enclosed is licensee event report 90-013 for the perry ... · the root cause of this event is...

4
:. , - , ;p. p. ~ G. ;;: ' 6200 00k Tree Boutevoro Mail Accress: . Independence 0H PO Box 94661= I' 216 447 310 0 Cleveland.0H 441014661 e + July 13, 1990 , PY-CEI/NRR-1198 L U.S.-Nuclear Regulatory Commission Document Control Desk L- Washington, D.C.. 20555 Perry Nuclear Power Plant Docket No. 50-440 ; LER 90-013 I Dear Sir: Enclosed is Licensee Event Report 90-013 for the Perry Nuclear Power Plant. ' il | Sinc j .. / Michael D.-L ster , '' Vice President, Nuclear - Perry i ! | :MDL:nje- j Enclosure: LER 90-013 | cc: NRR Project Manager | NRC Resident Inspector- | -i t ,1 L 'U.S. Nuclear Regulatory Commission | 799 Roosevelt Ro.d Glen Ellyn, Illinois 60137 =j ' ' } 9007170312 900713 " PDR ADOCK 05000440 S PDC ' Operahr.g Companies : Cleveland Electric liluininahng , e ., Tcla Edison .. k *. _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ - - - _ - _ - - _ - - - _ - - - _ _ - _ _ - - _ _ -

Upload: others

Post on 01-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Enclosed is Licensee Event Report 90-013 for the Perry ... · The root cause of this event is personnel error, inattention to detail. Both the 4' Tc.nnician who performed the surveillance

:., - ,

;p.

p. ~

G.

;;: ' 6200 00k Tree Boutevoro Mail Accress:. Independence 0H PO Box 94661=I' 216 447 310 0 Cleveland.0H 441014661

e+

July 13, 1990,

PY-CEI/NRR-1198 L

U.S.-Nuclear Regulatory CommissionDocument Control Desk

L- Washington, D.C.. 20555

Perry Nuclear Power PlantDocket No. 50-440 ;

LER 90-013 I

Dear Sir:

Enclosed is Licensee Event Report 90-013 for the Perry Nuclear Power Plant.' il

|Sinc j..

- /_

Michael D.-L ster,

'' Vice President, Nuclear - Perryi!

| :MDL:nje- j

Enclosure: LER 90-013

| cc: NRR Project Manager| NRC Resident Inspector-

|-it ,1

L 'U.S. Nuclear Regulatory Commission.

| 799 Roosevelt Ro.dGlen Ellyn, Illinois 60137 =j

' '} .

9007170312 900713 "

PDR ADOCK 05000440S PDC

'Operahr.g Companies:

Cleveland Electric liluininahng, e ., Tcla Edison

.. k*.

_ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ - - - _ - _ - - _ - - - _ - - - _ _ - _ _ - - _ _ -

Page 2: Enclosed is Licensee Event Report 90-013 for the Perry ... · The root cause of this event is personnel error, inattention to detail. Both the 4' Tc.nnician who performed the surveillance

_ . _ __

Nageomm as U slucL4*J 6.8Gutatony CommisesoN *d.PPnovi0 ows No. 31to4104

4 KPr E 8 4130797 6

j. ,

EsteM1Tf D OUMEN Pt3 f tSPON94 TO CouPLY C'TM TH1'

" "' ' ''

LICENSEE EVENT REPORT (LER) CO"t#iUo*&o'i*o'.'ub##,'iJ84'TMERT"o'"c-

AseD miPORTS MAhAof MENT ORameCM 19 4 301 U S NUCLI A i

PAPERWO Rt T e. U to 0 O IC t.. 1, MANAotMa ~T ANo .voott..A-i oioN.oC w.n -

r o4 eACnifv =Aufau ooCat, =viseen ai === m

$ Parry liuelear Power Plant, Unit 1 10 |5 | 010 | 0 | 4| 4 | C 1 |OF| 013I ' " ' ' ' ' ' iPersonnel Error During Surveillance Results in an Inoperable Main Steam Line

Radiation Monitor in Excess of Technical Sr.eelfication Allowances4vtNT DAT4168 Ltn ,synetR f6) RIPO.t? OATI 171 OTMtR f ACitfTit8 INVOLVED 108

MONTM DAV YEAR vl&R " $, "$n" "'vY, MONtM OAV vtAR 8 AC'Leiv mamas DOCEtT Muesetnist, ,,

015101010 1 | |

0|6 ||8 90 9| 0 0| | | 3 0|0 0 |7 ||8 9|0~ ~

9 1 51 0 10 t 0 i l 1TMi6 etPoar is sueuiTTeo PunsuA=T to THE mLovinautNu o, a C,n s ,c . . ., , nu

, , , , , , , , , ,* * * * * ' | n onmo

_n eems.\ u rmuH.I n nmo

_ _

m assi.HiHn eo mi.Hu ettwuH.i ts.ni.iy _ _ _ _

11010 m assi. Hum_

eo.mi.im swmwi gu g,y,,=eonei_ _

m .mi.in He 1 ee.rwuHe em.Hni.MHA> m4sg _ _

i M etStei(1 HNI 94 734eH311el SC.73teiuH.aelitti4

M 40PisinH.) 90.734sH3HelH to 134.It3 Hal4LICENG8t COetTACT 70m TMis Len uti

NiMt YtLEPHONE i.umetR *.

AmtAC004

Henry L. Hegrat, Compliance Engineer, Extension 6855 21116 215191-13171317CORAPLif t ONE Liast pom S ACM COnposiENT PalLURE D00CAISED iN TMe8 RSPOAT H31

CAUSE 8v 3 TIM C04sPO etNT "^"$'g Age g, $IN'g 'O' "$ 'fg AC Re

CAUSE $VlttM COMPONINT yy y

x' '

! ! I I I I I I I I I 1 1 I>

>

8I I I I I I l I I I I I I l

'

SuprLeassNT AL AIPOAT E APOCT80 llei es0Nin DAY vlAA

eveMinioN" ' " " ' '

] v8:ita . .- exeectro sve.,imo o4 res ~il o j | |r ,,

AesT a Act u. , > <= . . . -, a, . . ... . , nei

On June 19, 1990 at 1035, it was realized that the "C" Main Steam Line' Radiation.Monitor [IL) '(MSL RM) had been inoperable for greater than the time allowed byTechnical Specification 3.3.1.a and 3.3.2.b without taking the required actions.

The root cause of this event is personnel error, inattention to detail. Both the

4'Tc.nnician who performed the surveillance and the Control Room Unit Supervisorwho reviewed the results failed to recognize that one of the tested values was <

outside of its allowable value. After replacing the faulty MSL RM drawer, themode of failure could not be recreated while performing additional bench testing.

. AfLer further review, it has been determined that a prob'able cause of the drawerfailure was due to oxidation of the drawer test switch contacts.

At the time of the event discovery, the faulty MSL RM drawer was replaced and acomplete retest and calibration of the new circuitry was performed. Both theoperator and technician involved were counseled on the importance of surveillance >

reviews and attention to detail. All Instrument and Control Technicians will betrained on the lessons learned from this event. All Licensed Operators will betrained on the lessone learned from this event through routine requalificationtraining.

N.~C F.,m 30016491

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .______ _ ____ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Page 3: Enclosed is Licensee Event Report 90-013 for the Perry ... · The root cause of this event is personnel error, inattention to detail. Both the 4' Tc.nnician who performed the surveillance

.

'

g,o.u, a u .. vCm. . .ovmo., c- .oN ,,,,,,,,,,,,,,,,,,o,,

EXPIRES 4/3092,

LICENSEE EVENT REPORT (LER) f,2','.','ic'd|,0 No"'!;?,*,MT'* f'|''# ,T."JO*

TEXT CONTINU ATION - F,.t".'."a' Fit'Nd ?On!',E"','!# ',".' MUA,

i m^,'.*.M Jt"".'=,a'. n."=?* =n' t". ! 'a"'

of RA48th04 MENT AND 9UDGtt ASHtN0Yoss. DC 70003"

,acettiv NAME tu DoCIL41 NUMBER 42) gga tsubdSER (46 PA06 (31

" M." - '"J,.*.O |vsaa

|Perry Nuclear Power Plant, Unit I o p |ojo|oj4]4|0 9| 0 0|0 0|2 or 0 |30|l| 3- -

,

ru,wn mm. ns m-mm.amcu.amavnn !

On June 19, 1990 at 1035, it was realized that the "C" Main Steam Line Radiation |Monitor [IL) (MSL RM) had been inoperable for greater than the time allowed by |

Technical Specification (TS) 3.3.1.a and 3.3.2.b without taking the required ;

- actions. At the time of the event, the plant was in Operational Condition ! |(Power Operation) with reactor power at 100 percent of rated thermal power. The '

.Reactor Pressure Vessel [RPV) was at oaturated conditions.at approximately 1038 ;

|j .psig. "

fl On June 18, 1990 at 2101, Surveillance Instruction (SVI-D17-T0040-C) "MSL RM? Channel C Functional For ID17-K6100" was released for work by the control room.

The applicable steps of the procedure were physically completed and then reviewedby the technicians. Upon completing the cover sheet of the surveillance at 2145,the technicians marked that three of the test readings had as found values

outside of their leave as is zones (LAIZ) but within their allowable values. TheControl Room. Unit Supervisor then reviewed the results of the testing andconcurred with the technician by signing the cover sheet. A work reouest wasthen submitted to correct the calibration of the drawer. On June 19, the systemengineer reviewed the work package and identified that an additional parameterhad been outside of both its LAIZ and allowable value. The engineer immediatelybrought this to the attention of the control room at 1035. The "C" MSL RM wasthen. declared inoperable and the trip system for this chanoc1 was placed in the. tripped condition in accordance with Technical Specification Action Statement3.3.1.a and 3.3.2.b. Troubleshooting activities determined that a problem

" existed within the MSL RM instrumentation drawer. This drawer was replaced and asystem retest was conducted. At 0546 on June 20, 1990, the "C" MSL RM wasdeclared operable and the manually inserted trip condition was removed.

The mode of failure for the faulty MSL RM drawer could not be recreated while-performing additional bench testing. After further review, it has beendetermined that a probable cause of the drawer failure was due to oxidation of-

% the drawer function switch. Since this function switch does not affect the

$ component operability during normal operation, no negative affects are expected6 to be experienced in the other.three MSL RM drawers.

The root cause of the failure to comply with Technical Specifications ispersonnel error, irattention to detail. Plant Administrative procedure(PAP-1105) " Surveillance Test Control" requires that upon discovering asurveillance value outside the allowable value the person performing the testshall inform the Control Room Unit Supervisor and document the problem through acondition report. This procedural guidance is given so that action can be takento satisfy any Technical Specification action requirements. During theperformance of SVI-D17-T00400, the technician performed all the required steps in

.

accordance with plant procedures; however, he failed to recognize the individual2 parameter as being outside of allowable value. Additionally, during the review

'A of the surveillance after completion, both the technician and the Control RoomUnit Supervisor, who reviews all completed surveillances, failed to recognizethat one of the parameters was outside of its allowable value. As a result, therequired Technical Specification actions were not taken.

NiC F.m JE4A (6496

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Page 4: Enclosed is Licensee Event Report 90-013 for the Perry ... · The root cause of this event is personnel error, inattention to detail. Both the 4' Tc.nnician who performed the surveillance

3i

.ohh M ut hWCLl_R R iU4A,ORY CoseMintoh. gp g

LICENSEE EVENT REPORT (LERI "''"'"*'u'*'"""""'""'*c"'""'"'"''*

D' *Y'' ' ' 'N''"'"*"'" " ''*'' '

TEXT CONTINUATION Mfd?o"n','M.E"o!"U".'.i.fM *M #! T='d'o'

\-

'"

-

.'

t D'i'o*M *:o*fu'st,.'" iiL?s@e%*'"c'.Aem, . m Can v .. . , , , , , . , ,... o,p ,

.... a = .- =.n:

0|0,013 0F 0|30 ||| 3Perry Nuclear Power Plant, Unit I o |5 j o j o |c | 4| 410 9|0 - -

iSMT f# mese ansee a mensouf, o.s eswesamt Nec Fenn Jme al1171|

)

-The MSL RM' system monitors the radiation level exterior to the MSL. The( detectors are geometrically located so that each detector is capable of

.

I

detecting significant increases in radiation levels from any of the MSL's. The i

detectors are physically located in separate pipe wells which extend into the- ,

j; steam tunnel just downstream of the main steam line isolation valves. In the'

'' event of a gross release of fission products from the core, t.his monitoring

{j;- system provides channel trip signals to the Reactor Protection System [JE] (RPS)- I

and the Nuclear Steam Shutoff System [JM) (NSSS) to initiate a reactor scram andcontainment isolation. The MSL RM system consists of four redundant' !

instrumentation channels serving two RPS and NSSS trip systems. Since the RPS |and NSSS trip logics are both one out of two taken twice and with only one MSL RM

, (,

inoperable, any high level of rs.diation would have been detected and all,

required protective actions would have been taken. Therefore, this event is notconsidered safety significant. No previous similar events have been identified.

.At the time of the event discovery, the faulty MSL RM drawer was replaced and a" complete retest and calibration of the-new circuitry was performed, Both,the

operator and technician involved were counseled on the importance +k surveillanceo

reviews and attention to detail. All Instrument and Control Technicians will be ,

trained on the lessons learned from this event. All Licensed Operators will betrained on the lessons learned form this event through routine requalification

,

i training.

Energy Industry Identification System Codes are identified in the text as [XX].*

pakk..;

,

..g -

s

NIC F.am 3e4A 16491