energy cost reduction study at
DESCRIPTION
Energy Cost Reduction Study at. Draft Presentation 23-09-05. DSCL ENERGY SERVICES COMPANY LTD 2 nd Floor, Kanchenjunga, 18 Barakhambha Road, New Delhi 110001 Tel. 0091 11 23316801 Fax 0091 11 23319062. Contents. Accepted Energy cost reduction measures for implementation Status - PowerPoint PPT PresentationTRANSCRIPT
DSCL ENERGY SERVICES COMPANY LTD2nd Floor, Kanchenjunga, 18 Barakhambha Road, New Delhi 110001
Tel. 0091 11 23316801 Fax 0091 11 23319062
Draft Presentation 23-09-05
Energy Cost Reduction Studyat
ContentsAccepted Energy cost reduction measures for implementationStatusWay forward
Accepted measures but to be decided after trialEnergy cost reduction measures on ‘Hold’Way forward
Summary of savings
Summary of savingsMost Likely SavingsMost Likely Savings Possible SavingsPossible Savings Investment Investment
(Rs. Lacs)(Rs. Lacs)PayPaybacbackk
kW Kg/hr
CM/day
Rs. Lacs
kW Kg/hr
CM/day
Rs. Lacs
Most Likely
Possible
Months
II Measures of Less than 6 months PaybackMeasures of Less than 6 months Payback
Sub TotalSub Total 207 69 10 108 22
2 87 10 121 35 41 3-4
IIII Measures of Greater than 6 months paybackMeasures of Greater than 6 months payback
Sub TotalSub Total 135
267 66 115 13
5288 66 125 58 60 7-8
TOTALTOTAL 342
336 76 22
3357
375 76 246 93 100
IIIIII Accepted Project but to be decided after trialsAccepted Project but to be decided after trialsSub TotalSub Total - - - 15 - - - 15 2 2 2
IVIV Project on holdProject on holdSub TotalSub Total 20 44 - 51 30 44 - 58 40 41 8
TotalTotal 362
380 76 28
9362
419 77 319 135 129
Long Term ProjectsTotalTotal - - - 418 - - - 434 700 800 22
Grand TotalGrand Total 362
380 76 70
7362
419 77 753 835 929
Measures of Less than 6 months Payback
List of Energy Saving List of Energy Saving MeasuresMeasures
Most Likely SavingsMost Likely Savings Possible SavingsPossible Savings Investment Investment (Rs. Lacs)(Rs. Lacs)
PaybPaybackack
kW Kg/hr
CM/day
Rs. Lacs
kW Kg/hr
CM/day
Rs. Lacs
Most Likely
Possible
Months
1.1. Installation of higher Installation of higher Efficient bigger BFW PumpEfficient bigger BFW Pump 93 - - 31.
5 93 - - 31.5 5 5 2
2.2.Utilization of Steam Utilization of Steam
instead of using Electrical instead of using Electrical Heaters in Power House for Heaters in Power House for
F.O. pre-heatingF.O. pre-heating- - - 22 - - - 22 10 10 5
3.3.Installation of screen to Installation of screen to
avoid re-crushing of fines avoid re-crushing of fines before crusher and to before crusher and to
reduce unburnts.reduce unburnts.5.2 43 - 10.
7 5.2 61 - 14.8 5 5 6
4.4. DG Cooling Tower Pump DG Cooling Tower Pump Efficiency ImprovementEfficiency Improvement 14 - - 4.8 14 - - 4.8 2 2 5
5.5. High Efficiency Low Head High Efficiency Low Head Pump for DM Water supplyPump for DM Water supply
11.4 - - 3.8
511.4 - - 3.85 2 2 6
6.6.Chemtech Cooling Tower Chemtech Cooling Tower
pump Efficiency pump Efficiency ImprovementImprovement
11 - - 3.28 11 - - 3.28 1.5 1.5 5
7. 7. Floorwise segregation of Floorwise segregation of cooling watercooling water 48 - - 16.
3 63 - - 25 6 12 6
8.8.Return water from top 3 Return water from top 3 segments of Fermenters segments of Fermenters directly to CT instead of directly to CT instead of
sumpsump24 - - 8 24 - - 8 2 2 3
Accepted Energy Conservation Measures:
Measures of Less than 6 months Payback
List of Energy Saving List of Energy Saving MeasuresMeasures
Most Likely SavingsMost Likely Savings Possible SavingsPossible Savings Investment Investment (Rs. Lacs)(Rs. Lacs)
PaybPaybackack
kW Kg/hr
CM/day
Rs. Lacs
kW Kg/hr
CM/day
Rs. Lacs
Most Likely
Possible
Months
9.9. Chiller condensate Chiller condensate recoveryrecovery - - 10 1.1 - - 10 1.1 Nil Nil
Immediate
110.0. Arresting steam LeakagesArresting steam Leakages - 26 - 6.6 - 26 - 6.6 1 1 2
SUB- TOTALSUB- TOTAL 207 69 10 10
8222 87 10 121 35 41 3-4
Accepted Energy Conservation Measures:
Measures of Greater than 6 months Payback
List of Energy Saving List of Energy Saving MeasuresMeasures
Most Likely SavingsMost Likely Savings Possible SavingsPossible Savings Investment Investment (Rs. Lacs)(Rs. Lacs)
PaybPaybackack
kW Kg/hr
CM/day
Rs. Lacs
kW Kg/hr
CM/day
Rs. Lacs
Most Likely
Possible
Months
1.1. Efficiency improvement of Efficiency improvement of 03 area CT pumps03 area CT pumps 15 - - 5 18 - - 6 3 3 7
2.2.Segregation of HP and LP Segregation of HP and LP
Lines for Raw Water supply Lines for Raw Water supply from sumpfrom sump
9 - - 3 9 - - 3 4 4 16
3.3.Bigger high efficient raw Bigger high efficient raw
Water supply pumps to RO Water supply pumps to RO PlantPlant
14.7 - - 4.5 17.
7 - - 6 3 4 8
4.4.Installation of smaller low Installation of smaller low head RO pump for starch head RO pump for starch
preparationpreparation4 - - 1.5 8 - - 2.7 2 3 9
5.5. Low head pump for soft Low head pump for soft water tankwater tank 7.5 - - 2.5 8.5 - - 3 2 3 8
6.6. Main CT Fans - Power Main CT Fans - Power Consumption OptimizationConsumption Optimization 19 - - 5.3 19 - - 5.3 3.5 3.5 8
7. 7. DG and Chemtech CT Fans DG and Chemtech CT Fans
- Power consumption - Power consumption OptimizationOptimization
4 - - 1.35 4 - - 1.35 1.4 1.4 12
8.8. Chilled water distribution Chilled water distribution systemsystem 14 - - 4.7
5 14 - - 4.75 3 3 8
9. 9. Flash steam recovery from Flash steam recovery from
the flash tank in the the flash tank in the Dextrose Plant + saving of Dextrose Plant + saving of
RO WaterRO Water- 20 5 6.2
5 - 20 5 6.25 5 5 10
Accepted Energy Conservation Measures:
Measures of Greater than 6 months Payback
List of Energy Saving List of Energy Saving MeasuresMeasures
Most Likely SavingsMost Likely Savings Possible SavingsPossible Savings Investment Investment (Rs. Lacs)(Rs. Lacs)
PaybPaybackack
kW Kg/hr
CM/day
Rs. Lacs
kW Kg/hr
CM/day
Rs. Lacs
Most Likely
Possible
Months
110.0.
Condensate Recovery of Condensate Recovery of Mycelium Broth PHEMycelium Broth PHE - 22.
4 37 8.2 - 22.4 37 8.2 6 6 9
111.1.
Cooling Water return from Cooling Water return from seal pot and de-seal pot and de-
composition vessel directly composition vessel directly to Fermenter sumpto Fermenter sump
9.73 - - 3.2
89.73 - - 3.28 2 2 7
112.2.
Usage of RO Rejects for Usage of RO Rejects for the Backwashing of MGF, the Backwashing of MGF,
ACF, Sidestream Filter and ACF, Sidestream Filter and Plant CleaningPlant Cleaning
- - - 2.5 - - - 2.5 5 5 24
113.3. Line condensate RecoveryLine condensate Recovery - 18 24 2.6 - 18 24 2.6 2 2 9
114.4.
Lighting Energy Lighting Energy conservationconservation
2.55 - - 0.8
62.55 - - 0.86 1.2 1.2 17
115.5. WHRB Steam UtilizationWHRB Steam Utilization 36 20
7 - 63 36 207 - 69 15 15 3
SUB-TOTALSUB-TOTAL 135
267 66 11
5135
288 66 125 58 60 7-8
Accepted Energy Conservation Measures:
On HOLD
List of Energy Saving List of Energy Saving MeasuresMeasures
Most Likely SavingsMost Likely Savings Possible SavingsPossible Savings Investment Investment (Rs. Lacs)(Rs. Lacs)
PaybPaybackack
kW Kg/hr
CM/day
Rs. Lacs
kW Kg/hr
CM/day
Rs. Lacs
Most Likely
Possible
Months
1.1.ETP Final Discharge ETP Final Discharge
Pumps: Gravity flow or Pumps: Gravity flow or Installation of high Installation of high
efficiency pumpefficiency pump20 - - 3 30 - - 10.3 2 2 4-8
2.2.Condensate & Flash Heat Condensate & Flash Heat
Recovery during Recovery during sterilization of PF and IFsterilization of PF and IF
- - - 17.3 - - - 17.3 15.4 15.4 11
3.3.
Crystallizer and Crystallizer and Evaporators condensate Evaporators condensate
Utilization in the De-Utilization in the De-aerator instead of using in aerator instead of using in
Ion-Exchange columnsIon-Exchange columns
- 44 - 11 - 44 - 11 8 8 9
4.4.Usage of Raw Water Usage of Raw Water
instead of Soft water in instead of Soft water in the Dextrose Plant CTthe Dextrose Plant CT
- - - 0.41 - - - 0.41 Nil Nil
Immediate
5.5.Usage of Raw Water Usage of Raw Water
instead of Soft water in instead of Soft water in the 03 Area CTthe 03 Area CT
- - - 1.02 - - - 1.02 Nil Nil
Immediate
6.6. Wheeling of Power to GridWheeling of Power to Grid - - - 18 - - - 18 15 15 10
SUB-TOTALSUB-TOTAL 20 44 - 51 30 44 - 58 40 41 8
Projects on hold
To be decided after trials
List of Energy Saving List of Energy Saving MeasuresMeasures
Most Likely SavingsMost Likely Savings Possible SavingsPossible Savings Investment Investment (Rs. Lacs)(Rs. Lacs)
PaybPaybackack
kW Kg/hr
CM/day
Rs. Lacs
kW Kg/hr
CM/day
Rs. Lacs
Most Likely
Possible
Months
1.1. Zero BOD stream to be Zero BOD stream to be taken directly to Clarifiertaken directly to Clarifier - - - 15.
47 - - - 15.47 2 2 7
Projects to be decided after trials
Long Term Projects
List of Energy Saving List of Energy Saving MeasuresMeasures
Most Likely SavingsMost Likely Savings Possible SavingsPossible Savings Investment Investment (Rs. Lacs)(Rs. Lacs)
PaybPaybackack
kW Kg/hr
CM/day
Rs. Lacs
kW Kg/hr
CM/day
Rs. Lacs
Most Likely
Possible
Months
1.1. Co-Generation Co-Generation Opportunities:Opportunities:
Option 1: Running of CFB Option 1: Running of CFB at 28 TPH Load and install at 28 TPH Load and install a Back pressure STG and a Back pressure STG and Utilization of 7.5 kg/cm2 Utilization of 7.5 kg/cm2
steam for the Jet cooker + steam for the Jet cooker + Installation of suitable Installation of suitable Electrical CompressorElectrical Compressor
- - - 418 - - - 418 700 700 20
Option 2: Running of CFB Option 2: Running of CFB at 32 TPH and install a at 32 TPH and install a
Extraction cum condensing Extraction cum condensing Turbine and fulfill Turbine and fulfill
10kg/cm2 requirement 10kg/cm2 requirement thro' PRDS + Installation of thro' PRDS + Installation of
suitable Electrical suitable Electrical compressorcompressor
- - - 434 - - - 434 800 800 22
Long term projects – Cogeneration option
Project-1: Installation of high efficient high capacity Boiler Feed Water Pump for CFB
OBSERVATIONOBSERVATIONCombined efficiency of 2 BFW pumps: 33%Combined efficiency of 2 BFW pumps: 33%
OPPORTUNITYOPPORTUNITY Replacing these 2 pumps with a single high Replacing these 2 pumps with a single high
capacity high efficient pump. capacity high efficient pump. BENEFITSBENEFITS
Power savings – 93 KW Power savings – 93 KW Annual savings – Rs. 31.5 lacsAnnual savings – Rs. 31.5 lacs
Investment – Rs. 5 Lacs (Including motor)Investment – Rs. 5 Lacs (Including motor)Payback: : 2 monthsPayback: : 2 months
ISSUES:ISSUES:Hydraulic testing of the boilersHydraulic testing of the boilers
SOLUTIONSOLUTIONUse the existing pumps during the hydraulic testsUse the existing pumps during the hydraulic tests
Project-1: Installation of high efficient high capacity Boiler Feed Water Pump for CFB
STATUSSTATUSAgreed, Pump specifications frozen and Enquiry Agreed, Pump specifications frozen and Enquiry
floatedfloatedSPECIFICATIONSSPECIFICATIONS
PROCESS OWNERPROCESS OWNER
New pump Design specs
Flow (cum/hr) Head (m) Motor(KW)
45 570 110
CFB-BFWP: Existing System
Design Flow (cum/hr)
Head (m) Power (KW)
27.9 640 90
Power:86.7 KWDesign Eff: 55%Actual eff:33%
Power:87.1 KWDesign Eff: 55%Actual eff:33%
Two pumps with a total capacity of 55.8 Cum/hr is operated.Two pumps with a total capacity of 55.8 Cum/hr is operated.Design Efficiency of each pump: 55%Design Efficiency of each pump: 55%
Combined system efficiency:33% Combined system efficiency:33% Opportunity for shifting to a single high capacity high efficient pumpOpportunity for shifting to a single high capacity high efficient pump
Total flow: 33.8 cum/hr
Discharge pressure: 56 kg/cm2
Suction pressure: 1.1 kg/cm2
CFB-BFWP: Installation of efficient, bigger Pump
New pump Design specsFlow (cum/hr)
Head (m)
Motor(KW)
45 570 110
Total flow: 33.8 cum/hr
Discharge pressure: 56 kg/cm2
Suction pressure: 1.1 kg/cm2
New bigger sized pump
Power:80 KWDesign Eff: 70%
The combined efficiency of both the pumps is 33%s The combined efficiency of both the pumps is 33%s Replacing these 2 pumps with a single high capacity high efficient pump . For hydraulic Replacing these 2 pumps with a single high capacity high efficient pump . For hydraulic
testing the old pump can be used.testing the old pump can be used.Power savings – 93 KW Power savings – 93 KW
Annual savings – Rs. 31.5 lacsAnnual savings – Rs. 31.5 lacsInvestment – Rs. 5 Lacs (Including motor)Investment – Rs. 5 Lacs (Including motor)
Payback: : 2 monthsPayback: : 2 months
Project-2: Usage of Steam heaters instead of Electrical Heaters in power house for FO
preheatingOBSERVATIONOBSERVATION
184 kW electrical heaters are used for FO pre-184 kW electrical heaters are used for FO pre-heating at the power househeating at the power house
OPPORTUNITYOPPORTUNITY Electrical heaters may be replaced with steam Electrical heaters may be replaced with steam
heatersheatersBENEFITSBENEFITS
Savings in energy cost: 22 Lac Rs. Per annum Investment: Rs 10 Lacs
(Investment to be revalidated taking into account automation sensors and other controls)
Payback:5 monthsISSUES:ISSUES:
Investment to be revalidatedInvestment to be revalidated
STATUSSTATUSAgreed and already in touch with vendors for Agreed and already in touch with vendors for
freezing the investmentfreezing the investment
PROCESS OWNERPROCESS OWNER
DSCL ES RoleDSCL ES RoleWould revalidate the investment required and the Would revalidate the investment required and the
cost benefit analysiscost benefit analysis
Project-2: Usage of Steam heaters instead of Electrical Heaters in power house for FO
preheating
Usage of Steam instead of Electrical Heaters in power house
In the HFO Separator 72 kW Heaters (one standby) are used presently for heating of F.O.Booster Heaters are also of 72 kW(one standby) rating each.One Electrical Lube Oil Heater of 40 kW is also in operation.
Total Steam Requirement: 4.5 to 4.8 TPDSaving Possible: 22 Lac Rs. Per annum
Investment: Rs 10 Lacs(Investment to be revalidated taking into account
automation sensors and other controls)Payback:5 months
Usage of Steam instead of Electrical Heaters in power house
Actual consumption:45.2 KWA.C:30.1 KW
Lube oil heater:A.C: 20.1 KW
Project-3: Installation of screen before crusher to reduce unburnts
OBSERVATIONOBSERVATION30 to 50% of coal fed into the crusher is –6 mm size 30 to 50% of coal fed into the crusher is –6 mm size and fines. More than 50% of coal fed into the boiler and fines. More than 50% of coal fed into the boiler is less than –2 mm. Average unburnts in ash is 15%is less than –2 mm. Average unburnts in ash is 15%
OPPORTUNITYOPPORTUNITY Reduction of fines in coal by installing a screen Reduction of fines in coal by installing a screen before the crusher and reduction of unburnts in before the crusher and reduction of unburnts in
ashashBENEFITSBENEFITS
Coal savings – 43 kg/hr to 61 Kg/Hr Coal savings – 43 kg/hr to 61 Kg/Hr Annual savings – Rs. 10.2 to 14.3 lacsAnnual savings – Rs. 10.2 to 14.3 lacs
Savings due to crusher load reduction: 5.2 KWSavings due to crusher load reduction: 5.2 KWAnnual savings:0.48 LacsAnnual savings:0.48 Lacs
Total savings: Rs. 10.7 to 14.8 LacsTotal savings: Rs. 10.7 to 14.8 LacsInvestment – Rs. 5 LacsInvestment – Rs. 5 Lacs
Payback: 5.6 monthPayback: 5.6 month
ISSUES:ISSUES:NilNil
STATUSSTATUSAgreed and already quotation for the screen has Agreed and already quotation for the screen has
been obtainedbeen obtained
PROCESS OWNERPROCESS OWNER
Project-3: Installation of screen before crusher to reduce unburnts
Installation of screen before crusher to reduce unburnts
10*10 cm
8*8 mm
Requirement: (-)6 mm to +2mm
As per samples taken on 19th & 20th
25.9%25.4%
53.3%37.2%
44.1%32%
Rejects
5.1%33.4%
5 mm sieve
Installation of screen before crusher to reduce unburnts
10*10 cm
8*8 mm
Unburnts increase because of fines. Provision of screens at the Inlet to hammer mills.
As per samples taken on 14h & 20th
43.03%
22.48%
63.2%
Rejects
0.85%2 mm sieve
Requirement: (-)6 mm to +2mm
Installation of screen before crusher to reduce unburnts
Proposed schemeProposed scheme 6*6 mm screen
Possibility of maintaining the fines from 5 to 10% in imported coal
Installation of screen before crusher to reduce unburnts
Sample size: 1.5 kgAverage fines (-2mm) in raw coal : 18.8%Average fines (-2mm) to coal bunker: 60%- 2 mm sieve coal increases from 18.8 units to 60 unitsAvg unburnts in ash: 15.47%
25% of the total fines generated at crusher25% of the total fines generated at crusher
Limit fines Generation at crusher by installation of screen at inlet to the crusher. Limit fines Generation at crusher by installation of screen at inlet to the crusher. This Will help reduce the unburnts in ash and reduce power consumption at the crusherThis Will help reduce the unburnts in ash and reduce power consumption at the crusher
Maintaining unburnts from 5 to 8%Maintaining unburnts from 5 to 8%Coal savings – 43 kg/hr to 61 Kg/Hr Coal savings – 43 kg/hr to 61 Kg/Hr
Annual savings – Rs. 10.2 to 14.3 lacsAnnual savings – Rs. 10.2 to 14.3 lacsSavings due to crusher load reduction: 5.2 KWSavings due to crusher load reduction: 5.2 KW
Annual savings:0.48 LacsAnnual savings:0.48 LacsTotal savings: Rs. 10.7 to 14.8 LacsTotal savings: Rs. 10.7 to 14.8 Lacs
Investment – Rs. 5 LacsInvestment – Rs. 5 LacsPayback: 5.6 monthPayback: 5.6 month
05
10152025
31 30 29 28 27 26 25 24 23 22 20 19 18 17 14 1August
unbu
rnt %
var
iatio
n
Unburnt % variation