energy trade with india

Upload: wasik

Post on 04-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Energy Trade With India

    1/22

    1

    Prospects of Energy Trade With India

  • 7/29/2019 Energy Trade With India

    2/22

    PROSPECTS IN PRESENT SITUATION

    The surplus power available in Pakistan started

    decreasing and nearly balanced in FY 2004.

    From 2005, the deficit scenario started building up,which became severein FY 2008-09.

    The situation is still continuing because despite best

    efforts, a wide gap between supply and demand isexisting. The year-wise power balance scenario is

    depicted in next slide.

    2

  • 7/29/2019 Energy Trade With India

    3/22

    3

    DEMAND & SUPPLY POSITION (2001 2010)PEPCO (Including Export to KESC)

    (All Figures in MW)

    Year Computed PeakDemand CorrespondingSupply Surplus/ Shortfall

    2000-01 10459 10894 435

    2001-02 11044 10958 -86

    2002-03 11598 11834 236

    2003-04 12595 12792 197

    2004-05 13847 12600 -1247

    2005-06 15838 13292 -2546

    2006-07 17398 12442 -4956

    2007-08 17852 13637 -42152008-09 18583 13413 -5170

    2009-10 18521 13163 -5358

    2010-11 18930 14468 -4462

    2011-12 20058 15062 -4996

  • 7/29/2019 Energy Trade With India

    4/22

    Summary of Power Balances (MW)

    4

    PEPCO System

    Year Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

    2012-13 -3458 -3331 -4214 -3683 -891 -1767 -2771 -1791 -3120 -4015 -3777 -4304

    2013-14 -4059 -3973 -4854 -3970 -1078 -903 -1746 -810 -2347 -3289 -3081 -3607

    2014-15 -3202 -3219 -4134 -3400 -375 -1058 -1930 -903 -2439 -3394 -3249 -3718

    2015-16 -3209 -3392 -4444 -3592 -440 -651 -1458 -544 -2185 -3183 -3078 -3701

    2016-17 -3734 -3936 -3397 -2093 1207 897 228 1073 -709 -1394 -698 -1517

    2017-18 -1478 -1729 -2944 -1912 847 1299 -92 858 -892 -1535 -613 -1367

    2018-19 -1609 -2261 -3818 -2844 13 2377 1002 1901 95 -301 1274 746

    2019-20 1337 386 -1703 -949 1838 2554 1123 2185 377 13 2187 1410

    Based on Generation Data as of 30-06-2012

  • 7/29/2019 Energy Trade With India

    5/22

    Summary of Power Balances (MW)

    5

    YearSurplus/Deficit

    MW

    Surplus/Deficit

    MW

    2012-13 -891(min deficit) -4304(max deficit)

    2013-14 -810(min deficit) -4854(max deficit)2014-15 -375(min deficit) -4134(max deficit)

    2015-16 -440(min deficit) -4444(max deficit)

    2016-17 1207 (max surplus) -3936(max deficit)

    2017-18 1299 (max surplus) -2944(max deficit)

    2018-19 2377 (max surplus) -3818(max deficit)

    2019-20 2554 (max surplus) -1703(max deficit)

  • 7/29/2019 Energy Trade With India

    6/22

    6

    Period (2010-11) Energy (MU) Peak (MW)

    Requirement 861,591 122,287

    Availability 788,355 110,256

    Shortage 73,236 12,031

    (%) 8.5% 9.8%

    Actual Power Supply Position 2010-11

    All India

  • 7/29/2019 Energy Trade With India

    7/22

    7

    Period (2011-12) Energy (MU) Peak (MW)

    Requirement 933,741 136,193

    Availability 837,374 118,676

    Shortage 96,367 17,517

    (%) 10.3% 12.9%

    Expected Power Supply Position 2011-12

    All India

  • 7/29/2019 Energy Trade With India

    8/22

    FUTURE PROSPECTS OF ELECTRICITYTRADE

    Pakistan needs power in future also.

    The economic viability of import of power from

    India depends upon its overall cost of energy.

    India is also facing power deficit. The sustainability

    of power supply needs to be ascertained.

    8

  • 7/29/2019 Energy Trade With India

    9/22

    WAY FORWARD

    Prefeasibility study is required to;

    Assess the Surplus and Deficit power of the two countries and

    determine of quantum of energy that can be supplied.

    Identify possible locations for establishing interconnectionsbetween Pakistan and India.

    Examine:

    Technically possible solutions for the grid connectivity of both

    countries (like, voltage level, AC or DC etc.)

    The term of contract for import of power.

    The security and stability of power supply issues.

    An insight into possible tariff structure and its cost.

    9

  • 7/29/2019 Energy Trade With India

    10/22

    Assessment of potential for electricity trade keeping in view

    of current and future demand.

    Examine the power market structure, codes of electricity

    supply and existing legal framework.

    Developing methodology for implementation of transmission

    infrastructure.

    Explore technically and economically feasible

    interconnection options.

    Preliminary cost estimation and interconnection diagrams

    for feasible options.

    Contd..

    Scope of Work

    Prefeasibility Study By World Bank

    10

  • 7/29/2019 Energy Trade With India

    11/22

    Assess the economic and commercial viability of the

    interconnection options identified.

    Identification of other key constraints such as ROW that may limit

    the practical implementation.

    Recommend 2-3 interconnection options to GoP.

    Identification of strategic issues and important risks of the

    recommended interconnections and bilateral trade through those.

    Assess and analyze the potential of private sector participation in

    energy trade.

    Recommend further studies and actions to be taken by GoP to

    further develop the recommended interconnection option.

    Scope of Work

    Prefeasibility Study By World Bank

    11

  • 7/29/2019 Energy Trade With India

    12/22

    TECHNICAL DETAILS

    12

  • 7/29/2019 Energy Trade With India

    13/22

    The NTDC Power Transmission System

    13

  • 7/29/2019 Energy Trade With India

    14/22

    INTERCONNECTION ISSUES

    The NTDC Transmission System is longitudinal whichis Running parallel to Indian border from north to

    south.

    Interconnections are possible at various points.

    The interconnection voltage level depends upon

    the volume of energy to be transmitted.

    14

  • 7/29/2019 Energy Trade With India

    15/22

    India , Pakistan AC TransmissionVoltages

    The transmission voltages in Pakistan are- 132 kV

    - 220 kV

    - 500 kV The Indian system voltages are

    - 132 kV

    - 220 kV- 400 kV

    - 765 kV

    15

  • 7/29/2019 Energy Trade With India

    16/22

    Probable Interconnection Points

    Batapur Lahore at 132 kV

    Ghazi Road Lahore at 132 kV

    Ghazi Road Lahore at 220 kV Sarfraz Nagar at 132 kV

    Sarfraz Nagar at 220 kV

    Kasur at 132 kV

    16

  • 7/29/2019 Energy Trade With India

    17/22

    Possible Interconnection Option For

    200-500 MW

    17

  • 7/29/2019 Energy Trade With India

    18/22

    Interconnection Problemswith AC System

    Both interconnected systems need to beoperated at same frequency. If the system with

    shortage of power is operating at the lower

    frequency, the other system may refuse to

    synchronize with that system.

    Phase-shifting transformers are required to

    control the quantum of power flowing from one

    system to the other. Short circuit powers of the two systems get

    added which may be beyond the capacity of

    some of the switchyard equipment on both or

    either side. 18

  • 7/29/2019 Energy Trade With India

    19/22

    Interconnection Problemswith AC System

    The disturbance/fault on one system may disturb

    the other system.

    The above mentioned problems can be

    overcome by isolating a small portion of thereceiving system and connecting it up-to the

    supply system. In this case the power flow will be

    fluctuating according to the demand of the

    isolated portion of receiving system.

    19

  • 7/29/2019 Energy Trade With India

    20/22

    Approximate Costs

    1. Back to Back ConverterStation Cost = 250 MUS$

    2. 500 kV HVAC S/C = 0.30 MUS$/km

    (Drake Conductor)3. 500 kV HVAC D/C = 0.6 MUS$/km

    (Drake Conductor)

    4. 220 kV HVAC D/C = 0.22 MUS$/km(Twin Bundle Rail Conductor)

    5. 132 kV AC D/C = 0.10 MUS$/km

    (Rail Conductor) 20

  • 7/29/2019 Energy Trade With India

    21/22

    Due to problems associated with HVAC

    system, India has required interconnection

    through HVDC line.

    The voltage level for power upto 500 MW can

    be 220 kV. For higher power levels it should be

    400 kV or higher.

    21

    Recommended Interconnection Option

  • 7/29/2019 Energy Trade With India

    22/22

    22