Test powerpoint

Jan van ‘t Westeinde – IMWes installatiemanagement

Ontwerp- en realisatie De Rotterdam

Lezing Projectgroep Biomassa & WKKRotterdam, 25 juni 2015

6/25/201

5

Agenda

1. Introduction (video De Rotterdam)

2. Challenges Design phase (1998-2009)

3. Challenges Construction phase (2009-2013)

4. Questions

6/25/201

5

Introduction

1. Video De Rotterdam

6/25/201

5

Challenges design phase

6/25/201

5

Challenges design phase

1. Economy (9/11 and crisis 2008)

2. Design/function mix

3. Structural challenges

4. Fire-safety

5. Integration installations (M&E-elevators/escalators)

Economical challenges

• 1998 Start

• 2001 9/11; project ON HOLD

• 2006 Partner OVG; re-start design phase

• 2008/2009 Contracts (financial crisis 2008 !)

• 2009 Start construction

• 2013 Completion (15-11-2013: 12.00 AM)

0911 2008 Fin. crisis

ON HOLD CONSTRUCTION

Businesscase

• Investment appr. 375 mio

• 70% pre rent / pre sold

• Construction time 4 years

• Cash flow finance < 200 mio

• Planning / budget

6/25/201

5

Where it all started…

LocationThe Netherlands – Rotterdam - Wilhelminapier

Wilhelminapier

w

CITY CENTER NORTH

CITY CENTER SOUTH

Offices

Hotel / congress

Apartments

Multiplex Cinema

Retail / Restaurants

Health center

Leisure

Parking

Totaal gross area 115.000 m2

1997 2001

Offices

Hotel / congress

Apartments

Multiplex Cinema

Retail / Restaurants

Health center

Leisure

Parking

Totaal gross area 140.000 m2

Design/function mixOMA – Rem Koolhaas

O.M.A. / Rem Koolhaas

Dutch Ambassy, Berlin

Headquarter CCTV, Beijing

Library, Seattle Kunsthal, Rotterdam Stadskantoor

Vertical City - Mix of functions

160.000 m2

5.500 m2 footprint – the size of a soccerfield

HOTELOFFICESAPPARTMENTS

Low rise

High rise

APPARTMENTS OFFICES OFFICES

w

w

Office AreaTotal of 60,000 m2

Mid Tower 40,000 m2 Municipality

East Tower 20,000 m2

w

w

Hotel AreaNhow Hotel,

4-star design, 278 rooms +

2,000 m2 congress facilities

w

Living Area / 44floors.com

240 luxurious apartments

rental (54) and for sale 186

From 65 m2 - 250 m2

Waterfront Area

1,500 m2 for cafés, restaurants and shops overlooking the river Maas

Total of 670 parking spaces

5 Storeys

Parking

6/25/201

5

Distribution

airhandling

Design of M&E; distribution systems

6/25/201

5

Energy distribution

electricity

Design of M&E; distribution systems

6/25/201

5

Design of M&E; free height 3.40/3.00 m

6/25/201

5

Integration of installationsAppartements Tower West

6/25/201

5

Kijken of dit werkt

Fire SafetyMasterplan Fire Safety De Rotterdam

6/25/201

5

Fire Safety engineering

Masterplan

Fire Safety

6/25/201

5

Fire safety measures De Rotterdam

• Main structure 120 minutes fire resistant

• Fire safe compartments of max. 1.000 m2

• Complete building sprinkler-installation

• No flashover between towers/floors in case of failing sprinkler

• 2 firefighting elevators per building (each tower)

• Wet (pressurized) riser per building

• Façade partially fire resistant (fire on the Maas river)

• Fire-alarm (complete surveillance) and evacuation system with

spoken voice

• Overpressure in emergency staircases

• Emergency generator

• Commando room for fire-brigade

6/25/201

5

External Safety

6/25/201

5

Fuel fire from a ship on the Maas river

6/25/201

5

Radiation on facade

6/25/201

5

Testing radiation resistant glass

Challenges construction

phase

6/25/201

5

Construction phase

Challenges

• 7 contractors (coordination developer)

• Bankrupt contractor hotel (fit-out)

• Changes during construction (NH

Hotelles/Municipality of Rotterdam)

• Planning (building time exactly 4 years)

• Structure (settings)

• Logistics (ticket-system/just in time delivery)

• Integration installations (M&E)

Project information

• 160.000 m2 (on footprint soccer field)

• 150 m high

• Appr. 7.588 rooms

• 40.000 drawings

• 46 months construction time

• Weight : 230.000 ton (traffic queue Rotterdam-Milaan)

• 12.000 concrete mixers to deliver concrete: traffic jam

of 23 km

• 1.165 piles, total length 24 km

• 24 elevators

• Construction speed : ca. 300 m2 a day

• Peak 800 people on site

• Employment appr. 5.000 people direct / indirect.

Structure; settings and jacking

Structure; settings and jacking

Structure; settings and jacking

6/25/201

5

Logistics; routing

6/25/201

5

Logistics: just in time delivery

• Online reservation system

• 5 tower cranes

• 2 (outside) elevators

• 1 jumplift per tower

• Use of containers for prefab installations

6/25/201

5

Logistics during constructionJumplifts; lifts move up simultaneasly with structural shell and core

6/25/201

5

Logistics during construction

Jumplifts; lifts move up simultaneasly with structural shell and core

6/25/201

5

Jump lift in each tower

6/25/201

5

Containers for airducts

6/25/201

5

6/25/201

5

6/25/201

5

6/25/201

5

De Rotterdam; Sustainability

• Dynamic mix of functions (social cohesion)

• Intensive Land Use (floor space index approx. 50)

• Underground bicycle storage (> 500 places)

• Sustainable Energy Production on site (Maaswater cooling/bio fueled co-generation of heat and Electricity)

• Connection to City Heating

• Close to Public Transport (metro/bus/train)

• Good indoor climate