entsog | entsog - central eastern europe grip · 2018. 11. 29. · total cs power (mw) expected...

226
GAS REGIONAL INVESTMENT PLAN 2014 – 2023 ANNEX B : INFRASTRUCTURE PROJECTS GRIP Central Eastern Europe

Upload: others

Post on 26-Apr-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GAS REGIONAL INVESTMENT PLAN

2014 – 2023

ANNEX B : INFRASTRUCTURE PROJECTS

GRIP

Central Eastern Europe

Page 2: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 2

1 AustriaGas Connect Austria Gmbh

Page 3: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Bidirectional Austrian-Czech Interconnector (BACI, formerly LBL project)

Gas Connect Austria GmbH

Gas Connect Austria GmbH

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-021 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

27.02.2012 2013

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2

+58,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2019

+24,00

Date of Request Year Funding GrantedTEN-E Requests

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Pipeline on Austrian territory, GAS

CONNECT AUSTRIA GmbH (100%)

Pipeline on Czech territory, NET4GAS,

s.r.o (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 3

AUSTRIA

Page 4: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entry

Security of Supply, Market Integration, Diversification of Sources, Diversification of Routes

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Reinthal - Bidirectional Austrian-Czech Interconnector

PROJECTED CAPACITY INCREASES

Hub AustriaHub Czech Republic255,13

255,13

The Bidirectional-Austrian-Czech-Interconnector (BACI) will be the first bidirectional connection between the Austrian and the Czech Market.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub AustriaHub Czech Republic

GRIP Central Eastern Europe 2014 – 2023 Annex B | 4

AUSTRIA

Page 5: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 5

1 AustriaTauerngasleitung GmbH

Page 6: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of common interest

Yes

Tauerngasleitung Gas Pipeline Project

Tauerngasleitung GmbH

Tauerngasleitung GmbH

Pipeline including CS

www.tauerngasleitung.at

Interested by PCI ?

IGAs

Web Link

TRA-N-035 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

Not yet

28.04.2010

26.04.2006

2011

2007

Planned0%

2014 Q2FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12014 Q4

+290,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2015 Q1

2018/4

+66,00

Date of Request Year Funding GrantedTEN-E Requests

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

TIGAS-Erdgas Tirol GmbH (3%) Rohöl-Aufsuchungs

Aktiengesellschaft (10%)

Energie AG Oberösterreich

(18%)

KELAG-Kärntner Elektrizitäts-

Aktiengesellschaft (4%)

E.ON Ruhrgas AG (47%)

Salzburg AG für Energie, Verkehr und Telekommunikation

(18%)

Private Financing (70,00%)

Multilateral Financing (30,00%)

* In 2013, the sponsor’s shareholders announced that they intended to amend the sponsor’s ownership structure through a tendering process.

*

GRIP Central Eastern Europe 2014 – 2023 Annex B | 6

AUSTRIA

Page 7: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entryYes exitYes entryYes exitYes entryYes exitYes entry

Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional, Back-up for renewables, Power-to-gas, Biogas, SoS: Investments will be necessary, especially in cross-border gas transmission capacity, with a view to diversifying sources of supply, and gas transmission systems in general, especially where capacities may be needed in an emergency to supply areas with capacity shortfalls. The TGL is inline with these objectives, which focus mainly on security of supplies. Market Integration: By linking the Central European (Southern Germany) with the South-East European (mainly Italy) natural gas market, the TGL increasesinteroperability between gas markets in Europe which are still separate, develop new natural gas sources for these markets and therefore significantly improve competition within a European single market for natural gas. Diversificationof European natural gas supplies: By creating the infrastructure required for a functioning North-South/South-North system to develop the North African and Arab supply region, including liquefied natural gas (LNG) for theMediterranean region, the TGL will reduce dependence on individual suppliers in the North and East.,

Hub Germany (NCG)Haiming (bayernets) - DE / Burghausen-Auerbach (Austrian Storage) - TGLHaiming (bayernets) - DE / Burghausen (Transit) - TGL Tauerngas Leitung (Austria)

Tauerngas Leitung (Austria)Haiming (bayernets) - DE / Burghausen (Austrian Hub) - TGL Hub Germany (NCG)

136,65180,7430,14

148,61

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Hub Germany (NCG)

Hub Germany (NCG)Storage Austria

Tarvisio - IT / Arnoldstein (Transit) - TGL

Haiming-Oberkappel (OGE) - DE / Burghausen (Transit) - TGLHaiming (OGE) - DE / Burghausen-Auerbach (Austrian Storage) - TGL

PROJECTED CAPACITY INCREASES

Tauerngas Leitung (Austria)Hub Germany (NCG)Storage Austria

Hub Italia

143,82

314,9665,4033,82

Pipeline (incl. compressor stations) in North-South direction. TGL allows feed significant volumes from different sources from South-East regions towards Central Europe.

Own financing 30%. Loans 70% of which 70-80% fromcommercial banksand the rest from multilateral financing

20-30% of 70% of the overall external financing needs

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Tauerngas Leitung (Austria)

Hub Germany (NCG)Hub Austria

Hub ItaliaTauerngas Leitung (Austria)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 7

AUSTRIA

Page 8: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 8

2 BulgariaBulgartransgaz EAD

Page 9: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Bulgartransgaz EAD

Bulgartransgaz EAD

Storage Facility

http://www.bulgartransgaz.bg/en/index.php

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

Planned0%

FID

Construction

Commissioning

Last completed Phase :

Storage facility

Working volume (mcm)

Not defined yet

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

2020

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Bulgartransgaz EAD (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 9

BULGARIA

Page 10: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Security of Supply, Market integration, N-1 National, N-1 Regional (Central Eastern Europe, South Eastern Europe, Balkan Region),

,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Provision is made for the construction of new gas storage facility on the territory of Bulgaria with a view to ensuring security of supply and a stimulus to gas market liberalisation. Different opportunities for the construction of a new gasstorage in suitable geological structures are considered - in salt caverns, depleted gas field (inland or offshore) or aquifer.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 10

BULGARIA

Page 11: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Interconnection Turkey-Bulgaria

Bulgartransgaz EAD

Bulgartransgaz EAD

Pipeline including CS

http://www.bulgartransgaz.bg/en/index.php

Interested by PCI ?

IGAs

Web Link

TRA-N-140 Non-FID

Promoter

Operator

TEN-E Project ?

2

Not relevant

0%

Not relevant

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2

+205,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2016

Considered TPA Regime

Considered Tariff Regime Not applicable

Not applicable

Bulgartransgaz EAD for the gas pipeline

section on the territory of Bulgaria

(100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 11

BULGARIA

Page 12: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional (Central and Eastern Europe, South Eastern Europe, Balkan Region), The interconnection Turkey-Bulgaria is a key project whose realization shall lead to the increase of the security of supply and the opportunity for diversification of gas supply not only to Bulgaria, but to the Central and South-Eastern Europe region as well. Theproject contributes directly to the diversification of gas sources: alternative gas producers - countries from the Caspian region, Turkish LNG terminals and Middle East.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector ITB (Turkey - Bulgaria)

PROJECTED CAPACITY INCREASES

Hub Greece92,00

The interconnection is foreseen to be built as a development to the existing connection of Bulgartransgaz EAD and Botas – Turkey systems by creating the technical opportunity for enabling bi-directional physical flow of natural gasbetween both systems. Thus a significantly greater security of gas supply to our country can be achieved, meeting the N-1 security standard and diversification of natural gas supply sources. Preliminary plans are for a staged projectdevelopment, with the commissioning in 2014 or 2015 of the first stage depending on the development of the Turkish gas transmission system.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Turkey (Imports)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 12

BULGARIA

Page 13: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Rehabilitation, Modernization and Expansion of the National Transmission System

Bulgartransgaz EAD

Bulgartransgaz EAD

Pipeline including CS

http://www.bulgartransgaz.bg/en/index.php

Interested by PCI ?

IGAs

Web Link

TRA-N-298 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

0%

2015FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2017

Considered TPA Regime

Considered Tariff Regime Not applicable

Not applicable

Bulgartransgaz EAD (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 13

BULGARIA

Page 14: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional (Central and Eastern Europe, South Eastern Europe, Balkan Region), The modernisation, rehabilitationand expansion of the existing gas transmission network are directly linked to the planned new interconnections with Greece (IGB), Romania (IBR), Turkey (ITB) and Serbia (IBS), the integration of the national and the transit gastransmission system on the territory of Bulgaria and the development of the large cross-border gas projects in the region. The efficient use of the new entry and exit points from/to Bulgartransgaz gas transmission networks is directlylinked to the technical possibilities of the existing gas transmission infrastructure on the territory of Bulgaria to ensure sufficient capacity and suitable technical conditions to accommodate the transport of the planned new natural gasquantities and to the available storage capacity and and the expansion of the gas storage facility in Chiren unique on the territory of the country accordingly. ,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

A set of activities involving rehabilitation, modernisation and expansion of the existing national gas transmission infrastructure with a view to guaranteeing the possibility of the national gas transmission system to ensure the transport ofsufficient natural gas volumes through the territory of the country using the planned new interconnections to other countries from the region of South Eastern, Central and Eastern Europe and in the context of the large cross-border gasprojects in the region. The project mostly include compressor stations modernisation (CS Valchi Dol and CS Polski Senovets) as well as in-line inspections, complete overhauls and replacement of gas pipeline sections of the main gaspipelines that are part of the annularly built gas transmission system and construction regulating lines at the exits of gas pipeline branches off the main and transit gas pipeline to enhance its reliability, security and capacity.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 14

BULGARIA

Page 15: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Bulgartransgaz EAD

Bulgartransgaz EAD

Storage Facility

http://www.bulgartransgaz.bg/en/index.php

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

0%

2014FID

Construction

Commissioning

Last completed Phase :

Storage facility

Working volume (mcm)

UGS Chiren

+450,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

2017

+5,80

+5,80

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Bulgartransgaz EAD (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 15

BULGARIA

Page 16: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entryYes exitYes entry

Security of Supply, Market integration, N-1 National, N-1 Regional (Central Eastern Europe, South Eastern Europe, Balkan Region), In this moment UGS Chiren covers mainly seasonal fluctuations in domestic consumption and ensures thesecurity of supply. Additional stored volumes and higher withdrawal and injection rates will serve Bulgarian and regional gas markets (Greek, Romanian, Macedonian and Serbian) via the existing and the new interconnections - IBR, IGB,

,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Storage Bulgaria (NGTS)

UGS - BG - Chiren - Bulgartransgaz

PROJECTED CAPACITY INCREASES

Hub Bulgaria (NGTS)Storage Bulgaria (NGTS)Hub Bulgaria (NGTS)

Storage Bulgaria (NGTS)

65,00

65,0065,0065,00

The project for expansion of the existing gas storage facility Chiren consists of staged capacity increse of the gas storage facility higher stored gas volumes, higher pressures in the gas reservoir and reaching higher average dailywithdrawal and injection flow rates.Two options of reaching maximum capacities are mainly under consideration:

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Bulgaria (NGTS)Storage Bulgaria (NGTS)Hub Bulgaria (NGTS)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 16

BULGARIA

Page 17: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 17

2 BulgariaICGB EAD

Page 18: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Interconnector Greece Bulgaria - IGB

DEPA S.A.

ICGB a.d.

Pipeline including CS

www.icgb.eu

Interested by PCI ?

IGAs

Web Link

TRA-N-149 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not yet

0%

Yes

Permitting0%

2014 Q2FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

22014 Q1

+182,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2014 Q3

2016/1

+10,00

Considered TPA Regime

Considered Tariff Regime Negotiated (e.g. Exemption)

Negotiated (e.g. Exemption)

Bulgarian Energy Holding EAD (50%)

IGI Poseidon S.A. (50%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 18

BULGARIA

Page 19: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryYes exitYes entryYes exit

Security of Supply, Market integration (Greece, Bulgaria, Romania, Hungary, FYROM, Serbia), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Greece, Bulgaria), N-1 Regional (NSI East Gas), Back-up forrenewables, Power-to-gas, The project will contribute significantly in the itegration of the market area, specifically the South Eastern Europe, and will allow to alleviate to a great extend the dependency of countries in the area to a singlesource/counterpart.Taking into account that the objective of the project is to bring additional import quantities of natural gas in Bulgaria and South Eastern Europe it significantly improves the resilience of the system in both short (theadditional quantities will be able to cover daily peak demands) and long term.Specifically for the long term, the diversification in route, supply source as well as counterparts will have a great positive impact on the resilience of the system and will be able to cater to any forecasted increase in demand over thecoming years.The impact of the project in the systems flexibility under disruption (n-1 rule) will be significant taking into account that it will create a new interconnections carrying gas from a new source allowing new counterparts to enter the market.A possible disruption in any of the other import sources (including the regional disruption of Russian gas) will NOT AFFECT this one having a great positive impact on the remaining flexibility of the system.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector Greece-Bulgaria

Komotini - TAP / IGB

Stara Zagora - IGB / BG

PROJECTED CAPACITY INCREASES

Trans-Adriatic Pipeline (Greece)Interconnector Greece-Bulgaria (Bulgaria)Hub Bulgaria (NGTS)

Interconnector Greece-Bulgaria (Bulgaria)

82,00

82,0082,0082,00

An onshore natural gas pipeline that will connect Komotini in Greece to Stara Zagora in Bulgaria. The IGB pipeline is being developed by ICGB AD, with shareholders IGI-Poseidon S.A. and Bulgarian Energy Holding EAD

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Trans-Adriatic Pipeline (Greece)Interconnector Greece-Bulgaria Hub Bulgaria (NGTS)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 19

BULGARIA

Page 20: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 20

2 BulgariaMinistry of Economy and Energy of Republic of Bulgaria

Page 21: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Interconnection Bulgaria - Serbia

Bulgarian Ministry of Economy and energy (MEE)

Bulgartransgaz EAD

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-137 Non-FID

Promoter

Operator

TEN-E Project ?

3

No

0%

No

Planned0%

2014FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

22014

+155,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2015

2015

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 21

BULGARIA

Page 22: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector BG RS

PROJECTED CAPACITY INCREASES

Hub Bulgaria (NGTS)Hub Serbia51,00

51,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Bulgaria (NGTS)Hub Serbia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 22

BULGARIA

Page 23: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 23

2 BulgariaSouth Stream Bulgaria AD(Bulgarian Shareholder Bulgarian Energy Holding EAD)

Page 24: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

South Stream Bulgaria - Stage I

South Stream Bulgaria AD (Bulgarian

Bulgartransgaz EAD

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-308 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2015

Considered TPA Regime

Considered Tariff Regime Not applicable

Not applicable

Bulgartransgaz EAD (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 24

BULGARIA

Page 25: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

South Stream into Bulgaria (BG)

PROJECTED CAPACITY INCREASES

Hub Bulgaria (NGTS)162,50

First stage of the South Stream interconnection to the Bulgarian network, as understood by ENTSOG based on e-mail exchange.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

South Stream (Russia)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 25

BULGARIA

Page 26: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

South Stream Bulgaria - Stage II

South Stream Bulgaria AD (Bulgarian

Bulgartransgaz EAD

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-309 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2016

Considered TPA Regime

Considered Tariff Regime Not applicable

Not applicable

Bulgartransgaz EAD (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 26

BULGARIA

Page 27: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

South Stream into Bulgaria (BG)

PROJECTED CAPACITY INCREASES

Hub Bulgaria (NGTS)62,10

Second stage of the South Stream interconnection to the Bulgarian network, as understood by ENTSOG based on e-mail exchange.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

South Stream (Russia)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 27

BULGARIA

Page 28: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

South Stream Bulgaria - Stage III

South Stream Bulgaria AD (Bulgarian

Bulgartransgaz EAD

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-310 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2017

Considered TPA Regime

Considered Tariff Regime Not applicable

Not applicable

Bulgartransgaz EAD (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 28

BULGARIA

Page 29: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

South Stream into Bulgaria (BG)

PROJECTED CAPACITY INCREASES

Hub Bulgaria (NGTS)15,50

Third and final stage of the South Stream interconnection to the Bulgarian network, as understood by ENTSOG based on e-mail exchange.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

South Stream (Russia)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 29

BULGARIA

Page 30: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 30

3 CroatiaPlinacro d.o.o.

Page 31: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Ionian Adriatic Pipeline

Plinacro Ltd

Plinacro Ltd

Pipeline including CS

www.plinacro.hr

Interested by PCI ?

IGAs

Web Link

TRA-N-068 Non-FID

Promoter

Operator

TEN-E Project ?

2

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

3

+540,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2015

2020

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Fieri to Montenegro border, Ministry of

Economy , Trade and Energy (Albania)

(100%)

Montenegro, Ministry of Economy (Montenegro) (100%)

Bosnia and Herzegovina, BH Gas

(Bosnia and Herzegovina);

Ministry of Foreign Trade and Economic

Relations (BiH) (100%)

Croatia (From Split to Montenegro border), Plinacro Ltd; Ministry of Economy (Croatia)

(100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 31

CROATIA

Page 32: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entryYes entryYes exitYes exit

Security of Supply, Market integration (Market Integration benefits for Croatiaand the region (Albania, Montenegro, Bosnia and Herzegovina and neighbouring countries), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional (Balkan region ), Back-up for renewables,

Hub MontenegroIonic-Adriatic Pipeline - IAP / ME 15,00

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Ionic-Adriatic Pipeline (Croatia)Ionic-Adriatic Pipeline (Croatia)

Ionic-Adriatic Pipeline - IAP / ABTrans-Adriatic Pipeline - TAP / Ionic-Adriatic Pipeline - IAPIonic-Adriatic Pipeline - IAP / Split - HRIonic-Adriatic Pipeline - IAP / BH

PROJECTED CAPACITY INCREASES

Ionic-Adriatic Pipeline (Croatia)Hub CroatiaHub Bosnia Herzegovina

Hub Albania

30,00

30,00150,0075,00

The pipeline will cross the territory along the Adriatic coast from Fieri in Albania via Montenegro to Split in Croatia and will be linked to the existing Croatian gas transmission system (main direction Bosiljevo Split). The Ionian-AdriaticPipeline is considered a part of the Energy Community Gas Ring, which is the concept of gasification for the entire region, proposed by the WB Study and accepted by the Gas Fora of the Energy Community.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Ionic-Adriatic Pipeline (Croatia)Trans-Adriatic Pipeline (Greece)Ionic-Adriatic Pipeline (Croatia)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 32

CROATIA

Page 33: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

2023

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2

+30.00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

Not part of TEN-E

No

Interconnection Croatia-Bosnia and Herzegovina (Licka Jesenica-Rakovica-Trzac-Bosanska

Plinacro Ltd

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-303 Non-FID

Promoter

Operator

TEN-E Project ?

None

Plinacro Ltd, BH Gas

GRIP Central Eastern Europe 2014 – 2023 Annex B | 33

CROATIA

Page 34: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Croatia45.00Rakovica (HR) / Trzac (BA)

PROJECTED CAPACITY INCREASES

Hub Bosnia and Herzegovina

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

GRIP Central Eastern Europe 2014 – 2023 Annex B | 34

CROATIA

Page 35: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

NO

Interconnection Croatia/Bosnia and Herzegovina (Slobodnica- Bosanski Brod-Zenica)

Plinacro Ltd

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-066 Non-FID

Promoter

Operator

TEN-E Project ?

2

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+6,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2018

2019 +0,90

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Plinacro Ltd, BH Gas

GRIP Central Eastern Europe 2014 – 2023 Annex B | 35

CROATIA

Page 36: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Slobodnica- Bosanski Brod-Zenica

PROJECTED CAPACITY INCREASES

Hub Bosnia Herzegovina44,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Croatia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 36

CROATIA

Page 37: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

2018

# of Pipelines, nodes, CS

Total Pipeline Length (km)

3

+29.00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

Not part of TEN-E

No

Interconnection Croatia-Bosnia and Herzegovina (South)

Plinacro Ltd

Pipeline including CS

www.plinacro.hr

Interested by PCI ?

IGAs

Web Link

TRA-N-302 Non-FID

Promoter

Operator

TEN-E Project ?

Noneparts in B&H, BH Gas

(100%)

Croatian part of both options, Plinacro

d.o.o. (100%)

Plinacro Ltd, BH Gas

GRIP Central Eastern Europe 2014 – 2023 Annex B | 37

CROATIA

Page 38: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

South Interconnection of Croatia and B&H - the pipeline is actually branch from planned regional Ionic Adriatic Pipeline - IAP.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Ionic-Adriatic Pipeline (Croatia)45.00

PROJECTED CAPACITY INCREASES

Hub Bosnia and Herzegovina

Security of Supply, Market integration, Diversification of sources, N-1 National (for B&H), N-1 Regional, The aim of the project is to establish a new supply route for B&H providing a diversified and reliable natural gas supply.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

GRIP Central Eastern Europe 2014 – 2023 Annex B | 38

CROATIA

Page 39: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

NO

Plinacro Ltd

Plinacro Ltd

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-070 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2

+102,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2018

2023

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 39

CROATIA

Page 40: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Hub Serbia176,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Croatia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 40

CROATIA

Page 41: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Plinacro Ltd

Plinacro Ltd

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-086 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

2017FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

5

+296,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2018 +0,90

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 41

CROATIA

Page 42: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

No exitYes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Rogatec

PROJECTED CAPACITY INCREASES

Hub Croatia165,00165,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Slovenia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 42

CROATIA

Page 43: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

2027 +0.90

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2

+220.00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

Not part of TEN-E

Yes

Plinacro Ltd

Plinacro Ltd

Pipeline including CS

www.plinacro.hr

Interested by PCI ?

IGAs

Web Link

TRA-N-083 Non-FID

Promoter

Operator

TEN-E Project ?

NoneCroatian section, Plinacro (100%)

Italian section, tbd (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 43

CROATIA

Page 44: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

No entryNo exit

Covering the territory from the gas node Omišalj on the island of Krk (Croatian Gas Transmission System) via Adriatic Sea to Casal Borsetti (Italian Gas Transmission System)

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub ItaliaHub Croatia

506.00506.00

Casalborsetti

PROJECTED CAPACITY INCREASES

Hub ItaliaHub Croatia

Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (For Croatia), N-1 Regional, Back-up for renewables, It will be new cross border transmission between Croatia andItaly; fits in the idea of Adriatic Gas Ring,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

GRIP Central Eastern Europe 2014 – 2023 Annex B | 44

CROATIA

Page 45: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Plinacro Ltd

LNG Hrvatska d.o.o.

LNG Terminal

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

Regasification facility

Expected volume (bcm/y)

LNG RV Croatia

+2,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction No

Total CS Power (MW)

Send-out (mcm/d)

End of permitting phase

Ship size (m3)

Reloading ability ?

2017 +5,50

Considered TPA Regime

Considered Tariff Regime Not applicable

Not applicable

Plinacro (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 45

CROATIA

Page 46: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

Security of Supply, Market integration (Croatia, markets of Central and Western Europe (Austria, Slovenia, Hungary, Slovakia, Check Republic) as well as the Balkan countries (Serbia, B&H, Diversification of sources,Diversification of routes, N-1 National (for Croatia), N-1 Regional, Back-up for renewables,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

LNG RV (Regasification Vessel) to Croatia

PROJECTED CAPACITY INCREASES

Hub Croatia60,50

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

LNG Terminals Croatia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 46

CROATIA

Page 47: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

2017

2018 +0.90

# of Pipelines, nodes, CS

Total Pipeline Length (km)

3

+103.60

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

Not part of TEN-E

Yes

Plinacro Ltd

Plinacro Ltd

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-090 Non-FID

Promoter

Operator

TEN-E Project ?

1

GRIP Central Eastern Europe 2014 – 2023 Annex B | 47

CROATIA

Page 48: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Croatia506.00

PROJECTED CAPACITY INCREASES

Hub Slovenia

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

GRIP Central Eastern Europe 2014 – 2023 Annex B | 48

CROATIA

Page 49: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

2017

2019 +0.90

# of Pipelines, nodes, CS

Total Pipeline Length (km)

5

+692.00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

Not part of TEN-E

Yes

LNG main gas transit pipeline (Part of North-South Gas Corridor) Zlobin-Bosiljevo-Sisak-Kozarac-Slobodnica

Plinacro Ltd

Plinacro Ltd

Pipeline including CS

www.plinacro.hr

Interested by PCI ?

IGAs

Web Link

TRA-N-075 Non-FID

Promoter

Operator

TEN-E Project ?

None

Plinacro (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 49

CROATIA

Page 50: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

The pipeline will be construted on the territory of Croatia from the gas node Zlobin via Bosiljevo, Sisak, the gas node Kozarac to Slobodnica. It will be the "backbone" of the croatian gas system.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

PROJECTED CAPACITY INCREASES

Security of Supply, Market integration (Croatia, Hungary, Bosnia and Herzegovina, Serbia), Reverse Flows, Diversification of routes, N-1 National (for Croatia), Back-up for renewables, This main transit gas pipeline is the future strategicgas transmission connector of great significance and is an integral part of the North South European Corridor designated the North-South (Baltic Adriatic) Gas Connection. Its purpose is linking the Polish and Croatian LNG (LiquefiedNatural Gas) solutions under the umbrella of the European Commission (EC). This project is foreseen under the Gas Forum administered by the Energy Community Secretariat, and although in Croatia, is regionally significant. The maintransit gas pipeline Zlobin-Bosiljevo-Sisak-Kozarac-Slobodnica:

- will be connected to the future Ionian Adriatic Pipeline (IAP)

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

GRIP Central Eastern Europe 2014 – 2023 Annex B | 50

CROATIA

Page 51: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 51

4Czech RepublicNET4GAS, s.r.o.

Page 52: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Bidirectional Austrian Czech Interconnection (BACI)

NET4GAS, s.r.o.

NET4GAS, s.r.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-133 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

27.02.2012 2013

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+58,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2019

+24,00

Date of Request Year Funding GrantedTEN-E Requests

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Reinthal (AT/CZ border) to

Baumgarten, GAS CONNECT AUSTRIA

GmbH (100%)

-Reinthal (CZ/AT border), NET4GAS, s.r.o.

(100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 52

CZECH REPUBLIC

Page 53: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryYes exit

Security of Supply, Market integration (CEE Region), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (CZ, AT), N-1 Regional (CEE Region), Back-up for renewables, Power-to-gas, Biogas, The BidirectionalAustrian-Czech interconnector (BACI) ensures transmission capacity between the two member states and facilitates better market integration and security of gas supply also for adjacent countries. It contributes to the diversification ofgas supply and the increased transportation opportunities to and from countries like Hungary, Poland, Germany, Italy, France, Slovenia, Croatia and Slovakia and access to new and existing trading markets.BACI enhances the market development due to access to underground gas storages both on the Austrian and Czech side and therefore enhances the market development by providing peak regulation and the flexibility of gas flow.BACI is a key element in creating a well-functioning internal market in the CEE region due to access to existing and new import infrastructures such as new LNG regasification plants, Nord Stream, South Stream and unconventional gassources.With BACI the CEE region would become less vulnerable to a supply disruption through the Ukraine and Belarus route and therefore the region will have an increased security of supply.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Reinthal - Bidirectional Austrian-Czech Interconnector

PROJECTED CAPACITY INCREASES

Hub AustriaHub Czech Republic254,00

254,00

The BACI will be a new infrastructure directly connecting the Austrian and Czech market. It will be connected to the existing Czech transmission system via CS (NET4GAS, s.r.o.) and to the Austrian transmission system viaBaumgarten (GAS CONNECT AUSTRIA GmbH). The BACI will enable capacity transmission for the first time between these two member states and it will facilitate better market integration and security of gas supply also for adjacentcountries like Hungary, Poland, Germany, Italy, France, Slovenia, Croatia and Slovakia due to the creation of additional transportation opportunities. The project will also increase the overall flexibility of the Czech, Austrian and alsoPolish system by diversification of gas supply routes and by connecting UGS in the Czech Republic and Austria.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub AustriaHub Czech Republic

GRIP Central Eastern Europe 2014 – 2023 Annex B | 53

CZECH REPUBLIC

Page 54: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Connection to Oberkappel

NET4GAS, s.r.o.

NET4GAS, s.r.o.

Pipeline including CS

www.tauerngasleitung.at/5GL

Interested by PCI ?

IGAs

Web Link

TRA-N-135 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+110,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2022

+2,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Pipeline on Austrian territory, potential

partner in Austria - in discussion (100%)

Pipeline on Czech territory, NET4GAS,

s.r.o. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 54

CZECH REPUBLIC

Page 55: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryYes exit

Security of Supply, Market integration (CEE Region), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (CZ, AT), N-1 Regional (CEE Region), Back-up for renewables, Power-to-gas, Biogas, Increase thediversification of gas supply routes (i.e. especially Russian gas from Nord Stream and Norwegian sources to the Southern part of Europe; African, LNG and Caspian gas sources from the South / South-East to the North / North West part ofEurope).Therefore the project is also part of the 5GL Project together with TGL (AT) and Monacco (GER) as well as the planned interconnection to Slovenia that takes a comprehensive approach for completion the gas network in this region.

,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Oberkappel (Net4Gas)

PROJECTED CAPACITY INCREASES

Hub AustriaHub Czech Republic55,00

55,00

The project will interconnect the existing transmission pipelines in the Czech Republic with AT/DE border at Oberkappel. It will be the first interconnection between these states and it will be connected to Penta West as well as WAGpipeline (AT) and to the Southern branch of the N4G transmission system (CZ). Connection to Oberkappel is a part of the “5 Gas-market Link - of the partners Tauerngasleitung GmbH (AT), Bayernets GmbH (DE), Plinovodi s.r.o. (SLO)and NET4GAS, s.r.o. (CZ). As part of the 5GL Project the Oberkappel project would be interconnected indirectly also to the TGL pipeline project, the storages 7Fields and Haidach (AT) as well as to the gas grid in Southern Germany atHaiming/Burghausen.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub AustriaHub Czech Republic

GRIP Central Eastern Europe 2014 – 2023 Annex B | 55

CZECH REPUBLIC

Page 56: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Poland-Czech Republic Interconnection within the North-South Corridor (STORK II)

NET4GAS, s.r.o.

NET4GAS, s.r.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-136 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+107,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2019

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

(CZ and PL border), NET4GAS, s.r.o. (CZ)

(100%)

from Kedzierzyn to

border), GAZ-SYSTEM S.A. (PL) (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 56

CZECH REPUBLIC

Page 57: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entry

Security of Supply, Market integration (CEE Region (mainly CZ, PL)), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (CZ, PL), N-1 Regional (CEE Region), Back-up for renewables, Power-to-gas, Biogas, Theproject aims to increase the cross-border capacity between Poland and the Czech Republic by establishing a large transportation corridor that will allow for flexible transport of gas in Central Europe in direction North-South.Increase the security of gas supply and provide the overall flexibility for the CEE region and diversify the supply routes for the CEE region.Improve European gas grid interconnection.Increase the security and reliability of the cross-border gas transmission between the Czech Republic and Poland (fulfilment of N-1 rule in Poland). Create a robust, well-functioning internal market in the Czech Republic and Poland and promote the competition. Contribute to the creation of the integrated and competitive gas market in CEE region.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector CZ-PL

PROJECTED CAPACITY INCREASES

Hub Czech RepublicHub Poland220,50

153,40

The STORK II interconnector pipeline will be part of the Czech and Polish transmission system and will increase cross-border capacity between these two countries by establishing a large transportation corridor that will allow flexibletransport of gas in Central Europe in direction North-South.The development of the physical interconnection between Poland and Czech Republic will contribute to reinforcement of the effective operation of the gas transmissionsystems, efficient gas exchange between the markets, as well as increase of the security of supply not only for Poland and Czech Republic, but also for the CEE region by enabling the supply link with the European gas market (NCG, CEGH

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Czech RepublicHub Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 57

CZECH REPUBLIC

Page 58: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 58

5 GermanyGASCADE Gastransport GmbH

Page 59: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

Expansion of Nord Stream connection to markets in western Europe - Exit Eynatten

GASCADE Gastransport GmbH

GASCADE Gastransport GmbH

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-324 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

3

+440,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2022

+203,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 59

GERMANY

Page 60: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Eynatten 1 (BE) // Lichtenbusch / Raeren (DE)Bunde (DE) / Oude Statenzijl (H) (NL) (GASCADE)

PROJECTED CAPACITY INCREASES

Hub Netherlands (VIP NL/Gaspool)Hub Belgium (H-Zone)374,00

234,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Germany (GASPOOL)Hub Germany (GASPOOL)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 60

GERMANY

Page 61: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

Expansion of Nord Stream connection to markets in western Europe - Entry Greifswalder Bodden area

GASCADE Gastransport GmbH

NEL Gastransport GmbH

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-323 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2022

+171,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 61

GERMANY

Page 62: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Greifswald / NEL

PROJECTED CAPACITY INCREASES

Hub Germany (GASPOOL)857,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Nord Stream (Russia Greifswald)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 62

GERMANY

Page 63: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

Installation of Nord Stream onshore project

GASCADE Gastransport GmbH

GASCADE Gastransport GmbH

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-289 FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

Permitting0%

2012FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

22013

+90,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2013 Q1

2014/1

+27,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GASCADE (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 63

GERMANY

Page 64: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes exit

Market integration (GASPOOL / NCG (Gernsheim)), Diversification of sources,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

GernsheimEynatten 1 (BE) // Lichtenbusch / Raeren (DE)

PROJECTED CAPACITY INCREASES

Hub Belgium (H-Zone)Hub Germany (NCG)105,60

30,00

None

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Germany (GASPOOL)Hub Germany (GASPOOL)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 64

GERMANY

Page 65: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

Installing a reverse flow in Mallnow

GASCADE Gastransport GmbH

GASCADE Gastransport GmbH

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-292 FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

Permitting0%

2013FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2013

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2013

2014

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GASCADE (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 65

GERMANY

Page 66: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

Reverse Flows, Diversification of sources,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Mallnow

PROJECTED CAPACITY INCREASES

Yamal (Poland)168,00

new metering station

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Germany (GASPOOL)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 66

GERMANY

Page 67: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

new net connection from Rehden to Drohne (new covenant from NEP2012)

GASCADE Gastransport GmbH

GASCADE Gastransport GmbH

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-291 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12016 Q4

+26,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2017

2018/1

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GASCADE (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 67

GERMANY

Page 68: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

Market integration (GASPOOL / NCG),

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Drohne GASCADE / OGE

PROJECTED CAPACITY INCREASES

Hub Germany (NCG)144,00

It is necessary to increase the capacity of the pipeline between the OGE Infrastructure (market area of NCG) and GASCADE (Market area of GASPOOL).This connection will increase the capacity by 6 GW to ensure the supply in south-westGermany.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Germany (GASPOOL)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 68

GERMANY

Page 69: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 69

5 GermanyGasunie Deutschland Transport Services GmbH

Page 70: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

Expansion of Nord Stream connection to markets in western Europe - Exit Bunde-Oude

Gasunie Deutschland Transport Services GmbH

Gasunie Deutschland Transport Services GmbH

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-316 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+25,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2020/3

+30,00

+0,90

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 70

GERMANY

Page 71: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

No exitNo exitYes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Bunde (DE) / Oude Statenzijl (H) (NL) (GUD)

PROJECTED CAPACITY INCREASES

Hub Netherlands (VIP NL/Gaspool)Hub Netherlands (VIP NL/Gaspool)

Hub Netherlands (VIP NL/Gaspool)676,00169,00338,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Germany (GASPOOL)Hub Germany (GASPOOL)Hub Germany (GASPOOL)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 71

GERMANY

Page 72: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Extension of existing gas transmission capacity in the direction to Denmark - 1. Step

Gasunie Deutschland Transport Services GmbH

Gasunie Deutschland Transport Services GmbH

Pipeline including CS

www.gasunie.de

Interested by PCI ?

IGAs

Web Link

TRA-F-231 FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

Construction0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2014/4

+15,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Gasunie Deutschland (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 72

GERMANY

Page 73: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

Security of Supply, Market integration, )o Better connection of the gas hubs (TTF in the Netherlands and market area GASPOOL in Germany);o Compensation of the depletion of Danish gas fields and better connection of gas hubs;o Connection of new storages to the GUD-grid.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Ellund (GUD)

PROJECTED CAPACITY INCREASES

Hub Denmark (Ellund)50,81

None

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Germany (GASPOOL)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 73

GERMANY

Page 74: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Extension of existing gas transmission capacity in the direction to Denmark - 2. Step

Gasunie Deutschland Transport Services GmbH

Gasunie Deutschland Transport Services GmbH

Pipeline including CS

www.gasunie.de

Interested by PCI ?

IGAs

Web Link

TRA-N-232 FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

Construction0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2

+63,50

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2015/2016

+16,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Gasunie Deutschland (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 74

GERMANY

Page 75: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

Security of Supply, Market integration, o Better connection of the gas hubs (TTF in the Netherlands and market ared GASPOOL in Germany);o Compensation of the depletion of Danish gas fields and better connection of gas hubs;o Connection of new storages to the GUD-grid.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Ellund (GUD)

PROJECTED CAPACITY INCREASES

Hub Denmark (Ellund)40,56

None

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Germany (GASPOOL)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 75

GERMANY

Page 76: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 76

5 GermanyGasunie Ostseeanbindungsleitung GmbH

Page 77: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

Expansion of Nord Stream connection to markets in western Europe - Entry Greifswald

Gasunie Deutschland Transport Services GmbH

Gasunie Ostseeanbindungsleitung GmbH

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-321 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+100,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2020/3

+60,00

+0,90

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 77

GERMANY

Page 78: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

No entryYes entryNo entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Greifswald / GOAL

PROJECTED CAPACITY INCREASES

Hub Germany (GASPOOL)Hub Germany (GASPOOL)

Hub Germany (GASPOOL)1.188,00679,00338,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Nord Stream (Russia Greifswald)Nord Stream (Russia Greifswald)Nord Stream (Russia Greifswald)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 78

GERMANY

Page 79: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 79

5 GermanyGRTgaz Deutschland GmbH

Page 80: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

Gernsheim-MIDAL

GRTgaz Deutschland

GRTgaz Deutschland GmbH

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-327 FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

Construction0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2013/4

+8,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 80

GERMANY

Page 81: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Gernsheim

PROJECTED CAPACITY INCREASES

Hub Germany (NCG)106,60

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Germany (GASPOOL)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 81

GERMANY

Page 82: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 82

5 GermanyOpen Grid Europe GmbH

Page 83: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Open Grid Europe GmbH

Open Grid Europe GmbH

Production Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

Production facility

Expected volume (bcm/y)

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

End of permitting phase

2016/4

Considered TPA Regime

Considered Tariff Regime Not applicable

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 83

GERMANY

Page 84: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 84

GERMANY

Page 85: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

Stepwise change-over to physical H-gas operation of L-gas networks

Open Grid Europe GmbH

Open Grid Europe GmbH

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-244 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

Planned0%

2020FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2020

Considered TPA Regime

Considered Tariff Regime Not applicable

Not applicable

OGE (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 85

GERMANY

Page 86: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Security of Supply, Market integration, o Security of Supplyo Market Integration (Increase of competition)o A decline in availability of L-gas necessitates action.Open Season 2008: The project prioritisation process has been carried out in a non-discriminatory manner based on criteria suggested by BNetzA. It takes into account the factors competition, security of supply, as well as networkefficiency. Capacities were allotted to new market entrants. North-south and west-east de-bottlenecking strengthens security of supply.Future projects: The overall economic benefit of a physical change-over from L (low calorific) to H-gas (high calorific) is higher than permanent conversion. Furthermore, enabling access of storage and gas fired power stations to thenetwork necessitates investments. These measures also serve both market integration and security of supply.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Stepwise change-over to physical H-gas operation of L-gas networks (due to decreasing L-gas supply)

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 86

GERMANY

Page 87: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

System enhancements, including the connection of gas-fired power plants, storages and the integration of power to gas facilities

Open Grid Europe GmbH

Open Grid Europe GmbH

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-243 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

Not relevant

Planned0%

2020FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2020

Considered TPA Regime

Considered Tariff Regime Not applicable

Not applicable

GRIP Central Eastern Europe 2014 – 2023 Annex B | 87

GERMANY

Page 88: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 88

GERMANY

Page 89: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 89

5 Germanyterranets bw GmbH

Page 90: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

2015 Q1

2015/4

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12014 Q1

+70.00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

No

0%

No

Planned0%

2013 Q4FID

Construction

Commissioning

Last completed Phase :

Not part of TEN-E

Not defined yet

Nordschwarzwaldleitung

terranets bw GmbH

terranets bw GmbH

Pipeline including CS

www.terranets-bw.de

Interested by PCI ?

IGAs

Web Link

TRA-N-228 Non-FID

Promoter

Operator

TEN-E Project ?

NoneNOS 1, terranets bw

(100%) NOS 2, terranets bw

(100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 90

GERMANY

Page 91: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

No entry

pipeline between Au am Rhein, coupling to TENP and Leonberg/Stuttgart

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Germany (NCG)72.00Au am Rhein

PROJECTED CAPACITY INCREASES

Hub Germany (NCG)

Security of Supply, Diversification of sources, Diversification of routes, Firm capacity can be provided to downstream distribution network operator. Security of Supply will be increased in south-west Germany.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

GRIP Central Eastern Europe 2014 – 2023 Annex B | 91

GERMANY

Page 92: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 92

5 GermanyStorengy Deutschland GmbH

Page 93: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Considered TPA Regime

Considered Tariff Regime Negotiated (e.g. Exemption)

Negotiated (e.g. Exemption)

2014/4

+3.00

+7.00

Storage facility

Working volume (mcm)

Peckensen Storage

+180.00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

Not relevant

0%

No

Construction0%

FID

Construction

Commissioning

Last completed Phase :

Not part of TEN-E

Yes

Storengy

Storengy Deutschland GmbH

Storage Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

Storengy Deutschland (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 93

GERMANY

Page 94: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Extension of the existing salt cavity gas storage.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

PROJECTED CAPACITY INCREASES

Security of Supply, Market integration (Western and Central Europe), Apart from the benefits listed above, the projects will contribute to increased flexibility of the system which will have a positive impact on both market integration and security of supply. Thanks to its location (on the link between the NGC market area and the Gaspool market area), the project will have a positive expected influence on price convergence and arbitrage opportunities.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

GRIP Central Eastern Europe 2014 – 2023 Annex B | 94

GERMANY

Page 95: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Considered TPA Regime

Considered Tariff Regime Negotiated (e.g. Exemption)

Negotiated (e.g. Exemption)

2017/4

+1.00

+3.00

Storage facility

Working volume (mcm)

Peckensen Storage

+100.00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

Not relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

Not part of TEN-E

Yes

Storengy

Storengy Deutschland GmbH

Storage Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

Storengy Deutschland (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 95

GERMANY

Page 96: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Extension of the existing salt cavity gas storage.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

PROJECTED CAPACITY INCREASES

Security of Supply, Market integration (Western and Central Europe), Apart from the benefits listed above, the projects will contribute to increased flexibility of the system which will have a positive impact on both market integration and security of supply. Thanks to its location (on the link between the NGC market area and the Gaspool market area), the project will have a positive expected influence on price convergence and arbitrage opportunities.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

GRIP Central Eastern Europe 2014 – 2023 Annex B | 96

GERMANY

Page 97: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 97

6 HungaryFGSZ Ltd.

Page 98: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

Csepel connecting pipeline

FGSZ Ltd

FGSZ Ltd.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-019 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

2014 Q3FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12016 Q1

+14,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2016 Q1

2016/4

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 98

HUNGARY

Page 99: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 99

HUNGARY

Page 100: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Ercsi-Szazhalombatta

FGSZ Ltd

FGSZ Ltd.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-061 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

2014 Q4FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12016 Q1

+11,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2016 Q1

2017/3

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 100

HUNGARY

Page 101: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Vecsés MGT / FGSZ

PROJECTED CAPACITY INCREASES

Hub HungaryHub Hungary (SK-HU Interconnector)51,00

25,50

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub HungaryHub Hungary (SK-HU

GRIP Central Eastern Europe 2014 – 2023 Annex B | 101

HUNGARY

Page 102: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

Hajduszoboszlo CS

FGSZ Ltd

FGSZ Ltd.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-065 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

2017 Q4FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12018 Q2

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2019 Q2

2020/1

+5,70

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 102

HUNGARY

Page 103: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 103

HUNGARY

Page 104: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Local Odorisation - FGSZ

FGSZ Ltd

FGSZ Ltd.

Pipeline including CS

www.fgsz.hu

Interested by PCI ?

IGAs

Web Link

TRA-N-124 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Permitting0%

2014 Q1FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2014 Q3

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2014 Q3

2015/3

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

FGSZ (100%)

Private Financing (100,00%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 104

HUNGARY

Page 105: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Market integration ( The overall flexibility of the system is enhanced through AT/HU border capacity.), o The Hungarian projects taken as a whole main aim, is to enhance the flexibility of the Hungarian transmission system by connectingto neighbouring systems, ensuring reserves flow availability, and guaranteeing flow deliverability which will enhance the transmission systems security of supply position along with helping with further market integration. ,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Elimination of central odorisation in the western part of Hungary, and establishment of local odorisation

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 105

HUNGARY

Page 106: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Romanian-Hungarian reverse flow Hungarian section

FGSZ Ltd

FGSZ Ltd.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-286 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Planned0%

2013 Q2FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

32014 Q1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2014 Q1

2015/4

+13,50

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 106

HUNGARY

Page 107: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryYes entryNo exitNo entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Hub Romania

Csanadpalota

PROJECTED CAPACITY INCREASES

Hub HungaryHub RomaniaHub Hungary

Hub Hungary

76,85

51,2012,6076,85

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub RomaniaHub RomaniaHub Hungary

GRIP Central Eastern Europe 2014 – 2023 Annex B | 107

HUNGARY

Page 108: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Slovenian-Hungarian interconnector

FGSZ Ltd

FGSZ Ltd.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-325 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

2015 Q2FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12016 Q3

+41,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2016 Q3

2017/4

+7,50

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 108

HUNGARY

Page 109: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector SI-HU

PROJECTED CAPACITY INCREASES

Hub HungaryHub Slovenia45,25

45,25

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub HungaryHub Slovenia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 109

HUNGARY

Page 110: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Városföld CS

FGSZ Ltd

FGSZ Ltd.

Pipeline including CS

www.fgsz.hu

Interested by PCI ?

IGAs

Web Link

TRA-N-123 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

2014 Q3FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12015 Q3

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2016 Q1

2017/3

+5,70

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

FGSZ (100%)

Private Financing (100,00%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 110

HUNGARY

Page 111: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entry

Market integration (Increase AT/HU border capacity, Security of Supply of Western Hungary, New power plant supply at Budapest region, Reverse fllow HU>AT, Create capacity RO>AT), o The Hungarian projects taken as a whole mainaim, is to enhance the flexibility of the Hungarian transmission system by connecting to neighbouring systems, ensuring reserves flow availability, and guaranteeing flow deliverability which will enhance the transmission systems securityof supply position along with helping with further market integration. ,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Mosonmagyarovar

PROJECTED CAPACITY INCREASES

Hub HungaryHub Austria153,00

25,00

Compressor station extension, 5,7 MW

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub HungaryHub Austria

GRIP Central Eastern Europe 2014 – 2023 Annex B | 111

HUNGARY

Page 112: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

FGSZ Ltd

FGSZ Ltd.

Pipeline including CS

www.fgsz.hu

Interested by PCI ?

IGAs

Web Link

TRA-N-018 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

2014 Q1FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12017 Q4

+210,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2015 Q1

2017/3

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

FGSZ (100%)

Private Financing (100,00%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 112

HUNGARY

Page 113: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entryYes exitYes entry

Security of Supply, Market integration (Increase AT/HU border capacity, Security of Supply of Western Hungary, new power plant supply, Reverse fllow HU>AT, Increase capacity Sk>HU and HU>SK, Create capacity RO>AT), ReverseFlows, Diversification of sources, o The Hungarian projects taken as a whole main aim, is to enhance the flexibility of the Hungarian transmission system by connecting to neighbouring systems, ensuring reserves flow availability, andguaranteeing flow deliverability which will enhance the transmission systems security of supply position along with helping with further market integration. ,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Hub Austria

Vecsés MGT / FGSZ

Mosonmagyarovar

PROJECTED CAPACITY INCREASES

Hub HungaryHub AustriaHub Hungary

Hub Hungary (SK-HU Interconnector)

25,00

51,0025,50

153,00

Pipeline between Városföld-Ercsi and nodes, DN1000, PN100, 210 km.This project will enable the Mosonmagyarovar interconnection point to reach its full capacity of 153 GWh/d from Austria to Hungary.It will also enable theMosonmagyarovar interconnection point to realize reverse flow capacity up to 153 GWh/d from Hungary to Austria as well.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub HungaryHub Hungary (SK-HU Hub Hungary

GRIP Central Eastern Europe 2014 – 2023 Annex B | 113

HUNGARY

Page 114: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 114

6 HungaryHungarian Gas Storage

Page 115: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

E.ON Földgaz

E.ON Hungary Storage

Storage Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

No

0%

No

FEED0%

2012 Q4FID

Construction

Commissioning

Last completed Phase :

Storage facility

Working volume (mcm)

Pusztaederics2013 Q1

+340,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

2013 Q2

2013

+2,50

+2,90

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

E.ON Hungary Storage (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 115

HUNGARY

Page 116: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryYes exit

Market integration, Diversification of routes,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

UGS - HU - FGSZ/E.ON Hungary

PROJECTED CAPACITY INCREASES

Hub HungaryStorage Hungary27,50

31,90

��

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub HungaryStorage Hungary

GRIP Central Eastern Europe 2014 – 2023 Annex B | 116

HUNGARY

Page 117: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Not defined yet

E.ON Földgaz

E.ON Hungary Storage

Storage Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Market test0%

2015 Q4FID

Construction

Commissioning

Last completed Phase :

Storage facility

Working volume (mcm)

Zsana2016 Q1

+2.140,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

2016 Q3

2016/4

+17,20

+28,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 117

HUNGARY

Page 118: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryYes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

UGS - HU - FGSZ/E.ON Hungary

PROJECTED CAPACITY INCREASES

Hub HungaryStorage Hungary189,20

308,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub HungaryStorage Hungary

GRIP Central Eastern Europe 2014 – 2023 Annex B | 118

HUNGARY

Page 119: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 119

6 HungaryMagyar Gaz Tranzit Zrt.

Page 120: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

AGRI Pipeline - Hungarian section

Magyar Gaz Tranzit Zrt.

MGT Hungarian Gas Transit Ltd.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-195 FID

Promoter

Operator

TEN-E Project ?

1

no

0%

No

0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2023*

Considered TPA Regime

Considered Tariff Regime Not applicable

Not applicable

Hungarian section, MVM,SOCAR,GOGC,R

OMGAZ (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 120

HUNGARY

Page 121: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

The project is in feassibility phase

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 121

HUNGARY

Page 122: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

Slovak-Hungarian interconnector (Vecsés-Szada-Balassagyarmat)

Magyar Gaz Tranzit Zrt.

MGT Hungarian Gas Transit Ltd.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-148 FID

Promoter

Operator

TEN-E Project ?

1

no

0%

No

Construction0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

22014

+110,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2013

2014/1

Considered TPA Regime

Considered Tariff Regime regulated

regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 122

HUNGARY

Page 123: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryYes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Balassagyarmat

PROJECTED CAPACITY INCREASES

Hub SlovakiaHub Hungary (SK-HU Interconnector)127,40

50,90

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub SlovakiaHub Hungary (SK-HU

GRIP Central Eastern Europe 2014 – 2023 Annex B | 123

HUNGARY

Page 124: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

South Stream Hungary

Magyar Gaz Tranzit Zrt.

MGT Hungarian Gas Transit Ltd.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-196 FID

Promoter

Operator

TEN-E Project ?

1

Not relevant

45%

Not relevant

50%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12015

+220,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2014

2015/1

Considered TPA Regime

Considered Tariff Regime Not applicable

Not applicable

GRIP Central Eastern Europe 2014 – 2023 Annex B | 124

HUNGARY

Page 125: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

South Stream (Bata, Nagykanizsa) (HU)

PROJECTED CAPACITY INCREASES

Hub Hungary224,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

South Stream (Russia)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 125

HUNGARY

Page 126: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 126

7 PolandGas Transmission Operator GAZ-SYSTEM S.A.

Page 127: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Gas Interconnection Poland-Lithuania (GIPL)

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A.

Pipeline including CS

en.gaz-system.pl/nasze-inwestycje/integracja-z-europejski-systemem/polska-litwa/

Interested by PCI ?

IGAs

Web Link

TRA-N-212 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

30.04.2010 2012

Planned0%

2015FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2

+534,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2018

+16,00

Date of Request Year Funding GrantedTEN-E Requests

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Lithuanian section, AB Amber Grid

(100%)

Polish section, Gas Transmission

Operator GAZ-SYSTEM S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 127

POLAND

Page 128: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

No exitYes entryYes exit

Security of Supply, Market integration (market areas in the Baltic States and Central-Eastern Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Lithuania and possibly Latvia, Estonia), N-1 Regional(the Baltic Sea region), Back-up for renewables, The very aim of GIPL is the integration of the isolated gas markets of the Baltic States into the EU gas grid, by introducing the alternative gas supply route to the Baltic States. Thisinterconnection will diversify the gas supply sources, increase the security of supply and will serve for the enhancement of competition in the gas market of the Baltic States.For the Baltic States, GIPL will provide the access both to EU gas spot market and to the global LNG market via LNG terminal in In the long-term perspective, it may also be used to import shale-gas from Poland, if theproduction reaches into large scale level. For the Polish market players, GIPL will provide the opportunity of using Latvian Incukalns UGS. Also through GIPL, gas could be supplied to currently non-gasified areas in Poland and Lithuania.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector PL-LT

PROJECTED CAPACITY INCREASES

Hub PolandHub Lithuania

Hub Lithuania63,7029,0068,00

GIPL aims to connect the gas transmission systems in Poland and Lithuania and, consiquently, enable the integration of the isolated gas markets in the Baltic States (and Finland) with the Polish and EU gas markets contributing to thecreation of the regional gas market, enhancing competition and the security of gas supply. The project will also provide an access to the global LNG market for the Baltic States (via the LNG terminal in The construction ofGIPL, except the above benefits for security and diversification of gas supplies in the Baltic region, will allow to connect the Baltic States with the CEE countries, thus providing strategic link between the BEMIP and North-South prioritycorridors in this part of Europe.

TEN-E (obtained for studies), support from other EU funds is expected

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub PolandHub LithuaniaHub Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 128

POLAND

Page 129: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Priority Project

No

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A.

LNG Terminal

en.gaz-system.pl/terminal-lng/

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

FID0%

2010FID

Construction

Commissioning

Last completed Phase :

Regasification facility

Expected volume (bcm/y) +5,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction No

Total CS Power (MW)

Send-out (mcm/d)

End of permitting phase

Ship size (m3)

Reloading ability ?

2014

+320.000,00

+13,68

216.000,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Gas Transmission Operator GAZ-

SYSTEM S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 129

POLAND

Page 130: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

Security of Supply, Diversification of sources, Diversification of routes, N-1 National (Poland and possibly Lithuania, Latvia, Estonia, Denmark, Slovakia and Hungary), N-1 Regional (Baltic Sea region, Central-Eastern Europe), Back-up forrenewables, The LNG terminal in Swinoujscie will have an impact on:increasing security of supply in the Baltic Sea and CEE regions by diversifying supply routes, sources (the first new physical source of supply for both regions) and counterparts (access to global LNG market);creating well-interconnected gas infrastructure in the Baltic Sea and CEE regions;eliminating the energy islands, as the terminal in Swinoujscie may play the role of regional LNG terminal for the Baltic States and Finland (transport of gas via Gas Interconnection Poland-Lithuania or transport by LNG vessels);enhancing competition on regional markets;promoting natural gas as a reliable, competitive and environmentally-friendly source of energy e.g. in the transport sector (maritime transport);creating a physical hub in Swinoujscie and/or a virtual hub in Poland;establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in theBaltic Sea region and in Central-Eastern Europe.The LNG terminal in contributes to North-South gas interconnections in Central Eastern and South Eastern Europe, as the supplies from may be directed through upgraded transmission system in Poland (theNorth-South Corridor in Poland), PL-CZ and PL-SK interconnections towards the South, to other CEE countries.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Swinoujscie

PROJECTED CAPACITY INCREASES

Hub Poland150,48

The LNG terminal in will be the first LNG terminal in the Baltic Sea region. It will come on stream in 2014 with annual re-gasification capacity of 5 bcm/y. In the following years, depending on the increase of demand for gas, itwill be possible to increase the capacity up to 7,5 bcm/y, without the need to increase the area on which the terminal will be constructed. The terminal in will consist of two storage tanks, each with the capacity of 160 tcm.The LNG terminal in will offer its regasification capacities not only to gas consumers in Poland, but also in the Baltic Sea region (supplies to be directed via Gas Interconnection Poland-Lithuania and/or LNG ships) and inCentral-Eastern Europe (supplies within the North-South Gas Interconnections).

EEPR, ERDF (Operational Programme Infrastructure and Environment), TEN-E

Equity, commercial banks EIB, EBRD

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

LNG Terminals Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 130

POLAND

Page 131: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

Physical reverse flow on the metering station in Mallnow

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A. (ISO)

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-326 FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Construction0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2013

2013

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Gas Transmission Operator GAZ-

SYSTEM S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 131

POLAND

Page 132: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Mallnow

PROJECTED CAPACITY INCREASES

Yamal (Poland)168,00

The project aims to introduce physical reverse flow on the Yamal-Europe pipeline (flow in the direction from DE to PL). The project increases security of supply to Poland by diversifying supply sources and routes. Implementation of theproject facilitates the access of the network users in Poland to the gas market in Germany.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Germany (GASPOOL)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 132

POLAND

Page 133: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

PL - CZ interconnection

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-273 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Planned0%

2017FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+107,60

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2019

+16,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Czech section, NET4GAS, s.r.o.

(100%)

Polish section, Gas Transmission

Operator GAZ-SYSTEM S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 133

POLAND

Page 134: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

No entryYes entryYes exit

Security of Supply, Market integration (market areas in Central-Eastern Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland, possibly Slovakia and Hungary), N-1 Regional (Central-EasternEurope), Back-up for renewables, Implementation of PL-CZ interconnection will have an impact on:increasing the security of gas supply and providing the overall flexibility for the CEE region and diversifying the supply routes for the CEE region;improving European gas grid interconnection;increasing the security and reliability of the cross-border gas transmission between the Czech Republic and Poland (fulfilment of N-1 rule in Poland);creating a robust, well-functioning internal market in the Czech Republic and Poland and promoting the competition;contributing to the creation of an integrated and competitive gas market in the CEE region;establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in Central-Eastern Europe.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector CZ-PL

PROJECTED CAPACITY INCREASES

Hub PolandHub Czech Republic

Hub Poland105,40195,90150,60

The project aims to increase the cross-border capacity between Poland and the Czech Republic by establishing a large transportation corridor that will allow for flexible transport of gas in Central-Eastern Europe within the North-Southcorridor.

Support from EU funds is expected

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Czech RepublicHub Czech RepublicHub Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 134

POLAND

Page 135: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

PL - DK interconnection (Baltic Pipe)

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A.

Pipeline including CS

en.gaz-system.pl/nasze-inwestycje/integracja-z-europejski-systemem/baltyckibaltic-pipe/

Interested by PCI ?

IGAs

Web Link

TRA-N-271 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

30.06.2008

24.04.2009

2009

2010

Planned0%

2015FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2

+324,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2020

Date of Request Year Funding GrantedTEN-E Requests

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Gas Transmission Operator GAZ-

SYSTEM S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 135

POLAND

Page 136: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryYes exit

Security of Supply, Market integration (market areas in the Baltic Sea region and Central-Eastern Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland, Denmark), N-1 Regional (the Baltic Searegion), Back-up for renewables, Baltic Pipe will have a significant impact on:increasing security of supply in the Baltic Sea region by diversifying supply routes, sources and counterparts;creating well-interconnected gas infrastructure in the Baltic Sea region;enhancing competition on the regional markets;promoting natural gas as a reliable, competitive and environmentally-friendly source of energy e.g. in the power generation sector. The Baltic Pipe project also contributes to North-South gas interconnections in Central Eastern and South Eastern Europe, as the project which will allow to transport gas from North Sea deposits to the CEE countries, namely to the CzechRepublic and Slovakia (via the North-South corridor in Poland, PL-CZ and PL-SK interconnections).,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector PL-DK

PROJECTED CAPACITY INCREASES

Hub DenmarkHub Poland90,40

90,40

Baltic Pipe aims to connect the gas transmission systems in Poland and Denmark and thus cover the higher import needs of Danish and Swedish markets originating from declining production in the Danish part of the North Sea. Theproject will also cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in the Baltic States and Central-Eastern Europe.

TEN-E (obtained), support from other EU funds is expected

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub DenmarkHub Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 136

POLAND

Page 137: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

PL - SK interconnection

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A.

Pipeline including CS

en.gaz-system.pl/nasze-inwestycje/integracja-z-europejski-systemem/polska-slowacja/

Interested by PCI ?

IGAs

Web Link

TRA-N-275 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

28.02.2011 2012

Planned0%

2017FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+164,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2019

+29,10

Date of Request Year Funding GrantedTEN-E Requests

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Polish section, Gas Transmission

Operator GAZ-SYSTEM S.A. (100%)

Slovak section, eustream, a.s. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 137

POLAND

Page 138: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entryYes entry

Security of Supply, Market integration (market areas in Central-Eastern Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland, Slovakia and possibly Hungary), N-1 Regional (Central-EasternEurope), Back-up for renewables, Implementation of PL-SK interconnection will have an impact on:creating the cross-border capacity between Poland and Slovakia by establishing a large transportation corridor that will allow for flexible transport of gas in Central Europe within the North-South axis;increasing the security of gas supply and diversification of supply routes for the CEE region;improve European gas grid interconnection;increasing the security and reliability of the cross-border gas transmission between Slovakia and Poland (contribution to N-1 standard in Poland and Slovakia);creating a robust, well-functioning internal market in Slovakia and Poland and promote the competition;establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in Central-Eastern Europe.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector PL - SK

PROJECTED CAPACITY INCREASES

Hub PolandHub Poland

Hub Slovakia141,60129,50171,70

The main goal of the project is to create an important part of the North-South gas interconnections in Central-Eastern Europe by implementing a missing interconnection between the transmission systems in Poland and Slovakia and,thus, increase the security of gas supplies in Central-Eastern Europe through the diversification of supply sources and routes, as well as integration of Sub-Carpathian Market Area and enhancing market functionality.

TENE (obtained), support from EU funds is expected

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub PolandHub SlovakiaHub Slovakia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 138

POLAND

Page 139: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-276 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2015

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Gas Transmission Operator GAZ-

SYSTEM S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 139

POLAND

Page 140: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryYes entry

Security of Supply, Market integration (integration of market areas in the Baltic Sea region and Central-Eastern Europe with Western Europe (GASPOOL and NetConnect in Germany)), Reverse Flows, Diversification of sources,Diversification of routes, N-1 National (Poland and possibly Lithuania, Latvia, Estonia, Slovakia, Hungary), N-1 Regional (the Baltic Sea region, Central-Eastern Europe), Back-up for renewables, The upgrade of the capacity of the entrypoints in Lwowek and Wloclawek on the Yamal-Europe pipeline will have an impact on:enhancing competition in Poland and other countires in the Baltic and CEE regions by significantly facilitating the access to the Western European gas markets (in particular GASPOOL and NetConnect in Germany);increasing security of supply in the Baltic Sea and CEE regions by diversifying supply routes and counterparts (the access to the Western European gas markets);creating well-interconnected gas infrastructure between Western Europe (Germany), the Baltic Sea and CEE regions;contributing to elimination of the energy islands, as the project may constitute a source of gas supplies for the Baltic States and Finland (via Gas Interconnection Poland-Lithuania);establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in theBaltic Sea region and in Central-Eastern Europe.

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

WloclawekLwowek

PROJECTED CAPACITY INCREASES

Hub PolandHub Poland183,00

36,60

The main objective of the project is to upgrade the capacity of the entry points in Lwówek and Wloclawek on the Yamal-Europe pipeline. The project will enable to benefit from the economies of scale, as relatively low investment costswill significantly increase the possibility of gas deliveries via physical reverse flow (currently virtual reverse flow is available only) on the Yamal-Europe pipeline to entry into the transmission system in Poland and later on in the BalticStates (via Gas Interconnection Poland-Lithuania) and other CEE countries (via the North-South Gas Interconnections). This will in turn enhance the access of gas markets players in these countries to well-developed market area inGermany.

Support from EU funds is expected

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Yamal (Poland)Yamal (Poland)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 140

POLAND

Page 141: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

Upgrade of gas infrastructure in northern and central Poland

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A.

Pipeline including CS

en.gaz-system.pl/nasze-inwestycje/krajowy-system-przesylowy/

Interested by PCI ?

IGAs

Web Link

TRA-F-248 FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

FID0%

2007FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

5

+875,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2014

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Gas Transmission Operator GAZ-

SYSTEM S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 141

POLAND

Page 142: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Security of Supply, Market integration (market areas in the Central-Eastern Europe and possibly in the Baltic States), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland and possibly Slovakia, Hungary,Lithuania, Latvia and Estonia), N-1 Regional (Central-Eastern Europe, Baltic Sea region), Back-up for renewables, ,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

The project consists of the internal pipelines that are currently being constructed in northern and central Poland with the aim to enhance functionality of the transmission system in Poland and, thus, provide adequate techincalconditions to distribute natural gas supplied to the LNG terminal in The project is strictly linked to the development of gas infrastructure within the North-South gas interconnections in Central Eastern and South EasternEurope. Implementation of the internal pipelines will contribute to increasing the security of supply sources, routes and counterparts, as well as to providing the overall flexibility for the gas market in Poland and the whole CEE region.

EEPR, ERDF (Operational Programme Infrastructure and Environment) Equity, commercial banks

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 142

POLAND

Page 143: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A.

LNG Terminal

en.gaz-system.pl/terminal-lng/

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Planned0%

2014FID

Construction

Commissioning

Last completed Phase :

Regasification facility

Expected volume (bcm/y) +2,50

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction Yes

Total CS Power (MW)

Send-out (mcm/d)

End of permitting phase

Ship size (m3)

Reloading ability ?

2020

+160.000,00

+6,84

216.000,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Gas Transmission Operator GAZ-

SYSTEM S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 143

POLAND

Page 144: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

Security of Supply, Diversification of sources, Diversification of routes, N-1 National (Poland and possibly Lithuania, Latvia, Estonia, Denmark, Slovakia and Hungary), N-1 Regional (Baltic Sea region, Central-Eastern Europe), Back-up forrenewables, The extension of the LNG terminal in Swinoujscie will have an impact on:increasing security of supply in the Baltic Sea and CEE regions by diversifying supply routes, sources (the first new physical source of supply for both regions) and counterparts (access to global LNG market);creating well-interconnected gas infrastructure in the Baltic Sea and CEE regions;eliminating the energy islands, as the terminal in Swinoujscie may play the role of regional LNG terminal for the Baltic States and Finland (transport of gas via Gas Interconnection Poland-Lithuania or transport by LNG vessels);enhancing competition on regional markets;promoting natural gas as a reliable, competitive and environmentally-friendly source of energy e.g. in the transport sector (maritime transport);creating a physical hub in Swinoujscie and/or a virtual hub in Poland;establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in theBaltic Sea region and in Central-Eastern Europe.The LNG terminal in contributes to North-South gas interconnections in Central Eastern and South Eastern Europe, as the supplies from may be directed through upgraded transmission system in Poland (theNorth-South Corridor in Poland), PL-CZ and PL-SK interconnections towards the South, to other CEE countries.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Swinoujscie

PROJECTED CAPACITY INCREASES

Hub Poland75,24

The main objective of the project is to upgrade the capacity of the LNG terminal in from 5 up to 7,5 bcm/y. The project will enable to benefit from the economies of scale, as relatively low investment costs (no need toconstruct the facility from scratch, the majority of costs will be related to the construction of the 3rd storage tank) may bring further benefits to gas consumers in the Baltic Sea area and the CEE region (increase of SoS, competition andliquidity, decrease of gas prices).

Support from EU funds is expected

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

LNG Terminals Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 144

POLAND

Page 145: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

2021

+10.00

# of Pipelines, nodes, CS

Total Pipeline Length (km)

4

+106.00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

Not relevant

0%

No

Planned0%

2015FID

Construction

Commissioning

Last completed Phase :

Project of Common Interest

Yes

Upgrade of PL-DE interconnection in Lasów

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A.

Pipeline including CS

en.gaz-system.pl/nasze-inwestycje/

Interested by PCI ?

IGAs

Web Link

TRA-N-274 Non-FID

Promoter

Operator

TEN-E Project ?

None

Gas Transmission Operator GAZ-

SYSTEM S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 145

POLAND

Page 146: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

The main objective of the project is to modernise and expand the transmission system near PL-DE interconnection in Lasów with a view to upgrading the capacity of the interconnection point in Lasow from 1,5 up to 3 bcm/y. Theupgraded PL-DE interconnection in Lasów will improve security of gas supplies, increase reliability of cross-border transmission infrastructure between Poland and Germany and will contribute to well-interconnected gas network in theCEE region. The scope of necessary investments is currently investigated.

Support from EU funds is expected

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Germany (GASPOOL)42.00Lasów

PROJECTED CAPACITY INCREASES

Hub Poland

Security of Supply, Market integration (integration of market areas in Central-Eastern Europe and Western Europe (GASPOOL in Germany)), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland), N-1Regional (Central-Eastern Europe), Back-up for renewables, The upgraded PL-DE interconnection in Lasów will have an impact on:improving security of gas supplies and increasing reliability of cross-border transmission infrastructure between Poland and Germany;creating well-interconnected gas network in the CEE region;enhancing the access of gas market players in the CEE region to a developed, competitive and diversified Western European gas market (Germany);establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in Central-Eastern Europe.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

GRIP Central Eastern Europe 2014 – 2023 Annex B | 146

POLAND

Page 147: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

The North-South Gas Corridor in Eastern Poland

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-245 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Planned0%

2015FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

7

+409,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2023

+18,30

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Gas Transmission Operator GAZ-

SYSTEM S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 147

POLAND

Page 148: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Security of Supply, Market integration (market areas in Central-Eastern Europe and the Baltic States), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland and possibly Lithuania, Latvia, Estonia.), N-1Regional (Central-Eastern Europe, Baltic Sea region), Back-up for renewables, Implementation of the investment tasks within this project will allow for significant volumes of gas to be transported by means of PL-SK interconnection. Theywill also enhance the access to the USG Strachocina that have large expansion potential and may serve as essential security of supply infrastructure in the CEE region.The projects in eastern Poland are located in the area which offers the possibility to extract unconventional gas. If reserves are confirmed, the transmission infrastructure in Eastern Poland might well be used to transport unconventionalgas to the Baltic states (via Gas Interconnection Poland-Lithuania) and CEE countries (via PL-SK and PL-CZ interconnections).Construction of the pipelines within this project, together with completion of the PL-SK interconnection and GIPL, will definitely have a positive impact on the competition in the CEE and Baltic regions, as the project will provide apossibility to open the market for more gas suppliers. This would in turn mean ending the state of major dependency on one single gas supplier for the countries in the respective regions thanks to the potential access to gas deliveriesfrom new sources.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

The investment tasks within the project constitute essential elements of the planned North-South gas interconnections in Central Eastern and South Eastern Europe. The corridor consists of two routings on the Polish territory the basicone that is located in western and southern Poland and the complementary routing covering the area of potential unconventional gas deposits in Eastern Poland and being connected to two interconnectors, i.e. Poland Lithuania (GIPL)and Poland Slovakia. Implementation of the project will allow for significant volumes of gas to be transported by means of PL-SK interconnection. It will also enhance the access to the USG Strachocina that have large expansionpotential and may serve as essential security of supply infrastructure in the CEE region.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 148

POLAND

Page 149: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

The North-South corridor in Western Poland

GAZ-SYSTEM S.A.

GAZ-SYSTEM S.A.

Pipeline including CS

en.gaz-system.pl/nasze-inwestycje/krajowy-system-przesylowy/

Interested by PCI ?

IGAs

Web Link

TRA-N-247 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Planned0%

2015FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

10

+739,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2018

+7,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Gas Transmission Operator GAZ-

SYSTEM S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 149

POLAND

Page 150: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Security of Supply, Market integration (market areas in Central-Eastern Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland), N-1 Regional (Central-Eastern Europe), Back-up for renewables,Implementation of the investment tasks within this project will have an impact on:enhancing functionality of transmission system in Central and Southern Poland in order to facilitate better operational functioning of the upgraded PL-CZ interconnection, as well as to initiate gas flow on the planned PL-SKinterconnection.increasing the security of supply sources, routes and counterparts, as well as to providing the overall flexibility for the CEE region. improving European gas grid interconnections. creating a robust, well-functioning internal market in the CEE region, by ensuring high reliability of the cross-border transmission between Poland, the Czech Republic and Slovakia.,

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

The investment tasks within the project constitute essential elements of the planned North-South gas interconnections in Central-Eastern Europe. This corridor consists of two routings on the Polish territory the basic one that is locatedin Western and Southern Poland and the complementary routing covering the area of potential unconventional gas deposits in Eastern Poland. Implementation of the project will enhance functionality of transmission system in Westernand Southern Poland. It will also enforce the internal system in order to facilitate better operational functioning of the upgraded PL-CZ interconnection, as well as to initiate gas flow on the planned PL-SK interconnection.

support from EU funds is expected

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 150

POLAND

Page 151: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 151

7 PolandPGNiG SA

Page 152: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

PGniG

Operator Systemu Magazynowania Sp. Z o.o.

Storage Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

No

0%

No

FID0%

2010 Q4FID

Construction

Commissioning

Last completed Phase :

Storage facility

Working volume (mcm)

PMG Husów2014 Q2

+150,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

2014 Q2

2014/3

+0,94

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

PGNiG S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 152

POLAND

Page 153: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

UGS - PL - Gaz-System/Magazynowania

PROJECTED CAPACITY INCREASES

Storage Poland10,34

Underground gas storage (PMG) extension in order to increase working gas capacity injection and withdrawal rates. Instalation of additional compressor station to allow for a more flexible opeartion.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 153

POLAND

Page 154: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

PGniG

Operator Systemu Magazynowania Sp. Z o.o.

Storage Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

No

0%

No

FID0%

2007 Q1FID

Construction

Commissioning

Last completed Phase :

Storage facility

Working volume (mcm)

PMG Wierzchowice2014 Q2

+625,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

2013 Q4

2014/2

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

PGNiG S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 154

POLAND

Page 155: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

UGS - PL - Gaz-System/Magazynowania

PROJECTED CAPACITY INCREASES

Storage PolandHub Poland52,80

39,60

Underground gas storage (PMG) extension in order to increase working gas capacity, injection and withdrawal rates

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Storage PolandHub Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 155

POLAND

Page 156: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

PGniG

Operator Systemu Magazynowania Sp. Z o.o.

Storage Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

No

0%

No

FID0%

2010 Q1FID

Construction

Commissioning

Last completed Phase :

Storage facility

Working volume (mcm)

PMG Brzeznica2016 Q2

+35,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

2015 Q4

2016/2

+0,34

+0,51

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

PGNiG S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 156

POLAND

Page 157: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryYes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

UGS - PL - Gaz-System/Magazynowania

PROJECTED CAPACITY INCREASES

Hub PolandStorage Poland3,74

5,61

Underground gas storage (PMG) extension in order to increase working gas capacity injection and withdrawal rates. Instalation of compressor station to allow for a more flexible operation.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub PolandStorage Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 157

POLAND

Page 158: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

PGniG

Operator Systemu Magazynowania Sp. Z o.o.

Storage Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

No

0%

No

FID0%

2007 Q4FID

Construction

Commissioning

Last completed Phase :

Storage facility

Working volume (mcm)

KPMG Mogilno2020

+392,10

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

2020

2020 +10,80

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

PGNiG S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 158

POLAND

Page 159: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

UGS - PL - Gaz-System/Magazynowania

PROJECTED CAPACITY INCREASES

Hub Poland118,80

Under gas storage (KPMG) extension in order to increase working gas capacity

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Storage Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 159

POLAND

Page 160: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

PGniG

Operator Systemu Magazynowania Sp. Z o.o.

Storage Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

No

0%

No

FID0%

2007 Q1FID

Construction

Commissioning

Last completed Phase :

Storage facility

Working volume (mcm)

KPMG Kosakowo2021

+250,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

2021

2021

+2,40

+9,60

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

PGNiG S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 160

POLAND

Page 161: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

UGS - PL - Gaz-System/Magazynowania

PROJECTED CAPACITY INCREASES

Storage PolandHub Poland105,60

26,40

Construction of new underground gas storage (KPMG) to secure uninterrupted gas supplies in northern Poland.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Storage PolandHub Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 161

POLAND

Page 162: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

PGniG

Operator Systemu Magazynowania Sp. Z o.o.

Storage Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

2014FID

Construction

Commissioning

Last completed Phase :

Storage facility

Working volume (mcm)

PMG Wierzchowice

+800,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

2023*

+8,40

+11,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

PGNiG S.A. (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 162

POLAND

Page 163: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

UGS - PL - Gaz-System/Magazynowania

PROJECTED CAPACITY INCREASES

Storage PolandHub Poland121,00

92,40

Underground gas storage (PMG) extension in order to increase working gas capacity.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Storage PolandHub Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 163

POLAND

Page 164: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 164

8RomaniaGdF Suez Energy Romania

Page 165: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

GdF Suez Energy Romania

Depomures

Storage Facility

Interested by PCI ?

IGAs

Web Link

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

FEED0%

2012 Q4FID

Construction

Commissioning

Last completed Phase :

Storage facility

Working volume (mcm)

Depomures2013 Q1

+300,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Deliverability (mcm/d)

End of permitting phase

2013 Q2

2015/4

+2,30

+2,30

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 165

ROMANIA

Page 166: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 166

ROMANIA

Page 167: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 167

8RomaniaTransgaz S.A.

Page 168: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

AGRI Pipeline - Romanian section (East-West Pipeline)

Transgaz

SNGN Transgaz S.A.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-132 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+850,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2015

+42,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 168

ROMANIA

Page 169: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

East-West Pipeline RO-HU (AGRI)

PROJECTED CAPACITY INCREASES

Hub Hungary168,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Romania

GRIP Central Eastern Europe 2014 – 2023 Annex B | 169

ROMANIA

Page 170: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Integration of the transit and transmission system - reverse flow Isaccea

Transgaz

SNGN Transgaz S.A.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-139 FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Permitting0%

2010FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2013

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 170

ROMANIA

Page 171: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Isaccea (RO) - Orlovka (UA)

PROJECTED CAPACITY INCREASES

Hub Romania147,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Transit Ukraine

GRIP Central Eastern Europe 2014 – 2023 Annex B | 171

ROMANIA

Page 172: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Reverse flow at Negru Voda

Transgaz

SNGN Transgaz S.A.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-142 FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Permitting0%

2010FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2013

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 172

ROMANIA

Page 173: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Negru Voda I

PROJECTED CAPACITY INCREASES

Trans-Balkan Pipeline (Romania)168,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Bulgaria (NGTS)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 173

ROMANIA

Page 174: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Reverse flow on the interconnector Romania - Hungary

Transgaz

SNGN Transgaz S.A.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-126 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2013/4

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 174

ROMANIA

Page 175: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Csanadpalota

PROJECTED CAPACITY INCREASES

Hub Hungary12,60

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Romania

GRIP Central Eastern Europe 2014 – 2023 Annex B | 175

ROMANIA

Page 176: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

RO-BG Interconnection

Transgaz

SNGN Transgaz S.A.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-029 FID

Promoter

Operator

TEN-E Project ?

None

Not relevant

0%

No

Supply contract0%

2010 Q4FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12011 Q4

+25,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2013 Q2

2013/2 +1,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 176

ROMANIA

Page 177: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryYes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Ruse (BG) / Giurgiu (RO)

PROJECTED CAPACITY INCREASES

Hub Bulgaria (NGTS)Hub Romania14,38

14,38

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Bulgaria (NGTS)Hub Romania

GRIP Central Eastern Europe 2014 – 2023 Annex B | 177

ROMANIA

Page 178: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 178

9 Slovakiaeustream, a.s.

Page 179: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Poland - Slovakia interconnection

eustream, a.s.

eustream, a.s.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-190 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

2015 Q2FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

22015 Q3

+106,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2016 Q3

2019

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 179

SLOVAKIA

Page 180: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector PL - SK

PROJECTED CAPACITY INCREASES

Hub SlovakiaHub Poland290,50

143,70

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub SlovakiaHub Poland

GRIP Central Eastern Europe 2014 – 2023 Annex B | 180

SLOVAKIA

Page 181: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Yes

Slovakia - Hungary interconnection

eustream, a.s.

eustream, a.s.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-016 FID

Promoter

Operator

TEN-E Project ?

1

No

0%

No

Construction0%

2010 Q1FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12012 Q1

+18,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2012 Q2

2015 +0,80

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 181

SLOVAKIA

Page 182: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitYes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Balassagyarmat

PROJECTED CAPACITY INCREASES

Hub SlovakiaHub Hungary (SK-HU Interconnector)127,40

50,90

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub SlovakiaHub Hungary (SK-HU

GRIP Central Eastern Europe 2014 – 2023 Annex B | 182

SLOVAKIA

Page 183: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

No

System Enhancements - Eustream

eustream, a.s.

eustream, a.s.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-017 FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

FID0%

2010 Q1FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

12009 Q4

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2010 Q1

2017

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 183

SLOVAKIA

Page 184: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 184

SLOVAKIA

Page 185: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

GRIP Central Eastern Europe 2014 – 2023 Annex B | 185

10 SloveniaPLINOVODI d.o.o.

Page 186: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-096 FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

FEED0%

2011FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2014

+3,50

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 186

SLOVENIA

Page 187: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 187

SLOVENIA

Page 188: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Not defined yet

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-093 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2023*

+20,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 188

SLOVENIA

Page 189: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 189

SLOVENIA

Page 190: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

www.plinovodi.si/wp-content/uploads/2011/09/RN-2013-2022-Posvetovalni-dokument.pdf

Interested by PCI ?

IGAs

Web Link

TRA-N-092 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2016

+5,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Plinovodi (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 190

SLOVENIA

Page 191: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Removing bottlenecks of transmission system and increase of its capacities up to the existing capacities of neighbouring transmission system operators (first phase)Ensuring additional capacities for further market development and transits, including reverse flows (second phase),

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Adjustment to operating parameters of the transmission system of the Italian TSO. Reverse flow.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 191

SLOVENIA

Page 192: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Not defined yet

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-094 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2016

+30,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 192

SLOVENIA

Page 193: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 193

SLOVENIA

Page 194: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Not defined yet

CS Vodice II (on M2/1 pipeline up to 3 units with total power up to 30 MW)

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-102 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2023*

+30,00

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 194

SLOVENIA

Page 195: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 195

SLOVENIA

Page 196: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Not defined yet

M1/3 SLO-A border crossing

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

www.plinovodi.si/wp-content/uploads/2011/09/RN-2013-2022-Posvetovalni-dokument.pdf

Interested by PCI ?

IGAs

Web Link

TRA-N-109 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+0,20

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2023* +0,70

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Plinovodi (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 196

SLOVENIA

Page 197: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

No entry

Removing bottlenecks of transmission system and increase of its capacities up to the existing capacities of neighbouring transmission system operators (first phase)Ensuring additional capacities for further market development and transits, including reverse flows (second phase),

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

181,35

Adjustment to operating parameters of the transmission system of the Austrian TSO, with parallel connection to the existing pipeline.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 197

SLOVENIA

Page 198: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-100 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not yet

0%

Not yet

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+79,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2017 +0,90

Considered TPA Regime

Considered Tariff Regime Negotiated (e.g. Exemption)

Negotiated (e.g. Exemption)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 198

SLOVENIA

Page 199: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exitNo exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Hub ItaliaHub Italia289,00

754,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub SloveniaHub Slovenia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 199

SLOVENIA

Page 200: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Not defined yet

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-104 FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Supply contract0%

2010FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+65,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2013

2014

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 200

SLOVENIA

Page 201: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 201

SLOVENIA

Page 202: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Not defined yet

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-F-097 FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Supply contract0%

2010FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+34,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2013

2014

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 202

SLOVENIA

Page 203: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 203

SLOVENIA

Page 204: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Not defined yet

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

www.plinovodi.si/wp-content/uploads/2011/09/RN-2013-2022-Posvetovalni-dokument.pdf

Interested by PCI ?

IGAs

Web Link

TRA-N-108 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

01.04.2010 2011

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+31,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2023*

Date of Request Year Funding GrantedTEN-E Requests

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Plinovodi (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 204

SLOVENIA

Page 205: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

No exitNo exit

Removing bottlenecks of transmission system and increase of its capacities up to the existing capacities of neighbouring transmission system operators (first phase)Ensuring additional capacities for further market development and transits, including reverse flows (second phase),

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Hub ItaliaHub Italia25,40

62,99

Adjustment to operating parameters of the transmission system of the Italian TSO.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub SloveniaHub Slovenia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 205

SLOVENIA

Page 206: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-099 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not yet

0%

Not yet

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+29,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2017 +0,75

Considered TPA Regime

Considered Tariff Regime Negotiated (e.g. Exemption)

Negotiated (e.g. Exemption)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 206

SLOVENIA

Page 207: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

No exitNo exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Hub ItaliaHub Italia340,00

102,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub SloveniaHub Slovenia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 207

SLOVENIA

Page 208: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-262 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not yet

0%

Not yet

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+24,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2017 +0,75

Considered TPA Regime

Considered Tariff Regime Negotiated (e.g. Exemption)

Negotiated (e.g. Exemption)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 208

SLOVENIA

Page 209: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 209

SLOVENIA

Page 210: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

M3/1c Kalce - Vodice

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-261 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not yet

0%

Not yet

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+47,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2017 +0,75

Considered TPA Regime

Considered Tariff Regime Negotiated (e.g. Exemption)

Negotiated (e.g. Exemption)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 210

SLOVENIA

Page 211: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 211

SLOVENIA

Page 212: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Not defined yet

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-107 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

2

+73,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2015

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 212

SLOVENIA

Page 213: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

San Dorligo della Valle (IT) /Osp (SI)

PROJECTED CAPACITY INCREASES

Hub Slovenia6,10

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Italia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 213

SLOVENIA

Page 214: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-101 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+51,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2018 +0,80

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 214

SLOVENIA

Page 215: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Hub Slovenia414,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Croatia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 215

SLOVENIA

Page 216: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

up to 80 MW)

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-098 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not yet

0%

Not yet

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+72,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2016

+80,00

+0,90

Considered TPA Regime

Considered Tariff Regime Negotiated (e.g. Exemption)

Negotiated (e.g. Exemption)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 216

SLOVENIA

Page 217: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

No entryNo entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector SI-HU

PROJECTED CAPACITY INCREASES

Hub SloveniaHub Slovenia819,00

288,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub HungaryHub Hungary

GRIP Central Eastern Europe 2014 – 2023 Annex B | 217

SLOVENIA

Page 218: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-263 Non-FID

Promoter

Operator

TEN-E Project ?

None

Not yet

0%

Not yet

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+115,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2018

+60,00

+0,90

Considered TPA Regime

Considered Tariff Regime Negotiated (e.g. Exemption)

Negotiated (e.g. Exemption)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 218

SLOVENIA

Page 219: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

GRIP Central Eastern Europe 2014 – 2023 Annex B | 219

SLOVENIA

Page 220: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Not defined yet

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

www.plinovodi.si/wp-content/uploads/2011/09/RN-2013-2022-Posvetovalni-dokument.pdf

Interested by PCI ?

IGAs

Web Link

TRA-F-110 FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

2012FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2014

2014

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

Plinovodi (100%)

GRIP Central Eastern Europe 2014 – 2023 Annex B | 220

SLOVENIA

Page 221: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes exit

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Hub Italia25,00

Adjustment to operating parameters of the transmission system to the Italian TSO. Reverse flow.

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Slovenia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 221

SLOVENIA

Page 222: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Project of Common Interest

Yes

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-112 Non-FID

Promoter

Operator

TEN-E Project ?

1

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+70,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2018 +0,70

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 222

SLOVENIA

Page 223: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

Interconnector SI-HU

PROJECTED CAPACITY INCREASES

Hub Slovenia38,00

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub Hungary

GRIP Central Eastern Europe 2014 – 2023 Annex B | 223

SLOVENIA

Page 224: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

SPONSORS GENERAL INFORMATION FINANCING

THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION

Not part of TEN-E

Not defined yet

Plinovodi d.o.o.

Plinovodi d.o.o.

Pipeline including CS

Interested by PCI ?

IGAs

Web Link

TRA-N-114 Non-FID

Promoter

Operator

TEN-E Project ?

None

No

0%

No

Planned0%

FID

Construction

Commissioning

Last completed Phase :

# of Pipelines, nodes, CS

Total Pipeline Length (km)

1

+10,00

Applied for Exemption ?

Exemption granted ?

% Exemption in entry direction

% Exemption in exit direction

Total CS Power (MW)

Expected Load Factor

End of permitting phase

2021

Considered TPA Regime

Considered Tariff Regime Regulated

Regulated

GRIP Central Eastern Europe 2014 – 2023 Annex B | 224

SLOVENIA

Page 225: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

Modelled Direction

Yes entryNo entry

DESCRIPTION OF THE PROJECT

EXPECTED BENEFITS

PROJECTED CAPACITY INCREASES

Hub SloveniaHub Slovenia2,31

5,08

Public financing Private financing Multilateral financing

COMMENTS ABOUT THE PROJECT FINANCING

Interconnection Capacity (GWh/d) From Zone To Zone

Hub CroatiaHub Croatia

GRIP Central Eastern Europe 2014 – 2023 Annex B | 225

SLOVENIA

Page 226: ENTSOG | ENTSOG - Central Eastern Europe GRIP · 2018. 11. 29. · Total CS Power (MW) Expected Load Factor End of permitting phase 2015 Q1 2018/4 +66,00 TEN-E Requests Date of Request

ENTSOG AISBL

Avenue de Cortenbergh 100

1000 Brussels, Belgium

Tel. +32 2 894 51 00

[email protected] www.entsog.eu