Information Technology ProjectManagement, Sixth Edition
Project Scope ManagementProcesses
Collecting requirements : defining and documenting
the features and functions of the products producedduring the project as well as the processes used forcreating themDefining scope : reviewing the project charter,
requirements documents, and organizational processassets to create a scope statementCreating the WBS : subdividing the major projectdeliverables into smaller, more manageable
componentsVerifying scope : formalizing acceptance of theproject deliverablesControlling scope : controlling changes to project
scope throughout the life of the projectInformation Technology ProjectManagement, Sixth Edition 1
F r o m p r e v
i o u s
l e c t u r e
-
8/3/2019 Week 4 Time Chapter 06
2/55
F
Chapter 6:Project Time Management
Information TechnologyProject Management, Sixth
Edition
-
8/3/2019 Week 4 Time Chapter 06
3/55
Information Technology ProjectManagement, Sixth Edition
Learning ObjectivesUnderstand the importance of project
schedules and good project time managementDefine activities as the basis for developingproject schedulesDescribe how project managers use networkdiagrams and dependencies to assist inactivity sequencingUnderstand the relationship betweenestimating resources and project schedulesExplain how various tools and techniques helpproject managers perform activity durationestimating
3
-
8/3/2019 Week 4 Time Chapter 06
4/55
Information Technology ProjectManagement, Sixth Edition
Learning Objectives (continued)Use a Gantt chart for planning andtracking schedule information, find thecritical path for a project, and describehow critical chain scheduling and theProgram Evaluation and Review
Technique (PERT) affect scheduledevelopmentDiscuss how reality checks and peopleissues are involved in controlling andmanaging changes to the projectscheduleDescribe how project managementsoftware can assist in project timemanagement and review words of cautionbefore using this software 4
-
8/3/2019 Week 4 Time Chapter 06
5/55
Information Technology ProjectManagement, Sixth Edition
Importance of Project SchedulesManagers often cite delivering projectson time as one of their biggestchallengesTime has the least amount of flexibility;it passes no matter what happens on aprojectSchedule issues are the main reason
for conflicts on projects, especiallyduring the second half of projects
5
-
8/3/2019 Week 4 Time Chapter 06
6/55
Information Technology ProjectManagement, Sixth Edition
Individual Work Styles and CulturalDifferences Cause Schedule Conflicts
Some people prefer to followschedules and meet deadlines whileothers do notDifference cultures and even entirecountries have different attitudes
about schedules
6
-
8/3/2019 Week 4 Time Chapter 06
7/55
Information Technology ProjectManagement, Sixth Edition
Project Time ManagementProcesses
Defining activities : identifying the specific activitiesthat the project team members and stakeholdersmust perform to produce the project deliverables Sequencing activities : identifying and documentingthe relationships between project activitiesEstimating activity resources : estimating howmany resources a project team should use toperform project activitiesEstimating activity durations : estimating thenumber of work periods that are needed to completeindividual activitiesDeveloping the schedule : analyzing activity
sequences, activity resource estimates, and activityduration estimates to create the project scheduleControlling the schedule : controlling andmanaging changes to the project schedule
7
-
8/3/2019 Week 4 Time Chapter 06
8/55
Information Technology ProjectManagement, Sixth Edition
Figure 6-1. Project TimeManagement Summary
8
-
8/3/2019 Week 4 Time Chapter 06
9/55
Information Technology ProjectManagement, Sixth Edition
Defining Activities
An activity or task is an element ofwork normally found on the workbreakdown structure (WBS) that has an
expected duration, a cost, and resourcerequirementsActivity definition involves developing amore detailed WBS and supportingexplanations to understand all the workto be done so you can develop realisticcost and duration estimates
9
-
8/3/2019 Week 4 Time Chapter 06
10/55
Information Technology ProjectManagement, Sixth Edition
Activity Lists and Attributes
An activity list is a tabulation ofactivities to be included on a projectschedule that includes: The activity name An activity identifier or number A brief description of the activityActivity attributes provide moreinformation such as predecessors,
successors, logical relationships, leadsand lags, resource requirements,constraints, imposed dates, andassumptions related to the activity
10
-
8/3/2019 Week 4 Time Chapter 06
11/55
Information Technology ProjectManagement, Sixth Edition
Milestones
A milestone is a significant event thatnormally has no durationIt often takes several activities and a
lot of work to complete a milestoneTheyre useful tools for settingschedule goals and monitoringprogressExamples include obtaining customersign-off on key documents orcompletion of specific products
11
-
8/3/2019 Week 4 Time Chapter 06
12/55
Information Technology ProjectManagement, Sixth Edition
What Went Wrong?
At the U.S. Federal Bureau of Investigation (FBI),poor time management was one of the reasonsbehind the failure of Trilogy, a disastrous,unbelievably expensive piece of vaporware, whichwas more than four years in the (un)making. Thesystem was supposed to enable FBI agents tointegrate intelligence from isolated information siloswithin the Bureau.* In May 2006, the Government Accounting Agency
said that the Trilogy project failed at its core missionof improving the FBIs investigative abilities and wasplagued with missed milestones and escalatingcosts
12
*Roberts, Paul, Frustrated contractor sentenced for hacking FBI to speed deployment, InfoWorld Tech Watch, (July 6, 2006).
-
8/3/2019 Week 4 Time Chapter 06
13/55
Information Technology ProjectManagement, Sixth Edition
Sequencing Activities
Involves reviewing activities anddetermining dependenciesA dependency or relationship is the
sequencing of project activities ortasksYou must determine dependencies in
order to use critical path analysis
13
-
8/3/2019 Week 4 Time Chapter 06
14/55
Information Technology ProjectManagement, Sixth Edition
Three types of Dependencies
Mandatory dependencies : inherent inthe nature of the work being performed ona project, sometimes referred to as hardlogic Discretionary dependencies : defined bythe project team; sometimes referred toas soft logic and should be used with care
since they may limit later schedulingoptions External dependencies : involverelationships between project and non-project activities 14
-
8/3/2019 Week 4 Time Chapter 06
15/55
Information Technology ProjectManagement, Sixth Edition
Network Diagrams
Network diagrams are the preferredtechnique for showing activitysequencing
A network diagram is a schematicdisplay of the logical relationshipsamong, or sequencing of, project
activitiesTwo main formats are the arrow andprecedence diagramming methods
15
-
8/3/2019 Week 4 Time Chapter 06
16/55
Information Technology ProjectManagement, Sixth Edition
Figure 6-2. Sample Activity-on-Arrow(AOA) Network Diagram for Project X
16
-
8/3/2019 Week 4 Time Chapter 06
17/55
Information Technology ProjectManagement, Sixth Edition
Arrow Diagramming Method(ADM)
Also called activity-on-arrow (AOA)network diagramsActivities are represented by arrowsNodes or circles are the starting andending points of activitiesCan only show finish-to-startdependencies
17
-
8/3/2019 Week 4 Time Chapter 06
18/55
Information Technology ProjectManagement, Sixth Edition
Process for Creating AOA Diagrams1. Find all of the activities that start at node 1. Draw
their finish nodes and draw arrows between node 1and those finish nodes. Put the activity letter orname and duration estimate on the associatedarrow.
2. Continue drawing the network diagram, working
from left to right. Look for bursts and merges. Bursts occur when a single node is followed by two or moreactivities. A merge occurs when two or more nodesprecede a single node.
3. Continue drawing the project network diagram untilall activities are included on the diagram that havedependencies.
4. As a rule of thumb, all arrowheads should facetoward the right, and no arrows should cross on an
AOA network diagram. 18
-
8/3/2019 Week 4 Time Chapter 06
19/55
Information Technology ProjectManagement, Sixth Edition
Precedence DiagrammingMethod (PDM)
Activities are represented by boxesArrows show relationships betweenactivitiesMore popular than ADM method andused by project management softwareBetter at showing different types ofdependencies
19
-
8/3/2019 Week 4 Time Chapter 06
20/55
Information Technology ProjectManagement, Sixth Edition
Figure 6-3. Task Dependency Types
20
-
8/3/2019 Week 4 Time Chapter 06
21/55
-
8/3/2019 Week 4 Time Chapter 06
22/55
Information Technology ProjectManagement, Sixth Edition
Estimating Activity ResourcesBefore estimating activity durations, you must
have a good idea of the quantity and type ofresources that will be assigned to each activity;resources are people, equipment, andmaterialsConsider important issues in estimatingresources How difficult will it be to do specific activities on
this project? What is the organizations history in doing similar
activities?
Are the required resources available?A resource breakdown structure is ahierarchical structure that identifies theprojects resources by category and type
22
-
8/3/2019 Week 4 Time Chapter 06
23/55
Information Technology ProjectManagement, Sixth Edition
Activity Duration EstimatingDuration includes the actual amount oftime worked on an activity plus elapsedtimeEffort is the number of workdays orwork hours required to complete a taskEffort does not normally equal durationPeople doing the work should helpcreate estimates, and an expert shouldreview them
23
-
8/3/2019 Week 4 Time Chapter 06
24/55
Information Technology ProjectManagement, Sixth Edition
Three-Point Estimates
Instead of providing activity estimatesas a discrete number, such as fourweeks, its often helpful to create athree-point estimate An estimate that includes an optimistic,
most likely, and pessimistic estimate, suchas three weeks for the optimistic, fourweeks for the most likely, and five weeksfor the pessimistic estimate
Three-point estimates are needed forPERT and Monte Carlo simulations
24
-
8/3/2019 Week 4 Time Chapter 06
25/55
Information Technology ProjectManagement, Sixth Edition
Developing the ScheduleUses results of the other timemanagement processes to determinethe start and end date of the projectUltimate goal is to create a realisticproject schedule that provides a basisfor monitoring project progress for thetime dimension of the projectImportant tools and techniques includeGantt charts, critical path analysis,and critical chain scheduling, andPERT analysis
25
-
8/3/2019 Week 4 Time Chapter 06
26/55
Information Technology ProjectManagement, Sixth Edition
Gantt ChartsGantt charts provide a standardformat for displaying project scheduleinformation by listing project activitiesand their corresponding start and finish
dates in a calendar formatSymbols include: Black diamonds: milestones Thick black bars: summary tasks Lighter horizontal bars: durations of tasks Arrows: dependencies between tasks
26
-
8/3/2019 Week 4 Time Chapter 06
27/55
Information Technology ProjectManagement, Sixth Edition
Figure 6-5. Gantt Chart forProject X
27
Note: Darker bars would be red in Project 2007 to represent critical tasks.
-
8/3/2019 Week 4 Time Chapter 06
28/55
Information Technology ProjectManagement, Sixth Edition
Figure 6-6. Gantt Chart for SoftwareLaunch Project
28
-
8/3/2019 Week 4 Time Chapter 06
29/55
Information Technology ProjectManagement, Sixth Edition
Adding Milestones to GanttCharts
Many people like to focus on meetingmilestones, especially for largeprojects
Milestones emphasize importantevents or accomplishments onprojects
Normally create milestone by enteringtasks with a zero duration, or you canmark any task as a milestone
29
-
8/3/2019 Week 4 Time Chapter 06
30/55
Information Technology ProjectManagement, Sixth Edition
SMART Criteria
Milestones should be: S pecific Measurable Assignable Realistic Time-framed
30
-
8/3/2019 Week 4 Time Chapter 06
31/55
Information Technology ProjectManagement, Sixth Edition
Best Practice
Schedule risk is inherent in the development of complexsystems. Luc Richard, the founder ofwww.projectmangler.com, suggests that projectmanagers can reduce schedule risk through projectmilestones, a best practice that involves identifying andtracking significant points or achievements in the project.The five key points of using project milestones includethe following:1. Define milestones early in the project and include them in the
Gantt chart to provide a visual guide.2. Keep milestones small and frequent.3. The set of milestones must be all-encompassing.4. Each milestone must be binary, meaning it is either complete or
incomplete.5. Carefully monitor the critical path.
31
Fi 6 7 S l T ki G tt
-
8/3/2019 Week 4 Time Chapter 06
32/55
Information Technology ProjectManagement, Sixth Edition
Figure 6-7. Sample Tracking GanttChart
32
-
8/3/2019 Week 4 Time Chapter 06
33/55
Information Technology ProjectManagement, Sixth Edition
Critical Path Method (CPM)CPM is a network diagrammingtechnique used to predict total projectdurationA critical path for a project is the seriesof activities that determines the earliest time by which the project can becompletedThe critical path is the longest path through the network diagram and has the
least amount of slack or floatSlack or float is the amount of time anactivity may be delayed without delayinga succeeding activity or the project finish
date 33
-
8/3/2019 Week 4 Time Chapter 06
34/55
Information Technology ProjectManagement, Sixth Edition
Calculating the Critical Path
First develop a good network diagramAdd the duration estimates for allactivities on each path through the
network diagramThe longest path is the critical pathIf one or more of the activities on thecritical path takes longer than planned,the whole project schedule will slipunless the project manager takes
corrective action 34
-
8/3/2019 Week 4 Time Chapter 06
35/55
Information Technology ProjectManagement, Sixth Edition
Figure 6-8. Determining the Critical Pathfor Project X
35
-
8/3/2019 Week 4 Time Chapter 06
36/55
Information Technology ProjectManagement, Sixth Edition
More on the Critical PathA project team at Apple computer put a
stuffed gorilla on the top of the cubicle of theperson currently managing critical taskThe critical path is not the one with all thecritical activities; it only accounts for time
Remember the example of growing grass beingon the critical path for Disneys Animal Kingdom There can be more than one critical path ifthe lengths of two or more paths are thesameThe critical path can change as the projectprogresses
36
-
8/3/2019 Week 4 Time Chapter 06
37/55
Information Technology ProjectManagement, Sixth Edition
Using Critical Path Analysis toMake Schedule Trade-offs
Free slack or free float is the amount oftime an activity can be delayed withoutdelaying the early start of any immediatelyfollowing activities
Total slack or total float is the amount oftime an activity may be delayed from itsearly start without delaying the plannedproject finish dateA forward pass through the networkdiagram determines the early start andfinish datesA backward pass determines the late startand finish dates
37
-
8/3/2019 Week 4 Time Chapter 06
38/55
Information Technology ProjectManagement, Sixth Edition
Figure 6-9. Calculating Early and LateStart and Finish Dates
38
-
8/3/2019 Week 4 Time Chapter 06
39/55
Information Technology ProjectManagement, Sixth Edition
Table 6-1. Free and Total Float orSlack for Project X
39
-
8/3/2019 Week 4 Time Chapter 06
40/55
Information Technology ProjectManagement, Sixth Edition
Using the Critical Path toShorten a Project Schedule
Three main techniques for shorteningschedules Shortening durations of critical
activities/tasks by adding more resourcesor changing their scope Crashing activities by obtaining the
greatest amount of schedule compressionfor the least incremental cost
Fast tracking activities by doing them inparallel or overlapping them
40
-
8/3/2019 Week 4 Time Chapter 06
41/55
Information Technology ProjectManagement, Sixth Edition
Importance of Updating CriticalPath Data
It is important to update projectschedule information to meet timegoals for a project
The critical path may change as youenter actual start and finish datesIf you know the project completion
date will slip, negotiate with the projectsponsor
41
-
8/3/2019 Week 4 Time Chapter 06
42/55
Information Technology ProjectManagement, Sixth Edition
Critical Chain SchedulingCritical chain scheduling A method of scheduling that considers
limited resources when creating a projectschedule and includes buffers to protect theproject completion date
Uses the Theory of Constraints (TOC) A management philosophy developed by
Eliyahu M. Goldratt and introduced in hisbook The Goal and Critical Chain
Attempts to minimize multitasking When a resource works on more than one
task at a time
42
Figures 6 10a and 6 10b
-
8/3/2019 Week 4 Time Chapter 06
43/55
Information Technology ProjectManagement, Sixth Edition
Figures 6-10a and 6-10b.Multitasking Example
43
-
8/3/2019 Week 4 Time Chapter 06
44/55
Information Technology ProjectManagement, Sixth Edition
Buffers and Critical ChainA buffer is additional time to complete ataskMurphys Law states that if something cango wrong, it willParkinsons Law states that work expandsto fill the time allowedIn traditional estimates, people often add abuffer to each task and use it if its neededor notCritical chain scheduling removes buffersfrom individual tasks and instead creates: Project buffers or additional time added before
the projects due date Feeding buffers or additional time added
before tasks on the critical path
44
Figure 6 11 Example of Critical Chain
-
8/3/2019 Week 4 Time Chapter 06
45/55
Information Technology ProjectManagement, Sixth Edition
Figure 6-11. Example of Critical ChainScheduling
45
-
8/3/2019 Week 4 Time Chapter 06
46/55
Information Technology ProjectManagement, Sixth Edition
Program Evaluation and ReviewTechnique (PERT)
PERT is a network analysis techniqueused to estimate project durationwhen there is a high degree ofuncertainty about the individual activityduration estimatesPERT uses probabilistic timeestimates Duration estimates based on using
optimistic, most likely, and pessimisticestimates of activity durations, or a three-point estimate
46
-
8/3/2019 Week 4 Time Chapter 06
47/55
Information Technology ProjectManagement, Sixth Edition
PERT Formula and ExamplePERT weighted average =
optimistic time + 4X most likely time + pessimistic time6
Example:PERT weighted average =8 workdays + 4 X 10 workdays + 24 workdays = 12
days 6where optimistic time = 8 daysmost likely time = 10 days , andpessimistic time = 24 days
Therefore, youd use 12 days on the network diagraminstead of 10 when using PERT for the above example
47
h d l l
-
8/3/2019 Week 4 Time Chapter 06
48/55
Information Technology ProjectManagement, Sixth Edition
Schedule ControlSuggestions
Perform reality checks on schedulesAllow for contingenciesDont plan for everyone to work at100% capacity all the timeHold progress meetings withstakeholders and be clear and honest
in communicating schedule issues
48
-
8/3/2019 Week 4 Time Chapter 06
49/55
Information Technology ProjectManagement, Sixth Edition
Controlling the ScheduleGoals are to know the status of theschedule, influence factors that causeschedule changes, determine that theschedule has changed, and managechanges when they occur
Tools and techniques include: Progress reports A schedule change control system Project management software, including
schedule comparison charts like the tracking
Gantt chart Variance analysis, such as analyzing float orslack
Performance management, such as earnedvalue (Chapter 7)
49
-
8/3/2019 Week 4 Time Chapter 06
50/55
Information Technology ProjectManagement, Sixth Edition
Reality Checks on Scheduling
First review the draft schedule orestimated completion date in theproject charter
Prepare a more detailed schedule withthe project teamMake sure the schedule is realistic
and followedAlert top management well in advanceif there are schedule problems
50
-
8/3/2019 Week 4 Time Chapter 06
51/55
Information Technology ProjectManagement, Sixth Edition
Working with People Issues
Strong leadership helps projectssucceed more than good PERT chartsProject managers should use: Empowerment Incentives Discipline
Negotiation
51
-
8/3/2019 Week 4 Time Chapter 06
52/55
Information Technology ProjectManagement, Sixth Edition
What Went Right?Mittal Steel Poland earned Polands Project
Excellence Award in 2007 for implementing a SAPsystemDerek Prior, research director at AMR Research,identified three things the most successful SAP
implementation projects do to deliver businessbenefits: Form a global competence centre Identify super-users for each location Provide ongoing involvement of managers in
business processes so they feel they own theseprocesses
52
f
-
8/3/2019 Week 4 Time Chapter 06
53/55
Information Technology ProjectManagement, Sixth Edition
Using Software to Assist in TimeManagement
Software for facilitatingcommunications helps peopleexchange schedule-related
informationDecision support models help analyzetrade-offs that can be made
Project management software canhelp in various time managementareas
53
d f
-
8/3/2019 Week 4 Time Chapter 06
54/55
Information Technology ProjectManagement, Sixth Edition
Words of Caution on UsingProject Management Software
Many people misuse projectmanagement software because theydont understand important conceptsand have not had trainingYou must enter dependencies to havedates adjust automatically and todetermine the critical path
You must enter actual scheduleinformation to compare planned andactual progress
54
-
8/3/2019 Week 4 Time Chapter 06
55/55
Chapter Summary
Project time management is often citedas the main source of conflict onprojects, and most IT projects exceedtime estimatesMain processes include: Define activities Sequence activities
Estimate activity resources Estimate activity durations Develop schedule Control schedule