerm (1999) argues that, in the light of
empirical best-practice, adequate and effective should be interpreted as going
beyond mere publication in an official gazette, probably including the use of mass
media as a means of communication. Finally the article states that outcomes of
public participation shall be taken into account in the decision and that the content
and justification for the decision are made known to the public.
In the context of EIA, the Directive only mentions that the opportunity for
public participation should occur before development consent is granted, but the
Arhus Convention establishes that reasonable time-frames should be employed
and participation should occur early in the process, when all options are open and
effective public participation can take place (Article 6.3). This should be inter-
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217202
preted as allowing for public participation before the Environmental Impact
Statement (EIS) is produced and, ideally, during a participative scoping phase
(Palerm, 1999).
In addition to the regulatory framework, there also exists European Commis-
sion guidance which includes:
� EIA–Guidance on Screening–June 2001 (Environmental Resources Manage-
ment, 2001c)� EIA–Guidance on Scoping–June 2001 (Environmental Resources Manage-
ment, 2001b)� EIA Review Check List–June 2001 (Environmental Resources Management,
2001a)� Guidelines for the Assessment of Indirect and Cumulative Impacts as well as
Impact interactions–May 1999 (Walker and Johnston, 1999).
So, for the particular case of nuclear power plant decommissioning there will
normally be a requirement to produce an Environmental Impact Statement and an
Article 37 submission to the European Commission. In addition, nuclear power
plants already have an operational requirement to present a safety case, under the
International Atomic Energy Agency’s ‘Joint Convention on the Safety of Spent
Fuel Management and on the Safety of Radioactive Waste Management’, which
is the licensee’s documented demonstration that the plant is safe to operate
(International Atomic Energy Agency, 1997); this convention came into force for
those countries which had ratified it (which includes all EU states) on June 18,
2001. There are significant overlaps in the information requirements of the safety
case, the Article 37 submission and the Environmental Assessment procedure and
therefore considerable scope for removal of duplication. This could be achieved,
for example, by incorporating the information requirements of all three proce-
dures into the Environmental Assessment report. Alternatively, common formats
for reports supporting the main submissions required by each procedure could be
developed, such that the current practice of providing similar information in
different formats, e.g. relating to calculated impacts on human health, is avoided.
2. Deriving a best practicable approach
EIA is a procedure which aims to provide information to decision makers on the
environmental consequences of their decisions on applications for development
(Bond, 2000; Glasson et al., 1999; Wathern, 1988; Wood, 1995). A country’s EIA
system is often accompanied by guidance on its implementation indicating good
practice approaches to meeting the requirements of the procedure as opposed to
minimum compliance approaches, for example, the UK Government has produced
a general guide to what the EIA procedures mean (Department of the Environment
Transport and the Regions/National Assembly for Wales, 2000), and a good
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217 203
practice guide to help with the preparation of Environmental Impact Statements
compliant with the procedures (Department of the Environment, 1995). Despite
the guidance literature that is available, the stark reality is that developers often aim
for minimum compliance rather than adopt best practice due to financial con-
straints. Proving that best practice can be cost effective is difficult. Furthermore,
when extended to a European Union scale, even getting agreement on what would
constitute good practice across all member states is a huge undertaking, fraught
with similar difficulties to the process followed in getting agreement on Directives
in the first place. Before the Single European Act amended the Treaty of Rome in
1987, Environmental Directives required unanimity for adoption and therefore
allowed each member state a veto over the text—leading to what was termed
‘‘lowest common denominator decision-making’’ (Scott, 1998, p. 7). Since 1987,
qualified majority voting and increasing influence of the European Parliament
have moved the development of environmental Directives away from this position
to one of greater cooperation between the Commission, Council and the European
Parliament, but there is still much scope for obligations disliked by member states
to be rejected during the negotiation of the text. As such, the challenge is to devise
an approach which can be applied by all member states; it therefore needs to be
practicable, to comply with all relevant legal frameworks and, if it is to improve
practice, it needs to contain as many elements of good practice as can be
universally agreed. Thus this paper aims to derive what will be termed a ‘‘best
practicable approach’’ for EIA and the decommissioning of nuclear power plants.
In deriving a best practicable approach for EIA it is not intended to propose a
prescriptive procedure, rather to illustrate an approach that may be helpful for
organisations and stakeholders concerned with the EIAs for decommissioning
projects.
The basic study approach can be broken into three components:
(1) To determine, through literature reviews, the mandatory and semi-mandatory
legal requirements stemming from Directives, EU Guidance and International
Conventions. This review has been summarised in the introduction to this
paper.
(2) To determine, through literature reviews and web page searches, question-
naire surveys supplemented by direct consultation with key organisations and
individuals (nuclear operators, nuclear safety regulators, EIA practitioners,
researchers and members of public interest groups) what the current regu-
latory procedures are for EIA of decommissioning of nuclear power plants in
European Union member states and accession countries. The main aim here
was to obtain feedback for every one of the study countries and there was no
attempt to include views of all stakeholders in determining the legal context.
Perceptions and expectations for best practice formed an important study area
and involved the review of guidance documents and good practice guides
both from the European Commission and from individual member states, and
a literature review. To gain comprehensive feedback on the study and the
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217204
approach suggested, the data were collated, analysed, and were then dis-
cussed in depth at a two-day workshop (Cassiopee et al., 2001c) which
allowed delegates from those countries investigated to test the accuracy of the
information, and to debate the proposed approach. This workshop involved
59 participants including nuclear operators, nuclear safety regulators, EIA
practitioners, researchers, members of public interest groups, and a number of
representatives of the European Commission also took part. This workshop
allowed the various stakeholders participating to suggest changes where
necessary—the final approach described in this paper incorporates changes
made as a result of this workshop.
(3) To determine, through case study analysis, what lessons could be learnt from
practice of decommissioning and whether elements of good practice could be
extracted. Whilst decommissioning is becoming necessary for a large number
of nuclear reactors, experience to date is still quite limited. However, a case
study was used from each of Germany (Greifswald reactor), Spain (Vandellos
1 reactor) and the UK (Trawsfynydd reactor); in addition a review was
undertaken of case studies of contentious projects in order to identify good
practice in public participation and consultation—13 case studies were used
drawing on experience from Hungary, Spain, UK, Switzerland, Hong Kong,
USA and Japan (detailed in Cassiopee et al., 2001a).
3. An approach for EIA associated with decommissioning a nuclear power
plant
Based on the legal and guidance framework, case study evidence and con-
sultations, an illustrative approach is detailed in Fig. 2 and essentially comprises 20
stages. In practice, the different stages may be organised differently than proposed
here, however it is suggested that all the key elements of the approach are necessary
for a successful EIA to be carried out. Each of these stages is numbered and the
detail of what is expected, both procedurally and in terms of public participation, is
indicated below, along with an explanation of whether the stage has been included
through legal obligations or as an element of good practice.
3.1. Steps 1 and 3: Identification of stakeholders and list of stakeholders
That the input of stakeholders is vital to the success of the scoping stage and
thereby to the entire EIA process, was a clear conclusion both from a review of
the regulatory framework (full consultation with the public concerned is required
by the Arhus Convention) and from the consultation undertaken. Good practice
dictates that it is important to start by identifying all individuals/organisations
wishing to be considered as stakeholders and (subject to their agreement) list their
full contact details in a single, publicly available, document. This stage needs to
be undertaken at the start of the project and will ideally build upon existing
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217 205
stakeholder contacts. Table 2 is a simple checklist to facilitate the initial
identification of stakeholders.
3.2. Step 2: Outline of feasible alternatives
Also at the start of the process, and in parallel with the identification of
stakeholders to save time, an initial outline of feasible alternatives should be
Fig. 2. The suggested Environmental Impact Assessment process for a nuclear power plant
decommissioning project.
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217206
prepared. These alternatives are later screened, on the basis of criteria agreed by
the stakeholders, to obtain a list of the alternative(s) to be assessed in more
detail. This step is in line with the requirement of the Environmental
Assessment Directive to outline the main alternatives considered, although it
goes further than legal obligations in having the stakeholders consider which
will be subject to further study and, therefore, which will be outlined in the
EIS.
3.3. Step 4: Definition of decision-making procedures and criteria
This is the core of the scoping stage and thus the widest support from
stakeholders should be sought through active public participation to define the
decision-making procedures and criteria to be used during the EIA process.
This step goes much further than legal obligations require and meets percep-
tions of good practice, particularly regarding public involvement. Ideally, a
consensus will be reached but, in any case, efforts must be made to integrate
stakeholders’ concerns. Face-to-face meetings which allow a two-way com-
munication process (e.g. public meetings, workshops) are preferred to indirect
means (e.g. questionnaires, allowing for submission of written comments,
surveys, etc.). However, indirect participatory strategies may still be used to
complement two-way communication processes. Further details on the par-
ticipation techniques which may be appropriate at this stage can be found in
Cassiopee et al. (2001b).
Another aspect to be considered at this point is the definition of the project
baseline, specifying the existing situation against which comparisons of potential
environmental impacts should be made.
It is expected that Steps 1–4 would take from 3 to 6 months to complete.
The amount of time required depends to a large extent on the degree of support
for the decommissioning project. If there are disagreements between stake-
holders, repeated meetings may be necessary before reaching an agreement on
the scope.
Table 2
Checklist for identification of stakeholders
. Local residents
. Trades unions
. Media
. Religious groups
. Local community groups
. Commercial associations
. Educational institutions
. Non-governmental organisations
. Independent experts
. National and local government agencies with responsibility for management of natural resources and
welfare of people likely to be affected by the project
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217 207
3.4. Step 5: Alternatives screened according to agreed decision-making criteria
A first screening of the proposed (feasible) alternatives should be undertaken
as part of the public participation procedure at this stage. As for Step 2, the
Environmental Assessment Directive dictates that alternatives outlined should
be considered in the EIS, but this step incorporates good practice in that the
public are involved in the decision on which alternatives are included for further
study.
3.5. Step 6: Public information on agreed decision-making criteria and
remaining alternatives
The public should be informed about the results of this first part of the scoping
stage, i.e. the decision-making procedures and criteria as well as the alternatives
selected for further examination. This step ensures that transparency is main-
tained in the process. The information should be sent directly to the stakeholders
who participated in earlier stages and should be made publicly available. At
present, this goes further than the Environmental Assessment Directive, but can
be considered as a requirement under the Arhus Convention.
3.6. Step 7: Scoping for impacts of remaining alternatives
The remaining alternatives should then be scoped for impacts, in order to
select the final alternative(s) for the remainder of the EIA process. This ensures
that only alternatives that are technically and financially feasible, socially
acceptable and with potentially low environmental impacts are subjected to a
detailed assessment. This is a practical requirement to ensure that resources are
focused on the ‘main alternatives’ as required by the Environmental Assessment
Directive, and involves choosing the option(s) (from the feasible alternatives)
best meeting the established decision-making criteria.
3.7. Step 8: Draft scoping report
As an element of good practice taken from the US EIA system, a draft scoping
report is produced at this stage, establishing the scope of the EIA for the
decommissioning project. The draft scoping report will serve as a working
document; it should be made publicly available and a scoping meeting organised
to discuss it and agree on the final scope of the project. This step is not an obligation
of the Environmental Assessment Directive nor is it suggested in EU Guidance;
though it is compatible with the philosophy of the Arhus Convention for greater
public participation.
The process including the rejection of alternatives not meeting decision-
making criteria (Step 5) through to the production of the draft scoping report
(Step 8) is expected to take approximately 3–6 months.
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217208
3.8. Steps 9 and 10: Discussion and agreement of draft and final scoping reports
As scoping is the key to efficient EIA, helping to focus all resources onto the
significant issues of concern, all stakeholders discuss the draft scoping report, and
outstanding issues or inaccuracies are pointed out at this stage (Step 9). A
notification should be made through the local press as well as by traditional
means (e.g. posting notices or use of bulletin boards in public libraries and local
authorities). Whilst not a legal obligation under the Environmental Assessment at
present, this step is, arguably, required by the Arhus Convention and by EU
Guidance. The information which should be provided to the public in the
notification as part of this step is detailed in Table 3.
In addition, the previously identified stakeholders should be directly notified
of the proceedings and invited to participate in the scoping meeting. Sufficient
time should be allowed between notification and the scoping meeting in order to
allow the public to study the information and form an opinion. This allows the
public an opportunity to express an interest and identify themselves as stake-
holders in the process. Two primary means of participation may be used: indirect
participation (unilateral) through sending written comments and multilateral
participation through a scoping meeting.
The scoping meeting serves as a two-way communication forum where the
draft scoping document can be discussed and agreed. Care should be taken to
ensure the integration of all comments and concerns, and to be flexible and
willing to change the scope of the EIA in order to accommodate all major
concerns.
A final scoping report (Step 10) is then produced and made publicly available
in line with good practice and the requirements of the Arhus Convention for early
and effective communication in the environmental decision-making procedure.
This report incorporates all the changes agreed to the draft report at the
stakeholder meeting, and this document then forms the basis of the EIA to be
undertaken. Further scoping meetings may be needed if discrepancies remain to
be resolved. If, on the other hand, no major opposition arises, another scoping
Table 3
Information to be provided to the public in notification of scoping meeting
. The request for development consent
. The fact that the project is subject to an environmental impact assessment
. Details of the competent authorities responsible for taking the decision or from which relevant
information can be obtained or to which comments (or questions) can be submitted
. An indication of what relevant information is accessible to the public concerned and the places
where and means by which it will be made available
. An invitation to review the information and submit comments, specifying the means to convey the
information and the time frames involved
. An invitation to attend the scoping meeting, specifying the time and place
. Where relevant, the fact that there are transboundary impacts
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217 209
meeting may not be necessary and the final scoping report may be prepared. The
review of the scoping report should become an iterative process until a document
agreeable to all parties is produced.
3.9. Step 11: Determination of the environmental baseline
In order to predict the potential environmental impacts of the proposed project,
as required by the Environmental Assessment Directive, the initial environmental
conditions must be known. Environmental damage varies according to the initial
conditions: for example, a given level of emissions may be more damaging in
ecologically sensitive zones or may surpass the ecosystem’s tolerance level if the
area is already polluted; tall structures may be tolerable in industrial areas but not
within a site of outstanding natural beauty.
The definition of the baseline conditions (e.g. meteorological conditions,
geological formations, groundwater flow direction) also provides data necessary
to make impact predictions. Because the same baseline conditions apply to all
of the options this step can be started before the full scope of the EIA has been
agreed if time is a concern. There may be some unnecessary expenditure
incurred but this would be small compared to the wider project and is likely to
be more than offset by the benefits of completing this stage early in the
process.
3.10. Step 12: Impact identification
Potential environmental impacts are identified at this stage, as required by
the Environmental Assessment Directive, based on parameters related to the
degree of physical and socio-economic impact, as well as according to the
public perceptions and values. For each alternative being evaluated, a separate
analysis needs to be carried out to determine the likelihood of environmental
impacts.
3.11. Step 13: Assessment of the significance of impacts
This step considers the implications of the impacts identified previously and
assesses their significance, as required by the Environmental Assessment Direct-
ive. Significance can be gauged relative to environmental standards or to public
perception for some more subjective impacts, and relative to radiological standards
as required by Directive 96/29/Euratom and the safety case. Frequent dialogue with
stakeholders throughout the Environmental Impact Assessment can, therefore, be
very helpful.
It is important for this step to include an evaluation of the uncertainties
associated with specific assessments. In particular it must be made clear whether
predictions represent best estimate or worst case scenarios, although in most
cases it will be appropriate to present both.
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217210
3.12. Step 14: Development of mitigation measures
One aim of EIA is to try and remove or reduce to acceptable levels all the
impacts which may occur as required by the Environmental Assessment Direct-
ive. Good practice dictates that the identification of possible mitigation measures
must have the agreement of the developer if they are to be included in the EIS.
3.13. Step 15: Listing of residual impacts
Mitigation can rarely remove all the identified impacts and a clear statement has
to be made about the impacts which would still occur even after the implementation
of the mitigation measures. The Environmental Assessment Directive does require
that all impacts are described and assessed, but this step makes it very clear where
mitigation is not possible or might not be fully effective.
3.14. Step 16: Development of a monitoring plan
In recognition of the fact that the evaluation of impacts is subject to
uncertainties, it is appropriate to develop a monitoring plan which would be
able to check that the residual impacts identified are the only ones which occur.
This would ensure that no unexpected impacts arise and that the proposed
mitigation measures are working adequately. This goes beyond the requirements
of the Environmental Assessment Directive but does meet with perceptions of
good practice. If unexpected impacts do arise, this would give an opportunity to
take remedial action.
The study to evaluate the impacts of the alternatives under investigation (Steps
11–16) is expected to last up to 12 months. This timing depends on the
information which is already available and that which must be specifically
collected (e.g. local meteorological and ecological data).
The developer may have an ongoing communication with stakeholders during
this phase in order to ensure that their concerns are being properly addressed and
that local and expert knowledge have been used effectively.
3.15. Steps 17 and 18: Production of EIS
The product of all the environmental studies taking place in Steps 11–16 is
reported in the EIS, which typically is written as the evaluation work is taking
place. The EIS is the public report of the study that has taken place and needs to
convey the information gathered in an understandable way.
After the EIS is produced, it may be issued as a draft version (this is not
required by the Environmental Assessment Directive but would be an element of
good practice) and subjected to a public review. This review is recommended
when the project has proved to be controversial, but the stage may be omitted if
there is already a large degree of agreement. After the final EIS is produced
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217 211
(Step 17), it must be made publicly available and submitted to the competent
authority in line with the requirements of the Environmental Assessment
Directive (Step 18).
3.16. Step 19: EIS review
Once the EIS has been submitted to the competent authority, it forms part of
the information on which a decision is based. As such, it needs to be checked to
ensure that appropriate evaluation techniques have been used and that there is no
undue bias. (The involvement of stakeholders earlier in the process should make
this stage little more than a formality).
The EIS review is normally the responsibility of the competent authority. Each
country, in line with the obligations of the Environmental Assessment Directive,
has defined the procedure for undertaking the EIS review; this normally involves
the public (e.g. allowing them to submit comments, organising public meetings or
hearings) and/or expert committees such as the EIA Commission in the Nether-
lands (see Wood, 1995). Sometimes, although the review is formally the re-
sponsibility of the competent authority, public meetings may need to be organised
by the developer.
3.17. Step 20: Decision
Depending on the country, the decision on the EIS may be the sole decision
required in order to authorise decommissioning or may be but another source of
evidence feeding into the sectoral decision-making process. Decision makers may
approve the proposed development, reject it, or approve it subject to meeting
certain conditions. In any case, the Environmental Assessment Directive indicates
that the decision should be justified and be made publicly available. Once the
decision has been made the EIA process can be said to be complete although the
monitoring programme must be implemented and the results of this programme
must also be made publicly available. If the project is likely to have significant
environmental impacts in a neighbouring country, the authorities in such country,
as well as that country’s concerned public must be considered stakeholders. In
this case, in line with the requirements of the Espoo Convention (United Nations
Economic Commission for Europe, 1991), the information and notifications must
be translated, if relevant.
3.18. All stages
Besides the formal scoping meeting(s) and the formal opportunity to review the
final scoping report, the most effective integration of public concerns will occur
when they are consulted in an ongoing (though maybe informal) manner. Such
ongoing participation can be arranged through an ad hoc organisation, such as a
Citizen’s Advisory Committee or through other non-formal means (e.g. open
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217212
houses) and should remain open for new organisations or individuals to join.
However, if nomajor public controversies arise, consultations may be scaled down.
4. Discussion
In deciding a strategy for decommissioning it should be appreciated that the
cost of different technical and timing options will inevitably be an important
consideration. In many countries, for example, sufficient funding may not be
available to make immediate dismantling of nuclear power plants a feasible
option, regardless of other technical considerations. Such countries may need to
establish funds that will grow over time such that dismantling will be undertaken
when sufficient funds are available (see, for example, UK Nirex et al., 1999). In
countries where nuclear power plants are privately owned, the financial viability
of the companies operating the facilities may not allow certain options such as
immediate dismantling.
The approach discussed above allows such considerations to be taken into
account. For example, referring to Fig. 2, the definition of ‘‘feasible’’ should be
taken to include technical as well as financial feasibility. Thus the procedure can
still be followed, therefore fulfilling legal obligations and using elements of good
practice, but at the same time facilitates dialogue with the public over financial
constraints to alternatives.
Another issue of relevance is the time that should be spent on the consultation.
In fact the approach discussed at the 2-day workshop (Cassiopee et al., 2001c)
did include a timeline, albeit with some flexibility built in. A timeline has been
included in Fig. 2; however, because of the differences in the appropriate
approaches to public participation in different countries and also because of the
different administrative structures which already have variation in their timelines,
this will need to be modified according to circumstance.
Inevitably, a suggested approach like this cannot satisfy entirely all the
stakeholders involved in a decommissioning project. Some stakeholders, particu-
larly some organisations responsible for decommissioning, were unhappy with
the suggested approach as it would impose obligations not formalised in the EIA
Directive, thereby increasing the time and expense involved. Fig. 2 tries to
accommodate this by including ‘‘optional stages’’ which include the production
and review of draft EISs (based on the US system of EIA; see Canter, 1996); the
approach incorporates the draft EIS as a good practice stage which is optional to
facilitate this view. The workshop involving the stakeholders did support the
proposed process, though there was some discussion about the timeline asso-
ciated with the completion of stages. It is clear that existing administrative
procedures in countries vary greatly in terms of the expected timings of some of
these stages, and the large range of time allowed for completion of stages allow
for this, whilst at the same time indicating that an EIA has to be expected to last
1–2 years or more for a project of this kind.
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217 213
The approach suggested in this paper has been written to fully comply with
all the relevant European legislation and guidance and also UNECE Con-
ventions. The process suggested in Fig. 2 clearly takes a long time and is
resource intensive, but at the same time such projects can be contentious and
clearly have a potential for significant environmental impacts if they are not
managed properly. Flexibility has been built into the approach to facilitate the
differences in the legislative and administrative procedures which exist in
different countries, but the main stages of the approach, including the public
participation requirements, provide a means of compliance with all existing
EU legislation.
5. Conclusions
Whilst negotiations to amend the Environmental Assessment Directive pro-
duced some improvements in practice with the amendments in 1997, these fell
short of what many would have considered best practice (Bond and Wathern,
1999) and this can probably be explained by the process involved in negotiating a
Directive (Scott, 1998). However, events outside the sphere of Directive
negotiations are beginning to exert a significant influence on EIA and, specif-
ically, the Arhus Convention will require changes to the text in that it requires
significant enhancement of the public participation procedures within the EIA
process. The recent revision of the European Commission’s screening, scoping
and review guidance reflects these necessary changes.
It is too early to say whether the aim to establish a best-practicable approach
for EIA has been met. Certainly an approach has been established which is
available as advice on the web pages of the Directorate-General for Energy and
Transport of the European Commission, and which can now be applied in
practice to determine its effectiveness; the wide consultation carried out means
that the approach incorporates the requirements of current legal frameworks and
some elements of good practice outlined in guidance whilst being acceptable to at
least some of the developers and stakeholders involved in the decommissioning
process. Of particular significance is the amount of time which has been set aside
for public participation in this proposed approach which exceed the requirements
of current legislation in this area. By focussing on practicability, the approach
should be capable of achieving greater harmonisation of decision-making
procedures relating to decommissioning of nuclear power plants within the
European Union as it uses the Environmental Assessment Directive as one of
the prime vehicles for gathering all the information needed for the decision
process. Indeed, the study is available on the European Commission’s web pages
(Cassiopee et al., 2001a,b,c) and is, therefore, available as an approach to be
followed by organisations responsible for decommissioning.
The approach cannot be considered to represent ‘best practice’ as such an
approach would be likely to meet with great resistance from some organ-
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217214
isations responsible for decommissioning, concerned with potential increases
in cost and time involved in achieving a decision, particularly where some
steps are not legally required. However, by adopting a ‘best practicable’
approach, where legal obligations are met and elements of good practice are
included where they are likely to be accepted, it seems logical that the
procedure has a better chance of being used, and that greater consistency
achieved in this way should lead to greater consistency in the decision-making
procedures overall, although evidence would need to be collected to dem-
onstrate any clear relationship.
There are clearly limitations to the study which have led to the
development of this approach. The study did identify the current legislation
related to EIA of nuclear power plant decommissioning, but though three
case studies from actual decommissioning projects were used, experience in
this area is still limited. In addition, consultation over the approach tried to
be inclusive, but certainly focussed on the nuclear industry with public
involvement being limited primarily to an association of Mayors from
potentially affected communities—their input was extremely useful but
may not represent the strength of feeling of other stakeholders in the
process. The feeling from the stakeholders present at the workshop was that
this approach was workable, though inevitably the stages will be adapted
accordingly.
Whilst developed for nuclear power plants, there is no reason why this
suggested approach cannot be used for any contentious projects where
careful planning and good consultation will save time in the long run. As
it is applied, experience will be able to develop and improve the
approach.
Acknowledgements
The ideas presented in this paper were developed as part of a collaborative
study undertaken for the Nuclear Safety Unit, now part of the Directorate-General
for Energy and Transport, of the European Commission (Ref.: EC Contract B4-
3040/99/MAR/C2) on the application of Environmental Impact Assessment
(EIA) to the decommissioning of nuclear facilities in EU member states and the
applicant countries. The authors wish to express their gratitude to the
Commission services for their helpful comments and advice and also for their
permission to produce this paper, but stress that the views presented in the paper
are those of the authors and not necessarily those of the Commission. Those
organisations involved in the study were the EIA Unit of The University of
Wales, Aberystwyth; Cassiopee, a European Economic Interest group formed of
the waste management agencies of Belgium, France, Germany, Spain, The
Netherlands and United Kingdom; and ECA Global, an environmental
consultancy company based in Barcelona.
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217 215
References
Anon. EU Commission urged to act on nuclear safety. ENDS Daily [Friday 19 May 2000].
Bond AJ. Environmental impact assessment in the UK: background, basics, context and procedure.
Oxford: Chandos, 2000.
Bond AJ, Wathern P. EIA in the European Union. In: Petts J, editor. Handbook of environmental
impact assessment. Oxford: Blackwell; 1999. p. 223–48.
Bond A, O’Sullivan P, Russell S. Harmonising EIA processes for geological repositories for nuclear
waste in the European Union. Impact Assess Proj Apprais 2001;19:205–14.
Braeckeveldt M. Overview of Nuclear Decommissioning. Cassiopee, University of Wales Aberyst-
wyth, ECA Global. Study on EIA for Decommissioning Nuclear Installations. Final Report-Vol-
ume 1-Situation Report. Commission of the European Communities, 2001. Available at http://
europa.eu.int/comm/energy/nuclear/pdf/eur20051_vol1.pdf.
Canter LW. Environmental impact assessment. New York: McGraw-Hill; 1996.
Cassiopee, University of Wales Aberystwyth, ECA Global. Study on EIA for Decommission-
ing Nuclear Installations. Final Report-Volume 1-Situation Report. Commission of the
European Communities; 2001a. Available at http://europa.eu.int/comm/energy/nuclear/pdf/
eur20051_vol1.pdf.
Cassiopee, University of Wales Aberystwyth, ECA Global. Study on EIA for Decommissioning
Nuclear Installations. Final Report-Volume 2-Guidance for Undertaking an EIA of Proposals to
Decommission a Nuclear Power Plant. Commission of the European Communities; 2001b. Avail-
able at http://europa.eu.int/comm/energy/nuclear/pdf/eur20051_vol2.pdf.
Cassiopee, University of Wales Aberystwyth, ECA Global. Study on EIA for Decommissioning Nu-
clear Installations. Final Report-Volume 3-Workshop Report. Commission of the European Com-
munities; 2001c. Available at http://europa.eu.int/comm/energy/nuclear/pdf/eur20051_vol3.pdf.
Commission of the European Communities. Commission Recommendation of 6 December 1999 on
the application of Article 37 of the Euratom Treaty (notified under document number C(1999)
3932). Official J Eur Communities 1999;L324:23–43.
Commission of the European Communities. Proposal for a Directive of the European Parliament and
of the Council providing for public participation in respect of the drawing up of certain plans and
programmes relating to the environment and amending Council Directive 85/337/EEC and 96/61/
EC. Brussels: Commission of the European Communities; 2001.
Council of the European Communities. Council Directive of 27 June 1985 on the assessment of the
effects of certain public and private projects on the environment. Official J Eur Communities 1985;
C175:40–9.
Council of the European Union. Directive 96/29/Euratom laying down basic safety standards for the
protection of the health of workers and the general public against the dangers arising from ionizing
radiation. Official J Eur Communities 1996;39:1–114.
Council of the European Union. Council Directive 97/11/EC of 3 March 1997 amending Directive 85/
337/EEC on the assessment of the effects of certain public and private projects on the environ-
ment. Official J Eur Communities 1997;40:5–14.
Department of the Environment. Preparation of environmental statements for planning projects that
require environmental assessment: a good practice guide. London: HMSO; 1995.
Department of the Environment Transport and the Regions/National Assembly for Wales. Environ-
mental impact assessment. A guide to procedures. Tonbridge: Thomas Telford; 2000.
Environmental Resources Management. Guidance on EIA—EIS review. Brussels: Commission of the
European Communities; 2001a.
Environmental Resources Management. Guidance on EIA—scoping. Brussels: Commission of the
European Communities; 2001b.
Environmental Resources Management. Guidance on EIA—screening. Brussels: Commission of the
European Communities; 2001c.
Forsstrom H, Taylor D. Current policy on radioactive waste management in the European Union.
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217216
IAEA International Conference on the Safety of Radioactive Waste Management, Cordoba, Spain;
2000.
Glasson J, Therivel R, Chadwick A. Introduction to environmental impact assessment. Principles and
procedures, process, practice and prospects. London: UCL Press; 1999.
International Atomic Energy Agency. Joint Convention on the Safety of Spent Fuel Management and
on the Safety of Radioactive Waste Management. International Atomic Energy Agency; 1997.
Available at http://www.iaea.org/worldatom/Documents/Legal/jointconv.shtml.
O’Sullivan P, Bond AJ, Russell S, Dagg S, Russell I. Environmental Impact Assessments and Geo-
logical Repositories for Radioactive Waste. Final Report, Volume 3: Central and East European
Countries. Luxembourg: Office for Official Publications of the European Communities; 1999a.
O’Sullivan P, McKirdy B, Askarieh M, Bond AJ, Russell S, Dagg S, Russell I, Alonso J, Santiago
JJ. Environmental Impact Assessments and Geological Repositories for Radioactive Waste.
Volume 1: Main Report. Luxembourg: Office for Official Publications of the European Com-
munities; 1999b.
Palerm JR. Public participation in environmental decision making: examining the Aarhus convention.
J Environ Assess Policy Manag 1999;1:229–44.
Scott J. EC environmental law. London: Longman; 1998.
Taylor D. Radioactive Waste Management in the European Union. Seminar on Nuclear Energy and
Radioactive Waste. Brussels; 2000.
UK Nirex, DBE, Pricewaterhouse Coopers, Sofres Conseil, C&E, ANDRA, COVRA, ENRESA,
ONDRAF/NIRAS. Schemes for financing radioactive waste storage and disposal. Brussels: Euro-
pean Commission, Directorate General for Environment, Nuclear Safety and Civil Protection;
1999.
United Nations Economic Commission for Europe. Convention on environmental impact assessment
in a transboundary context. Geneva: United Nations Economic Commission for Europe; 1991.
United Nations Economic Commission for Europe. Convention on access to information, public
participation in decision-making and access to justice in environmental matters. Geneva: United
Nations Economic Commission for Europe, Committee on Environmental Policy; 1998.
Vankerckhoven P. Decommissioning of nuclear installations in the European Union. Supporting docu-
ment for the preparation of an EC Communication on the subject of decommissioning nuclear
installations in the EU. Brussels: European Commission, Directorate General for Environment,
Nuclear Safety and Civil Protection; 1998.
Walker LJ, Johnston J. Guidelines for the assessment of indirect and cumulative impacts as well as
impact interactions. Brussels: Commission of the European Communities, Directorate General
XI; 1999.
Wathern P. Environmental impact assessment: theory and practice. London: Routledge; 1988.
Wood C. Environmental impact assessment: a comparative review. Harlow: Longmann Scientific and
Technical; 1995.
A. Bond et al. / Environ. Impact Asses. Rev. 23 (2003) 197–217 217