Project Progress – 19th Oct 2013
![Page 2: Status report as on 19th oct 2013](https://reader034.vdocuments.mx/reader034/viewer/2022042714/5560fc64d8b42aff3f8b4f81/html5/thumbnails/2.jpg)
STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 19.10.13
1.10th Floor Slab : Except 3rd Flat Remain All Flats Completed, 3rd Flat Slab shuttering work Under Progress.
![Page 3: Status report as on 19th oct 2013](https://reader034.vdocuments.mx/reader034/viewer/2022042714/5560fc64d8b42aff3f8b4f81/html5/thumbnails/3.jpg)
STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 19.10.13
1.10th Floor Slab : Flat No 1 and 2 flat Slab Completed, 4 & 5 flats Bar Bending work under Progress , 3rd flat Shuttering work In Progress
![Page 4: Status report as on 19th oct 2013](https://reader034.vdocuments.mx/reader034/viewer/2022042714/5560fc64d8b42aff3f8b4f81/html5/thumbnails/4.jpg)
STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 19.10.13
1.8th Floor Slab : Flat No 01 Shuttering Completed ,Flat No 02 Columns work completed.
![Page 5: Status report as on 19th oct 2013](https://reader034.vdocuments.mx/reader034/viewer/2022042714/5560fc64d8b42aff3f8b4f81/html5/thumbnails/5.jpg)
STATUS REPORT OF MY HOME ABHRA Tower-”D” As On 19.10.13
3.10th Floor Slab : Except 3rd Remain all Flats Slabs Completed.3rd flat Slab Shuttering Work Completed .
![Page 6: Status report as on 19th oct 2013](https://reader034.vdocuments.mx/reader034/viewer/2022042714/5560fc64d8b42aff3f8b4f81/html5/thumbnails/6.jpg)
STATUS REPORT OF MY HOME ABHRA Tower-”E” As On 19.10.13
1.10th Floor Slab : Completed2.11th Floor Slab : Flat No 01 Beam Bottom Shuttering Work In Progress Flat No 02 Columns work In
progress