entsog | entsog - central eastern europe grip · 2018. 11. 29. · total cs power (mw) expected...
TRANSCRIPT
GAS REGIONAL INVESTMENT PLAN
2014 – 2023
ANNEX B : INFRASTRUCTURE PROJECTS
GRIP
Central Eastern Europe
GRIP Central Eastern Europe 2014 – 2023 Annex B | 2
1 AustriaGas Connect Austria Gmbh
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Bidirectional Austrian-Czech Interconnector (BACI, formerly LBL project)
Gas Connect Austria GmbH
Gas Connect Austria GmbH
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-021 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
27.02.2012 2013
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2
+58,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2019
+24,00
Date of Request Year Funding GrantedTEN-E Requests
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Pipeline on Austrian territory, GAS
CONNECT AUSTRIA GmbH (100%)
Pipeline on Czech territory, NET4GAS,
s.r.o (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 3
AUSTRIA
Modelled Direction
Yes exitYes entry
Security of Supply, Market Integration, Diversification of Sources, Diversification of Routes
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Reinthal - Bidirectional Austrian-Czech Interconnector
PROJECTED CAPACITY INCREASES
Hub AustriaHub Czech Republic255,13
255,13
The Bidirectional-Austrian-Czech-Interconnector (BACI) will be the first bidirectional connection between the Austrian and the Czech Market.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub AustriaHub Czech Republic
GRIP Central Eastern Europe 2014 – 2023 Annex B | 4
AUSTRIA
GRIP Central Eastern Europe 2014 – 2023 Annex B | 5
1 AustriaTauerngasleitung GmbH
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of common interest
Yes
Tauerngasleitung Gas Pipeline Project
Tauerngasleitung GmbH
Tauerngasleitung GmbH
Pipeline including CS
www.tauerngasleitung.at
Interested by PCI ?
IGAs
Web Link
TRA-N-035 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
Not yet
28.04.2010
26.04.2006
2011
2007
Planned0%
2014 Q2FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12014 Q4
+290,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2015 Q1
2018/4
+66,00
Date of Request Year Funding GrantedTEN-E Requests
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
TIGAS-Erdgas Tirol GmbH (3%) Rohöl-Aufsuchungs
Aktiengesellschaft (10%)
Energie AG Oberösterreich
(18%)
KELAG-Kärntner Elektrizitäts-
Aktiengesellschaft (4%)
E.ON Ruhrgas AG (47%)
Salzburg AG für Energie, Verkehr und Telekommunikation
(18%)
Private Financing (70,00%)
Multilateral Financing (30,00%)
* In 2013, the sponsor’s shareholders announced that they intended to amend the sponsor’s ownership structure through a tendering process.
*
GRIP Central Eastern Europe 2014 – 2023 Annex B | 6
AUSTRIA
Modelled Direction
Yes exitYes entryYes exitYes entryYes exitYes entryYes exitYes entry
Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional, Back-up for renewables, Power-to-gas, Biogas, SoS: Investments will be necessary, especially in cross-border gas transmission capacity, with a view to diversifying sources of supply, and gas transmission systems in general, especially where capacities may be needed in an emergency to supply areas with capacity shortfalls. The TGL is inline with these objectives, which focus mainly on security of supplies. Market Integration: By linking the Central European (Southern Germany) with the South-East European (mainly Italy) natural gas market, the TGL increasesinteroperability between gas markets in Europe which are still separate, develop new natural gas sources for these markets and therefore significantly improve competition within a European single market for natural gas. Diversificationof European natural gas supplies: By creating the infrastructure required for a functioning North-South/South-North system to develop the North African and Arab supply region, including liquefied natural gas (LNG) for theMediterranean region, the TGL will reduce dependence on individual suppliers in the North and East.,
Hub Germany (NCG)Haiming (bayernets) - DE / Burghausen-Auerbach (Austrian Storage) - TGLHaiming (bayernets) - DE / Burghausen (Transit) - TGL Tauerngas Leitung (Austria)
Tauerngas Leitung (Austria)Haiming (bayernets) - DE / Burghausen (Austrian Hub) - TGL Hub Germany (NCG)
136,65180,7430,14
148,61
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Hub Germany (NCG)
Hub Germany (NCG)Storage Austria
Tarvisio - IT / Arnoldstein (Transit) - TGL
Haiming-Oberkappel (OGE) - DE / Burghausen (Transit) - TGLHaiming (OGE) - DE / Burghausen-Auerbach (Austrian Storage) - TGL
PROJECTED CAPACITY INCREASES
Tauerngas Leitung (Austria)Hub Germany (NCG)Storage Austria
Hub Italia
143,82
314,9665,4033,82
Pipeline (incl. compressor stations) in North-South direction. TGL allows feed significant volumes from different sources from South-East regions towards Central Europe.
Own financing 30%. Loans 70% of which 70-80% fromcommercial banksand the rest from multilateral financing
20-30% of 70% of the overall external financing needs
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Tauerngas Leitung (Austria)
Hub Germany (NCG)Hub Austria
Hub ItaliaTauerngas Leitung (Austria)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 7
AUSTRIA
GRIP Central Eastern Europe 2014 – 2023 Annex B | 8
2 BulgariaBulgartransgaz EAD
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Bulgartransgaz EAD
Bulgartransgaz EAD
Storage Facility
http://www.bulgartransgaz.bg/en/index.php
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
Planned0%
FID
Construction
Commissioning
Last completed Phase :
Storage facility
Working volume (mcm)
Not defined yet
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
2020
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Bulgartransgaz EAD (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 9
BULGARIA
Modelled Direction
Security of Supply, Market integration, N-1 National, N-1 Regional (Central Eastern Europe, South Eastern Europe, Balkan Region),
,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Provision is made for the construction of new gas storage facility on the territory of Bulgaria with a view to ensuring security of supply and a stimulus to gas market liberalisation. Different opportunities for the construction of a new gasstorage in suitable geological structures are considered - in salt caverns, depleted gas field (inland or offshore) or aquifer.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 10
BULGARIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Interconnection Turkey-Bulgaria
Bulgartransgaz EAD
Bulgartransgaz EAD
Pipeline including CS
http://www.bulgartransgaz.bg/en/index.php
Interested by PCI ?
IGAs
Web Link
TRA-N-140 Non-FID
Promoter
Operator
TEN-E Project ?
2
Not relevant
0%
Not relevant
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2
+205,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2016
Considered TPA Regime
Considered Tariff Regime Not applicable
Not applicable
Bulgartransgaz EAD for the gas pipeline
section on the territory of Bulgaria
(100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 11
BULGARIA
Modelled Direction
Yes entry
Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional (Central and Eastern Europe, South Eastern Europe, Balkan Region), The interconnection Turkey-Bulgaria is a key project whose realization shall lead to the increase of the security of supply and the opportunity for diversification of gas supply not only to Bulgaria, but to the Central and South-Eastern Europe region as well. Theproject contributes directly to the diversification of gas sources: alternative gas producers - countries from the Caspian region, Turkish LNG terminals and Middle East.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector ITB (Turkey - Bulgaria)
PROJECTED CAPACITY INCREASES
Hub Greece92,00
The interconnection is foreseen to be built as a development to the existing connection of Bulgartransgaz EAD and Botas – Turkey systems by creating the technical opportunity for enabling bi-directional physical flow of natural gasbetween both systems. Thus a significantly greater security of gas supply to our country can be achieved, meeting the N-1 security standard and diversification of natural gas supply sources. Preliminary plans are for a staged projectdevelopment, with the commissioning in 2014 or 2015 of the first stage depending on the development of the Turkish gas transmission system.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Turkey (Imports)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 12
BULGARIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Rehabilitation, Modernization and Expansion of the National Transmission System
Bulgartransgaz EAD
Bulgartransgaz EAD
Pipeline including CS
http://www.bulgartransgaz.bg/en/index.php
Interested by PCI ?
IGAs
Web Link
TRA-N-298 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
0%
2015FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2017
Considered TPA Regime
Considered Tariff Regime Not applicable
Not applicable
Bulgartransgaz EAD (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 13
BULGARIA
Modelled Direction
Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional (Central and Eastern Europe, South Eastern Europe, Balkan Region), The modernisation, rehabilitationand expansion of the existing gas transmission network are directly linked to the planned new interconnections with Greece (IGB), Romania (IBR), Turkey (ITB) and Serbia (IBS), the integration of the national and the transit gastransmission system on the territory of Bulgaria and the development of the large cross-border gas projects in the region. The efficient use of the new entry and exit points from/to Bulgartransgaz gas transmission networks is directlylinked to the technical possibilities of the existing gas transmission infrastructure on the territory of Bulgaria to ensure sufficient capacity and suitable technical conditions to accommodate the transport of the planned new natural gasquantities and to the available storage capacity and and the expansion of the gas storage facility in Chiren unique on the territory of the country accordingly. ,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
A set of activities involving rehabilitation, modernisation and expansion of the existing national gas transmission infrastructure with a view to guaranteeing the possibility of the national gas transmission system to ensure the transport ofsufficient natural gas volumes through the territory of the country using the planned new interconnections to other countries from the region of South Eastern, Central and Eastern Europe and in the context of the large cross-border gasprojects in the region. The project mostly include compressor stations modernisation (CS Valchi Dol and CS Polski Senovets) as well as in-line inspections, complete overhauls and replacement of gas pipeline sections of the main gaspipelines that are part of the annularly built gas transmission system and construction regulating lines at the exits of gas pipeline branches off the main and transit gas pipeline to enhance its reliability, security and capacity.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 14
BULGARIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Bulgartransgaz EAD
Bulgartransgaz EAD
Storage Facility
http://www.bulgartransgaz.bg/en/index.php
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
0%
2014FID
Construction
Commissioning
Last completed Phase :
Storage facility
Working volume (mcm)
UGS Chiren
+450,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
2017
+5,80
+5,80
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Bulgartransgaz EAD (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 15
BULGARIA
Modelled Direction
Yes exitYes entryYes exitYes entry
Security of Supply, Market integration, N-1 National, N-1 Regional (Central Eastern Europe, South Eastern Europe, Balkan Region), In this moment UGS Chiren covers mainly seasonal fluctuations in domestic consumption and ensures thesecurity of supply. Additional stored volumes and higher withdrawal and injection rates will serve Bulgarian and regional gas markets (Greek, Romanian, Macedonian and Serbian) via the existing and the new interconnections - IBR, IGB,
,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Storage Bulgaria (NGTS)
UGS - BG - Chiren - Bulgartransgaz
PROJECTED CAPACITY INCREASES
Hub Bulgaria (NGTS)Storage Bulgaria (NGTS)Hub Bulgaria (NGTS)
Storage Bulgaria (NGTS)
65,00
65,0065,0065,00
The project for expansion of the existing gas storage facility Chiren consists of staged capacity increse of the gas storage facility higher stored gas volumes, higher pressures in the gas reservoir and reaching higher average dailywithdrawal and injection flow rates.Two options of reaching maximum capacities are mainly under consideration:
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Bulgaria (NGTS)Storage Bulgaria (NGTS)Hub Bulgaria (NGTS)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 16
BULGARIA
GRIP Central Eastern Europe 2014 – 2023 Annex B | 17
2 BulgariaICGB EAD
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Interconnector Greece Bulgaria - IGB
DEPA S.A.
ICGB a.d.
Pipeline including CS
www.icgb.eu
Interested by PCI ?
IGAs
Web Link
TRA-N-149 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not yet
0%
Yes
Permitting0%
2014 Q2FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
22014 Q1
+182,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2014 Q3
2016/1
+10,00
Considered TPA Regime
Considered Tariff Regime Negotiated (e.g. Exemption)
Negotiated (e.g. Exemption)
Bulgarian Energy Holding EAD (50%)
IGI Poseidon S.A. (50%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 18
BULGARIA
Modelled Direction
Yes entryYes exitYes entryYes exit
Security of Supply, Market integration (Greece, Bulgaria, Romania, Hungary, FYROM, Serbia), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Greece, Bulgaria), N-1 Regional (NSI East Gas), Back-up forrenewables, Power-to-gas, The project will contribute significantly in the itegration of the market area, specifically the South Eastern Europe, and will allow to alleviate to a great extend the dependency of countries in the area to a singlesource/counterpart.Taking into account that the objective of the project is to bring additional import quantities of natural gas in Bulgaria and South Eastern Europe it significantly improves the resilience of the system in both short (theadditional quantities will be able to cover daily peak demands) and long term.Specifically for the long term, the diversification in route, supply source as well as counterparts will have a great positive impact on the resilience of the system and will be able to cater to any forecasted increase in demand over thecoming years.The impact of the project in the systems flexibility under disruption (n-1 rule) will be significant taking into account that it will create a new interconnections carrying gas from a new source allowing new counterparts to enter the market.A possible disruption in any of the other import sources (including the regional disruption of Russian gas) will NOT AFFECT this one having a great positive impact on the remaining flexibility of the system.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector Greece-Bulgaria
Komotini - TAP / IGB
Stara Zagora - IGB / BG
PROJECTED CAPACITY INCREASES
Trans-Adriatic Pipeline (Greece)Interconnector Greece-Bulgaria (Bulgaria)Hub Bulgaria (NGTS)
Interconnector Greece-Bulgaria (Bulgaria)
82,00
82,0082,0082,00
An onshore natural gas pipeline that will connect Komotini in Greece to Stara Zagora in Bulgaria. The IGB pipeline is being developed by ICGB AD, with shareholders IGI-Poseidon S.A. and Bulgarian Energy Holding EAD
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Trans-Adriatic Pipeline (Greece)Interconnector Greece-Bulgaria Hub Bulgaria (NGTS)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 19
BULGARIA
GRIP Central Eastern Europe 2014 – 2023 Annex B | 20
2 BulgariaMinistry of Economy and Energy of Republic of Bulgaria
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Interconnection Bulgaria - Serbia
Bulgarian Ministry of Economy and energy (MEE)
Bulgartransgaz EAD
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-137 Non-FID
Promoter
Operator
TEN-E Project ?
3
No
0%
No
Planned0%
2014FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
22014
+155,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2015
2015
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 21
BULGARIA
Modelled Direction
Yes exitYes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector BG RS
PROJECTED CAPACITY INCREASES
Hub Bulgaria (NGTS)Hub Serbia51,00
51,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Bulgaria (NGTS)Hub Serbia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 22
BULGARIA
GRIP Central Eastern Europe 2014 – 2023 Annex B | 23
2 BulgariaSouth Stream Bulgaria AD(Bulgarian Shareholder Bulgarian Energy Holding EAD)
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
South Stream Bulgaria - Stage I
South Stream Bulgaria AD (Bulgarian
Bulgartransgaz EAD
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-308 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2015
Considered TPA Regime
Considered Tariff Regime Not applicable
Not applicable
Bulgartransgaz EAD (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 24
BULGARIA
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
South Stream into Bulgaria (BG)
PROJECTED CAPACITY INCREASES
Hub Bulgaria (NGTS)162,50
First stage of the South Stream interconnection to the Bulgarian network, as understood by ENTSOG based on e-mail exchange.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
South Stream (Russia)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 25
BULGARIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
South Stream Bulgaria - Stage II
South Stream Bulgaria AD (Bulgarian
Bulgartransgaz EAD
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-309 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2016
Considered TPA Regime
Considered Tariff Regime Not applicable
Not applicable
Bulgartransgaz EAD (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 26
BULGARIA
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
South Stream into Bulgaria (BG)
PROJECTED CAPACITY INCREASES
Hub Bulgaria (NGTS)62,10
Second stage of the South Stream interconnection to the Bulgarian network, as understood by ENTSOG based on e-mail exchange.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
South Stream (Russia)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 27
BULGARIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
South Stream Bulgaria - Stage III
South Stream Bulgaria AD (Bulgarian
Bulgartransgaz EAD
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-310 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2017
Considered TPA Regime
Considered Tariff Regime Not applicable
Not applicable
Bulgartransgaz EAD (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 28
BULGARIA
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
South Stream into Bulgaria (BG)
PROJECTED CAPACITY INCREASES
Hub Bulgaria (NGTS)15,50
Third and final stage of the South Stream interconnection to the Bulgarian network, as understood by ENTSOG based on e-mail exchange.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
South Stream (Russia)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 29
BULGARIA
GRIP Central Eastern Europe 2014 – 2023 Annex B | 30
3 CroatiaPlinacro d.o.o.
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Ionian Adriatic Pipeline
Plinacro Ltd
Plinacro Ltd
Pipeline including CS
www.plinacro.hr
Interested by PCI ?
IGAs
Web Link
TRA-N-068 Non-FID
Promoter
Operator
TEN-E Project ?
2
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
3
+540,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2015
2020
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Fieri to Montenegro border, Ministry of
Economy , Trade and Energy (Albania)
(100%)
Montenegro, Ministry of Economy (Montenegro) (100%)
Bosnia and Herzegovina, BH Gas
(Bosnia and Herzegovina);
Ministry of Foreign Trade and Economic
Relations (BiH) (100%)
Croatia (From Split to Montenegro border), Plinacro Ltd; Ministry of Economy (Croatia)
(100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 31
CROATIA
Modelled Direction
Yes exitYes entryYes entryYes exitYes exit
Security of Supply, Market integration (Market Integration benefits for Croatiaand the region (Albania, Montenegro, Bosnia and Herzegovina and neighbouring countries), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional (Balkan region ), Back-up for renewables,
Hub MontenegroIonic-Adriatic Pipeline - IAP / ME 15,00
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Ionic-Adriatic Pipeline (Croatia)Ionic-Adriatic Pipeline (Croatia)
Ionic-Adriatic Pipeline - IAP / ABTrans-Adriatic Pipeline - TAP / Ionic-Adriatic Pipeline - IAPIonic-Adriatic Pipeline - IAP / Split - HRIonic-Adriatic Pipeline - IAP / BH
PROJECTED CAPACITY INCREASES
Ionic-Adriatic Pipeline (Croatia)Hub CroatiaHub Bosnia Herzegovina
Hub Albania
30,00
30,00150,0075,00
The pipeline will cross the territory along the Adriatic coast from Fieri in Albania via Montenegro to Split in Croatia and will be linked to the existing Croatian gas transmission system (main direction Bosiljevo Split). The Ionian-AdriaticPipeline is considered a part of the Energy Community Gas Ring, which is the concept of gasification for the entire region, proposed by the WB Study and accepted by the Gas Fora of the Energy Community.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Ionic-Adriatic Pipeline (Croatia)Trans-Adriatic Pipeline (Greece)Ionic-Adriatic Pipeline (Croatia)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 32
CROATIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
2023
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2
+30.00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
Not part of TEN-E
No
Interconnection Croatia-Bosnia and Herzegovina (Licka Jesenica-Rakovica-Trzac-Bosanska
Plinacro Ltd
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-303 Non-FID
Promoter
Operator
TEN-E Project ?
None
Plinacro Ltd, BH Gas
GRIP Central Eastern Europe 2014 – 2023 Annex B | 33
CROATIA
Modelled Direction
Yes exit
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Croatia45.00Rakovica (HR) / Trzac (BA)
PROJECTED CAPACITY INCREASES
Hub Bosnia and Herzegovina
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
GRIP Central Eastern Europe 2014 – 2023 Annex B | 34
CROATIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
NO
Interconnection Croatia/Bosnia and Herzegovina (Slobodnica- Bosanski Brod-Zenica)
Plinacro Ltd
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-066 Non-FID
Promoter
Operator
TEN-E Project ?
2
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+6,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2018
2019 +0,90
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Plinacro Ltd, BH Gas
GRIP Central Eastern Europe 2014 – 2023 Annex B | 35
CROATIA
Modelled Direction
Yes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Slobodnica- Bosanski Brod-Zenica
PROJECTED CAPACITY INCREASES
Hub Bosnia Herzegovina44,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Croatia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 36
CROATIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
2018
# of Pipelines, nodes, CS
Total Pipeline Length (km)
3
+29.00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
Not part of TEN-E
No
Interconnection Croatia-Bosnia and Herzegovina (South)
Plinacro Ltd
Pipeline including CS
www.plinacro.hr
Interested by PCI ?
IGAs
Web Link
TRA-N-302 Non-FID
Promoter
Operator
TEN-E Project ?
Noneparts in B&H, BH Gas
(100%)
Croatian part of both options, Plinacro
d.o.o. (100%)
Plinacro Ltd, BH Gas
GRIP Central Eastern Europe 2014 – 2023 Annex B | 37
CROATIA
Modelled Direction
Yes exit
South Interconnection of Croatia and B&H - the pipeline is actually branch from planned regional Ionic Adriatic Pipeline - IAP.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Ionic-Adriatic Pipeline (Croatia)45.00
PROJECTED CAPACITY INCREASES
Hub Bosnia and Herzegovina
Security of Supply, Market integration, Diversification of sources, N-1 National (for B&H), N-1 Regional, The aim of the project is to establish a new supply route for B&H providing a diversified and reliable natural gas supply.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
GRIP Central Eastern Europe 2014 – 2023 Annex B | 38
CROATIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
NO
Plinacro Ltd
Plinacro Ltd
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-070 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2
+102,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2018
2023
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 39
CROATIA
Modelled Direction
Yes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Hub Serbia176,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Croatia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 40
CROATIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Plinacro Ltd
Plinacro Ltd
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-086 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
2017FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
5
+296,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2018 +0,90
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 41
CROATIA
Modelled Direction
No exitYes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Rogatec
PROJECTED CAPACITY INCREASES
Hub Croatia165,00165,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Slovenia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 42
CROATIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
2027 +0.90
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2
+220.00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
Not part of TEN-E
Yes
Plinacro Ltd
Plinacro Ltd
Pipeline including CS
www.plinacro.hr
Interested by PCI ?
IGAs
Web Link
TRA-N-083 Non-FID
Promoter
Operator
TEN-E Project ?
NoneCroatian section, Plinacro (100%)
Italian section, tbd (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 43
CROATIA
Modelled Direction
No entryNo exit
Covering the territory from the gas node Omišalj on the island of Krk (Croatian Gas Transmission System) via Adriatic Sea to Casal Borsetti (Italian Gas Transmission System)
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub ItaliaHub Croatia
506.00506.00
Casalborsetti
PROJECTED CAPACITY INCREASES
Hub ItaliaHub Croatia
Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (For Croatia), N-1 Regional, Back-up for renewables, It will be new cross border transmission between Croatia andItaly; fits in the idea of Adriatic Gas Ring,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
GRIP Central Eastern Europe 2014 – 2023 Annex B | 44
CROATIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Plinacro Ltd
LNG Hrvatska d.o.o.
LNG Terminal
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
Regasification facility
Expected volume (bcm/y)
LNG RV Croatia
+2,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction No
Total CS Power (MW)
Send-out (mcm/d)
End of permitting phase
Ship size (m3)
Reloading ability ?
2017 +5,50
Considered TPA Regime
Considered Tariff Regime Not applicable
Not applicable
Plinacro (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 45
CROATIA
Modelled Direction
Yes exit
Security of Supply, Market integration (Croatia, markets of Central and Western Europe (Austria, Slovenia, Hungary, Slovakia, Check Republic) as well as the Balkan countries (Serbia, B&H, Diversification of sources,Diversification of routes, N-1 National (for Croatia), N-1 Regional, Back-up for renewables,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
LNG RV (Regasification Vessel) to Croatia
PROJECTED CAPACITY INCREASES
Hub Croatia60,50
�
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
LNG Terminals Croatia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 46
CROATIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
2017
2018 +0.90
# of Pipelines, nodes, CS
Total Pipeline Length (km)
3
+103.60
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
Not part of TEN-E
Yes
Plinacro Ltd
Plinacro Ltd
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-090 Non-FID
Promoter
Operator
TEN-E Project ?
1
GRIP Central Eastern Europe 2014 – 2023 Annex B | 47
CROATIA
Modelled Direction
Yes exit
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Croatia506.00
PROJECTED CAPACITY INCREASES
Hub Slovenia
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
GRIP Central Eastern Europe 2014 – 2023 Annex B | 48
CROATIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
2017
2019 +0.90
# of Pipelines, nodes, CS
Total Pipeline Length (km)
5
+692.00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
Not part of TEN-E
Yes
LNG main gas transit pipeline (Part of North-South Gas Corridor) Zlobin-Bosiljevo-Sisak-Kozarac-Slobodnica
Plinacro Ltd
Plinacro Ltd
Pipeline including CS
www.plinacro.hr
Interested by PCI ?
IGAs
Web Link
TRA-N-075 Non-FID
Promoter
Operator
TEN-E Project ?
None
Plinacro (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 49
CROATIA
Modelled Direction
The pipeline will be construted on the territory of Croatia from the gas node Zlobin via Bosiljevo, Sisak, the gas node Kozarac to Slobodnica. It will be the "backbone" of the croatian gas system.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
PROJECTED CAPACITY INCREASES
Security of Supply, Market integration (Croatia, Hungary, Bosnia and Herzegovina, Serbia), Reverse Flows, Diversification of routes, N-1 National (for Croatia), Back-up for renewables, This main transit gas pipeline is the future strategicgas transmission connector of great significance and is an integral part of the North South European Corridor designated the North-South (Baltic Adriatic) Gas Connection. Its purpose is linking the Polish and Croatian LNG (LiquefiedNatural Gas) solutions under the umbrella of the European Commission (EC). This project is foreseen under the Gas Forum administered by the Energy Community Secretariat, and although in Croatia, is regionally significant. The maintransit gas pipeline Zlobin-Bosiljevo-Sisak-Kozarac-Slobodnica:
- will be connected to the future Ionian Adriatic Pipeline (IAP)
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
GRIP Central Eastern Europe 2014 – 2023 Annex B | 50
CROATIA
GRIP Central Eastern Europe 2014 – 2023 Annex B | 51
4Czech RepublicNET4GAS, s.r.o.
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Bidirectional Austrian Czech Interconnection (BACI)
NET4GAS, s.r.o.
NET4GAS, s.r.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-133 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
27.02.2012 2013
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+58,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2019
+24,00
Date of Request Year Funding GrantedTEN-E Requests
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Reinthal (AT/CZ border) to
Baumgarten, GAS CONNECT AUSTRIA
GmbH (100%)
-Reinthal (CZ/AT border), NET4GAS, s.r.o.
(100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 52
CZECH REPUBLIC
Modelled Direction
Yes entryYes exit
Security of Supply, Market integration (CEE Region), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (CZ, AT), N-1 Regional (CEE Region), Back-up for renewables, Power-to-gas, Biogas, The BidirectionalAustrian-Czech interconnector (BACI) ensures transmission capacity between the two member states and facilitates better market integration and security of gas supply also for adjacent countries. It contributes to the diversification ofgas supply and the increased transportation opportunities to and from countries like Hungary, Poland, Germany, Italy, France, Slovenia, Croatia and Slovakia and access to new and existing trading markets.BACI enhances the market development due to access to underground gas storages both on the Austrian and Czech side and therefore enhances the market development by providing peak regulation and the flexibility of gas flow.BACI is a key element in creating a well-functioning internal market in the CEE region due to access to existing and new import infrastructures such as new LNG regasification plants, Nord Stream, South Stream and unconventional gassources.With BACI the CEE region would become less vulnerable to a supply disruption through the Ukraine and Belarus route and therefore the region will have an increased security of supply.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Reinthal - Bidirectional Austrian-Czech Interconnector
PROJECTED CAPACITY INCREASES
Hub AustriaHub Czech Republic254,00
254,00
The BACI will be a new infrastructure directly connecting the Austrian and Czech market. It will be connected to the existing Czech transmission system via CS (NET4GAS, s.r.o.) and to the Austrian transmission system viaBaumgarten (GAS CONNECT AUSTRIA GmbH). The BACI will enable capacity transmission for the first time between these two member states and it will facilitate better market integration and security of gas supply also for adjacentcountries like Hungary, Poland, Germany, Italy, France, Slovenia, Croatia and Slovakia due to the creation of additional transportation opportunities. The project will also increase the overall flexibility of the Czech, Austrian and alsoPolish system by diversification of gas supply routes and by connecting UGS in the Czech Republic and Austria.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub AustriaHub Czech Republic
GRIP Central Eastern Europe 2014 – 2023 Annex B | 53
CZECH REPUBLIC
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Connection to Oberkappel
NET4GAS, s.r.o.
NET4GAS, s.r.o.
Pipeline including CS
www.tauerngasleitung.at/5GL
Interested by PCI ?
IGAs
Web Link
TRA-N-135 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+110,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2022
+2,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Pipeline on Austrian territory, potential
partner in Austria - in discussion (100%)
Pipeline on Czech territory, NET4GAS,
s.r.o. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 54
CZECH REPUBLIC
Modelled Direction
Yes entryYes exit
Security of Supply, Market integration (CEE Region), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (CZ, AT), N-1 Regional (CEE Region), Back-up for renewables, Power-to-gas, Biogas, Increase thediversification of gas supply routes (i.e. especially Russian gas from Nord Stream and Norwegian sources to the Southern part of Europe; African, LNG and Caspian gas sources from the South / South-East to the North / North West part ofEurope).Therefore the project is also part of the 5GL Project together with TGL (AT) and Monacco (GER) as well as the planned interconnection to Slovenia that takes a comprehensive approach for completion the gas network in this region.
,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Oberkappel (Net4Gas)
PROJECTED CAPACITY INCREASES
Hub AustriaHub Czech Republic55,00
55,00
The project will interconnect the existing transmission pipelines in the Czech Republic with AT/DE border at Oberkappel. It will be the first interconnection between these states and it will be connected to Penta West as well as WAGpipeline (AT) and to the Southern branch of the N4G transmission system (CZ). Connection to Oberkappel is a part of the “5 Gas-market Link - of the partners Tauerngasleitung GmbH (AT), Bayernets GmbH (DE), Plinovodi s.r.o. (SLO)and NET4GAS, s.r.o. (CZ). As part of the 5GL Project the Oberkappel project would be interconnected indirectly also to the TGL pipeline project, the storages 7Fields and Haidach (AT) as well as to the gas grid in Southern Germany atHaiming/Burghausen.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub AustriaHub Czech Republic
GRIP Central Eastern Europe 2014 – 2023 Annex B | 55
CZECH REPUBLIC
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Poland-Czech Republic Interconnection within the North-South Corridor (STORK II)
NET4GAS, s.r.o.
NET4GAS, s.r.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-136 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+107,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2019
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
(CZ and PL border), NET4GAS, s.r.o. (CZ)
(100%)
from Kedzierzyn to
border), GAZ-SYSTEM S.A. (PL) (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 56
CZECH REPUBLIC
Modelled Direction
Yes exitYes entry
Security of Supply, Market integration (CEE Region (mainly CZ, PL)), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (CZ, PL), N-1 Regional (CEE Region), Back-up for renewables, Power-to-gas, Biogas, Theproject aims to increase the cross-border capacity between Poland and the Czech Republic by establishing a large transportation corridor that will allow for flexible transport of gas in Central Europe in direction North-South.Increase the security of gas supply and provide the overall flexibility for the CEE region and diversify the supply routes for the CEE region.Improve European gas grid interconnection.Increase the security and reliability of the cross-border gas transmission between the Czech Republic and Poland (fulfilment of N-1 rule in Poland). Create a robust, well-functioning internal market in the Czech Republic and Poland and promote the competition. Contribute to the creation of the integrated and competitive gas market in CEE region.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector CZ-PL
PROJECTED CAPACITY INCREASES
Hub Czech RepublicHub Poland220,50
153,40
The STORK II interconnector pipeline will be part of the Czech and Polish transmission system and will increase cross-border capacity between these two countries by establishing a large transportation corridor that will allow flexibletransport of gas in Central Europe in direction North-South.The development of the physical interconnection between Poland and Czech Republic will contribute to reinforcement of the effective operation of the gas transmissionsystems, efficient gas exchange between the markets, as well as increase of the security of supply not only for Poland and Czech Republic, but also for the CEE region by enabling the supply link with the European gas market (NCG, CEGH
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Czech RepublicHub Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 57
CZECH REPUBLIC
GRIP Central Eastern Europe 2014 – 2023 Annex B | 58
5 GermanyGASCADE Gastransport GmbH
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
Expansion of Nord Stream connection to markets in western Europe - Exit Eynatten
GASCADE Gastransport GmbH
GASCADE Gastransport GmbH
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-324 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
3
+440,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2022
+203,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 59
GERMANY
Modelled Direction
Yes exitYes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Eynatten 1 (BE) // Lichtenbusch / Raeren (DE)Bunde (DE) / Oude Statenzijl (H) (NL) (GASCADE)
PROJECTED CAPACITY INCREASES
Hub Netherlands (VIP NL/Gaspool)Hub Belgium (H-Zone)374,00
234,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Germany (GASPOOL)Hub Germany (GASPOOL)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 60
GERMANY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
Expansion of Nord Stream connection to markets in western Europe - Entry Greifswalder Bodden area
GASCADE Gastransport GmbH
NEL Gastransport GmbH
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-323 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2022
+171,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 61
GERMANY
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Greifswald / NEL
PROJECTED CAPACITY INCREASES
Hub Germany (GASPOOL)857,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Nord Stream (Russia Greifswald)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 62
GERMANY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
Installation of Nord Stream onshore project
GASCADE Gastransport GmbH
GASCADE Gastransport GmbH
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-289 FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
Permitting0%
2012FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
22013
+90,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2013 Q1
2014/1
+27,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GASCADE (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 63
GERMANY
Modelled Direction
Yes exitYes exit
Market integration (GASPOOL / NCG (Gernsheim)), Diversification of sources,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
GernsheimEynatten 1 (BE) // Lichtenbusch / Raeren (DE)
PROJECTED CAPACITY INCREASES
Hub Belgium (H-Zone)Hub Germany (NCG)105,60
30,00
None
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Germany (GASPOOL)Hub Germany (GASPOOL)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 64
GERMANY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
Installing a reverse flow in Mallnow
GASCADE Gastransport GmbH
GASCADE Gastransport GmbH
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-292 FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
Permitting0%
2013FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2013
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2013
2014
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GASCADE (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 65
GERMANY
Modelled Direction
Yes exit
Reverse Flows, Diversification of sources,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Mallnow
PROJECTED CAPACITY INCREASES
Yamal (Poland)168,00
new metering station
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Germany (GASPOOL)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 66
GERMANY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
new net connection from Rehden to Drohne (new covenant from NEP2012)
GASCADE Gastransport GmbH
GASCADE Gastransport GmbH
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-291 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12016 Q4
+26,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2017
2018/1
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GASCADE (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 67
GERMANY
Modelled Direction
Yes exit
Market integration (GASPOOL / NCG),
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Drohne GASCADE / OGE
PROJECTED CAPACITY INCREASES
Hub Germany (NCG)144,00
It is necessary to increase the capacity of the pipeline between the OGE Infrastructure (market area of NCG) and GASCADE (Market area of GASPOOL).This connection will increase the capacity by 6 GW to ensure the supply in south-westGermany.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Germany (GASPOOL)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 68
GERMANY
GRIP Central Eastern Europe 2014 – 2023 Annex B | 69
5 GermanyGasunie Deutschland Transport Services GmbH
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
Expansion of Nord Stream connection to markets in western Europe - Exit Bunde-Oude
Gasunie Deutschland Transport Services GmbH
Gasunie Deutschland Transport Services GmbH
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-316 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+25,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2020/3
+30,00
+0,90
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 70
GERMANY
Modelled Direction
No exitNo exitYes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Bunde (DE) / Oude Statenzijl (H) (NL) (GUD)
PROJECTED CAPACITY INCREASES
Hub Netherlands (VIP NL/Gaspool)Hub Netherlands (VIP NL/Gaspool)
Hub Netherlands (VIP NL/Gaspool)676,00169,00338,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Germany (GASPOOL)Hub Germany (GASPOOL)Hub Germany (GASPOOL)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 71
GERMANY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Extension of existing gas transmission capacity in the direction to Denmark - 1. Step
Gasunie Deutschland Transport Services GmbH
Gasunie Deutschland Transport Services GmbH
Pipeline including CS
www.gasunie.de
Interested by PCI ?
IGAs
Web Link
TRA-F-231 FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
Construction0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2014/4
+15,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Gasunie Deutschland (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 72
GERMANY
Modelled Direction
Yes exit
Security of Supply, Market integration, )o Better connection of the gas hubs (TTF in the Netherlands and market area GASPOOL in Germany);o Compensation of the depletion of Danish gas fields and better connection of gas hubs;o Connection of new storages to the GUD-grid.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Ellund (GUD)
PROJECTED CAPACITY INCREASES
Hub Denmark (Ellund)50,81
None
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Germany (GASPOOL)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 73
GERMANY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Extension of existing gas transmission capacity in the direction to Denmark - 2. Step
Gasunie Deutschland Transport Services GmbH
Gasunie Deutschland Transport Services GmbH
Pipeline including CS
www.gasunie.de
Interested by PCI ?
IGAs
Web Link
TRA-N-232 FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
Construction0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2
+63,50
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2015/2016
+16,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Gasunie Deutschland (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 74
GERMANY
Modelled Direction
Yes exit
Security of Supply, Market integration, o Better connection of the gas hubs (TTF in the Netherlands and market ared GASPOOL in Germany);o Compensation of the depletion of Danish gas fields and better connection of gas hubs;o Connection of new storages to the GUD-grid.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Ellund (GUD)
PROJECTED CAPACITY INCREASES
Hub Denmark (Ellund)40,56
None
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Germany (GASPOOL)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 75
GERMANY
GRIP Central Eastern Europe 2014 – 2023 Annex B | 76
5 GermanyGasunie Ostseeanbindungsleitung GmbH
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
Expansion of Nord Stream connection to markets in western Europe - Entry Greifswald
Gasunie Deutschland Transport Services GmbH
Gasunie Ostseeanbindungsleitung GmbH
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-321 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+100,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2020/3
+60,00
+0,90
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 77
GERMANY
Modelled Direction
No entryYes entryNo entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Greifswald / GOAL
PROJECTED CAPACITY INCREASES
Hub Germany (GASPOOL)Hub Germany (GASPOOL)
Hub Germany (GASPOOL)1.188,00679,00338,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Nord Stream (Russia Greifswald)Nord Stream (Russia Greifswald)Nord Stream (Russia Greifswald)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 78
GERMANY
GRIP Central Eastern Europe 2014 – 2023 Annex B | 79
5 GermanyGRTgaz Deutschland GmbH
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
Gernsheim-MIDAL
GRTgaz Deutschland
GRTgaz Deutschland GmbH
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-327 FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
Construction0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2013/4
+8,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 80
GERMANY
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Gernsheim
PROJECTED CAPACITY INCREASES
Hub Germany (NCG)106,60
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Germany (GASPOOL)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 81
GERMANY
GRIP Central Eastern Europe 2014 – 2023 Annex B | 82
5 GermanyOpen Grid Europe GmbH
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Open Grid Europe GmbH
Open Grid Europe GmbH
Production Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
Production facility
Expected volume (bcm/y)
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
End of permitting phase
2016/4
Considered TPA Regime
Considered Tariff Regime Not applicable
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 83
GERMANY
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 84
GERMANY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
Stepwise change-over to physical H-gas operation of L-gas networks
Open Grid Europe GmbH
Open Grid Europe GmbH
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-244 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
Planned0%
2020FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2020
Considered TPA Regime
Considered Tariff Regime Not applicable
Not applicable
OGE (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 85
GERMANY
Modelled Direction
Security of Supply, Market integration, o Security of Supplyo Market Integration (Increase of competition)o A decline in availability of L-gas necessitates action.Open Season 2008: The project prioritisation process has been carried out in a non-discriminatory manner based on criteria suggested by BNetzA. It takes into account the factors competition, security of supply, as well as networkefficiency. Capacities were allotted to new market entrants. North-south and west-east de-bottlenecking strengthens security of supply.Future projects: The overall economic benefit of a physical change-over from L (low calorific) to H-gas (high calorific) is higher than permanent conversion. Furthermore, enabling access of storage and gas fired power stations to thenetwork necessitates investments. These measures also serve both market integration and security of supply.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Stepwise change-over to physical H-gas operation of L-gas networks (due to decreasing L-gas supply)
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 86
GERMANY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
System enhancements, including the connection of gas-fired power plants, storages and the integration of power to gas facilities
Open Grid Europe GmbH
Open Grid Europe GmbH
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-243 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
Not relevant
Planned0%
2020FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2020
Considered TPA Regime
Considered Tariff Regime Not applicable
Not applicable
GRIP Central Eastern Europe 2014 – 2023 Annex B | 87
GERMANY
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 88
GERMANY
GRIP Central Eastern Europe 2014 – 2023 Annex B | 89
5 Germanyterranets bw GmbH
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
2015 Q1
2015/4
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12014 Q1
+70.00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
No
0%
No
Planned0%
2013 Q4FID
Construction
Commissioning
Last completed Phase :
Not part of TEN-E
Not defined yet
Nordschwarzwaldleitung
terranets bw GmbH
terranets bw GmbH
Pipeline including CS
www.terranets-bw.de
Interested by PCI ?
IGAs
Web Link
TRA-N-228 Non-FID
Promoter
Operator
TEN-E Project ?
NoneNOS 1, terranets bw
(100%) NOS 2, terranets bw
(100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 90
GERMANY
Modelled Direction
No entry
pipeline between Au am Rhein, coupling to TENP and Leonberg/Stuttgart
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Germany (NCG)72.00Au am Rhein
PROJECTED CAPACITY INCREASES
Hub Germany (NCG)
Security of Supply, Diversification of sources, Diversification of routes, Firm capacity can be provided to downstream distribution network operator. Security of Supply will be increased in south-west Germany.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
GRIP Central Eastern Europe 2014 – 2023 Annex B | 91
GERMANY
GRIP Central Eastern Europe 2014 – 2023 Annex B | 92
5 GermanyStorengy Deutschland GmbH
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Considered TPA Regime
Considered Tariff Regime Negotiated (e.g. Exemption)
Negotiated (e.g. Exemption)
2014/4
+3.00
+7.00
Storage facility
Working volume (mcm)
Peckensen Storage
+180.00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
Not relevant
0%
No
Construction0%
FID
Construction
Commissioning
Last completed Phase :
Not part of TEN-E
Yes
Storengy
Storengy Deutschland GmbH
Storage Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
Storengy Deutschland (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 93
GERMANY
Modelled Direction
Extension of the existing salt cavity gas storage.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
PROJECTED CAPACITY INCREASES
Security of Supply, Market integration (Western and Central Europe), Apart from the benefits listed above, the projects will contribute to increased flexibility of the system which will have a positive impact on both market integration and security of supply. Thanks to its location (on the link between the NGC market area and the Gaspool market area), the project will have a positive expected influence on price convergence and arbitrage opportunities.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
GRIP Central Eastern Europe 2014 – 2023 Annex B | 94
GERMANY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Considered TPA Regime
Considered Tariff Regime Negotiated (e.g. Exemption)
Negotiated (e.g. Exemption)
2017/4
+1.00
+3.00
Storage facility
Working volume (mcm)
Peckensen Storage
+100.00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
Not relevant
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
Not part of TEN-E
Yes
Storengy
Storengy Deutschland GmbH
Storage Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
Storengy Deutschland (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 95
GERMANY
Modelled Direction
Extension of the existing salt cavity gas storage.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
PROJECTED CAPACITY INCREASES
Security of Supply, Market integration (Western and Central Europe), Apart from the benefits listed above, the projects will contribute to increased flexibility of the system which will have a positive impact on both market integration and security of supply. Thanks to its location (on the link between the NGC market area and the Gaspool market area), the project will have a positive expected influence on price convergence and arbitrage opportunities.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
GRIP Central Eastern Europe 2014 – 2023 Annex B | 96
GERMANY
GRIP Central Eastern Europe 2014 – 2023 Annex B | 97
6 HungaryFGSZ Ltd.
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
Csepel connecting pipeline
FGSZ Ltd
FGSZ Ltd.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-019 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
2014 Q3FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12016 Q1
+14,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2016 Q1
2016/4
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 98
HUNGARY
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 99
HUNGARY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Ercsi-Szazhalombatta
FGSZ Ltd
FGSZ Ltd.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-061 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
2014 Q4FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12016 Q1
+11,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2016 Q1
2017/3
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 100
HUNGARY
Modelled Direction
Yes exitYes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Vecsés MGT / FGSZ
PROJECTED CAPACITY INCREASES
Hub HungaryHub Hungary (SK-HU Interconnector)51,00
25,50
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub HungaryHub Hungary (SK-HU
GRIP Central Eastern Europe 2014 – 2023 Annex B | 101
HUNGARY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
Hajduszoboszlo CS
FGSZ Ltd
FGSZ Ltd.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-065 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
2017 Q4FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12018 Q2
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2019 Q2
2020/1
+5,70
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 102
HUNGARY
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 103
HUNGARY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Local Odorisation - FGSZ
FGSZ Ltd
FGSZ Ltd.
Pipeline including CS
www.fgsz.hu
Interested by PCI ?
IGAs
Web Link
TRA-N-124 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Permitting0%
2014 Q1FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2014 Q3
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2014 Q3
2015/3
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
FGSZ (100%)
Private Financing (100,00%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 104
HUNGARY
Modelled Direction
Market integration ( The overall flexibility of the system is enhanced through AT/HU border capacity.), o The Hungarian projects taken as a whole main aim, is to enhance the flexibility of the Hungarian transmission system by connectingto neighbouring systems, ensuring reserves flow availability, and guaranteeing flow deliverability which will enhance the transmission systems security of supply position along with helping with further market integration. ,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Elimination of central odorisation in the western part of Hungary, and establishment of local odorisation
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 105
HUNGARY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Romanian-Hungarian reverse flow Hungarian section
FGSZ Ltd
FGSZ Ltd.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-286 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Planned0%
2013 Q2FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
32014 Q1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2014 Q1
2015/4
+13,50
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 106
HUNGARY
Modelled Direction
Yes entryYes entryNo exitNo entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Hub Romania
Csanadpalota
PROJECTED CAPACITY INCREASES
Hub HungaryHub RomaniaHub Hungary
Hub Hungary
76,85
51,2012,6076,85
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub RomaniaHub RomaniaHub Hungary
GRIP Central Eastern Europe 2014 – 2023 Annex B | 107
HUNGARY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Slovenian-Hungarian interconnector
FGSZ Ltd
FGSZ Ltd.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-325 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
2015 Q2FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12016 Q3
+41,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2016 Q3
2017/4
+7,50
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 108
HUNGARY
Modelled Direction
Yes exitYes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector SI-HU
PROJECTED CAPACITY INCREASES
Hub HungaryHub Slovenia45,25
45,25
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub HungaryHub Slovenia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 109
HUNGARY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Városföld CS
FGSZ Ltd
FGSZ Ltd.
Pipeline including CS
www.fgsz.hu
Interested by PCI ?
IGAs
Web Link
TRA-N-123 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
2014 Q3FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12015 Q3
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2016 Q1
2017/3
+5,70
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
FGSZ (100%)
Private Financing (100,00%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 110
HUNGARY
Modelled Direction
Yes exitYes entry
Market integration (Increase AT/HU border capacity, Security of Supply of Western Hungary, New power plant supply at Budapest region, Reverse fllow HU>AT, Create capacity RO>AT), o The Hungarian projects taken as a whole mainaim, is to enhance the flexibility of the Hungarian transmission system by connecting to neighbouring systems, ensuring reserves flow availability, and guaranteeing flow deliverability which will enhance the transmission systems securityof supply position along with helping with further market integration. ,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Mosonmagyarovar
PROJECTED CAPACITY INCREASES
Hub HungaryHub Austria153,00
25,00
Compressor station extension, 5,7 MW
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub HungaryHub Austria
GRIP Central Eastern Europe 2014 – 2023 Annex B | 111
HUNGARY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
FGSZ Ltd
FGSZ Ltd.
Pipeline including CS
www.fgsz.hu
Interested by PCI ?
IGAs
Web Link
TRA-N-018 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
2014 Q1FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12017 Q4
+210,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2015 Q1
2017/3
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
FGSZ (100%)
Private Financing (100,00%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 112
HUNGARY
Modelled Direction
Yes exitYes entryYes exitYes entry
Security of Supply, Market integration (Increase AT/HU border capacity, Security of Supply of Western Hungary, new power plant supply, Reverse fllow HU>AT, Increase capacity Sk>HU and HU>SK, Create capacity RO>AT), ReverseFlows, Diversification of sources, o The Hungarian projects taken as a whole main aim, is to enhance the flexibility of the Hungarian transmission system by connecting to neighbouring systems, ensuring reserves flow availability, andguaranteeing flow deliverability which will enhance the transmission systems security of supply position along with helping with further market integration. ,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Hub Austria
Vecsés MGT / FGSZ
Mosonmagyarovar
PROJECTED CAPACITY INCREASES
Hub HungaryHub AustriaHub Hungary
Hub Hungary (SK-HU Interconnector)
25,00
51,0025,50
153,00
Pipeline between Városföld-Ercsi and nodes, DN1000, PN100, 210 km.This project will enable the Mosonmagyarovar interconnection point to reach its full capacity of 153 GWh/d from Austria to Hungary.It will also enable theMosonmagyarovar interconnection point to realize reverse flow capacity up to 153 GWh/d from Hungary to Austria as well.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub HungaryHub Hungary (SK-HU Hub Hungary
GRIP Central Eastern Europe 2014 – 2023 Annex B | 113
HUNGARY
GRIP Central Eastern Europe 2014 – 2023 Annex B | 114
6 HungaryHungarian Gas Storage
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
E.ON Földgaz
E.ON Hungary Storage
Storage Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
No
0%
No
FEED0%
2012 Q4FID
Construction
Commissioning
Last completed Phase :
Storage facility
Working volume (mcm)
Pusztaederics2013 Q1
+340,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
2013 Q2
2013
+2,50
+2,90
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
E.ON Hungary Storage (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 115
HUNGARY
Modelled Direction
Yes entryYes exit
Market integration, Diversification of routes,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
UGS - HU - FGSZ/E.ON Hungary
PROJECTED CAPACITY INCREASES
Hub HungaryStorage Hungary27,50
31,90
��
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub HungaryStorage Hungary
GRIP Central Eastern Europe 2014 – 2023 Annex B | 116
HUNGARY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Not defined yet
E.ON Földgaz
E.ON Hungary Storage
Storage Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Market test0%
2015 Q4FID
Construction
Commissioning
Last completed Phase :
Storage facility
Working volume (mcm)
Zsana2016 Q1
+2.140,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
2016 Q3
2016/4
+17,20
+28,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 117
HUNGARY
Modelled Direction
Yes entryYes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
UGS - HU - FGSZ/E.ON Hungary
PROJECTED CAPACITY INCREASES
Hub HungaryStorage Hungary189,20
308,00
�
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub HungaryStorage Hungary
GRIP Central Eastern Europe 2014 – 2023 Annex B | 118
HUNGARY
GRIP Central Eastern Europe 2014 – 2023 Annex B | 119
6 HungaryMagyar Gaz Tranzit Zrt.
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
AGRI Pipeline - Hungarian section
Magyar Gaz Tranzit Zrt.
MGT Hungarian Gas Transit Ltd.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-195 FID
Promoter
Operator
TEN-E Project ?
1
no
0%
No
0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2023*
Considered TPA Regime
Considered Tariff Regime Not applicable
Not applicable
Hungarian section, MVM,SOCAR,GOGC,R
OMGAZ (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 120
HUNGARY
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
The project is in feassibility phase
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 121
HUNGARY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
Slovak-Hungarian interconnector (Vecsés-Szada-Balassagyarmat)
Magyar Gaz Tranzit Zrt.
MGT Hungarian Gas Transit Ltd.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-148 FID
Promoter
Operator
TEN-E Project ?
1
no
0%
No
Construction0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
22014
+110,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2013
2014/1
Considered TPA Regime
Considered Tariff Regime regulated
regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 122
HUNGARY
Modelled Direction
Yes entryYes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Balassagyarmat
PROJECTED CAPACITY INCREASES
Hub SlovakiaHub Hungary (SK-HU Interconnector)127,40
50,90
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub SlovakiaHub Hungary (SK-HU
GRIP Central Eastern Europe 2014 – 2023 Annex B | 123
HUNGARY
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
South Stream Hungary
Magyar Gaz Tranzit Zrt.
MGT Hungarian Gas Transit Ltd.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-196 FID
Promoter
Operator
TEN-E Project ?
1
Not relevant
45%
Not relevant
50%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12015
+220,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2014
2015/1
Considered TPA Regime
Considered Tariff Regime Not applicable
Not applicable
GRIP Central Eastern Europe 2014 – 2023 Annex B | 124
HUNGARY
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
South Stream (Bata, Nagykanizsa) (HU)
PROJECTED CAPACITY INCREASES
Hub Hungary224,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
South Stream (Russia)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 125
HUNGARY
GRIP Central Eastern Europe 2014 – 2023 Annex B | 126
7 PolandGas Transmission Operator GAZ-SYSTEM S.A.
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Gas Interconnection Poland-Lithuania (GIPL)
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A.
Pipeline including CS
en.gaz-system.pl/nasze-inwestycje/integracja-z-europejski-systemem/polska-litwa/
Interested by PCI ?
IGAs
Web Link
TRA-N-212 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
30.04.2010 2012
Planned0%
2015FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2
+534,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2018
+16,00
Date of Request Year Funding GrantedTEN-E Requests
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Lithuanian section, AB Amber Grid
(100%)
Polish section, Gas Transmission
Operator GAZ-SYSTEM S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 127
POLAND
Modelled Direction
No exitYes entryYes exit
Security of Supply, Market integration (market areas in the Baltic States and Central-Eastern Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Lithuania and possibly Latvia, Estonia), N-1 Regional(the Baltic Sea region), Back-up for renewables, The very aim of GIPL is the integration of the isolated gas markets of the Baltic States into the EU gas grid, by introducing the alternative gas supply route to the Baltic States. Thisinterconnection will diversify the gas supply sources, increase the security of supply and will serve for the enhancement of competition in the gas market of the Baltic States.For the Baltic States, GIPL will provide the access both to EU gas spot market and to the global LNG market via LNG terminal in In the long-term perspective, it may also be used to import shale-gas from Poland, if theproduction reaches into large scale level. For the Polish market players, GIPL will provide the opportunity of using Latvian Incukalns UGS. Also through GIPL, gas could be supplied to currently non-gasified areas in Poland and Lithuania.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector PL-LT
PROJECTED CAPACITY INCREASES
Hub PolandHub Lithuania
Hub Lithuania63,7029,0068,00
GIPL aims to connect the gas transmission systems in Poland and Lithuania and, consiquently, enable the integration of the isolated gas markets in the Baltic States (and Finland) with the Polish and EU gas markets contributing to thecreation of the regional gas market, enhancing competition and the security of gas supply. The project will also provide an access to the global LNG market for the Baltic States (via the LNG terminal in The construction ofGIPL, except the above benefits for security and diversification of gas supplies in the Baltic region, will allow to connect the Baltic States with the CEE countries, thus providing strategic link between the BEMIP and North-South prioritycorridors in this part of Europe.
TEN-E (obtained for studies), support from other EU funds is expected
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub PolandHub LithuaniaHub Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 128
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Priority Project
No
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A.
LNG Terminal
en.gaz-system.pl/terminal-lng/
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
FID0%
2010FID
Construction
Commissioning
Last completed Phase :
Regasification facility
Expected volume (bcm/y) +5,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction No
Total CS Power (MW)
Send-out (mcm/d)
End of permitting phase
Ship size (m3)
Reloading ability ?
2014
+320.000,00
+13,68
216.000,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Gas Transmission Operator GAZ-
SYSTEM S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 129
POLAND
Modelled Direction
Yes entry
Security of Supply, Diversification of sources, Diversification of routes, N-1 National (Poland and possibly Lithuania, Latvia, Estonia, Denmark, Slovakia and Hungary), N-1 Regional (Baltic Sea region, Central-Eastern Europe), Back-up forrenewables, The LNG terminal in Swinoujscie will have an impact on:increasing security of supply in the Baltic Sea and CEE regions by diversifying supply routes, sources (the first new physical source of supply for both regions) and counterparts (access to global LNG market);creating well-interconnected gas infrastructure in the Baltic Sea and CEE regions;eliminating the energy islands, as the terminal in Swinoujscie may play the role of regional LNG terminal for the Baltic States and Finland (transport of gas via Gas Interconnection Poland-Lithuania or transport by LNG vessels);enhancing competition on regional markets;promoting natural gas as a reliable, competitive and environmentally-friendly source of energy e.g. in the transport sector (maritime transport);creating a physical hub in Swinoujscie and/or a virtual hub in Poland;establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in theBaltic Sea region and in Central-Eastern Europe.The LNG terminal in contributes to North-South gas interconnections in Central Eastern and South Eastern Europe, as the supplies from may be directed through upgraded transmission system in Poland (theNorth-South Corridor in Poland), PL-CZ and PL-SK interconnections towards the South, to other CEE countries.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Swinoujscie
PROJECTED CAPACITY INCREASES
Hub Poland150,48
The LNG terminal in will be the first LNG terminal in the Baltic Sea region. It will come on stream in 2014 with annual re-gasification capacity of 5 bcm/y. In the following years, depending on the increase of demand for gas, itwill be possible to increase the capacity up to 7,5 bcm/y, without the need to increase the area on which the terminal will be constructed. The terminal in will consist of two storage tanks, each with the capacity of 160 tcm.The LNG terminal in will offer its regasification capacities not only to gas consumers in Poland, but also in the Baltic Sea region (supplies to be directed via Gas Interconnection Poland-Lithuania and/or LNG ships) and inCentral-Eastern Europe (supplies within the North-South Gas Interconnections).
EEPR, ERDF (Operational Programme Infrastructure and Environment), TEN-E
Equity, commercial banks EIB, EBRD
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
LNG Terminals Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 130
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
Physical reverse flow on the metering station in Mallnow
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A. (ISO)
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-326 FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Construction0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2013
2013
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Gas Transmission Operator GAZ-
SYSTEM S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 131
POLAND
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Mallnow
PROJECTED CAPACITY INCREASES
Yamal (Poland)168,00
The project aims to introduce physical reverse flow on the Yamal-Europe pipeline (flow in the direction from DE to PL). The project increases security of supply to Poland by diversifying supply sources and routes. Implementation of theproject facilitates the access of the network users in Poland to the gas market in Germany.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Germany (GASPOOL)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 132
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
PL - CZ interconnection
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-273 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Planned0%
2017FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+107,60
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2019
+16,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Czech section, NET4GAS, s.r.o.
(100%)
Polish section, Gas Transmission
Operator GAZ-SYSTEM S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 133
POLAND
Modelled Direction
No entryYes entryYes exit
Security of Supply, Market integration (market areas in Central-Eastern Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland, possibly Slovakia and Hungary), N-1 Regional (Central-EasternEurope), Back-up for renewables, Implementation of PL-CZ interconnection will have an impact on:increasing the security of gas supply and providing the overall flexibility for the CEE region and diversifying the supply routes for the CEE region;improving European gas grid interconnection;increasing the security and reliability of the cross-border gas transmission between the Czech Republic and Poland (fulfilment of N-1 rule in Poland);creating a robust, well-functioning internal market in the Czech Republic and Poland and promoting the competition;contributing to the creation of an integrated and competitive gas market in the CEE region;establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in Central-Eastern Europe.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector CZ-PL
PROJECTED CAPACITY INCREASES
Hub PolandHub Czech Republic
Hub Poland105,40195,90150,60
The project aims to increase the cross-border capacity between Poland and the Czech Republic by establishing a large transportation corridor that will allow for flexible transport of gas in Central-Eastern Europe within the North-Southcorridor.
Support from EU funds is expected
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Czech RepublicHub Czech RepublicHub Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 134
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
PL - DK interconnection (Baltic Pipe)
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A.
Pipeline including CS
en.gaz-system.pl/nasze-inwestycje/integracja-z-europejski-systemem/baltyckibaltic-pipe/
Interested by PCI ?
IGAs
Web Link
TRA-N-271 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
30.06.2008
24.04.2009
2009
2010
Planned0%
2015FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2
+324,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2020
Date of Request Year Funding GrantedTEN-E Requests
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Gas Transmission Operator GAZ-
SYSTEM S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 135
POLAND
Modelled Direction
Yes entryYes exit
Security of Supply, Market integration (market areas in the Baltic Sea region and Central-Eastern Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland, Denmark), N-1 Regional (the Baltic Searegion), Back-up for renewables, Baltic Pipe will have a significant impact on:increasing security of supply in the Baltic Sea region by diversifying supply routes, sources and counterparts;creating well-interconnected gas infrastructure in the Baltic Sea region;enhancing competition on the regional markets;promoting natural gas as a reliable, competitive and environmentally-friendly source of energy e.g. in the power generation sector. The Baltic Pipe project also contributes to North-South gas interconnections in Central Eastern and South Eastern Europe, as the project which will allow to transport gas from North Sea deposits to the CEE countries, namely to the CzechRepublic and Slovakia (via the North-South corridor in Poland, PL-CZ and PL-SK interconnections).,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector PL-DK
PROJECTED CAPACITY INCREASES
Hub DenmarkHub Poland90,40
90,40
Baltic Pipe aims to connect the gas transmission systems in Poland and Denmark and thus cover the higher import needs of Danish and Swedish markets originating from declining production in the Danish part of the North Sea. Theproject will also cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in the Baltic States and Central-Eastern Europe.
TEN-E (obtained), support from other EU funds is expected
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub DenmarkHub Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 136
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
PL - SK interconnection
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A.
Pipeline including CS
en.gaz-system.pl/nasze-inwestycje/integracja-z-europejski-systemem/polska-slowacja/
Interested by PCI ?
IGAs
Web Link
TRA-N-275 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
28.02.2011 2012
Planned0%
2017FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+164,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2019
+29,10
Date of Request Year Funding GrantedTEN-E Requests
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Polish section, Gas Transmission
Operator GAZ-SYSTEM S.A. (100%)
Slovak section, eustream, a.s. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 137
POLAND
Modelled Direction
Yes exitYes entryYes entry
Security of Supply, Market integration (market areas in Central-Eastern Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland, Slovakia and possibly Hungary), N-1 Regional (Central-EasternEurope), Back-up for renewables, Implementation of PL-SK interconnection will have an impact on:creating the cross-border capacity between Poland and Slovakia by establishing a large transportation corridor that will allow for flexible transport of gas in Central Europe within the North-South axis;increasing the security of gas supply and diversification of supply routes for the CEE region;improve European gas grid interconnection;increasing the security and reliability of the cross-border gas transmission between Slovakia and Poland (contribution to N-1 standard in Poland and Slovakia);creating a robust, well-functioning internal market in Slovakia and Poland and promote the competition;establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in Central-Eastern Europe.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector PL - SK
PROJECTED CAPACITY INCREASES
Hub PolandHub Poland
Hub Slovakia141,60129,50171,70
The main goal of the project is to create an important part of the North-South gas interconnections in Central-Eastern Europe by implementing a missing interconnection between the transmission systems in Poland and Slovakia and,thus, increase the security of gas supplies in Central-Eastern Europe through the diversification of supply sources and routes, as well as integration of Sub-Carpathian Market Area and enhancing market functionality.
TENE (obtained), support from EU funds is expected
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub PolandHub SlovakiaHub Slovakia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 138
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-276 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2015
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Gas Transmission Operator GAZ-
SYSTEM S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 139
POLAND
Modelled Direction
Yes entryYes entry
Security of Supply, Market integration (integration of market areas in the Baltic Sea region and Central-Eastern Europe with Western Europe (GASPOOL and NetConnect in Germany)), Reverse Flows, Diversification of sources,Diversification of routes, N-1 National (Poland and possibly Lithuania, Latvia, Estonia, Slovakia, Hungary), N-1 Regional (the Baltic Sea region, Central-Eastern Europe), Back-up for renewables, The upgrade of the capacity of the entrypoints in Lwowek and Wloclawek on the Yamal-Europe pipeline will have an impact on:enhancing competition in Poland and other countires in the Baltic and CEE regions by significantly facilitating the access to the Western European gas markets (in particular GASPOOL and NetConnect in Germany);increasing security of supply in the Baltic Sea and CEE regions by diversifying supply routes and counterparts (the access to the Western European gas markets);creating well-interconnected gas infrastructure between Western Europe (Germany), the Baltic Sea and CEE regions;contributing to elimination of the energy islands, as the project may constitute a source of gas supplies for the Baltic States and Finland (via Gas Interconnection Poland-Lithuania);establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in theBaltic Sea region and in Central-Eastern Europe.
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
WloclawekLwowek
PROJECTED CAPACITY INCREASES
Hub PolandHub Poland183,00
36,60
The main objective of the project is to upgrade the capacity of the entry points in Lwówek and Wloclawek on the Yamal-Europe pipeline. The project will enable to benefit from the economies of scale, as relatively low investment costswill significantly increase the possibility of gas deliveries via physical reverse flow (currently virtual reverse flow is available only) on the Yamal-Europe pipeline to entry into the transmission system in Poland and later on in the BalticStates (via Gas Interconnection Poland-Lithuania) and other CEE countries (via the North-South Gas Interconnections). This will in turn enhance the access of gas markets players in these countries to well-developed market area inGermany.
Support from EU funds is expected
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Yamal (Poland)Yamal (Poland)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 140
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
Upgrade of gas infrastructure in northern and central Poland
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A.
Pipeline including CS
en.gaz-system.pl/nasze-inwestycje/krajowy-system-przesylowy/
Interested by PCI ?
IGAs
Web Link
TRA-F-248 FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
FID0%
2007FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
5
+875,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2014
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Gas Transmission Operator GAZ-
SYSTEM S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 141
POLAND
Modelled Direction
Security of Supply, Market integration (market areas in the Central-Eastern Europe and possibly in the Baltic States), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland and possibly Slovakia, Hungary,Lithuania, Latvia and Estonia), N-1 Regional (Central-Eastern Europe, Baltic Sea region), Back-up for renewables, ,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
The project consists of the internal pipelines that are currently being constructed in northern and central Poland with the aim to enhance functionality of the transmission system in Poland and, thus, provide adequate techincalconditions to distribute natural gas supplied to the LNG terminal in The project is strictly linked to the development of gas infrastructure within the North-South gas interconnections in Central Eastern and South EasternEurope. Implementation of the internal pipelines will contribute to increasing the security of supply sources, routes and counterparts, as well as to providing the overall flexibility for the gas market in Poland and the whole CEE region.
EEPR, ERDF (Operational Programme Infrastructure and Environment) Equity, commercial banks
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 142
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A.
LNG Terminal
en.gaz-system.pl/terminal-lng/
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Planned0%
2014FID
Construction
Commissioning
Last completed Phase :
Regasification facility
Expected volume (bcm/y) +2,50
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction Yes
Total CS Power (MW)
Send-out (mcm/d)
End of permitting phase
Ship size (m3)
Reloading ability ?
2020
+160.000,00
+6,84
216.000,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Gas Transmission Operator GAZ-
SYSTEM S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 143
POLAND
Modelled Direction
Yes entry
Security of Supply, Diversification of sources, Diversification of routes, N-1 National (Poland and possibly Lithuania, Latvia, Estonia, Denmark, Slovakia and Hungary), N-1 Regional (Baltic Sea region, Central-Eastern Europe), Back-up forrenewables, The extension of the LNG terminal in Swinoujscie will have an impact on:increasing security of supply in the Baltic Sea and CEE regions by diversifying supply routes, sources (the first new physical source of supply for both regions) and counterparts (access to global LNG market);creating well-interconnected gas infrastructure in the Baltic Sea and CEE regions;eliminating the energy islands, as the terminal in Swinoujscie may play the role of regional LNG terminal for the Baltic States and Finland (transport of gas via Gas Interconnection Poland-Lithuania or transport by LNG vessels);enhancing competition on regional markets;promoting natural gas as a reliable, competitive and environmentally-friendly source of energy e.g. in the transport sector (maritime transport);creating a physical hub in Swinoujscie and/or a virtual hub in Poland;establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in theBaltic Sea region and in Central-Eastern Europe.The LNG terminal in contributes to North-South gas interconnections in Central Eastern and South Eastern Europe, as the supplies from may be directed through upgraded transmission system in Poland (theNorth-South Corridor in Poland), PL-CZ and PL-SK interconnections towards the South, to other CEE countries.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Swinoujscie
PROJECTED CAPACITY INCREASES
Hub Poland75,24
The main objective of the project is to upgrade the capacity of the LNG terminal in from 5 up to 7,5 bcm/y. The project will enable to benefit from the economies of scale, as relatively low investment costs (no need toconstruct the facility from scratch, the majority of costs will be related to the construction of the 3rd storage tank) may bring further benefits to gas consumers in the Baltic Sea area and the CEE region (increase of SoS, competition andliquidity, decrease of gas prices).
Support from EU funds is expected
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
LNG Terminals Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 144
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
2021
+10.00
# of Pipelines, nodes, CS
Total Pipeline Length (km)
4
+106.00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
Not relevant
0%
No
Planned0%
2015FID
Construction
Commissioning
Last completed Phase :
Project of Common Interest
Yes
Upgrade of PL-DE interconnection in Lasów
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A.
Pipeline including CS
en.gaz-system.pl/nasze-inwestycje/
Interested by PCI ?
IGAs
Web Link
TRA-N-274 Non-FID
Promoter
Operator
TEN-E Project ?
None
Gas Transmission Operator GAZ-
SYSTEM S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 145
POLAND
Modelled Direction
Yes entry
The main objective of the project is to modernise and expand the transmission system near PL-DE interconnection in Lasów with a view to upgrading the capacity of the interconnection point in Lasow from 1,5 up to 3 bcm/y. Theupgraded PL-DE interconnection in Lasów will improve security of gas supplies, increase reliability of cross-border transmission infrastructure between Poland and Germany and will contribute to well-interconnected gas network in theCEE region. The scope of necessary investments is currently investigated.
Support from EU funds is expected
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Germany (GASPOOL)42.00Lasów
PROJECTED CAPACITY INCREASES
Hub Poland
Security of Supply, Market integration (integration of market areas in Central-Eastern Europe and Western Europe (GASPOOL in Germany)), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland), N-1Regional (Central-Eastern Europe), Back-up for renewables, The upgraded PL-DE interconnection in Lasów will have an impact on:improving security of gas supplies and increasing reliability of cross-border transmission infrastructure between Poland and Germany;creating well-interconnected gas network in the CEE region;enhancing the access of gas market players in the CEE region to a developed, competitive and diversified Western European gas market (Germany);establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in Central-Eastern Europe.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
GRIP Central Eastern Europe 2014 – 2023 Annex B | 146
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
The North-South Gas Corridor in Eastern Poland
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-245 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Planned0%
2015FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
7
+409,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2023
+18,30
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Gas Transmission Operator GAZ-
SYSTEM S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 147
POLAND
Modelled Direction
Security of Supply, Market integration (market areas in Central-Eastern Europe and the Baltic States), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland and possibly Lithuania, Latvia, Estonia.), N-1Regional (Central-Eastern Europe, Baltic Sea region), Back-up for renewables, Implementation of the investment tasks within this project will allow for significant volumes of gas to be transported by means of PL-SK interconnection. Theywill also enhance the access to the USG Strachocina that have large expansion potential and may serve as essential security of supply infrastructure in the CEE region.The projects in eastern Poland are located in the area which offers the possibility to extract unconventional gas. If reserves are confirmed, the transmission infrastructure in Eastern Poland might well be used to transport unconventionalgas to the Baltic states (via Gas Interconnection Poland-Lithuania) and CEE countries (via PL-SK and PL-CZ interconnections).Construction of the pipelines within this project, together with completion of the PL-SK interconnection and GIPL, will definitely have a positive impact on the competition in the CEE and Baltic regions, as the project will provide apossibility to open the market for more gas suppliers. This would in turn mean ending the state of major dependency on one single gas supplier for the countries in the respective regions thanks to the potential access to gas deliveriesfrom new sources.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
The investment tasks within the project constitute essential elements of the planned North-South gas interconnections in Central Eastern and South Eastern Europe. The corridor consists of two routings on the Polish territory the basicone that is located in western and southern Poland and the complementary routing covering the area of potential unconventional gas deposits in Eastern Poland and being connected to two interconnectors, i.e. Poland Lithuania (GIPL)and Poland Slovakia. Implementation of the project will allow for significant volumes of gas to be transported by means of PL-SK interconnection. It will also enhance the access to the USG Strachocina that have large expansionpotential and may serve as essential security of supply infrastructure in the CEE region.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 148
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
The North-South corridor in Western Poland
GAZ-SYSTEM S.A.
GAZ-SYSTEM S.A.
Pipeline including CS
en.gaz-system.pl/nasze-inwestycje/krajowy-system-przesylowy/
Interested by PCI ?
IGAs
Web Link
TRA-N-247 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Planned0%
2015FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
10
+739,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2018
+7,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Gas Transmission Operator GAZ-
SYSTEM S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 149
POLAND
Modelled Direction
Security of Supply, Market integration (market areas in Central-Eastern Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (Poland), N-1 Regional (Central-Eastern Europe), Back-up for renewables,Implementation of the investment tasks within this project will have an impact on:enhancing functionality of transmission system in Central and Southern Poland in order to facilitate better operational functioning of the upgraded PL-CZ interconnection, as well as to initiate gas flow on the planned PL-SKinterconnection.increasing the security of supply sources, routes and counterparts, as well as to providing the overall flexibility for the CEE region. improving European gas grid interconnections. creating a robust, well-functioning internal market in the CEE region, by ensuring high reliability of the cross-border transmission between Poland, the Czech Republic and Slovakia.,
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
The investment tasks within the project constitute essential elements of the planned North-South gas interconnections in Central-Eastern Europe. This corridor consists of two routings on the Polish territory the basic one that is locatedin Western and Southern Poland and the complementary routing covering the area of potential unconventional gas deposits in Eastern Poland. Implementation of the project will enhance functionality of transmission system in Westernand Southern Poland. It will also enforce the internal system in order to facilitate better operational functioning of the upgraded PL-CZ interconnection, as well as to initiate gas flow on the planned PL-SK interconnection.
support from EU funds is expected
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 150
POLAND
GRIP Central Eastern Europe 2014 – 2023 Annex B | 151
7 PolandPGNiG SA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
PGniG
Operator Systemu Magazynowania Sp. Z o.o.
Storage Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
No
0%
No
FID0%
2010 Q4FID
Construction
Commissioning
Last completed Phase :
Storage facility
Working volume (mcm)
PMG Husów2014 Q2
+150,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
2014 Q2
2014/3
+0,94
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
PGNiG S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 152
POLAND
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
UGS - PL - Gaz-System/Magazynowania
PROJECTED CAPACITY INCREASES
Storage Poland10,34
Underground gas storage (PMG) extension in order to increase working gas capacity injection and withdrawal rates. Instalation of additional compressor station to allow for a more flexible opeartion.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 153
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
PGniG
Operator Systemu Magazynowania Sp. Z o.o.
Storage Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
No
0%
No
FID0%
2007 Q1FID
Construction
Commissioning
Last completed Phase :
Storage facility
Working volume (mcm)
PMG Wierzchowice2014 Q2
+625,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
2013 Q4
2014/2
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
PGNiG S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 154
POLAND
Modelled Direction
Yes exitYes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
UGS - PL - Gaz-System/Magazynowania
PROJECTED CAPACITY INCREASES
Storage PolandHub Poland52,80
39,60
Underground gas storage (PMG) extension in order to increase working gas capacity, injection and withdrawal rates
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Storage PolandHub Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 155
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
PGniG
Operator Systemu Magazynowania Sp. Z o.o.
Storage Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
No
0%
No
FID0%
2010 Q1FID
Construction
Commissioning
Last completed Phase :
Storage facility
Working volume (mcm)
PMG Brzeznica2016 Q2
+35,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
2015 Q4
2016/2
+0,34
+0,51
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
PGNiG S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 156
POLAND
Modelled Direction
Yes entryYes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
UGS - PL - Gaz-System/Magazynowania
PROJECTED CAPACITY INCREASES
Hub PolandStorage Poland3,74
5,61
Underground gas storage (PMG) extension in order to increase working gas capacity injection and withdrawal rates. Instalation of compressor station to allow for a more flexible operation.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub PolandStorage Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 157
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
PGniG
Operator Systemu Magazynowania Sp. Z o.o.
Storage Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
No
0%
No
FID0%
2007 Q4FID
Construction
Commissioning
Last completed Phase :
Storage facility
Working volume (mcm)
KPMG Mogilno2020
+392,10
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
2020
2020 +10,80
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
PGNiG S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 158
POLAND
Modelled Direction
Yes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
UGS - PL - Gaz-System/Magazynowania
PROJECTED CAPACITY INCREASES
Hub Poland118,80
Under gas storage (KPMG) extension in order to increase working gas capacity
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Storage Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 159
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
PGniG
Operator Systemu Magazynowania Sp. Z o.o.
Storage Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
No
0%
No
FID0%
2007 Q1FID
Construction
Commissioning
Last completed Phase :
Storage facility
Working volume (mcm)
KPMG Kosakowo2021
+250,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
2021
2021
+2,40
+9,60
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
PGNiG S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 160
POLAND
Modelled Direction
Yes exitYes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
UGS - PL - Gaz-System/Magazynowania
PROJECTED CAPACITY INCREASES
Storage PolandHub Poland105,60
26,40
Construction of new underground gas storage (KPMG) to secure uninterrupted gas supplies in northern Poland.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Storage PolandHub Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 161
POLAND
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
PGniG
Operator Systemu Magazynowania Sp. Z o.o.
Storage Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
2014FID
Construction
Commissioning
Last completed Phase :
Storage facility
Working volume (mcm)
PMG Wierzchowice
+800,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
2023*
+8,40
+11,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
PGNiG S.A. (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 162
POLAND
Modelled Direction
Yes exitYes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
UGS - PL - Gaz-System/Magazynowania
PROJECTED CAPACITY INCREASES
Storage PolandHub Poland121,00
92,40
Underground gas storage (PMG) extension in order to increase working gas capacity.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Storage PolandHub Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 163
POLAND
GRIP Central Eastern Europe 2014 – 2023 Annex B | 164
8RomaniaGdF Suez Energy Romania
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
GdF Suez Energy Romania
Depomures
Storage Facility
Interested by PCI ?
IGAs
Web Link
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
FEED0%
2012 Q4FID
Construction
Commissioning
Last completed Phase :
Storage facility
Working volume (mcm)
Depomures2013 Q1
+300,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Deliverability (mcm/d)
End of permitting phase
2013 Q2
2015/4
+2,30
+2,30
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 165
ROMANIA
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 166
ROMANIA
GRIP Central Eastern Europe 2014 – 2023 Annex B | 167
8RomaniaTransgaz S.A.
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
AGRI Pipeline - Romanian section (East-West Pipeline)
Transgaz
SNGN Transgaz S.A.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-132 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+850,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2015
+42,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 168
ROMANIA
Modelled Direction
Yes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
East-West Pipeline RO-HU (AGRI)
PROJECTED CAPACITY INCREASES
Hub Hungary168,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Romania
GRIP Central Eastern Europe 2014 – 2023 Annex B | 169
ROMANIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Integration of the transit and transmission system - reverse flow Isaccea
Transgaz
SNGN Transgaz S.A.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-139 FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Permitting0%
2010FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2013
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 170
ROMANIA
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Isaccea (RO) - Orlovka (UA)
PROJECTED CAPACITY INCREASES
Hub Romania147,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Transit Ukraine
GRIP Central Eastern Europe 2014 – 2023 Annex B | 171
ROMANIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Reverse flow at Negru Voda
Transgaz
SNGN Transgaz S.A.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-142 FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Permitting0%
2010FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2013
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 172
ROMANIA
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Negru Voda I
PROJECTED CAPACITY INCREASES
Trans-Balkan Pipeline (Romania)168,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Bulgaria (NGTS)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 173
ROMANIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Reverse flow on the interconnector Romania - Hungary
Transgaz
SNGN Transgaz S.A.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-126 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2013/4
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 174
ROMANIA
Modelled Direction
Yes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Csanadpalota
PROJECTED CAPACITY INCREASES
Hub Hungary12,60
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Romania
GRIP Central Eastern Europe 2014 – 2023 Annex B | 175
ROMANIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
RO-BG Interconnection
Transgaz
SNGN Transgaz S.A.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-029 FID
Promoter
Operator
TEN-E Project ?
None
Not relevant
0%
No
Supply contract0%
2010 Q4FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12011 Q4
+25,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2013 Q2
2013/2 +1,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 176
ROMANIA
Modelled Direction
Yes entryYes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Ruse (BG) / Giurgiu (RO)
PROJECTED CAPACITY INCREASES
Hub Bulgaria (NGTS)Hub Romania14,38
14,38
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Bulgaria (NGTS)Hub Romania
GRIP Central Eastern Europe 2014 – 2023 Annex B | 177
ROMANIA
GRIP Central Eastern Europe 2014 – 2023 Annex B | 178
9 Slovakiaeustream, a.s.
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Poland - Slovakia interconnection
eustream, a.s.
eustream, a.s.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-190 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
2015 Q2FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
22015 Q3
+106,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2016 Q3
2019
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 179
SLOVAKIA
Modelled Direction
Yes exitYes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector PL - SK
PROJECTED CAPACITY INCREASES
Hub SlovakiaHub Poland290,50
143,70
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub SlovakiaHub Poland
GRIP Central Eastern Europe 2014 – 2023 Annex B | 180
SLOVAKIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Yes
Slovakia - Hungary interconnection
eustream, a.s.
eustream, a.s.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-016 FID
Promoter
Operator
TEN-E Project ?
1
No
0%
No
Construction0%
2010 Q1FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12012 Q1
+18,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2012 Q2
2015 +0,80
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 181
SLOVAKIA
Modelled Direction
Yes exitYes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Balassagyarmat
PROJECTED CAPACITY INCREASES
Hub SlovakiaHub Hungary (SK-HU Interconnector)127,40
50,90
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub SlovakiaHub Hungary (SK-HU
GRIP Central Eastern Europe 2014 – 2023 Annex B | 182
SLOVAKIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
No
System Enhancements - Eustream
eustream, a.s.
eustream, a.s.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-017 FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
FID0%
2010 Q1FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
12009 Q4
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2010 Q1
2017
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 183
SLOVAKIA
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 184
SLOVAKIA
GRIP Central Eastern Europe 2014 – 2023 Annex B | 185
10 SloveniaPLINOVODI d.o.o.
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-096 FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
FEED0%
2011FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2014
+3,50
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 186
SLOVENIA
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 187
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Not defined yet
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-093 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2023*
+20,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 188
SLOVENIA
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 189
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
www.plinovodi.si/wp-content/uploads/2011/09/RN-2013-2022-Posvetovalni-dokument.pdf
Interested by PCI ?
IGAs
Web Link
TRA-N-092 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2016
+5,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Plinovodi (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 190
SLOVENIA
Modelled Direction
Removing bottlenecks of transmission system and increase of its capacities up to the existing capacities of neighbouring transmission system operators (first phase)Ensuring additional capacities for further market development and transits, including reverse flows (second phase),
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Adjustment to operating parameters of the transmission system of the Italian TSO. Reverse flow.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 191
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Not defined yet
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-094 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2016
+30,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 192
SLOVENIA
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 193
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Not defined yet
CS Vodice II (on M2/1 pipeline up to 3 units with total power up to 30 MW)
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-102 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2023*
+30,00
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 194
SLOVENIA
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 195
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Not defined yet
M1/3 SLO-A border crossing
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
www.plinovodi.si/wp-content/uploads/2011/09/RN-2013-2022-Posvetovalni-dokument.pdf
Interested by PCI ?
IGAs
Web Link
TRA-N-109 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+0,20
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2023* +0,70
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Plinovodi (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 196
SLOVENIA
Modelled Direction
No entry
Removing bottlenecks of transmission system and increase of its capacities up to the existing capacities of neighbouring transmission system operators (first phase)Ensuring additional capacities for further market development and transits, including reverse flows (second phase),
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
181,35
Adjustment to operating parameters of the transmission system of the Austrian TSO, with parallel connection to the existing pipeline.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 197
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-100 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not yet
0%
Not yet
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+79,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2017 +0,90
Considered TPA Regime
Considered Tariff Regime Negotiated (e.g. Exemption)
Negotiated (e.g. Exemption)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 198
SLOVENIA
Modelled Direction
Yes exitNo exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Hub ItaliaHub Italia289,00
754,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub SloveniaHub Slovenia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 199
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Not defined yet
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-104 FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Supply contract0%
2010FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+65,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2013
2014
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 200
SLOVENIA
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 201
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Not defined yet
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-F-097 FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Supply contract0%
2010FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+34,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2013
2014
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 202
SLOVENIA
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 203
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Not defined yet
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
www.plinovodi.si/wp-content/uploads/2011/09/RN-2013-2022-Posvetovalni-dokument.pdf
Interested by PCI ?
IGAs
Web Link
TRA-N-108 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
01.04.2010 2011
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+31,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2023*
Date of Request Year Funding GrantedTEN-E Requests
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Plinovodi (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 204
SLOVENIA
Modelled Direction
No exitNo exit
Removing bottlenecks of transmission system and increase of its capacities up to the existing capacities of neighbouring transmission system operators (first phase)Ensuring additional capacities for further market development and transits, including reverse flows (second phase),
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Hub ItaliaHub Italia25,40
62,99
Adjustment to operating parameters of the transmission system of the Italian TSO.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub SloveniaHub Slovenia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 205
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-099 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not yet
0%
Not yet
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+29,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2017 +0,75
Considered TPA Regime
Considered Tariff Regime Negotiated (e.g. Exemption)
Negotiated (e.g. Exemption)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 206
SLOVENIA
Modelled Direction
No exitNo exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Hub ItaliaHub Italia340,00
102,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub SloveniaHub Slovenia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 207
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-262 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not yet
0%
Not yet
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+24,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2017 +0,75
Considered TPA Regime
Considered Tariff Regime Negotiated (e.g. Exemption)
Negotiated (e.g. Exemption)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 208
SLOVENIA
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 209
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
M3/1c Kalce - Vodice
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-261 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not yet
0%
Not yet
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+47,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2017 +0,75
Considered TPA Regime
Considered Tariff Regime Negotiated (e.g. Exemption)
Negotiated (e.g. Exemption)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 210
SLOVENIA
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 211
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Not defined yet
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-107 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
2
+73,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2015
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 212
SLOVENIA
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
San Dorligo della Valle (IT) /Osp (SI)
PROJECTED CAPACITY INCREASES
Hub Slovenia6,10
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Italia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 213
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-101 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+51,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2018 +0,80
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 214
SLOVENIA
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Hub Slovenia414,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Croatia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 215
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
up to 80 MW)
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-098 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not yet
0%
Not yet
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+72,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2016
+80,00
+0,90
Considered TPA Regime
Considered Tariff Regime Negotiated (e.g. Exemption)
Negotiated (e.g. Exemption)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 216
SLOVENIA
Modelled Direction
No entryNo entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector SI-HU
PROJECTED CAPACITY INCREASES
Hub SloveniaHub Slovenia819,00
288,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub HungaryHub Hungary
GRIP Central Eastern Europe 2014 – 2023 Annex B | 217
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-263 Non-FID
Promoter
Operator
TEN-E Project ?
None
Not yet
0%
Not yet
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+115,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2018
+60,00
+0,90
Considered TPA Regime
Considered Tariff Regime Negotiated (e.g. Exemption)
Negotiated (e.g. Exemption)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 218
SLOVENIA
Modelled Direction
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
GRIP Central Eastern Europe 2014 – 2023 Annex B | 219
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Not defined yet
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
www.plinovodi.si/wp-content/uploads/2011/09/RN-2013-2022-Posvetovalni-dokument.pdf
Interested by PCI ?
IGAs
Web Link
TRA-F-110 FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
2012FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2014
2014
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
Plinovodi (100%)
GRIP Central Eastern Europe 2014 – 2023 Annex B | 220
SLOVENIA
Modelled Direction
Yes exit
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Hub Italia25,00
Adjustment to operating parameters of the transmission system to the Italian TSO. Reverse flow.
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Slovenia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 221
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Project of Common Interest
Yes
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-112 Non-FID
Promoter
Operator
TEN-E Project ?
1
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+70,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2018 +0,70
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 222
SLOVENIA
Modelled Direction
Yes entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
Interconnector SI-HU
PROJECTED CAPACITY INCREASES
Hub Slovenia38,00
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub Hungary
GRIP Central Eastern Europe 2014 – 2023 Annex B | 223
SLOVENIA
SPONSORS GENERAL INFORMATION FINANCING
THIRD-PARTY ACCESS REGIME SCHEDULE TECHNICAL INFORMATION
Not part of TEN-E
Not defined yet
Plinovodi d.o.o.
Plinovodi d.o.o.
Pipeline including CS
Interested by PCI ?
IGAs
Web Link
TRA-N-114 Non-FID
Promoter
Operator
TEN-E Project ?
None
No
0%
No
Planned0%
FID
Construction
Commissioning
Last completed Phase :
# of Pipelines, nodes, CS
Total Pipeline Length (km)
1
+10,00
Applied for Exemption ?
Exemption granted ?
% Exemption in entry direction
% Exemption in exit direction
Total CS Power (MW)
Expected Load Factor
End of permitting phase
2021
Considered TPA Regime
Considered Tariff Regime Regulated
Regulated
GRIP Central Eastern Europe 2014 – 2023 Annex B | 224
SLOVENIA
Modelled Direction
Yes entryNo entry
DESCRIPTION OF THE PROJECT
EXPECTED BENEFITS
PROJECTED CAPACITY INCREASES
Hub SloveniaHub Slovenia2,31
5,08
Public financing Private financing Multilateral financing
COMMENTS ABOUT THE PROJECT FINANCING
Interconnection Capacity (GWh/d) From Zone To Zone
Hub CroatiaHub Croatia
GRIP Central Eastern Europe 2014 – 2023 Annex B | 225
SLOVENIA
ENTSOG AISBL
Avenue de Cortenbergh 100
1000 Brussels, Belgium
Tel. +32 2 894 51 00
[email protected] www.entsog.eu