Engineering Change Request System {CRS}
Released in the Windchill Environment
User Training Manual
Engineering Change Request System {CRS}
Released in the Windchill Environment
User Training Manual
TRW Automotive
November, 2004
TRW Automotive
November, 2004
2
TRWTRWTraining Topics Training Topics Introduction & Overview / Task Driven System
CRS Access, Navigation, Setting User Profile
Worklist, Search, Personal Calendars, Reassign, BOM View
Part Master / Summary of all Part Data
Review and Approve
Change Issues
Document Creation
Part Generator / Clipboard
Deviation, P&R & GI
IPD (Internal Plant Document)
Engineering Request Documents
Value Additions & Technical Support
Introduction & Overview / Task Driven System
CRS Access, Navigation, Setting User Profile
Worklist, Search, Personal Calendars, Reassign, BOM View
Part Master / Summary of all Part Data
Review and Approve
Change Issues
Document Creation
Part Generator / Clipboard
Deviation, P&R & GI
IPD (Internal Plant Document)
Engineering Request Documents
Value Additions & Technical Support
3
TRWTRW
Aschau Engineering
Center
Customer Assembly Plants
Aschaffenburg Engineering Center
Washington/MesaEngineering Centers
Alfdorf Engineering
Center
About CRS - Global Overview/Impact - Design Release/Update Shared Drawing Use, Notifications,
Approvals, BOM Control and Access, Multiple Manufacturing Centers, Customers, Suppliers About CRS - Global Overview/Impact - Design Release/Update Shared Drawing Use, Notifications,
Approvals, BOM Control and Access, Multiple Manufacturing Centers, Customers, Suppliers
Production
Production
Production
ProductionProduction
Production
Production
Production
Production
Production
Production
Production
Supply Base
Supply Base
Supply Base
Supply
Base
Drawing
Formats
Supply Base
Drawing
Formats
Drawing
Formats
Drawing
Formats
Drawing
Formats
Drawing
Formats
Drawing
Formats
Drawing
Formats
Drawing
Formats
Drawing Formats
Drawing
Formats
Supply Base
Supply
BaseSupply Base
4
TRWTRWOur Global electronic system is called CRS (Change Request System), within the system we process various documents that are used to summarize all information that pertains to that document type
Our Global electronic system is called CRS (Change Request System), within the system we process various documents that are used to summarize all information that pertains to that document type
ERD - Engineering Request Document authorizes the release of procedures, production and prototype drawings. Gathers customer, functional group and plant approvals. Identifies all impacted facilities and authorizes BOM activity. Requires addressing service, engineering tests, DFMEA, global and other issues.
DEV - Deviations provide authorization for variances from the acceptable production intent on design, testing, shipments, bill of material (part replacement to prevent obsolescence or support availability), rework, part traceability, PPAP, recall and other conditions that do not meet production standards
P&R – Process and Routing documents are used for supplier tool moves, line moves, tool refurbishment and component PPAPs. They describe and authorize a permanent change to a process and facilitate PFMEA and Control Plan document updates due to design change.
GI - General Information notices are used for documentation, notification and confirmation of various engineering activity.
CI – Change Issues are new documents used for information gathering and soliciting responses from selected individuals where posted and response dates are tracked. Responses can be used to support engineering decisions or represent concurrence from a supplier that drawings and PO’s have been received.
IPD – Internal Plant Documents are new routings to be used for the notification and releasing of plant specific documentation. Very automated and simple to use
5
TRWTRW
Input Sources: Customer / Supplier / Test / Manufacturing / VAVE / Issues
Originator / Engineer initiates ERD and leaves in create status
PRA completes ERD(impact analysis upon customer, carlines, parts, plant, tools, etc.)
Design initiates the final drawing(s) update process then approves their task
Approval Team
Finished
ERD and Drawings in "Release" status {Viewable in WCRS}
Drawing Mark-Up process begins.
SET approval process is initaited. Includes; engineering, quaility, plant, design etc.
Global ERD Process Flow
for Parts and BOM
yes
no
Approval Issues are resolved by contacting the appropriate individuals
Create Status
In-Process Status
Information contained on the ERD: ERD(folder)#Initiation Source Lead ProgramProject NumberPart Numbers EffectedFacilities ImpactedService ImpactNotif ication TeamApproval SummaryProblem/Descriptions/ReasonsBOM information Customer approval requirementsDesign center responsibleCross customer / Global indicatorsCost (PCS/RPPA) Information supplied by engineer:Electronic Mark-Up'sOther attachmentsCustomer Approval Documents
Pre-Release
Release Status
Note: May be slight variations in flow at each engineering center; i.e. Design update initiated after approvals
Essential Steps:
All Parts Released in ERD and Notification made
ERD Approval of Proposed Changes
Drawings Completed and Registered (ERD Release)
Part Utilization in Affected Mfg plants
Global access to BOM information
Continued
Engineering Part Release Process Improvements Note: A Change Issue can be used to gather and assemble engineering information prior to the initiation of an ERD.
6
TRWTRW
Parts from ERD are auto loaded into Global EBOM Part Master Plant specific
templates created for Part Downloads to ERP System Part Masters
Structure BOM in Plant Specific ERP system (MBOM) {Engineering Control}
Manufacturing Info attached, PM, Plant management of Prod effective dates
"WCRS" VIEW All
BOM Information
From One System
Selections:
* Enter Plant
* Enter Part Number
* Select Single or Multi Level
* Select BOM Display
* Print Out BOM
BOM Displays:
* Date Range Parameters
* No Date - All Confi gurations
All Parts are released in WCRS and electronically downloaded to all impacted plants, as indicated in ERD
Engineering Part Release Process Improvements Continued
7
TRWTRWCRS Access & NavigationCRS Access & Navigation
Internet Browser Internet Explorer 5.5 or higher
URL: Training: http://wctrn4.washmi.trw.com/Windchill/wtcore/jsp/wt/portal/index.jsp
Production: http://connect.trw.com/Windchill/wtcore/jsp/wt/portal/index.jsp
Login Dialog Box: Enter User ID, &
Password
Internet Browser Internet Explorer 5.5 or higher
URL: Training: http://wctrn4.washmi.trw.com/Windchill/wtcore/jsp/wt/portal/index.jsp
Production: http://connect.trw.com/Windchill/wtcore/jsp/wt/portal/index.jsp
Login Dialog Box: Enter User ID, &
PasswordPeople Soft ID, if available, or, use your Email Address
Password can be Customized
If you are new to Windchill (do not have a current ID and password) you will be sent an email prior to Launch
8
TRWTRWHow To Request a Userid How to Change a password if you have forgottenHow To Request a Userid How to Change a password if you have forgotten
If you do not have a user ID you can request one online.
If you have forgotten your password you can request a reset.
This must be completed prior to using the system
9
TRWTRWCRS Access & Navigation Winchill HomepageCRS Access & Navigation Winchill Homepage
CRS Main Menu
Toolbar
Access Worklist
Personal Cabinet
Setup Page
Search
Visualization
Meeting Center
Library
The remainder of these icons are used for administrative purposes.
10
TRWTRWSetting User ProfileSetting User Profile
From the Home Page, select My Profile
Select Change User Preference*YOU MUST ENTER USER FACILITY AND FUNCTION to use the system.
11
TRWTRWSetting User ProfileSetting User Profile
Select Facility from Change Facility Drop Down List (i.e. Plant)
Select Function from Drop Down List (i.e. Job title)
Change Password Utility
(People Soft IDOr Email Address)
TRWTRW
Worklist, Search, Personal
Calendars, Reassign, BOM View, ENG Part
List
Worklist, Search, Personal
Calendars, Reassign, BOM View, ENG Part
List
13
TRWTRWAccessing the WorklistAccessing the Worklist
The Worklist supplies each user with “tasks” that allows the user to complete the activity indicated (varies with each document).
Manage Layouts allows user to customize worklist, see next slide.
14
TRWTRWAccessing the WorklistChanging worklist layoutAccessing the WorklistChanging worklist layout
The Manage Layouts feature allows the user to change the way tasks are displayed in their worklist. Each column can be sorted or grouped. *Note: the recommended Default for CRS users is as Shown above and results shown below.
15
TRWTRWPersonal CalendarDelegate Task – used with a know time of absencePersonal CalendarDelegate Task – used with a know time of absence
The calendar allows the user to delegate tasks on indicated days.
Look up another users calendar.Calendar will show users working days &If tasks will be assigned to a different user.
Select days to delegate tasks, click delegate.Select User from list and click OK button.All tasks assigned on that calendar day will be reassigned to the indicated user. (New users name will now be written on that calendar day.
16
TRWTRWReassigning TaskIf you received a task meant for someone else you can forward to the correct individual
Reassigning TaskIf you received a task meant for someone else you can forward to the correct individual
Check the “Work Item Selector” box and select the Reassign button.
Select User to reassign to, and click Submit, task will delete out of worklist.The approval page of the document will show user 1 reassigned to user 2.
17
TRWTRWGroupWise Task Notification GroupWise Task Notification
To access the worklist from your email notification select the “HERE” link
18
TRWTRWA Task is sent to a users worklist upon their role in the Work flow. For example, when a user creates any type of CRS document, a task will enter that users worklist. The Instructions indicate their next actions.
Example Task Example Task
The CRS document “ERD”, is accessed through a Link in the Task
You may enter Comments that will appear in the Task that is sent to the next user in the workflow.
An ‘OkToTool’ selection will need a Checker and a Release Analyst. Just the Release Analyst for a ‘Standard Release’ selection
Selecting Task Complete continues the workflow for a newly created document.
19
TRWTRWSearch optionsSearch options
Windchill allows the user to search specifically for certain documents, reports, parts, etc.By entering a key word, Windchill will search for all documents including that word.
20
TRWTRWExample Search ResultsExample Search Results
Example search results for all Released ERDs originating in Aschau.
21
TRWTRWExample Search ResultsExample Search Results
Search on Part will give you results like below:
Links to PartMaster
Links to Spicer
Links to Eng Part List
22
TRWTRWInformation acquired from ERP SystemInformation acquired from WCRS SystemManual editing i.e.Plant/Part Variation
Assemblies should have a link to launch their Eng Part List
Example from Search Results - Eng Part ListExample from Search Results - Eng Part List
23
TRWTRWView BOM from SAPView BOM from SAP
From the WCRS homepage, select WCRS, View BOMs from SAP.
Type the part number, select plant, effectivity dates and click single level or multiple level query.
24
TRWTRWExample of Single Level BOM Query from SAPExample of Single Level BOM Query from SAP
Note: View BOM from Maxcim is used the same.
TRWTRW
Part MasterPart Master
26
TRWTRWPart MasterPart Master
Continued
Link to all drawings registered (markups, released, etc.)
6L3435611B08AAW
6L3435611B08ABWB6L3435611B08AAW
000395, 000398
ENG Part List
27
TRWTRWPart Master, cont.Part Master, cont.
Part Master includes all platforms affected, and all related parts (service numbers, customer numbers, colors, SAP numbers) if applicable.
TRWTRW
Change IssueChange Issue
29
TRWTRW
35
CreatorInitiates
CI
Prg. MgrRequired
?
YesPrg. Mgr selectsChange Owner
No
Change Owner selects
Reviewers
Users review CIComplete Task,
Provide Feedback
Change Ownerreviewsfeedback
Accepted
Cancel
Creator selects
Reviewers
Flow Chart for WC Change Issue
Additional Info
Creator becomes the Change
Owner
CancelCreator selects
Prg.Mgr
Sent to wrong PM
When reviewers have responded or a Maximum of 5 working days, the Change Owner will receive another task summarizing the reviewer responses.
System OverviewInformal information gathering tool – CI workflow
Many uses exist for this tool. The routing, sharing, concurrence, gathering of information can easily be acquired through this workflow and available for decision making or use as an attachment to an ERD.
30
TRWTRWCreating a Change IssueCreating a Change Issue
A Change Issue is an informal document, that can be used for:
Gathering ideas Obtaining, Attaching or Sending files Attaching to a CRS Document when beneficial
Select WCRS from the menu bar. Select Create CI – Change Issue.
31
TRWTRWCreating Change Issue, cont.Creating Change Issue, cont.
Complete all fields on Request screen. Fields flagged with “*” are required. When attachments are completed select WorkList link.
Click Save
Link to add attachments
For attachments select Browse to locate file, when finished adding files, select Complete.
Continued
32
TRWTRWCreating Change Issue, cont.Creating Change Issue, cont.By selecting Worklist from Change Issue you would view as below
Select link to launch into task.
OR:Task can be accessed via Groupwise notification
Select link.
33
TRWTRWCreating Change Issue, cont.This is the Change Issue TaskCreating Change Issue, cont.This is the Change Issue Task
Link to view Change Issue
To add Program Manager or Reviewers, select Add Users button. Search for users, select and click Add. Multiple users may be selected from this window. Once finished, select OK.
Select from available options.Perform Review (send to Reviewers) or to Program Manager.Select Task Complete
34
TRWTRWCompleting a Change IssueCompleting a Change Issue
Once the Change Owner accepts the final task, the Change Issue will move to ‘Completed’ State. Once a Change Issue is complete, it may be attached to an ERD for supporting documentation if needed. A Change Issue may only be attached to one ERD.
TRWTRW
Part GeneratorPart Generator
36
TRWTRWPart GeneratorPart Generator
From the Windchill home page, select WCRS from the menu bar on the left. Select Part Generator. You have the option to create TRW Part Numbers, Non-TRW Part Numbers (admin only), TRW Chart Part Numbers or Engineering Document numbers i.e. specs, procedures.
37
TRWTRWPart GeneratorPart Generator
Select from pop-up window Part Description & Commodity Code. All fields except for Part Ref. Desc are req’d.
Select Number of Parts to Generate and select Create Part(s).
The Clipboard will store all parts that you have previously created.
All Part or Document Types Can be Selected from this field
* Buyer Mary Jane - Plastic
38
TRWTRWUpdating/Viewing PartsCreated Parts – The ClipboardUpdating/Viewing PartsCreated Parts – The Clipboard
Part Generator will automatically pull a CV & DV part. Select the links to view the part master. The update link will allow you to change any information if needed.
Example clipboard.
TRWTRW
Engineering Request
Documents, Creation and MU
Example
Engineering Request
Documents, Creation and MU
Example
40
TRWTRWEngineering Request DocumentCreateEngineering Request DocumentCreate
From the Windchill main menu select Create ERD.
41
TRWTRWEngineering Request DocumentRequest PageEngineering Request DocumentRequest Page
Complete all required fields and click Save.
WCRS will do three things: 1) assign an ERD number2) add the attachment bars3) send a task to the creators
worklist.
Documents/Drawings for Release:Any document to be released within the ERD.User Reference Documents:Attachment added for supporting documentation.Change Issue:Attach from within WCRS for link to files/approvals, etc.Windchill System Documents:Any document attached from within Windchill (i.e. Procedures, IP Documents, CAD files, etc.)
Go to Part Submissions to complete ERD
42
TRWTRWCreate new layer.
Mark up drawing using tools on left side of screen.
**Include ERD#, revision, your name, and date in revision column Mark-up note. If ERD is Advanced Release or OK to Tool, also note on drawing.**
New Layer
Line
Arrow
Creating an Electronic Markup in Spicer
Text
Highlight
Circle
Dimension
Select
Move/Resize
43
TRWTRW
4. Choose file location. This can be a folder created on your computer
5. Type file name (followed by .smf), use this format
6. File type should be Spicer Document (.smf)
1. File
2. Save As
3. Browse
7. Save
Saving an Electronic Markup
33045678_A01.smf
44
TRWTRWEngineering Request DocumentPart SubmissionsEngineering Request DocumentPart Submissions
Once the Request page is complete, click Part Submissions to add parts to be released.
A Part Submission Wizard will pop up similar to that of a Deviation.
Click here to add Parts.
45
TRWTRWEngineering Request DocumentPart Submission WizardEngineering Request DocumentPart Submission Wizard Change Item Type:
TRW PartNon-TRW PartDocumentSource Selection:Select from WCRSCopy from Submissions Already DefinedGenerate New Number (Links to Part Master)Current Part Number:Can be manually entered, or searched in WCRSChange Type:Initial ReleaseMajor RevisionMinor RevisionNo Drawing ImpactObsoleteProgram AddComplete required fields and click Next.
Step 2 will display the current status of the part in Part Master.Status on Pending ERDs will display all ERDs that that part is listed on and not yet released. Select revision that the new ERD will be superceding.
000553
46
TRWTRWEngineering Request DocumentPart Submission WizardEngineering Request DocumentPart Submission Wizard
Complete required fields in Step 3. and click Finish.
WCRS will then ask if you want to add more Parts.Yes will direct you back to Step 1. of the Part Submission.No will close the window and exit the wizard.
47
TRWTRWEngineering Request DocumentSelect PRA TaskEngineering Request DocumentSelect PRA Task
Always review Instructions for each task.They are different for each step in the workflow.
Enter comments if desired.A comment is required if user is canceling, or placing a document on hold.
Select Standard Release or Ok to Tool/Advanced Release.This selection must match field selected on Request page.
Select Design Checker (if Ok to Tool / Advanced Release), PRA, and select Task Complete.
After completing Request Page & Part Submissions page, go to your worklist to access Task.
48
TRWTRWEngineering Request DocumentApproval Team Review/ApprovalEngineering Request DocumentApproval Team Review/Approval
After PRA completes document, approval members can access task through their worklist.
Link to view document.Recommendation: right click and select Open in New Window.This allows user to view document and close window vs. clicking back button to task page.
Enter comments if desired. Required if placing on hold.Click Task Complete.
49
TRWTRWEngineering Request DocumentPart Detail pageEngineering Request DocumentPart Detail page
Print option allows user to select specific pages or all information to print.Document will be formatted and opened in new window. Select File, Print in browser.This link is available from all screens within the document.
Click on part number to view drawings. Links will appear below.
Update Print
50
TRWTRWEngineering Request DocumentPlatform PageEngineering Request DocumentPlatform Page
Select links to display platforms associated to that part number. Active part number will be highlighted.
51
TRWTRWEngineering Request DocumentApproval PageEngineering Request DocumentApproval Page
Approval page will display pending & completed approvals. Plant Facilitator may add approvers as required.
Everyone has the ability to extend an FYI in any state of the document.WCRS will record and display sent to, sent from, date & comment.
52
TRWTRWEngineering Request DocumentTrackingEngineering Request DocumentTracking
Approvals prior to submitting OTT/Adv. Release to PRA. Must be checked in Create State
Approval by PRA after design has completed drawing(s).
Design approval by engineer. This box will auto fill via task.
To be completed by plant personnel.
TRWTRW
Deviation, GI & P&RDeviation, GI & P&R
54
TRWTRWCreating a DeviationCreating a Deviation
From the WCRS homepage, select WCRS from the menu bar. Select Create DEV - Deviation
55
TRWTRWCreating a DeviationCreating a Deviation
56
TRWTRWCreating a Deviation (Part Details)Creating a Deviation (Part Details)
User must be in Update mode to add/update the part details page. To add parts, click the Add New Details button .
57
TRWTRWTakes you to Part Detail WizardTakes you to Part Detail Wizard
Complete the required fields using the Part Details Wizard.
Select Finish when complete, the Part Details page will auto fill.
58
TRWTRWCreating a DeviationCreating a Deviation
Active Part number will be RedDeselect the Unaffected Platforms in relation to this part number.
Note: After you Save, now you have completed user input for the DeviationNow you can go to the Worklist and send to PRA for processing
59
TRWTRWApproval PageApproval Page
System will display all pending approvals. Hold comments will also appear under Pending Approvals
Approvals with comments will appear under Approvals.
Click Create FYI to extend FYI.
60
TRWTRWCreating a DeviationCreating a Deviation
Once the deviation is complete, access task via worklist. Choose PRA Product Release Analyst, Add comments if desired and select Task Complete. This sends your newly created Deviation out for processing
61
TRWTRWReview and ApproveReview and Approve
Access Task via worklist or GroupWise notification.
Review document by selecting link (right click and open in new window)
After review of document enter comments if desired, select Approve or On Hold (comments required if placing the document on Hold) and click Task Complete.
62
TRWTRWCreating a GICreating a GI
63
TRWTRWCreating a GICreating a GI
Enter Part Number and select Check. The system will auto fill all fields except for Part Summary.**Be sure to select Add button before switching screens or part will not be saved.**
64
TRWTRWCreating a GICreating a GI
Deselect the Unaffected Platforms in relation to this part number.
65
TRWTRWCreating a P&RCreating a P&R
Complete required fields, add attachments if desired and select Save
66
TRWTRWCreating a P&RCreating a P&R
Enter Part Number and click Check. Fields will auto fill, complete Part Summary and click Save.
TRWTRW
Internal Plant Documents
Internal Plant Documents
68
TRWTRWInternal Plant DocumentsCreateInternal Plant DocumentsCreate
An IPD is used within Windchill to create documents used strictly for the originating facility.IPD’s may be used for:Manufacturing InstructionsPlant documentsPlant drawingsPlant proceduresQC documentsRouting instructionsService documents
From the Windchill main menu select Create IP document
69
TRWTRW
Your Primary content file will be your main document, any attachments may be added as necessary. Click on the appropriate link to browse files and add to IPD.
Document Categories include OPS Doc, Alert Doc, & CAD Doc.
Number may be assigned by originator, or if left blank, be a system assigned number (ex. IP000001
“*” indicates required field
A team can be assigned as default according to user needs / document types.
Internal Plant DocumentsCreate
70
TRWTRWInternal Plant DocumentsProperties PageInternal Plant DocumentsProperties Page
Click on the Update link to make changes, add attachments, add carlines, etc.
71
TRWTRWInternal Plant DocumentPlatforms PageInternal Plant DocumentPlatforms PageIn the Update mode, carlines may be added by clicking the Select Platform box, and removed by the remove link.
Platforms may be searched by Customer, Platform ID, or Platform.Select the Platform by checking the box, and selecting OK.
Upon completion of your Platform Page you go to your worklist and select reviewersto send out document for release into system
72
TRWTRWValue Additions - Incorporated into the New WCRS
Value Additions - Incorporated into the New WCRS
Web Based Secure System – Access through browser able to link pertinent information to parts. The system offers ‘Full Text Search Capability’ to retrieve registered documents
Engineering Change Documents are - Easily understood containing all pertinent information
Performance Improvements – The system speed will be greatly improved for Europe
System Response Reminders – Example system will send a reminder to take action 7 Days after the posted date into a users In-Box through an email reminder
System Referencing – Reference documents to parts in Part Master i.e. Specifications to Drawing #
Improved Reporting – User selected reports and ad hoc tool for customized needs
Proxy Delegation – A User can redirect their approval notifications if unavailable e.g.. Holiday
Standardized Part Usage – All facilities using same part generator – part numbers and specs
Change Issue – The informal information sharing and gathering tool
Task Driven Responses – Workflow notifications communicate response through a task
File Submissions - Improvements for drawing mark–ups, documents and attachments
Service Improvements – Capture service impact for part interchangeability at time of design change. Customer production and service numbers captured in a system table
Color Information – Colored parts will be captured on a table, very useful for part extensions
73
TRWTRW Value Additions - Incorporated into the New WCRS – Continued Value Additions - Incorporated into the New WCRS – Continued
Improved commodity and buyer identification - Resulting in fewer change notification issues
Simple, efficient CRS Document creation - To begin the routing and approval process
Automated Final Drawing registration - upon engineers approval task
Engineering Part List - Would supplement our global drawings and provide complete component part numbers and suffix levels (a complete BOM) for assembly and subassemblies.
All Drawings Contained - In a single system and database (legacy - DMS and EIS systems)
One CRS System - All product line information in a single database (legacy – 2 databases)
Single System Access - View BOM’s contained in various manufacturing systems
New Document Type IPD – This is a simple notification and document release workflow for plants
ELV – Link in Part Master to Centor software where material and recycle information is viewed
External Document Access – Connect WCRS on the road, at supplier, or customer with just an ID
Drawing Distribution – Utility to provide electronic drawing distribution for purchasing, internal TRW and external users
Standard Part Identifiers – Query attributes maintained for standard parts {based upon part description} – enhancement started, to be completed after launch
Ease of ERD completion for charted parts – Indicate chart number, Parts display and are auto updated
74
TRWTRWHelpful HintsHelpful Hints
Saving your Userid and Password: When entering your USERID and PASSWORD, check the box “save this password in your password list”.
Creating a Shortcut to Windchill: To add an icon to your desktop, log into the application. Once in Windchill, RIGHT CLICK anywhere on the page. Choose the “Create Shortcut” option. The system will tell you “a shortcut to the current page will be placed on your desktop”. Choose “OK”.
To Open Documents in Windchill within the Application the Document was Authored in: Sometimes browsers are configured to open all documents within the browser application. To correct this, your browser must be configured correctly.
Double click on the My Computer icon on your desktopChoose the “Tools” option (at top of page)Select “Folder Options”Select the “File Types” tab (at top of page)For each document type you access via Windchill:
Scroll to the correct document type (e.g. Microsoft Word Document {doc})Highlight the document type (e.g. Microsoft Word Document {doc})Select the “Advanced” option (bottom of page)De-Select (remove checkmark from) the “Browse in Same Window” option. Press
OK to save.
75
TRWTRWTechnical AssistanceTechnical Assistance
To receive assistance with the use of WCRS Contact your Local Engineering Administrator, WCRS Plant Facilitator or IS Person
Or Contact Your Local help desk (24 x 7)
Please inform the helpdesk of your issue and the Document number if Applicable of which you are having the Issue with.
To receive assistance with the use of WCRS Contact your Local Engineering Administrator, WCRS Plant Facilitator or IS Person
Or Contact Your Local help desk (24 x 7)
Please inform the helpdesk of your issue and the Document number if Applicable of which you are having the Issue with.
76
TRWTRWTraining Manual Development Updates Training Manual Development Updates
Updated OCT 12 2004 (Items 1-14)
1) Slide 26 – Described by document link updates, ENG Part List, Pending ERD’s
2) Slide 30 - Updated text at top of slide
3) Slide 7 – User name text
4) Slide 23 – Updated view to include Maxcim
5) Slide 33 – References reviewers selections (was PM)
6) Slide 13 – Updated text to say “see next slide”
7) Slide 37 – Updated CC to Buyer
8) Slide 40 – Updated view from WCRS menu
9) Slide 41 – Updated text in lower text boxes
10) Slide 44 – Added up-assembly impact to the part submission
11) Slide 49 – Updated view includes Eng Pts List & update field
12) Slide 60 – Added arrows
13) Slide 64 – Updated deselect text for platform
14) Slide 73 – Text added - Ease of ERD completion for charted parts
15)
Updated OCT 12 2004 (Items 1-14)
1) Slide 26 – Described by document link updates, ENG Part List, Pending ERD’s
2) Slide 30 - Updated text at top of slide
3) Slide 7 – User name text
4) Slide 23 – Updated view to include Maxcim
5) Slide 33 – References reviewers selections (was PM)
6) Slide 13 – Updated text to say “see next slide”
7) Slide 37 – Updated CC to Buyer
8) Slide 40 – Updated view from WCRS menu
9) Slide 41 – Updated text in lower text boxes
10) Slide 44 – Added up-assembly impact to the part submission
11) Slide 49 – Updated view includes Eng Pts List & update field
12) Slide 60 – Added arrows
13) Slide 64 – Updated deselect text for platform
14) Slide 73 – Text added - Ease of ERD completion for charted parts
15)