dr. godfried williams1 project management – topic 6 lecture content planning tools/techniques...
TRANSCRIPT
Dr. Godfried Williams 1
Project Management – Topic 6
Lecture Content
Planning Tools/Techniques
Optimization TechniquesResource Planning & Allocation
Linear Programming
Dr. Godfried Williams 2
Planning Tools Tools/Techniques
List of activities Diaries Bar charts Gantt charts Networking
PERT (Programme Evaluation Review Technique) CPM (Critical Path Method)
Optimization & Resource Allocation
Dr. Godfried Williams 3
Overview of Project ManagementResources that a planning engineer has to co-ordinate.
People/Skill/Manpower money Materials/Logistics Machines ) eg. Computers time
Dr. Godfried Williams 4
Steps to achieve project objective. establish the objective/strategy define the scope of work/activities arrange the activities into a plan estimate the cost, time and
resources(CTR) for each activity analyze the network optimize the network to form a base
plan monitor progress against the plan measure variances and forecast/trends re-plan against objectives
Dr. Godfried Williams 5
THE OBJECTIVE To exploit the reserves of block x and
y at an acceptable profitability to the company.
Optimise or maximise resources x and y to achieve objective z.
(Linear Programming technique to allocate resources)
Dr. Godfried Williams 6
Scope of work Translate the objectives
into the scope of work. Feasibility stage Analysis stage Conceptual design stage Detailed design Construction or
Implementation(coding) conversion Changeover Production (going online or live)
Dr. Godfried Williams 7
Planning the project
Create a list of high level management activities. Convert high level activities to low level
tactical & operational activities. Construct the network by identifying
ES,EF,LS,LF.
Dr. Godfried Williams 8
PERT (Programme Evaluation Review Technique)
Addresses Uncertainty in the duration of the project using 3 time estimates Optimistic Most likely Pessimistic
(These estimates are used in calculating the “expected time” of the project)
Dr. Godfried Williams 9
3 Time Estimates Optimistic Time
The minimum time, a , an activity will take.
Most likely time The most likely time, m, is the normal time
to complete the Job. Pessimistic time
The pessimistic time, b, is the maximum time an activity could take
Dr. Godfried Williams 10
How to derive the time estimates ?
The time estimates are obtained from the most knowledgeable experts about difficulties likely to be encountered and the variability in time during the project
Expert Estimators or those who will manage the project
Dr. Godfried Williams 11
Time Estimates based on Beta Distribution
Time estimates related in the form of a Beta Distribution because it is unimodal
(finite end points and not necessarily symmetrical). A property that is desirable for a distribution of activity times
Dr. Godfried Williams 12
Calculating the “Expected Time” Based on this distribution, the mean or expected time, te ,
and the variance, V, of each activity are calculated with time estimates a, m, b using the formulas:
te = a + 4m + b 6
V = b – a 2
6
The variance, V is a measure of variability in the activity completion time
Dr. Godfried Williams 13
Example – Figure 1 (See calculation on slide 14)
0 3 5
Start of Activity
Most likely, m
13
Optimistic, a Average, te
Prob. Of t
Activity duration time t (days)
Pessimistic b
6
Dr. Godfried Williams 14
Calculation for Figure 1
te = 3 + 4(5) + 13 = 6 days
6
V = 13 – 3 2 = (1.67 days) 2 = 2.78
6 The larger V, the less reliable te. and the higher the
likelihood that the activity will be completed much earlier or later than te, . In a standard project estimates a and b are close to each other, V is small and te is more reliable.
Dr. Godfried Williams 15
Expected Duration of Project
Te = te CP
Where te are expected times of the activities on the critical path
Dr. Godfried Williams 16
Variance in the project duration
VP = V CP
Variance of project duration distribution is calculated as the sum of the variances of the activity durations along the CP
Dr. Godfried Williams 17
Guidelines to forming a network. Start time
Earliest start time Latest start time
Finish time Earliest finish time Latest finish time
Float Total Float = LS - ES or LF - EF Free Float = float on the critical path
Activity Dummy activity
Events as Nodes - Milestones
Dr. Godfried Williams 18
Estimating
Rules to be observed estimating time. Duration should be estimated after
the logic has been defined. Duration should be based on scope
of work and resources required. Time estimate is based on
assumptions. Very few estimates are 100%
certain or unalterable.
Dr. Godfried Williams 19
Time Analysis Activity Number Description Duration(weeks) Earliest Start Earliest Finish(ES + Duration - 1) Latest Start Latest Finish Float
Total Float Free Float
Critical Path & Activities
Dr. Godfried Williams 20
Determining Critical Path & Activities
Rule 1 - The early start (ES) time for a particular activity is the same as the late start(LS) time.
Rule 2 - The early finish (EF) time for a particular activity is the same as the late finish (LF) time.
Rule 3 - The ES or LS added to the duration of the activity results in the EF or LF.
Dr. Godfried Williams 21
Resource allocation & Scheduling(optimization)
Allocating the right resource to the right activity. eg money time labour equipment materials Logistics (support)
Dr. Godfried Williams 22
PRINCE Structured Project Management Method
Programme plan
Project plan
Stage plan
Team plan
PRINCE Plans
Exception plan
Dr. Godfried Williams 23
PRINCE Project Management Method(Contents & stage plans)
Product breakdown structure Product flow diagram Activity network Financial budget Resource requirements Risk assessment Quality plan Gantt charts Product descriptions for major products
Dr. Godfried Williams 24
Example Network diagrams