dredging, disposal management and impacts on lake sediments us army corps of engineers

18
Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Post on 21-Dec-2015

228 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Dredging, Disposal Management and Impacts on Lake SedimentsUS Army Corps

of Engineers

Page 2: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Great Lakes HarborsUS Army Corpsof Engineers

• Corps maintains 139 channels and harbors (total harbors on the Great Lakes is over 200)– 68 commercial harbors

• Represents 24% of Nation’s commercial harbors

– 71 recreation harbors• Represents 12% of Nation’s recreation harbors• About 700,000 recreation vessels traverse the lakes annually

Duluth Harbor, MNCommercial

Arcadia, MIRecreation

Page 3: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Operation & Maintenance BudgetUS Army Corpsof Engineers

• Annual budget to operate and maintain Corps navigation projects on the Great Lakes ranges from $82M to $89M– Includes surveys, dredging, structure and lock maintenance

• Cost to dredge Corps projects ranges from $16M to $24M annually, with an average of $20M– Federal yardage dredged is 3.5 - 4.0 million cubic yards

– Including non-Federal harbors yardage is 5 - 6 million cubic yards

Page 4: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Great Lakes DredgingUS Army Corpsof Engineers

• Corps dredges 26 - 41 projects annually– Average is about 35 for deep and shallow draft harbors

– Average 9 recreation harbors

• In FY 2000 Corps dredged 41 projects– 25 were commercial and 16 recreation

• In FY 2001 Corps estimates 40 projects will be dredged– 24 are commercial and 16 recreation

Page 5: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

US Army Corpsof Engineers

• Did the low lake levels in 1999 & 2000 change the way the Corps dredges within the Great Lakes?– No

– Projects are dredged to depths to meet user needs, up to authorized depths below low water datum (LWD)

• LWD establishes the depth to which projects are maintained

• Harbors dredged to project depth whether lake levels are high or low

• Some channels maintained to less than authorized depth

• Projects are dredged based on shoaling rates and commercial importance (priority) of the project

• High lake levels allow dredging at recreation harbors to be deferred

Dredging (con’t)

Page 6: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

US Army Corpsof Engineers

• Commercial navigation industry was impacted by low lake levels in 1999 and 2000– Industry was used to above average lake levels

• One inch loss in draft equates to a loss of 270 tons of cargo carrying capacity for a 1000-foot vessel

• In general, lake levels do not impact dredging– Some impact at tributaries entering the lake

• Sediments drop out quicker with lower lake levels

• Corps now has authority to dredge deeper– Section 343, WRDA 2000, allows Corps to dredge to

provide authorized depths when lake levels go below LWD

Dredging (con’t)

Page 7: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

US Army Corpsof Engineers

• Did the Corps dredge all harbors which had shoaling problems in 2000?– Funding constraints prevented dredging at some

recreation harbors

• Previous high lake levels masked the issue of a lack of funding for all needed dredging

• Some harbors have issues preventing dredging– Lack of a disposal site

– Other environmental issues

Dredging (con’t)

Page 8: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

US Army Corpsof Engineers

• If low lake levels continue in FY 2001, what impact will this have on the way the Corps dredges?– Commercial harbors will receive highest priority

– Funding constraints will impact some recreation harbors• The Corps will dredge as many harbors as funding allows

– In FY 2000 the Corps dredged more harbors than it had originally scheduled due to dropping lake levels

Dredging (con’t)

Page 9: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Confined Disposal FacilitiesUS Army Corpsof Engineers

• Disposal of dredged material used to be unconfined and placed in the open water– Least cost alternative

• Lake water quality degradation dictated alternative disposal methods be investigated

• Public Law 91-611 provided funds to construct CDFs– First CDF constructed in early 1970s

• 44 CDFs constructed on the Great Lakes• Current disposal methods include open water, beach

nourishment, or a CDF

Page 10: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Dredging and Its PlacementUS Army Corpsof Engineers

• Quantity dredged averages 3.6 M CY of sediments

• Cost to dredge averages $20 M annually

• About a 50 - 50 split between confinement and open lake disposal, but recent trend is towards more confinement

– Confined disposal accounts for 55 percent of material– Open lake disposal or beach nourishment accounts for 45 percent of material Pt. Mouillee

Page 11: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Great Lakes Dredged Material Testing & Evaluation Manual

• Regional guidance developed by USEPA

and Corps• Applicable to dredged material discharges

to Great Lakes, connecting channels, and

tributaries

• Tiered testing approach consistent with national

guidance, but using regionally chosen methods• Available online:

www.epa.gov/glnpo/sediment/gltem

US Army Corpsof Engineers

Page 12: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Confined Disposal FacilitiesUS Army Corpsof Engineers

• Existing CDFs won’t last forever– Slightly less than half are filled or inactive

• Corps is assessing each project’s disposal needs– Dredged Material Management Plans developed to

assess disposal needs over a 20 year period

• All new CDFs require cost sharing with a sponsor– WRDA 1996 establishes cost sharing requirements

• Non-federal cost linked to project depth requirements– Approximately from 10 to 50 percent of total cost

• Allows for private disposal facilities

Page 13: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Disposal ManagementUS Army Corpsof Engineers

• What can be done to extend the useful life of existing containment facilities?– Better consolidation of dredged material

• Use of ditches to drain water

– Beneficial re-use of dredged material• Beach & near-shore nourishment

• Mining and treatment of material for some productive use– habitat restoration, landscaping, road construction fill, agricultural

soils, strip mine restoration, or temporary cover for landfills

Page 14: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Disposal Management (con’t)US Army Corpsof Engineers

• Beneficial use of dredged material offers a sustainable long-term management option for dredged material

• Regulatory and public perception issues are major obstacles to beneficial use– State regulations lack a coordinated regulatory approach

to beneficial use

– Better communicate pertinent information to the public

– Institutionalize the concept that dredged material is a valuable resource

Page 15: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Disposal Management (con’t)US Army Corpsof Engineers

• The Corps is dredging the same quantity of sediments while the quality of it is improving– Sources of pollutants becoming less

• Dredging reduces pollutants within channels

• Requirement for confining dredged sediments will continue in the future– The Public and State agencies will require it

• Requirements for dredged material management will increase rather than decrease in the future– Trend is to confine more dredged material

– Unused capacity of CDFs is diminishing

Page 16: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Cooperative EffortsUS Army Corpsof Engineers

• Corps is working with the USEPA and State / local agencies to clean up toxic harbor sediments

• Examples– Ashtabula Harbor

– Indiana Harbor

– Waukegan Harbor

Page 17: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Impacts on Lake SedimentsUS Army Corpsof Engineers

• Effect of lower lake levels and vessel traffic – Vessels closer to channel bottom

• Prop wash aggravates sediments

• Suspends toxic materials within the water column

• Effect of lower lake levels on tributaries– More scour occurs near the mouth of a tributary

• Causes more sediments / toxic materials to enter lake

• Sediments more mobile with low lake level conditions

• No studies which quantify the effect between low lake levels and toxic sediments– Conceptual efforts and cannot quantify numbers / impacts

Page 18: Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers

Dredging, Disposal Management and Impacts on Lake SedimentsUS Army Corps

of Engineers

Questions ?