energy performance contracting guideline for smes€¦ · ecm energy conservation measure ee energy...
TRANSCRIPT
ENERGY PERFORMANCE CONTRACTING GUIDELINE FOR SMES
Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
Prepared for:
SME Energy Efficiency Project
Final
February 14, 2017
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 ii
ABBREVIATIONS
ECM Energy conservation measure
EE Energy efficiency
EMO Energy management outsourcing
EOI Expression of interest
EPC Energy performance contracting
ESCO Energy service company
IGA Investment-grade audit
IRR Internal rate of return
LOI Letter of intent
M&V Measurement and verification
NPV Net present value
O&M Operation and maintenance
RE Renewable energy
RFP Request for proposal
SME Small and medium enterprises
TPF Third-party financing
WTA Walkthrough audit
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 iii
TABLE OF CONTENTS
INTRODUCTION ................................................................................................................................... 1
1 EPC CONCEPT ............................................................................................................................ 2
1.1 Energy Service Company (ESCO) ...................................................................................... 2
1.1.1 Types of ESCOs ............................................................................................................... 4
1.2 Advantages of working with an ESCO for SMEs ............................................................... 4
1.2.1 Technical Risk Management ............................................................................................ 4
1.2.2 Project Financing and Benefits ......................................................................................... 4
1.2.3 Guaranteed Savings ......................................................................................................... 4
1.2.4 Expertise ........................................................................................................................... 5
1.2.5 Environment ..................................................................................................................... 5
2 EPC PROCUREMENT MECHANISMS AND IMPLEMENTATION STEPS ................................. 6
2.1 Initial Project Development Phase ...................................................................................... 7
2.1.1 Tender Process ................................................................................................................ 8
2.1.2 Spontaneous Process ...................................................................................................... 9
2.2 Project Design and Implementation Phase ...................................................................... 12
2.2.1 IGA Preparation .............................................................................................................. 12
2.2.2 EPC Contract Negotiation and Signature ....................................................................... 13
2.2.3 Project Design Finalization and Implementation ............................................................. 13
2.2.4 Project Commissioning ................................................................................................... 14
2.2.5 Savings Management and Reporting ............................................................................. 14
3 FINANCING MECHANISMS: EPC, CONTRACTUAL AND NEGOTIATION ELEMENTS ........ 15
3.1 Guaranteed Savings ........................................................................................................... 15
3.2 Verified Savings ................................................................................................................. 16
3.3 Lease Contract Model ........................................................................................................ 17
3.4 Comparative Analysis of Models ...................................................................................... 18
4 MEASUREMENT AND VERIFICATION OF SAVINGS ............................................................. 19
5 OPERATION AND MAINTENANCE AND CAPACITY BUILDING............................................ 20
APPENDIX I MAIN SERVICES OF AN ESCO .................................................................................... 21
APPENDIX II RFP GUIDELINES ........................................................................................................ 23
APPENDIX III EXAMPLES OF RFP EVALUATION CRITERIA ......................................................... 24
APPENDIX IV M&V PLAN GUIDELINES ........................................................................................... 25
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 iv
LIST OF FIGURES
Figure 1: Traditional Approach ............................................................................................................... 3 Figure 2: ESCO Approach ..................................................................................................................... 3 Figure 3: EPC Development Process .................................................................................................... 7 Figure 4: Guaranteed-Savings EPC .................................................................................................... 15 Figure 5: Verified-Savings EPC ........................................................................................................... 16
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 v
The present guidebook is intended to provide guidance and advice to SMEs on the use of the energy
performance contracting (EPC). It provides them with a basic introduction to the main process to be
followed in order to develop a successful contractual relationship with Energy Service Companies
(ESCOs) to develop and implement energy efficiency (EE) projects in the specific context of Turkey.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 1
INTRODUCTION
EPC is a contractual scheme that aims to eliminate the market barriers that prevent the implementation
of EE projects at end users facilities. The major difference between an EPC is not based on the
successful implementation of a project based on requested equipment installations but rather a scheme
then focuses on projects performance where the contractor (the ESCO) payment is linked in some ways
to such performance. The final aim of the partnership established between an SME and an ESCO under
an EPC is to enable the implementation of a successful EE project where the needed investment has
to be covered by the generated financial savings over a pre-defined time frame.
Even if quite different as per its nature, EPC shares many similarities with conventional engineering
work design and construction practices. However, EPC’s distinctive differences from conventional
practices can provide SMEs with opportunities to install EE equipment that could not be otherwise
implemented when using a conventional process.
Section 1 of this report provides a basic introduction to the EPC model, ESCO services and the benefits
of doing business with an ESCO.
Section 2 presents the implementation steps for an EPC project development and implementation by
detailing the main stages to be completed before and after the signature of an EPC contract between
the parties.
Section 3 presents the different type of financing mechanisms related to the use of different contractual
approaches that can be used under an EPC contractual scheme. It also presents the different specific
elements of each type of contracts to be used including contractual and negotiation process.
Section 4 outlines the main characteristics and components of an effective measurement and
verification (M&V) plan, which should be prepared in the EPC development phase
Section 5 introduces the additional services that can be offered under an EPC approach and the benefits
that an end users can get as an added value through them.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 2
1 EPC CONCEPT
An EPC is defined as “a contractual arrangement between the beneficiary and the provider of an EE
improvement measure, according to which the payment for the investment made by the provider is in
relation to a contractually agreed level of EE improvement or other agreed-upon energy performance
criteria, such as financial savings”.1 Therefore, an EPC has the following specific characteristics:
› An EPC is a contract between two parties — the beneficiary and the service provider.
- The beneficiary is the institution, the industry or the building owner that seeks to implement
energy-saving measures or an EE project.
- The service provider is the ESCO that is contracted to implement the energy savings project.
› An EPC defines the terms of the contract, i.e., the responsibilities of each party.
› In most cases, compensation for the services provided by the ESCO is based on the level of
energy savings or the reduction in energy expenditures after project completion.
› The EPC is time bound and has a typical duration ranging from five years for small projects to
over 20 years for very large projects.
Lack of access to financing should not be seen by the Turkish SMEs as a barrier to EE improvement
since EPC is getting better known by local financial institutions who can help provide an alternative
financing adapted to the scheme in order to help secure funding for EE measures.
1.1 Energy Service Company (ESCO)
An ESCO is a company specialized in developing and implementing measures aimed at reducing
energy consumption in facilities by identifying and implementing EE measures and measuring and
verifying the results achieved. In order to perform these activities, the ESCO signs a contract called an
EPC with their clients.
ESCOs in Turkey can offer a wide range of services, including one or several of the following: energy
auditing, design engineering, financing, equipment supply, installation, operation, maintenance and
upgrades, energy management, and measurement and verification of energy savings.
From the Turkish SME perspective, the most attractive aspect of the ESCO model is perhaps that it
deals with a single entity in handling all the project components throughout all stages of the project
cycle, rather than with several institutions (design office, entrepreneurs, energy suppliers, equipment
manufacturers, financing institutions, government bodies, etc.). This “one-stop” feature greatly reduces
the transaction costs for the SME, and these costs are often the biggest obstacle to EE project
implementation.
1 http://eur-lex.europa.eu/legal-content/EN/TXT/PDF/?uri=CELEX:52011PC0370&from=EN
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 3
Figure 1: Traditional Approach
Figure 2: ESCO Approach
Information on the detailed services that could be offered by an ESCO is presented in Appendix I.
Professional Consulting Engineer
Contractors
Equipment
Manufacturers
Governments
Financial
Institutions
Energy
Suppliers
SMEs
Professional Consulting
Engineer
Equipment Manufacturers .
Governments
Financial
Institutions .
Energy
Suppliers .
SMEs
Guarantee
• Analysis • Concept • Installation • Financing • Monitoring
• Training
ESCO
Contractors
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 4
1.1.1 Types of ESCOs
ESCOs in Turkey are generally classified into the following three categories based on their composition
and ownership:
› Independent ESCO: ESCOs that are not owned by an electric or gas utility, an equipment/control
manufacturer or an energy supply company. Many independent ESCOs focus on a few geographic
markets and/or target specific SME market segments.
› Equipment manufacturer: This type of ESCO is owned by an equipment or control manufacturer.
Some of these ESCOs have an extensive network of branch offices that provides nationwide and
international coverage, with sales forces and specialized national staff providing packages of EE
to SME market segments.
› Other energy/engineering companies: This type of ESCO is owned by international oil or gas
companies, non-regulated energy suppliers or large engineering firms.
1.2 Advantages of working with an ESCO for SMEs
The following subsections summarize the main benefits of EPC projects as implemented by ESCOs for
SMEs.
1.2.1 Technical Risk Management
ESCOs are responsible for bearing the technical risks associated with the project, which is not possible
in a business-as-usual project. This means that the ESCO ensures that the project will perform as it is
designed in order to recover the costs as revenues are tied to the performance of the equipment installed
or the energy management plan implemented. Furthermore, the ESCO ensures that the equipment
installed operates properly and is well maintained during the EPC duration, and that there will be no
budget overruns despite technical difficulties.
1.2.2 Project Financing and Benefits
EPC projects can be financed through the energy savings, i.e., the cash flow generated by the EPC
project implementation is sufficient to repay the ESCO service costs, thus avoiding capital expenditures
for the company. Furthermore, depending on the terms of the EPC, a part of the cash flow generated is
returned to the SME as benefits from the EPC.
1.2.3 Guaranteed Savings
ESCOs are responsible for ensuring that the claimed savings are obtained over the contractual period
of the agreement. If not, they have to pay for the shortfalls, as set out in the contract. The guaranteed
savings help predict stable cash flows and negotiate financing arrangements.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 5
1.2.4 Expertise
ESCOs bring expertise from previous work experience to new SME projects. Because ESCOs have
strong skills and proven track records, it is advisable to deal with an ESCO as a one-stop contact on a
project providing turnkey solutions than to have multiple intermediaries. Also, because the benefits
expected by the ESCO are tied to the level of energy savings, it works continuously to improve the level
of energy savings, thus putting to good use its expertise in equipment operation and maintenance.
1.2.5 Environment
EE is one of the key solutions to mitigate climate change. The ESCO business model and/or EPC are
policy instruments widely used to enable the implementation of EE projects that do generate carbon
emission reduction that are at the source of climate change.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 6
2 EPC PROCUREMENT MECHANISMS AND IMPLEMENTATION STEPS
Turkish SMEs can implement an EPC by receiving a spontaneous offer from an ESCO or by issuing a
call for tenders to choose from different proposals:
› In the spontaneous process, the ESCO selects the SME based on various criteria, including
financial, technical, marketing and promotion criteria, as well as the level of risk. The ESCO
initiates project development and invests its time and effort in developing the EE project and in
convincing the SME to go forward with the implementation.
› In the tender process, the SME takes the initiative for EE project development. In this process
the SME selects the best ESCO proposal based on its own evaluation criteria and pre-defined
needs.
The difference between the two approaches lies in the project’s initial development phase, after which
both processes follow the same path during the project design and implementation phase, starting with
the development of the investment-grade audit, as shown in Figure 3 below.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 7
Figure 3: EPC Development Process
2.1 Initial Project Development Phase
The EPC project development can be initiated by the ESCO or the SME. In the spontaneous process
the SME is approached by an ESCO where the latter completes a series of steps to make the best
proposal to the SME. In the tender process, the SME will take the initiative to request proposals from
the ESCOs. This section presents the initial development phase of the two approaches.
RFP to (shortlisted) ESCOs
Proposals Preparation by ESCOs
RFP Evaluation and ESCO Selection
IGA Preparation
Contract Negotiation and Signature
Project Design Finalization and Implementation
Project Commissioning
Savings Management and Reporting
Letter of Intent (optional)
Walkthrough Audit (WTA)
Spontaneous Process Tender Process
Init
ial
De
ve
lop
me
nt
Ph
as
e
Pro
jec
t D
es
ign
an
d Im
ple
me
nta
tio
n P
has
e
P
IGA Agreement Preparation
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 8
2.1.1 Tender Process
If the SME wishes to develop an EPC with an ESCO, it is a good indication that it is most probably aware
of the company’s current energy situation, EE level and energy consumption patterns, and that it wishes
to improve its energy performance and efficiency.
Having gathered energy consumption indicators and assessed energy savings opportunities will
certainly help the SME establish and evaluate the EE project milestones, such as the ECM to be
considered, the energy savings goals, the project’s financial and technical boundaries, etc.
Request for Proposal (RFP)
To initiate the process, the SME should proceed with issuing a Request for Proposal (RFP), inviting
ESCOs and energy service providers to prepare proposals for an EPC. For this purpose, the SME
should prepare the RFP, including supporting tendering documents, such as a statement of work and
an energy performance contract. The RFP also includes a description of the expected scope of work
and mandatory rated criteria. Mandatory rated criteria are a minimum set of specific and objective criteria
that all ESCOs must meet. These criteria will help bidders submit complete and competitive proposals
and help the SME assess proposals adequately. Rated criteria can include:
› Financial merit;
› Technical merit;
› Implementation approach;
› Operation and maintenance approach;
› Project management approach;
› Training and awareness approach;
› Performance measurement and verification approach.
Appendix II presents some guidelines for the contents of the RFP.
Proposal Preparation by ESCOs
ESCOs preparing responses to the RFP will require access to the facilities as well as time with staff.
The quality of the proposal is directly related to how well ESCOs understand the facility, the opportunities
available and any restrictions on how they can implement them. It is normal, though not essential for all
ESCOs, to attend site visits together. This ensures no ESCO has an advantage over another. It also
minimizes the time the SME staff has to devote to the process.
It should be noted that the SME can select a shortlisted ESCO or invite only those selected in the RFP.
The main purpose of this is to identify and qualify the ESCOs able and willing to offer proposals for the
project.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 9
RFP Evaluation and ESCO Selection
This stage involves selecting the ESCO for the project design and implementation phase. The evaluation
criteria should place considerable weight on the originality, creativity and technical soundness of the
approach.
A system should be set up to evaluate each proposal based on the requirements of the SME. The
selected ESCO is given the opportunity to negotiate an EPC with the SME. As the proposals
considerably vary in approach, the use of a conventional weighted scoring method at this stage can
skew the result significantly. It is thus recommended, if possible, that the SME create a best-case
scenario, and choosing the closest fit to this scenario will produce more reliable results. Financing, if
requested or desired, should be assessed as part of the proposal with the weighing of the option defined
in the evaluation criteria.
Cost (or lowest cost) is not the main driver for the selection of the ESCOs, since detailed project costing
cannot be carried out until the IGA has been conducted. Consequently, originality, understanding and
approach are usually given significantly more weight. Appendix II presents an example of evaluation
criteria of an RFP.
It is recommended that the evaluation be completed during a face-to-face meeting with each of the
participating ESCOs since some clarifications are normally necessary.
2.1.2 Spontaneous Process
This process is followed by ESCOs when selecting their clients in order to “sell” their services by
investigating the opportunities for EPC in the client facilities. Each of the ESCOs has their own business
plan and consequently a specific list of sectors or clients to contact in order to offer their services and
develop a project. Once the ESCO has approached the SME and agreed to collaborate, some ESCOs
prepare a letter of intent (LOI) for the SME to sign. This LOI is optional, but recommended to establish
a common understanding between the ESCO and the SME.
Letter of Intent (optional)
This letter is designed to confirm to the ESCO that the SME is willing to enter into an EPC agreement,
to address the SME’s energy concerns and to establish a schedule for project development.
This should be regarded as the beginning of the trust-building process. Generally no analysis of the
SME’s facility will be undertaken until the SME and the ESCO sign such letter.
Objective of the LOI
To reach a common understanding between the ESCO and the SME regarding the EPC’s objectives
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 10
The Walk-through Audit Stage
Once the LOI is signed, the ESCO will need to perform a preliminary analysis of the energy consumption
and cost data by conducting a walkthrough audit (WTA). Data and additional information not yet obtained
can be requested from the SME, including bills and other relevant records.
The functions, conditions and approximate ages of all major mechanical and electrical systems are
reviewed and the retrofit opportunities are identified. Any other building/facility/business issues and
requirements set by the SME should also be noted, including security, air quality, communications,
energy information, transportation, infrastructure and waste disposal. To the greatest extent possible,
these should be addressed in line with the priorities of the SME.
A preliminary budget and savings estimate for the potential project should be established at this stage.
The preliminary analysis of the SME’s energy bills, facility survey, operating procedure survey and
operating cost data will be used as the basis for the presentation of a proposal to the SME for the
development and implementation of an energy and cost reduction project.
The review of this preliminary information should be done with the SME before the preliminary IGA
agreement proposal is formally submitted as to avoid any surprises for decision-makers.
Ultimately, this information is packaged together in a preliminary proposal and presented in the WTA
report. The word “preliminary” is key for a number of reasons:
› Preliminary nature of the various EE strategies under consideration;
› Preliminary nature of the energy savings estimates;
› Rough retrofit and equipment cost estimates;
› Need to limit the amount of information transmitted to the SME when it still has the option of
considering suppliers or mechanisms other than those proposed by the ESCO’s integrated
services;
› ESCO’s needs to have product and design flexibility during the IGA stage and before the final
implementation contract is proposed to the SME.
Objective of the Walkthrough Audit
› To enable the ESCO to gain insights into the range of facility equipment/systems and their age and condition, operating conditions/factors, and to listen to the operating personnel’s concerns and experiences with the operation.
› To collect data to support a preliminary budget analysis of the project, including the range of probable retrofits and corresponding energy savings to support a preliminary cost estimate.
› To enable the ESCO to communicate to the SME the overall scope of the project, and to demonstrate the ESCO’s ability to address the critical issues of the project.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 11
Preparation of Investment-Grade Audit (IGA) Agreement
The ESCO is responsible for preparing an IGA agreement, which includes a preliminary financial plan
and references to the walkthrough report. This preliminary agreement to conduct the IGA is usually
submitted at the same time as the WTA presentation. The last point in the walk-through audit report
presentation should be a review of the main clauses of the IGA agreement to highlight the main
obligations to be met by both parties for the project’s next step.
An IGA must be completed in order to develop a more precise project scope, estimate the savings,
gather the cost data and gain a better understanding of the effects and benefits the anticipated efficiency
measures will have on operations and maintenance. It is important to differentiate the contents of an
IGA from those of a “traditional” energy audit done by an engineering firm so that the SME understands
that they are two different audits with different costs and results. Among other things, the IGA will have
to include the preparation of an adapted M&V plan to demonstrate the savings that will be generated by
the proposed projects.
Because it requires a large amount of the ESCO’s resources to complete the IGA, it usually cannot be
offered by the ESCO without seeking a strong commitment from the SME prior to its realisation. An IGA
agreement is therefore designed to define the terms and conditions under which the IGA will be
performed and how the services will be paid for by the SME, whether the SME chooses to or not to
proceed with the implementation stage.
The IGA agreement generally states that the ESCO shall undertake an IGA at a specified cost. If the
IGA confirms the preliminary findings from the walkthrough audit, the SME will agree to enter into a full
EPC agreement with the ESCO and go forward with the project. The cost of the IGA can then generally
be financed as part of the total cost of the project and reimbursed from the energy savings in the future.
The agreement further stipulates that, in the event that the SME chooses, for any reason, not to move
forward with the EPC, following the completion and submission of the IGA report, the SME’s only
obligation will be to pay for the cost of the IGA. An important element of the agreement is the provision
of a performance feature regarding the results of the IGA. If the results of the IGA fail to confirm the
predictions of the preliminary proposal, the SME has no obligation to pay for the IGA.
Objective of the IGA Agreement
› To secure the commitment and authorization from the SME for the ESCO to proceed with the IGA. If the preliminary findings in the preliminary proposal are confirmed, actions can be taken in a timely fashion to enter into a full EPC contractual agreement.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 12
2.2 Project Design and Implementation Phase
Once the SME has selected the ESCO through the tender process or signed the IGA agreement in the
spontaneous process, the project design and implementation phase is started by the development of
the IGA.
2.2.1 IGA Preparation
ECM Identification and Design
It may take between a few weeks and a few months to complete a typical IGA, depending on the size
of the facility targeted and the number of measures to be evaluated.
ESCOs investigate all opportunities that will deliver a project within the required return on investment,
the overall capital budget, the payback period or any other indicators that meet the SME’s requirement
or wishes. The strength of an EPC is that ESCOs identify all potential opportunities, not only those within
the predefined scope of work. While the SME still has the final say, a more complete picture of
opportunities can be evaluated.
As the EE measures and strategies are developed, the ESCO should check the following items with the
SME:
› Final operational savings estimates (and potential sharing);
› Final energy savings estimates;
› Final EE measures and strategies to be implemented.
It is vital that the SME and the ESCO work as partners, responding to the each other’s needs and
requirements. Mutual and continuous dialogue is essential as it helps foster understanding between the
parties though discussion and negotiation and obtain the best possible result and contract.
Measurement and Verification Plan
It is within the IGA preparation that the measurement and verification (M&V) plan has to be designed. It
becomes a fundamental part of the IGA.
Presentation of the IGA, Final Financial Plan and IGA Acceptance
Once the IGA has been completed, a formal presentation should be made to the SME’s senior
executives. An initial implementation plan should be presented along with a review of the key elements
of the EPC. This presentation will also be an opportunity to cover contract-related questions.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 13
The main topics to be presented and discussed are the following:
› Contract term;
› Verified savings or guaranteed savings;
› Floor and ceiling price for energy by source;
› Financing condition and parameters;
› Invoicing;
› Ownership;
› Additional services, maintenance, and energy management.
The SME should request time to study the results and consider alternatives, or ask additional questions.
The IGA might need further work to adjust to SME’s selected ECMs or additional requests.
2.2.2 EPC Contract Negotiation and Signature
With the final approval of the IGA by the SME and the confirmation of the list of measures to be
implemented, the EPC can be drafted by the ESCO and presented to the SME based on the earlier
discussions and SME’s requirements. This draft version will be the basis for the SME and the ESCO to
engage in negotiations.
Once all the negotiations have been completed, the EPC is finalized, and implementation work
commences. In the case where final negotiations do not result in a signed EPC, the SME may be
required to pay for the IGA as per the cost indicated in the signed IGA agreement.
2.2.3 Project Design Finalization and Implementation
Most ESCOs will not have finished all final engineering designs upon completion of the IGA and prior to
signing the EPC. This is to avoid unnecessary upfront costs and reduce commercial risk should the
project not go forward. Once the EPC is signed by all parties, the SME will notify the ESCO to start the
implementation phase. The ESCO will take on the role of project manager by ensuring that the
specifications and drawings have been properly prepared, by inviting qualified contractors to bid (where
necessary), and by supervising and managing the installation process.
Objective of the IGA Presentation
› To present an overview of the project and explain its benefits and critical elements; to present the finalized energy services contract documents
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 14
At this stage, a detailed program work chart should be prepared and the final components of the EPC
complied with. With the detailed work specifications and schedule in place, the ESCO starts hiring
subcontractors as necessary and organizing the site for work on the project. All these activities must be
coordinated with the SME as to ensure any special requirements or restrictions are taken into account
(planned shutdowns, critical periods of operations, public holidays, vacations, etc.).
2.2.4 Project Commissioning
This task is typically performed by the ESCO, but it is strongly recommended that the SME’s operational
staff also participate to learn more about the performance aspects of the project. Commissioning is
typically not a static process, particularly when several ECMs are involved. Also, with EPCs the SME
may find that the commissioning process is more about fine-tuning until the ECMs deliver on the
expected energy savings proposed by the ESCO. As in the construction phase, the commissioning
process should be well documented and scheduled according to the SME’s and ESCO’s requirements.
Finally, the commissioning process is an ideal opportunity to train the operational staff on the detailed
aspects of each of the ECMs — it is advisable that the SME discuss this opportunity with the ESCO and
incorporate such option in the scope of work, if appropriate.
2.2.5 Savings Management and Reporting
Once project implementation has been completed, the ESCO will evaluate the energy savings
generated at the SME’s facility as per the M&V plan agreed upon at the IGA stage. The ESCO will
measure and verify the actual levels of energy savings achieved and compare these with the forecasted
levels in the proposals. The ESCO will prepare the required report as per the M&V Plan and determine
the monetary value of the savings. The cost recovery phase will continue until the entire investment has
been recovered or until the contract expires.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 15
3 FINANCING MECHANISMS: EPC, CONTRACTUAL AND NEGOTIATION ELEMENTS
The EPC models presented below are those that were identified as the most appropriate to be used for
private-sector transactions in Turkey.
Three types of performance-based contract structures will be notably used by ESCOs in Turkey, namely
“guaranteed savings”, “verified savings” and lease agreement. A template for each contract type has
been prepared and should be used as a basis for contract preparation. It should be noted that these
templates can be adjusted and adapted to the SME’s situation, project risk exposure and general project
specificities.
3.1 Guaranteed Savings
The guaranteed-savings structure is an arrangement whereby the “SME makes regular fixed debt
service payments to a third-party financial institution in the amount required to repay the ESCO’s turnkey
project price, plus the financing costs”. Under this approach, the ESCO guarantees the SME that the
achieved savings from the project will be equal to all project payments, including debt service plus any
downstream fees to the ESCO for its ongoing M&V, operation and maintenance services, under a fix
time duration. If the achieved savings fall short of the project payments made by the SME, the ESCO
will pay the difference between the achieved savings and the project payments. If the achieved savings
exceed the project payments, the SME and the ESCO may share the surplus, depending on the risk
taken and the extent of services provided by the ESCO.
Under the guaranteed-savings model, the SME uses the loan from the financial institution to finance the
project, thus bearing the financial risk of the project. The ESCO is then responsible for the design,
installation and technical performance of the installation (i.e. the operational risk) by guaranteeing the
energy savings. It can help design the loan according the expected cash flow of the project based on
the energy savings. The guaranteed energy savings model is shown in the figure below.
Figure 4: Guaranteed-Savings EPC
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 16
The ESCO is paid for its services after the installation is complete and once the performance parameters
(energy savings or cost savings) have been confirmed.
3.2 Verified Savings
The verified-savings structure refers to an arrangement whereby the ESCO partly pays for the project
and bears the obligation to repay the Lender for its investment. Under this contract model, the SME
commits, under an EPC, to providing a down payment to the ESCO for project implementation
amounting to about 50% of the initial investment and to repaying the remainder of the investment,
financed by the ESCO, through monthly installments within a limited period (up to 12-month period) as
of the project completion date. Each of the payments is paid after the ESCO has confirmed the project’s
expected savings.
Figure 5: Verified-Savings EPC
The monthly payment amounts are agreed upon by both parties on the day of signing of the contract,
and it will be tied to the savings achievement. Failure to achieve the savings will have a proportional
impact on the amount due to the ESCO by the SME based on the SME incurred losses.
The ESCO assumes the project performance risk, but also the credit risk of the SME by being obligated
to repay the Lender, even if the SME does not pay the ESCO the agreed monthly installments. Due to
the increased risk assumed by the ESCO, the SME is typically charged a higher cost for financing
the project.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 17
3.3 Lease Contract Model
A lease is in essence an extended rental agreement whereby the owner of the equipment (the ESCO)
allows the user (the SME) to operate or otherwise make use of the equipment in exchange for periodic
lease payments while still retaining ownership. Leasing is a process by which a firm can obtain the use
of a certain fixed asset for which it must pay a series of periodic, contractual and tax deductible
payments.
There are a number of reasons that companies prefer to lease equipment rather than buying it. The
main advantage of leasing lies in a business’ ability to attain assets without outlaying essential cash,
but there are many other reasons. For example, there may be good tax reasons if the operator cannot
use the depreciation tax shield; it would then make sense to sell the equipment to someone who can.
Also, the lessor may be in a better position to bear the risk of obsolescence or resell second-hand
assets. The lessor may be able to offer a very good maintenance deal. Finally, it may be much less
costly in time and effort to arrange a simple lease contract than a regular EPC.
The main advantages for leasing can be summarized as follows:
› Leasing is less capital intensive than purchasing, which means if a business has capital
constraints, it can grow more rapidly by leasing rather than purchasing property.
› Capital assets may fluctuate in value, whereas leasing transfers the risks to the ESCO.
› Depreciation of capital assets has a different tax and financial reporting treatment from ordinary
business expenses. Lease payments are considered expenses rather than assets, which can be
set off against revenue when calculating taxable profits at the end of the relevant tax accounting
period.
› Regarding tax benefits, the ESCO owns the equipment for tax reporting purposes. In a tax lease,
the SME is trading the tax benefits of equipment ownership (amortization) with the ESCO for
favourable payments and more flexible tax management. Depending on the SME’s specific tax
situation, this lease feature can significantly lower the total cost of equipment.
› Regarding maintenance, this option generally results in higher lease payments, but is often money
well spent. Under the terms of a full-service lease, the ESCO is responsible for all maintenance
associated with the leased equipment.
Under an EPC agreement using the leasing approach, the ESCO will provide a savings guarantee as
per the one found in the guaranteed savings model.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 18
3.4 Comparative Analysis of Models
Guaranteed Savings Verified Savings Lease Agreement
Performance related to the level of energy saved, typically verified monthly, quarterly or annually
Performance related to the level of energy saved, usually verified with a single commissioning test
Performance related to the level of energy saved, usually verified based on engineering estimates.
Value of energy saved is guaranteed to meet debt service obligations down to a floor price, with the ESCO covering any shortfalls.
Lump sum payments are based on achievement of key milestones, mostly based on a commissioning test and the final payment occurs after 6-12 months of successful operation.
Value of energy saved is calculated to be sufficient to cover the lease payments.
The ESCO bears performance risk; the financier bears the SME’s credit risk.
The ESCO bears the performance risk at the commissioning test; the SME bears performance risk over the life of the equipment; the financier bears the SME’s credit risk.
The ESCO bears performance risk at the commissioning test; the SME bears credit risk, risk as the lessor; the SME bears performance risk over the life of the equipment.
Because the SME takes out a loan to finance the project, the debt appears on its balance sheet.
Because the SME takes out a loan to finance the project, the debt appears on its balance sheet. But a portion of the loan is not disbursed until the commissioning test is successful.
The lease is on the balance sheet of the ESCO/lessor; there is no debt on the SME’s balance sheet.
Requires creditworthy SME. Requires creditworthy SME. Does not require credit worthiness of the SME
Requires a creditworthy ESCO;
Periodic M&V required One-time M&V required One-time M&V required
The ESCO can implement more projects without being burdened by credit/equity investments, although it will have some contingent liability.
The ESCO can recover its investment cost within a short period
The ESCO can implement more projects without being burdened by credit/equity investments.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 19
4 MEASUREMENT AND VERIFICATION OF SAVINGS
M&V is used to measure and verify, in a defined, disciplined, rigorous and transparent way, the energy
savings resulting from the implementation of ECMs to improve the energy performance of a specific
facility.
The preparation of an M&V plan is a fundamental part of an EPC. Advance planning ensures that all
data needed for savings determination will be available after the implementation of the ECMs within an
acceptable budget. The M&V methods appropriate for a given measure will depend on the equipment
type, the operational predictability and the complexity involved in the retrofit. The ESCO should develop
a project-specific M&V plan based on the project’s ECMs and site conditions prior to implementation.
Appendix IV presents the different approaches that can be used for measuring and verifying savings.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 20
5 OPERATION AND MAINTENANCE AND CAPACITY BUILDING
Under the EPC agreement, the operation and maintenance (O&M) responsibilities must be defined. This
is done to ensure that all maintenance requirements are being complied with, and that maintenance
issues do not cause lower-than-expected savings.
Based on the type of project and implemented technologies, some ESCOs can take charge of the entire
operation and maintenance of the system or simply follow up on and verify O&M activities realized by
the end user’s team, as specified by the ESCO. Potential additional savings can be generated by such
an additional service.
ESCOs can also provide ongoing energy management and training services to industrial clients
throughout the contract period to ensure that projected savings are achieved. As the M&V and
maintenance tasks are being performed, the ESCO can be constantly fine-tuning the savings from the
ECMs to reduce its risks, and if appropriate, maximize savings. This task may also include identifying
ECMs that are not performing as planned, and introducing new ECMs to make up for the loss in savings.
This continuous improvement can also frequently identify new savings opportunities in the SME
facilities, which the ESCO may from time to time present to the SME.
ESCOs can finally provide customized training and capacity building through industrial energy
management programs to help SME staff follow energy consumption, and put in place the required tools
and structures to comply with different national and international norms like ISO 50001.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 21
APPENDIX I MAIN SERVICES OF AN ESCO
The following sections describe some of the main services that an ESCO can provide to SMEs. This list
is by no means exhaustive.
Energy Auditing
An essential component of the service package offered by an ESCO is the detailed energy audit, without
which it would be impossible to identify the potential for energy cost savings that the ESCO relies on to
earn its revenues. While a typical energy consultant usually considers an energy analysis to be the final
product, the key feature of an ESCO is that this analysis is only the starting point in project
implementation.
Project Design and Implementation
The ESCO is responsible for project design, hardware specifications, procurement and installation. The
ESCO usually also oversees the operation of the new equipment over a specified period of time.
Financing
Traditional Financing
One important role frequently played by ESCOs is to participate in the development of an adapted
financing mechanism for project implementation. Although the ESCO plays no formal role in the
financing agreement itself (the guarantee is based on the SME’s balance sheet and not on the ESCO’s),
the fact that they are willing to enter into a performance contract can help increase the bank’s confidence
in the proposed project.
The financing package negotiated by the ESCO in such case is fairly conventional, consisting of a
combination of self-financing using the SME’s own resources and a typical term loan offered by a
financial institution. This type of loan appears on the SME’s balance sheet. However, the involvement
of the ESCO in developing and negotiating the loan can lead to more favourable loan terms than what
could be achieved if the SME applied for it through regular channels.
Third-Party Financing
Unlike traditional financing models, under third-party financing (TPF) the ESCO not only develops the
adapted financing mechanism, but also provides the bulk of the financing needed to implement the
project, either by investing its own money or borrowing it from a financial institution. The expected
guarantee made to the financial institution is based on the project’s value or the ESCO’s balance sheet.
The SME may or may not be expected to commit to making a small investment from its own resources.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 22
In addition, the SME is effectively shielded from any financial risk related to project performance. In
order to protect itself against default by the SME, the ESCO may retain some form of legal title to the
project equipment throughout the duration of the contract.
Measurement and Verification of Savings
The ESCO must perform rigorous M&V on the energy savings in order to convince stakeholders that
the savings are sufficient to repay the investment. M&V essentially means ongoing verification of energy
savings, sometimes by periodically comparing an energy end-user’s energy bills with an established
pre-project baseline, or by performing a direct measurement of the energy consumption before and after
the implementation of the energy conservation measure on the targeted equipment or systems. The
performance of an ongoing M&V not only ensures that the project’s savings have been achieved, but
that they will persist over time by monitoring the quality and effectiveness of ongoing maintenance,
which is key to sustained efficiency and more importantly to being able to manage the return on
investment for EE projects.
Energy Management
The services offered by an ESCO to an SME may include energy management. Energy management
outsourcing (EMO) allows the SME to use external specialists to perform this function rather than using
its in-house staff. This way, the SME can devote more of its own management resources to what it does
best—focusing on its core competency areas. Energy management services are likely to require
relatively modest capital expenditures to achieve most of the cost savings through improved
management systems rather than through the installation of new hardware, but will greatly contribute to
achieving the expected savings.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 23
APPENDIX II RFP GUIDELINES
The RFP is the mechanism used to select the ESCO with which the SME chooses to negotiate an EPC.
The RFP defines the general scope of work, along with specific requirements that must be addressed
in a performance contract. Typically, the RFP will include information on the following aspects:
› List of facilities under investigation
› Projects already identified
› Maximum contract duration (if applicable)
› Maintenance and operational requirements and
› Selection criteria
› Financial targets
Financial targets might, for example, include any of the following conditions:
› Have a minimum internal rate of return (IRR) (e.g., 15% over a specific number of years) or reach
a net present value (NPV) greater than a set value.
› Project cost must be below a present maximum capital limit.
› Contract cannot be extended beyond a maximum number of years.
› Fixed minimum annual savings or a maximum cost.
› Contract structured with a neutral or positive annual cash flow.
› Savings must be guaranteed.
The evaluation criteria include the specific requirements above and may also require information on the
following aspects:
1 Proposed savings
2 Financing options
3 Additional opportunities beyond those identified in the tender documents
The RFP is not meant to be a detailed specification of works. The main focus of the proposal is to state
the basic methodology to guarantee savings, the general EPC details, how the scope identified in the
RFP would be approached, and other opportunities the ESCO feels offer value for the SME.
The evaluation process should also be described, so that the ESCO can ensure it provides all necessary
information. This typically involves deciding on the essential requirements of the contract, giving each
requirement a weighted score and compiling results into a table. The evaluation table should be included
in the RFP document without the weighted scores.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 24
APPENDIX III EXAMPLES OF RFP EVALUATION CRITERIA
The criteria listed below can be used by SMEs to evaluate written proposals and the subsequent
interviews. The scoring weight is listed for each criterion.
These criteria can be applied and interpreted solely at the discretion of the SME. Proposals should
include all necessary information relevant to these evaluation criteria. Additional information required
for the proper assessment of proposals may be requested from the ESCO at the discretion of the
Customer.
The criteria are not listed in order of importance. The subcriteria are approximately of equal weight.
1. QUALIFICATIONS AND EXPERTISE (Scoring Weight: 50%)
a. Firm Experience: › General experience in energy-related and performance contracting services.
b. Scope of Services:
› Comprehensiveness of the proposed management, maintenance and monitoring services.
c. Financial Soundness: › Financial soundness, bonding capability and stability of the ESCO. › Completeness and strength (financial viability) of the most recent annual financial
statements.
d. Staff Information: › Qualifications and relevant experience of the engineering and project management staff, in
addition to staff in other areas of importance.
2. LEVEL OF PROPOSED SAVINGS WITHIN A GIVEN PERIOD OF TIME (Scoring Weight: 50%)
a. Project Scope: › Understanding of conditions in existing facilities, systems, and operation and maintenance
projects
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 25
APPENDIX IV M&V PLAN GUIDELINES
Measurement and Verification (M&V) of energy savings generated is the process of using measurement
to reliably determine actual savings created within an individual facility by an energy management
program. Since savings cannot be measured directly because they represent the absence of energy
use, they have to be determined by comparing measured use before and after implementation of a
project and by making appropriate adjustments for changes in conditions during this process.
Depending on the type and size of the project, M&V activities include some or all of the following:
development of the M&V plan, operational verification, meter installation, calibration and maintenance,
data gathering and screening, development of a computation method, adoption of acceptable estimates,
computations with measured data, and reporting, quality assurance, and third party verification of
reports.
Energy savings generated by an EE project can be measured using several techniques. This section
provides an overview of each option and provides a recommendation in which case it is most appropriate
to use each option when considering Turkey’s market specifics.
Retrofit Isolation / Key Parameter Measurement
Savings are determined by field measurements (spot / short-term measurements at component / system
level during baseline & reporting period) of the key performance parameters. Wherever a parameter,
known to vary independently, is not measured, it can be estimated. Typically, those estimates are based
on historical and/or manufacturer’s data.
This option can be preferred when savings are below 10% - 20% of total facility consumption and when
relevant performance and/or usage parameters can be estimated, (e.g. in case of a lighting upgrade in
which existing lamps are replaced by high efficiency versions, the consumption per lamp can usually be
estimated with sufficient accuracy and reliability).
Retrofit Isolation / All Parameter Measurement
Savings are determined by field measurements of the energy use such that all performance parameters
at component / system level are included.
This option can be preferred when the expected savings are below 10% - 20% of the total facility
consumption and none of the performance and usage parameters are sufficiently constant to allow
estimation. Measurement of the key parameters will typically be short-term and should be documented
in detail in the M&V plan.
Energy Performance Contracting Guideline for SMEs Preparation of Guidelines for EPC Contracting for ESCOs and Case Study Development
Turkish Ministry of Energy and Natural Resources
SME Energy Efficiency Project
Project No. 6008 26
Whole Facility
Savings are determined by measuring energy use at the whole facility or sub-facility level.
This option can be preferred when many different EE measures are implemented and when expected
savings are in excess of 10% - 20% of the energy consumption that is measured on a facility or sub-
facility level.
Deemed Savings
Savings are determined based on engineering calculations using typical equipment characteristics and
operating schedules without field testing or metering. Instead, verification may consist of checking units
installed & confirmation of proper operation of the equipment / measure.
This option can be preferred when the EE projects have relatively low expected savings, typically less
than 10% of the facility’s total energy consumption, that can be calculated sufficiently accurately based
on constant performance and usage parameters. Often this requires the availability of reliable, accurate
and validated engineering calculations to determine the expected savings per ECM related equipment
/ change.
Additional information
More information on M&V can be found at evo-world.org through the International Performance
Measurement and Verification Protocol (IPMVP).
160, rue Saint-Paul, bureau 200, Québec (Québec) G1K 3W1 CANADA | Tél. : +1 418 692-2592 Téléc. : +1 418 692-4899
www.econoler.com