ECP 11-0511a Schneider RN2, RN2c and RE2c Test Form
Schneider RN2, RN2c and RE2c Test Form
Document Number: ECP 11-0511a
Version: 5.0
Date: 27/02/2018
Schneider RN2, RN2c and RE2c Test Form
Substation Name
Substation Number
Voltage
Switchgear
Installed Mode
Free-standing
()
Transformer-mounted
()
Switchboard Number
Manufacturer
Schneider
Serial Number
Type (RN2/RN2c/RE2c)
Protection CTs
FPI CT Ratios in Use
Ratio in Use
RSW1
RSW2
TLF
Rating
Transformer Rating
kVA
Shunt Trip Coil (if fitted)
20-48V DC
()
110-240V AC/DC
()
Preliminary Checks
()
Disconnect the umbilical cable from the RTU (if fitted)
Visual inspection satisfactory (no visible signs of damage etc)
Earthing satisfactory
SF6 gas pressure satisfactory
Functional/Interlock Checks
()
Open and close switches
Earth switches cannot be operated when service selected
Switch/circuit-breaker cannot be operated when earth selected
Open and close earth switches
Test access cannot be opened when switch/circuit-breaker in On and Off position
Test access can be opened when earth switch closed
Switch/circuit-breaker cannot be operated when test access open
Motorised actuator operation satisfactory using an RTU simulator (LPN Remsdaq RTU only)
Transformer Winding Insulation Resistance using Test Voltage from ECS 11-0006 (transformer-mounted units only)
HV windings to earth (LV windings connected together and to earth)
M
LV windings to earth (HV windings connected together and to earth)
M
Switchgear Continuity Test
RSW1
RSW2
CB
Terminals Under Test
Continuity
TM*
FS*
TM*
FS*
RSW1 to RSW2
RSW1 to RSW2 to CB
Closed
Closed
Open
Closed
L1 - L1
L1 - L1 - L1
L2 - L2
L2 - L2 - L2
L3 - L3
L3 - L3 - L3
Open
Closed
L1 - L2 (RSW1)
L2 - L3 (RSW1)
RSW1
RSW2
CB
Terminals Under Test
Continuity
Earthed
Open
Open
RSW1
L1 - E
L2 - E
L3 - E
Open
Earthed
Open
RSW2
L1 - E
L2 - E
L3 - E
* TM - transformer-mounted and FS - free-standing.
HV Insulation Tests using Test Voltage from ECS 11-0006
RSW1
RSW2
CB
Terminal
Voltage (kV)
Duration (min)
IR (M)
Under Test
Earthed
TM*
FS*
RSW1
RSW2
CB(FS* only)
Closed
Closed
Open
Closed
L1
L2, L3
L2
L1, L3
L3
L1, L2
Open
L1, L2, L3
L1, L2, L3
L1, L2, L3
Closed
Open
Open
L1, L2, L3
L1, L2, L3
* TM - transformer-mounted and FS - free-standing.
FPI CTs Insulation Resistance using 1kV Test Voltage(test from CT wiring terminal block)
Disconnect FPI (if fitted)
()
RSW1
RSW2 (if fitted)
Remove CT wiring earth link
D190 - D170
()
D190 - D270
()
L1, L2, L3
D111, D131, D151 - Earth
M
D111/2, D131/2, D151/2 - earth
M
Replace CT wiring earth link
D190 - D170
()
D190 - D270
()
FPI CTs Loop Continuity(test from CT wiring terminal block)
RSW1
RSW2 (if fitted)
L1
D111 - D170
D111/2 - D170/2
L2
D131 - D170
D131/2 - D170/2
L3
D151 - D170
D151/2 - D170/2
Reconnect FPI (if fitted)
()
Figure 1 – Customer Trip Connections (18, 19 & 20)
Protection CTs Insulation Resistance using 1kV Test Voltage
Remove CT wiring earth link
C70 - C90
()
CTs, AC trip coils and TLFs
C70 - Earth
M
Replace CT wiring earth link
C70 - C90
()
Protection CTs Loop Continuity(test CT and trip coil from TLF ratio terminal block with test link removed)
Remove shorting link and test link
()
100/5 Ratio
50/5 Ratio
L1
C110 - C70
C210 - C70
L2
C130 - C70
C230 - C70
L3
C150 - C70
C250 - C70
Replace shorting link and test link
()
C110-C130-C150-C70-C210-C230-C250
100/5 50/5
Test Link
C90-C70
Primary Injection Test (free-standing units only)
Earth Fault Release Test
Remove TLFs and replace with shorting links
()
RSW1
RSW2
CB
Conductors Under Test
CT Ratios
RN2 Trip Range
RN2c Trip Range
Trip Current
RSW1
CB
Closed
Open
Closed
L1
L1
50/5
20 - 26.5A
19 - 28A
A
100/5
25 - 31A
24 - 33A
A
L2
L2
50/5
20 - 26.5A
19 - 28A
A
100/5
25 - 31A
24 - 33A
A
L3
L3
50/5
20 - 26.5A
19 - 28A
A
100/5
25 - 31A
24 - 33A
A
Overcurrent Release Test
Remove TLF shorting-links, connect shorting-link between L1, L2, L3 on CB
()
RSW1
RSW2
CB
Conductors Under Test
Short Conductors
CT Ratios
RN2 Trip Range
RN2c Trip Range
Trip Current
RSW1
CB
Closed
Open
Closed
L1 – L2
L1, L2, L3
50/5
20 - 25A
20 - 25A
A
100/5
30 - 36A
30 - 36A
A
L2 - L3
L1, L2, L3
50/5
20 - 25A
20 - 25A
A
100/5
30 - 36A
30 - 36A
A
Secondary Injection Test (transformer-mounted units only)
Earth Fault Release Test
Remove TLFs and replace with shorting links
()
RSW1
RSW2
CB
Test Connections
CT Ratios
RN2 Trip Range
RN2c Trip Range
Trip Current
Open
Open
Closed
C31 - C70
50/5
2 - 2.65A
1.7 - 2.8A
A
100/5
1.25 - 1.55A
1.1 - 1.65A
A
Overcurrent Release Test
Remove shorting links
()
RSW1
RSW2
CB
Test Connections
CT Ratios
RN2 Trip Range
RN2c Trip Range
Trip Current
Open
Open
Closed
C11 - C31
50/5
1.6 - 2.2A
1.6 - 2.2A
A
100/5
1.4 - 2.0A
1.4 - 2.0A
A
C31 - C51
50/5
1.6 - 2.2A
1.6 - 2.2A
A
100/5
1.4 - 2.0A
1.4 - 2.0A
A
Note: If the circuit-breaker does not operate when the injected current is gradually applied then the maximum value of current should be applied instantaneously.
Shunt Trip and Emergency Trip (if fitted)
Check correct shunt trip coil voltage is selected
()
Test
Coil
Terminals
Test Voltage
CB Trips
Apply 70% (dc) or 85% (ac) of coil rated voltage
20-48V DC
47 - 48
V
()
110-240V AC/DC
47 - 49
V
()
Apply 110% Voltage of coil rated voltage
20-48V DC
47 - 48
V
()
110-240V AC/DC
47 - 49
V
()
Check emergency trip button operates circuit-breaker
()
Final Checks
()
Check correct CT ratio selected
Check correct TLF rating selected and fitted
Check all links are replaced and secure
Ensure FPI CT shorting-link(s) are replaced if CTs are not used or not connected to FPI or RTU
Reconnect umbilical cable to RTU (if fitted)
Asset data form completed and submitted
Test Equipment
Make/Type
Serial Number
Calibration Date
Certification
()
All tests have been completed satisfactorily
Comments
Commissioning Engineer
Signature
Date
The completed test form shall be left on-site in a plastic wallet and in secure location. A copy of the completed test shall be sent to the relevant ART mailbox.
This page is intentionally left blank.
THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE
Document Number: ECP 11-0511a
Version: 5.0
Date: 27/02/2018
Schneider RN2, RN2c and RE2c Test Form
Document Number: ECP 11-0511a
Version: 5.0
Date: 27/02/2018
© UK Power Networks 2018 All rights reserved 7 of 7