electrical testing procedures

Upload: norazmi-hj-mohamed-noor

Post on 07-Apr-2018

245 views

Category:

Documents


6 download

TRANSCRIPT

  • 8/6/2019 Electrical Testing Procedures

    1/51

    1

    GK Batchelor Laboratory

    Department of Applied Mathematics and Theoretical Physics

    UNIVERSITY OF CAMBRIDGE

    Elec t r ic a l Safet y :

    Pol ic y and Proc edures

    Contents

    1 Scope .......................................................................................................................... 5

    2 Use of Equipment....................................................................................................... 5

    2.1 Policy................................................................................................................... 5

    2.1.1 Offices.......................................................................................................... 52.1.2 Laboratory .................................................................................................... 5

    2.1.3 Laptops......................................................................................................... 5

    2.1.4 Home office.................................................................................................. 6

    2.2 Testing................................................................................................................. 6

    2.3 Auditing............................................................................................................... 7

    2.4 Rig Risk Assessment........................................................................................... 7

    2.5 Elemental Risk Assessment ................................................................................ 8

    2.6 Operating Procedures .......................................................................................... 8

    2.7 Standard Procedures............................................................................................ 9

    2.7.1 Positioning of Equipment............................................................................. 9

    2.7.2 RCD Protection ............................................................................................ 92.7.3 Switching...................................................................................................... 9

    2.7.4 Extension leads and plug boards ................................................................ 10

    2.7.5 Earth bonding............................................................................................. 10

    2.7.6 Submersible equipment.............................................................................. 10

    2.8 Faults ................................................................................................................. 11

    2.9 Disposal ............................................................................................................. 11

    2.10 People .............................................................................................................. 11

    2.10.1 User .......................................................................................................... 11

    2.10.2 Electrical Safety Assessor ........................................................................ 11

    3 Tests ......................................................................................................................... 11

    3.1 Brand New Equipment ...................................................................................... 113.2 Equipment from Other Sources......................................................................... 12

    3.3 Standard Tests ................................................................................................... 12

    3.3.1 Cable damage ............................................................................................. 12

    3.3.2 Casing damage and condition .................................................................... 12

    3.3.3 Fuse rating.................................................................................................. 12

    3.3.4 Earth bond .................................................................................................. 12

    3.3.5 Insulation.................................................................................................... 13

    3.3.6 Operational................................................................................................. 13

    3.3.7 Earth leakage.............................................................................................. 13

    3.4 Flash Tests ......................................................................................................... 13

    3.5 Supplementary Tests ......................................................................................... 13

    4 Documentation ......................................................................................................... 14

  • 8/6/2019 Electrical Testing Procedures

    2/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 2

    4.1 Record Sheet ..................................................................................................... 14

    4.2 Test Sticker........................................................................................................ 14

    4.3 Database ............................................................................................................ 14

    5 Office Equipment ..................................................................................................... 15

    5.1 Office Appliances.............................................................................................. 15

    5.1.1 Desk lamps ................................................................................................. 155.1.2 Fans ............................................................................................................ 15

    5.1.3 Heaters........................................................................................................ 15

    5.2 Kitche and Cleaning .......................................................................................... 16

    5.2.1 Kettles......................................................................................................... 16

    5.2.2 Microwaves ................................................................................................ 16

    5.2.3 Vacuum cleaners ........................................................................................ 16

    5.3 IT Equipment..................................................................................................... 17

    5.3.1 Computers .................................................................................................. 17

    5.3.2 Computer monitors..................................................................................... 17

    5.3.3 Laptops....................................................................................................... 18

    5.3.4 Printers ....................................................................................................... 185.3.5 Data hubs.................................................................................................... 18

    5.4 Communication Equipment............................................................................... 19

    5.4.1 Answerphones and dictation machines ...................................................... 19

    5.4.2 Fax machines.............................................................................................. 19

    5.5 Reproduction Equipment................................................................................... 19

    5.5.1 Photocopiers............................................................................................... 19

    5.5.2 Binders ....................................................................................................... 19

    5.6 Projection Equipment........................................................................................ 20

    5.6.1 Slide projectors........................................................................................... 20

    5.6.2 Overhead projectors ................................................................................... 20

    5.6.3 Data projectors ........................................................................................... 20

    Video tape recorders............................................................................................ 21

    6 General Equipment................................................................................................... 21

    6.1 Catering Equipment........................................................................................... 21

    6.2 Plant................................................................................................................... 21

    6.3 Lighting and Sockets......................................................................................... 21

    7 Laboratory Equipment.............................................................................................. 21

    7.1 Office Appliances.............................................................................................. 21

    7.1.1 Desk lamps ................................................................................................. 21

    7.1.2 Fans ............................................................................................................ 22

    7.1.3 Vacuum cleaners ........................................................................................ 227.2 Laboratory Appliances ...................................................................................... 22

    7.2.1 Densitometer .............................................................................................. 22

    7.2.2 Refrigerator ................................................................................................ 23

    7.2.3 Freezer........................................................................................................ 23

    7.3 IT Equipment..................................................................................................... 23

    7.3.1 Computers .................................................................................................. 23

    7.3.2 Computer monitors..................................................................................... 24

    7.3.3 Printers ....................................................................................................... 24

    7.3.4 Data hubs.................................................................................................... 24

    7.3.5 Portable equipment..................................................................................... 25

    7.4 Video Equipment and Cameras......................................................................... 257.4.1 Video tape recorders................................................................................... 25

  • 8/6/2019 Electrical Testing Procedures

    3/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 3

    7.4.2 Video monitors........................................................................................... 25

    7.4.3 Video timers ............................................................................................... 26

    7.4.4 High-speed cine camera ............................................................................. 26

    7.4.5 Video cameras............................................................................................ 26

    7.4.6 Camera power supplies .............................................................................. 27

    7.5 Light Sources..................................................................................................... 277.5.1 Projectors.................................................................................................... 27

    7.5.2 Photographic lamps.................................................................................... 28

    7.5.3 Turntable lamps.......................................................................................... 28

    7.5.4 Fluorescent lamps....................................................................................... 29

    7.5.5 Light boxes................................................................................................. 30

    7.5.6 Arc lamps ................................................................................................... 30

    7.5.7 Strobe lights ............................................................................................... 31

    7.6 Lasers ................................................................................................................ 31

    7.7 Power Supplies.................................................................................................. 31

    7.7.1 Bench supplies ........................................................................................... 31

    7.7.2 Plug-in adapters.......................................................................................... 327.7.3 High voltage supplies ................................................................................. 32

    7.8 Laboratory Instrumentation............................................................................... 33

    7.8.1 Amplifiers................................................................................................... 33

    7.8.2 Bridge circuits ............................................................................................ 34

    7.8.3 Multimeters ................................................................................................ 34

    7.8.4 Oscilloscopes.............................................................................................. 34

    7.8.5 High voltage equipment ............................................................................. 35

    7.9 Motors and Controllers...................................................................................... 36

    7.9.1 Servo motor controllers.............................................................................. 36

    7.9.2 Servo motors .............................................................................................. 36

    7.9.3 AC motors .................................................................................................. 36

    7.10 Pumps.............................................................................................................. 37

    7.10.1 Integrated pumps...................................................................................... 37

    7.10.2 Peristaltic pumps ...................................................................................... 37

    7.10.3 Submersible pumps .................................................................................. 38

    7.10.4 Vacuum pumps......................................................................................... 38

    7.10.5 Double-bucket pumps .............................................................................. 38

    7.10.6 Variable speed pumps .............................................................................. 39

    7.11 Turntables........................................................................................................ 39

    7.11.1 Turntables................................................................................................. 39

    7.12 Laboratory Equipment..................................................................................... 407.12.1 Heat baths................................................................................................. 40

    7.12.2 Stirrers ...................................................................................................... 40

    7.12.3 Scales........................................................................................................ 41

    7.12.4 Immersion heaters .................................................................................... 41

    7.13 Frameworks and Tanks ................................................................................... 41

    7.13.1 Metalwork ................................................................................................ 41

    7.14 Power Cords .................................................................................................... 42

    7.14.1 Standard cords (IEC)................................................................................ 42

    7.14.2 Non-standard cords .................................................................................. 43

    7.14.3 Cords with RCD....................................................................................... 43

    7.15 Plug-boards and Extension Leads ................................................................... 437.15.1 Plug-boards............................................................................................... 43

  • 8/6/2019 Electrical Testing Procedures

    4/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 4

    7.15.2 Integrated plug-boards.............................................................................. 44

    7.15.3 Extension Leads ....................................................................................... 44

    7.16 RCDs............................................................................................................... 45

    7.16.1 RCD adapters ........................................................................................... 45

    7.16.2 RCD plugs................................................................................................ 45

    7.16.3 RCD sockets............................................................................................. 457.17 Fixed Installations ........................................................................................... 45

    7.17.1 Hand driers ............................................................................................... 45

    7.17.2 Heaters...................................................................................................... 46

    7.18 Three-phase Installations................................................................................. 46

    7.18.1 Wind tunnels ............................................................................................ 46

    7.18.2 Flumes...................................................................................................... 46

    7.18.3 Sump pump .............................................................................................. 46

    7.18.4 Ventilation equipment.............................................................................. 47

    8 Workshop ................................................................................................................. 47

    8.1 Hand Tools ........................................................................................................ 47

    8.1.1 Drills........................................................................................................... 478.1.2 Grinders...................................................................................................... 47

    8.1.3 Saws ........................................................................................................... 48

    8.1.4 Routers ....................................................................................................... 48

    8.1.5 Heat guns.................................................................................................... 49

    8.1.6 Soldering irons ........................................................................................... 49

    8.2 Fixed Tools........................................................................................................ 49

    Three Years ......................................................................................................... 49

    8.3 Three-phase Installations................................................................................... 50

    8.3.1 Milling machines........................................................................................ 50

    8.3.2 Lathes ......................................................................................................... 50

    8.3.3 Drilling machines....................................................................................... 50

    8.3.4 Compressor ................................................................................................ 50

    8.3.5 Abrasion tools ............................................................................................ 51

  • 8/6/2019 Electrical Testing Procedures

    5/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 5

    1 Scope

    This document outlines the various procedures, responsibilities, and risks

    associated with the use of mains-operated electrical equipment in the Fluid

    Dynamics Laboratory. The document provides guidance for the development of

    Risk Assessments, and describes the various test procedures and hazards

    associated with the main classes of equipment used in the Laboratory and

    Workshop.

    NOTE: A replacement for this document is under preparation. A draft of the

    new CMS Site Policy may be found at

    http://www.damtp.cam.ac.uk/lab/safety/ElectricalDraftPolicy.pdf

    2 Use of Equipment

    2.1POLICY

    2.1.1 Offices

    No mains-operated electrical or electronic equipment may be used unless it has a

    valid test sticker issued by the Department. Test stickers from other sources are

    not acceptable alternatives. This requirement applies to all office equipment and

    domestic appliances, including computers and even if they are brand new. Any

    equipment that has been modified or is not standard equipment must be subject to

    the procedures and standards outlined for laboratory equipment.

    The user must be familiar with the manufacturers instructions for the equipment

    and use it in accordance with these.

    Failure to observe these procedures may result in sanctions or disciplinary actionagainst the offender.

    2.1.2 Laboratory

    No mains-operated electrical or electronic equipment may be used unless it has a

    valid test sticker issued by the Department and a Risk Assessment has been

    carried out. Test stickers from other sources are not acceptable alternatives, and

    stickers are required even for brand new equipment. The user must have read and

    be familiar with the Operational Procedures for the equipment. The user must also

    be familiar with and adhere to the general guidance and procedures given in the

    Laboratory Safety Guidelines and the specific procedures outlined below.

    Failure to observe these procedures may result in sanctions or disciplinary action

    against the offender.

    2.1.3 Laptops

    All laptops purchased or owned by the Department must be tested in accordance

    with this policy, even if the laptop is never used within the Department itself.

    Testing should include inspection of any multi-standard mains adapter that may

    be used with the laptop.

    When outside the Department, users should only connect to the mains if they are

    confident that the electrical outlet is safe and that their laptop is not damaged.

    http://www.damtp.cam.ac.uk/lab/safety/ElectricalDraftPolicy.pdfhttp://www.damtp.cam.ac.uk/lab/safety/ElectricalDraftPolicy.pdfhttp://www.damtp.cam.ac.uk/lab/safety/ElectricalDraftPolicy.pdf
  • 8/6/2019 Electrical Testing Procedures

    6/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 6

    Visitors from outside the Department are requested not to connect their laptops

    unless they have been tested to a level comparable to that outlined in this

    document. The Department is happy to test laptops for long-term visitors. It is

    recommended that short-term visitors run their laptops from batteries. The

    Department does not condone the use of laptops that have not been tested and

    cannot be held liable for any injury, damage or other consequence of failing toobserve this guideline.

    2.1.4 Home office

    Some members of staff have equipment (primarily IT equipment) in their own

    homes where this equipment is purchased out of departmental or research funds.

    The responsibility for ensuring that this equipment is tested regularly (typically

    every three years) falls solely on the user of such equipment. The Department will

    test such equipment if the user brings it into the Department for testing. The

    Department will also test other equipment that is used predominantly for work at

    home, even when it is not owned by the Department, provided it is brought into

    the Department for testing.

    Users should adhere to the same level of standards in both the home office and

    Departmental contexts. This includes but is not limited to Electrical Safety and the

    Universitys guidelines for the use of VDU screen equipment.

    The Department cannot be held responsible for loss or injury resulting from

    failure to adhere to this guideline or from failure to ensure the equipment is tested

    regularly.

    2.2TESTING

    Prior to 2000, the test stickers on items of equipment indicated only the date the

    equipment was last tested. From July 2000 onwards, the stickers indicate both thedate tested, and the date the next test is due. With the older type of stickers, the

    user should seek verification that the equipment is still safe to use for any

    equipment where the date is more than two years before the present. For the

    newer style of sticker, equipment must not be used beyond the next test due

    date.

    For equipment where the mains power cable is not integral, both the cable and the

    equipment itself should have a valid test sticker.

    Brand new items, and equipment sourced from elsewhere must also be issued with

    test stickers. The equipment must not be used until this has been completed. The

    level of testing required for this is detailed elsewhere in this document.

    In the Risk Assessment for a laboratory experiment, the user must list all electrical

    equipment and record the next test due date for each item. It is the responsibility

    of the user to react accordingly when this due date is approaching. It is

    recommended that a re-test is requested four weeks before the due date. Note that

    failure to request testing at least three weeks in advance of the due date may lead

    to delays in the experimental programme while awaiting for a test to be

    undertaken.

    The user should also complete a visual inspection of all equipment on a regular

    basis. Any defective, damaged or otherwise unsafe equipment should be

    disconnected immediately and the reason for the disconnection indicated on the

  • 8/6/2019 Electrical Testing Procedures

    7/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 7

    equipment. Notices for indicating faults are available from the Electronics

    Technician. The defect should also be reported to the Electronics Technician.

    Not all equipment will be subject automatically to regular testing. The testing of

    items that have not been used for a long time, or are only used infrequently, may

    be allowed to lapse to avoid unnecessary testing. It is the responsibility of the

    user to check that the testing is up to datebefore connecting the equipment.

    2.3AUDITING

    All equipment in active use will be audited on a regular basis. For equipment in

    the Laboratory and Workshop, this auditing will occur every six months. For

    equipment in the offices, this auditing will occur annually.

    Typically, an audit will involve inspecting a subset of equipment to ensure the

    relevant procedures have been adhered to.

    During an audit (or at any other time), any equipment found not to have a valid

    test sticker, found not to meet standard practices, or found to have an obvious

    defect, must be disconnected immediately. Such equipment must not be

    reconnected until it has been tested and any problems have been rectified. The

    Safety Officer must be informed of all such equipment. In most cases, failure

    during an audit will trigger a more detailed examination of any associated

    equipment.

    2.4RIG RISK ASSESSMENT

    A Risk Assessment must always be undertaken for an experimental rig. This Rig

    Risk Assessment is normally developed by the user or potential user of the rig,

    often in consultation with previous users or other Laboratory personnel. The Rig

    Risk Assessment may draw upon details contained in the Risk Assessment forother similar rigs; when this occurs, this link should be spelt out explicitly in the

    assessment.

    The scope of this Rig Risk Assessment is not limited to electrical equipment, but

    must include the full range of mechanical, chemical, light and other potential

    hazards.

    This Rig Risk Assessment must list each of the items of electrical equipment used

    in the rig, and the date at which they are next due to be tested must be recorded.

    The Rig Risk Assessment should highlight all potential risks, safe operating

    procedures, safe methods in which the rig may be shutdown, and the risk posed

    through any equipment connected via signal or data cables. The Rig RiskAssessment must be completed before the experimental rig is first used, and

    reviewed or revised whenever there is any material change in the set-up. The

    adequacy of the Rig Risk Assessment and the overall safety of the experimental

    rig must be reviewed by an Electrical Safety Assessor prior to any work being

    undertaken.

    The Rig Risk Assessment must also contain a copy of or explicit reference to the

    Risk Assessment for any individual component that requires a separate Elemental

    Risk Assessment, and any limitations of use or recommended practice contained

    in such a separate assessment must be observed.

  • 8/6/2019 Electrical Testing Procedures

    8/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 8

    Such separate Elemental Risk Assessments are required for all discrete electrical

    components that are custom-built, modified in any way, or used in a manner or for

    a purpose differing from that envisaged by the manufacturer.

    All queries concerning electrical safety should be directed to the Director of the

    Laboratory or the Electronics Technician. The Electronics Technician will

    normally undertake any electrical tests required.

    2.5ELEMENTAL RISK ASSESSMENT

    An Elemental Risk Assessment should be completed for every custom-made or

    modified item of equipment. Elemental Risk Assessments are also required for

    standard items of equipment when such an item is to be operated in am manner

    not envisioned by the manufacturer, although such assessments may be derived

    from the manufacturers documentation.

    The Elemental Risk Assessment should indicate the potential hazards associated

    with the equipment, its intended use, the tests to which the equipment should be

    subject, the interval for testing, and verification that the Operating Procedures arevalid and appropriate. Generic Elemental Risk Assessments are permitted for

    standard laboratory items (e.g. conductivity bridges) even when there may be

    some small differences between each individual example.

    Elemental Risk Assessments for custom equipment should be reviewed at an

    interval of two years, or twice the test interval, whichever is longer. A review is

    also required whenever the equipment is modified, or it is to be used in a

    substantially different manner.

    These Elemental Risk Assessments do not replace the need for a Rig Risk

    Assessment.

    2.6OPERATING PROCEDURES

    All users should consult the Operating Procedures for an item of equipment before

    using the equipment. Moreover, if the Operating Procedures or Risk Assessment

    specifies that training is required, the use must seek and obtain this training.

    For standard commercial equipment, the manufacturers operating procedures are

    all that is required,providedthe equipment is to be used for the purpose envisaged

    by the manufacturer. Any deviation to this requires supplementary Operating

    Procedures to be developed and, potentially, an Elemental Risk Assessment.

    All custom-made equipment requires Operating Procedures to be written. These

    procedures may be developed during the first six months followingcommissioning, provided the Laboratory Safety Officer deems the user

    competent. In such cases, the user will be responsible for developing the

    Operating Procedures and will be required to submit a first draft of these

    procedures to the Laboratory Safety Officer within two months of the equipment

    being commissioned.

    Items that are identical or similar to items for which Operating Procedures already

    exist may refer to the existing procedures only after those procedures have been

    reviewed.

    Where possible, all operating procedures should be provided in both electronic

    and hard copy. Where the source documentation is electronic, both the source file

    (TEX, Word or plain text) and a PostScript or Acrobat version must be logged

  • 8/6/2019 Electrical Testing Procedures

    9/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 9

    with the Laboratory Safety Officer. Electronic copy in Acrobat format may be

    created from hardcopy by the use of a suitable scanner.

    2.7STANDARD PROCEDURES

    This section lists various standard procedures that must be adhered to for the

    majority of equipment. If any of these procedures is to be waived, the reasons fordoing so and the associated risks must be discussed explicitly in the Rig Risk

    Assessment.

    Spills of water are inevitable in the laboratory. If such spills occur over or close to

    electrical or electronic equipment then this represents a serious risk of

    electrocution. The standard procedures listed here will help reduce the risk to an

    acceptable level.

    2.7.1 Positioning of Equipment

    Mains operated equipment must be positioned where it is not subject to splashes,

    chemicals spills, or other potentially hazardous contamination.When located above water (or any other fluid), it must be fastened in such a way

    to prevent any chance of it falling into the fluid. Where possible, avoid mounting

    any item below a source of water. If this is unavoidable (e.g. some electric motors

    or pumps) careful consideration must be given to minimise the chance of the

    water reaching live connections.

    The equipment must not be located where it is likely to fall or otherwise suffer

    mechanical damage. Where necessary, the technicians will make special brackets

    to hold the equipment securely.

    2.7.2 RCD Protection

    All equipment should be connected to the mains only through a Residual Current

    Device (RCD). These devices are designed to immediately cut the supply as soon

    as any imbalance occurs between the live and neutral wires, or when any current

    is detected in the earth wire. Note that this does not completely remove the chance

    of electrocution, but does decrease it significantly.

    The RCD should be installed as the first component when connecting to the

    mains. Where possible, wall-mounted RCD sockets should be employed. If this is

    not possible, RCD plugs or RCD adapters (in that order of preference) should be

    used. There is no harm (but also no advantage) in having more than one RCD in

    the circuit to a given item of electrical equipment.

    RCDs should be checked at least once a month using their integrated test

    facility.

    Computer equipment may be connected without an RCD unless there is a chance

    that it may be exposed to splashes. As a rule, computer equipment should always

    be located where there is no chance of such exposure. Note, however, that if the

    computer is in any way connected to a probe or control circuit, then an RCD is

    required.

    2.7.3 Switching

    Never turn off, connect or disconnect equipment when your hands are wet, orwhen standing on a wet floor.

  • 8/6/2019 Electrical Testing Procedures

    10/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 10

    Similarly, do not operate equipment with wet hands or when you are in contact

    with water unless the equipment has been designed to allow safe operation when

    wet. In such cases, the need for such operation and the risks involved must be

    assess in the Risk Assessment.

    Ensure the power to the equipment may be safely shut off in the event of an

    accident. This should be marked clearly as it may be necessary for someone

    unfamiliar with the equipment or rig to do so.

    Any cut-out switch should be of a type that may be operated safely with wet

    hands. Operation of the cut-out switch should be tested at six-month intervals.

    2.7.4 Extension leads and plug boards

    Extension leads and plug boards may be used to provide a suitable number and

    location of electrical sockets.

    No more than one additional plug board may be connected to a plug board.

    The total electrical load on the plug board must not exceed the rating of the plugboard, and the total electrical load on a given double socket must not exceed 20A.

    Plug boards must be positioned where there is no danger of them being splashed,

    stood on, or likely to be immersed in the event of an accidental spillage.

    Cables leading both too and from the plug board must be kept tidy and routed to

    ensure they do not represent a risk of entanglement. Cables must not be under

    strain, and nor should they be of excessive length.

    Double adapters must never be used.

    2.7.5 Earth bonding

    All permanent and substantial equipment containing exposed metalwork must be

    earth bonded. Earth bonding consists of providing wires, straps or other direct

    electrical connection between each piece of metal, and connecting this into a good

    earth.

    The Electrical Safety Assessor will check the integrity of these connections.

    2.7.6 Submersible equipment

    Submersible equipment such as pumps and immersion heaters must only should

    preferably be used in tanks where a suitable route to earth is provided. This route

    to earth may be provided by an earth connection on the submersible unit, by earth

    bonding of metal work exposed to the water, or by the insertion of an earthelectrode into the tank.

    If the earth connection is provided by a separate electrode, then this electrode

    should be positioned so that it has at least 200mm2

    contact with the working fluid

    when the fluid is at the lowest level likely to be encountered.

    The earth electrode must be kept clean and free from corrosion. It is

    recommended that the electrode be constructed from stainless steel and is located

    at the bottom of a tank side wall (location on the tank floor may allow an

    insulating layer of particles to form on top of the electrode).

    The earth electrode must be connected to a suitable earth. For fixed installations,this should be a permanent route to earth. For moveable equipment, it is

  • 8/6/2019 Electrical Testing Procedures

    11/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 11

    recommended that the connection be made through the same RCD-protected

    circuit as the electrical equipment used with the tank. This connection may be

    through a dedicated earth terminal on the electrical equipment, or using an

    adapted earth-only mains plug inserted into a socket.

    2.7.6.1 Faults

    Any instances of blown fuses either in the plugs or in the equipment must be

    reported to the Electronics Technician. The equipment must be inspected by the

    Technician to ascertain the causepriorto the fuse being replaced.

    Any instances of the local RCD tripping must be reported to the Electronics

    Technician. All the equipment on the circuit that tripped, or any other equipment

    connected to this through signal cables, must be inspected by the Technician to

    ascertain the causepriorto any of the equipment on the tripped circuit being used

    again.

    Any instances of thermal cut-outs operating must be reported to the Electronics

    Technician. The equipment must be inspected by the Technician to ascertain thecausepriorto any of the equipment being used again.

    2.8DISPOSAL

    If an item of equipment is sold, given away or otherwise disposed of, the

    equipment must be marked with a sticker stating that it has not been electrically

    tested and that it is the recipients responsibility to ensure the electrical safety

    before use. In the case of any equipment disposed of through the rubbish, the plug

    must be cut off.

    2.9PEOPLE

    2.9.1 User

    For the purposes of this document, the User is the person or group of people who

    will make direct use of the equipment. In the case of a group, every member must

    understand any limits or procedures imposed by the Risk Assessment or

    Operational Procedures.

    2.9.2 Electrical Safety Assessor

    The Electrical Safety Assessor is required to assess the safety (or otherwise) of an

    experimental rig as a whole. The Director of the Fluid Dynamics Laboratory will

    appoint appropriate Assessors once he is satisfied of their competence to

    undertake this task.

    The Electronics Technician is an Electrical Safety Assessor.

    3 Tests

    This section outlines the various standard tests that may be performed on

    electrical and electronic equipment. Additional tests for certain categories of

    equipment are detailed under the documentation for that equipment.

    3.1BRAND NEW EQUIPMENT

    Brand new equipment must be tested or, if it carries the appropriate certification

    (e.g. a CE mark), may be deemed safe based that certification, provided the levelof testing required for that certification is at lease comparable with the procedures

  • 8/6/2019 Electrical Testing Procedures

    12/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 12

    laid out in this document. If the equipment is deemed safe based on the

    manufacturers testing then the test sticker should be completed with New in

    place of the date tested, and with an appropriate date entered for the date the next

    test is due. All equipment processed in this manner must be logged and the record

    sheet must indicate that no tests were undertaken.

    3.2EQUIPMENT FROM OTHER SOURCES

    Equipment that has been tested by another source (e.g. another department in the

    University) should be inspected by someone authorised to undertake electrical

    testing. If such equipment appears to be in good order and the tester is satisfied

    that the test procedures the equipment has been subjected to previously are

    adequate, then the equipment may be handled in a manner similar to that for brand

    new equipment. The date for the next test should be calculated based on the

    information contained on the existing sticker. If this produces a different date for

    the next test than is indicated on the existing sticker, then the earlier of the two

    dates must be selected. All equipment processed in this manner must be logged

    and the record sheet must indicate that no tests were undertaken.

    3.3STANDARD TESTS

    3.3.1 Cable damage

    Visual inspection.

    Any cuts, abrasions, distortions or bad kinks in the cable, or damage to the

    connectors, are to be rectified by replacing the cable. This work must be carried

    out before proceeding with any of the other tests.

    The integrity of the cable clamps should be confirmed at both ends of the cable.

    Any fault or inadequacy found is to be rectified.

    3.3.2 Casing damage and condition

    Visual inspection.

    Any damage to the equipment case should be mended and a risk assessment

    undertaken on the adequacy of the repair. When the casing cannot be repaired to

    an acceptable standard, the casing must be replaced or the equipment

    decommissioned.

    Ventilation slots, heat sinks and fans must be clear of obstruction.

    Any build-up of dust or grease must be removed.

    3.3.3 Fuse rating

    Visual inspection.

    The rating of the fuse in the plug must not exceed the rating of the associated

    cable.

    The type and rating of any user-replaceable fuse in the equipment must be in

    accordance with the manufacturers specification.

    3.3.4 Earth bond

    If not double-insulated.

  • 8/6/2019 Electrical Testing Procedures

    13/51

  • 8/6/2019 Electrical Testing Procedures

    14/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 14

    actually submersed, and confirmation of earth terminals and routes to earth for

    probes. Recommended supplementary tests for each category of equipment are

    listed in 7.

    4 Documentation

    4.1RECORD SHEET

    The test record sheet for every item should be completed. If an item fails, this

    should be recorded, along with details of the cause of failure. Details of the

    remedy should also be recorded.

    Any item that deviates from the expected performance (e.g. the operational

    current), must be noted along with the conditions under which the deviation was

    found. Future tests should always include assessing whether this level of deviation

    has changed.

    When a record sheet is changed, it must be moved to the Updated folder. At

    regular intervals, the details in this folder will be added to the database and thecorresponding sheets returned to the main folder.

    If an item is disposed of, the record sheet should be removed from the main series

    and transferred into the Decommissioned folder. The reason for

    decommissioning should be recorded.

    4.2TEST STICKER

    Every item passing the test procedures should be marked with an appropriate test

    sticker indicating the initials of the person responsible for the test, the date tested,

    and the date the next test is due.

    Cables and equipment must both have test stickers attached, unless the cable is anintegral (non-removable) part of the equipment. For the cable, the test sticker

    should be located close to the mains plug. For the equipment, the test sticker

    should be located in such a position that it is obvious to anyone attempting to

    operate the equipment.

    An item failing the test should be immediately removed from service and a

    Failed Electrical Test Do Not Use notice attached to the plug and over the face

    of the item.

    4.3DATABASE

    The database should reflect the contents of the Record Sheets and tie thisinformation in with the main equipment inventory, operation manuals and risk

    assessments.

    The database should be updated at regular intervals (at least quarterly) from the

    Record Sheets contained in the Updated folder. Once the details contained by an

    updated Record Sheet has been transferred to the database, the sheet should be

    marked and returned to the main folder.

    Once a quarter, the database should be used to generate a list of equipment for

    which a test is over due, and a list of tests due in the coming quarter.

  • 8/6/2019 Electrical Testing Procedures

    15/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 15

    5 Office Equipment

    5.1OFFICE APPLIANCES

    5.1.1 Desk lamps

    Elements of risk assessmentLocation.Proximity to combustible material.Routing of cable.Test interval

    Three years.Tests required

    Standard tests.Switch.

    5.1.2 Fans

    Elements of risk assessment

    Location.Routing of cable.Stability.Test interval

    Three years.Tests required

    Standard tests.Finger guards.

    5.1.3 Heaters

    Elements of risk assessment

    Location.Routing of cable.

    Stability.Proximity to flammable materials.Test interval

    Three years.Tests required

    Standard tests.Finger guards.Tilt switch.

  • 8/6/2019 Electrical Testing Procedures

    16/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 16

    5.2KITCHE AND CLEANING

    5.2.1 KettlesManual kettles are not permissible.

    Elements of risk assessment

    Location.Routing and length of cable.Stability.Proximity to flammable materials.Test interval

    Three years.Tests required

    Standard tests.Automatic turn off.

    5.2.2 MicrowavesManual kettles are not permissible.

    Elements of risk assessment

    Location.Routing and length of cable.Operator instructions.Suitable cooking implements.Cleanness.Test interval

    Three years.Tests required

    Standard tests.Timer.

    5.2.3 Vacuum cleaners

    Elements of risk assessmentDry or wet and dry usage.Period of operation.Storage location.Dust filtering.Use with toner spillages.Test interval

    One year.Tests requiredStandard tests.

  • 8/6/2019 Electrical Testing Procedures

    17/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 17

    RCD plug (if wet and dry ability).5.3ITEQUIPMENT

    5.3.1 Computers

    Elements of risk assessmentLocation.

    Ergonomics.

    Routing of cables.Power and data.

    Interchangeable power cables.These must be designated explicitly to the associated IT item and not

    interchanged with any other cable. The 13A mains plug must be clearly

    marked as to which item it belongs to. It is recommended that the IEC

    connector is also marked. The cable must carry a test sticker and be re-tested

    at the same time as the computer. If either the cable or the computer has a teststicker that is out of date, then both must be re-tested.

    Test interval

    Three years.Tests required

    Standard tests.Cable.Dust.

    Fan operational.Obstruction of ventilation.Internal operational temperatures (where motherboard/BIOS provide these).

    5.3.2 Computer monitors

    Elements of risk assessment

    Routing of cables.Adequacy of ventilation.Refresh rate and interference.Stability and crispness of picture.Ambient illumination.Ergonomics.Interchangeable power cables.

    These must be designated explicitly to the associated IT item and not

    interchanged with any other cable. The 13A mains plug must be clearly

    marked as to which item it belongs to. It is recommended that the IEC

    connector is also marked. The cable must carry a test sticker and be re-tested

    at the same time as the monitor. If either the cable or the monitor has a test

    sticker that is out of date, then both must be re-tested.

  • 8/6/2019 Electrical Testing Procedures

    18/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 18

    Test interval

    Three years.Tests required

    Standard tests.Obstruction of ventilation.

    5.3.3 Laptops

    Elements of risk assessment

    Damage due to transportation.Especially of power cables and power supplies.

    Connection to other standards.Any adapters should be tested.

    Test interval

    One year.Tests required

    Standard tests.Cable.Adapter.

    5.3.4 Printers

    Elements of risk assessment

    Adequacy of ventilation.

    Toner spillage.Interchangeable power cables.

    These must be designated explicitly to the associated IT item and not

    interchanged with any other cable. The 13A mains plug must be clearly

    marked as to which item it belongs to. It is recommended that the IEC

    connector is also marked. The cable must carry a test sticker and be re-tested

    at the same time as the printer. If either the cable or the printer has a test

    sticker that is out of date, then both must be re-tested.

    Test interval

    Three years.Tests required

    Standard tests.Cable.Obstruction of ventilation.Filters.Internal dust and toner.

    5.3.5 Data hubs

  • 8/6/2019 Electrical Testing Procedures

    19/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 19

    Elements of risk assessment

    Routing of cables.Test interval

    Three years.Tests required

    Standard tests.5.4COMMUNICATION EQUIPMENT

    5.4.1 Answerphones and dictation machines

    Elements of risk assessment

    Location.Ergonomics.

    Routing of cables.

    Test interval

    Three years.Tests required

    Standard tests.5.4.2 Fax machines

    Elements of risk assessment

    Location.Ergonomics.

    Routing of cables.Test interval

    Three years.Tests required

    Standard tests.5.5REPRODUCTION EQUIPMENT

    5.5.1 PhotocopiersThe testing of this equipment is part of the Service Contract for this equipment.

    Elements of risk assessment

    Adequacy of ventilation.Toner spillage.Test interval

    As recommended in Service Contract.Tests required

    As recommended in Service Contract.5.5.2 Binders

  • 8/6/2019 Electrical Testing Procedures

    20/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 20

    Elements of risk assessment

    Location.Test interval

    Three years.Tests required

    Standard tests.Finger guards.

    5.6PROJECTION EQUIPMENT

    5.6.1 Slide projectors

    Elements of risk assessment

    Routing of cables.Dazzle of lecturer.Test interval

    Three years.Tests required

    Standard tests.Fan & ventilation slots.Procedure for replacing bulb.

    5.6.2 Overhead projectors

    Elements of risk assessment

    Routing of cables.Dazzle of lecturer.Test interval

    One year.Tests required

    Standard tests.

    Fan & ventilation slots.Procedure for replacing bulb.

    5.6.3 Data projectors

    Elements of risk assessment

    Routing of cables.Dazzle of lecturer.Test interval

    Three years.

  • 8/6/2019 Electrical Testing Procedures

    21/51

  • 8/6/2019 Electrical Testing Procedures

    22/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 22

    Availability of low-voltage alternative.Test interval

    Three years if in Office.Two years if in Laboratory.Tests required

    Standard tests.Switch.

    7.1.2 Fans

    Elements of risk assessment

    Location.Stability.Test intervalThree years if in Office.Two years if in Laboratory.Tests required

    Standard tests.Finger guards.

    7.1.3 Vacuum cleaners

    Elements of risk assessment

    Dry or wet and dry usage.Use in wet environment.Period of operation.Unattended operation.Test interval

    One year.Tests required

    Standard tests.RCD plug (wet and dry).

    7.2LABORATORY APPLIANCES

    7.2.1 Densitometer

    Elements of risk assessment

    Frequency of relocation.Test interval

    Three years.Tests requiredStandard tests.

  • 8/6/2019 Electrical Testing Procedures

    23/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 23

    Dust in heater/cooler unit.Leaks.

    7.2.2 Refrigerator

    Elements of risk assessment

    Nature of contents.Location of electrics in event of leakage.Test interval

    Three years.Tests required

    Standard tests.Dust on condenser & compressor.

    Corrosion damage.Warning notices.

    7.2.3 Freezer

    Elements of risk assessment

    Nature of contents.Use: storage or experiment.Risk of damage from experiments.Location of electrics in event of leakage.Test intervalTwo years.Tests required

    Standard tests.Dust on condenser & compressor.Corrosion damage.Warning notices.Temperature within acceptable range.

    7.3ITEQUIPMENT

    7.3.1 Computers

    Elements of risk assessment

    Office or Laboratory location.Location relative to experiments.Risk of splashing.Connection to control or measurement circuits.Connection to data ports and other computer peripherals.

  • 8/6/2019 Electrical Testing Procedures

    24/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 24

    Test interval

    Three years.Tests required

    Standard tests.Dust.Fan operational.Obstruction of ventilation.Internal operational temperatures (where motherboard/BIOS provide these).

    7.3.2 Computer monitors

    Elements of risk assessment

    Office or Laboratory location.Location relative to experiments.Risk of splashing.Adequacy of ventilation.Refresh rate and interference.Stability and crispness of picture.Ambient illumination.Ergonomics.Test interval

    Three years.Tests required

    Standard tests.Obstruction of ventilation.

    7.3.3 Printers

    Elements of risk assessment

    Office or Laboratory location.Risk of splashing.

    Adequacy of ventilation.Test interval

    Three years.Tests required

    Standard tests.Obstruction of ventilation.Filters.Internal dust and toner.

    7.3.4 Data hubs

  • 8/6/2019 Electrical Testing Procedures

    25/51

  • 8/6/2019 Electrical Testing Procedures

    26/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 26

    Risk of splashing.Adequacy of ventilation.Stability and crispness of picture.Equipment stacks.

    Video monitors are often positioned directly on top of VTRs. While thispractice is acceptable, it is not acceptable to subsequently position any further

    equipment or items on top of the video monitor.

    Test interval

    Three years.Tests required

    Standard tests.Obstruction of ventilation.

    7.4.3 Video timersElements of risk assessment

    Location relative to experiments.Risk of splashing.Adequacy of ventilation.Test interval

    Three years.Tests required

    Standard tests.Obstruction of ventilation.

    7.4.4 High-speed cine camera

    Elements of risk assessment

    Location relative to experiments.Risk of splashing.Trip hazard from stand.Test interval

    Three years.Tests required

    Standard tests.7.4.5 Video cameras

    Most video cameras operate on a low voltage, using either batteries or an

    external power supply. The present section deals only with those cameras

    having a direct connection to the mains supply.

    Elements of risk assessment

    Location relative to experiments.Risk of splashing.

  • 8/6/2019 Electrical Testing Procedures

    27/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 27

    Adequacy of mounting arrangements.Test interval

    Two years.Tests required

    Standard tests.7.4.6 Camera power supplies

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.Risk of mechanical damage.Adequacy of physical attachment.

    This is particularly relevant on turntables.

    Test interval

    Two years.Tests required

    Standard tests.Obstruction of ventilation.Damage to low voltage cable.

    7.5LIGHT SOURCES

    7.5.1 Projectors

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.Risk of mechanical damage.Proximity to flammable materials.Adequacy of physical attachment.

    This is particularly relevant on turntables, tripods and when light sources are

    mounted in any orientation other than sitting on a bench.

    Control of stray light.Even the relatively low intensities from a standard slide projector represent a

    hazard, both directly to the eyes, and through dazzling laboratory users.

    Measures must be taken to ensure no light causes a risk or inconvenience to

    other Laboratory users.

    Test interval

    Two years.Tests required

    Standard tests.

    Obstruction of ventilation.

  • 8/6/2019 Electrical Testing Procedures

    28/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 28

    Operation of fan.Integrity of tripod plate or other mounting system.

    7.5.2 Photographic lamps

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.Risk of mechanical damage.Proximity to flammable materials.Risk to user of casing temperature.

    These lamps run very hot. The case is fitted with a thermal cut-out to switch

    the lamp off if the case temperature exceeds 150oC, but this temperature is still

    sufficiently high to burn a user trapped against the lamp.

    Adequacy of ventilation.These lamps should not have their fans or ventilation slots hindered in any

    way.

    Adequacy of physical attachment.Control of stray light.

    The high intensities from these lamps represent a serious hazard, both directly

    to the eyes, and through dazzling laboratory users. Measures must be taken to

    ensure no light causes a risk or inconvenience to other Laboratory users. Non-

    combustible materials must be used for any shielding closer to the lamp than

    500mm. All shielding must be secured firmly and designed to prevent any

    hindrance to the air flow through the lamp.

    Can low voltage lamps or light sources in other locations be used instead?The typical location of these turntable lamps exposes the user to greater risk

    than would be the case if the lighting was provided by low voltage lamps or

    provided from a remotely mounted lamp.

    Test interval

    Two years.Tests required

    Standard tests.

    Obstruction of ventilation.Case temperature.

    7.5.3 Turntable lamps

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.Risk of mechanical damage.Risk of injuring entangling user.

    These lamps are intended for mounting on a turntable. As such, they willnormally be in motion relative to the user, introducing additional potential

    hazards.

  • 8/6/2019 Electrical Testing Procedures

    29/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 29

    Proximity to flammable materials.Adequacy of physical attachment.Control of stray light.

    Even the relatively low intensities from a standard slide projector represent a

    hazard, both directly to the eyes, and through dazzling laboratory users.

    Measures must be taken to ensure no light causes a risk or inconvenience to

    other Laboratory users.

    Can low voltage lamps or light sources in other locations be used instead?The typical location of these turntable lamps exposes the user to greater risk

    than would be the case if the lighting was provided by low voltage lamps or

    provided from a remotely mounted lamp.

    Test interval

    Two years.Tests required

    Standard tests.7.5.4 Fluorescent lamps

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.Risk of mechanical damage.

    The fluorescent tubes are particularly susceptible to breakage. Moreover, if

    broken, they represent a greater hazard due to the cocktail of fluorescent

    materials they contain.

    Proximity to flammable materials.Fluorescent lamps run relatively cool and may safety be used much closer to

    flammable materials than most other light sources. However, it is important

    that adequate ventilation be maintained when doing so.

    Adequacy of physical attachment.Can low voltage lamps or light sources in other locations be used instead?

    It is sometimes necessary to locate these lamps below an experimental

    apparatus, thus exposing the lamps to a significantly increased risk from leaks

    and splashes. The possibility of using low voltage lamps or other remote

    sources of light should be considered.

    Test interval

    Two years.Tests required

    Standard tests.Diffusers and end caps.

    The diffuser and end caps provide part of the protection to the tube and

    electrics within the lamp. The diffuser and end caps, or a suitable alternative

    arrangement, must be secure and intact.

    Temperature.

  • 8/6/2019 Electrical Testing Procedures

    30/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 30

    The operational temperature, when the lamp has been left on for a number of

    hours, should be checked if air flow around the lamp is hindered in any way.

    7.5.5 Light boxes

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.Risk of mechanical damage.Test interval

    Two years.

    Tests required

    Standard tests

    7.5.6 Arc lampsThe xenon arc lamps consist of a separate power supply and lamp unit. The

    power supply generates both very high voltages (30kV) for striking the arc,

    and high currents (at relatively low voltages) for maintaining the arc. For

    most of the units, the power supply and lamp unit are permanently wired

    together, but for one it is possible to disconnect the two.

    Elements of risk assessment

    Location relative to experiments.The relatively short length of the cables connecting the lamp unit to the power

    supply can cause difficulty. It is important to ensure that this cable is not put

    under any significant strain, and that both the lamp and the power supply aremounted in a secure fashion in a safe location.

    Risk of splashing or leaks.These lamps use very high voltages (30kV) to strike the ark. Any splashes or

    moisture may lead to the user being exposed to these voltages.

    Risk of mechanical damage.The cables and terminals connecting the lamps and power supplies are

    particularly vulnerable. Due to the high voltages associated with striking the

    ark, it is extremely important that the insulation remains intact.

    Proximity to flammable materials.The collimated or focused light produced by the arc lamps is potentiallyextremely hot and capable of igniting most flammable materials if placed

    within 500mm of the lamp. The use of a cold mirror or cold window to filter

    the heat from the light reaching an experiment is strongly recommended.

    Adequacy of ventilation.These lamps and their power supplies must not have their fans or ventilation

    slots hindered in any way.

    Adequacy of physical attachment.Both the power supply and lamp unit need to be attached securely.

    Control of stray light.The high intensities from these lamps represent a serious hazard, both directlyto the eyes, and through dazzling laboratory users. Measures must be taken to

  • 8/6/2019 Electrical Testing Procedures

    31/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 31

    ensure no light causes a risk or inconvenience to other Laboratory users. Non-

    combustible materials must be used for any shielding closer to the lamp than

    500mm. All shielding must be secured firmly and designed to prevent any

    hindrance to the air flow through the lamp.

    Can low voltage lamps or light sources in other locations be used instead?The typical location of these turntable lamps exposes the user to greater riskthan would be the case if the lighting was provided by low voltage lamps or

    provided from a remotely mounted lamp.

    Test interval

    One year.This short test interval is required due to the presence of the high voltages

    associated with striking the arc.

    Tests required

    Standard tests.Obstruction of ventilation of power supply.Obstruction of ventilation of lamp.Check cable to lamp.Check and clean cable terminals/connectors.

    7.5.7 Strobe lights

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.Risk of mechanical damage.Adequacy of physical attachment.Control of stray light.

    The high intensities from these lamps represent a serious hazard, both directly

    to the eyes, and through dazzling laboratory users. Measures must be taken to

    ensure no light causes a risk or inconvenience to other Laboratory users.

    Test interval

    Two years.Tests requiredStandard tests.

    7.6LASERS

    Not currently in use. Secured under lock and key.

    7.7POWER SUPPLIES

    7.7.1 Bench supplies

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.

  • 8/6/2019 Electrical Testing Procedures

    32/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 32

    It is often possible and desirable to locate the power supplies well clear of the

    experiment, bringing only low-voltage connections through to the experiment.

    Adequacy of ventilation.Adequacy of physical attachment.

    When the supply is integrated into an experimental rig such as a rotating table,

    it is essential that it is firmly attached.

    Low-voltage route to earth.Under most circumstances the low voltage side of the power supply should be

    earth-referenced. This will ensure that, in the event of power supply failure,

    the equipment will remain safe. This earth referencing is most conveniently

    achieved at the power supply itself; often power supplies have an earth

    terminal and a removable strap between this and either the positive or

    negative side. If connection to earth is not possible or not desirable (e.g. to

    avoid earth loops), then an earth point should still be provided somewhere in

    the equipment.

    Test interval

    Two years.Tests required

    Standard tests.Obstruction of ventilation.Earth terminal.

    7.7.2 Plug-in adapters

    Elements of risk assessmentLocation relative to experiments.Risk of splashing or leaks.

    It is often possible and desirable to locate the power supplies well clear of the

    experiment, bringing only low-voltage connections through to the experiment.

    Adequacy of ventilation.Free movement of air around the adapter must be maintained. As most

    adapters have internal temperature fuses, failure to observe this is likely to

    lead to the adapter ceasing to function. Note that under normal circumstances

    the Laboratory will not attempt to repair any plug-in adapters following

    failure of this fuse.

    Test interval

    Two years.Tests required

    Standard tests.Low voltage cable insulation.

    7.7.3 High voltage suppliesThis category of equipment is for power supplies generating voltages in excess

    of mains voltages. Where at all possible, alternative solutions not requiringsuch voltages should be employed.

  • 8/6/2019 Electrical Testing Procedures

    33/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 33

    Elements of risk assessment

    Location relative to experiments.The presence of high voltages, the generation of interference and the need to

    keep cables relatively short complicate the location of high voltage supplies. It

    is critical that the high voltage cables are not put under strain and do not run

    through an area where they are likely to suffer damage or be exposed to

    electrolytes.

    Risk of splashing or leaks.Any splashes or moisture may lead to the user being exposed to these voltages.

    Risk of mechanical damage.The high voltage cables are especially sensitive and prone to damage. Where

    these cables must be exposed, they should be provided with some for of

    covering or armouring. The cables and terminals connecting the lamps and

    power supplies are particularly vulnerable. Due to the high voltages

    associated with striking the ark, it is extremely important that the insulation

    remains intact.

    Adequacy of physical attachment.The power supply, cables and any associated equipment need to be attached

    securely.

    Can low voltage equipment be used instead?Where possible, low voltage equipment should be used instead. Where only

    high-voltage equipment is feasible, the reasons behind this must be given

    explicitly in the Risk Assessment.

    Test interval

    One year.Tests required

    Standard tests.Check HV insulation.

    7.8LABORATORY INSTRUMENTATION

    7.8.1 Amplifiers

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.Adequacy of physical attachment.Earth for probes.

    Probe casings should normally be earthed. If this is not possible, or not

    desirable (e.g. due to the formation of earth loops), a separate earth

    electrode must be incorporated into the design of the apparatus.

    Risk to/from attached equipment.What risks might the user be exposed to if any attached equipment fails? Does

    failure of this equipment have other vectors with potential risk (e.g. probes).

    Test intervalTwo years.

  • 8/6/2019 Electrical Testing Procedures

    34/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 34

    Tests required

    Standard tests.Input/output isolation.

    7.8.2 Bridge circuits

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.Adequacy of physical attachment.Earth for probes.

    Probe casings should normally be earthed. If this is not possible, or not

    desirable (e.g. due to the formation of earth loops), a separate earth

    electrode must be incorporated into the design of the apparatus.

    Risk to/from attached equipment.What risks might the user be exposed to if any attached equipment fails? Does

    failure of this equipment have other vectors with potential risk (e.g. probes).

    Test interval

    Two years.Tests required

    Standard tests.Probe isolation.

    7.8.3 MultimetersBattery-powered multimeters should also be tested.

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.Adequacy of physical attachment.Probe insulation.

    This must be adequate to withstand the maximum voltage present on the

    experimental rig, not just the voltage that is to be measured.

    Test intervalTwo years.Tests required

    Standard tests.Probe isolation.

    7.8.4 Oscilloscopes

    Elements of risk assessment

    Location relative to experiments.By use of probe cables of a suitable length, the location of the oscilloscopeneed not be close to the experiment.

  • 8/6/2019 Electrical Testing Procedures

    35/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 35

    Risk of splashing or leaks.Adequacy of physical attachment.Probe insulation.

    This must be adequate to withstand the maximum voltage present on the

    experimental rig, not just the voltage that is to be measured.

    Test interval

    Two years.Tests required

    Standard tests.Probe isolation.

    7.8.5 High voltage equipmentThis category of equipment is for equipment utilising voltages in excess of

    mains voltages. Where at all possible, alternative solutions not requiring such

    voltages should be employed.

    Elements of risk assessment

    Location relative to experiments.The presence of high voltages, the generation of interference and the need to

    keep cables relatively short complicate the location of high voltage supplies. It

    is critical that the high voltage cables are not put under strain and do not run

    through an area where they are likely to suffer damage or be exposed to

    electrolytes.

    Risk of splashing or leaks.Any splashes or moisture may lead to the user being exposed to these voltages.This will occur at much lower levels of contamination than for standard

    voltage equipment.

    Risk of mechanical damage.The high voltage cables are especially sensitive and prone to damage. Where

    these cables must be exposed, they should be provided with some for of

    covering or armouring. The cables and terminals connecting the lamps and

    power supplies are particularly vulnerable. Due to the high voltages

    associated with striking the ark, it is extremely important that the insulation

    remains intact.

    Adequacy of physical attachment.The power supply, cables and any associated equipment need to be attached

    securely.

    Can low voltage equipment be used instead?Where possible, low voltage equipment should be used instead. Where only

    high-voltage equipment is feasible, the reasons behind this must be given

    explicitly in the Risk Assessment.

    Test interval

    One year.Tests requiredStandard tests.

  • 8/6/2019 Electrical Testing Procedures

    36/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 36

    Check HV insulation.7.9MOTORS AND CONTROLLERS

    7.9.1 Servo motor controllers

    Elements of risk assessmentLocation relative to experiments.Risk of splashing or leaks.Adequacy of physical attachment.Earth-referencing.

    Should the motor be earth referenced, or is it safer to have it floating? Earth-

    referencing in combination with a suitable fuse, circuit breaker or RCD may

    reduce the risk associated with higher voltage servo motors.

    Test interval

    Two years.Tests required

    Standard tests.Output isolation.

    7.9.2 Servo motors

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.Adequacy of physical attachment.Risk of entanglement or injury.

    Are guards required? Have all sharp corners been removed?

    Earth-referencing.Should the motor be earth referenced, or is it safer to have it floating? Earth-

    referencing in combination with a suitable fuse, circuit breaker or RCD may

    reduce the risk associated with higher voltage servo motors.

    Test interval

    Two years.Tests required

    Standard tests.Output isolation.

    7.9.3 AC motors

    Elements of risk assessment

    Location relative to experiments.Risk of splashing or leaks.

    Adequacy of physical attachment.Risk of entanglement or injury.

  • 8/6/2019 Electrical Testing Procedures

    37/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 37

    Are guards required? Have all sharp corners been removed?

    Low voltage alternatives.Is it possible to use a low voltage motor instead?

    Test interval

    Two years.Tests required

    Standard tests.7.10PUMPS

    7.10.1 Integrated pumps

    Elements of risk assessment

    Location within experimental rig.

    Risk of splashing or leaks.What additional risks will occur if the pump leaks risks both due to the pump,

    and due to anything that may be contaminated as the result of the pump

    leaking?

    Adequacy of physical attachment.Cable routing.

    Does this take the best route available? Is it protected from mechanical

    damage? Is it possible to inspect the cable for damage?

    Switching and control.How is the pump to be controlled? Can it be shut off safely in the result of a

    leak or a detached hose?Guards.

    Some integrated pumps are not self-contained units. In such cases, the

    question of whether guards are necessary should be addressed.

    Test interval

    Two years.Tests required

    Standard tests.Check for leaks.

    7.10.2 Peristaltic pumps

    Elements of risk assessment

    Location relative to experimental rig.Risk of splashing or leaks.

    What additional risks will occur if the pump leaks risks both due to the pump,

    and due to anything that may be contaminated as the result of the pump

    leaking?

    Adequacy of physical attachment.Test intervalTwo years.

  • 8/6/2019 Electrical Testing Procedures

    38/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 38

    Tests required

    Standard tests.Check for leaks.

    7.10.3 Submersible pumps

    Elements of risk assessment

    Location within experimental rig.Adequacy of physical attachment.Route to earth.

    If the pump or cable insulation fails, the water may become live. It is desirable

    that a suitable route to earth must always be is provided, either through earth-

    bonding of metal parts of the apparatus exposed to the water, or by the

    provision of an additional earth electrode of at least 200mm2

    area, as outlined

    in 2.7.6of the standard procedures.

    RCD on mains cable.The mains cable of the submersible pump should normally be fitted with an

    RCD plug, even if this will be plugged into circuits with other RCD protection.

    Test interval

    One year.

    Tests required

    Standard tests.Optional: check insulation and/or leakage current when submerged.RCD required.

    7.10.4 Vacuum pumps

    Elements of risk assessment

    Location relative to experimental rig.Risk of splashing or leaks.Adequacy of physical attachment.Test interval

    Two years.Tests required

    Standard tests.7.10.5 Double-bucket pumps

    Elements of risk assessment

    Route to earth. All metal work on the double buckets must be earth-bonded via the earth

    provided on the pump.

    RCD on mains cable.The mains cable of the submersible pump should normally be fitted with an

    RCD plug, even if this will be plugged into circuits with other RCD protection.

  • 8/6/2019 Electrical Testing Procedures

    39/51

  • 8/6/2019 Electrical Testing Procedures

    40/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 40

    Emergency shut-off.Are the provisions for stopping the turntable in an emergency adequate? Will

    this also cut the power to the mains sockets?

    Maximum speed.Is there a limit on the maximum speed of the turntable? Is this limit safe? Who

    has the ability to change or over-ride this limit? What will happen if this limitis exceeded?

    Test interval

    Two years.Tests required

    Standard tests.RCD required.Shut-off switch.Speed limiter.

    Verify that turntable cannot be rotated faster than the maximum allowable

    speed.

    7.12LABORATORY EQUIPMENT

    7.12.1 Heat baths

    Elements of risk assessment

    Location relative to experimental rig.Risk of splashing or leaks.

    What additional risks will occur if the bath or associated tubing leaks risksboth due to the bath, and due to anything that may be contaminated as the

    result of the bath leaking?

    Temperature control.What is the effect of the temperature control circuit failing (or user error),

    resulting in temperatures either much higher or much lower than intended?

    Test interval

    Two years.Tests required

    Standard tests.Check for leaks.Check earth leakage current when full.

    7.12.2 Stirrers

    Elements of risk assessment

    Location relative to experimental rig.Risk of splashing or leaks.

    What additional risks will occur if the bath or associated tubing leaks risks

    both due to the bath, and due to anything that may be contaminated as the

    result of the bath leaking?

  • 8/6/2019 Electrical Testing Procedures

    41/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 41

    Test interval

    Two years.Tests required

    Standard tests.7.12.3 Scales

    Elements of risk assessment

    Location.Contamination by chemicals.Test interval

    Two years.Tests required

    Standard tests.7.12.4 Immersion heaters

    Elements of risk assessment

    Location within experimental rig.Risk of drying out.

    What will happen if the heater does not remain immersed?

    Route to earth. If the insulation fails, the water may become live. A suitable route to earth

    must always be provided. In most cases this will be through the metal case of

    the immersion heater. If this route is not possible, the route to earth may eitherbe through earth-bonding of metal parts of the apparatus exposed to the water,

    or through the provision of an additional earth electrode of at least 200mm2

    area, as outlined in 2.7.6of the standard procedures.

    RCD on mains cable.The mains cable of the immersion heater should normally be fitted with an

    RCD plug, even if this will be plugged into circuits with other RCD protection.

    Test interval

    Two years.Tests requiredStandard tests.Check for leaks.Check leakage current when immersed.RCD required.

    7.13FRAMEWORKS AND TANKS

    7.13.1 Metalwork

    Elements of risk assessment

    Live metalwork.

  • 8/6/2019 Electrical Testing Procedures

    42/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 42

    The metalwork of tanks may become live due to the failure of equipment, the

    incorrect connection of equipment, or as a result of stray electromagnetic

    fields. To prevent this happening, all metalwork must be connected to earth as

    described by the wiring regulations BS7671.

    A conductor with cross-section not less than 6mm2

    must connect all fixedframes to a suitable earth. Water supply pipe work may be used as the earth

    only once its continuity to earth has been adequately verified to have a

    resistance of less than 0.1.

    Moveable frameworks and tanks must be provided with a suitable earth

    terminal and lead. This earth lead must be connected to a suitable earth

    whenever the framework or tank is used in conjunction with any electrical

    equipment. It is recommended that the connection be made through the same

    RCD-protected circuit as the electrical equipment used with the framework or

    tank. This connection may be through a dedicated earth terminal on the

    electrical equipment, or using an adapted earth-only mains plug inserted intoa socket.

    Each electrically separate but mechanically integrated part of the metalwork

    must be connected with an earth strap of at least 2.5mm2

    cross-section (4mm2

    if not sheathed or mechanically protected). This earth strap may be omitted

    only when a reliable earth with a resistance of less than 0.1 is formed as an

    inherent part of the design of the framework or tank.

    Test interval

    Three years.Tests required

    Test earth bonding of all exposed metal work on frames and tanks.7.14POWER CORDS

    7.14.1 Standard cords (IEC)

    Elements of risk assessment

    Routing.Trip hazard.Location.

    In Office or Laboratory?

    Use.For computer or laboratory equipment?

    Test interval

    Three years.Tests required

    Visual inspection.

    Earth continuity.Fuse.

  • 8/6/2019 Electrical Testing Procedures

    43/51

    Electrical testing: Intervals and procedures DAMTP

    25 March 2004 43

    7.14.2 Non-standard cords

    Elements of risk assessment

    Routing.Trip hazard.Location.

    In Office or Laboratory?

    Use.For computer or laboratory equipment?

    Test interval

    Two years.Tests required

    Visual inspection.Earth continuity.Fuse.

    7.14.3 Cords with RCD

    Elements of risk assessment

    Routing.Trip hazard.Location.

    In Office or Laboratory?

    Use.For computer or laboratory equipment?Test interval

    One year.Tests required

    Visual inspection.Earth continuity.Fuse.RCD.

    7.15PLUG-BOARDS AND EXTENSION LEADS

    7.15.1 Plug-boardsPlug-boards that are not integrated permanently into an experimental set-up.

    Elements of risk assessment

    Location relative to experimental rig.Risk of splashing or le