OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 2 / 27
INDEX
INDEX ........................................................................................................................... 2AMENDMENTS AND REVISIONS .............................................................................. 41. INTRODUCTION .................................................................................................. 5
1.1 PROJECT OVERVIEW ..............................................................................................51.2 PIPELINE SYSTEM DESCRIPTION ..........................................................................5
2. DEFINITIONS AND ABBREVIATIONS .............................................................. 62.1 DEFINITIONS .............................................................................................................62.2 ABBREVIATIONS ......................................................................................................7
3. REFERENCE RULES, CODES AND STANDARDS .......................................... 73.1 CODES AND STANDARDS .......................................................................................73.2 OWNER DOCUMENTS ..............................................................................................73.3 CONTRACTOR DOCUMENTS ..................................................................................7
4. SCOPE OF DOCUMENT ..................................................................................... 85. RESPONSIBILITIES ............................................................................................ 86. PROCEDURE ...................................................................................................... 9
6.1 ORGANIZATION OF PROJECT FILES ...................................................................106.2 HANDLING OF CORRESPONDENCE DOCUMENTS ............................................106.3 HANDLING OF TECHNICAL DOCUMENTS ...........................................................106.4 HANDLING OF INCOMING TECHNICAL DOCUMENTS ........................................12
6.4.1 Logging of Technical Documents ....................................................................126.4.2 Deciding of the Distribution List and the Necessary Actions ...........................126.4.3 Distribution of Technical Documents ...............................................................126.4.4 Examination of Technical Documents ............................................................. 126.4.5 Contractors Evaluation of Comments on Technical Documents .................... 126.4.6 Updating of the MDR .......................................................................................136.4.7 Approval of the MDR .......................................................................................136.4.8 Handling of Master Documentation .................................................................13
6.5 HANDLING OF OUTGOING TECHNICAL DOCUMENTS ......................................13
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
3/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 3 / 27
6.6 TECHNICAL DOCUMENTS REFERENCES ...........................................................136.6.1 Technical Documents Template ......................................................................136.6.2 Technical Drawing Template ...........................................................................146.6.3 Technical Documents Checks .........................................................................146.6.4 Documents development phases ....................................................................14
6.7 DOCUMENT NUMBERING ......................................................................................166.7.1 Codification for Technical Documents .............................................................166.7.2 Codification for Technical Specifications .........................................................176.7.3
Codification for Drawings .................................................................................17
6.7.4 ANNEX 1 Codes for Technical Documents and Technical Specifications
Subject (D) .......................................................................................................196.7.5 ANNEX 2 Codes for Technical Document Category (E) ..............................206.7.6 Forms Records .............................................................................................206.7.7 ANNEX 3 Codes for Drawings Category ......................................................216.7.8 Sheet Number (Drawings) ...............................................................................216.7.9 Revision Number .............................................................................................22
6.8 ELECTRONIC FILING OF DOCUMENTS................................................................226.9
FINAL DOCUMENTATION ......................................................................................23
7. ATTACHMENTS ................................................................................................ 24
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
4/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 4 / 27
AMENDMENTS AND REVISIONS
Amendmentand revision
Date Page DescriptionProjectManager
A1 16/12/11 All Issued for Comments/Approval
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
5/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 5 / 27
1. INTRODUCTION
1.1 PROJECT OVERVIEW
Public Natural Gas System Operator (DESFA) of Greece plans to install an N.G.T.S. Offshore NaturalGas Pressure Pipeline Varnavas-Karavos (Aliveri) whose purpose will be to supply natural gas to EvviaIsland.
The southern landfall in Attiki is named Varnavas while the previous names used for this landfall are Ag.
Apostoli or Grammatiko. The northern landfall in Evvia is named Karavos which is also indicated asAliveri landfall.
The maximum water depth along the 20 Gas Pipeline route is approx. 70m (MSL).
Figure 1-1 Natural Gas Pressure Pipeline Varnavas-Karavos route layout
1.2 PIPELINE SYSTEM DESCRIPTION
The offshore pipeline system consist of an 20 Natural Gas High Pressure Pipeline from the battery limitat Varnavas landfall, Attiki to the battery limit at Karavos landfall at Evvia island. The length of the new20 Natural Gas High Pressure Pipeline is about 14.2 km. The 20 Natural Gas High Pressure Pipeline
will consist of the two offshore sections, joined together offshore by Above Water Tie In method.
The Varnavas side offshore pipeline section commences at the KP -0.020 and finishes at AWTI Targetpoint at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is70m.
The Karavos side offshore pipeline section commences at the KP 14.205 and finishes at AWTI Targetpoint at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is31.2m.
Both pipeline sections will be manufactured from carbon steel with internal corrosion coating.
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
6/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 6 / 27
2. DEFINITIONS AND ABBREVIATIONS
2.1 DEFINITIONS
The following definitions will be applicable in this document:
CONTRACTOR CONSORTIUM SAIPEM - ELTER
OWNER DESFA HELLENIC GAS TRANSMISSION SYSTEM OPERATOR S.A.
PROJECTDetailed Engineering, Procurement Of Materials & Construction Of TheOffshore Part Of The Stefani-Aliveri Natural Gas High Pressure Pipeline
PROJECT MANAGERMeans, respectively, the entity and the person appointed by OWNER toprovide project management services
SITE Means the lands, waters and other places on, under, in or through whichthe WORKS are to be performed including offshore installations, floatingconstruction equipment, vessels (including the area covered byapproved anchor patterns) design offices, workshops and places whereequipment, materials or supplies are being obtained, storied or used forthe purposes of the CONTRACT and any and all other places where thePERMANENT WORKS are to be executed and to which PLANT andMaterials are to be delivered and any other places as may be specifiedin the CONTRACT as forming part of the SITE.
SUBCONTRACTOR Selected Sub-Contractor to perform the work described in this document
SUPERVISING ENGINEER Means the company(ies) appointed by OWNER to carry out theConstruction Supervision duties, as well as the review of the detaileddesign issued by CONTRACTOR, as defined in Clause 2 hereof and inother CONTRACT DOCUMENTS
WORKS Means all CONTRACTORs services and supplies to be rendered andPLANT furnished in accordance with the CONTRACT including bothTEMPORARY WORKS and PERMANENT WORKS. Without limitation toitems set out in the CONTRACT DOCUMENTS, the WORKS includeeverything of whatever nature that is required for the achievement of theobjective of the CONTRACT, except for any exclusion that arespecifically itemized in the CONTRACT DOCUMENTS
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
7/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 7 / 27
2.2 ABBREVIATIONS
DC Document Controller
MDR Master Document Register
PE Project Engineer
CPM Contractor Project Manager
CIM Contractor Installation Manager
CEM Contractor Engineering ManagerPMT Project Management Team
3. REFERENCE RULES, CODES AND STANDARDS
3.1 CODES AND STANDARDS
Ref Document Number Title
/1/ ISO 9001:2000 Quality management system - Requirements
3.2 OWNER DOCUMENTS
Ref Document Number Title
Specifications
/2/ APENDIX F Contractor Documents Requirements
/3/ DC-028Review/Approval of Contractors Technical Documentsusing Document Approval Form
3.3 CONTRACTOR DOCUMENTS
Ref Document Number Title
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
8/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 8 / 27
Procedures
/4/ WI-SMS-PCON-100-E Documentation Management
/5/DSF-1101401-436-6300-QAC-MAN-0200
Overall Quality Manual
/6/DSF-1101401-436-6300-PRM-MAN-0100
Project Overview Manual
/7/ WI-SMS-INST-101-EOffshore Installation Engineering Documentsand Approval
/8/ WI-SMS-OOFS-111-EWork Instruction Offshore AS BUILTdocumentation
/9/ WI-SMS-INST-112-E Work Instruction Preparation of Drawings
/10/ WI-SMS-INST-104-EWork Instruction Installation methods / designcontrol
4. SCOPE OF DOCUMENT
This procedure describes the system for handling the documents concerning the OFFSHORE PART OFTHE STEFANI-ALIVERI NATURAL GAS HIGH PRESSURE PIPELINE PROJECT.
The objective is to guarantee the traceability, distribution, monitoring, disposal when necessary, and thesafekeeping of the Documents.
5. RESPONSIBILITIES
The DC is the focal point for the control of the Project Documentation during the whole project life.
The mission of the DC is to insure the implementation of Project Document Control within the Project as
follows:
To make available the applicable project documentation to the project team (including Owner
Subcontractors, Partners);
To manage all project documentation flow (paper and electronic)
The Document controller responsibilities include:
Assigning on the request of the originator, a unique identification number for all project documents(including Subcontractors documents);
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
9/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 9 / 27
Listing and controlling Project documents number within the project MDR;
Only the duly endorsed documents (signed and approved by CONTRACTORs responsible persons)are sent to OWNER for review/approval;
That all transmittals are duly indentified, numbered and filed ;
Issuing Transmittals;
Ensures that the MDR is updated and that transmittals and reports are issued embracing alldocuments generated in-house and by Vendor/Subcontractors or Third Parties during the ProjectLife (Engineering documents, Project Procedures, Queries, Vendor documents, OWNER) ;
That the MDR is updated on daily basis with the support of the PMT and available on the Projectdrive in the last revision;
All documents are available to CONTRACTOR interested personnel, at any utilization point ;
To upload all the issued documents on the FTP server that CONTRACTOR has set up in order toexchange the Project documentation with the OWNER, or to send all the documents and transmittalsby e-mail, and to send all the transmittals by fax;
Information flow within the Project Team about documents status;
Ensuring the collection of final AS BUILT and transmission to OWNER;
To alert of any delays in pending documentation.
ProjectTeam shall comply with this procedure and shall assist the DC in number assignment.
6. PROCEDURE
The project Document Control System includes:
receipt;
issuing;
numbering
logging;
distribution;
Document flowchart is shown in chapter 6.3.
All incoming and outgoing transmittals and documents shall be transmitted at the following address:
Mr. Giorgio Danieli
Contractor Project Manager
e-mail: [email protected]
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
10/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 10 / 27
Mrs. Lorena Jerkovic
Document Controller
51000 Rijeka, A. Colonnella 2, Croatia
Tel.: 00 385 51 651 908
Fax: 00 385 51 651 940
e-mail: [email protected]
6.1 ORGANIZATION OF PROJECT FILES
The CPM in collaboration with the DC shall establish the list of the incoming and outgoing files, and therelated logs:
for the OWNER;
On the basis of any other classifications the PM wishes to use.
This system shall be kept active, and updated with any new items, for the entire duration of this project.
The DC carries out the following activities:
organises the file,
labels the back of the file volumes, to facilitate consultation,
Prepares the logs and keeps them updated.
6.2 HANDLING OF CORRESPONDENCE DOCUMENTS
All correspondence between CONTRACTOR and OWNER should be approved and signed by CPM, whodecides the distribution list and necessary actions.
6.3 HANDLING OF TECHNICAL DOCUMENTS
Management of CONTRACTORs project Technical documents should be carried out accordingly to itsQuality System and the following flow chart:
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
11/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 11 / 27
Flow chartCoveringdocuments
Consequent actions Action by
IDC Form
Discipline check
Interdisciplinary check
Archiving documents
Updating MDR
Contractor
transmittal
Sending / receiving documentsInsert OWNER comments
Archiving transmittals
Updating LOGs
Contractor
Documents review andcomment / approve
Sending / receiving documents
OWNER(when required)
transmittal
Sending documents
Archiving documents
Updating MDR
Updating LOGs
Contractor
Implementation of documentsAll involved
persons
All documents issued for this project shall be signed by the Originator (Prepared), Checker (Verified) andCONTRACTORs Project Manager (Approved), in the absence of the CPM, all documents can be signed byCIM or CEM.
All documents issued by SUBCONTRACTOR shall go through their document control and approval process
before being sent to the CONTRACTOR.
All transfers of documentation should be accompanied with established Transmittal form.
Project documents shall be approved by OWNER.
START
Document issued forcomments/approval /reissued / revised by
Contractor
OWNERcomments
NO
YES
Document issuedapproved forconstruction
END
Insert OWNERcomments
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
12/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 12 / 27
6.4 HANDLING OF INCOMING TECHNICAL DOCUMENTS
The handling of the incoming technical documents includes the following activities:
Logging,
Deciding the distribution list and necessary actions,
Distribution.
Archiving
6.4.1 Logging of Technical Documents
Logging of the technical documents is DC responsibilities and has to do the following actions:
LOG the Document in MDR or other registers
check the technical documents by the list of documents on the transmittal form;
record the transmittal form and file the original, updating the Transmittal Log IN (FORM-DESFA-003 );
return to the sender, when required, a copy of the transmittal form signed for receipt;
The DC turns over all incoming technical documents to the CPM.
6.4.2 Deciding of the Distributi on List and the Necessary Actions
The CPM examines the incoming external documents and indicates the distribution list, specifying the action
requested by Project Team members for each document if its necessary.
6.4.3 Distribut ion of Technical Documents
The DC distributes the technical documents as per the distribution list so that they return to the CPM with theinformation requested.
6.4.4 Examination of Technical Documents
The persons indicated by the CPM examine received technical documents and carry out the requestedactions. Comments to the technical documents have to be written, using Comment sheet form.
The documents, with the comments incorporated, have to be returned to the DC.
6.4.5 Contractors Evaluation of Comments on Technical Documents
The CPM, or person indicated by CPM, after evaluating the comments received on the technical documents,decides to:
reject the documents, returning them with the comments to the originator for the preparation of anew revision;
Approve them, upon approval document should be sent to OWNER for review/approval;
Approve them, upon approval document should be issued for IFC (Issued for Construction) tothe OWNER.
The OWNER evaluates the documents and returns them as R Reviewed, WC - reviewed with comments,
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
13/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 13 / 27
orRWMC Reviewed with Minor Comments.
6.4.6 Updating of the MDR
The DC updates the MDR, on the basis of the CPMs instructions, throughout the life of the project, preparingeach time a new revision to be issued.
6.4.7 Approval of the MDR
The CPM approves the MDR, after the PE has checked the document.
The DC arranges the distribution of the updated MDR to all Project Team members, and to any otherspecified by CPM, including the OWNER.
MDR will be issued to OWNER on monthly basis.
6.4.8 Handling of Master Documentation
The DC organises, manages, and keeps the master documentation up to date replacing each document withthe latest revision. Prior revisions shall be stamped SUPERSEDED
6.5 HANDLING OF OUTGOING TECHNICAL DOCUMENTS
The DC handles all outgoing technical documentation, prepared according to this Procedure, and approvedby the CPM, in the following manner:
files the document originals;
prepares the Transmittal form (FORM-DESFA-001), which is to be sent to the receiver;
updates the Transmittal Log OUT (FORM-DESFA-002) and MDR Take the different numbers and filing system for outgoing documentation to the OWNER, and
the other one for outgoing documentation to the Subcontractors.
6.6 TECHNICAL DOCUMENTS REFERENCES
All Technical documents shall be written in the English and shall bear the Project references, as displayed onthe cover of this document and as described below in detail.
6.6.1 Technical Documents Template
A Technical document cover page and title block format, will display the following:
Project Title OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGHPRESSURE PIPELINE
Owner Logo, Main Contractor Logo, Contractor Logo;
Title of Document
Document Number;
Issue Date and Revision number, Description of issue;
Area for Originator, Checker and Engineering and OWNER approval sign-offs
The Technical document Template is shown inAttachment 1 and it is prepared in Word format.
Project Document, shall always include as minimum the following sections (drawings excluded):
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
14/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 14 / 27
Each Technical Document shall contain the table Revision Status Log which shall be positioned after pagewith table of contents.
6.6.2 Technical Drawing Template
Technical Drawing Template used for the Drawings in this Project corresponds to the requirements ofCONTRACTORs document system.
The CONTRACTOR Technical Drawing Template is shown inAttachment 2 and it is prepared in AutoCAD2004 (DWG) format. In case that newer AutoCAD is used, drawing will be always saved in 2004 format.
Drawing identification table placed in the bottom right side of the template shall be filled according to thisprocedure.
6.6.3 Technical Documents Checks
Each Technical document prepared utilising the Technical document Template, shall be checked as follows.
Self-Check Check made by the Originator on his own work.
On completion of the document the Originator shall sign off the original document in order to confirmthe correctness of his work. One clean copy shall be forwarded at this stage to the respective LeadDiscipline Engineer for further processing.
Discipline Check Check made by a Discipline Specialist (Checker).Discipline Check shall be carried out by the Discipline function. A qualified person, different form theoriginator, shall subject each design deliverable to a Discipline Check.
Inter-discipline Check if required.Check regarding item(s) interfacing with other design disciplines, performed by the respectiveDiscipline Specialist.The PE shall be responsible for deciding which documents shall be subject to IDC and by whichdisciplines.
6.6.4 Documents development phases
Phases of document development shall be defined, as it is described bellow:
PHASE PROGRESS
Start Date of the document 0%
Issued for Internal Review 10%
Issued for Comments / Approval (IFA) 60%
Issued for Construction (IFC) 100%
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
15/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 15 / 27
NOTE: Documents issued for Information (I1) shall be issued to OWNER after Internal Review cycle and willhave 100% progress.
Engineering documents shall be issued with status clearly indicated in the description column of title block asfollows:
Issued (or Re-issued in case of any further rev ) for Internal Review
Issued (or Re-issued in case of any further rev ) for comments / approval
Issued (or Re-issued in case of any further rev ) for construction
OWNER will review and comment on the document within maximum of 10 calendar days. Urgent documents
may require shorter review period, but it shall never be less than two working days.
Documents / drawings returned by OWNER with comments shall be reviewed by relevant Originator.
Whenever these comments can be incorporated without further questions the document / drawing shall berevised by the Originator, rechecked by the Checker approved by CPM and issued as Issued forconstruction.
Upon document issue in new revision, the previous one shall be stamped SUPERSEDED.
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
16/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 16 / 27
6.7 DOCUMENT NUMBERING
Control of issued documents is established through the Master Document register (MDR).
Each technical document (drawings, specifications, calculations, technical reports) originated for this Projectby CONTRACTOR and by its SUBCONTRACTORS shall be assigned with an unequivocal OWNERsidentification number as per the scheme as follows:
6.7.1 Codification for Technical Documents
Document code as per the following structure:
A B C D E - F
(A) Project Code: DSF-1101401
(B) Contract No.: 436
(C) Unit No.: 6300
(D) Document subject according to Annex 1
(E) Document category according to Annex 2
(F) Document Serial Number
Example:
DSF-1101401-436-6300-CNV-STU-001
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
17/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 17 / 27
6.7.2 Codification for Technical Specifi cations
Specification code as per the following structure:
A B C D E
(A) Project Code: DSF-1101401
(B) Contract No.: 436
(C) Specification Code: SPC
(D) Specification subject according to Annex 1
(E) Specification Serial Number:
1XX for Material Technical Specifications
2XX for Job Technical Specifications
Example:
DSF-1101401-436-SPC-CON-201
6.7.3 Codification for Drawings
Drawing code as per the following structure:
A B C D E - F
(A) Project Code: DSF-1101401
(B) Contract No.: 436
(C) Unit Code: 6300
Note: In case of Issue of Standard Drawings the above Unit Number shall be replaced by the code STD.
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
18/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 18 / 27
(D) XXX/ZZ
The first part XXX designates this drawing Category according to the Annex 3 and the second part ZZdesignates the Drawing Subject and is valid only for the category 55 (pipeline plans and longitudinalsections) as follows:
01 for recording plans
02 for longitudinal sections
(E) Drawing Size:
0 for drawing standard size A0
1 for drawing standard size A1
2 for drawing standard size A2
3 for drawing standard size A3
4 for drawing standard size A4
N for non-standard size drawings
(F) Drawing Serial Number:
a.) For the Drawings category 03 (Annex 3) as follows:
001, 002 etc. for Engineering Flow Diagrams
101, 102 etc. for Process Flow, Utility Balance, Block Flow Diagrams
201, 202 etc. for Materials of Construction diagrams
301, 302 etc. for Design Pressure / Temperature Diagrams
401, 402 etc. for packaged Unit Diagrams
b.) For all other drawings: Serial Number
Example:
DSF-1101401-436-6300-93-2-001
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
19/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 19 / 27
6.7.4 ANNEX 1 Codes for Technical Documents and Technical Specifications Subject(D)
The following are the letters for the types of technical documents (3) to be used in the documentsidentification code:
D
ADM Administration
COA Coating
CON Construction
CPR Cathodic Protection
DCC Document Control
ENV Environmental
GEO Geological
GET Geotechnical
NAV Naval
NDT Non Destructive Testing
PCO Project Control
PLN Pipeline (Natural Gas Service)
POS Positioning
PRC Procurement
PRJ Project Engineering
PRM Project Management
QAC Quality Assurance / Control
SAF Safety
SEI Seismic
STA Stress Analysis
STR Structural (Steel Structures)
SUR Survey
TOP Topographical
WEL Welding
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
20/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 20 / 27
6.7.5 ANNEX 2 Codes for Technical Document Category (E)
The following are the letters for the types of technical documents (3) to be used in the documentsidentification code:
E
CHT Chart
CLC Calculation
DAB Data Book
DAT Data Sheet
IND IndexLST List
MAN Manual
MST Method Statement
MTO Material Take Off
PHL Philosophy
PLN Plan
PRC Procedure
REG Register
REP Report
REQ RequisitionSCH Schedule
SHT Sheet
SOW Scope of Work
SPE Specification
STU Study
GEN General Document
6.7.6 Forms Records
Forms Records shall be numbered as follows:
DESFA FORM-xxx
xxx progressive number
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
21/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 21 / 27
6.7.7 ANNEX 3 Codes for Drawings Category
D
01 Plot Plan and elevations
46 Steel Structures
55 Pipeline plans & Longitudinal sections
59 Pipe Supports
78 Cathodic Protection
89 Pre-commissioning (heads, layouts,)
90 Rigging Laouyts
91 Survey dwgs Scale 1:1000
92 Survey dwgs Details
93 Survey dwgs Scale 1:5000
94 Survey dwgs Scale 1:50000
95 Survey maps
96 Anchor Patterns
97 Vessels Equipment, Layouts
98 Pipeline installation aids (heads, clamps,)
99 Installation sequence drawings (story boards)
6.7.8 Sheet Number (Drawings)
Each drawing issued regarding this procedure shall contain sheet number. Sheet number shall consist of twonumerical digit starting from "01".
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
22/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 22 / 27
6.7.9 Revision Number
Documents circulated internally for review / comments can be assigned with revision number 0 (zero) (textin the description of revision shall be Issued for Internal Review).
Document ready to be submitted to the OWNER for comments / approval, it shall be assigned with revisionnumberA1 (text in the description of revision shall be Issued for Comments / Approval). In case of re-submission of a document following the OWNER comments subsequent numbers (i.e. A2, A3.,) shall beassigned until the document is finally approved.
Once the document has been approved by the OWNER, it shall be re-issued with revision code C1 (text inthe description of revision shall be Approved for Construction). In case of re-submission of a documentfollowing the OWNER comments subsequent numbers (i.e. C2, C3.) shall be assigned until the document isfinally approved.
Document ready to be submitted to the OWNER for Info, it shall be assigned with revision numberI1 (textin the description of revision shall be Issued for Information). CONTRACTOR does not expect commentson such documents, but in case of required changes document will be issued in next revision (I2, I3, etc.).
6.8 ELECTRONIC FILING OF DOCUMENTS
All documents shall be stored in the computer system, in the OFFSHORE PART OF THE STEFANI-ALIVERINATURAL GAS HIGH PRESSURE PIPELINE Project dedicated area.
The document number together with the revision number shall constitute the name of the electronic file ofeach document, for example:
DSF-1101401-436-6300-SAF-MAN-0400_A1.doc
All drawings shall be stored in AutoCAD 2004 version. The drawing number together with the sheet numberand revision number shall constitute the name of the electronic file of each drawing, for example:
DSF-1101401-436-6300-5501-3-0700_A1.dwg
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
23/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 23 / 27
6.9 FINAL DOCUMENTATION
Prior to issue the final As-Built document/drawings CONTRACTOR shall submit to OWNER forreview/comments As-Built documents/drawings.
The final As-Built drawings must fully conform to the final arrangement. The final As-Built drawings shall bebased on the drawings issued for construction but shall include modifications, alterations, corrections orremarks concerning changes effected during construction.
Documents to be included in the Asbuilt shall be defined by issuing As built Dossier Index (Doc. No. DSF-1101401-436-6300-PCO-IND-0303) and shall be sent to OWNER for approval.
Subcontractor shall submit to CONTRACTOR a proposed Index of As-Built Documentation for approval priorcommencement of the Supply of the Work.
CONTRACTOR shall also submit to OWNER the final As-built drawings and documents in digital file formin CD-ROMs. The drawings shall be submitted in standard DXF or DWG format for AutoCAD latest release.All other final Technical Documentation (reports, tables, lists, etc) shall be also submitted in MicrosoftOffice Word/Excel files.
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
24/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT CONTROL PROCEDURE
DSF-1101401-436-6300-DCC-PRC-0302
REV. A1 Page 24 / 27
7. ATTACHMENTS
Attachment 1 Technical Document Template - Word format for technical documents consisting more than 1page (pages 7)
Attachment 2 Technical Drawing Template AutoCAD format (pages 1/1)
Attachment 3 Transmittal Form (page 1)
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
25/36
Attachment 1 Technical document Template
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
26/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT TITLE
DSF-1101401-436-6300-xxx-xxx-xxxx
REV. X Page 1 / 7
DOCUMENT TITLE
Rev Date Descripti on of Revision Prepared Checked Approved Owner
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
27/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT TITLE
DSF-1101401-436-6300-xxx-xxx-xxxx
REV. X Page 2 / 7
INDEX
1. INTRODUCTION ...................................................................................................................... 41.1 PROJECT OVERVIEW ..................................................................................................... 41.2 PIPELINE SYSTEM DESCRIPTION ................................................................................. 4
2. DEFINITIONS AND ABBREVIATIONS .................................................................................... 52.1 DEFINITIONS ................................................................................................................... 52.2 ABBREVIATIONS ............................................................................................................. 62.3 REFERENCES .................................................................................................................. 6
3. RESPONSIBILITIES AND OBLIGATIONS ............................................................................... 64. SCOPE OF DOCUMENT ......................................................................................................... 65. HEADING 01 (PROCEDURE DESCRIPTION) ........................................................................ 7
5.1 HEADING02 (STYLE HEADING 02, FONT: ARIAL 10PT) ............................................... 75.1.1. TITLE 03 (STYLE HEADING 03, FONT: ARIAL 10PT) .............................................. 7
6. ATTACHMENTS ....................................................................................................................... 7
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
28/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT TITLE
DSF-1101401-436-6300-xxx-xxx-xxxx
REV. X Page 3 / 7
AMENDMENTS AND REVISIONS
Amendmentand revision
Date Page Description
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
29/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT TITLE
DSF-1101401-436-6300-xxx-xxx-xxxx
REV. X Page 4 / 7
1. INTRODUCTION
1.1 PROJECT OVERVIEW
Public Natural Gas System Operator (DESFA) of Greece plans to install an N.G.T.S. Offshore Natural GasPressure Pipeline Varnavas-Karavos (Aliveri) whose purpose will be to supply natural gas to Evvia island.
The southern landfall in Attiki is named Varnavas while the previous names used for this landfall are Ag.Apostoli or Grammatiko. The northern landfall in Evvia is named Karavos which is also indicated as Aliverilandfall.
The maximum water depth along the 20 Gas Pipeline route is approx. 70m (MSL).
Figure 1-1 Natural Gas Pressure Pipeline Varnavas-Karavos route layout
1.2 PIPELINE SYSTEM DESCRIPTION
The offshore pipeline system consist of an 20 Natural Gas High Pressure Pipeline from the battery limitat Varnavas landfall, Attiki to the battery limit at Karavos landfall at Evvia island. The length of the new20 Natural Gas High Pressure Pipeline is about 14.2 km. The 20 Natural Gas High Pressure Pipelinewill consist of the two offshore sections, joined together offshore by Above Water Tie In method.
The Varnavas side offshore pipeline section commences at the KP -0.020 and finishes at AWTI Targetpoint at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is
70m.
The Karavos side offshore pipeline section commences at the KP 14.205 and finishes at AWTI Targetpoint at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is31.2m.
Both pipeline sections will be manufactured from carbon steel with internal corrosion coating.
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
30/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT TITLE
DSF-1101401-436-6300-xxx-xxx-xxxx
REV. X Page 5 / 7
2. DEFINITIONS AND ABBREVIATIONS
2.1 DEFINITIONS
The following definitions will be applicable in this document:
CONTRACTOR CONSORTIUM SAIPEM - ELTER
OWNER
DESFA HELLENIC GAS TRANSMISSION SYSTEM OPERATOR
S.A.
PROJECTDetailed Engineering, Procurement Of Materials & Construction Of TheOffshore Part Of The Stefani-Aliveri Natural Gas High PressurePipeline
PROJECT MANAGERMeans, respectively, the entity and the person appointed by OWNER toprovide project management services
SITE Means the lands, waters and other places on, under, in or trhoughwhich the WORKS are to be performed including offshore installations,floating construction equipment, vessels (including the area covered byapproved anchor patterns) design offices, workshops and places whereequipment, materials or supplies are being obtained, storied or used forthe purposes of the CONTRACT and any and all other places where
the PERMANENT WORKS are to be executed and to which PLANTand Materials are to be delivered and any other places as may bespecified in the CONTRACT as forming part of the SITE.
SUBCONTRACTORSelected Sub-Contractor to perform the work described in thisdocument
SUPERVISING ENGINEER
Means the company(ies) appointed by OWNER to carry out theConstruction Supervision duties, as well as the review of the detaileddesign issued by CONTRACTOR, as defined in Clause 2 hereof and inother CONTRACT DOCUMENTS.
WORKS
Means all CONTRACTORs services and supplies to be rendered andPLANT furnished in accordance with the CONTRACT including bothTEMPORARY WORKS and PERMANENT WORKS. Without limitationto items set out in the CONTRACT DOCUMENTS, the WORKS include
everything of whatever nature that is required for the achievement ofthe objective of the CONTRACT, except for any exclusions that arespecifically itemized in the CONTRACT DOCUMENTS.
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
31/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT TITLE
DSF-1101401-436-6300-xxx-xxx-xxxx
REV. X Page 6 / 7
2.2 ABBREVIATIONS
The following abbreviations will be applicable in this document:
CPM Contractor Project Manager
2.3 REFERENCES
Ref. Document No. Document Title
1
2
3
4
5
6
7
8
9
3. RESPONSIBILITIES AND OBLIGATIONS
Text (Style P1, Font: Arial 10 pt)
Bullet (Style P1, Font: Arial 10pt)
Text (Style P1, Font: Arial 10pt)
4. SCOPE OF DOCUMENT
Text (Style P1, Font: Arial 10 pt)
Bullet (Style P1, Font: Arial 10pt)
Text (Style P1, Font: Arial 10pt)
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
32/36
OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH
PRESSURE PIPELINEContract No. 436/11
DOCUMENT TITLE
DSF-1101401-436-6300-xxx-xxx-xxxx
REV. X Page 7 / 7
5. HEADING 01 (PROCEDURE DESCRIPTION)
Text (Style P1, Font: Arial 10 pt)
Bullet (Style P1, Font: Arial 10pt)
Text (Style P1, Font: Arial 10pt)
5.1 HEADING02 (STYLE HEADING 02, FONT: ARIAL 10PT)
Text (Style P1, Font: Arial 10 pt)
Bullet (Style P1, Font: Arial 10pt)
Text (Style P1, Font: Arial 10pt)
5.1.1. Title 03 (Style Heading 03, Font: ARIAL 10pt)
Text (Style P1, Font: Arial 10 pt)
Bullet (Style P1, Font: Arial 10pt)
Text (Style P1, Font: Arial 10pt)
6. ATTACHMENTS
Attachment 1 - Text (Style P1, Font: Arial 10pt)
Attachment 2 - Text (Style P1, Font: Arial 10pt)
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
33/36
Attachment 2 Technical Drawing Template
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
34/36
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
35/36
Attachment 3 Transmittal Form
-
7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure
36/36
Date:
4= For Bid
No.off Rev. Acti on Co de Resp. Cod e
1
Transmitted by:
Date:
Received by:
Date:
Project No.: DSF-1101401
Distribution
Correspondence number:
PROJECT NAME: OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH PRESSURE
PIPELINE
CONTRACT No.: 436/11
To:
Address:
TRANSMITTAL FORM
Form no.: FORM-DESFA-0001
Rev. 01 DatE: 17.11.2011
Pag. 1 of 1
Title / Description
B = Approved on condition
CLIENT: DESFA- HELLENIC GAS TRANSMISSION
SYSTEM OPERATOR S.A.
Ref.No.:
Subject:
Quantity:
From: SAIPEM
PLESE SIGN AND RETURN COPY
RESPONSE CODE:
Document No.
D= No comment - For info
only
ACTION CODE:
1 = For Approval
2 = For Comment
3 = For Information
5= For Construction
6= For Design
A = Approved C= Unnaceptable