PROJECT - 5MW SOLAR PROJECT PHALODI RAJASTHAN
Format no SOL- 01 Date : 02-11-2011 WORK DONE
Discipline Description of work UOM Scope Planned Actual Of Last Day Remarks
Civil
Block 20.09.11 ALL FIVE BLOCKS
PILE MARKING BLOCK -1 nos completed
PILE MARKING BLOCK-2 nos 1009
PILE MARKING BLOCK-4 nos 1926 883
Control Room Raft Casting nos 14.09.11 14 14
Inverter room raft casting 15.10.11 20 16
16.10.11 14 14
NOS 20 16
BORINGBLOCK - 1 NO 1992 2032 40
BLOCK - 2 NO 5 294 289
BLOCK - 3 0
BLOCK - 4 NO 508 1843 1335
BLOCK - 5 1849 1849 COMPLETED
BASE PILE CASTING 6018
BLOCK - 1 NO 1992
BLOCK - 2 5
BLOCK - 3BLOCK - 4 508
BLOCK - 5 1849 COMPLETED
PILE CAPE CASTING 4354
BLOCK - 1 678 1140 462
BLOCK - 2 0
BLOCK - 3 0
BLOCK - 4 373 480 107
BLOCK - 5 503 503 0
MAN POWER AND MACHINERY
Discipline Category SWL Contractor C Contractor D Cumulative
Manpower
Engineer 4 2 1 7Supervisor 2 2 2 6
Skilled Labor 5 20 25
Bar Bender 6 8 14
Unskilled Labor 57 24 81Security Guard 4 4
137
Machinery
Pile boring machine
DG 1 1 1JCB 1 Concrete Mixers 2 1 Vibrator 2 1Tractors 3 2 Water tanker 4 1Fork LiftsHydra Total Station 1 2Air Compressor 1Boaring Rig Machine 1 1
MATERIAL RECEIVEDDecipline Item Description Uom Qty. Received Cumulative Qty Remarks
GRIT CUM20mm CUM 18410mm CUM 134SAND CUM 174STEEL KG 45500Cement Bags 2540
Observations
Sl.No Category Location Picture Action agreed Pictures issue rectification Detected by Priority
1 Grouting of Module structure
all locations welspun critical
Prepared by SWL Approved by WEL
Signature
Name k simhadri
Designation
DAILY PROGRESS REPORT
Starting Dt :
Actual/Expected
Finish date
Cumulative actual to Date
Land Survey and Marking for foundation
Control Room Foundation Piller casting( 1st lift)
INVERTER ROOM 5 PILLER CASTING (UP TO PLINTH BEAM)
13400 nos anchor bolts received at site
BENIWAL CONSTRUCTI
ON
Hemraj Constractio
n
BENIWAL CONSTRUCT
ION
Hemraj Constractio
n
Description open issue
Person Responsible for
rectification
Disturbance in the structure in the module in the event of severe wind and electrical shotcircuit
Grouting required before power flow
Date 2/11/2011
PROJECT - 5 MW RAJASTHAN SOLAR POWER PROJECT
INCIDENT REPORTFormat No Date : DD-MM-2011
Incident DetailsCause of Incident Effect Corective action
Date Time
Prepared by SWL Approved by WELNameDesignationSignatureDate
Corective action
Approved by WEL