History of PMIS in TxDOT • PMIS development began in May 1990 in response
to a Federal mandate that every State have a Pavement Management System in place by February 1993.
• PMIS was an expansion of the existing Pavement • Evaluation System (PES), PES used 2-mile rating
sections instead of the 0.5-mile sections now used in PMIS.
Footer Text
BACKGROUND
Objective: to establish a modern pavement management system for the State of Texas An Integrated system including PMIS and Mapzapper
functionality and more (e.g., 4-year plan). From Mainframe to Windows-Based (user-friendly) GIS-based Web-accessed Enhanced analytical capability
Project contractor: AgileAssets®, Inc.
Project duration: 2 years (1st year go-live, 2nd year testing)
Footer Text
LOG IN INTERFACE
Footer Text
PICK A “DEPARTMENT”
Footer Text
SIX MODULES
Database: PMIS data and more Analysis: performance and network analysis Reports: annual report, detailed reports, etc. Setup: to support database and analysis etc. Utilities: dynamic segregation GIS: mapping functions
Footer Text
DATABASE MODULE
Footer Text
DATABASE MODULE
Footer Text
Condition Summary Table
10
Footer Text
Filter Menu
11
Footer Text
DATABASE MODULE – EXAMPLE (GRAPH)
Footer Text
Graph Down the Road
13
Footer Text
DATABASE MODULE
Footer Text
DATABASE MODULE – EXAMPLE (WORK HISTORY)
Footer Text
Example Work History
16
Footer Text
DATABASE MODULE
Footer Text
DATABASE MODULE
Footer Text
DATABASE MODULE
Footer Text
DATABASE MODULE
Footer Text
ANALYSIS MODULE
Footer Text
ANALYSIS MODULE – EXAMPLE (OPTIMIZATION)
Footer Text
Analysis Module
Determine how much money is needed to achieve a specific
target Determine the future pavement condition based on current
spending levels. Ability to run different scenarios and evaluate the impact.
23
Footer Text
Reports
24
Footer Text
REPORTS MODULE
Footer Text
District Scores
26
Footer Text
Sample Report Menu
27
Footer Text
Reports
Lane Miles by Pavement Scores Lane Miles by Lane width
Lane Miles by Shoulder width
Lane Miles by Pavement type (Broad & Detailed)
Lane Miles of frontage roads
Lane Miles by highway classification
28
Footer Text
GIS MODULE
Footer Text
GIS Menu
30
Footer Text
GIS MODULE - EXAMPLE
Footer Text
Summary
TxDOT will have a state of the art Pavement Management System. Comprehensive System