Project Number: 37231-033 Loan 2841 Period Covered: July to September 2016 PAK: Punjab Irrigated Agriculture Investment Program — Project 2 EA Progress Report Prepared by the Project Management Office (PMO) for Punjab Irrigation Department, Lahore, Pakistan The Executing Agency’s Progress Reports are documents owned by the Borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff. These documents are made publicly available in accordance with ADB’s Public Communications Policy 2011 and as agreed between ADB and Islamic Republic of Pakistan.

Upload: others

Post on 29-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Project Number: 37231-033 Loan 2841 Period Covered: July to September 2016

PAK: Punjab Irrigated Agriculture Investment Program — Project 2

EA Progress Report

Prepared by the Project Management Office (PMO) for Punjab Irrigation Department, Lahore, Pakistan

The Executing Agency’s Progress Reports are documents owned by the Borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff. These documents are made publicly available in accordance with ADB’s Public Communications Policy 2011 and as agreed between ADB and Islamic Republic of Pakistan.

Page 2: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Progress Report No.12 (April to June 2010)

LBDC Improvement Project 1

MFF 0009-PAK: PUNJAB IRRIGATED AGRICULTURE INVESTMENT PROGRAM (PIAIP)

PROJECT 2: NEW KHANKI BARRAGE CONSTRUCTION PROJECT

(NKBP)

ADB Loan No. 2841-PAK (SF)

Quarterly Progress Report # 19

(July-September 2016)

Project Management Office (PMO) for Barrages, Punjab Irrigation Department

LAHORE, PAKISTAN

Page 3: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

TABLE OF CONTENTS

A.  PROJECT BASIC DATA .............................................................................................. 1  B.  UTILIZATION OF FUNDS-ADB LOAN AND COUNTERPART FUNDS .................... 1  C.  PROJECT DESIGN AND MONITORING FRAMEWORK (2011-12 TO 2014-15

Kharif) .......................................................................................................................... 2  D.  IMPLEMENTATION PROGRESS ............................................................................ 215

E. LAND ACQUISITION AND RESETTLEMENT PLAN (LARP)………………………..18 F. ENVIRONMENTAL MANAGEMENT PLAN (EMP)……………………………………22 G.  COMPLIANCE WITH LOAN COVENANTS .............................................................. 30  H.  MAJOR PROJECT ISSUES AND PROBLEMS ........................................................ 49  Annex 1-Status of Preparation, Vetting and Implementation of Resettlement Plan as on 30-09-2015 ...................................................................................................................... 50  Annex 2 – Revised ImplementationSchedule .................................................................. 51 

Page 4: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 1

NEW KHANKI BARRAGE CONSTRUCTION PROJECT Quarterly Progress Report

(1stJuly to 30thSeptember 2016) A. PROJECT BASIC DATA

No Item Description 1 Loan Number 2841-PAK(SF) 2 Project Title Punjab Irrigated Agriculture Investment Program (PIAIP)—Project 2 for New Khanki

Barrage Construction Project (NKBP) 3 Borrower Islamic Republic of Pakistan 4 Executing Agencies

(EA) Punjab Irrigation Department (PID)

5 Implementation Agency

PID through Project Management Office (PMO) for Barrages

6 Estimate project cost US$309 million 7 Loan amount SDR 172,417,000 (US$270 Million equivalent), from ADB Special Fund (ADF)

resources 8 PC-1 Cost Pak Rs. 23,442 Million 9 Date of loan approval 22 December 2011 10 Date of loan

effectiveness 17 February 2012

11 Project completion date

27June, 2017

12 Loan closing date 31July, 2017 13 MFF closing date 30 September 2017 14 Elapsed loan period 55 Months 15 Physical progress 86% (Revised Schedule) 16 To-date contracts

award Pak Rs. 22,127.540 ($232.150)

17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694 Million) – ADB Loan B. UTILIZATION OF FUNDS-ADB LOAN AND COUNTERPART FUNDS

Cumulative contract award and Disbursement Contract award

Source of Funds PKR-Millions Average Rate USD MillionsADB Loan 19,292.377 95.306 202.46 GoP Counterpart Funds 2,835.203 95.384 29.724 Total 22,127.450 95.315 232.150 Disbursements

Source of Funds PKR-Millions Average Rate USD MillionsADB Loan 15,136.478 102.4854 147.694 GoP Counterpart Funds 2,215.332 101.5514 21.815 Total 17,351.810 102.3651 169.509 Re-estimated cost to completion, need for reallocation within ADB loan categories.

……………………………NA……………………………

Page 5: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 2

C. PROJECT DESIGN AND MONITORING FRAMEWORK (2011-12 TO KHARIF2015 ) Loan 2841- PAK (SF): New Khanki Barrage Project, Pakistan

Design and Monitoring Framework (Based on data of Lower Chenab Canal)

Average farm size = 2.4 ha Design Summery

Performance Target/ Indicators

Baseline Data (2011-2012)

Intermediate(2015-2016)

Final (2020-2021)

Data Source/Reporting Mechanism

Remarks

Impact Improved agricultural production and farm income in Lower Chenab Canal Area

10% increase in cropping intensity over 50,000 ha by 2020 over baseline of 2011-12

10% increase in

average farm income of 25,000 farming families over baseline of 2011-12 by 2020

Cropping Intensity Annual cropping intensity = 146.5% - Kharif cropping intensity = 66.8% - Rabi cropping intensity 79.7% Crop Yield Cotton = 1510 kg/ha Rice = 1928 kg/ha Millet = 900 kg/ha Maize = 4343 kg/ha K. Fodder = 13506 kg/ha Wheat = 3071 kg/ha R. Fodder = 31980 kg/ha Sugarcane = 52920 kg/ha Guava = 7760 kg/ha and Citrus = 12050 Kg/ha Crop Production Cotton = 282,900 tons Rice = 747,100 tons Millet = 18,000 tons Maize = 120,600 tons K. Fodder = 1708,400 tons Wheat = 2137,900 tons R. Fodder = 3679,900 tons Sugarcane = 6492,700

-

-

-

-

-

-

-Directorate of Agriculture, Crop Reporting Services, Punjab, Lahore. -Ministry of Food & Agriculture (Economic Wing), Islamabad - Directorate of Agriculture, Crop Reporting Services, Punjab, Lahore. -Ministry of Food & Agriculture (Economic Wing), Islamabad

Page 6: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 3

Tons Guava = 100,500 tons and Citrus 158,100 tons Average Farm Income The average farm size of 2.4 ha farm have cropped area of 3.23 ha annually. Farm budget reveals that net farm income of average size farm has Pak. Rs. 1, 84,021.5 per annum.

-

-

- Agricultural Census Organization, Govt. of Pakistan, Lahore and field survey 2014 of project area

Outcome Sustainable improved delivery of services for irrigated agriculture and better water management

Designed water supplies up to 326 m3s-1 diverted to canal for at least 90% of the year by 2017 with no risk of failure compared to high risk of failure now

More climate

resilient infrastructure through strengthened flood design capacity from 1:50 return period event now to 1:100 years by 2017

Risk to Irrigation Supplies Supply at present during the year 2011-12 diverted up to 264 m3s-1 in canal for 81 percent of the year with high risk of failure. Assuming that by 2017 the preset supply 326 m3s-1 will continue at least 90 percent of year with no risk of failure. Flood Design Capacity Khanki Barrage present flood design capacity is 800,000 cfs which will rise to 1100,000 cfs on completion of New Khanki Barrage

- -

-

-

- Project feasibilities studies carried out by the consultants under the supervision of Punjab Irrigation Department, Govt. of Punjab, Pakistan.

- Director Regulation, Irrigation Department, Govt. of Punjab, Lahore

Outputs New barrage Elimination of leakages - - -Director Regulation,

Page 7: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 4

New Khanki Barrage completed on time and within the budget

eliminated the annual water leakage of 370 million cubic meters by 2017.

The flood capacity

increased from 22,654 m3s-1 in 2011 to 31150 m3s-1 in 2017

Annual diversion to

LCC increased from maximum of 7991 million cubic meters in 2011 to maximum of 8286 million cubic meters in 2017.

Leakages are expecting till the completion of New Khanki Barrage; the New Khanki Barrage will eliminate the annual water leakages of 370 million cubic meters by 2017 after completion of barrage construction. Flood Capacity Expecting increase in flood capacity from 800,000 cfs to 1100,000 cfs on completion. Annual Diversion Annual diversion was 8365.05 million cubic meters in 2011 due to extensive remodeling of LCC canal and it distribution system. These phenomena took place under high risk to sustainable deliveries from old Khanki Barrage.

-

-

-

-

Irrigation Department, Govt. of Punjab, Lahore. -Irrigation Department, PMIU, Govt. of Punjab, Lahore

Page 8: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 5

Loan 2841- PAK (SF): New Khanki Barrage Project, Pakistan Design and Monitoring Framework

(Based on data of Lower Chenab Canal) Average farm size = 2.4 ha Design Summery

Performance Target/ Indicators

Data for (2012-2013)

Intermediate (2015-2016)

Final (2020-2021)

Data Source/Reporting Mechanism

Remarks

Impact Improved agricultural production and farm income in Lower Chenab Canal Area

10% increase in cropping intensity over 50,000 ha by 2020 over baseline of 2011-12

10% increase in

average farm income of 25,000 farming families over baseline of 2011-12 by 2020

Cropping Intensity Annual cropping intensity = 146.3% - Kharif cropping intensity = 64.3% - Rabi cropping intensity 81.9% Crop Yield Cotton = 1410 kg/ha Rice = 2039 kg/ha Millet = 917 kg/ha Maize = 4951 kg/ha K. Fodder = 13575 kg/ha Wheat = 3098 kg/ha R. Fodder = 32117 kg/ha Sugarcane = 53008 kg/ha Guava = 7580 kg/ha and Citrus = 11453 Kg/ha Crop Production Cotton = 201,200 bales Rice = 790,200 tons Millet = 17,100 tons Maize = 143,300 tons K. Fodder = 1738,400 tons Wheat = 2143,500 tons R. Fodder = 3683,100 tons Sugarcane = 6105,600 Tons Guava = 99,300 tons and Citrus 150,100 tons

-

-

-

-

-

-

-Directorate of Agriculture, Crop Reporting Services, Punjab, Lahore. -Ministry of Food & Agriculture (Economic Wing), Islamabad - Directorate of Agriculture, Crop Reporting Services, Punjab, Lahore. -Ministry of Food & Agriculture (Economic Wing), Islamabad

Page 9: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 6

Average Farm Income The average farm size of 2.4 ha farm have cropped area of 3.24 ha annually. Farm budget reveals that net farm income of average size farm has Pak. Rs. 2, 15,164.79 per annum.

-

-

- Agricultural Census Organization, Govt. of Pakistan, Lahore and field survey 2014 of project area

Outcome Sustainable improved delivery of services for irrigated agriculture and better water management

Designed water supplies up to 326 m3s-1 diverted to canal for at least 90% of the year by 2017 with no risk of failure compared to high risk of failure now.

More climate

resilient infrastructure through strengthened flood design capacity from 1:50 return period event now to 1:100 years by 2017

Risk to Irrigation Supplies Supply at present during the year 2012-13 diverted up to 247 m3s-1 in canal for 76 percent of the year with high risk of failure. Assuming that by 2017 the preset supply 326 m3s-1 will continue at least 90 percent of year with no risk of failure. Flood Design Capacity Khanki Barrage present flood design capacity is 800,000 cfs which will rise to 1100,000 cfs on completion of New Khanki Barrage

- -

-

-

- Project feasibilities studies carried out by the consultants under the supervision of Punjab Irrigation Department, Govt. of Punjab, Pakistan.

-Director Regulation, Irrigation Department, Govt. of Punjab, Lahore

Outputs New Khanki Barrage completed on

New barrage eliminated the annual water leakage of 370

Elimination of leakages Leakages are expecting till the completion of New Khanki Barrage; the New

-

-

-Director Regulation, Irrigation Department, Govt. of Punjab, Lahore.

Page 10: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 7

time and within the budget

million cubic meters by 2017.

The flood capacity

increased from 22,654 m3s-1 in 2011 to 31150 m3s-1 in 2017

Annual diversion to LCC increased from maximum of 7991 million cubic meters in 2011 to maximum of 8286 million cubic meters in 2017.

Khanki Barrage will eliminate the annual water leakages of 370 million cubic meters by 2017 after completion of barrage construction. Flood Capacity Expecting increase in flood capacity from 800,000 cfs to 1100,000 cfs on completion.

Annual Diversion Annual diversion was 7632.878 million cubic meters in 2012-13 which is 4.5 percent less than outputs indicator. In spite of extensive remodeling of canal and it distribution system and water demand of the existing cropping level maximum annual diversion for 2012-13 could not reach up to the maximum level of 2011due to lesser regular and flood available supplies. These phenomena took place under high risk to sustainable deliveries from old Khanki Barrage.

-

-

-

-

-Irrigation Department, PMIU, Govt. of Punjab, Lahore

Page 11: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 8

Loan 2841- PAK (SF): New Khanki Barrage Project, Pakistan Design and Monitoring Framework

(Based on data of Lower Chenab Canal) Average farm size = 2.4 ha Design Summery Performance Target/

Indicators

Data (2013-2014)

Intermediate (2015-2016)

Final (2020-2021)

Data Source/Reporting Mechanism

Remarks

Impact Improved agricultural production and farm income in Lower Chenab Canal Area

10% increase in cropping intensity over 50,000 ha by 2020 over baseline of 2011-12

10% increase in

average farm income of 25,000 farming families over baseline of 2011-12 by 2020

Cropping Intensity Annual cropping intensity = 145.7% - Kharif cropping intensity = 63.6% - Rabi cropping intensity 82.1% Crop Yield Cotton = 1,427 kg/ha Rice = 1,912 kg/ha Millet = 871 kg/ha Maize = 4,860 kg/ha K. Fodder = 13,332 kg/ha Wheat = 3,129 kg/ha R. Fodder = 32,214 kg/ha Sugarcane = 5,3945 kg/ha Guava = 7,585 kg/ha and Citrus = 13,682 Kg/ha Crop Production Cotton =165,700 bales Rice = 754,800 tons Millet = 16,500 tons Maize = 159,200 tons K. Fodder = 1722,200 tons Wheat = 2310,400 tons R. Fodder = 3651,700 tons Sugarcane = 6,010,800 Tons Guava = 86,600 tons and Citrus 156,200 tons

-

-

-

-

-

-

-Directorate of Agriculture, Crop Reporting Services, Punjab, Lahore. -Ministry of Food & Agriculture (Economic Wing), Islamabad - Directorate of Agriculture, Crop Reporting Services, Punjab, Lahore. -Ministry of Food & Agriculture (Economic Wing), Islamabad

Page 12: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 9

Average Farm Income The average farm size of 2.4 ha farm have cropped area of 3.24 ha annually. Farm budget reveals that net farm income of average size farm has Pak. Rs. 2, 24,120.82 per annum.

-

-

-Agricultural Census Organization, Govt. of Pakistan, Lahore -Cropping and yield data from Provincial and Federal secondary sources -Field survey 2014 of project area

Outcome Sustainableimproved delivery of services for irrigated agriculture and better water management

Designed water supplies up to 326 m3s-1 diverted to canal for at least 90% of the year by 2017 with no risk of failure compared to high risk of failure.

More climate

resilient infrastructure through strengthened flood design capacity from 1:50 return period event now to 1:100 years by 2017

Risk to Irrigation Supplies Supply at present during the year 2013-14 diverted up to 268 m3s-1 in canal for 82 percent of the year with high risk of failure. Assuming that by 2017 the preset supply 326 m3s-1 will continue at least 90 percent of year with no risk of failure. Flood Design Capacity Khanki Barrage present flood design capacity is 800,000 cfs which will rise to 1100,000 cfs on completion of New Khanki Barrage

- -

-

-

- Project Management Office, Irrigation Department, Govt. of Punjab, Pakistan

- Project feasibilities studies carried out by the consultants under the supervision of Punjab.

- Director Regulation, Irrigation Department, Govt. of Punjab, Lahore

Outputs New barrage Elimination of leakages - - - Project Management

Page 13: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 10

New Khanki Barrage completed on time and within the budget

eliminated the annual water leakage of 370 million cubic meters by 2017.

The flood capacity

increased from 22,654 m3s-1 in 2011 to 31150 m3s-

1 in 2017 Annual diversion to

LCC increased from maximum of 7991 million cubic meters in 2011 to maximum of 8286 million cubic meters in 2017.

Leakages are expecting till the completion of New Khanki Barrage; the New Khanki Barrage will eliminate the annual water leakages of 370 million cubic meters by 2017 after completion of barrage construction. Flood Capacity Expecting increase in flood capacity from 800,000 cfs to 1100,000 cfs on completion. Annual Diversion Annual diversion was 8339.12 million cubic meters in 2013-14 which is 4.4 percent higher than outputs indicator. It occurs mainly due to extensive remodeling of LCC main canal and it distribution system and to utilize excessive available flood supplies for fulfilling the system requirement and cropping needs. These phenomena took place under high risk to sustainable deliveries from old Khanki Barrage. The New Khanki Barrage will provide annual

-

-

-

-

Office, Irrigation Department, Govt. of Punjab, Pakistan

-Project feasibilities studies carried out by the consultants under the supervision of Punjab Irrigation Department, Govt. of Punjab, Pakistan

Page 14: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 11

diversion to LCC increased from maximum of 7991 million cubic meters (6.472 million acre feet) in 2011 to maximum of 8286 million cubic meters / 6.711 million acre feet by 2017 with no risk to sustainable deliveries and to make use of excessive supplies.

Loan 2841- PAK (SF): New Khanki Barrage Project, Pakistan Revised (October-2015) Design and Monitoring Framework

(Based on data of Lower Chenab Canal) Average farm size = 2.4 ha Design Summary

Performance Target/Indicators

Data (2014-2015)

Intermediate (2015-2016)

Final (2020-2021)

Data Source/Reporting

Mechanism

Assumptions and Risks

Impact Sustainable improved agricultural production and farm income in Lower Chenab Canal (LCC) command area (Gujranwala, Hafizabad, Sheikhupura, Nankana Sahib, Faisalabad, Jhang, Chinnot and Toba Tek Singh districts.)

Cropping Intensity 10% increase in

cropping intensity over 1.2 million ha by 2021 (2011 baseline: 146.5%)

-Annual CI = 146.5% -Kharif CI = 66.8% -Rabi CI = 79.7% Crop Production 10% increase in main

crops production by 2021 (2011 baseline)

-Cotton= 282,900 tons, -Rice = 747,100 tons, -Millet = 18,000 tons, -Maize = 120,600 tons,

Cropping Intensity Annual cropping intensity = 146.1% - Kharif cropping intensity = 62.5% - Rabi cropping intensity = 83.5% Crop Yield Cotton = 1,831 kg/ha Rice = 1,902 kg/ha Millet = 887 kg/ha Maize = 5,422 kg/ha K. Fodder = 13,400 kg/ha Wheat = 3,094 kg/ha R. Fodder = 31,786 kg/ha

-

-

-

-

Directorate of Agriculture, Crop Reporting Services (DACRS), Punjab, Lahore.

Directorate of

Agriculture, Crop Reporting Services (DACRS), Punjab, Lahore.

Assumption Governments of Pakistan and Punjab will continue to see the delivery of irrigation water critical to achieving economic growth in Punjab.

Page 15: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 12

-K. Fodder = 1708,400 tons, -Wheat=2137,900 tons, -R. Fodder = 3679,900 tons, -Sugarcane = 6492,700 tons, Guava = 100,500 tons Citrus = 158,100 tons Farm Income 5% increase in average annual farm income of 500,000 farming families by 2021 (2011 baseline: PRs. 184,000)

Sugarcane = 54,383 kg/ha Guava = 7,925 kg/ha and Citrus = 14,464 Kg/ha Crop Production Cotton =179,500 bales Rice = 710,000 tons Millet = 19,000 tons Maize = 269,400 tons K. Fodder = 1572,100 tons Wheat = 2265,900 tons R. Fodder = 3,763,400 tons Sugarcane = 6,140,700 Tons Guava = 120,300 tons and Citrus 219,500 tons Average Farm Size and Farm Income The average farm size of project area is 2.4 ha farm have cropped area of 3.23 ha annually. The farm budget reveals that average size farm net income per ha is Rs. 77,297.58 whereas average size farm net income is Rs. 2, 49, 563.26 per annum.

-

-

-

-

Agricultural

Census Organization, Govt. of Pakistan, Lahore GoP

Directorate of Marketing Agriculture Department Punjab Lahore

Outcome Reliable improved irrigation supply

LCC irrigated area is maintained at 1.2 million ha in 2018 (2011 baseline: 1.2

Presently LCC irrigate 1.2 million ha culturalble commanded area (CCA) with unreliable irrigation

-

-

PAD’s Directorate of Agriculture crop Reporting Services.

Risk Climate-induced reduction in water flows and overall

Page 16: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 13

to the LCC

million ha) NKB can divert

designed irrigation supplies for 90% of the time with no risk of failure by 2018 (2011 baseline: 80% of time with high risk of failure)

More climate-resilient

infrastructure is safe, stable and better regulate the flows by 2018 (2011 baseline: none)

supply during 2014-15. Anticipated to maintain and irrigate an area of 1.2 million ha through reliable improved irrigation supply from LCC. in 2018 Risk to Irrigation Supplies Old KB diverted irrigation supply during 2014-15 up to 213 m3s-1 (6717 million cubic meter/5.45 MAF) in LCC canal for 68.1% of the year (Kharif 78.6% and Rabi 57.6%) against designed capacity of 326 m3s-1 (10280.7 million cubic meter/8.34 MAF) with high risk of failure. Whereas by 2018 NKB can divert designed irrigation supplies up to 425 m3s-1 (13402.8 million cubic meter/10.87MAF) for 90% of the time with no risk of failure Foresee that NKB is more climate-resilient infrastructure is safe, stable and better regulate the flows by 2018 whereas old KB 2011 baseline is not

-

-

Directorate

Regulation, of PID for barrage operation data.

PID’s NKB

Division’s data analysis of uplift pressure and Barrage is inspection reports.

Director Regulation, of PID for barrage operation data.

reduced water availability for irrigation. Extreme flood event delays barrage construction.

Outputs New barrage Elimination of leakages - - Director Regulation Risk

Page 17: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 14

1. Operational New Khanki Barrage replaced century-old underperforming Khanki Headworks.

2. Community’s

and EA’s improved capacity.

3. Upgraded

communal basic facilities.

eliminated the annual water leakage to Zero by 2017 (2011 baseline: 370 million m3)

The flood passage

capacity of the Barrage increased to 31,150 m3s-1 by 2017 (2011 baseline: 22,654 m3s-1)

New Barrage diverts

water up to 425 m3 s-1 by 2017 (2011 baseline: 328 m3 s-1)

30 local community

members including women received vocational training. PMO’s 11 staff

including women trained. One basic health unit

constructed and equipped.

Leakages are expecting till the completion of New Khanki Barrage; the New Khanki Barrage will eliminate the annual water leakages of 370 million cubic meters by 2017 after completion of barrage construction. Flood Capacity Expecting increase in flood capacity of NKB to 31,150 m3s-1 by 2017 on completion from 22,654 m3s-1 (2011 baseline) New Barrage diverts

water up to 425 m3 s-1 by 2017 (2011 baseline: 328 m3 s-1) whereas during 2014-15 water diverted up to 213 m3s-1.

-

-

-

-

of PID for barrage operation data.

EA’s quarterly

report. Director

Regulation of PID for barrage operation data.

EA’s quarterly

progress report. EA’s quarterly

progress report. EA’s quarterly

progress report. EA’s quarterly

progress report.

Security conditions worsen to a level that reduces interest of international contractor in ICB bidding.

Page 18: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 15

One girl’s elementary school constructed and equipped. 26 km of rural link

roads constructed. One Family Park and

water-based recreation facility developed.

EA’s quarterly

progress report. EA’s quarterly

progress report.

Activities with Milestones 1.1 Mobilization and establishing construction camps and laboratory (jun 2014) 1.2 Construction work in one half of the Barrage (Jan 2016) 1.3 Construction work in other half of the Barrage (Dec 2016) 1.4 Construction of canal head regulator and silt excluder (Jan 2016) 1.5 Lead channel and dismantling the existing head works (Mar 2017) 1.6 Commissioning and operation tests (Apr 2017)

2.1 Identity the potential trainee from PID (Dec 2014) 2.2 Delivered training to the trainees (Jul 2015) 2.3 Identity trainees from the local communities including (Nov 2015) 2.4 Provide training to the community for first batch (Apr 2016) 2.5 Provide training to the community for second batch (Jul 2016)

3.1 Award of contract to the subcontractor (Jul 2014) 3.2 Construction of structure (Feb 2016) 3.3 Furnishing and equipping and handing over to relevant agency (Jun 2016) 3.4 Link roads constructed and operational (Sep 2016) 3.5 Family park ready for opening (Feb 2017)

Inputs ADB – SDR 172,417,000 ($ 247.7 million equivalent)

- works – SDR 132,342,000 - contingencies – SDR 28, 961,000 - Project management cost (PMO,

consultants, resettlement) – SDR 6,618,000

Government - $39.1 million International consultants – 76 pm National consultants – 2046 pm

CI = Cropping Intensity; EA = Executing Agency; GoP = Government of Pakistan; LCC = Lower Chenab Canal; NKB = New Khanki Barrage; m3

=cubic meter; PID = Punjab Irrigation Department; PMO = Project Management Office

Page 19: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 16

Loan 2841- PAK (SF): New Khanki Barrage Project, Pakistan Design and Monitoring Framework

(Based on data of Lower Chenab Canal) Average farm size = 2.4 ha Design Summary

Performance Target/Indicators

Data (2015-2016)-Kharif

Intermediate (2015-2016)

Final (2020-2021)

Data Source/Reporting

Mechanism

Assumptions and Risks

Impact Sustainable improved agricultural production and farm income in Lower Chenab Canal (LCC) command area (Gujranwala, Hafizabad, Sheikhupura, Nankana Sahib, Faisalabad, Jhang, Chinnot and Toba Tek Singh districts.)

Cropping Intensity 10% increase in

cropping intensity over 1.2 million ha by 2021 (2011 baseline: 146.5%)

-Annual CI = 146.5% -Kharif CI = 66.8% -Rabi CI = 79.7% Crop Production 10% increase in main

crops production by 2021 (2011 baseline)

-Cotton= 282,900 tons, -Rice = 747,100 tons, -Millet = 18,000 tons, -Maize = 120,600 tons, -K. Fodder = 1708,400 tons, -Wheat=2137,900 tons, -R. Fodder = 3679,900 tons, -Sugarcane = 6492,700 tons,

Cropping Intensity Annual cropping intensity = cropping data for rabi 2015-16 is not yet published and under process of development. - Kharif cropping intensity = 57.54% Without orchards and Spring maize area - Rabi cropping intensity secondary data not yet published and under process. Crop Yield Cotton = 1,131 kg/ha Rice = 2,000 kg/ha Millet = 938 kg/ha Maize Autumn = 5,431 kg/ha K. Fodder = 13,491 kg/ha Sugarcane = 54,272 kg/ha

-

-

-

-

-

-

Directorate of Agriculture, Crop Reporting Services (DACRS), Punjab, Lahore.

Directorate of

Agriculture, Crop Reporting Services (DACRS), Punjab, Lahore.

Assumption Governments of Pakistan and Punjab will continue to see the delivery of irrigation water critical to achieving economic growth in Punjab.

Page 20: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 17

Guava = 100,500 tons Citrus = 158,100 tons Farm Income 5% increase in average annual farm income of 500,000 farming families by 2021 (2011 baseline: PRs. 184,000)

Crop Production Cotton =105,700 bales Rice = 712,100 tons Millet = 20,800 tons Maize Autumn = 215,100 tons K. Fodder = 1575,600 tons Sugarcane = 5,971,660 Tons Average Farm Size and Farm Income The average farm size of project area is 2.4 ha Average farm size annual cropped area, farm budget and net income will be estimated on publication of rabi 2015-16 cropping secondary data.

-

-

Agricultural

Census Organization, Govt. of Pakistan, Lahore GoP

Directorate of Marketing Agriculture Department Punjab Lahore

Outcome Reliable improved irrigation supply to the LCC

LCC irrigated area is maintained at 1.2 million ha in 2018 (2011 baseline: 1.2 million ha)

NKB can divert

designed irrigation supplies for 90% of the

Presently LCC irrigate 1.2 million ha culturalble commanded area (CCA) with unreliable irrigation supply during kharif 2015. Anticipated to maintain and irrigate an area of 1.2 million ha through reliable improved irrigation supply from LCC. in 2018 Risk to Irrigation Supplies Old KB diverted irrigation supply during 2015-16

- -

-

-

PAD’s Directorate of Agriculture crop Reporting Services.

Directorate

Regulation, of PID for barrage operation data.

Risk Climate-induced reduction in water flows and overall reduced water availability for irrigation. Extreme flood event delays barrage construction.

Page 21: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 18

time with no risk of failure by 2018 (2011 baseline: 80% of time with high risk of failure)

More climate-resilient

infrastructure is safe, stable and better regulate the flows by 2018 (2011 baseline: none)

up to 213 m3s-1 (6717 million cubic meter/5.45 MAF) in LCC canal for 78.0% of the year (Kharif 94.3% and Rabi 61.7%) against designed capacity of 326 m3s-1 (10280.7 million cubic meter/8.34 MAF) with high risk of failure. Whereas by 2018 NKB can divert designed irrigation supplies up to 425 m3s-1 (13402.8 million cubic meter/10.87MAF) for 90% of the time with no risk of failure Foresee that NKB is more climate-resilient infrastructure is safe, stable and better regulate the flows by 2018 whereas old KB 2011 baseline is not

PID’s NKB

Division’s data analysis of uplift pressure and Barrage is inspection reports.

Director Regulation, of PID for barrage operation data.

Outputs 4. Operational

New Khanki Barrage replaced century-old underperforming Khanki Headworks.

New barrage eliminated the annual water leakage to Zero by 2017 (2011 baseline: 370 million m3)

Elimination of leakages Leakages are expecting till the completion of New Khanki Barrage; the New Khanki Barrage will eliminate the annual water leakages of 370 million cubic meters by 2017 after completion of barrage construction.

-

-

-

-

Director Regulation of PID for barrage operation data.

EA’s quarterly

Risk Security conditions worsen to a level that reduces interest of international contractor in ICB bidding.

Page 22: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 19

5. Community’s

and EA’s improved capacity.

6. Upgraded

communal basic facilities.

The flood passage

capacity of the Barrage increased to 31,150 m3s-1 by 2017 (2011 baseline: 22,654 m3s-1) New Barrage diverts

water up to 425 m3 s-1 by 2017 (2011 baseline: 328 m3 s-1)

30 local community

members including women received vocational training. PMO’s 11 staff

including women trained. One basic health unit

constructed and equipped. One girl’s elementary

school constructed and equipped. 26 km of rural link

roads constructed. One Family Park and

water-based recreation facility developed.

Flood Capacity Expecting increase in flood capacity of NKB to 31,150 m3s-1 by 2017 on completion from 22,654 m3s-1 (2011 baseline) New Barrage diverts

water up to 425 m3 s-1 by 2017 (2011 baseline: 328 m3 s-1) whereas during 2015-16 water diverted up to 213 m3s-1.

-

-

report. Director

Regulation of PID for barrage operation data.

EA’s quarterly

progress report. EA’s quarterly

progress report. EA’s quarterly

progress report. EA’s quarterly

progress report. EA’s quarterly

progress report. EA’s quarterly

progress report.

Activities with Milestones 1.7 Mobilization and establishing construction camps and laboratory (jun 2014) 1.8 Construction work in one half of the Barrage (Jan 2016)

Inputs ADB – SDR 172,417,000 ($ 247.7 million equivalent)

Page 23: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 20

1.9 Construction work in other half of the Barrage (Dec 2016) 1.10 Construction of canal head regulator and silt excluder (Jan 2016) 1.11 Lead channel and dismantling the existing head works (Mar 2017) 1.12 Commissioning and operation tests (Apr 2017)

2.1 Identity the potential trainee from PID (Dec 2014) 2.2 Delivered training to the trainees (Jul 2015) 2.3 Identity trainees from the local communities including (Nov 2015) 2.4 Provide training to the community for first batch (Apr 2016) 2.5 Provide training to the community for second batch (Jul 2016)

6.1 Award of contract to the subcontractor (Jul 2014) 6.2 Construction of structure (Feb 2016) 6.3 Furnishing and equipping and handing over to relevant agency (Jun 2016) 6.4 Link roads constructed and operational (Sep 2016) 6.5 Family park ready for opening (Feb 2017)

- works – SDR 132,342,000 - contingencies – SDR 28, 961,000 - Project management cost (PMO,

consultants, resettlement) – SDR 6,618,000

Government - $39.1 million International consultants – 76 pm National consultants – 2046 pm

CI = Cropping Intensity; EA = Executing Agency; GoP = Government of Pakistan; LCC = Lower Chenab Canal; NKB = New Khanki Barrage; m3

=cubic meter; PID = Punjab Irrigation Department; PMO = Project Management Office

Page 24: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 21

D. IMPLEMENTATION PROGRESS Activities:

Activity Start Date End Date Completed Progress Mobilization and establishing construction camps and laboratory.

08-Jul-2013 15-Mar-2014 Yes 100 %

Construction work in one half of the Barrage (Bays 1-28)

12-Dec-2013 19-March-2015 In Progress 99.5%

Construction work in other half of the Barrage (Bays 29-40)

16-Oct-2014 08-Feb-2016 In Progress 99%

Construction work in other half of the Barrage (Bays 41-65)

16-Sept-2015 14-July-2016 In Progress 98%

Construction of canal head regulator and silt excluder

27-Dec-2013 26-Jun-2015 In Progress 99%

Lead Canal and Pumping Station

24-Feb-2015 17-May-2017 In Progress 78%

Buildings & Roads 02-May-2014 19-Dec-2016 In Progress 87%

Dismantling of Old Headworks

15-Sep-2016 27-Jun-2017 Started 1%

Environmental management plan implementation continues during construction period.

08-Jul-2013 27-Junt-2017 In Progress 85%

Commissioning and operation tests.

18-Feb-2017 30-March-2017 -

Assessment of Physical Progress during Implementation

Sr. No.

Activities (a) (b) (a) x (b)

Assigned Weight

Actual Progress Weighted Progress

1 Establishment of PMO 5% 100% 5.00%

2 Consultants Recruitment 5% 100% 5.00%

3 Detailed Design, Tender Documents and Contract Award

10% 100% 10.00%

4 Construction 70% 82 % (rev schedule) 57.40%

5 Implementation of RP & EMP

10% 85% 8.50%

Total Weight 100% Project Progress 86%

Project progress= sum of weighted progress for each activity.

Page 25: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 22

1. EA's improved project management efficiency. Indicators Status

PMO's 11 senior staff trained 20 Engineers of PID has been sent to AIT for Master in Water Resources and Irrigation Engineering. Similar process will be adopted for Capacity Building for next intake with universities. ADB Mission (28 April to 11 May 2015) has proposed a plan of training programs for capacity building of PMO/PID/communities. The matter has been taken up with the Authorities for its approval.

Activities

Activities Start date End Date Completed Status

Recruitment of PMO staff for NKB unit.

01-Mar-2012 01-Jun-2012 Yes The required positions are now filled.

Preliminary training/mentoring by the PMO senior staff and management.

01-Jul-2012 01-Sep-2012 No 3 Days (23 – 25 April, 2012) training at PRM Islamabad. Project Implementation and Administration: Procurement and consulting modules attended by Director (Proc. & CA.) and Director Technical.

On-the-job and special trainings in procurement, financial management and safeguards.

01-Oct-2012 01-Dec-2012 No 2-days loan disbursement training attended by Accounts Officer and Deputy Director Finance. 3-days workshop on Resettlement (June 18-20, 2014) attended by Director (Social&Env.)

PMO staff Recruitment

No Positions Due date Status

1 Director Technical /Deputy Project Director

4th Quarter of 2012 ShahidSalim was appointed and joined on 13-11-2012

2 Deputy Director Technical

4th Quarter of 2012 Shabbir Ahmad Saqib was attached from Irrigation Department from Nov2013).

3 Deputy Director Contracts

4th Quarter of 2012 Shakeel Ahmed Already working

4 Deputy Director Mechanical

4th Quarter of 2012 Zulfiqar Ali was appointed and joined on 01-12-2012

5 Deputy Director Sociology

4th Quarter of 2012 Waheed Ahmad newly appointed.

Page 26: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 23

No Positions Due date Status

6 Assistant Director Mechanical

4th Quarter of 2012 M. Waseem Anwar was appointed and joined on 28-12-2012

7 Assistant Director Electrical

4th Quarter of 2012 AhsanMushtaq was appointed and joined on 01-12-2012

10 Manager Accounts and Administration

4th Quarter of 2012 Murtaza Ali Usama was appointed and joined on April 2015.

11 Accounts Officer

4th Quarter of 2012 Khalil Ahmad was appointed and joined on 03-12-2012

12 Office support staff (office Assistants, Drivers, office Boys etc)

4th Quarter of 2012 14 number support staff have been recruited and joined in June/July 2013

Consultants Recruitment

No Activity Planned date Status Finish Date 1. Tech. Evaluation (Submission– 2)

submitted to Asian Development Bank

12-Mar-2012 Completed 18-Jun- 2012

2. NOL from Bank 23-Mar-2012 Completed 02-Aug-2012 3. Financial Proposal opened 06-Apr-2012 Completed 08-Aug-2012 4. Combined Evaluation approved by

CSC 20-Apr-2012 Completed 17-Sep-2012

5. Combined Evaluation (Submission-3) to ADB

21-Apr-2012 Completed 19-Sep-2012

6. Approval on Combined Evaluation from Bank

30-Apr-2012 Completed 18-Nov- 2012

7. Contract Negotiation 24-May-2012 Completed 18-Jan- 2013 8. Draft Negotiated Contract

(Submission-4) to ADB 31-May-2012 Completed 18-Jan- 2013

9. Approval on Contract Negotiation (Submission-4)

05-Jun-12 Completed 16-Feb-2013

10. Contract Signing 19-Jun-12 Completed

21-Feb- 2013

11. Mobilization/commencement Completed 13-April- 2013 12 Production of Construction Drawings

/ Construction Supervision /Contract Administration

In-progress

Civil Works Contract

No Activity Planned date Status Finish Date

1 Submission of revised qualification criteria to ADB

31-Jul-12 Completed

30-Jul-12

2 Bank’s NOL 10-Aug-12 Completed 24-Aug-12 3 Finalization of Bidding Documents

(updating Engineer Estimate, BOQ, Technical specification & drawings)

20-Aug-12 Completed

17-Aug-12

4 Bank’s NOL 4-Sep-12 Completed 5-Sep-12 5 Invitation for Bids 14-Sep-12 Completed 10-Sep-12 6 Bid Submission/Opening of

Technical Bid 9-Nov-12

Completed 15-Nov-12

7 Preparation of Technical Bid Evaluation Report by Consultants

21-Dec-12 Completed

11-Jan-13

8 Review of TBER by PMO & submission to ADB

31-Dec-12 Completed

16-Jan-13

9 Approval of TBER by ADB 01-Feb-13 Completed 01-Mar-13 10 Opening of Price Bid 17-Feb-13 Completed 11-Mar-2013

Page 27: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 24

No Activity Planned date Status Finish Date

11 PBER sent to ADB for Approval 28-Feb-13 Completed 04-April-2013 12 Approval of PBER byADB 15-Mar-13 Completed 30-April-2013 13 Contract Award 25-Mar-13 Completed 02-May-2013 14 Contract Signing 05-April-2013 Completed 29-May-2013 15 Contract Commencement 20-April-2013 Completed 08-Jul-2013 16 Preliminary Works / Construction

activities from Bay # 1-65

In progress

E.  LAND ACQUISITION AND RESETTLEMENT PLAN (LARP) 

The project is category “B” for involuntary resettlement and category “C” for indigenous people. Draft Land Acquisition and Resettlement Plan (LARP) for New Khanki Barrage was prepared and submitted to ADB for approval. ADB cleared the draft LARP on July 07, 2012. LARP was revised/ updated and cleared by ADB in Feb 2014. Land Acquisition  is  in progress according to requirement of Land Acquisition Act 1894. A total of 8.6 acres of land was required for construction of Head Regulator and Head Reach of the new LCC. Section 4 and section 5 of Land Acquisition Act for 8.6 acres of land were notified and published in the Punjab Gazette on August 07, 2012 and January 21, 2013 respectively. Land price was assessed, and the EA released the total amount Rs. 9.925 million to the Revenue Department, Government of the Punjab.  However, due to change in engineering design it was found that only 4.58 acres out of 8.6 acres of land was required along with a new piece of land 1 acre, 6 kanal, 3 marlas, and 4.5 Sarsai. Due to this change, process of  land acquisition was re‐initiated. The section 4 & 5 of  land Acquisition Act 1894  for additional  land was notified and published in the Punjab Gazette on July 11, 2014 and July 29, 2015 respectively.  Again due  to  change  in engineering design of  LCC  Lead Channel,  the procedure  for acquiring 5  kanal, 10 Marla of private land from one landowner (Mr. Farooq Akbar Cheema) is still in process. Compensation rates have been re‐calculated to reflect current values and procedures. The landowner has received full payment for crop losses, trees and structures.  The five affected families which were residing at the Dera of land owner, now they have been shifted in their new  accommodation  built  by  the  landowner  on  his  remaining  land.  Their  livelihoods  remain  unaffected. These  households  have  received  their  relocation  allowance  (Pak  Rupees  5,000/household)  and  cash assistance  for vulnerable households  (Pak Rupees72, 000/‐household). Alternative accommodation  for  the 15 no. of the affected  families of  Irrigation staff  is also being constructed and all AFs have been shifted  in new buildings. Compensation payment for 6.625 acres land now will be paid by October 2016.  LARP implementation activities for Tranche‐2 relates to LCC Lead Channel (component) of New  Khanki Barrage  Project.  Internal  Resettlement Monitoring  of  all  relevant  activities  is  the  responsibility  of PMO  (Environment  and  Social  Unit  (ESU).  Internal  Monitoring  Reports  in  the  shape  of  QPR  are  being regularly  submitted  to  the  Bank.  The  implementation  schedule  of  LARP  has  been  discussed  in  detail  in Quarterly Internal Resettlement Monitoring Report (July‐September 2016). Total amount under LARP  is Rs. 18.05 Million. Out of which, Rs. 9.925 Million has already been paid to the Revenue Department  for  land Acquisition. Rupees 4.175 million have been paid  to  the 21 no. of affected families  as  compensation  amount  for  their  structures,  crop,  Tubewell,  hand  pumps  and  trees.  The vulnerability  allowance  &  shifting  allowance  has  also  been  paid  to  the  PAPs.  The  detail  is  discussed  in Quarterly Internal Resettlement Monitoring Report (July‐September‐2016) as Annex‐A.  2. ADJUSTMENT MADE IN THE COMPENSATION RATE DURING UPDATING OF LARP  The LARP of New Khanki Barrage was approved  in 2012. Again,  it was updated and approved  in 2014. The adjustment was made  in  compensation  rates of  the  land  after  certification by  the Revenue Department, Government  of  Punjab.  The  rates  are  still  applicable  up  till  now.  The  detail  is  given  in  the  Internal Resettlement Monitoring Report as Annex‐B.  

Page 28: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 25

3. EMPLOYMENTS.  The percentage of skilled and un‐skilled  laborer remained 60%, 60% and 58% during the reporting quarter respectively. Three persons from the affected families are working with contractor and the remaining do not want  to  work.  Twenty  (20)  family members  of  Irrigation  department  have  also  got  employments  with contractor. The details is given in the Quarterly Internal Resettlement Monitoring Report (July‐September).  4. RELOCATION OF AFFECTED HOUSEHOLDS AND THEIR CURRENT LIVING CONDITION   The relocation process of the AHs has been completed and all effectedfamilies  (AFs) have been dislocated from LCC Lead Channel component of New Khanki Barrage Project. Compensation  (except  land)  regarding crop,  trees,  structure  and  other  essential  allowances  have  been made  to  the  affected  households.  The details about the relocation of AHs along with photographs have been discussed  in the current IRMR (July‐September 2016).  5. PID OWNED PUBLIC INFRASTRUCTURE   High  Level  Irrigation  Non‐perennial  Channel was  supplying  canal water  to  the  village  Khanki,  Kot  Imam Bukhsh  and  Faqiranwali.  Due  to  construction  activities  this  channel  was  damaged  and  contractor  had provided  a  temporary  bridge  and  outlet  to  supply water  to  the  cultivators  for  their  smooth  agricultural practices. Pictures of bridge, outlet and water course are as under:   

 A view of temporary bridge and outlet at                   A view of lined community watercourse at  RD: 2066‐R of High Level Channel. RD: 2066‐R                                                                                                                                         Community watercourse was dismantled during  the construction work of new High Level Channel, due  to this  issue the concerned  farmer were  facing a  lot of difficulty. On  the  request of  the affected  farmers the unlined water course was restored during the reporting quarter.   

Page 29: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 26

 A view of unlined community watercourse at RD: 2066‐R.  6. GRIEVENCE REDRESSAL MECHANISM   Tranche‐2  also  has  an  operational Grievance Redressal Mechanism  that  covers  all  types of  grievances of NKBP,  including Environmental & Social. Complaint register  is also being maintained by the Consultants to record community concerns and  their  solutions. Out of 38 complaints, 30 complaints have been  resolved while 8 complaints are yet to be resolved. The detail of complaints is given in the IRMR (July‐September 2016 as annex –D.  

F. ENVIRONMENTAL MANAGEMENT PLAN (EMP) 

Environmental Management Plan (EMP) was prepared and submitted to ADB for approval. ADB cleared the EMP with appreciation on August 05. 2011.  It was made part of  the bidding document as volume –IV on September.2012. Environmental Social Unit  (ESU) has already been established  in PMO  to  implement  the EMP during the mobilization and execution stage of the project. Contractor  (DESCON)  is broadly  following the said plan while Engineer’s Environmental Specialist and Senior Environmentalist along with  their team regularly and  strictly monitor  the overall compliance  related  to environmental and  safety  issues. The ESU PMO  is  the  overall monitor  of  the  proper  implementation  of  the  EMP  /  SSEMP  /  HSE  Plan  during  the execution stage of the Project.    EIA / IEE /EMP implementation Schedule  

Sr.No.  Activity  Date  Status Reasons for 

delay Corrective action 

1  Establishment  of PMO     

‐  PMO  is  already  in  place at Lahore. 

No Delay  ‐ 

2  Setting‐up the ESU in PMO Barrages 

  Already established  No Delay  ‐ 

3  Submission of EIA to EPA for clearance 

August,2011  Accepted  No Delay  ‐ 

4   

Submission of  IEE  to ADB  for approval 

August,2011  Approved  No Delay  ‐ 

Page 30: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 27

5  Approval  of  Public Hearing  Notice  for EIA  from EPA 

August, 2011  

Approved No Delay  ‐

6  Public  Hearing notice  Published  in the News Paper 

August, 2011  Published  

No Delay  ‐ 

7  Public  Hearing  at Khanki Barrage 

September, 2011 

Successfully Conducted  

No Delay  ‐ 

8  Environmental Impact Assessment(EIA) Approval  from  the EPA 

December12, 2011 

NOC  has  been  given  by EPA 

No Delay  ‐ 

9  Finalization of EMP   July,2011  Finalized  No Delay  ‐ 

10  EMP‐  sent  to  ADB for approval. 

August,2011 Approved No Delay  ‐

11.  EARF‐sent to ADB for approval 

September,2011 

Approved No Delay  ‐

12  Implementation  of EMP 

On – going Status It is Discussed below 

   Implementation Of EMP  Construction work  of New  Khanki  Barrage  Project  is  in  progress.  This  quarterly  Environmental 

Progress Report provides up to date status of implementation of the SSEMP of the Main Barrage, 

SSEMP  of  Roads,  HSE  Plan,  Traffic  Management  Plan,  Tree  Plantation  Plan  and  Solid Waste 

Management Plan. DESCON has three Site specific EMP documents for this Project. 

 

I. SSEMP for Main Barrage Project 

II. SSEMP for Chanawan and LMB Roads 

III. SSEMP for the Mechanical Workshop. The work  in the Mechanical workshop has 

been presently completed.  

Engineer’s  Environment  and  Social Monitoring  Team  is  regularly monitoring  the  construction 

activities and environmental performance of DESCON Engineering Limited at various work site(s) 

to ensure that the day to day construction activities are carried out in an environmentally sound 

and  sustainable manner  and  to  ensure  the  implementation  of ADB’s  environmental  safeguard 

policies, national laws and regulations applicable to this Project.

1. PHYSICAL WORKS AT PROJECT SITE 

During  this  quarter  of  the  year,  construction  activities  remained  in  progress  on main  barrage, 

upstream and downstream Left as well as Right Guide Banks, roads, buildings etc. On LMB road, 

the Contractor completed final layer of Asphalt wearing coarse from RD 38+00 to RD 137+00. The 

unpaved portion of LMB  from RD 0+600 to RD 3+600 has been graded by the contractor.  It has 

also been carpeted with Asphalt base coarse from RD 2+400 to RD 3+600. The Chanawan road is 

complete in all respects including TST shoulders as well as earthen shoulders. The contractor has 

Page 31: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 28

laid down sub base and base course on Chanawan road from RD 2+700 to RD 3+400. A culvert at 

RD  2+450  is  under  construction.  The  purpose of  this  culvert  is  to provide  storm  runoff  to  the 

villagers of Kot Imam Buksh.  

The construction of RMB Road is being carried out by Sub contractor Ashraf Rind & Co. Currently 

road  embankment  is  in  progress.  The  Contractor  has  also  started work  from  RD  39+00  to  RD 

60+00 as its design is approved by the Engineer. This section of road is realigned/straightened to 

overcome sharp turns and minimize tree cutting. The change in design has reduced tree cutting to 

half the number envisaged at preliminary design stage. 

The contractor has also started work on different buildings  like Flood office, cook house and to 

Annexe of the  Irrigation Rest house etc. The brick work  for the Cook house  is  in progress. Brick 

work of Annexe  is  complete up  to  roof  level. As  far as Flood office  is concerned, backfilling by 

engineering  fill  has  been  done.  Layout  for  new  flood  office  building  has  been  done  to  start 

construction activities till September 30, 2016. 

2. INTERNAL & EXTERNAL ENVIRONMENTAL MONITORING 

The main objective of  the  Environmental Monitoring  is  to  check whether mitigation measures 

documented  in the Environmental Management Plan  (EMP)  for the construction of New Khanki 

Barrage  are  adequately  and  effectively  adopted  in  the  field.  For  this  purpose,  two  types  of 

environmental monitoring (internal monitoring & external  i.e. 3rd party) are being carried out at 

the project construction site.  

 

External Instrumental Monitoring is being carried out after each quarter while internal monitoring 

is being carried out as per  instructions of the Engineer.  In the external Instrumental Monitoring, 

air  quality  (PM10,  PM2.5,  NOx,  SOx,  and  CO)  including  stack  emission  of  power  generators, 

exhaust emissions of vehicles, waste water quality, surface water quality, drinking water quality 

and noise level are being tested. The Internal Monitoring is being carried out to check the surface 

water quality of River Chenab and noise of heavy equipment and machinery. 

3. ENVIRONMENTAL SPECIALIST’S FIELD VISITS AND FIELD TRIP REPORTS: 

From July to September 2016, Environmental Specialist SMEC Engr. Anwar H. Mujahid carried out 

site visit to New Khanki Barrage project site. The Environmental Specialist’s Field Trip Reports are 

being submitted to PMO regularly.  

4. HSE PLAN IMPLEMENTATION AND BEST PRACTICES:  

According to the HSE Plan, the Contractor is bound to provide safety including first aid, personal 

protective equipment, safe drinking water, clean accommodation and hygienic and sufficient food 

to all workers/staff working on New Khanki Barrage Project. 

Workers need to be provided with necessary Personal Protective Equipments  (PPEs) comprising 

of hard helmets, coveralls,  long rubber shoes, steel toe safety shoes and dust masks depending 

upon  the  job  description  to  prevent  injuries.  Hard  helmets  should  be  provided  to  shield  the 

worker  from  overhead  and  flying  object  hazards.  Safety  shoes  are  required  with  the  aim  of 

Page 32: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 29

protecting the worker while carrying or handling materials such as heavy tools, which if dropped, 

could  injure their feet. Gas masks are required for the workers engaged  in welding and painting 

works. These gas masks provide respiratory protection to the  labourers performing welding and 

painting jobs. 

DESCON has hired their own staff/laborer while several sub‐contractors are also working for the 

New  Khanki  Barrage  Project.It  is  important  to mention  that  all  the  sub‐contractors  and  their 

laborer  are  presumed  to  be  working  for  DESCON  and  HSE  Plan  application  will  include  all 

staff/workers of the sub‐contractors. Different applications/methods and rules described  in HSE 

Plan are for both DESCON hired/appointed staff/workers and the sub‐contractors. Table‐1 shows 

the up‐to‐date HSE Statistics including the month of September 2016. 

Table‐1: HSE Statistics  

Category  

Current Month  Project to Date

Project to Date Man Hours 231780  15387886 

Safe Man Hours  231780  4443964 

First Aid Cases  6  222 

Medical Treatment Cases (MTC) 0  7 

Lost Time Injury (LTI)  0  1 

Restricted Work Injury (RWI)  0  6 

Near Miss  29  468 

No. of Environmental Damage  0  0 

Trainings  4  128 

HSE Orientation   202  7069 

Total Recordable Injury Rate (TRIR) 0.0  0.181 

  *Courtesy DESCON EMR September 2016 

(1) Measures for Health Improvement: 

Health promotion and  Improvement aims  to enact preventative health  care and  steps  in  the 

settings where people live, learn, socialize and work. Lifestyle behaviors impacting on health are 

addressed  to  improve  the  health  of  workers,  working  for  the  construction  of  New  Khanki 

Barrage such as smoking, alcohol consumption, physical inactivity and obesity.  

a) Drinking water 

According to the HSE and EMP Plan, the Contractor  is bound to provide safe and clean drinking 

water  to  the  laborers working  for the construction of New Khanki Barrage. External Monitoring 

for  quality  of  drinking water was  carried  out  in March  2016  by M/S GEL  and  found  bacterial 

contamination  in both the samples. The Contractor was therefore advised to  install UV filters at 

water  coolers.  These water  filters were  installed  in  the month  of April  2016.All  the UV  filters 

remained operational during the current month. The Contractor has always been advised to carry 

Page 33: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 30

out visual inspection of these filters on regular basis.

b) Hygiene inspection and food quality 

 

Currently, one Labor Canteen  is operational  in the Labour Camp which provides food services to 

the  laborers  and  workers  while  two  officer’s Mess  are  operational  in  Staff  Colony.  Hygienic 

inspection of dining area and cooking area was carried out during the month. Sr. Environmentalist 

of  the  Consultant  visited  the  Canteens  along  with  Contractor’s  representatives.    During  the 

hygienic inspections, following deficiencies were observed. 

 

Overall housekeeping has improved a lot in labor canteen 

There was lack of food serving staff in the Canteen 

Food quality was poor 

Cleanliness of bread baking area was poor. 

The Contractor has been advised  to  improve  the quality of  food. Follow up  inspections will be 

carried out next month to record improvements. 

c) Sanitation of living room, lavatories and bath rooms 

 

DESCON has established a good sanitation system  in  their camps. During  this month, The Labor 

Barracks  were  visited  by  the  environment  and  social  team  for  inspection  of  the  sanitation 

conditions  of  living  rooms,  lavatories  and wash  rooms. During  this  visit,  following  issues were 

highlighted.  

 

All the rooms have been provided with barriers to hamper rain water infiltration 

Wash rooms have been made operational  

Lack of proper lighting for wash rooms 

Wash basins have not been shifted with other utilities. 

 

d) Physical Fitness Center: 

 

Regular  exercise  is  essential  to  keep  oneself  healthy.  For  this  purpose,  DESCON  has  provided 

physical fitness center/gym facility for their officers/staff at staff dormitories. Necessary tools for 

fitness have been provided at this fitness center. This is a step in the right direction which needs to 

be commended. 

 

e) Mosquito prevention spray  

 

With the advent of the monsoon season, rainfall results in stagnation of part of the storm water 

on ground. It also causes mosquito’s population to intensify. Workers tired of working long hours 

need  some  rest  but mosquitoes  distract  their  nap;  therefore  proper mosquito  prevention  is 

required to safeguard workers from malaria, dengue etc. and to get a sound, uninterrupted sleep. 

During  the  reporting period, mosquito prevention  spray has been carried out multiple  times  in 

Labour Barracks, Staff Dormitory and office area. 

 

Page 34: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 31

(2) Safety of Personnel: 

It is the Contractor’s responsibility to identify potential hazards and control risks and explain to his 

workers how to plan, organize, control, monitor and minimize hazards/risks assessed throughout 

the  life  of  a  project.  The  Contractor  has  an  approved  HSE  Plan  and  its  implementation  is 

continuously being monitored by The Engineer. Following is a synopsis of HSE Plan compliance at 

site.  

 

a) Tool Box talks: 

Tool box  talk  is carried out daily by HSE Department of DESCON  in both day and night shifts at 

various working  locations. Site management also participates along with workers  in these TBTs. 

The main TBT topics in this month were work at height, defensive driving, removal of coffer dam, 

manual lifting, housekeeping, rigg lifting, crane operation, vehicle movement, unsafe acts, use of 

PPEs, material stacking, electrical safety, behavior based safety, firefighting etc.. 

 

b) Site Inspections: 

Multiple site inspections were carried out by the Sr. Environmentalist and unsafe acts/conditions 

were  noted  and  communicated  to  the  Contractor’s  HSE  In  charge.  Table  2  shows  a  list  of 

noncompliance along with status of corrective action taken so far. 

Table 2 Non Compliances at site 

Sr.# 

 

Environmenta

l Issue 

Recommendatio

Severity Target date Follow up 

date  

Status

1.   Cartridges of UV filters have been found contaminated 

Replace the cartridges immediately 

High July 26, 2016 

July 30, 2016 

Cartridgesreplaced

2.   Stagnant water has been observed near main warehouse and in labor camp 

Drain out stagnant water immediately 

High  July 26, 2016 

July 30, 2016 

Addressed

3.   Hard barricading New LCC diversion is not proper 

Properly hard barricade the area as deep excavation can cause serious injury 

High July 26, 2016 

July 30, 2016 

Addressed

4.   Workers on Barrage (especially stone Apron and   new LCC) and Chanawan Road work 

Enforce PPEs on site especially under scaffoldings and high risk areas 

High July 26, 2016 

July 30, 2016 

MinorImprovemnt 

Page 35: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 32

without PPEs 

5.   UV module of 

water Filter at 

Canteen No. 3 

was non 

operational 

Replace the filter 

immediately 

High  August 9, 

2016 

August 10, 

2016 

Water Filter

changed 

6.   Internal walls of Labour Canteen look untidy. 

Labour Canteen require white wash at its interior walls 

Minor August 12, 

2016 

August 30, 

2016 

Addressed

7.   Lofty grass 

has been 

observed in 

Labour Camp 

as well as in 

staff camp 

Grass trimming is 

required on 

urgent basis 

High  August 12, 

2016 

August 30, 

2016 

Addressed

8.   Hygienic 

conditions of 

Labour 

Canteen and 

food quality is 

poor 

Improve food 

quality and 

hygiene 

conditions 

High   August 25, 

2016 

August 31, 

2016 

Partial 

improveme

nt 

9.   Lack of PPE’s 

for the 

workers 

working on 

Cook house 

and Annexe. 

At least shoes be 

provided to 

laborers working 

at these locations 

High  August 26, 

2016 

August 31, 

2016 

Partial 

improveme

nt 

10.   Wash rooms 

were found 

nonoperation

al in labor 

barracks  

Wash rooms 

should be made 

operational on 

urgent basis 

medium September 15, 2016 

September 25, 2016 

Addressed 

11.   Housekeeping in labor rooms in improper 

Daily sweeping is required in rooms 

medium  September 15, 2016 

September 25, 2016 

Addressed

12.   Lack of 

lighting at 

canal wards 

access route 

of DESCON 

staff camp 

Arrange proper 

lighting as in the 

dark snakes can 

bite any 

employee 

High   September 15, 2016 

September 25, 2016 

Addressed

13.   Hygienic 

conditions of 

Labour 

Improve food 

quality and 

hygiene 

High   September 

15, 2016 

September 25, 2016 

improveme

nt 

Page 36: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 33

Canteen and 

food quality is 

poor 

conditions 

14.   Lack of PPE’s 

for the 

workers 

working on 

Cook house 

and Annexe. 

At least shoes be 

provided to 

laborers working 

at these locations 

High  September 

15, 2016 

September 25, 2016 

improveme

nt 

 

c) Training of staff and workers: 

 

Training of workers and staff is arranged on regular basis to ensure the awareness of the project 

staff about  the health and safety  requirements of  the project site. For  this purpose, a separate 

training  room  has  been  provided where weekly  training  sessions  are  being  arranged. Multiple 

training  sessions have been  arranged  during  the  reporting period on  different  topics. Detail  is 

presented in Table 3: 

 

Table 3 Training to staff and workers 

 

Sr. No.  Date  Training Topic  No of Participant 

Trainer 

1.   01‐07‐2016  Crane Operation   15  Abdul Khaliq 

2.   15‐07‐2016  Scaffolding, Use of full body harness. 

17  Sahib Dino  

3.   18‐07‐2016  Defensive Driving  09  Abdul Khaliq 

4.   21‐07‐2016  Rigging & Lifting 15  Asif Kamran

5.   26‐07‐2016  HIV/AIDS  22  Nazir Ahmed 

6.   05‐08‐2016  Electrical Safety    31  Abdul Khaliq 

7.   13‐08‐2016  Scaffolding and Fall 

protection  

22  Abdul Khaliq 

8.   17‐08‐2016  Safety Plan for Flood   42  Abdul Khaliq 

9.   20‐08‐2016  Hand Injury 38  Atta ul Momin

10.   02‐09‐2016  Emergency Response Plan   37  Sahib Dino 

11.   07‐09‐2016  Defensive Driving   53  Asif Kamran 

12.   24‐09‐2016  Excavation  54  Abdul Khaliq

13.   29‐09‐2016  HIV/AIDS  58  Nazir Ahmed 

 

d) First Aid Center at site: 

An ambulance equipped with all necessary first aid tools has been provided by the Contractor to 

deal with any kind of emergency at site. The response time of this ambulance has been practiced 

at site to deal with any medical emergency. Twoparamedicsare deployed to deal with emergency 

including snake bite etc. MBBS doctor  is available at BHU newly constructed by  the contractor. 

Serious cases are referred to the Tehsil Headquarter Hospital at Wazirabad for treatment.  

 

e) Fire Prevention at site 

Page 37: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 34

The Contractor has provided  fire prevention  and  protection  system  at  site.At  the  advice  of  Sr. 

Environmentalist,  Fire  alarm  system  with  smoke  detectors  has  been  installed  in  the  main 

warehouse of DESCON NKBP. Fire Extinguishers have already been installed in Labour Colony and 

staff dormitories as well as in offices. The Contractor has provided 12 no. fire extinguishers to the 

Engineer’s  representative.  Its  installation  in  field  office  has  been  arranged  by Admin Manager 

SMEC.  

 

f) Security arrangements 

The overall security arrangements are satisfactory as security guards have been deployed by the 

Contractor  for the project site. Presently, there are three  (3) entry points  into the Project Area, 

two (02) on left side and one on right side of the Barrage. Security personnel have been deployed 

at  all  the  entry  points.  ZIMS  security  agency  has  been  deployed  for  the  security  of  the  site 

facilities.  The  vehicles  containing  construction material  enter  the  site  by  using  the  entry point 

located near  the Batching Plant. The  same point  is used  for  the entry of personnel. This entry 

point  is  equipped with  security  guards with  a  barrier  that  checks  the  employee  card  of  every 

person and then allows them to enter the site. The entry points of Labour Camp and Staff Colony 

are also equipped with security guards.  

 

(3) Environmental Management 

As per volume  IV of the Contract  (EMP),  it  is contractual obligation of the Contractor to comply 

with  all  local,  national  as  well  as  international  protocols  applicable  to  this  project.  For  this 

purpose, site specific Environmental Management Plans have been prepared and approved by The 

Engineer. 

A. Construction of Coffer Dam / River Water Quality Monitoring  

The Contractor raised the Coffer Dam on the Right Bank of River Chenab to facilitate construction 

of the remaining Barrage and the Right Guide Bank at upstream and downstream of New Khanki 

Barrage Section. Another Coffer Dam has been constructed on the upstream  left side of existing 

Head Works  to  facilitate  construction of  Left Guide Bank. As  the Coffer Dam  is  constructed by 

using clay and stone material inside River Chenab, this material can degrade the water quality and 

become a threat for the aquatic  life especially fish during construction/dismantling phase of the 

Coffer Dam. The surface water quality at the upstream and downstream of the Coffer Dams was 

however analyzed during the reporting period and was found to be satisfactory. 

 

(i) Surface Water Quality Monitoring 

River water quality monitoring was carried out by Environmental Officer of DESCON the presence 

of Safety  Inspector SMEC. Two to three samples were collected  from different points. Currently 

one Coffer Dam has been constructed to facilitate construction activities of Right U/S Guide Bank 

and dismantling of old head works at right side while second Coffer Dam has been made for the 

construction of guide bank at  the upstream side. The Guide Bank construction activities are on 

both left and right side of Old Barrage. 

 

(ii) Collection of Samples: 

One  sample was  collected  from  the upstream  side of Coffer Dam  raised  for dismantling of old 

head works while other  sample was collected  from  its downstream  side  to evaluate  impact on 

Page 38: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 35

river water quality. 

 

(iii) Analysis of Samples: 

The samples were analyzed on spot with  the equipment owned by DESCON. The samples were 

collected in sample holder and analyzed. The results of analysis are shown in Table‐4: 

Table 4 Surface water Quality Monitoring 

 

 

 Sr. 

No. 

Parameter  Unit  NEQS Baseline 

July‐16 August‐16  Sep‐16

U/s  D/s  U/s  D/s  U/s  U/s  D/s 

1  Temperature  C0  <=30 30 26.6 26.5 29.1 30.5 30.7  24.2  25.8

2  pH  ‐  6.6‐8.5  7.4 8.6 8.3 8.4 8.4 8.4  8.4  8.4

3 Total Dissolved 

Solids (TDS) mg/l  3500  110 110 170 80 180 240  90  80

4 Electrical 

Conductivity 

(EC) 

µs/cm  1055 N/A 240 280 160 180 280  190  170

5  Dissolved 

Oxygen (DO) mg/l  ‐  N/A 8.50 7.73 7.74 6.80 7.89  6.96  6.38

 

Analysis of results: 

From the above results, it is clear that Dissolved Oxygen is more than 4 mg/l i.e. minimum value 

for sustenance of aquatic life/fish; hence water is safe for sustenance of aquatic life.  

B. Air Emissions, Noise and control measure 

The  construction  activities  generate dust due  to excavation  and  vehicle movement. Diesel  and 

other petroleum products used  for  the operation of construction machinery and  transportation 

equipment also cause air pollution but the impacts generated from such activities need attention 

and  proper mitigation measures  are  required  to minimize  the  impact  on  human  health  and 

environment. The main pollutants  released by burning of  fossil  fuels and construction activities 

are CO, NO2, SO2, PM10 and PM2.5. The air emissions and air quality monitoring as stipulated  in 

EIA/EMP has been carried out, results of which are given below: 

1. Ambient Air Quality analysis: 

Air  quality  monitoring  helps  us  in  better  understanding  the  sources,  levels  of  different  air 

pollutants, effects of air pollution control measures and exposure of various substances in the air 

we breathe. It helps us in improving and developing air pollution control strategies to reduce the 

effect of air pollution. The ambient air quality analysis was carried out in the month of June 2016. 

Its results showed that all parameters were within NEQS. 

 

2. Generator’s emissions monitoring: 

Vehicles and generators are periodically checked  for  their maintenance. For  this purpose, noise 

and exhaust emission monitoring has been carried out. Moreover record for the change of Mobile 

Page 39: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 36

Oil for vehicles is also being maintained by the concerned department. These tests help assess the 

vehicular efficiency and need for its repair and maintenance. Its record is being maintained at E&P 

workshops  by  the  Contractor.  The  Generator  gaseous  emission  results  in  the  3rd  party 

Environmental Monitoring in June 2016 show that all parameters for generator’s emissions were 

within NEQS limit.  

 

3. Vehicles Emissions monitoring 

The vehicles gaseous emission  results  in 3rd Party Environmental Monitoring  in  June 2016 show 

that all the parameters were within NEQS limit and could be considered environmentally safe. 

4. Noise 

Noise survey for various equipment and machinery is being carried out on regular basis. The noise 

level is being monitored internally on monthly basis as well as externally on quarterly basis along 

with external monitoring. Noise monitoring of residential as well as construction site  is regularly 

being  carried  out  by  the  Contractor  and  Consultant’s  staff. During  the  reporting  period,  noise 

monitoring has been carried out at different points. The results are presented in Table 5: 

 

Table‐5 Noise Monitoring 

Sr. No. 

Equipment  NEQS S.R.O 1062 (1) 2010. Effected from July 01‐2012 

Noise level dB (A) 

Method

1  Transit Mixture CC 78114 

85 dB(A)   63.5   Digital Sound Meter 

2  Transit Mixture CC 78107 

85 dB(A)  62.8  Digital Sound Meter 

3  Transit Mixture CC 78113 

85 dB(A) 64.2  Digital Sound Meter 

4  Hilux LEE 9067  85 dB(A)  66.8  Digital Sound Meter 

5  Hilux LEE 5543  85 dB(A)  67.2  Digital Sound Meter 

6  Dumper Truck CC  77156 

85 dB(A) 67.5  Digital Sound Meter 

7  Dumper Truck CC  77150 

85 dB(A)  62.7  Digital Sound Meter 

8  Dumper Truck CC  77148 

85 dB(A)  63.4  Digital Sound Meter 

9  Dumper Truck CC  77154 

85 dB(A) 67.7  Digital Sound Meter 

10  Transit Mixture CC 78114 

85 dB(A)   63.5   Digital Sound Meter 

11  Dumper Truck CC  77154 

85 dB(A)   69.8   Digital Sound Meter 

Page 40: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 37

12  Dumper Truck CC  77159 

85 dB(A)  68.4  Digital Sound Meter 

13  Dumper Truck CC  77133 

85 dB(A) 68.2  Digital Sound Meter 

14  Dumper Truck CC  77157 

85 dB(A)  70.1  Digital Sound Meter 

15  Dumper Truck CC  77156 

85 dB(A)  67.9  Digital Sound Meter 

16  Dumper Truck CC  67161 

85 dB(A)  68.6  Digital Sound Meter 

17  Dumper Truck CC  67165 

85 dB(A)  69.3  Digital Sound Meter 

18  Dumper Truck CC  67159 

85 dB(A) 71.8  Digital Sound Meter 

19  Transit Mixture CC 

78126 

85 dB(A)   66.3   Digital Sound 

Meter 

20  Transit Mixture CC 

78118 

85 dB(A)  65.6  Digital Sound 

Meter 

21  Transit Mixture CC 

78114 

85 dB(A) 63.9  Digital Sound 

Meter 

22  Dumper Truck CC  

77151 

85 dB(A)  69.6  Digital Sound 

Meter 

23  Dumper Truck CC  

77150 

85 dB(A)  68.1  Digital Sound 

Meter 

6  Dumper Truck CC  

77146 

85 dB(A) 70.4  Digital Sound 

Meter 

24  HI‐ace  CC  76130  85 dB(A)  60.9  Digital Sound 

Meter 

25  Dumper Truck CC  

74151 

85 dB(A)  70.4  Digital Sound 

Meter 

Areas  

1 RGB  

75 dB(A)  61.3  Digital Sound Meter 

2   LGB Up Stream 

75 dB(A) 63.4  Digital Sound Meter 

3 Batch Plant 

75 dB(A)  52.6  Digital Sound Meter 

4 LCC Head Regulator 

75 dB(A)  68.2  Digital Sound Meter 

5  Coffer Dam Up Stream 

75 dB(A)  51.7  Digital Sound Meter 

6 Right guide bank 

75 dB(A)  58.6  Digital Sound Meter 

Page 41: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 38

7 Batch Plant 

75 dB(A)  53.2  Digital Sound Meter 

8 RGB Up Stream 

75 dB(A) 52.3  Digital Sound 

Meter 

9 Site Office Area 

75 dB(A)  52.7  Digital Sound 

Meter 

10 Batch Plant 

75 dB(A) 51.2  Digital Sound 

Meter 

11 LCC Head Regulator 

75 dB(A)  56.8  Digital Sound 

Meter 

 

Analysis of Results: 

The results show that all the parameters were within NEQS. The Contractor has complied with the 

recommendations of the Supervision Consultant to regularly carry out preventive maintenance. 

C. Tree cutting and removal 

A total of 2057 trees have been cut to date. No tree has been cut during the reporting period as 

reported by DESCON. The No. and location of trees cut to date is presented in Table 6: 

Table‐6 No. and Location of Tree cutting 

Serial No.  Area   Number of tree 

1.   RGB, Right Divide Wall, RMB 1287 

2.   NEW Lower Chenab Canal (LCC)  43 

3.   LMB Road  17 

4.   Chanawan Road  45 

5.   Laydown  Area,  Old  Mechanical  Colony,  Flood 

Office etc. 

665 

  Total   2057 

 

As  the  Contractor  and  Supervision  Consultants  are  committed  to  preserve  environment  and 

ensure minimum cutting of trees, design of RMB Road has been revised  from RD 39+000 to RD 

60+000. The trees between these two RDs has been excluded from cutting. Now, a revised list of 

365  trees  has  been  sent  to  District  Forest Officer  (DFO)  Gujrat  by  Executive  Engineer  Khanki 

Division for further processing. DFO (Gujrat) will assess the cost for auction of these trees. 

D. Tree Plantation Plan & Status 

In order to improve the Project Area Environment, EIA/EMP of NKBP envisaged the plantation of 

about 10,000 trees at different locations of New Khanki Barrage. The Contractor has started tree 

plantation at different  locations. Total 10,000 plants will be planted  in three phases as shown  in 

Table‐7.  In  this  connection,  the  Contractor  submitted  a  “Tree  Plantation  Plan”  to  the  TL/CRE 

which was approved by CRE/TL on June 09, 2016. 

 

Page 42: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 39

Table‐7: Proposed Tree Plantation

Phase  Period  Total Trees 

Phase 1  February to March 2016 4000 

Phase 2  September to November 2016 4000 

Phase 3  February to March 2017  2000 

 

Till April  30,  2016,  the  Contractor  planted  5123  trees  of  various  species  at  different  locations 

including  the  Staff Colony, BHU,  School,  LCC  and CRE Offices  etc.  Further plantation  has been 

planned  for  phase‐2  (from  September  to  November  2016)  that  is  already  in  progress.  The 

Contractor  has  provided  following  program  for  phase‐2.The  plantation  for  phase‐2  started  on 

September 29, 2016.  

Sr. No  

 Name of Plant 

 Plantation Area 

 Number 

1  

Cono  RMB Road  300 

2  

Neem  RMB Road  100 

3  

Astonia  Kot Jaffer Distributary   50 

4  

Ulta Ashok  Park Boundary  50 

5  

Termonaria  RMB Road  40 

6  

Bohr  Village ramps of LMB   10 

7  

Mango  Irrigation Colony  50 

 

E. Solid waste management 

Solid waste  is  collected  in  plastic  drums  from  residential  colonies  as well  as  from  site.  These 

drums  collect  waste  without  any  differentiation  of  reusable  and  recyclables.  All  the  waste  is 

collected  from  drums  and  transported  in  a  vehicle  for  final  disposal.  The  Contractor  is  now 

disposing off  its  solid waste  in  irrigation owned  land  known  as Bhattay Wali 200 meters  away 

from Khanki to Saroki Road and 300 meters away from Khanki village. It is a barren land, about 8 

to 9 Acre in area.  

 

Cement and Slag bags 

The  cement  and  slag bags  are  collected  and  stacked near  the batching plants  and  sold  to  the 

vendor  for recycling purpose. The rain damaged and solidified cement and slag bags have been 

stacked at the Defense Bund around Labor Barracks to strengthen it. 

Page 43: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 40

 

Scrape Iron and its Cuttings Small iron cuttings, wires and pieces are also generated in fabrication and construction activities. 

All  type of metallic waste  is  collected  from  site  for  re‐use or  recycling.  For  recycling purposes, 

scrape iron is sold to market.  

 

Medical Waste 

The medical waste is collected and segregated in the first aid center. In the dispensary, three bins 

are placed to segregate the medical waste into infectious, non‐infectious and general waste. The 

Contractor has assured he  is not using syringes or blades, as such sharp waste is not  included  in 

the waste. The waste  includes packaging of medicines and  infected cotton, bandages etc. With 

this covenant, the Contractor has been allowed to bury this waste as per Punjab Hospital Waste 

Management Rules 2014. Currently, the medical waste is collected at an optimum frequency and 

buried in the waste disposal area. 

 

F. Waste Water Quality Monitoring: 

Wastewater treatment is an important requirement at the construction sites since it ensures that 

the water  from  the domestic  as well  as  construction  activities does not harm  the  surrounding 

environment and allows the site to operate by meeting the NEQS. Waste water treatment is thru 

septic  tank  and  soakage  pit.  As  the  water  table  is  high  in  this  area,  soakage  pit  is  emptied 

frequently by using a water tank as communicated by HSE Department. This water tank sprinkles 

this water near Khanki Village away from populated area on a barren land.  

G. Staff and Labour Welfare 

DESCON as the Contractor for New Khanki Barrage seems to be committed to facilitate its labour 

force. For this purpose, The Contractor has provided cooling facility at Labour Barracks and staff 

dormitories. 

 

Two mosques  have  been  provided  to  offer  prayers  by  the  staff  / workers  and  to 

celebrate religious festivals. 

Guard rooms have been constructed on entrance gate of the project site along with 

security guard to keep an eye on all incoming staff, visitors and vehicles. 

General store has also been provided for the purchase of ordinary consumable items 

in the Labour Camp and Staff Colony. 

Other utility  shops  like barber  shop,  fruit  shops,  laundry  shop, etc. have also been 

provided to the workers living inside the Labour Barracks. 

Lighting arrangements have been provided in the wash rooms and bathrooms  

Roofing of  the wash  rooms  is  almost  complete  and bathrooms have been  covered 

with GI sheets. 

Installation of room air coolers in Labour Barracks is also complete  

Two electric water coolers have also been provided for the  labor  in Labour Barracks 

to provide drinking water.  

Page 44: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 41

Walkways  have  been  constructed  for  the  washrooms  and  living  rooms  in  Labour 

Camp. 

Surface Drainage all along the Labour Camp and Batching Plant is complete. 

Plantation in Officer Camp using different land scape style has been carried out. 

Insecticide spray was carried out for mosquitoes and other reptiles in the Staff Colony 

and Labor Camp. 

Drinking water has been arranged in all working areas of the Site. 

(4) Implementation of Social Safeguard Policies:  

The ADB's social safeguard policies are a cornerstone of  its support for sustainable development 

projects. The objective of these policies  is to prevent and mitigate undue harm to people  in the 

development  process.  The  effectiveness  and  development  impact  of  projects  and  programs 

supported  by  the  Bank  has  substantially  increased  as  a  result  of  attention  to  these 

policies.Safeguard policies have often provided a platform for the participation of stakeholders in 

the project design, and have been an  important  instrument  for building ownership among  local 

population/community.  

a) Public Consultations: 

 

During the reporting period, multiple sessions of public consultations were arranged by the social 

team. One public meeting was held  at Golayki  to  address  the  issue of  the  local  residents. The 

meeting was held at the Dera of Ch. Akram.17 number of participants expressed their concerns. 

Waheed  Ahmad  Deputy  Director  PMO,  Syed  Raza  Mashhadi  (Senior  Sociologist)  and  Hamdi 

Cheema (Social Enumerator) were also there.  

 

Local  community  raised  an  issue  that  there was  a protection bund on Downstream Right  Side 

Guide Bank to protect their lands from flood before the project started. Now that protective bund 

has  been  demolished  and  their  agriculture  land  is  vulnerable  to waters  in  flood  season.    The 

community was  told  by  the  Social  Team  that  the  new  barrage  has  been  constructed  900  ft. 

downstream  of  the  existing  head works.    In  the  end,  it was  decided  in  the meeting  that  the 

community  shall write  an  application  to  the  Project  Director  and  elaborate  their  concerns  in 

details. The issue will be resolved once it is approved by the PD, PMO Lahore. 

Another public meeting was arranged at Ratto Wali to address the issue of the residents regarding 

paved Ramps and access road leading to the village.  

Due to the construction of LMB Road, the said village, situated at LMB Road, has been prone to 

the rain water due to its lower level from the road. The village is adjacent to the road and higher 

level of  the  road makes  the  village  vulnerable  to  rain water  infiltration  into  their houses.  This 

situation has also caused their road/path to deteriorate badly. The residents are  in need of the 

ramps to step down and up for approaching city. 

Moreover,  the  rain water  lands  directly  into  their  houses without  any  hurdle  in  the way.  An 

application has been sent to PMO Office for necessary action to be taken.  

Page 45: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 42

  G. COMPLIANCE WITH LOAN COVENANTS

Of the twenty five (25) covenants, twenty one (21) are complied with, four (4) are not yet due. Covenant for NKBP: Loan 2841-PAK(SF) Sr. No.

Reference Covenant Status as of 30 June

2016 Loan agreement

1 LA Schedule 3, Para 6 (a) Except as ADB may otherwise agree, the Borrower shall cause Punjab to establish, within one month of the Effective Date, an imprest account at the National Bank of Pakistan. The imprest account shall be established, managed, replenished and liquidated in accordance with the Loan Disbursement Handbook and detailed arrangements agreed upon between the Borrower and ADB. The imprest account shall only be used for the purposes of the Project. The currency of the imprest account shall be Dollar. The ceiling for the imprest account shall not exceed the lower of (i) the estimated expenditure to be financed from the imprest account for the first 6 months of Project implementation, or (ii) the equivalent of $1.5 million.

Complied with

2 LA Schedule 4, Para 7 The Project Executing Agency shall not award any Works contract which involves environmental impact until:

(a) The IEE has been approved by ADB; and (b) The Project Executing Agency has

incorporated relevant provisions from the EMP into the Works contract.

Complied with

3 LA Schedule 4, Para 8 The Project Executing Agency shall not award any Works contract which involves involuntary resettlement impact until the Project Executing Agency has prepared and submitted to ADB the final LARP based on the Project’s detailed design, and obtained ADB’s clearance of such LARP.

Complied with

4 LA Schedule 4, Para Contracts procured under International Competitive Complied with

 

b) Employment for the local residents: 

The Contractor is bound to provide maximum employment to unskilled/skilled labour of the “local 

area”. The “local area”  is considered by  Irrigation Department as the area  irrigated by the Canal 

(LCC) emerging from the Khanki Head Works. This area  includes 8 districts of Punjab  irrigated by 

LCC and Gujrat as a nearby area of  the Barrage. Currently 861 employees are performing  their 

duties/work  at  the  New  Khanki  Barrage  on  September  30,  2016  whereas  543  workers  are 

employed from the eight districts irrigated by LCC and Gujrat as nearby area.  

  

Page 46: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 43

Sr. No.

Reference Covenant Status as of 30 June

2016 12 Bidding procedures and contracts for Consulting

Services shall be subject to prior review by ADB, unless otherwise agreed between the Project Executing Agency and ADB and set forth in the Procurement Plan.

5 LA Schedule 4, Para 13

The Project Executing Agency shall seek ADB’s approval before it:

a. grants any extension of the stipulated time for completion of a contract for Works;

b. agrees to any modification or waiver of the conditions of a contract for Works, including any change order that falls under (c) or (d) of this paragraph;

c. issues any change order under a contract for Works that will in aggregate increase the original contract price (for the avoidance of doubt, such aggregate shall take into account any previous or simultaneous change order or orders under such contract); or

d. (d) issues any change order under a contract for Works that will affect more than 15% of the original contract price (either through increases or decreases), even if the net effect of such change order will not in aggregate increase the original contract price. For the avoidance of doubt, such aggregate shall take into account any previous or simultaneous change order or orders under such contract.

Being complied Not yet due Not yet due

6 LA Schedule 4, Para 14

ADB undertakes to respond to each request for approval under paragraph 13 above within 10 business days (in Manila and Islamabad) of ADB’s receipt of such request. Such response will indicate that the request is (a) approved, (b) declined, or (c) pending receipt of additional information or documentation or (d) pending consideration by ADB’s Procurement Committee, in each case as determined by ADB. If ADB fails to respond within 10 business days (in Manila and Islamabad) of ADB’s receipt of such request, the request (except if it relates to consideration by the Procurement Committee) shall be deemed to have been approved by ADB. In the case of (c), the Project Executing Agency shall promptly provide the requested information or documentation to ADB and ADB undertakes to respond to the relevant request within 10 business days (in Manila and Islamabad) upon receipt of such requested information or documentation satisfactory to ADB. In the case of (d), ADB shall notify the Project Executing Agency of the decision by the Procurement Committee within 10 business days (in Manila and Islamabad) of such decision by the Procurement Committee.

Being complied

7 LA Schedule 4, Para 15

The Borrower shall, or shall ensure that the Project Executing Agency will:

a. provide a copy of all time extensions, modifications or waivers to the contracts (including change orders) requiring ADB’s

Being complied

Page 47: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 44

Sr. No.

Reference Covenant Status as of 30 June

2016 approval in accordance with paragraph 13 above to ADB for its record promptly after signing; and

b. maintain an accurate record of all change orders under all contracts for Works which do not require ADB’s prior approval under paragraph 13 above and submit such record for ADB’s review every six months.

Being complied

8 LA Schedule 5, Para 1 The Borrower shall ensure that the Project is implemented in accordance with the detailed arrangements set forth in the PAM and Schedule 3 of the FFA. Any subsequent change to the PAM shall become effective only after approval of such change by the Project Executing Agency and ADB. In the event of any discrepancy between the PAM and/or Schedule 3 of the FFA and this Loan Agreement, the provisions of this Loan Agreement shall prevail.

Complied with

Project Agreement

9 PA Article II, Particular Covenants Section 2.08.

(b) Without limiting the generality of the foregoing, the Project Executing Agency shall furnish to ADB quarterly reports on the execution of the Project and on the operation and management of the Project facilities. Such reports shall be submitted in such form and in such detail and within such a period as ADB shall reasonably request, and shall indicate, among other things, progress made and problems encountered during the quarter under review, steps taken or proposed to be taken to remedy these problems, and proposed program of activities and expected progress during the following quarter.

(c) Promptly after physical completion of the Project, but in any event not later than 3 months thereafter or such later date as ADB may agree for this purpose, the Project Executing Agency shall prepare and furnish to ADB a report, in such form and in such detail as ADB shall reasonably request, on the execution and initial operation of the Project, including its cost, the performance by Punjab of its obligations under this Project Agreement and the accomplishment of the purposes of the Loan.

Complied with Not yet due

Page 48: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 45

Sr. No.

Reference Covenant Status as of 30 June

2016 10 PA Article II, Particular

Covenants Section 2.09.

(a) Punjab shall cause PID to (i) maintain separate accounts for the Project; (ii) have such accounts and related financial statements (balance sheet, statement of income and expenses, and related statements) audited annually, in accordance with appropriate auditing standards consistently applied, by independent auditors whose qualifications, experience and terms of reference are acceptable to ADB; and (iii) furnish to ADB, promptly after their preparation but in any event not later than 6 months after the close of the fiscal year to which they relate, certified copies of such audited accounts and financial statements and the report of the auditors relating thereto (including the auditors' opinion on the use of the Loan proceeds and compliance with the financial covenants of the Loan Agreement as well as on the use of the procedures for imprest account and statement of expenditures), all in the English language. Punjab shall furnish to ADB such further information concerning such accounts and financial statements and the audit thereof as ADB shall from time to time reasonably request.

Being Complied

11 PA Article II, Particular Covenants Section 2.12

Except as ADB may otherwise agree, Punjab shall not sell, lease or otherwise dispose of any of its irrigation and water resources assets which shall be required for the efficient carrying on of its operations or the disposal of which may prejudice its ability to perform satisfactorily any of its obligations under this Project Agreement.

Complied with

12 PA Schedule, Implementation arrangement Para 1 (Covenants uploaded in e-ops)

Implementation Arrangement The Project Executing Agency shall ensure that the Project is implemented in accordance with the detailed arrangements set forth in the PAM and Schedule 3 of the FFA. Any subsequent change to the PAM shall become effective only after approval of such change by the Project Executing Agency and ADB. In the event of any discrepancy between the PAM and/or Schedule 3 of the FFA and this Project Agreement, the provisions of this Project Agreement shall prevail.

Complied with

13 PA Schedule, Environment, Para 2 (Covenants uploaded in e-ops)

Environment The Project Executing Agency shall ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with (a) all applicable laws and regulations of the Borrower relating to environment, health, and safety; (b) the Environmental Safeguards; (c) the EARF; and (d) all measures and requirements set forth in the respective IEE and EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.

Complied with

Page 49: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 46

Sr. No.

Reference Covenant Status as of 30 June

2016 14 PA Schedule, Land

Acquisition, Para 3 (Covenants uploaded in e-ops)

Land Acquisition The Project Executing Agency shall ensure that all land and all rights-of-way required for the Project and all Project facilities are made available to the Works contractor in accordance with the schedule agreed under the related Works contract and all land acquisition and resettlement activities are implemented in compliance with (a) all applicable laws and regulations of the Borrower relating to land acquisition and involuntary resettlement; (b) the Involuntary Resettlement Safeguards; (c) the LARF; and (d) all measures and requirements set forth in the LARP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.

Being complied

15

PA Schedule, Land Acquisition, Para 4 (Covenants uploaded in e-ops)

Without limiting the application of the Involuntary Resettlement Safeguards, the LARF or the LARP, the Project Executing Agency shall ensure that (a) no land shall be acquired for the purposes of the Project under the emergency acquisition provisions of the Borrower’s Land Acquisition Act (1984), as amended, and (b) no physical or economic displacement takes place in connection with the Project until:

(i) compensation and other entitlements have been provided to affected people in accordance with the LARP; and

(ii) a comprehensive income and livelihood

restoration program has been established in accordance with the LARP.

Being complied

16 PASchedule, Indigenous Peoples Para 5. (Covenants uploaded in e-ops)

Indigenous PeoplesThe Project Executing Agency shall ensure that the Project does not have any indigenous people’s impacts within the meaning of the Safeguard Policy Statement. In the event that the Project does have any such impact, The Project Executing Agency shall take all steps required to ensure that the Project complies with the applicable laws and regulations of the Borrower and the Safeguard Policy Statement.

Complied with

17 PA Schedule, Human and Financial Resources to Implement Safeguards Requirements, Para 6. (Covenants uploaded in e-ops)

Human and Financial Resources to Implement Safeguards Requirements Punjab shall make available necessary budgetary and human resources to fully implement the EMP and the LARP.

Complied with

18 PA Schedule, Safeguards – Related Provisions in Bidding Documents and Works Contracts Para 7. (Covenants uploaded in e-ops)

Safeguards – Related Provisions in Bidding Documents and Works Contracts The Project Executing Agency shall ensure that all bidding documents and contracts for Works contain provisions that require contractors to:

(a) comply with the measures and requirements relevant to the contractor set forth in the IEE, the EMP and LARP (to the extent they concern impacts on affected people during

Being complied with

Page 50: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 47

Sr. No.

Reference Covenant Status as of 30 June

2016 construction), and any corrective or preventative actions set out in a Safeguards Monitoring Report;

(b) make available a budget for all such

environmental and social measures; (c) provide the Project Executing Agency with a

written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP or the LARP;

(d) adequately record the condition of roads,

agricultural land and other infrastructure prior to starting to transport materials and construction; and

(e) fully reinstate pathways, other local

infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction;

Complied with Complied with Complied with Not yet due

19 PA Schedule, Safeguards Monitoring and Reporting Para 8. (Covenants uploaded in e-ops)

Safeguards Monitoring and Reporting The Project Executing Agency shall do the following:

(a) submit quarterly Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission;

(b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP or the LARP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan;

(c) no later than 6 months after the date of

effectiveness of the Loan Agreement, engage a qualified and experienced external expert or qualified NGO under a selection process and terms of reference acceptable to ADB, to verify information produced through the Project monitoring process, and facilitate the carrying out of any verification activities by such external expert; and

(d) Report any actual or potential breach of compliance with the measures and requirements set forth in the EMP or the LARP promptly after becoming aware of the breach.

Complied with Complied with Complied with Not yet due

20 PA Schedule, Prohibited List of Investments

Page 51: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 48

Sr. No.

Reference Covenant Status as of 30 June

2016 Prohibited List of Investments Para 9. (Covenants uploaded in e-ops)

Punjab shall ensure that no proceeds of the Loan are used to finance any activity included in the list of prohibited investment activities provided in Appendix 5 of the SPS.

Complied with

21 PA Schedule, Health and Labor Standards Para 10. (Covenants uploaded in e-ops)

Health and Labor Standards The Project Executing Agency shall ensure that all contractors: (a) comply with all laws and mandated provisions on labor, health, safety, sanitation and working conditions; (b) use their best efforts to employ women and local people negatively affected by, or living in the vicinity of, the Project; (c) disseminate information at worksites and campsites for those employed during construction on (i) the risks of sexually transmitted diseases and HIV/AIDS and (ii) the prevention of trafficking of women and children; (d) are required not to differentiate between men and women’s wages or benefits for work of equal value; (e) provide accommodation to construction workers at campsites during the construction period and ensure that all work sites and campsites are safe for all employees, service providers, the public and road users; (f) eliminate all forms of forced or compulsory labor; (g) allow freedom of association and the right of assembly; and (h) abstain from engaging persons below the legally employable age in Pakistan.

Complied with

22 PA Schedule, Governance and Corruption, Para 11 (Covenants uploaded in e-ops)

Governance and CorruptionPunjab shall, and shall cause PID to, (a) comply with ADB’s Anticorruption Policy (1998, as amended to date) and acknowledge that ADB reserves the right to investigate directly, or through its agents, any alleged corrupt, fraudulent, collusive or coercive practice relating to the Project; and (b) cooperate with any such investigation and extend all necessary assistance for satisfactory completion of such investigation.

Complied with

23 PA Schedule, Governance and Corruption, Para 12 (Covenants uploaded in e-ops)

The Project Executing Agency shall ensure that (a) relevant provisions of ADB’s Anticorruption Policy are included in all bidding documents for the Project; (b) all contracts finance by ADB in connection with the Project include provisions specifying the right of ADB to audit and examine the records and accounts of PID and PMO Barrages, and all contractors, suppliers, consultants, and other service providers as they relate to the Project; (c) an external audit of procurement activities is carried out at least twice during the Project implementation.

Complied with

24 PA Schedule, Governance and Corruption, Para 13 (Covenants uploaded in e-ops)

The Project Executing Agency shall use PID’s existing website to present financial statements and track procurement contract awards, and include information on, among other things, the list of participating bidders, name of winning bidders, basic details on bidding procedures adopted, amounts of the contracts awarded, the list of goods and/or services purchased, and their intended and actual utilization.

Complied with

25 PA Schedule, Auditing Auditing and Monitoring

Page 52: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 49

Sr. No.

Reference Covenant Status as of 30 June

2016 and Monitoring, Para 14 (Covenants uploaded in e-ops)

The proceeds of the Loan may be used to finance the expenditures for (a) the annual audits of Project accounts and financial statements in accordance with Section 2.09 of this Project Agreement, and (b) the external audit in accordance with paragraph 12(c) above, provided that the auditors have qualifications, expertise, and terms of reference acceptable to ADB, and are selected in accordance with the procedures acceptable to ADB.

Being complied

H. MAJOR PROJECT ISSUES AND PROBLEMS

1. Summary of the major problems and issues affecting or likely to affect implementation progress such as compliance with covenants, achievement of immediate development objectives. Issues

No major problems and issues. Recommend actions to overcome these problems and issues (e.g. changes in scope, changes in

implementation arrangements and reallocation of loan proceeds) Action Plan Not Applicable

Page 53: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 50

Annex 1-Status of Preparation, Vetting and Implementation of Resettlement Plan as on 30-06-2016 Amounts in Million PKR

No. Contract No. Status of Preparation, Vetting

and Approval of RPs

Compensation Due

Implementation %

Implementation Status of Award of Civil Works Contracts No. of

APs Amount

Due

Total APs Paid

Amount Paid

APs Paid

% Amount

Paid

1 New Khanki Barrage (NKB) Project.

RP Draft Land acquisition and Resettlement Plan (LARP) for New Khanki Barrage was prepared and submitted to ADB for approval. ADB cleared the draft LARP on 07.07.2012. LARP was revised/ updated and cleared by ADB in Feb 2014 which is being implemented.

40

Not yet due

Not yet due

Not yet due

Not yet due

Not yet due

Awarded

Page 54: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 51

Annex 2 – Revised ImplementationSchedule (As of May 2015)

Page 55: EA Progress Report...15 Physical progress 86% (Revised Schedule) 16 To-date contracts award Pak Rs. 22,127.540 ($232.150) 17 To-date disbursement Pak Rs. 15,136.478 Million ($ 147.694

Quarterly Progress Report No.19 (July to September 2016)

New Khanki Barrage Construction Project Page 52