    Problem #1

    Consider two different machines; with two different instruction sets have a clock

    rate of 200 MHz. The following measurements are recorded on the two machines

    running a given set of benchmark programs:

    Instruction Type Instruction Count

    (millions)

    Cycles per

    Instruction

    Machine A

    Arithmetic and logic

    Load and store

    Branch

    Others

    8

    4

    2

    4

    1

    2

    3

    4

    Machine B

    Arithmetic and logic

    Load and store

    Branch

    Others

    10

    8

    2

    4

    1

    2

    3

    4

    1- Determine the effective (average) CPI, MIPS rate, and execution time for

    each machine.

    2- Comment on the results.

    Problem #2

    Consider two different implementations of the same instruction sets architecture.

    There four classes of instructions A, B, C and D. The data clock rate and CPI for

    each implementation are given in the following table:

    Clock rate CPI Class A CPI Class B CPI Class C CPI Class D

    P1 1.5 GHz 1 2 3 4

    P2 2 GHz 2 2 2 2

    Given a program with 106 instructions divided into classes as following: 10%

    class A, 20% class B, 50% class C and 20% class D.

    1- What is average CPI for each implementation?

    2- Find the clock cycles required in both cases?

    3- Which implementation is faster? Show your calculations

  • Fayoum University Faculty of Engineering Electrical Engineering Dep.

    ECE 204 B 2nd year comm. Spring 2014

    21-

    Problem #3

    Assuming that arithmetic instructions take 1 cycle, load and store 5 cycles, and

    branches 2 cycles

    Arith Store Load Branch Total

    650 100 600 50 1400

    1- What is the execution time of the program in a 2 GHz processor?

    2- Find the CPI for the program.

    3- If the number of load instructions can be reduced by one half, what is the

    speedup and the CPI?

    Problem #4

    The following table shows the execution time (ms) of five routines of a program:

    Routine A Routine B Routine C Routine D Routine E

    12 45 6 36 3

    1- Find the total execution time and by how much it is reduced if the time of

    routines A, C, and E is improved by 15%.

    2- How much is the total time reduced if routine B is improved by 10%?

    3- How much is the total time reduced if routine D is improved by 10%?