efficacy of sa’s environmental · 2015. 1. 27. · issues raised in the report issues raised in...
TRANSCRIPT
Efficacy of SA’s Environmental
Impact Assessment (EIA)
Regime
Portfolio Committee Parliamentary Hearing
30 July 2013
1
Background • EIAs became a statutory requirement in September 1997
through Regulations 1182 and 1183 (sec 21 of Environment Conservation Act 73 of 1989 (ECA)) – Regulation 1182 identifies activities that would henceforth
require "environmental assessments“
– Regulation 1183 codified the conduct and the contents of environmental assessments.
• EIA requirement was reflected in Chapter 5 in The National Environmental Management Act 107, 1998 (NEMA) and repealed from the ECA
• In 2006 the Department initiated a study to assess the effectiveness and efficiency of the EIA tool
• Findings presented at the "10 years of EIA" Conference in Somerset West in November 2008
• The report concluded that the effectiveness of EIAs was marginal and made several recommendations as follows:
2
Issues raised in the report Issues raised in the 2008 Efficiency and Effectiveness Report • No “one size fits all” approach – e.g. housing vs nuclear power station
• EIA does not address social issues
• Not all aspects considered e.g. nuclear plant input – mining of uranium
• EIA more about procedure and administration not about sustainability
• Process flawed as EAPs are paid by applicant
• EAPs should be appointed & paid by Govt – fund to which applicants contribute
• Site specific assessment cannot address cumulative impacts – Need to use other tools – standards, EMFs, SEAs, risk assessment etc.
• Time Delays in decision making and added cost
• Capacity to review assessment documents
• Many small activities assessed – not the whole development strategic
• Public participation is not meaningful
• Excessive public participation – I&APs have all the power
• Affordability – Need to support applicants without means to comply with the EIA requirement
3
Issues raised report • Urgent requirements – e.g. industry limited due to need for storage
• Does not consider positive aspects – e.g. activity reduce climate change
• List of activities includes maintenance aspects & assessed as green
fields projects e.g. road maintenance – major cost for no reward
• Trivial reasons for appeals
• Listed activities do not consider projects within the sea
• Need to delist based on approved EMFs
• Minimal cooperation & regulatory alignment between departments
• EAPs lack technical expertise – industry use own staff & peer review
• Alternatives proposed are not realistic
• Alternatives need not be considered as applicant knows what they want
• Process just considers mitigation – “no development “ is not an option
• The advertising process should get into the digital space
• Review of projects not consistent
4
Issues raised report • Relevance of conditions & contradict other permits – beyond
mandate
• Interpretation of listed activities not consistent
• Reviewing Department not fully engaged early– late requests for additional information
• Lack of compliance monitoring
• Abuse of section 24G – development proceeds without authorisation and pay the fine
• Need a system to track authorisations & know who is dealing it
• Should be able to collect the information made available in specialist reports to create new data
• Reduce timeframes for State Departments to comment – if comments not received on time - proceed
• Need good GIS data
• Applicants should be able to access GIS data on line
• Need integrated permitting between & within Departments
5
Recommendations from the report • Requirement to ensure sustainable development
– stronger emphasis on indirect & cumulative impacts
– within strategic context – through strategic instruments e.g EMF’s, SEA’s, policies, etc.
• Strategic approach – Categorise activities ito strategic importance eg, infrastructure
needs
– through identification of geographical areas ito NEMA sec 24(2)(a) & (b)
– specific approaches for specific circumstances (e.g. tailor- made Basic Assessment pro-forma reports where activity does not require unnecessary information or assessment)
• Package of instruments – The effectiveness and efficiency can improve if they are
assessed within a context.
– The use of wide range of instruments (eg SEA) to create the required context should be explored
6
• A better screening mechanism – to provide an early “check” of sites for sensitive elements as screening by
specialists before assessments are done
• A holistic approach – Despite responsibilities allocated to the different spheres of government –
– need a holistic approach to EIM (strategic & policy & project levels) in a manner that is sensible to the strategic needs of South Africa
• Enhance the role of SEA in the development of SDFs – With better SEAs or EMFs underpinning SDFs these spatial planning
instruments can avoid unnecessary impacts at especially local level
• Compliance monitoring and enforcement – Area where current EIA is not effective or efficient.
• Delegation of decision-making – Where there are EMFs or other guidelines in place - delegation of the
authorisation of smaller activities to middle management is possible
• Human resource development – create a sustainable flow of environmental managers in a way that creates
capacity at all levels and also ensure career paths for employees
Recommendations from the report
7
2008 Conference – 10 years of EIA
• 2008 Conference resolution –
recommendations of the report would be
considered by stakeholders through a
formal process –
• Process would recommend a strategy for
IEM to government for consideration
8
Current activities being
undertaken to deal with concerns
raised
Environmental Implementation Assessment and Management
Strategy
9
Environmental Impact Assessment
and Management Strategy
• Following on from the “10 years of EIA” conference the Environmental Impact Assessment and Management Strategy has been initiated
• Process has been stakeholder driven
• Strategy also considering issues not identified in the Effectiveness and Efficiency report – e.g. independence
• Has taken 3 years to produce the findings which are expected in March 2014
10
• The EIAMS is a participatory process to compile a strategy
– provides overall context for IEM in SA within the context
of sustainable development
• The strategy will identify the desired future state for the
EIAM system and plan to achieve it.
• Desired state includes
– IEM supported by environmentally informed spatial
instruments, sector strategies and policies
– Optimizing of the regulatory system through the
introduction of a number of assessment tools - EIA being
used where it is the appropriate tool
– Integration of government processes e.g.
IDP/SDF/EMF/SEA/Zoning plans
– Capacitated sector
Purpose of the EIAMS
11
Proposed main elements for the EIAMS • All IEM processes are guided by a sustainability vision and intent
• Effective integration between spheres & govt depts – could include • Integrated permitting and authorizations
• Strategic development plans and frameworks are aligned in content timing and scale (EMF/SEA to inform SDFs)
• Mandate to Local authority - to implement national standards
• Technical tools effectively contribute to enacting of NEMA principles • Hierarchy of Environmental plans
• Tools for all management phases – increased focus on checking & acting phases
• Ability to choose the most appropriate tool
• Spatial tools to identify activities to be excluded from Environmental Authorization
• Up-to-date and readily available environmental information
• Sustainability targets identified and reported on
• Quality assurance through peer review 12
Proposed main elements for the EIAMS
• Adaptive management is informed by monitoring and evaluation of systems and processes
• Establish a professional and transformed environmental sector
• Environmental information and management system that are up to date, available and accessible to role-players
• All role-players are capacitated in terms of environmental awareness and environmental management instruments
• Understanding role of public participation and an appropriate Public participation process
13
Interim – Actions taken While the EIAMS strategy is unfolding - need for certain actions to be taken
• Restructuring of EIA function within DEA undertaken – separate EIA review from NEMA authorisation system
• Development of NEAS & public portal – tracks the progress of EIAs
• Improving statistics of assessment undertaken within timeframe
• Capacitation of provinces – implementation OSD, hardware/software provided, administration staff provided to capture data on the NEAS system
• GIS intranet and internet – spatial data to Case Officers and Applicants
• Screening tool developed to do pre-screening of issues to assist Case Officers
• Standards – Dangerous goods standards being developed, providing support to Provincial Standards – Ostrich farming, trout and abalone aquaculture
• EIA timeframe amendments & integration of permits – timeframes for submission of documents by applicant being legislated
• Integration of waste and EIA authorisations
• Drafting regulations to adopt spatial tools
• SEAs being developed to support Strategic Integrated Projects (SIPs)
14
Restructuring of Environmental
Impact Management function • The Department restructured to ensure efficiency.
The EIM Chief Directorate was split into two – Integrated Environmental Management and Integrated Environmental Assessment
• IEMS considers systems, tools and an enabling legislative system to support IEM, provides support to the 10 Competent Authorities including DEA
• IEA concentrates on improving the efficiency and review timeframes for EIAs
15
EIA review performance and
access to statistics
• National Environmental Assessment
System & Public Portal
• The system has been developed and work
is underway with the various Competent
Authorities to report accurately – to be
achieved within the 2013-3014 financial
year
16
EIAs received and reviewed / Competent
Authority from 2006
Competent
Authority
Total No. of
applications
received
No. of
applications
finalised
No. of
applications
pending
No. of
applications
pending in
time frames
Authorities) to
respond)
No. of
applications
pending out of
time frames
(Authorities) to
respond)
No. of
applications
pending within
time frames
(Awaiting
information
from the
EAP/Applicant)
No. of
applications
pending out of
time frames
(Awaiting
information
from the
EAP/Applicant)
DEA 2552 1912 640 95 14 451 80
EC 2165 1959 206 30 7 153 16
FS 637 545 92 9 0 81 2
GP 4528 4522 6 3 2 1 0
KZN 3229 2770 459 134 2 204 119
LP 2539 2321 218 40 8 127 43
MP 1958 1733 225 46 4 157 18
NC* 238 132 106 10 0 96 0
NW 1973 1845 128 16 0 101 11
WC 4017 3553 464 102 10 332 20
TOTALS 23836 21292 2544 485 47 1703 309
17
Comparison of Manual & NEAS Stats on Applications Dealt with in terms of the EIA Regs of 2010 until June 2013
Manual Stats 2010 NEAS 2010
Competent Authority Received Pending Finalised Received Pending Finalised
DEA* 1586 916 670
Eastern Cape 550 206 344 653 271 382
Free State* 280 96 184
Gauteng* 972 812 160
Kwa-Zulu Natal* 1090 1107 689 418
Limpopo* 453 211 242
Mpumalanga* 631 345 286
North West 354 140 214 344 148 196
Northern Cape 238 106 132 228 172 56
Western Cape 1276 448 828 1273 462 811
* Manual breakdown figures not provided
18
DEA applications received per quarter since April 2012 – 499/17 = 30a/a
19
DEA applications pending outside time frame per quarter since April 2012
20
EIA integrated with the WUL and
Mining right
EIA alignment, revised timeframes
and documentation
21
DMR decides upon Mining right within 50 days (10 days MLA, 10 days RM, 10 days RLC, 20 days
National Licensing ). If MR is not approved EA and WUL also not approved. If approved DWA
notified to approve as recommended). DWA sits on RLC. EA Decision made together with granting
/ Refusal of right.
Final reports received
30
0 D
AY
S
22
Proposed Process: Amendments to Regulations: BAR Process
Draft Basic Assessment
7 days : Acknowledge 40 days public participation
40
da
ys
AB
SOLU
TE M
INIM
UM
97
DA
YS
(No
n-
sub
stan
tive
)
Application
GAP
Final BAR, including Final EMPr
AB
SOLU
TE M
INIM
UM
14
7 D
AY
S (S
ub
stan
tive
)
Pre-application (Optional)
No substantive changes to Draft
Substantive changes to Draft
7 days Acknowledge Additional 50 days for PP if substantially Different from Draft 30 days Accept or Reject 20 days for decision
57
da
ys
DECISION
1
07
da
ys
Review Committee
Application for Prospecting Right
????? Mining Sustainability
Programme
Draft EMPr
23
GIS data supporting spatial applications – SEAs/EMFs
•GIS data for screening of applications on the DEA intranet,
•will become available on DEA internet within the next two months –
•applicants can determine sensitivity of a site by locating the development site and then identifying sensitivity related to different layers which can be switched on or off
24
GIS
SCREENING
TOOL
• APPLICANT
• COMPETENT
AUTHORITY
• ENVIRONMENTAL
PRACTITIONER
SPECIALIST REPORTS
Specialist reports
Spatial data
25
• Screening tool – Example of selected farm, buffer, threatened ecosystems …
GIS & Screening (cont.)
26
Set the context for EIAs through EMFs and SEAs using the
Infrastructural Development Plan as a case study
SEA process will facilitate coordination between departments, assess the cumulative effects of
developments, will consider the ecological infrastructure, reduce the numbers and
complexity of authorisations
27
Background • Government has identified that
after 18 years of democracy, poverty, unemployment and inequality is still a challenge
• The New Growth Path – sets a goal of 5 million new jobs by
2020
– Identified that poor coordination and weak integration limits the development impact of infrastructure
– identified structural problems in the economy to be overcome
– Identified opportunities in specific sectors and markets or “jobs drivers”
– the first jobs driver is infrastructure development 28
Overview of needs analysis
SIPs were selected to address the spatial imbalances of the past by addressing the needs of the poorer provinces and enabling socio-economic development.
Needs analysis done –
Indicated possible bulk
infrastructure requirements
• Electricity
• Water
• Transport
• Town planning
• Ports etc.
29
Waterberg Development Steelpoort
Development
Export Logistics
Mpumalanga Bottleneck Reduction
Moloto Corridor
Road
Electricity Generation
Transmission
Distribution
Coal to liquid
Water
Rail
Mining
Rail
Road
Water
Road
Rail
Road
Water
Rail
Regional clustering of projects linked with major corridor projects
• SIP 1: Unlocking the northern
mineral belt
Shifting from rail to road in Mpumulanga
30
Scale of projects – PV facility Brandenburg Germany
31
Authorisations response to SIPs
• Grouping of SIPS – Corridor developments –
pipelines, transmission lines – Large development projects –
ports, IDZ’s – Nodal projects and recurring
components – transport nodes – Coal based projects with
climate change and air emissions impacts – coal based industries
– Mining related projects – new mines
– Projects not requiring authorisation
• Proposed an authorisation approach using new IEM tools for each grouping
Group SIPs into similar authorisation components
32
Proposed authorisation approach
• SIP 8 – example of approach Adopting a strategic and innovative approach offered by SEA
– Identify geographical areas most suitable for the rollout of renewable energy projects
• Methodology – positive and negative mapping
– Positively map wind and solar radiation resources
– Negatively map environmental sensitivity
– Scenario analysis – trade offs – Identify site specific issues for
consideration
• Aim – Cabinet approval of corridors/zones
– all Departments buy into process – Exclude energy activities (including
the grid expansion) in the corridors/zones identified – subject to conformance to site specific protocol and EMP
– Allow opportunity to explore cooperation between authorising Departments to identify streamlined approaches
33
SEA to identify preferred development areas for specific activities – wind projects
34
Way forward
• Use SIPs process as a case study to inform the streamlining of authorisations
• Feed into learning's into the EIAMS
• Undertake the law reform process required to provide the legal provisions for the streamlined process where they do not exist
• Address all the issues raised relating to the efficiency and effectiveness of the current EIA process by ammending current legislation and developing and implementing new tools
35