Successful Instrument and ControlSuccessful Instrument and Control
System DesignSystem Design
Part III (3/3) Ch 15 to 18
8th-Jul-2011
AgendaAgenda
Chapter 15 Panel Arrangement
Chapter 16 Procurement
Chapter 17Quality Control
The Integrated Design Check
Chapter 18 Phase Three
Construction Support
-
8/4/2019 Successful Instrument and Control System Design
2/16
2011/6/26
2
Chapter 15Chapter 15 Panel ArrangementPanel Arrangement
Panel arrangement drawings accomplish
several things:
Contents and placement of front-panel equipment
such as control switches and lights.
Contents and placement of back-panel equipment.
Contents of any engraved labels.
Bill of material for each item.
The external enclosure to be sized with confidence.
Panel Arrangement SamplePanel Arrangement Sample
Graphic detail should be minimized, and no wiring detail need
to be included.
-
8/4/2019 Successful Instrument and Control System Design
3/16
2011/6/26
3
Arrange a Junction Box DrawingArrange a Junction Box Drawing
Set up a scale
Metric units or Imperial units
Design the panel
How many terminals are needs?
What kinds of terminals should be used?
Most specifications require 50% spare capacity on a
new installation.
Explosion proof and enclosure protection.
Arrange a Junction Box DrawingArrange a Junction Box Drawing
For each item, place at least one bubble and leader. And
generate a bill of materials on the left side of graphic.
Generate a Bill of Materials
-
8/4/2019 Successful Instrument and Control System Design
4/16
2011/6/26
4
Field Panel SampleField Panel Sample
Leaving a minimum of 1.5 inches
between a terminal and adjacent
wiring duct is good practice.
The space for cable entry shall be
consider.
SummarySummary
-
8/4/2019 Successful Instrument and Control System Design
5/16
2011/6/26
5
Chapter 16Chapter 16 ProcurementProcurement A design package is built from the conceptual
to the actual andprocurementis about as
actual as it gets.
A frequent lament from the construction
partner is How can I build something if I
dont have the parts
Primarily two types of material are specifiedby the I&C design team:
Electrical material
Mechanical material
Bulk MaterialsBulk Materials
Electrical material
Including cable, conduit, enclosure, and termination
hardware.
Mechanical material
Including pneumatic tubing, flanges gaskets, and
mounting brackets.
These types of materials are called bulk materials.
Instruments, items that require long lead time for
manufacture, or other equipment items that require
individual specifications do not fall into the bulk
materials category.
-
8/4/2019 Successful Instrument and Control System Design
6/16
2011/6/26
6
Typical Purchasing CycleTypical Purchasing Cycle
When a design is nearly complete, the design
team begins whats called a takeoff.
Someone begins building lists of materials for
purchase. These lists are called bill of
materials (B/M, or BOM.)
The BOM is a document that lists all the
materials required for construction. On large projects, it is critical that each BOM
be given a unique designation and that a bill of
materials index be maintained.
Typical Purchasing CycleTypical Purchasing Cycle
Once a bill of materials is produced, they are given to the
purchasing department. Purchasing pares the material,
reorganizing it according to vendor. A purchase order (PO) is
then produced for each vendor.
-
8/4/2019 Successful Instrument and Control System Design
7/16
2011/6/26
7
Material ClassificationMaterial Classification
Bulk materials can be stored in bulkor in
detail.
The materials on the bulk bill of materials are
nonspecific materials.For example: cable, conduit, conduit fitting, cable tray, bolts &
nuts and hookup wiring.
The detail bill of materials is for Bulk materials that
have specific uses as shown on detail drawings.
For example: most instrument, and instrument fitting.
Bulk materials TakeoffBulk materials Takeoff
Cost-effective
Most vendors allow quantity discounts. The amounts
of these discounts very as the quantity rises, so it is
desirable to make large orders. Wastage and contingencies
We must always allow for wastage as the excess ends
will be clipped and disposed. We usually allow for at
least 20% wastage, plus about another 5-10% for
contingencies.
Takeoff quantity * 1.25 = Procured quantity
-
8/4/2019 Successful Instrument and Control System Design
8/16
2011/6/26
8
Bulk materials TakeoffBulk materials Takeoff
SummarySummary
-
8/4/2019 Successful Instrument and Control System Design
9/16
2011/6/26
9
Chapter 17Chapter 17Quality ControlQuality Control The Integrated Design CheckThe Integrated Design Check Having progressed to the end of the design
phase, it is now necessary to validate the work
before sending it to the field to be built.
If the design events are properly logged as theyare executed, then the design check at the end is
much easier and much time will be saved.
Goal of design check Zero defects will not occur
No showstoppers or major problem will stop the
construction effort.
CheckpointsCheckpoints
There are few specific issue to consider in
terms of establishing checkpoints. Two
different points of view need to be consider:
administrative and technical.Administrative content Individual Checks
Technical content Squad Check
Squad check roster
Design check summary
-
8/4/2019 Successful Instrument and Control System Design
10/16
2011/6/26
10
Administrative contentAdministrative content Individual ChecksIndividual Checks
Non-technical experts should be designated to
page through the document set to check for
specific appearance aspects:
Is the title block correct in terms of drawing number,
revision level, and title?
Are the proper project data in place?
Are the proper initials in place? Designed, check, and
so on.
Are notes legible and grammatically complete?
Technical contentTechnical content Squad CheckSquad Check
Do the instrument specifications reflect the intent of
the P&ID, and will they meet the scope
requirements?
Do the elementaries reflect the intent of the
instrument specs and the P&ID?
Do the wiring diagram reflect the intent of the
elementaries?
Do the BOM reflect the needs presented on process
plans and cabinet arrangement?
Are all these properly reflected in the instrument
database?
-
8/4/2019 Successful Instrument and Control System Design
11/16
2011/6/26
11
Technical contentTechnical content Squad CheckSquad Check
The revised drawing should always be attached to its
original markup to retain the document trail.
When the design check is complete, the markups
should be rescued and stored. They should be
retained for one year after plant startup.
In CTCI I&C department principle:
Using design input/output check sheet.
Squad check rosterSquad check roster
Who should be on squad-check team?
For the most part, the design team itself.
If possible, the members not check their own work.
Rotating the personnel away from their own work does acouple of good things:
First, it makes sense. If a mistake was made once, it will
probably be missed if the same person look at it again.
Another benefit is the cross-training aspect.
One other addition to the squad should be an
experienced outsider. (AE)
-
8/4/2019 Successful Instrument and Control System Design
12/16
2011/6/26
12
Design check summaryDesign check summary
All the designers prepare for the check by
logging their progress in the database, by
keeping a personal log of potential problems
to watch out for, and by communicating with
each other. At the end of the project, the
database can be used as a checking tool that
streamlines the squad-check process andmaximizes the effectiveness of the time spent
in its execution.
summarysummary
-
8/4/2019 Successful Instrument and Control System Design
13/16
2011/6/26
13
Chapter 18Chapter 18Phase ThreePhase Three Construction SupportConstruction Support
Phase two has ended, and phase three has
begun (E C)
The designers may be able to spend some extra time
on-site with the constructor as well. Construction
support and support during checkout and startup are
key to the success of the design team as a whole.
If the designers are in the field and known to be
helpful, then perceptions will be enhanced all
around.
Construction SupportConstruction Support
There are two kinds of construction support:
on-site and off-site. It is a good idea to
determine ahead of time the periods that are
critical for on-site support and have people
available continuously through those periods.Otherwise, having someone on call off-site is
usually acceptable.
The construction phase breaks down into
several periods, each with a different set of
needs in terms of the design team.
-
8/4/2019 Successful Instrument and Control System Design
14/16
2011/6/26
14
Construction Phase PeriodsConstruction Phase Periods
Kickoff Meeting:
Each construction activity should begin with a kickoff
meeting. At this meeting, the phase-three lead for
the design team should present the package. The
presentation should cover, at a minimum, the
following topics:1. Bill of material
2. Design overview
3. Off-site support infrastructure
4. On-site support plan
Construction Phase PeriodsConstruction Phase Periods
Construction Period:
Construction activities usually provide a bit of a lull
for the design team. Some members of the team
may be reassigned to other duties at this time, never
to return to the project. Others may monitor theproject, getting involved only when a problem arises.
During certain predefined periods of particular risk to
the project, design team representative(s) may travel
to the site to observe and provide direct support.
Construction activities during this time include
installation and verification.
-
8/4/2019 Successful Instrument and Control System Design
15/16
2011/6/26
15
Construction Phase PeriodsConstruction Phase Periods
Checkout(Bump and Stroke):
The checkout period increases the level of attention
needed by design team. The following activities
occur during this time:1. Each analog sensor is checked for proper ambient reading
and electrically disconnected.
2. Each digital input is forced by either making it react to its
process condition or by shorting across its terminals.3. Motors are bumped to verify proper direction of rotation.
4. Valves are stroke to make sure they function and their
travel is not obstructed.
Construction Phase PeriodsConstruction Phase Periods
Startup:
Upon successful completion of the checkout phase,
the system is ready to run. At this point, the
customer begins to take command of the system.
The customers operators will have recevied trainingfrom the system integrator. It is now time to light
the candle.
This is the time for the customer and the system
integrator to assume primary roles.
The design and construction teams stand by to
respond should a need be identified.
-
8/4/2019 Successful Instrument and Control System Design
16/16
2011/6/26
Adjustment of Document to ReflectAdjustment of Document to ReflectConstruction ModificationConstruction Modification
Construction drawings are usually copied,
since redlines only exist there and cannot be
removed from the site. These copies are sent
to the engineering service provider to be
formally incorporated into the document.
As soon after startup as practical, thedrawings should be released back into
customers possession. This is an official
turnover of responsibility for the project.
Finally, the entire project is shipped to the customer.