The Role of EMIS in BC Hydro's Continuous Optimization Program and Beyond
Susan Doig, MBA, SCMP, Energy Manager, Capilano University
Bruce Herzer, Utility Account Manager, Pulse Energy
![Page 2: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/2.jpg)
Go To Webinar Control Panel
Ask us questions!
Hide the control panel
![Page 3: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/3.jpg)
Agenda
Overview of BC Hydro’s Continuous Optimization Program
The role of EMIS in the program
Case Study: Capilano University• Use of EMIS use in buildings outside the program
Q&A
![Page 4: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/4.jpg)
Targets operational savings in commercial buildings
Program Offer
• Fully funded retro-commissioning study
• Fully funded Energy Management Information System
• Customer implements bundle of capital and operational measures with a simple payback period of 2 years or less
Average energy cost reduction to date: 10%
• 7% electricity, 15% gas
BC Hydro’sContinuous Optimization Program
![Page 5: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/5.jpg)
Program Phases
Application Baseline Collection Investigation Implementation Persistence
(~2 months)
• Submit opportunity assessment
• Select consultants• Approve capital investment amount (~25¢/ ft2)
(6 months)
• Meter upgrades and EMIS installation
• Collect baseline energy models for M&V
(~3 months)
• Consultants perform audits and generate list of energy saving measures with <2 year pay back
(Up to 12 months)
• Implement identified capital and re-commissioning measures
(Ongoing)
• Monitor energy consumption
• Respond to exception reports and alerts
![Page 6: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/6.jpg)
Primary Functions
• Measurement and verification
• Exception reporting – maintaining savings
Other Benefits
• Occupant engagement and education
• Automated energy reporting (CUSUM, GHG, cost, etc.)
Role of EMIS in Continuous Optimization
![Page 7: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/7.jpg)
Pulse EMIS: Occupant Engagement Dashboard
![Page 8: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/8.jpg)
Pulse EMIS: Occupant Engagement Dashboard (Cont’d)
![Page 9: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/9.jpg)
Pulse EMIS: Management Module
![Page 10: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/10.jpg)
Pulse EMIS: Reporting Module
![Page 11: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/11.jpg)
To Apply
BC Hydro Customers
• Contact your Key Account Manager
• Or, Graham Henderson at (604) 453-6471
Other Utility Customers
• Contact Pulse Energy for suggestions
![Page 12: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/12.jpg)
Capilano University
• 14 buildings - 517,000 sq. ft.
• 4 buildings added to C-OP summer of 2010
• C-OP buildings range from 50,000 to 130,000 sq. ft.
• Baseline data is currently being collected
![Page 13: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/13.jpg)
Energy Consumption on N. Van. Campus
• Electrical consumption for all 14 buildings monitored by Pulse
• Electrical (2009) consumption: 6,937,000 kWh
• Natural gas (2009) consumption: 39,700 GJ
• 10 buildings not in COP program have Pulse EMIS for energy awareness program
![Page 14: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/14.jpg)
Why Pulse EMIS?
Available in the C-OP program
Engages students and employees in energy conservation on campus
Easy to use
![Page 15: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/15.jpg)
Why Pulse EMIS?
Accessibility
Very visual
People “get it”
Flexibility• Different layers of information
(users, operators, management)
![Page 16: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/16.jpg)
Current Initiatives
• BC Hydro funded Workplace Conservation (WCA) Campaign
• Launched Pulse software as part of 2010 Green Week
• Collecting baseline data to run an energy conservation contest in November
![Page 17: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/17.jpg)
• WCA: spread conservation message
• Reduce electrical consumption by 5% (approx $20,600 annually)
• Achieve community engagement of 20%
Goals
![Page 18: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/18.jpg)
• Dashboard appeal – students, employees and janitorial staff
• EMIS gives maintenance staff a new view of building consumption
• Visual reporting creates impact• Linked ‘waste’ to building occupant
behaviour• Using Pulse to engage people, create
awareness, and encourage conservation action
Results So Far
![Page 19: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/19.jpg)
#1 How to get people to engage with the online dashboard
Solutions• One-on-one presentations
• Make it fun, give prizes, take suggestions
• Use software to show participants’ positive impact
Challenges in Occupant Engagement
![Page 20: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/20.jpg)
#2 Resources• Time/people to carry the
message
Solution• Link dashboard to other events
happening on campus
Challenges in Occupant Engagement (Cont’d)
![Page 21: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/21.jpg)
Pulse Energy’s team is easy to work with
Promoting energy savings campaigns is not always easy
One-on-one conversations work better than mass information dumps
There is a ton of energy savings to be had!
Key Lessons Learned
![Page 22: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/22.jpg)
Add more layers of information to the Dashboard to make it “the” go-to spot for sustainability on Campus
Adding links to our Campus website to provide additional information to users
More energy conservation contests planned
More fun!
Future Plans
![Page 23: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/23.jpg)
Q & A
![Page 24: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/24.jpg)
Q & A
![Page 25: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/25.jpg)
Q & A
![Page 26: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/26.jpg)
Q & A
![Page 27: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/27.jpg)
Q & A
![Page 28: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/28.jpg)
Q & A
![Page 29: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/29.jpg)
Q & A
![Page 30: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/30.jpg)
Q & A
![Page 31: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/31.jpg)
Q & A
![Page 32: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/32.jpg)
Q & A
![Page 33: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/33.jpg)
Q & A
![Page 34: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/34.jpg)
Q & A
![Page 35: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/35.jpg)
Q & A
![Page 36: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/36.jpg)
Q & A
![Page 37: The Role of EMIS in BCHydro's Continuous Optimization Program and Beyond](https://reader035.vdocuments.mx/reader035/viewer/2022062614/547b538ab4af9fb9158b4ec0/html5/thumbnails/37.jpg)