![Page 1: U-M Construction Forecast; June 22, 2011 U-M Construction Forecast Summer– Fall 2011 North Campus Neighborhood Meeting June 22, 2011 Prepared by AEC Preliminary](https://reader035.vdocuments.mx/reader035/viewer/2022062619/5516574c550346b2068b5b4d/html5/thumbnails/1.jpg)
U-M Construction Forecast; June 22, 2011
U-M Construction Forecast Summer– Fall 2011
North Campus Neighborhood Meeting
June 22, 2011Prepared by AEC
Preliminary & Advisory
![Page 2: U-M Construction Forecast; June 22, 2011 U-M Construction Forecast Summer– Fall 2011 North Campus Neighborhood Meeting June 22, 2011 Prepared by AEC Preliminary](https://reader035.vdocuments.mx/reader035/viewer/2022062619/5516574c550346b2068b5b4d/html5/thumbnails/2.jpg)
U-M Construction Forecast; June 22, 2011
Agenda
1. Welcome, sign-in, introductions 2:00 PM
2. Meeting overview 2:05 PM• Project by season and in detail• Snapshot in time…not all projects• Construction coordination efforts
3. Projects FY 2011 2:10 PM• Project by season overview• Projects in detail
– Anticipated project start/end dates– Construction limits/logistics– Detour signage (if applicable)– Staging/impacts– Anticipated work hours
• About map reading
4. Questions/comments 2:45 PM
5. Adjourn 3:00 PM
![Page 3: U-M Construction Forecast; June 22, 2011 U-M Construction Forecast Summer– Fall 2011 North Campus Neighborhood Meeting June 22, 2011 Prepared by AEC Preliminary](https://reader035.vdocuments.mx/reader035/viewer/2022062619/5516574c550346b2068b5b4d/html5/thumbnails/3.jpg)
U-M Construction Forecast; June 22, 2011
North Campus – Summer 2011
![Page 4: U-M Construction Forecast; June 22, 2011 U-M Construction Forecast Summer– Fall 2011 North Campus Neighborhood Meeting June 22, 2011 Prepared by AEC Preliminary](https://reader035.vdocuments.mx/reader035/viewer/2022062619/5516574c550346b2068b5b4d/html5/thumbnails/4.jpg)
U-M Construction Forecast; June 22, 2011
North Campus – Summer 2011
Beal Avenue Water Main & Storm Sewer Relief Project
• Beal Avenue north of Electrical Engineering and
Computer Science (EECS) closed for duration of project
• Beal Avenue south of EECS closed intermittently
• Parking lots along Beal Avenue will have intermittent closures
![Page 5: U-M Construction Forecast; June 22, 2011 U-M Construction Forecast Summer– Fall 2011 North Campus Neighborhood Meeting June 22, 2011 Prepared by AEC Preliminary](https://reader035.vdocuments.mx/reader035/viewer/2022062619/5516574c550346b2068b5b4d/html5/thumbnails/5.jpg)
U-M Construction Forecast; June 22, 2011
North Campus – Summer 2011
Michigan Memorial Phoenix Lab Addition
![Page 6: U-M Construction Forecast; June 22, 2011 U-M Construction Forecast Summer– Fall 2011 North Campus Neighborhood Meeting June 22, 2011 Prepared by AEC Preliminary](https://reader035.vdocuments.mx/reader035/viewer/2022062619/5516574c550346b2068b5b4d/html5/thumbnails/6.jpg)
U-M Construction Forecast; June 22, 2011
North Campus – Fall 2011
![Page 7: U-M Construction Forecast; June 22, 2011 U-M Construction Forecast Summer– Fall 2011 North Campus Neighborhood Meeting June 22, 2011 Prepared by AEC Preliminary](https://reader035.vdocuments.mx/reader035/viewer/2022062619/5516574c550346b2068b5b4d/html5/thumbnails/7.jpg)
U-M Construction Forecast; June 22, 2011
Thank you!
For more information:
• U-M construction traffic updates:
http://www.umaec.umich.edu/closures.html
• City of Ann Arbor construction traffic updates:
http://www.a2gov.org/Alerts/Pages/EventRoadClosuresandDetours.aspx
• Weekly Construction Coordination meetings, Tuesdays at 3:00 PM, AEC
Contacts:
Sue Gott: [email protected]
Tony Catchot: [email protected]