energy recovery in water supply - seea.government.bg
TRANSCRIPT
Energy recovery in water supplyBGENERGY-1.001-0001. Webinar on hydro power in water supply systems, 08.06.2021
About Norconsult
Jonas Jessen Ruud to present Norwegian experiences with hydro
power units in water supply plants
Hans Olav Nyland to present findings from analysis based on the
studies performed by SEDA, along with criteria and assumptions for
a successful project (lessons learned)
Contents
07.06.2021 2
Norconsult is Norway’s largest,
and one of the Nordic region’s
leading, interdisciplinary
consultancy firms within social
planning, engineering design,
and architecture. We contribute
to a more sustainable society
and generate benefits for the
community through innovative
and targeted consultancy
services.
About Norconsult
2020-12-01 3Corporate presentation Norconsult
Fakta
2021-01-01 4Corporate presentation Norconsult
* Pr. 31.12.2019
Ill.: LP
O a
rkite
kte
r
4 600 Employees
119 Offices
11 Business areas
20 000 Projects
6,3 Billion NOK revenues*
49 Countries in whichwe have projects
Key figures
* Per. 31.12.2019
119 offices on four continents
52020-12-01 Corporate presentation Norconsult
Mozambique
Philippines
Thailand
Malaysia
Zambia
Botswana
New Zealand
Sweden
Denmark
Norway
South Africa
PolandIceland
Countries with permanent offices
Countries with projects in 2019
Countries with projects since 1956Pr. 31.12.2019
Finland
Business areas
62020-12-01
Architecture Buildings Energy
IT
Industry
Oil and Gas Planning
Risk ManagementTransport Water
Environment
Corporate presentation Norconsult
Project: BGENERGY-1.001- 0001 ”Feasibility study of the use of hydroenergypotential of existing water supply systems and increasingthe potential of existing small hydroelectric power plants in water supply systems”
07.06.2021 7
• Relevant sites for combining water supply and hydropower in Bulgaria has been studied
and data about potential sites has been collected by SEDA
• Based on documents received from NVE/SEDA, Norconsult has performed an evaluation
of 60 potential sites relevant for the introduction of hydro power in water supply facilities,
and from these extracted the sites that appear to have the highest potential. For each of
these we have performed a brief cost benefit analysis indicating potential for annual power
generation and capacity, as well as cost
Document basis
07.06.2021 8
As basis for this project, the following documents has been received from Seda:
SEDA: Report of identified locations and energy potential assessment (Translated under
Contract РД 05-02-26/03.07.2020. The Bulgarian text of the report is approved by Ivaylo
Aleksiev, Executive Director of SEDA – beneficiary of the BGENERGY-1.001-0001 Project).
SEDA: Summary Database Sites_EN. This is a database over 60 sites with owner information
and plant data
SEDA: Summary Report_Sites_EN. This is a summary report of the results of the activity,
including an assessment of the possibilities for extension of the water supply scheme and the
possibilities to integrate hydroenergy generation to replace pressure reduction valves.
(Translated under Contract РД 05-02-26/03.07.2020. The Bulgarian text of the report is
approved by Ivaylo Aleksiev, Executive Director of SEDA – beneficiary of the BGENERGY-
1.001-0001 Project)
Intake and waterway
Already in place
Not causing excessive
headloss
Assumptions
07.06.2021 9
Turbine selection diagrams
07.06.2021 10
Ref: Andritz
Ref: JHD
Submergence requirements
07.06.2021 11
• NPSH
• Space constraints
Turbine selection, summary
07.06.2021 12
Turbine type Key features Comment
Pelton turbine Governable from 5%-100% of max flow. High efficiency over a
broad flow range. Typically to be used at heads above 80-100 m
or specific speeds nq<20-30. Needs a free surface outlet
Preferred type if possible, Expensive and space
demanding
Francis turbine:
A. Regular Francis turbine
Governable from 30%-100% of max flow. High efficiency above
60-70% load. Typically to be used at heads below 80-100 m or
specific speeds nq>20-30. Needs a submerged outlet, as
required by the turbine supplier
Expensive and space demanding if equipped with
guide vane apparatus
Francis turbine:
A. PAT (pump as turbine,
reversed pump)
Has no guide vane apparatus and thus only one operational
point near maximum flow (one flow, operation on and off).
Needs a relief shaft for water regulation and submerged outlet,
as required by the turbine supplier
Inexpensive and takes little space. Possibilities for
matching the system to actual demand are very
low. Lower efficiency than regular Francis.
Kaplan turbine Suited for the combination of low head and high flows.
Governable from 20%-100% of max flow.
Expensive and space demanding. The combination
of low head and high flow is not typical for water
supply facilities. Water contamination risk due to oil
filled parts in the waterway
Other “Smart» turbine solutions
and prototypes
Various turbine types are available Often low efficiency. No good experiences known
to Norconsult over time. Stick to proven technology
Turbine selection SEDA - Bulgaria
Site number 5 8 21 23 24 27 36 47 48 57
Name Burgas Burgas Dobrich Kardzhali Kardzhali Kuystendil Pernik Staga
Zagora
Staga Zagora Haskovo
Capacity m³/s 0.25 0.95 0.1 0.4 0.4 0.14 2 0.55 0.4 0.107
Head m 84 33 20 23 61 29 43 71 54 45
Density kg/m³ 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000
Gravitational acceleration m/s² 9.81 9.81 9.81 9.81 9.81 9.81 9.81 9.81 9.81 9.81
Efficiency 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
Electrical Power kW 164.8 246 16 72 191 32 674.9 306 170 38
Estimated Operating hours Hours 5000 5000 5000 5000 5000 5000 5000 5000 5000 5000
Yearly Production kWh 824 040 1 230 174 78 480 361 008 957 456 159 314 3 374 640 1 532 322 847 584 188 941
Eletricity price €/kWh 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Depreciation 12 12 12 12 12 12 12 12 12 12
Total Production Value € 988 848 1 476 209 94 176 433 210 1 148 947 191 177 4 049 568 1 838 786 1 017 101 226 729
Turbine Type P F F F F F F F F F
Specific Price Electromechanical
Equipment
€/kW 800 880 1 600 1 200 940 1 400 700 830 900 1 150
Total Price Electromechanical € 131 846 216 511 25 114 86 642 180 002 44 608 472 450 254 365 152 565 43 456
Estimated Building Costs € 46 146 75 779 8 790 30 325 63 001 15 613 165 357 89 028 53 398 15 210
Estimated Consulting costs € 62 297 102 301 11 866 40 938 85 051 21 077 223 232 120 188 72 087 20 533
Estimated Power Plant Cost € 240 290 394 591 45 770 157 905 328 053 81 298 861 039 463 581 278 050 79 199
Comment
Has already
a turbine
Results
07.06.2021 13
The headloss in the penstocks analysed, appear to
be moderate and well designed, seen from a
hydropower perspective
General findings
07.06.2021 14
NOTE: The available information about each water supply plant site is limited.
Therefore, in the following description of suggested solutions introduced to
specific sites we will use SEDA’s own site numbers for reference to each site,
and present principal solutions only.
The following sites has been selected among the most attractive projects:
Site No 5 at Burgas municipality (Pelton turbine suggested)
Site No 8 at Burgas municipality (Francis turbine suggested)
Site No 47 at Staga Zagora municipality (Francis turbine suggested)
Detailed recommendations to each site
07.06.2021 15
Pelton unit configuration in water supply plants
07.06.2021 16
Load control of a Pelton unit
07.06.2021 17
©
Vertical small hydro Pelton unit with electric
actuators for injector control and no deflectors
Horizontal large hydro Pelton unit with straight flow injector with double
acting injector servomotor operated with oil pressure, with deflectors
Francis unit configuration in water supply plants
07.06.2021 18
PAT configuration in water supply plants
07.06.2021 19
PAT
Regular Francis turbine
PAT
Difference in load control of a regular Francis Vs. PAT
07.06.2021 20
Ref. EnergiTeknikk,
Norway. Horizontal
Francis turbine
Ref. KSB, Germany
𝑃𝑔 = 𝐻 ∗ 𝑄 ∗ 𝑔 ∗ 𝜌𝑤𝑎𝑡𝑒𝑟 ∗ 𝜂𝑔𝑒𝑛𝑒𝑟𝑎𝑡𝑜𝑟 ∗ 𝜂𝑡𝑢𝑟𝑏𝑖𝑛𝑒
Time t
Space
Limitations to the concept
07.06.2021 21
Dam safety
High voltage requirements
Municipal permits
Non-profit
Regulations and permits
07.06.2021 22
Positive focus on sustainable energy solutions in the organization, and willingness to pay more up front to achieve this
Acceptance for the project being engineering intensive, due to criticality, need for robustness and redundance, and good planning of operations to minimize outage and water supply cutoff
O&M staff are often heavily loaded already, new assets should thusnot tie up more resources. → Hassle free solutions and well proventurbine and valve technology! Bad experiences with turbines oftencause negative attitudes towards hydro power in water supply
When you go the extra mile with the engineering, safeguarding a robust function plan and turbine technology, the plant can generatestable income and green, short traveled electricity for generationsto come!
Hydro power in water supply also represents a positive SHA measure, as turbines generate less noise and vibrations thanthrottling/energy dissipating valves
Inouse electricity supply requires skilled, inhouse high voltagepower professionals. If not in place; sell the power directly in thepower market
Excess heat to supply the heating in the treatment plant offices
Power line removed and buried in trench. →Recreational benefit
Lessons learned. Premises for successful projects
07.06.2021 23
Goal: Robust plants with automatic operation and hassle free operation
Functional plans
Bypass line is the main line
Redundancy
A proper control system
A broad flow range enables even power/water production and high operational flexibility
If PAT is selected, even higher requirements to the control system
Robust solutions
Pelton unit at site 5, regular Francis units at sites 8 and 47
Conclusions
07.06.2021 24
Our knowledge contributes to a more valuable society