dune installation and manpower schedule for single phase ......-repack 2 apas in box-4h • apa...
TRANSCRIPT
William Miller
University of Minnesota
28-March, 2018
Dune Installation and Manpower Schedule
for Single Phase Detector
Overview • ProtoDUNE Installation Schedule
- APA
- CPA
• Schedule Assumptions and Overview
- When do we need to start?
• Mechanical Tests at Ash River
• Integration and Testing Facility
• Single Phase Installation and Manpower Schedule
• Summary and Comments
ProtoDUNE
28-March-18 William Miller | Dune Installation Schedule 3
While this is certainly a prototype
and installation times are much
longer, there are design
modifications required in decrease
installation times
• TPC component delivery schedule
- Numerous adjustments were made
to the installation schedule while
waiting for parts
• Safety Approval and
Documentation
- This task took many man-weeks of
effort, safety approval took even
longer
The first drift volume in DUNE
ProtoDUNE APA: ~100 hrs 2-5 FTEs
28-March-18 William Miller | Dune Installation Schedule 4
• Opening up the APA shipping crate, load test on the yoke and mounting the lifting fixture took ~10 hours with 4-5 FTEs plus 3 CERN riggers
- Clearly new design of box and lifting fixture required
• Picking up the APA, rotating it into a vertical position, lowering into the SAS and transferring the load to the Transport beam ~3 hours 3 FTEs plus 4-5 CERN Riggers
~13 hours 3-5 FTEs & Riggers
ProtoDUNE APA-Cleanroom
28-March-18 William Miller | Dune Installation Schedule 5
• Install cable trays and remove protection- ~2 hours 2 FTEs
• Vibration, Inspection and Photogrammetry- ~10 hours 1 FTE
• Install protection- ~1 hour 2 FTEs
• Cold Electronics- ~20 hours 2 FTEs
- ~8 hours 2 FTEs pre-boards and test
- ~8 hours 2 FTEs install & test on APA
- ~4 hours 2 FTEs to dress cables
• PD Installation- ~32 hours 2-4 FTEs
- ~16 hours 2 FTEs Test PD in test box
- ~8 hours 4 FTEs Insert PDs
- ~8 hours 2 FTEs to cable, test and dress
• Remove protection- ~1 hour 2 FTEs
~65 hours 2-4 FTEs
ProtoDUNE APA-Cold Box
28-March-18 William Miller | Dune Installation Schedule 6
This work or similar would happen at the ITF
• Open Cold Box- ~2-3 hours 2 FTEs & 2 CERN crane operators
• Attach transport beam to Cold box beam-1 hour 2 FTEs
• Roll APA into Cold Box and disconnect Beam- 1 hour 2 FTEs
• Feed cables in Feed Through- 1 hour 4 FTEs -2 man-lifts
• Cable to electronics ~3 hours 2 FTEs
• Close Cold Box- ~2-3 hours 2 FTEs & 2 CERN crane operators
~ 11 hours 2-3 FTEs
ProtoDUNE APA- Into cryostat
28-March-18 William Miller | Dune Installation Schedule 7
• Open cold box- ~2-3 hours 2 FTEs & 2 CERN crane operators
• Disconnect cables from electronics and secure cables-~2 hours 4 FTEs
• Connect transport beam to Cold Box- 1 hour 2 FTEs
• Move into cleanroom, replace bad electronics and re-test- 2-8 Hours 2 FTEs
• Attach transport beam to TCO beam- 1 hour 2 FTEs
• Move APA into cryostat- 1 hour 4 FTEs
~9-13 hours 2-4 FTEs
ProtoDUNE- CPA/FC: ~30 hrs
28-March-18 William Miller | Dune Installation Schedule 8
• Unpack, bolt together, add field shaping strips, test and hang single CPA- ~6 hours 3 FTEs
• Unpack second CPA and join with first to make a pair- ~6 hours 3 FTEs
• Lower 2 top field cages, inspect, test and install on CPA pair- ~8 hours 3-4 FTEs plus 3 CERN Crane operators ~ 6 hours
• Lower 2 bottom field cages, inspect, test and install on CPA pair- ~8 hours 3-4 FTEs plus 3 CERN Crane operators ~ 6 hours
• Attach transport beam to TCO beam and move into cryostat- 4 FTEs ~2 hours
First completed CPA-FC assembly
Comparing ProtoDUNE to DUNE
28-March-18 William Miller | Dune Installation Schedule 9
• The times shown for
ProtoDUNE are linear many
because of space constraints
in the 109sq. M cleanroom
• In DUNE we are moving the
PD installation and CE board
installation to the ITF. APA
and CPA are done in parallel.
Need 3 APA stations. Cables
will be done underground.
• ProtoDUNE
- APA: 98 Hours
- CPA: 30 CPA
• DUNE-12m 3 APA & 2 CPA
• ITF-APA ~30h
- Unpack-Hang Vertical-4h
- Install PDs and Test-8h
- Install CEs and Test-8h
- Cold box-In and Out-4h
- Repack 2 APAs in Box-4h
• APA Underground-Vic Est. ~24h
- 24 hours (3 ten hr shifts) to unpack, rotate into position, bolt together, cable and test
• CPA Underground-Vic’s Est.
- 8 hours (1 ten hr. shifts) to unpack, rotate 6 CPA pieces, bolt together, add Top and Bottom Field cages, make all electrical connections
Installation Schedule Overview
28-March-18 William Miller | Dune Installation Schedule 10
Beneficial Occupancy of the first Cryostat in the end of December 2022
The Basic Logistic Concept
28-March-18 William Miller | Dune Installation Schedule 11
• ~ 1 week buffer of TPC components underground and ~1 month at ITF
• Access underground controlled by SDSTA, slung loads take ~66 min, regular cage loads ~17 minutes. Personnel trips max 30 people ~15 minutes
Schedule Assumptions
28-March-18 William Miller | Dune Installation Schedule 12
• Lessons learned from
ProtoDUNE point out there are
numerous design modifications
required to reduce installation
time for SP DUNE detector
• The weekly installation
schedule assumes:
- We can install three APAs pairs
(2 vertically stacked)
- Two 12m CPA/FC assembly
- Move them into the cryostat,
deploy Field Cages and run
APAs cables into feed-thru
28-March-18 William Miller | Dune Installation Schedule 13
• Working two 10 hour shifts/4 days per week. Friday would be schedule contingency
• 2 APAs install/day so there is not time to install PD and CE underground, cables must be installed underground
• Shipping box design must be light weight, reusable, meet cage design criterial and able to make cage rotation
• ~ 1 week buffer of TPC components underground and ~1 month at ITF
• Access underground controlled by SDSTA
Installation Assumptions
What happens before B.O.?
28-March-18 William Miller | Dune Installation Schedule 14
• Design-Complete installation concept so engineered design can begin for TCP components and ITF concept
• Mechanical tests at Ash River to confirm that modifications will work
• Test pre-production APA, CE & PD at CERN in cold box
• Commission Integration and Testing Facility
• Begin testing of first TPC components
FY18 FY19 FY20 FY21 FY22
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Design
Mechanical
Pre-Production
Commission ITF
Testing ITF
DUNE Trial Assembly at Ash R
28-March-18 William Miller | Dune Installation Schedule 15
• NOvA Far detector assembly
area is 16.75m deep from
the loading bay with a hook
height of 6.1m on the crane
• The open loading bay area
is 21m x 21m if needed
• Two 10-ton overhead
cranes, tools, fork lifts, small
machine shop, etc. available
• Experienced crew that
helped build ProtoDUNE
staffed at Ash River
28-March-18 William Miller | Dune Installation Schedule 16
Dune
Assembly
Prototype
Area
17m
Glue machine will be removed
If needed NOvA access scissor lifts can be removed to
increase width ~20m
28-March-18 William Miller | Dune Installation Schedule 17
Dune
Assembly
Prototype
Area
16.75m
28-March-18 William Miller | Dune Installation Schedule 18
View looking North from NOvA assembly area to loading dock
Schedule for ITF: Pre-B.O.
28-March-18 William Miller | Dune Installation Schedule 19
ITF Cold Test Assumptions
28-March-18 William Miller | Dune Installation Schedule 20
• We need to cold test 6
APAs/week during the full speed
assembly of the Far Detector
• This requires ~6 cold boxes with
a cryogenic system
• It takes ~1 week to install, PD,
CE and about ~1 week for the
cold test
• This number can be reduced if a
large number of the APAs are
tested longer before assembly
begins and there is enough
space for a storage buffer
Building would need to be about 10-12,000 sq. ft. with an overhead
crane with 8m hook clearance
Need to better define tasks/tests to estimate FTE requirements
Underground Installation Schedule• Current installation schedule
is based on a top down
estimate to fit between the
beneficial occupancy's of the
first and second caverns.
• Time and motion studies from
the ProtoDUNE point to many
potential engineered
solutions that can help reduce
both the manpower and
schedule, but schedule is
extremely aggressive
• Shipping box design is critical
• DUNE crew does all the
rigging, box moving &
opening and moving TPC
components in the cryostat
• The different consortia do all
the cabling, testing and
commissioning
• First estimate is roughly 20
FTE DUNE crew, 30 FTE
consortortia
• Small ramp-up and ramp-
down installation
Underground Installation Phases
28-March-18 William Miller | Dune Installation Schedule 22
There are five major phases of the installation
• 2.1.3 Design
This is the design effort needed between the review of the TDR and the start of the production of the SP-TC infrastructure necessary for detector installation.
• 2.1.4 Production of Common Equipment
Production of the equipment which may be used for the second detector. It represents the costs that do not scale with the number of detectors. (Non-recurring costs)
• 2.1.5 Production of Detector#1 infrastructure
Production of the equipment which will scale with the number of detectors.
• 2.1.6 Integration and Test Facility
Operation of the ITF including logistics to receive, test, store and repackage goods including trucking and handling of return goods
• 2.1.7 Installation Underground
Underground installation operation and oversight
2.1.3 Design
28-March-18 William Miller | Dune Installation Schedule 23
• Some of the design phase needs to begin in Q3/Q4 2018
- To move the installation process design ahead enough to design the trial assembly structure at Ash River for FY19
- Early design phase and scope of the ITF to begin building facility in FY19
- Design work that involves CF information required
• Design work in FY19/FY20 would include cold box and cryogenic for ITF, APA fixtures for rotation and cabling. Shipping box designs, etc. Information required for the final design phase of the TPC
• FY21/22 Final design work
- Underground Installation
- Surface logistics & Testing
- Common Integration Facility
Infrastructure
- Common Underground
Infrastructure
- Detector Support System
2.1.4 Prod. of Common Equip
28-March-18 William Miller | Dune Installation Schedule 24
• Common Cleanroom Infrastructure
- Cleanroom
- Gantry Crane
- Cleanroom Rigging equipment
- Scissor Lifts
- Alamak/work platforms
• Common Integration Facility Infrastructure
- Office/Lunch Area
- Forklift
- Shop/tool area
- Pallet jacks
• Common Underground
Infrastructure
- CUC cable trays
- Underground storage
- Data room and Work Area
- Forklift
- Carts, pallet jacks,
conveyances
- Diagnostic equipment
2.1.5 Production of Det#1 Infra
28-March-18 William Miller | Dune Installation Schedule 25
These are all items required to
begin building Detector #1
• Install Cryogenic Piping
• Clean Cryostat-Install Floor
• Cryostat Roof
- Cable Trays
- Racks
- Rack Cooling
- AC Power
- Crossing Tubes & Flanges
• Detector Support System
- DSS components
- Survey
- Trollies
- Switchyard
- TCO Beam
2.1.7 Underground Installation
28-March-18 William Miller | Dune Installation Schedule 26
• Installation starts May 2023 with
End Wall #1
• A month long startup period of ½
speed construction APA-CPA-FC
1-2
• APA-CPA-FC 3-48 take 6
months
• APA-CPA-FC 49-50 take 1
month
• 1 month for End Wall#2
• 1 month to install instrumentation
and final testing
• 2 months to Close TCO
This is a first rough DRAFT!
28-March-18 William Miller | Dune Installation Schedule 27
I have been swamped working on making ProtoDUNE happen and have not devoted the time an effort this really requires.
I am hoping for feedback, need more help
• I have not tried to go thru all the steps in detail from Vic’s installation sequence and tried to optimize manpower levels, se have gone thru 5 different scenarios in the last 4 months
• I have used manpower cost estimates from Fermilab and School of Mines
• We have started a first pass of M&S costs for some of the tools and equipment needed but nothing has been optimized.
• I have assigned no cost to consortia effort
• There is no M&S for operation cost of disposables
Next Steps
28-March-18 William Miller | Dune Installation Schedule 28
• The WBS outline still needs
some organizational help
• It is critical over the next few
weeks/months to confirm that
any requirements we have that
impact the CF design as the
final design is starting now.
As the process moves forward
it will be close to impossible to
make any changes.
• Start the process of writing a
more detailed set of step by step
procedures so a reasonable
BOE can be written for both
manpower and M&S.
• Work directly with the different
consortia to define changes
required from the current
ProtoDUNE design to
maximize efficiency in
installation and quality for
longevity or operation
• We need to increase the
engineer detector effort as
ProtoDUNE comes to a
completion to answer critical
questions like cable routing,
electrical connections,
mechanical stability
• Do a time and motion study on
paper to check for conflicts in
gantry crane usage, staging etc.