SR 2108-A12 – Forbes Avenue Betterment
March 1, 2018
| | |
|
![Page 2: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/2.jpg)
2
Introductions
• Project Team– PENNDOT
• Cheryl Moon-Sirianni, PE; District Executive
• Jason Zang, P.E.; Acting Assistant District Executive-Construction
• John J. Zelesnak, PE; Project Manager-Design
• John Myler; Assistant Construction Manager – 412.429.5063 – [email protected]
• Jonathan Grimm; Project Manager-Construction – 609.214.0931 – [email protected]
– WRA• Eric C. Meyer, PE; Project Manager
• Daniel Fritz, PE; Senior Project Engineer
• Tyler Steele, PE; Project Engineer
– OTMA http://www.otma-pgh.org/
• Mavis Rainey; Executive Director – 412.687.4505
– Gulisek• Jonathan Gesinski, P.E.; Project Manager - 412.354.9207 - [email protected]
• Brandon Farrell; Project Engineer – 724.809.5804 - [email protected]
• Terry Kostelnik; Daytime Superintendent – 724.640.7104 - [email protected]
• Richard Dickson; Nighttime Superintendent – 724.640.7108 - [email protected]
– Lindy Paving• Dave Kauer; Project Manager – 724.333.6614 - [email protected]
• Eric Yauger; Project Engineer – 724.208.9474 - [email protected]
• C.J. Grant; Superintendent – 724.333.6758 - [email protected]
– Vantage Corporation• Craig Thomas; Project Manager – 412.429.4750 – [email protected]
![Page 3: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/3.jpg)
3
Agenda
• Overview of Project
• Project Improvements
• Maintenance and Protection of Traffic
• Schedule
• Q and A
![Page 4: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/4.jpg)
4
Project Description
• SR 2108-A12 – Forbes Avenue Betterment
• Birmingham Bridge to Margaret Morrison Street
– Resurfacing (mill/overlay) of the corridor
– Concrete pavement patching
– Grade Adjustments of existing Inlets, Manholes and Utility Valve Boxes.
– Eleven (11) New Traffic Signals with full pedestrian and Americans with Disabilities Act
(ADA) compliant upgrades
– Six (6) Traffic Signal Upgrades at existing traffic signals
– Bicycle Improvements between Bigelow Blvd. and Margaret Morrison Street
– Converting existing four lanes to two lanes w/ center turn lane and bike lanes in each
direction from Craig St. to Margaret Morrison St.
![Page 5: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/5.jpg)
5
Pedestrian Improvements
➢ Physical Improvements➢ Upgraded ADA curb ramps
➢ High visibility crosswalks (piano keys)
➢ New Stop Bars
➢ New Pedestrian countdown heads
➢ Audible signals/push buttons
➢ Operational Improvements➢ Leading/advance pedestrian walk phase
at all intersections except Forbes Ave/Morewood Ave and Forbes Ave/S. Craig St, which will remain an all-walk phase
➢ New signalized pedestrian crossing between Bouquet St and Bigelow Blvd/Schenley Dr
![Page 6: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/6.jpg)
6
Bicycle Improvements
➢ New bike lanes between Bigelow
Blvd/Schenley Dr and Margaret
Morrison St
➢ Completes connectivity to existing
bike facilities
➢ Two-stage left turns (Curb Cuts at
T intersections)
➢ Minimum 5’ width bike lanes with a
2’-4’ painted buffer where space
permits
➢ New bicycle safe inlet grates
➢ New and updated signing and
signals for bike infrastructure
![Page 7: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/7.jpg)
7
Forbes at Birmingham Br
Forbes at Margaret Morrison St
Project Overview – SR 2108- A12 Forbes Avenue
Betterment Project
Existing Signal – minor upgrades
Replaced Signal
New Signal
![Page 8: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/8.jpg)
8
Forbes at Birmingham Br
Forbes at Craft Ave
Birmingham Bridge to Craft Avenue (Zone 1)
Existing Signal
Replaced Signal
Existing Bus stop
![Page 9: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/9.jpg)
9
Forbes at Craft Ave
Forbes at Bouquet St
Craft Avenue to Bouquet Street (Zone 2)
Existing Signal – minor upgrades
Replaced Signal
Existing Bus stop
![Page 10: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/10.jpg)
10
Forbes at Bouquet St
Forbes at Bigelow Blvd
Bouquet Street to Bigelow Blvd (Zone 2)
Existing Signal – minor upgrades
New Pedestrian Signal
Existing Bus stop
![Page 11: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/11.jpg)
11
New Traffic Signal
![Page 12: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/12.jpg)
12
Bigelow Blvd to Craig Street (Zone 2)
Forbes at Bigelow Blvd
Forbes at Craig St
Existing Signal – minor upgrades
Replaced Signal
Existing Bus stop
![Page 13: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/13.jpg)
13
Forbes at Craig St Forbes at Beeler St
Craig Street to Beeler Street (Zone 3)
Replaced Signal
New Signal
Existing Bus stop
![Page 14: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/14.jpg)
14
Existing Intersection Configurations
Forbes Avenue at Bigelow Blvd/Schenley Drive & Schenley Drive Extension
Existing Signal – minor upgrades
Replaced Signal
Existing Bus stop
![Page 15: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/15.jpg)
15
Proposed Intersection Configurations
Forbes Avenue at Bigelow Blvd/Schenley Drive & Schenley Drive Extension
Existing Signal – minor upgrades
Replaced Signal
Existing Bus stop
![Page 16: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/16.jpg)
16
Existing Intersection Configurations
Forbes Avenue at Bellefield Avenue
Pull Off
Bellefield Avenue to Craig StreetSchenley Dr. Ext to Bellefield Ave
Replaced Signal
Existing Bus stop
![Page 17: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/17.jpg)
17
Proposed Intersection Configurations
Pull Off
Bellefield Avenue to Craig StreetSchenley Dr. Ext to Bellefield Ave
Forbes Avenue at Bellefield Avenue
Replaced Signal
Existing Bus stop
![Page 18: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/18.jpg)
18
Existing Intersection Configurations
Forbes Avenue at Craig Street
Existing Bus stop
Pull Off
![Page 19: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/19.jpg)
19
Proposed Intersection Configurations
Forbes Avenue at Craig Street
Pull Off
Replaced Signal
Existing Bus stop
![Page 20: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/20.jpg)
20
Corridor Improvements
Tepper Quadrangle
Pull Offs
Replaced Signal
New Signal
Existing Bus stop
![Page 21: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/21.jpg)
21
Proposed Intersection Configurations
Forbes Avenue at CIC Drive and Tepper Garage Ramp
Pull OffNew Signal
![Page 22: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/22.jpg)
22
Proposed Intersection Configurations
Forbes Avenue at Cyert Drive
Relocated and Replaced Signal
![Page 23: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/23.jpg)
23
Existing Intersection Configurations
Forbes Avenue at Morewood Avenue
Pull OffExisting Bus stop
Pull Off
![Page 24: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/24.jpg)
24
Proposed Intersection Configurations
Forbes Avenue at Morewood Avenue
Pull Off
Pull Off
Replaced Signal
Existing Bus stop
![Page 25: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/25.jpg)
25
Proposed Roadway Configuration
Morewood Avenue to Beeler Street
Existing Bus stop
![Page 26: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/26.jpg)
26
Existing Intersection Configurations
Forbes Avenue at Beeler Street
Existing Bus stop
![Page 27: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/27.jpg)
27
Proposed Intersection Configurations
Forbes Avenue at Beeler Street
Replaced Signal
Existing Bus stop
![Page 28: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/28.jpg)
28
Proposed Roadway ConfigurationsBeeler Street to Margaret Morrison Street
Existing Bus stop
![Page 29: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/29.jpg)
29
Existing Intersection Configurations
Forbes Avenue at Margaret Morrison Street
Existing Bus stop
![Page 30: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/30.jpg)
30
Proposed Intersection Configurations
Forbes Avenue at Margaret Morrison Street
Replaced Signal
Existing Bus stop
![Page 31: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/31.jpg)
31
Maintenance and Protection of Traffic
• Construction Operations– Combination of Daytime and Nighttime Work –
• 9:00 AM to 3:00 PM daily
• 8:00 PM to 6:00 AM nightly
– Weekend Work – 8:00 PM Friday to 6:00 AM Monday
• Seven weekend long single lane restrictions
• Five Block limit
• Otherwise maintain two lanes of traffic
– No work dates due to events (Attached Calendar)
– Weekend Closures - Two weekends
• Zone 1 – Birmingham Bridge to Craft Avenue
– EMS notifications during closures and weekend restrictions
• Sidewalk and Signal Construction– Maintain Pedestrian and Bike access at all times
– ADA Accessible
– Transit Accessibility
![Page 32: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/32.jpg)
32
Maintenance and Protection of Traffic
![Page 33: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/33.jpg)
33
Maintenance and Protection of Traffic
![Page 34: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/34.jpg)
34
Construction Schedule (No Work)
![Page 35: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/35.jpg)
35
Construction Schedule
• Zone 1: Birmingham Bridge to Craft Avenue − March 12, 2018 – April 30, 2018 (Week nights and weekends)
• Concrete Patching, inlet, manhole and utility valve adjustments along with asphalt milling
and paving.
![Page 36: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/36.jpg)
36
Construction Schedule
• Zone 3: S. Craig Street to Margaret Morrison Street− March 8, 2018 – June 25, 2018 (Week days and nights)
• Intersection section work for traffic signal infrastructure and ADA curb ramps. Inlet,
manhole and utility valve adjustments.
– Mid June to late August (Weekends as permitted)
• Asphalt milling and paving
– August 8, 2018 – August 31, 2018 (Week days and nights)
• Traffic signal installation
![Page 37: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/37.jpg)
37
Construction Schedule
• Zone 2: Craft Avenue to S. Craig Street– April 2, 2018 – August 31, 2018 (Week days and nights)
• Intersection section work for traffic signal infrastructure and ADA curb ramps.
– Mid May to Mid June (Weekends as permitted)
• Asphalt milling and paving
– Mid June to September (Week days and nights)
• Inlet, manhole and utility valve adjustments.
– September 2018 (Weekends as permitted)
• Asphalt Wearing Course
– August 8, 2018 – September 21, 2018 (Week days and nights)
• Traffic signal installation
![Page 38: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/38.jpg)
38
Construction Schedule
• Project Wrap-up– Mid September through October 2018(Week days and nights and weekends as permitted)
• Final Pavement Markings
• Sign Installation
• Miscellaneous delineation
• Traffic Signal testing
![Page 39: SR 2108-A12 Forbes Avenue Bettermentforbes.otmapgh.org/downloads/FINAL-Forbes-Avenue-PPT-3-1-2018.… · 01/03/2018 · • Birmingham Bridge to Margaret Morrison Street –Resurfacing](https://reader033.vdocuments.mx/reader033/viewer/2022050512/5f9d04d51200345d9f5d1f42/html5/thumbnails/39.jpg)
Questions?
This presentation will be made available within 10 days on the OTMA website