dynamics and vibration design of the ringhals motor

16
1 Dynamics and vibration design of the Ringhals Motor-Generator set Energiforsk - Seminar 2016-10-04 MG1 MG2 Åsa Collet, ÅF [email protected]

Upload: others

Post on 16-Oct-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

1

Dynamics and vibration design of the Ringhals Motor-Generator set

Energiforsk - Seminar2016-10-04

MG1

MG2

Åsa Collet, ÅF [email protected]

Dynamics and vibration staff

• Jean-Claude Luneno ÅF

• Åsa Collet ÅF

• Rolf Gustafsson Vattenfall AB, R&D

• Lena Skoglund Vattenfall, Ringhals AB

2

Quality

gro

up

Functionality

The motor-generator set (MG-set) at Ringhals 2 supplies

the control rods drives with power. For redundancy reasons,

two parallel MG-sets are used, one of which is dimensioned

to be able to supply all control rod drives with power.

3

Factory Acceptance Test

• Convert 50 Hz to 60 Hz power

• When the generator spin speed drops from N1=1800rpm to N2=1605rpm during a time period of 1sec the minimum change rate of the kinetic energy stored in the spinning flywheel should be P=100kW

Dynamic design requirements for assembled and installed MG-setVibration and structure integrity

• Dynamics and structural integrity should be checked in steady

state conditions as well as transient conditions caused by start-up

or electrical failure such as 2-phase and 3-phase short circuit.

• Primary Stress

• Lateral resonances

• Torsional resonances

• The design of the standing frame of the MG-set shall take into

account the dynamic stiffness of the floor on site.

4

This shall apply for all allowed temperature and load ranges!

Primary StressDynamic Requirements

Yield strength

Rp0,2

[MPa]

Fracture

strength Rm

[MPa]

Torsional

strength sv

[MPa]Static

parts

240 360 -

Rotating

parts

270 490 190

5

Table 1: Material properties for unknown materials

Start up and Fault Cases (2-phase and 3-phase short

circuit)

- Sf = 1,5 for all parts

The torsional yield strength used is 126MPa, where a safety

factor of 1.5 is considered.

MG-set design

6

Cut view MG-set

7

SimulationModal analysis: Ansys work bench as 3D modelsTorsional analysis: DyRoBeS

DyRoBeS: Rotordynamicmodelling of MG-set

8

• The upper springs in represent the stiffness of the used SKF bearings,

• The lower springs represent the stiffness of the standing frame.

• The springs connected to station 7 and 25 represent the magnet pulling forces modelled

with negative spring constants.

• Station 33 to 37 represent the weights of motor stator, gear box housing and generator

stator.

Torque Start-up curve

Induction motor torque as function of speed

9

Torque and Current as a Function of Speed

I, U=100% T, U=100% I, U=80% T, U=80%

n/ns

10,90,80,70,60,50,40,30,20,10

I/In

8

7

6

5

4

3

2

1

0

T/Tn

4

3,5

3

2,5

2

1,5

1

0,5

0

T = 3 x Tn

was used in transients

start-up simulation.

Tn = 846Nm.

Motor speed as function of time

10

Large fluctuations in rotor speed occur about 7.5 seconds after start.

Results – Start-uptorsional stress

OK: 116 Mpa < 126 MPa

11

Results Start-Upvibratory torque

Almost 15 times higher amplitude

magnitude torque (12520 Nm) than nominal (846 Nm) =

an important design parameter for selecting gear box!

12

2-Phase short circuit excitation torque as a function of time Induction motor torque as function of time

13

2-Phase Short Circuit

Torque Equation

t [ms]

2001901801701601501401301201101009080706050403020100

T/Tn

15

14

13

12

11

10

9

8

7

6

5

4

3

2

1

0

-1

-2

-3

-4

-5

-6

-7

-8

-9

-10

-11

-12

-13

-14

-15

T = 9 x Tn

was used in transients

start-up simulation.

Tn = 846Nm.

Results – 2-phase short circuit

OK: 120 MPa < 126 MPa

14

ODS of running MG1 – spectrumenvelope of 20 measurement points in x y z direction

All points below 0.9 mm/s rms < requirement 2.8 mm/s rms

18010 10050 15020 30 40 60 70 80 90 110 120 130 140 160

Hz

0.9e-3

20.0e-6

0.1e-3

0.2e-3

0.3e-3

0.4e-3

0.5e-3

0.6e-3

0.7e-3

0.8e-3

0.2e-3

0.3e-3

0.4e-3

0.5e-3

0.6e-3

0.7e-3

0.8e-3

0.9e-3

Am

plit

ude

m/s

1.00

0.00

Am

plit

ude

10.00

F Spectrum Envelope_MG1_100kW_w arm

15

ODS animation at f= 150 Hz

Test verification was performed with LMS Test.Lab

What we learned!

16

• Large electrical machines must be treated in a special way

during design phase. Don’t miss to check transient

conditions caused by start-up or electrical failure such as

2-phase and 3-phase short circuit.

• Material input data is not easy for a supplier to declare for

the components i.e. steel of shaft etc. Define your own

material requirements in purchase requirements!

• Nominal torque for a motor start-up for the individual

motor component may be scaled up couples of

magnitudes when motor is assembled in a large machine.

• ……….AND A LOT MORE!!!!