What role for Public-
Private Partnerships?Delivering on the Post-2015 Development
Agenda
Lessons from an IEG Evaluation
December 12, 2014
Stefan Apfalter
Senior Evaluation Officer, IEG
![Page 2: What is the role for Public-Private Partnerships? Delivering on the Post-2015 Development Agenda](https://reader035.vdocuments.mx/reader035/viewer/2022081816/55a37c321a28ab02168b456d/html5/thumbnails/2.jpg)
Title of Presentation 2
How can PPPs help close the
$ 1 trillion infrastructure gap?
• Leveraging scares public resources
• Potential to increase efficiency
• USD 79bn p.a. PPP volume globally
• But PPPs are not the panacea
• PPPs require their own infrastructure!
![Page 3: What is the role for Public-Private Partnerships? Delivering on the Post-2015 Development Agenda](https://reader035.vdocuments.mx/reader035/viewer/2022081816/55a37c321a28ab02168b456d/html5/thumbnails/3.jpg)
Licensing and regulation
PrivatizationServices contracts
Construction contracts
“Pure public“ “Pure private“
Exis
ting
Asse
tsN
ew
Asse
ts
Performance-based
maintenance
Operations and
Maintenance (O&M)
Design, Build,
Finance, Maintain
Build, Transfer,
OperateBuild, Own,
Operate, Transfer
Lease
Concession
Core PPP types Other type of private sector involvementKey:
PPPs respond to market failure
while minimizing government failure
![Page 4: What is the role for Public-Private Partnerships? Delivering on the Post-2015 Development Agenda](https://reader035.vdocuments.mx/reader035/viewer/2022081816/55a37c321a28ab02168b456d/html5/thumbnails/4.jpg)
Applying a strategic country
approach
Advise governments on “if and how” to use PPPs
Based on comprehensive diagnostics
Readiness of sector
Public sector capacity
Fiscal implications
Integrated in NIPs
4
![Page 5: What is the role for Public-Private Partnerships? Delivering on the Post-2015 Development Agenda](https://reader035.vdocuments.mx/reader035/viewer/2022081816/55a37c321a28ab02168b456d/html5/thumbnails/5.jpg)
Addressing political economy
Sector reform is foundation of success,
but often fails
Broad-based and early stakeholder
consultations
Government
commitment required
Local capacity
5
![Page 6: What is the role for Public-Private Partnerships? Delivering on the Post-2015 Development Agenda](https://reader035.vdocuments.mx/reader035/viewer/2022081816/55a37c321a28ab02168b456d/html5/thumbnails/6.jpg)
Investing more at the frontier
6
% = PPP market in these countries
![Page 7: What is the role for Public-Private Partnerships? Delivering on the Post-2015 Development Agenda](https://reader035.vdocuments.mx/reader035/viewer/2022081816/55a37c321a28ab02168b456d/html5/thumbnails/7.jpg)
Learning through better M&E
7
Data
NO Data
![Page 8: What is the role for Public-Private Partnerships? Delivering on the Post-2015 Development Agenda](https://reader035.vdocuments.mx/reader035/viewer/2022081816/55a37c321a28ab02168b456d/html5/thumbnails/8.jpg)
Going forward
• Applying strategic country
approach
• Addressing political
economy factors
• Investing at the
frontier
• Learning through better M&E
8
![Page 9: What is the role for Public-Private Partnerships? Delivering on the Post-2015 Development Agenda](https://reader035.vdocuments.mx/reader035/viewer/2022081816/55a37c321a28ab02168b456d/html5/thumbnails/9.jpg)
9Thank you!
![Page 10: What is the role for Public-Private Partnerships? Delivering on the Post-2015 Development Agenda](https://reader035.vdocuments.mx/reader035/viewer/2022081816/55a37c321a28ab02168b456d/html5/thumbnails/10.jpg)
Upfront
VGP
Comparison of Public Sector
Payment Profiles
Costs /
Expenditures
Capital
Costs
Estimated Running
Costs
Running Costs
Overruns
Costs
Overruns
5 10 15 20 Years
Construction Operation and
Maintenance Phase
• Capital and operating
costs are paid for by the
public sector who also
takes the risk of cost
overruns and late
delivery
Traditional Government Procurement
Costs /
Expenditures
Preparation
Payment based on
Availability
Payment based on
Usage
5 10 15 20 Years
Construction Operation and
Maintenance Phase
• Public sector pays over the long
term as services are delivered
• Has to cover increased
preparation costs and, at times,
part of capital costs to make PPP
project bankable.
• Takes on contingent liabilities
PPP Procurement
Contingent Liabilities