Southwest Lehigh Substation
Below-Grade Work
![Page 2: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/2.jpg)
Site Location
![Page 3: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/3.jpg)
Work to Be Done
• Install high- and low-side caissons for structural steel
Fifty-six (56) caissons of various sizes
Total of 300 cubic yards of concrete
![Page 4: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/4.jpg)
Work to Be Done
• Install high- and low-side caissons for structural steel
• Install concrete pads for breakers, regulators and capacitor bank
Eleven (11) breaker pads
Four (4) regulator pads
One (1) capacitor bank pad
Total of 66 cubic yards of concrete
![Page 5: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/5.jpg)
Caissons & Pads
![Page 6: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/6.jpg)
Work to Be Done
• Install high- and low-side caissons for structural steel
• Install concrete pads for breakers, regulators and capacitor bank
• Install conduit and cable trench
2,980 feet of 2” PVC
700 feet of 4” PVC
400 feet of cable trench
![Page 7: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/7.jpg)
Conduit and Cable Trench
![Page 8: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/8.jpg)
Work to Be Done
• Install high- and low-side caissons for structural steel
• Install concrete pads for breakers, regulators, and capacitor bank
• Install conduit and cable trench
• Install ground grid
Install 8,600 feet of 4/0 copper grounding conductor
Install 3,256 feet of ground rods (407 8’ rods)
Install 353 exothermic welds
![Page 9: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/9.jpg)
Ground Grid
![Page 10: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/10.jpg)
Work to Be Done
• Install high- and low-side caissons for structural steel
• Install concrete pads for breakers, regulators, and capacitor bank
• Install conduit and cable trench
• Install ground grid
• Construct relay vault
![Page 11: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/11.jpg)
Relay Vault
![Page 12: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/12.jpg)
Bidders List
• Aubrey Silvey Enterprises, Inc. Carrollton, Georgia
• Kent Power Inc. Kent City, Michigan
• PowerTown Line Construction St. Petersburg, Florida
• JL Malone & Associates, LLC Albany, Georgia
• McLaren Construction West Palm Beach, Florida
![Page 13: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/13.jpg)
Bid Results
McLaren Construction $640,323.00
Bidder 2 Higher Bid
Bidder 3 Higher Bid
Bidder 4 Higher Bid
Bidder 5 No Bid
NOTE: LCEC Engineering Estimate for Scope of Work - $720,000
![Page 14: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/14.jpg)
Staff Recommendation
• Low bidder: McLaren Construction
• Longstanding relationship
• Performed work at North Trail, Trafalgar, Lake Trafford, and Corbett substations.
![Page 15: Southwest Lehigh Substation - LCEC Lehigh Substation... · •Install high- and low-side caissons for structural steel Fifty-six ... construction of the Southwest Lehigh Substation](https://reader031.vdocuments.mx/reader031/viewer/2022031002/5b84bdf17f8b9ae0498cd350/html5/thumbnails/15.jpg)
Board Action Requested
Requesting a motion authorizing the CEO to sign a contract for below-grade work and relay vault construction of the Southwest Lehigh Substation
with McLaren Construction in the amount of $640,323.00.